SAN JOSE TO MERCED PROJECT SECTIONSan Jose Community Working Group Meeting

Monday, January 23, 2017

San Jose, California

Page 2: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

INTRODUCTIONS

Page 3: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

• Introductions• High-Speed Rail Statewide Program Update• San Jose to Merced Project Section Update• San Francisco to San Jose Project Section Update• Community Priorities Review• Outreach and Next Steps• Public Comment

AGENDA REVIEW

3

Page 4: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

• Purpose» Provide project updates to members» Present project alternatives to members for meaningful feedback» Access to Authority environmental and engineering technical staff» Collaborative engagement on environmental and engineering work» Move the environmental process forward in the spirit of cooperation

• Membership and Responsibilities » Broad spectrum of community representatives » Consider/present the interests of their respective communities/organizations» Participate in open communication among different interests» Help move the planning process forward in the spirit of cooperation

CWG ROLES & RESPONSIBILITIES

Page 5: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

HIGH-SPEED RAILSTATEWIDE OVERVIEW

Morgan Galli

Page 6: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

• Recent Board Actions:»Approved San Francisco to San Jose Peninsula Corridor

Segment Funding Plan »Approved Central Valley Segment Funding Plan»Approved Early Train Operator Request for Qualifications»Approved Central Valley Wye Preferred Alternative

• Next Board Meeting: February 14 in Sacramento

BOARD OF DIRECTORS: Recent Actions

Page 7: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

CONSTRUCTION UPDATE

Page 8: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

SAN JOSE TO MERCEDPROJECT SECTION UPDATE

Gary Kennerley

Page 9: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

Spring 2016Project

Definition

Ongoing Design and Technical AnalysisStation

FootprintsOutreach

Spring 2017Identify

Preferred Alternative

Summer 2017Release Draft

Environmental DocumentOutreach

Public Hearing

End of 2017Final

Environmental Document/ Record of Decision

MILESTONE SCHEDULE*

*Preliminary/Subject to Change

Page 10: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

ENVIRONMENTAL REVIEW PROCESS UPDATE

Winter• Range of alternatives developed and under public review

Spring

• Preferred Alternative developed and under public review; Board concurrence.

• Biological, cultural and geologic studies underway, with landowners visits scheduled.

Summer• Draft Environmental Impact Report and Statement

Page 11: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

SAN JOSE TO MERCED: Range of Alternatives

11

Page 12: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

SAN JOSE TO MERCED: Range of Alternatives

Page 13: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

SAN JOSE TO MERCED: San Jose Diridon Station Approach

13

Comments from 8/17/16 CWG and 8/17/16 TWG MeetingsLOCATION COMMENT

Dahlia Loop to W. Hedding Street at I-880

• Avoid neighborhood impacts

Diridon Station • Connect to BART• Reduce parking impacts

W. San Carlos Street • VTA double track/Los Gatos Creek Bridge projectsBird Avenue to Auzerias Avenue

• Support for aerial

Auzerais Avenue & West Virginia Street at Rail ROW

• Maintain ‘blighted’ ROW

I-280 to Guadalupe Freeway • Minimize property value/foundation impacts• Avoid Fuller Park no barrier/canvas for graffiti• Improve safety at rail crossings• Avoid further impacting “less fortunate and voiceless” already

impacted by transportation infrastructure• Listen to residents so they can influence decisions

Page 14: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

SAN JOSE TO MERCED: San Jose Diridon Station Approach

14

Viaduct to Scott Blvd. Viaduct to I-880

• Longer elevated section • Minimizes operational conflicts

with other rail operators

• Shorter elevated section• Reduces scale of project

• At-Grade element still being studied

60-80 feet high viaduct starts at Scott Blvd. or I-880, aerial Diridon Station, viaduct follows I-280/SR87 corridors to West Alma Ave.

Key Features:

Page 15: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

SAN JOSE TO MERCED: Monterey Corridor

15

LOCATION COMMENTMonterey Corridor • Property value and visual impacts of a Viaduct?

• What is the configuration of Monterey Road with Viaduct?

• Are there sidewalks and bike lanes? • How many travel lanes, turn lanes?• Utility impacts?

At Skyway Drive • Access to Valley Christian High School• Pedestrian crossing of Monterey Road

Between Branham Lane and Chynoweth Avenue

• Storm drainage, sanitary sewer and ATT fiber optic impacts?

Blossom Hill Road • US 101 Blossom Hill interchange project

Comments from 8/17/16 CWG and 8/17/16 TWG Meetings

Page 16: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

SAN JOSE TO MERCED: Monterey Corridor

16

Viaduct At-Grade

• In Monterey median • 60-80 feet high• No road grade separations• Minimizes utilities disturbance• More usable space under viaduct

• Adjacent to UPRR• Major roadway crossings would

be grade separated• Monterey lowered 30 feet at

grade separations• Some minor roadway crossings

would be closed • Includes intrusion barrier

At-grade through Communication Hill, transitions to viaduct in median of Monterey or continues at-grade east of UPRR to Coyote Creek Park.

