San Angelo City Council November 6, 2012 Hickory Update
-
Upload
city-of-san-angelo-texas -
Category
Documents
-
view
193 -
download
0
Transcript of San Angelo City Council November 6, 2012 Hickory Update
Progress Report
November 06, 2012
San Angelo City Council
2
Agenda
1. Progress Update a. Well Field Piping
b. Transmission Main
c. Booster Pump Station & Well Field
d. Treatment
2. THM Compliance Strategies: Challenges & Solutions
3. Questions & Discussion
3
Well Field Piping
Current Status: Construction is 100% complete
Contract close-out underway with the TWDB
4
Transmission Main
NTP January 23, 2012 Substantial completion July 16, 2013 (540
days) Final completion September 14, 2013 (600
days) Current status: Construction is approximately
45% Complete
5
Progress as of Oct. 29, 2012
6
Progress Summary
Work progressing at both lay headings Over 28 miles installed Slightly behind overall schedule, but catching
up and getting closer to planned schedule Valves and appurtenance work ongoing with
dig/lay/bury
7
Sta. 2624+00 looking west (Osburn cropfield)
8
Sta. 2624+00 looking east (note the solid rock)
Dig, Lay Bury
10
Expect utilities along the way (gas, etc)….
11
Booster Pump Station & Well Field
NTP June 18, 2012 Substantial completion June 18, 2013 (365
days) Final Completion July 17, 2013 (395 Days)
12
Progress Summary
On schedule Access road complete except for BCV areas Booster pumps and well pumps in fabrication Booster pump cans on site Cleaning and video of wells nearly complete
13
Excavation for meter vault 1
14
Hickory Wells 1-9 Background Wells drilled in the 1970s Potential obstructions or items identified by the
initial video survey at some wells. TCEQ required cleaning of the well casings at
each well along with removal of debris or obstructions noted in the initial video survey followed by a new video survey to confirm the condition of the wells.
15
Current status
Cleaning and video complete for wells 1, 3, and 8. Casing in good condition.
Cleaning work ongoing of wells 2, 5, 6, and 9.
16
Current status (Continued)
Well 4 known obstruction cleared only to encounter another obstruction (rubber plug). In process of evaluating options to remove the second obstruction.
Well 7 initial cleaning complete, video revealed a split in the casing at 65 feet depth. Proposed repair is press or “swage” a sleeve inside the casing.
17
Well brush fabrication
18
Brushing and cleaning of well
19
Well purge
20
Well 4 obstruction chunk
21
Groundwater Treatment Plant Design
Procurement documents• Select radium removal system supplier
• Complete
• Advertise November 2012
Expedited Design schedule• Bid plans and specs – March 2013
• Construction start – June 2013 (pending TCEQ & TWDB approval and council award for bids)
Visited three radium removal groundwater treatment facilities
Vineland, NJ• In service since 2006; retrofitted in 2011
Upper Deerfield, NJ• In service since 2009
Aqua NJ Southern Division• In service since 2008
23
Radium Removal System Site Visits
24
Radium Removal System Site Visits
Questions?
November 6, 2012
San Angelo City Council
THM Compliance Strategies: Challenges and Solutions
November 6, 2012
City of San Angelo Council Meeting
P. Greg Pope Ph.D., P.E.
Carollo Engineers, Inc.
27
What are THMs?
Cl2 + Natural Organic Matter + Bromide Halogenated Organics (THMs)
Disinfectant THMs
28
Why do we care about THMS?
THMs (Trihalomethanes) are a family of four chemicals (chloroform, bromodichloromethane, dibromochloromethane, and bromoform) that are regulated by the USEPA
EPA maximum contaminant level = 80 µg/L Some people who drink water containing THMs
in excess of the MCL over many years may experience health problems
29
Several Factors Impact THM Formation Source water quality
• natural organic matter (NOM)
• bromide
pH Water age Disinfectant type Disinfectant concentration
30
How Can THM Formation be Controlled?
Cl2 + NOM + Bromide THMs
Alternate Disinfectants
•Chloramines
31
How Can THM Formation be Controlled?
Cl2 + NOM + Bromide THMs
Alternate Disinfectants
•Chloramines
Remove/Reduce NOM Reactivity
•Reverse Osmosis•GAC•pH Control•Ozone•Chlorine Dioxide
32
How Can THM Formation be Controlled?
Cl2 + NOM + Bromide THMs
Alternate Disinfectants
•Chloramines
Remove/Reduce NOM Reactivity
•Reverse Osmosis•GAC•pH Control•Ozone•Chlorine Dioxide
THM Removal/Degradati
on•Biological Filtration•Aeration•GAC
To limit DBP formation the COSA Uses chloramines for disinfection
0
10
20
30
40
50
60
70
80
90
100
Jun Aug Sep Nov Jan Feb Apr Jun Jul
TTH
M (
µg
/L)
Water Plant
Mathis Field
34
High bromide source waters pose a challenge to utilities that use chloramines
Parameter O.H. Ivie Reservoir
Concho River
Hickory
Bromide (mg/L) 1.6 0.89 0.39
pH 7.9 8.1 7.5
TOC (mg/L) 4.8 7.6 0.2
TDS (mg/L) 1350 950 480
Blending Treated Groundwater with Treated Surface Water Reduced THM Formation
0
20
40
60
80
100
120
140
160
180TT
HM
Fo
rmati
on
(µg/
L)
2 day THM formation
100% TSW 100% TGW75% TSW/25% TGW
50% TSW/50% TGW
25% TSW/75% TGW
36
Current THM Formation
0
10
20
30
40
50
60
70
80
90
30 minutes 5 days
TTH
Ms
(µg/
L)
pH 7.5
37
Optimizing pH Decreased THM formation
0
10
20
30
40
50
60
70
80
90
30 minutes 5 days
TTH
Ms
(µg/
L)
pH 7.5
pH 8.3
38
Summary Strategies aimed at optimizing chloramine
formation conditions may reduce THM formation. Bench –studies indicated that:
• Blending the source water with a lower bromide, less reactive groundwater decreased DBP formation.
• Disinfection at elevated pH (8.3 vs. 7.5) reduced THM formation.
Questions?
November 6, 2012
San Angelo City Council