OYO FPSO Sanction to First Oil in 22 months in 22 months A CASE STUDY A CASE STUDY presented by Steve Hill COO Oceanic Houston Houston 7 th July 2010

Transcript of Sanction to First Oil in 22 monthsin 22 months “A CASE ...1].pdf · Sanction to First Oil in 22...

Page 1: Sanction to First Oil in 22 monthsin 22 months “A CASE ...1].pdf · Sanction to First Oil in 22 monthsin 22 months “A CASE STUDYA CASE STUDY ... • 7 FABRICATION SITES IN 5 DIFFERENT

OYO FPSO

Sanction to First Oilin 22 monthsin 22 months

“A CASE STUDY”A CASE STUDYpresented by

Steve HillCOO Oceanic

HoustonHouston7th July 2010

Page 2: Sanction to First Oil in 22 monthsin 22 months “A CASE ...1].pdf · Sanction to First Oil in 22 monthsin 22 months “A CASE STUDYA CASE STUDY ... • 7 FABRICATION SITES IN 5 DIFFERENT

PRESENTATION AGENDA

1. WHY AN FPSO: ADVANTAGES AND DISADVANTAGES

2 ORGANIZATION2. ORGANIZATION

3. PLANNING

4 INTERFACES4. INTERFACES

5. CONTRACT EXECUTION

6 LESSONS LEARNED6. LESSONS LEARNED

2

Page 3: Sanction to First Oil in 22 monthsin 22 months “A CASE ...1].pdf · Sanction to First Oil in 22 monthsin 22 months “A CASE STUDYA CASE STUDY ... • 7 FABRICATION SITES IN 5 DIFFERENT

WHAT IS FPSO

“Floating Production, Storage and Offloading”for deep water production 3

Page 4: Sanction to First Oil in 22 monthsin 22 months “A CASE ...1].pdf · Sanction to First Oil in 22 monthsin 22 months “A CASE STUDYA CASE STUDY ... • 7 FABRICATION SITES IN 5 DIFFERENT

WHAT IS DEEP WATER

Most common definitionW d h 1000 f– Water depth > 1000 ft

From Drilling and Production perspective– Any well connectionAny well connection

on a FLOATING structure

Conventional DeepwaterGOM W t d th f 3 000 8 000 ft– GOM Water depths of 3,000-8,000 ft

– Nigeria 1,000-3,000 ft

Ultra Deepwaterp– Brazil & GOM now drilling > 9,000’ ft

4

Page 5: Sanction to First Oil in 22 monthsin 22 months “A CASE ...1].pdf · Sanction to First Oil in 22 monthsin 22 months “A CASE STUDYA CASE STUDY ... • 7 FABRICATION SITES IN 5 DIFFERENT

PRODUCTION SYSTEMS BY WATER DEPTH

5

Page 6: Sanction to First Oil in 22 monthsin 22 months “A CASE ...1].pdf · Sanction to First Oil in 22 monthsin 22 months “A CASE STUDYA CASE STUDY ... • 7 FABRICATION SITES IN 5 DIFFERENT

NIGERIA LOCATION MAP

6

Page 7: Sanction to First Oil in 22 monthsin 22 months “A CASE ...1].pdf · Sanction to First Oil in 22 monthsin 22 months “A CASE STUDYA CASE STUDY ... • 7 FABRICATION SITES IN 5 DIFFERENT

OYO FUNCTIONAL CHART

Nigeria

Ministry of Oil

Allied EnergyNigeria

OML 120 121

DPR

CAMACInternational

O

NAEOperator

ENIOwner OML 120-121 Owner

OceanicConsultants

p

PSCMacom Tecom Fincom

HoustonCOOP

Procurement Committee

LagosIMTF. Maolucci / G. Moser

Allied DrillingS. Omidele

ENI Eng ProcurementM. Caramuta

Oceanic S. Hill

7Pkg 1 Pkg 2 Pkg 3 IT (DC)Houston LagosENG DC Procurement

Page 8: Sanction to First Oil in 22 monthsin 22 months “A CASE ...1].pdf · Sanction to First Oil in 22 monthsin 22 months “A CASE STUDYA CASE STUDY ... • 7 FABRICATION SITES IN 5 DIFFERENT

OYO FIELD LAYOUT & FPSO SPECFPSO SPECIFICATION_____________Storage (bbls)Design Flow Rate (b/d)Mooring type

