San Pablo Rapid Bus Stops - actransit.org
Transcript of San Pablo Rapid Bus Stops - actransit.org
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
San Pablo Rapid Bus StopsInventory 2004
Alameda County CMAAC TransitLocal jurisdictions
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Emeryville – 40th Street NorthboundIMPROVEMENTS
Existing•Bus Shelter
•Seat Bench w/o backs
•Trash Bin
•Light Pole
•Bus Stop Flag Sign
•Bus Stop System Map
•Custom Logo & Signage
•Street Trees
•Tree Grate
•Pedestrian Push Button
•Real Time Information
Desired•Benches w/ backs
•Information Kiosk
•Pedestrian Countdowns
•Bus Pads
•Audio Announce
•Ticket Machine
•Electrical Connections
•Bus Stop Flag Sign
COSTS$823
$6,420
$803
U/C
$2,006
$15,000
$2-$15,000
$1,800
UNDER CONTRACT:Bus pads
TOTAL: $28,852-$41,852
CONSTRAINTS:•High volume of boarding's and high vandalism at this site
•Potential future residential/commercial development of adjacent property
•“No advertising” sign ordinance in the City of Emeryville
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Emeryville – 40th Street SouthboundIMPROVEMENTS
Existing•Trash Bin
•Light Poles
•Bus Stop Flag Sign
•Bus Stop System Map
•Custom Logo & Signage
•Street Trees
•Tree Grate
•Real Time Information
Desired•Bus Shelter
•Benches w/ backs
•Pedestrian Countdowns
•Real Time Information
•Bus Pad
•Audio Announce
•Ticket Machine
•Electrical Connections
•Bus Stop Flag SignUNDER CONTRACTBus Pad
Real Time Information
CONSTRAINTS•Adjacent property awnings limit vertical space for shelter installation•Closest PG&E electrical connection is across San Pablo Avenue•“No advertising” sign ordinance in the City of Emeryville
TOTAL: $35,472-$48,472
Costs$13,040
$823
$803
U/C
U/C
$2,006
$15,000
$2-$15,000
$1,800
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Oakland – Alcatraz Northbound
Existing•Bus Shelter
•Benches w/ backs
•Trash & Recycle Bin
•Bus Stop Flag Sign
•Bus Stop System Map
•Custom Logo & Signage
•Street Trees
•Pedestrian Countdown
Desired•Seat Benches w/o backs
•Light Pole
•Concrete Unit Pavers
•Crosswalk Treatments
•Lean-On Rails
•Tree Grate
•Information Kiosk
•Audio Announce
•Real Time Information
•Ticket Machine
•Bus Pad
•Electrical Connections
•Bus Stop Flag Sign
UNDER CONTRACT:Bus Pads
Real Time Information
CONSTRAINTS:•Connected Oakland streetlight system for maximum 150 watts of power
Costs$702
$1,655
$4,633
$55,000
$602
$1,500
$6,420
$2006
Under Contract
$15,000
Under Contract
$2-$15,000
$1,800
TOTAL: $91,318-$104,318
IMPROVEMENTS
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Oakland – Alcatraz SouthboundExisting•Trash Bin
•Recycle Bin
•Seat Bench w/o back
•Bus Stop Flag Sign
•Street Trees
•Pedestrian Countdown
Desired•Bus Shelter
•Bench w/ back
•Seat Bench w/o back
•Light Pole
•Bus Stop System Map
•Custom Logo & Signage
•Concrete Unit Pavers
•Crosswalk Treatment
•Lean on Rails
•Tree Grate
•Information Kiosk
•Audio Announce
•Real Time Information
•Ticket Machine
•Electrical Connection
•Bus Pad
•Bus Stop Flag Sign
UNDER CONTRACT:Bus Pad
CONSTRAINTS:•Transit shelter could not be installed because adjacent property is residential with front landscaping•Sidewalk at this site is too narrow for additional street furniture; unable to post transit information or Next bus digital displays
IMPROVEMENTSCosts$13,040
$ 823
$702
$1,655
$1,304
$500
$4,633
See Alcatraz NB
$602
$1,500
$6,420
$2,006
See Constraints
$15,000
$2-$15,000
Under contract
$1,800
TOTAL: $51,985-$64,985
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Oakland – Stanford Northbound
Existing•Bus Shelter
•Benches w/ backs
•Trash & Recycle Bin
•Bus Stop Flag Sign
•Custom Logo & Signage
•Street Trees
•Audible & Ped Buttons
Desired•Seat Benches w/o backs
•Light Pole
•Concrete Unit Pavers
•Crosswalk Treatment
•Lean-on Rails
•Tree Grate
•Audio Announce
