Transcript of SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.
S A N M A R C O S U N I F I E D S C H O O L D I S T R I C T
A U G U S T 1 9 , 2 0 1 4
FACILITIES UPDATEGOVERNING BOARD MEETING
2
Facilities Update: In Planning/Design
• Proposition 39: Energy Jobs Act• “Kick-off” meeting• Conduct campus analyses• Create proposed project list• Submit proposals to CEC for approval• Construct projects
• Proposition K: Campus Modernization Projects• Preliminary master plans• Preliminary site surveys• Special Board Meeting “Workshop”
8/19/2014
3
Facilities Update: In Construction
• Woodland Park MS Modernization Project
• Professional Learning Center (PLC) – NCREC – S
• Shade Shelters – MHHS, SEMS, DSC, SME
• Facilities Needs for 2014-2015 – AD, DSC, SEMS
• New Classroom Buildings – CAR, DSC, SME
• Technology Infrastructure Projects
• San Marcos K-8 School
8/19/2014
4
Facilities Update: In Construction
• Woodland Park MS Modernization Project: Aug. 2014• Completed final accessible ramp, casework (cabinets), and A/V equipment
8/19/2014
New Front Entry
5
Facilities Update: In Construction
• Professional Learning Center (PLC) at NCREC – S• Professional Development
8/19/2014
6
Facilities Update: In Construction
• Professional Learning Center (PLC) at NCREC – S• Professional Development - TOSAs
8/19/2014
7
Facilities Update: In Construction
• Professional Learning Center (PLC) at NCREC – S• Centralized Kitchen
8/19/2014
8
Facilities Update: In Construction
• Facilities Needs for 2014-2015• Discovery ES• New Shade Shelter and reconstruct Walkway Cover
8/19/2014
9
Facilities Update: In Construction
• Facilities Needs for 2014-2015• Discovery ES• New Shade Shelter and reconstruct Walkway Cover
8/19/2014
10
Facilities Update: In Construction
• Discovery ES• 1 temporary Portable Building• Until SMK8 opens
8/19/2014
11
Facilities Update: In Construction
• San Elijo MS: Support for temporary enrollment growth for 2014-15 school year
School• 3 lunches• Large P.E. classes
Facilities• Shade Shelter for PE/Lunch
• Additional Basketball Courts
• Upper Field Power/Communications
8/19/2014
12
Facilities Update: In Construction
• Facilities Needs for 2014-2015• San Elijo MS• New shade shelter, new basketball courts, new track perimeter
8/19/2014
13
Facilities Update: In Construction
• Facilities Needs for 2014-2015• San Elijo MS• New shade shelter, new basketball courts, new track perimeter
8/19/2014
14
Facilities Update: In Construction
• Facilities Needs for 2014-2015• Mission Hills HS• New shade shelter for art and outdoor classroom
8/19/2014
15
Facilities Update: In Construction
• Facilities Needs for 2014-2015• San Marcos ES• New shade shelter for Kindergarten area
8/19/2014
16
Facilities Update: In Construction
• Facilities Needs for 2014-2015• Alvin Dunn ES• New perimeter fence
8/19/2014
17
Facilities Update: In Construction
• New Classroom Buildings• Anticipated enrollment growth
at CAR and SME
8/19/2014
18
Facilities Update: In Construction
• Carrillo ES: 5-Classroom Permanent Building
8/19/2014
19
Facilities Update: In Construction
• Carrillo ES: 5-Classroom Permanent Building
8/19/2014
20
Facilities Update: In Construction
• San Marcos ES: 4-Classroom Permanent Building
8/19/2014
21
Facilities Update: In Construction
• San Marcos ES: 4-Classroom Permanent Building
8/19/2014
22
Facilities Update: In Construction
• San Marcos ES: 4-Classroom Permanent Building
8/19/2014
23
Facilities Update: In Construction
• Prop K: Technology Infrastructure Projects: • Mission Hills HS, La Costa Meadows ES, Paloma ES – Completed• Knob Hill ES, Richland ES, Twin Oaks ES, San Elijo MS – Jul. – Oct. 2014• Remaining campuses – Oct. 2014 – Spring 2015
8/19/2014
24
Facilities Update: In Construction
• Prop K: Technology Infrastructure Projects
8/19/2014
25
Facilities Update: In Construction
• Prop K: Technology Infrastructure Projects
8/19/2014
26
Facilities In Construction: SMK-8
8/19/2014
27
Facilities In Construction: SMK-8
8/19/2014
Fields
ParkingParking
Buildings
Buildings
Central
Courtyard
G O V E R N I N G B O A R D M E E T I N G
A U G U S T 1 9 , 2 0 1 4
FACILITIES UPDATE:THANK YOU!