Key Features:

Page 17: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

SAN FRANCISCO TO SAN JOSE PROJECT SECTION UPDATE

Morgan Galli

17

Page 18: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

SAN FRANCISCO TO SAN JOSE: Update• 51-Mile Corridor

• Two alternatives along the blended service alignment

• Key Project Elements:» Alignment Operations» Brisbane Light Maintenance Facility» Passing Tracks» Stations• San Francisco (4th and King)• Millbrae (SFO)• San Jose (Diridon)

Page 19: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

• Range of alternatives developed and under public review• Preferred Alternative development to follow the current phase of

public involvement• Draft Environmental Impact Report/Statement will be ready for

review in late 2017• Community Working Groups:» San Mateo County CWG: January 30 at Millbrae Library» Santa Clara County CWG: January 31 at Central Park Library (Santa Clara)» San Francisco CWG: February 2 at MTC (San Francisco)

• Open House Meetings in March

SAN FRANCISCO TO SAN JOSE: Update

Page 20: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

COMMUNITY PRIORITIES REVIEW

Bruce Fukuji

Page 21: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

Avoidadverse impacts

Minimizeimpacts, when they cannot be avoided

Mitigateimpacts, when they cannot be avoided

or minimized

AVOIDING, MINIMIZING & MITIGATING POTENTIAL IMPACTSEnvironmental Process

Notice of Determination /

Record of Decision

Preferred Alternative

Alternatives Analysis

Draft Environmental

Document

Final Environmental

Document

ConfirmIdentify Inform

Collaborative Opportunities

Page 22: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

WE ARE HERE

Summer 2016 Early 2017 Spring 2017

Identify Community Objectives and Criteria

Confirmation of projects, objectives and criteria

Prioritize Projects with Nexus to Preferred Alternative

22

Page 23: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

NEXT STEPS

» Part of High-Speed Rail Project

» Collaborative Opportunity with High-Speed Rail Project

» Local Project

Prioritized List

23

Page 24: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

URBAN VIADUCT DESIGN EXAMPLE

Page 25: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

URBAN VIADUCT DESIGN EXAMPLE

Page 26: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

URBAN VIADUCT DESIGN EXAMPLE

Page 27: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

URBAN VIADUCT DESIGN EXAMPLE

Page 28: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

SAN JOSE DIRIDON STATION URBAN DESIGN APPROACH

Page 29: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

SAN JOSE STATION URBAN DESIGN OPPORTUNITIES

Page 30: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

SAN JOSE STATION URBAN DESIGN OPPORTUNITIES

Page 31: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

VALUES EXERCISE: Key Themes – San Jose CWG

Other (87) • Impacts to residential property values/house foundations• Avoid Fuller Park and creating a barrier/canvas for graffiti • Avoid impacts to “the less fortunate and voiceless” already heavily

affected by existing transport infrastructure• Listen to residents so they can influence decisions

Livability (79) • Increase attractiveness of public realm, existing parks & open space• Increase rail crossing safety for pedestrians, bicycles and vehicles• Increase access, availability and diversity of community resources• Promote and protect low-income housing

Mobility (27) • Improve pedestrian and bicycle access and connectivity• Support tech-enabled (Uber) and employer transport (shuttles)• Enhance mobility choices and minimize wait times

Environment (17)

• Protect natural resources and minimize fracturing habitat corridors• Achieve climate goals

Economy (7) • Economic development, talent retention & local business investment• Create mixed-use community hubs at stations

Page 32: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

OUTREACH UPDATEMorgan Galli

Page 33: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

• December 2016» EGOPIC Presentation: December 7» San Martin Community Meeting: December 15» Information Table at Gilroy Public Library: December 19

• January 2017» Community/Technical Working Group Meetings

• February 2017» Seven Trees Neighborhood Association Meeting: February 1» Los Paseos Neighborhood Association Meeting: February 4» Gardner Neighborhood Association Meeting: February 13

• March 2017» Goodyear-Mastic Neighborhood Association Meeting: March 8» Open House Meetings: TBD

UPCOMING AND ONGOING ACTIVITIES

Page 34: SAN JOSE TO MERCED PROJECT SECTION · PDF file23.01.2017 · SAN JOSE TO MERCED PROJECT SECTION San Jose Community Working Group Meeting Monday, January 23, 2017. San Jose, California

THANK YOU & STAY INVOLVED

Website: www.hsr.ca.govHelpline: 1-800-455-8166Email: [email protected]

instagram.com/cahsra

facebook.com/CaliforniaHighSpeedRail

twitter.com/cahsra

youtube.com/user/CAHighSpeedRail

Northern California Regional OfficeCalifornia High-Speed Rail Authority 100 Paseo De San Antonio, Suite 206 San Jose, CA 95113www.hsr.ca.gov

34