•Real Time Information
•Ticket Machine
•Electrical Connection
•Bus Pad
•Bus Stop Flag Sign
UNDER CONTRACT:Bus pad
Real Time Information
TOTAL: $84,898- $97,898CONSTRAINTS:•Adjacent church originally opposed bus stop relocation and street furniture•City of Oakland agreed to relocate bus stop from NS to FS and have it contractor install transit shelter with Rapid Branding•Connected Oakland streetlight system for maximum 150 watts of power
IMPROVEMENTSCosts:$702
$1,655
$4,633
$55,000
$602
$1,500
$2,006
Under Contract
$15,000
$2-15,000
Under Contract
$1,800
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Oakland – Stanford Southbound
Existing•Bus Shelter
•Benches w/ backs
•Seat Benches w/o backs
•Trash & Recycle Bins
•Bus Stop Flag Sign
•Bus Stop System Map
•Custom Logo & Signage
•Street Trees
Desired•Light Pole
•Concrete Unit Pavers
•Crosswalk Treatment
•Lean-on Rails
•Tree Grate
•Audio Announce
•Real Time Information
•Ticket Machine
•Electrical Connection
•Bus Pad
•Bus Stop Flag Sign
TOTAL
Cost$1.655
$4,633
See Stanford NB
$602
$1,500
$2,006
Under Contract
$15,000
$2-$15,000
Under Contract
$1,800
$29,196-$42,196
UNDER CONTRACT:Bus pad
Real Time Information
IMPROVEMENTS
CONSTRAINTS:•Narrow sidewalk not wide enough for additional street furniture•Connected Oakland streetlight system for maximum 150 watts of power
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Oakland – 30th Street NorthboundIMPROVEMENTS
Existing•Benches w/ backs
•Bus Stop Flag Sign
•Pay Phone
•Audible & Ped Push Button
Desired•Bus Shelter
•Seat Benches w/o backs
•Trash Bin
•Recycle Bin
•Light Pole
•Bus Stop System Map
•Custom Logo & Signage
•Concrete Unit Pavers
•Lean-on Rails
•Street Trees & Grate
•News Rack
•Pedestrian Countdowns
•Audio Announce
•Real Time Information
•Ticket Machine
•Bus Pad
•Bus Stop Flag Sign
•Electrical connections
UNDER CONTRACT:Bus Pad
CONSTRAINTS:•Narrow sidewalk not wide enough for any street furniture•Shelter also cannot be installed due to storefront windows•No place to post transit information or Nextbus digital displays
Costs$13,040
$702
$1,404
$1,404
$1,655
$1,304
$500
$4,633
$602
$2,200
$1,103
$803
$2,006
See Constraints
$15,000
Under Contract
$1,800
$2-15,000
TOTAL: $50,156-$63,156
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Oakland 30th Street SouthboundIMPROVEMENTS
Existing•Bus Shelter
•Bench w/ backs
•Custom Logo & Signage
•Bus Stop Flag Sign
Desired•New Bus Shelter
•Benches w/ backs
•Seat Benches w/o backs
•Trash Bin
•Recycle Bin
•Light Pole
•Bus Stop Flag Sign
•Bus Stop System Map
•Lean-on Rails
•Street Trees & Grate
•Audio Announce
•Real Time Info
•Ticket Machine
•Electrical Connection
•Bus Pad
UNDER CONTRACT:Bus Pads
Real Time Information
CONSTRAINTS:•Additional street furniture poses a safety hazard due to open adjacent parking lot•Connected Oakland streetlight system for maximum 150 watts of power
Costs$13,040
$823
$702
$1,404
$1,404
$1,655
$1,800
$1,304
$602
$2,200
$2,006
Under Contract
$15,000
$2-$15,000
Under Contract
TOTAL: $43,438-$56,438
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Oakland – Grand Northbound
Existing•Bus Shelter
•Benches w/ backs
•Trash Bin
•Bus Stop Flag Sign
•Bus Stop System Map
•Custom Logo & Signage
•Audio Announce
Desired•Seat benches w/o backs
•Recycle Bin
•Light Pole
•Concrete Unit Pavers
•Lean-on Rails
•Street Tree & Grate
•Pedestrian Countdowns
•Real Time Info
•Ticket Machine
•Electrical Connection
•Bus Pad
•Bus Stop Flag Sign
Costs$702
$1,404
$1,655
$4,633
$602
$2,200
$803
Under Contract
$15,000
$2-$15,000
Under Contract
$1,800TOTAL: $ 30,298-$43,298CONSTRAINTS:
•Adjacent property owner is opposed to transit shelter and additional street furniture•Bus shelter requires high level of maintenance and monitoring•AC Transit is working with City of Oakland to relocate shelter and reduce its size to minimize loitering in shelter•Connected Oakland streetlight system for maximum 150 watts of power