1,000,00040,000spread

Offloading typeProduction life (years)Gas treatment rate (mmscfd)Gas injection rate (mmscfd)Max Produced Water (bwpd)Overboard Water Quality

tandem1060

60 max9,000

Overboard Water Quality (ppm)Tandem Tanker size (dwt)Oil shipment cargo pump discharge flowrate (b/d)Metering system

< 15up to 350,000

1,000,00030,000 bp/hr

SUB SEA SPECIFICATIONSUB SEA SPECIFICATION__________Subsea (SS) tree typeX-Tree Design Pressure Rating (psi)Wellhead Design Pressure Rating (psi)

horizontal

10,000

15,000SS Control System TypeWell completion tubing sizeGaslift (one well)Production flowline MAOP (psia)

electro-hydraulic4.5” – 5.5”

yes

5,000

8

Horizontal Deepwater

Tree

UTA IUTA

Page 9: Sanction to First Oil in 22 monthsin 22 months “A CASE ...1].pdf · Sanction to First Oil in 22 monthsin 22 months “A CASE STUDYA CASE STUDY ... • 7 FABRICATION SITES IN 5 DIFFERENT

THE DRIVING FORCESFOR QUICK EXECUTION

• SAFETY FIRST. “SAFETY”

• PLAN THE WORK & WORK THE PLAN. “MAKE A PLAN”

• USE THE MOST EXPERIENCED PERSONNEL AVAILABLE.“THE BEST PEOPLE”

• CONSTANTLY CHECK AND RE-CHECK CONTRACT SPECIFICATIONS CO S C C C C CO C S C C O STO ACTUAL WORK. “AS-BUILTS”

• MANAGE THE PACKAGES, NOT THE INDIVIDUAL CONTRACTORS. “INTERFACES”“INTERFACES”

• USE DATA AND INFORMATION TO DETERMINE ACTIONS, NOT EMOTIONS FOR FEELINGS. “DATA BASE”

9

Page 10: Sanction to First Oil in 22 monthsin 22 months “A CASE ...1].pdf · Sanction to First Oil in 22 monthsin 22 months “A CASE STUDYA CASE STUDY ... • 7 FABRICATION SITES IN 5 DIFFERENT

MILESTONES

• DRILLED OYO 1 – 1998 (STATOIL)

• DRILLED OYO 2 – 2006 (BP)

• FEED for FPSO – 2006

• DRILLED OYO 3 – 2007

• DRILLIED OYO 4 – 2008

• SANCTION TO OYO DEVELOPMENT PLAN – FEB 2008

• HULL MOVED TO SINGAPORE AND CONVERSION STARTED APR 2008• HULL MOVED TO SINGAPORE AND CONVERSION STARTED – APR 2008

• MECHANICAL ACCEPTANCE – AUG 2009

• SAILED AWAY – 13 SEP 2009MO

NTH

S

• ARRIVED OYO – 5 NOV 2009

• FIRST OIL – 5 DECEMBER 2010

22

M

10

Page 11: Sanction to First Oil in 22 monthsin 22 months “A CASE ...1].pdf · Sanction to First Oil in 22 monthsin 22 months “A CASE STUDYA CASE STUDY ... • 7 FABRICATION SITES IN 5 DIFFERENT

PROJECT AFE BUDGET

11

Page 12: Sanction to First Oil in 22 monthsin 22 months “A CASE ...1].pdf · Sanction to First Oil in 22 monthsin 22 months “A CASE STUDYA CASE STUDY ... • 7 FABRICATION SITES IN 5 DIFFERENT

FEED ORGANIZATION 2007

12

Page 13: Sanction to First Oil in 22 monthsin 22 months “A CASE ...1].pdf · Sanction to First Oil in 22 monthsin 22 months “A CASE STUDYA CASE STUDY ... • 7 FABRICATION SITES IN 5 DIFFERENT

RESPONSIBILITY MATRIX 2006-2008

13

Page 14: Sanction to First Oil in 22 monthsin 22 months “A CASE ...1].pdf · Sanction to First Oil in 22 monthsin 22 months “A CASE STUDYA CASE STUDY ... • 7 FABRICATION SITES IN 5 DIFFERENT