UNDER CONTRACT:•Bus Pads•Real Time Information
IMPROVEMENTS
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Oakland Grand SouthboundIMPROVEMENTS
Existing•Benches w/ backs
•Trash & Recycle Bin
•Bus Stop Flag Sign
•Audio Announce
Desired•Bus Shelter
•Seat Bench w/o backs
•Light Pole
•Bus Stop System Map
•Custom Logo & Signage
•Concrete Unit Pavers
•Lean-on Rails
•Street Tree & Grate
•Ped Countdown
•Real Time Info
•Ticket Machine
•Electrical Connection
•Bus Pad
•Bus Stop Flag Sign
UNDER CONTRACT:Bus Pads
Real Time Information
CONSTRAINTS:•Street furniture of any type not appropriate for site due to high maintenance and vandalism possibilities•Oakland shelter contractor would not install a shelter at this site due to potential maintenance issues•No place to post transit information or Nextbus digital displays
Costs$13,040
$702
$1,655
$1,304
$500
$4,633
$602
$2,200
$803
See Constraints
$15,000
$2-$15,000
Under Contract
$1,800
TOTAL: $43,737-$56,737
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Oakland - 20th and Broadway NorthboundIMPROVEMENTS
Existing•Bus Shelter
•Benches with & w/o backs
•Trash Bin
•Bus Stop System Map
•Custom Logo & Signage
•Pedestrian Push Buttons
Desired•Recycle Bin
•Light Pole
•Bus Stop Flag Sign
•Concrete Unit Pavers
•Crosswalk Treatment
•Lean-on Rails
•Street Tree & Grate
•Audio Announce
•Real Time Info
•Ticket Machine
•Electrical Connection
•Bus Pad
UNDER CONTRACT:Bus Pads
Real Time Information
Costs$1,404
$1,655
$1,800
$4,633
$55,000
$602
$2,200
$2,006
Under Contract
$15,000
$2,000-$15,000
Under Contract
TOTAL: $85,798-$98,798• Sidewalk width and ground vaults prevent the installation of additional furniture and bus pole•High volume of boarding's and high maintenance requirement at this site
CONSTRAINTS:
•Adjacent property owner is greatly opposed to bus stop and street furniture due to potential for loiterers and increase in litter•AC Transit is working with City on creating bus bulb for stop to alleviate conflicts with adjacent property owner•Connected Oakland streetlight system for maximum 150 watts of power
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Oakland – 20th Street & Broadway SouthboundIMPROVEMENTS
Existing•Bus Shelter
•Benches with & w/o backs
•Trash Bin
•Bus Stop System Map
•Custom Logo & Signage
•Pedestrian Push Button
Desired•Recycle Bin
•Light Pole
•Bus Stop Flag Sign
•Concrete Unit Pavers
•Crosswalk Treatment
•Lean-on Rails
•Street Tree & Grate
•Audio Announce
•Real Time Information
•Ticket Machine
•Electrical Connection
•Bus Pad
Cost$1,404
$1,655
$1,800
$4,633
See 20th St NB
$602
$2,200
$2,006
Under Contract
$15,000
$2,000-$15,000
Under Contract
UNDER CONTRACT:Bus pads
Real Time Information
TOTAL: $30,798-$43,798CONSTRAINTS:•Sidewalk width and ground vaults prevent the installation of additional furniture•Connected Oakland streetlight system for maximum 150 watts of power
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Berkeley – Ashby Northbound
IMPROVEMENTS
Existing•Bus Shelter
•Benches with & w/o backs
•Trash Bins
•Bus Stop System Map
•Custom Logo & Signage
•Street Trees
•News Rack
•Real Time Information
Desired•Recycle Bin
•Light Pole (2)
•Bus Stop Flag Sign
•Tree Grate (6)
•Audio Announce
•Ticket Machine
•Electrical Connection
•Bus Pad
•Concrete Unit Pavers
•Crosswalk Treatments
•Bus Stop Flag Sign
UNDER CONTRACT:Bus Pads
Real Time Information
Bus Stop Flag Sign
CONSTRAINTS:•No PG&E connection; shelter is powered by private Walgreen’s power TOTAL: $93,651-$106,351
Costs$1,404
$3,310
U/C
$9,000
$2,006
$15,000
$2,000-15,000
Under Contract
$4,633
$55,000
$1,800
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Berkeley – Ashby Southbound
Existing•Bus Shelter
•Bench without Backs
•Trash Bin
•Bus Stop Flag Sign
•Bus Stop System Map
•Custom Logo & Signage
•Street Trees
•Tree Grate
•Pedestrian countdowns
•Real Time Information
Desired•Recycle Bin
•Light Pole (2)
•Audio Announce
•Ticket Machine
•Electrical Connection
•Bus Pad
•Concrete Unit Pavers
•Crosswalk Treatments
•New Tree Grates (2)
•Bus Stop Flag Sign
Costs$1,404
$3,310
$2,006
$15,000
$2-$15,000
Under Contract
$4,633
See Ashby NB
3,000
$1,800
TOTAL $32,651-$45,691
IMPROVEMENTS
UNDER CONTRACT:Bus PadsReal Time Information
CONSTRAINTS:•No PG&E connection; shelter is powered through SMART Corridors power draw
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Berkeley – Dwight NorthboundIMPROVEMENTS
Desired•Recycle Bin
•Light Pole (2)
•Tree Grates (4)
•Audio Announce
•Ticket Machine
•Electrical Connection
•Bus Pad
•Concrete Unit Pavers
•Crosswalk Treatment
•Bus Stop Flag Sign
Existing•Bus Shelter
•Bench without Backs
•Bus Stop Flag Sign
•Bus Stop System Map
•Custom Logo & Signage
•Street Trees
•Pedestrian Countdown
•Real Time InformationUNDER CONTRACT:Bus Pads
Real Time Information
CONSTRAINTS:•Adjacent liquor store owner is highly opposed to bus stop relocation and
installation of transit shelter due to potential for loiterers around his
business entrance
Costs$1,404
$3,310
$6,000
$2,006
$15,000
$2-$15,000
U/C
$4,633
$55,000
$1,800
TOTAL $90,651-$103-651
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Berkeley – Dwight SouthboundIMPROVEMENTS
Desired•Light Pole (2)
•Tree Grates (3)
•Audio Announce
•Real Time Information
•Ticket Machine
•Electrical Connection
•Bus Pad
•Bus Stop Flag Sign
Existing•Bench with Backs
•Trash Bin
•Recycle Bin
•Bus Stop Flag Sign
•Bus Stop System Map
•Custom Logo & Signage
•Information Kiosk
•Pedestrian Countdown TOTAL: $28,114-40,114
Costs$3,310
$4,500
$2,006
Under Contract
$15,000
$2-$15,000
Under Contract
$1,800
CONSTRAINTS:•Adjacent property owner and businesses highly opposed to bus shelter
installation because it will block storefront windows
•Some adjacent businesses are opposed to bus stop relocation
UNDER CONTRACT:Bus PadsReal Time Information
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Berkeley – University NorthboundIMPROVEMENTS
Desired•Light Pole (2)
•Tree Grate (3)
•Audio Announce
•Ticket Machine
•Electrical Connections
•Bus Pad
•Concrete Unit Pavers
•Crosswalk Treatment
•Bus Stop Flag Sign
Existing•Bus Shelter
•Bench without Backs
•Trash Bin
•Recycling Bin
•Bus Stop Flag Sign
•Bus Stop System Map
•Custom Logo & Signage
•Street Trees
•Pedestrian & Audible Countdowns
•Real Time Information
UNDER CONTRACT:Bus PadsReal Time Information
CONSTRAINTS:Bus stop is in between two driveways
TOTAL: $87,747-100,747
Costs$3,310
$4,500
$2,006
$15,000
$2-$15,000
Under
Contract
$4,633
$55,000
$1,800
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Berkeley – University SouthboundIMPROVEMENTS
Costs$3,310
$1,304
$2,200
$2,006
$15,000
$2-$15,000
U/C
$500
$4,633
See University NB
$1,800
Desired•Light Pole (2)
•Bus Stop System Map
•Tree & Grate
•Audio Announce
•Ticket Machine
•Electrical Connections
•Bus Pad
•Custom Logo and Signage
•Concrete Unit Pavers
•Crosswalk Treatment
•Bus Stop Flag Sign
Existing•Bench with Backs
•Trash Bin
•Recycle Bin
•Bus Stop Flag Sign
•Bus Stop System Map
•News Rack 4 unit
•Information Kiosk
•Pedestrian & Audible Countdowns
•Real Time Information
UNDER CONTRACT:Bus PadsReal Time InformationCONSTRAINTS:•City opposed shelter installation due to storefront windows
•Bus pole blocks State speed limit sign
•High pedestrian traffic
TOTAL: $32,753-$45,753
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Berkeley – Gilman NorthboundIMPROVEMENTS
Desired•Recycle Bin
•Tree Grate
•Audio Announce
•Ticket Machine
•Electrical Connections
•Bus Pad
•Concrete Unit Pavers
•Crosswalk Treatment
•Light Pole (2)
•Bus Stop Flag Sign
Existing•Bus Shelter
•Bench without Backs