IMT ORGANIZATION 2008

14

Page 15: Sanction to First Oil in 22 monthsin 22 months “A CASE ...1].pdf · Sanction to First Oil in 22 monthsin 22 months “A CASE STUDYA CASE STUDY ... • 7 FABRICATION SITES IN 5 DIFFERENT

IMT ORGANIZATION 2009 – 2010

15

Page 16: Sanction to First Oil in 22 monthsin 22 months “A CASE ...1].pdf · Sanction to First Oil in 22 monthsin 22 months “A CASE STUDYA CASE STUDY ... • 7 FABRICATION SITES IN 5 DIFFERENT

CONTRACTING PHYLOSOPHYPACKAGES AND INTERFACESPACKAGES AND INTERFACES

SUPPORT

INTERFACES

DRILLING MATERIALS SUPPORTVESSELS

FPSO CONVERSION

SUBSEA EQUIPMENT

AND SERVICES

FLOWLINESAND

INSTALLATION

• LUMP SUM TURN KEY FOR MATERIALS

AND SERVICESINSTALLATION

• DAY RATES AND HOURLY RATES FOR SERVICES

• COST PLUS FOR DRILLING/PRODUCTION EXPENDABLES

16

Page 17: Sanction to First Oil in 22 monthsin 22 months “A CASE ...1].pdf · Sanction to First Oil in 22 monthsin 22 months “A CASE STUDYA CASE STUDY ... • 7 FABRICATION SITES IN 5 DIFFERENT

TOPSIDES DELIVERY SCHEDULE

17

Page 18: Sanction to First Oil in 22 monthsin 22 months “A CASE ...1].pdf · Sanction to First Oil in 22 monthsin 22 months “A CASE STUDYA CASE STUDY ... • 7 FABRICATION SITES IN 5 DIFFERENT

OVERVIEW OFPROJECT MANAGEMENT INTERFACES

• TOTAL PROCUREMENT AND CONTRACTING1 BIL USD IN 36 MONTHS

• 7 MAIN CONTRACTORS IN 5 DIFFERENT COUNTRIES

• 158 VENDORS, 63 SUBCONTRACTORS, 27 DIFFERENT

MANUFACTURING LOCATIONS IN 14 COUNTRIES

• 7 FABRICATION SITES IN 5 DIFFERENT INTERNATIONALLOCATIONS

• 23 NATIONALITIES23 NATIONALITIES

• 5 FOREIGN LANGUAGES

• 22 MONTH EXECUTION PLAN

• 1723 INTERFACES 18

Page 19: Sanction to First Oil in 22 monthsin 22 months “A CASE ...1].pdf · Sanction to First Oil in 22 monthsin 22 months “A CASE STUDYA CASE STUDY ... • 7 FABRICATION SITES IN 5 DIFFERENT

LESSONS LEARNED

• DON’T LEAVE THE SHIPYARD UNTILL ALL WORK THAT WAS• DON T LEAVE THE SHIPYARD UNTILL ALL WORK THAT WASCONTRACTED IS DONE

• PUT MORE PROJECT AND COST CONTROL ENGINEERS AT THEVARIOUS SITES, AND YOU SAVE MILLIONSVARIOUS SITES, AND YOU SAVE MILLIONS

• CENTRALIZE INSPECTION PLAN FOR VENDORS, MANUFACTURESAND FABRICATORS

• CENTRALIZE MANAGEMENT REVIEWS AND STANDARDIZE• CENTRALIZE MANAGEMENT REVIEWS AND STANDARDIZEREPORTS; MONDAY 6AM WORLDWIDE VIDEOCONFERENCEMEETING WITH ALL STAKE HOLDERS

• MAKE BETTER USE OF “SHARE POINT” FOR ARCHIVING• MAKE BETTER USE OF SHARE POINT FOR ARCHIVINGDOCUMENTS

• EXPAND THE USE OF VIDEO CONFERENCING AT ALL SITES

• DON’T CHANGE ORGANIZATION IN THE MIDDLE OF THE PROJECT- WE JUST MOVED THE CHAIRS WITH SAME PEOPLE IN THEM

• FOCUS ON CAPEX COST SAVINGS AND NOT TRY TO SAVEFOCUS ON CAPEX COST SAVINGS AND NOT TRY TO SAVEMANHOURS ON PM; PM COSTS WERE CUT 50% AND CAPEX WENTUP BY 400 MIL.