•Trash Bin
•Bus Stop Flag Sign
•Bus Stop System Map
•Custom Logo & Signage
•Street Trees
•News Rack 4 unit
•Pedestrian & Audible Countdowns
•Real Time Information
CONSTRAINTS:•Additional street furniture causes potential safety hazard with adjacent open parking lot•Bus pole blocks State Highway sign
TOTAL: $86,653-$99,653
UNDER CONTRACT:Bus PadsReal Time Information
Costs$1,404
$1,500
$2,006
$15,000
$2-$15,000
U/C
$4,633
$55,000
$3,310
$1,800
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Berkeley – Gilman SouthboundIMPROVEMENTS
Costs$3,310
$3,000
$2,006
$15,000
$2-$15,000
U/C
$4,633
See Gilman NB
$1,800
Desired•Light Pole (2)
•Tree Grate (2)
•Audio Announce
•Ticket Machine
•Electrical Connection
•Bus Pad
•Concrete Unit Pavers
•Crosswalk Treatment
•Bus Stop Flag Sign
Existing•Bus Shelter
•Seat Bench without Backs
•Trash Bin
•Recycle Bin
•Bus Stop Flag Sign
•Bus Stop System Map
•Custom Logo & Signage
•Street Tree
•News Rack 4 unit
•Pedestrian Countdown
•Real Time Information
UNDER CONTRACT:Bus PadsReal Time Information
CONSTRAINTS:•Bus stop near gas station entry way•Bus stop relocated further south for better placement and opposition from gas station owner of bus stop and street furniture
TOTAL: $31,247-$43,247
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Albany – Solano NorthboundIMPROVEMENTS
Costs$823
$1,404
$1,655
$1,304
$500
$1,800
$4,633
$55,000
$1,500
$802
$2,006
$4,013
$15,000
$2-$15,000
Under Contract
TBD
Desired•Bench with Backs
•Recycle Bin
•Light Pole
•Bus Stop System Map-new
•Custom Logo & Signage
•Bus Stop Flag Sign
•Concrete Unit Pavers
•Crosswalk Treatment
•Tree Grate
•Pedestrian Countdown
•Audio Announce
•Security Camera
•Ticket Machine
•Electrical Connection
•Bus Pad
•Secure Utility Box
Existing•Bus Shelter
•Bench without Backs
•Trash Bin
•Bus Stop System Map
•Real Time Information
CONSTRAINTS:•Bus stop is nearside and shorter than desired. The City Chamber of Commerce opposed the relocation of the stop to the far side•Bus stop pole is not new and cannot be replaced due to potential visual conflict with the traffic signal
UNDER CONTRACT:•Bus Pad
TOTAL: $92,440 - $105,440
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Albany – Solano SouthboundIMPROVEMENTS
Costs$823
$1,404
$1,404
$1,655
$1,304
$500
$4,633
$1,500
$803
$2,006
$4,012
Under Contract
$15,000
$2-$15,000
Under Contract
$1,800
Desired•Bench with Backs
•Trash Bin
•Recycle Bin
•Light Pole (Pedestrian scale)
•Bus Stop System Map
•Custom Logo & Signage (street name & site identification)
•Concrete Unit Pavers
•Tree Grate
•Pedestrian Countdown
•Audio Announce
•Security Camera
•Real Time Information
•Ticket Machine
•Electrical Connection
•Bus Pad
•Bus Stop Flag Sign
Existing•Bus Shelter
•Seat Bench without Backs
•Bus Stop Flag Sign
•Bus Stop System Map (illegible due to condensation)
UNDER CONTRACT:Bus PadsReal Time Information
TOTAL: $38,844-$51,844
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
El Cerrito – Carlson Northbound
Costs$1,404
$4,633
$602
$1,103
$803
$15,000
$2-$15,000
$1,800
Desired•Recycle Bin
•Concrete Unit Pavers
•Lean on Rails
•News Rack 4 unit
•Pedestrian Countdowns
•Ticket Machine
•Electrical Connection
•Bus Stop Flag Sign
Existing•Bus Shelter
•Seat Bench without Backs
•Trash Bin
•Bus Stop Flag Sign
•Bus Stop System Map
•Custom Logo & Signage
•Street Trees
•Tree Grate
•Audio Announce & Pedestrian Countdown
•Real Time InformationUNDER CONTRACT:Bus PadsReal Time Information
TOTAL: $26,110-38,110
IMPROVEMENTS
CONSTRAINTS:•New sidewalk not necessary for this site because sidewalk was newly replaced as part of new development•Sidewalk is too narrow for additional street furniture•“No advertising” sign ordinance in the City of El Cerrito
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
El Cerrito – Carlson Southbound
Costs$13,040
$702
$1,404
$1,800
$1,304
$500
$700
$2,006
$803
U/C
$15,000
$2-$15,000
Desired•Bus Shelter
•Seat Bench without Backs (NEW)
•Trash Bin
•Bus Stop Flag Sign
•Bus Stop System Map
•Custom Logo & Signage
•Street Trees
•Audio Announce & Pedestrian Countdown
•Real Time Information
•Ticket Machine
•Electrical Connection
Existing•Bus Shelter
•Seat Bench without Backs
•Trash Bin
•Bus Stop Flag Sign
•Bus Stop System Map
•Custom Logo & Signage
•Street Trees
•Audible and Pedestrian Countdown
•Real Time Information
UNDER CONTRACT:Bus PadsReal Time Information
IMPROVEMENTS
TOTAL: $39,259-$52,259
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
El Cerrito – Moeser Northbound
Costs$1,404
$4,633
$602
$2,200
$1,103
$803
$15,000
$2-$15,000
$1,800
Desired•Recycle Bin
•Concrete Unit Pavers
•Lean on Rails
•Street Tree & Grate
•News Rack – 4 unit
•Pedestrian Countdown
•Ticket Machine
•Electrical Connections
•Bus Stop Flag Sign
Existing•Bus Shelter
•Seat Bench w/o Backs
•Trash Bin
•Bus Stop Flag Sign
•Bus Stop System Map
•Custom Logo & Signage
•Audio Announce
•Real Time Information
IMPROVEMENTS
TOTAL: $29,545-42,545
CONSTRAINTS:•Sidewalk is too narrow for additional street furniture
•“No advertising” sign ordinance in the City of El Cerrito
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
El Cerrito – Moeser SouthboundIMPROVEMENTS
Desired•Recycle Bin
•Concrete Unit Pavers
•News Rack-4 units
•Pedestrian Countdown
•Ticket Machine
•Electrical Connection
•Bus Stop Flag Sign
n
CONSTRAINTS:•No space for proper placement of shelter or additional street furniture
due to storefront windows
•“No advertising” sign ordinance in the City of El Cerrito
TOTAL: $26,743-39,743
Existing•Bench w/ Backs
•Bus Stop Flag Sign
•Bus Stop System Map
•Custom Logo & Signage
•Street Tree
•Pedestrian Countdow
•Audio Announce
•Real Time Information
Costs$1,404
$4,633
$1,103
$803
$15,000
$2-$15,000
$1,800
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
El Cerrito – Potrero Northbound
Existing•Bus Shelter
•Seat Bench w/o backs
•Trash Bin
•Bus Stop Flag Sign
•Bus Stop System Map
•Custom Logo & Signage
•Street Tree
•Real Time Informati
•Bus Pad
IMPROVEMENTS
Desired•Recycle Bin
•Concrete Unit Pavers
•Lean On Rails
•Tree Grate
•News Rack-4 unit
•Pedestrian Countdowns
•Ticket Machine
•Electrical Connection
•Bus Stop Flag Sign
on
Costs$1,404
$4,633
$602
$1,500
$1,103
$803
$15,000
$2-$15,000
$1,800
TOTAL: $28,845-$41,845
CONSTRAINTS:•“No advertising” sign ordinance in the City of El Cerrito
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
El Cerrito – Potrero SouthboundIMPROVEMENTS
Existing•Bus Shelter
•Seat Bench w/o Backs
•Trash Bin
•Bus Stop Flag Sign
•Bus Stop System Map
•Custom Logo & Signage
•Street Tree
•Real Time Information
•Bus Pad
DesiredRecycle Bin
Concrete Unit Pavers
Lean On Rails
Tree Grate
News Rack – 4 unit
Pedestrian Countdowns
Ticket Machine
Electrical Connection
Bus Stop Flag Sign
Costs$1,404
$4,633
$602
$1,500
$1,103
$803
$15,000
$2-$15,000
$1,800
UNDER CONTRACT:Bus Pads
Real Time Information
CONSTRAINTS:•“No advertising” sign ordinance in the City of El Cerrito
TOTAL: $28,845-$41,845
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
El Cerrito del Norte - Northbound
Existing•Bus Shelter
•Bench w/ Backs
•Real Time Informati
CONSTRAINTS:•BART jurisdiction; BART needs to agree to any additional street furniture installations and
ongoing maintenance
TOTAL: $19,702-$32,402
IMPROVEMENTS
Desired•Recycle Bin
•Ticket Machine
•Electrical Connection
•Bus Stop Flag Sign
on
Costs$1,404
$15,000
$2-$15,000
$1,800
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
El Cerrito del Norte - SBIMPROVEMENTS
Existing•Bus Shelter
•Bench w/ Backs
•Trash Bin
•Real Time Informatio
Desired•Recycle Bin
•Ticket Machine
•Electrical Connection
•Bus Stop Flag Signn
Costs$1,404
$15,000
$2-$15,000
$1,800
TOTAL: $19,702-$32,402
CONSTRAINTS:•BART jurisdiction; BART needs to agree to any additional street furniture installations and ongoing maintenance
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Richmond – MacDonald Northbound
Desired•Light Pole
•Bus Pad
•Ticket Machine
•Electrical Connection
•Bus Stop Flag Sign
Existing•Bus Shelter
•Bench with Backs
•Seat Bench w/o Backs
•Trash Bin
•Bus Stop Flag Sign
•Bus Stop System Map
•Custom Logo &
Signage
•Street Tree
•Pedestrian Countdown
•Real Time Information
CONSTRAINTS:•Sidewalk is too narrow for additional street furniture
TOTAL: $44,455-$57,455
IMPROVEMENTS
Cost$1,655
$24,000
$15,000
$2-$15,000
$1,800
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Richmond – MacDonald SouthboundIMPROVEMENTS
Costs$24,000
$15,000
$2-$15,000
$1,800
Desired•Bus Pad
•Ticket Machine
•Electrical Connection
•Bus Stop Flag Sign
Existing•Bus Shelter
•Bench w/ Backs
•Seat Bench w/o Backs
•Trash Bin
•Bus Stop Flag Sign
•Bus Stop System Map
•Street Tree
•Pedestrian Countdown
•Real Time Information
CONSTRAINTS:•Stop is in between driveways
TOTAL: $42,800-55,800
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Richmond – Garvin Northbound
Existing•Bench w/ Backs
•Bus Stop Flag Sign
•Bus Stop System Map
•Information Kiosk
•Real Time Information
IMPROVEMENTS
Desired•Bus Pad
•Ticket Machine
•Electrical Connection
•Bus Stop Flag Sign
Costs$24,000
$15,000
$2-$15,000
$1,800
TOTAL: $42,800-55,800
CONSTRAINTS:•No advertising shelter due to adjacent residential property
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Richmond – Garvin Southbound
Existing•Bench w/ Backs
•Bus Stop Flag Sign
•Bus Stop System Map
•Pay Phone
•Street Tree
•Information Kiosk
•Real Time Information
IMPROVEMENTS
Desired•Bus Pad
•Ticket Machine
•Electrical Connection
•Bus Stop Flag Sign
Costs$24,000
$15,000
$2-$15,000
$1,800
TOTAL: $42,800-$55,800
CONSTRAINTS:•No advertising shelter due to adjacent storefront windows.
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
San Pablo – San Pablo Dam Northbound IMPROVEMENTS
Desired•Light Pole
•Bus Stop Flag Sign
• Pedestrian Countdown
•Tree Grate
•Ticket Machine
•Electrical Connection
Costs$1,655
$1,800
$803
$1,500
$15,000
$2-$15,000
Existing•Bus Shelter
•Seat Bench w/o Backs
•Trash Bin
•Bus Stop Flag Sign
•Bus Stop System Map
•Custom Logo & Signage
•Street Tree
•Audio Announce
•Real Time Information
•Bus Pad
TOTAL: $22,758-$35,758
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
San Pablo – Tulare Southbound
Existing•Bus Shelter
•Seat Bench w/o Backs
•Trash Bin
•Bus Stop Flag Sign
•Bus Stop System Map
•Custom Logo and Signage
•Real Time Information
•Bus PadTOTAL: $21,258-$34,258
IMPROVEMENTS
Desired•Light Pole
•Bus Stop Flag Sign
•Pedestrian Countdowns
•Ticket Machine
•Electrical Connection
Cost$1,655
$1,800
$ 803
$15,000
$2-$15,000
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
San Pablo – Vale NorthboundIMPROVEMENTS
Costs$24,000
$1,800
$1,655
$15,000
$2-$15,000
Desired•Bus pad
•Bus Stop Flag Sign
•Light Pole
•Ticket Machine
•Electrical Connection
Existing•Bus Shelter
•Seat Bench w/o Backs
•Trash Bin
•Bus Stop Flag Sign
•Bus Stop System Map
•Custom Logo & Signage
•Street Tree
•Pedestrian Countdown
UNDER CONTRACT:Real Time Information
TOTAL: $44,455-$57,455
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
San Pablo – Vale SouthboundIMPROVEMENTS
Desired•Light Pole
•Bus Stop Flag Sign
•Ticket Machine
•Electrical Connection
Existing•Bus Shelter
•Seat Bench w/o Backs
•Trash Bin
•Bus Stop Flag Sign
•Bus Stop System Map
•Custom Logo & Signage
•Street Tree
•Tree Grate
•Pedestrian Countdown
• Real Time Information
•Bus Pad
CONSTRAINTS:•Light Pole may be difficult to install due to a
number of vaults in the sidewalk
TOTAL: $20,455-$33,455
Costs$1,655
$1,800
$15,000
$2-$15,000
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
San Pablo – Van Ness NorthboundIMPROVEMENTS
Desired•Bus Shelter
•Light Pole
•Bus Pad
•Ticket Machine
•Electrical Connection
•Bus Stop Flag Sign
Existing•Bus Stop Flag Sign
•Street Trees
Costs$13,040
$1,655
$24,000
$15,000
$2-$15,000
$1,800
TOTAL: $56,993-$69,993
UNDER CONTRACT:Real Time Information – To be confirmed by AC Transit
CONSTRAINTS:•Power for light pole will need to come from adjacent property private
power source
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
San Pablo – Van Ness SouthboundIMPROVEMENTS
Costs$13,040
$1,655
$1,800
$24,000
$15,000
$2-$15,000
Desired•Bus Shelter
•Light Pole
•Bus Stop Flag Sign
•Bus Pad
•Ticket Machine
•Electrical Connection
Existing•Bus Stop Flag Sign
•Street Trees
UNDER CONTRACT:Real Time Information – to be confirmed by AC Transit
CONSTRAINTS:•Power for light pole will need to come from adjacent property
private power source
TOTAL: $57,495-$70,495
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
San Pablo – El Portal NorthboundIMPROVEMENTS
Existing•Bus Stop Flag Si
•Street Trees
•Tree Grate
•Audio Announce
TOTAL: $56,993-$69,993
Desired•Bus Shelter
•Light Pole
•Bus Pad
•Ticket Machine
•Electrical Connection
•Bus Stop Flag Sign
gn
Costs$13,040
$1,655
$24,000
$15,000
$2-$15,000
$1,800
UNDER CONTRACT:Real Time Information – To be confirmed by AC Transit
CONSTRAINTS:•Final stop before end of line; no boardings at this stop
•Narrow sidewalk for street furniture installations
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
San Pablo – El Portal SouthboundIMPROVEMENTS
Desired•Light Pole
•Bus Stop Flag Sign
•Bus Pad
•Ticket Machine
•Electrical Connection
Existing•Bus Shelter
•Seat Bench w/o Backs
•Trash Bin
•Bus Stop Flag Sign
•Bus Stop System Map
•Custom Logo and Signage
•Real Time Information
•Bus Pad
TOTAL: $44,455-$57,455
Costs$1,655
$1,800
$24,000
$15,000
$2-$15,000
UNDER CONTRACT:Real Time Information
CONSTRAINTS:•Stop is in between two driveways with limited sidewalk length for
additional street furniture
•Sidewalk adjacent to restaurant parking lot
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
San Pablo – Contra Costa CollegeIMPROVEMENTS
Existing•Bus Shelter
•Bench w/ Backs
•Trash Bin
•Light Pole
•Bus Stop Flag Sign
•Custom Logo & Signage
•Real Time Information
UNDER CONTRACT:Real Time Information
TOTAL: $42,800-$55,800
Desired•Bus Stop Flag Sign
•Bus Pad
•Ticket Machine
•Electrical Connection
Costs$1,800
24,000
$15,000
$2-$15,000
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Alameda County Costs• Emeryville $ 64,324 - $90,324• Oakland $ 541,622 - $671,622• Berkeley $ 484,467 - $585,207• Albany $ 131,284 - $157,284
Subtotal $1,221,697 - $1,504,437
25% Contingency$ 305,424 - $ 376,10920% Soft Costs $ 244,339 - $ 300,887
TOTAL $1,771,461 - $2,181,434
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Contra Costa County Costs• El Cerrito $218,751 - $321,151• Richmond $172,855 - $224,855• San Pablo $367,662 - $484,662
Subtotal $759,268 - $1,030,668
25% Contingency $189,817- $257,667
20% Soft Costs $157,854- $206,134
TOTAL $1,100,939 - $1,494,469
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Total Costs of Improvements
Alameda County $1,771,461-$2,181,434Contra Costa County $ 1,100,939-$1,494,469Ticket Machine Start Up Cost $ 750,000 TOTAL $3,622,400 - $4,425,903
San Pablo Rapid Bus Inventory 2004
D R A F T Costs are at planning level only.
Site Constraints Identified by AC Transit
• Proof of Payment and Ticket Machines• Bus Shelters• Trash receptacles• Concrete Unit Pavers• Information Kiosks• Real Time Information• Stop Flag Signs• Light Poles (ownership, maintenance, liability issues)• Benches, Recycling Receptacles, Lean-on Rails and Freestanding
System Maps (ownership, maintenance, liability Issues)• Street Trees and Tree Grates• Pedestrian Countdowns, Security Cameras and Audio Announce