Sample Galvanizing Procedure +ITP

download Sample Galvanizing Procedure +ITP

If you can't read please download the document

description

it

Transcript of Sample Galvanizing Procedure +ITP

  • WWW.UNGERSTEEL.COM

    PAINTING / GALVANIZING PROCEDURE

    Page 1 of 6

    CLIENT : PETROFAC P.O Reference No. : 2013030011 PROJECT : CPF Phase 1 AT BADRA OIL FIELD PROJECT NO : 18495 DOCUMENT NO : 18495/PGP/001 Rev. 02 Date:06.09.2012

    Painting Procedure 1.0 Scope

    This Procedure describe surface preparation, paint application including blast and paint materials, paint touch up and paint inspection of structural steel for CPF Phase 1 (at BATRA Oilfield) project at Unger Steel Middle East FZE paint shop at Sharjah.

    2.0 Reference

    GB088-2013-200-MT-SP-003-001 Internal lining, coating and painting specification GB088-2013-200-CS-SP-003-002 Engineering Specification for Structural Steel Works GB088-2013030011-CV-Q03-01 Inspection and Test Plan

    3.0 Surface Preparation 3.1 General

    a) All surface irregularities and laminations - Such as weld spatters, rough welds, flame cut & sharp

    edges to be smoothed and ground properly before surface preparation.

    b) All surface contamination such as oil/Grease shall be removed prior to blasting.

    c) Surface preparation shall be by blast cleaning using abrasives (either Steel Grid GL-25 in the machine or Garnet 20/60 in the manual blasting) to achieve the required cleanliness.

    3.2 Cleanliness

    a) Cleanliness shall be to Sa 2.5 / SSPC-SP10.

    b) Reference Standard/Code shall be ISO 8501-1.

    3.3 Roughness

    a) Roughness shall be minimum 40 Microns.

    b) Reference Standard/Code shall be ISO 8503-4.

  • WWW.UNGERSTEEL.COM

    PAINTING / GALVANIZING PROCEDURE

    Page 2 of 6

    4.0 Paint Application 4.1 General. The following points are to be considered at application:

    a) Paint components (A & B) & type of thinner. b) Mixing ratio. c) Paint mixing by mechanical mixer. d) Consider induction time and pot life. e) Using the correct spray nozzle. f) Measurement of wet film thickness

    4.2 Climatic Condition.

    During surface preparation & paint application the following care shall be taken

    a) No presence of wind , dust or suspended particles. b) Humidity shall not exceed 85%. c) Steel temperature not to exceed 50

    oC and should not below 5

    oC.

    d) Steel temperature to be minimum 3oC higher than the recorded dew point.

    If climatic conditions exceed the above limits, the painting activities shall not proceed. 5.0 Paint System 5.1 System 01 - Non Insulated Surfaces

    No Process Type/manufacturer No of coat D.F.T (microns)

    1 PRIMER COAT Zinch Rich Epoxy / Amercoat 132 E 1 60

    2 INTERMEDIATE

    COAT High build -polyamide-cured epoxy /

    Amercoat 310 1 130

    3 TOP COAT Aliphatic Polyurethane / Amercoat 450X 1 40

    Total

    3

    230

    (Data sheets are attached) Final Color RAL To 7035 (Light Grey). 5.2 System 06 Fire Proofed Surfaces

    No Process Type/manufacturer No of coat D.F.T (microns)

    1 Primer High Solids Epoxy / Amerlock 400C* 1 100

    Total 1 100

    * Data sheet attached Color: Red

  • WWW.UNGERSTEEL.COM

    PAINTING / GALVANIZING PROCEDURE

    Page 3 of 6

    5.1.1. Method of application: Application shall be by airless spray.( All weld seams and inaccessible areas shall be stripe coated prior to Airless spray application and handrails shall be applied by rollers or by spray to achieve required DFT) 5.1.2 Paint Touch up:

    a) Surface preparation as per DIN 55928 / Part 4 or SSPC-SP2 cleaning degree ST3. b) Painting touch up as per above system. c) Application shall be by roller or by brush. d) Paint manufacturers recommendation shall be followed. e) Repair of damaged paintwork shall be as per paint manufacturer recommendation.

    6.0 Inspection & QC 6.1 Steel preparation

    a) Ensure all surface contamination such as oil; Grease etcI are removed by using solvent or by other agreed method in accordance with SSPC SP1.

    6.2 Climatic conditions 6.2.1 General

    a) Climatic conditions shall be checked at least 3 times per day in normal weather conditions and

    results shall be recorded. b) In case of any weather changes, climatic conditions to be monitored more frequently and results

    shall be recorded. 6.2.2 Relative Humidity

    a) Relative Humidity shall be measured by calibrated instrument b) Acceptance standard shall be ISO 8502-4. c) Relative Humidity shall be measured and recorded 3 times a day and the result shall be recorded.

    6.2.3 Dew point

    a) Dew point shall be measured by calibrated instrument. b) Acceptance standard shall be ISO 8502-4. c) Dew point shall be measured and recorded at least 3 times a day and results shall be recorded.

    6.2.4 Steel temperature

    a) Steel temperature should not be exceeding to 50oC and should not below 5

    oC.

    b) Steel temperature shall be measured by calibrated Thermometer. c) Acceptance standard shall be ISO 8502-4. d) Steel Temperature shall be measured at least 3 times a day and the results shall be recorded.

  • WWW.UNGERSTEEL.COM

    PAINTING / GALVANIZING PROCEDURE

    Page 4 of 6

    6.3 Surface preparation

    a) After surface preparation the member is inspected to ensure that it complies with the blasting / cleanliness standard specified.

    b) Dust shall be blown by compressed air. 6.3.1 Cleanliness

    a) Cleanliness shall be to Sa 2.5 b) Acceptance standard shall be ISO 8501-1.

    6.3.2 Roughness

    a) Surface roughness to be checked by using calibrated roughness comparator / PRESS-O-FILM or any other equivalent method.

    b) Roughness shall be Fine to coarse, minimum 40 Microns and in accordance with the recommendation of paint manufacturer.

    c) Acceptance standard shall be ASTM D-4417 / ISO 8502.1,2,3. d) Roughness shall be measured at least per shift and recorded.

    6.4 Paint application 6.4.1 General

    a) During the application of each coat wet film thickness checks shall be regularly carried out by the sprayer to ensure that the correct amount of material is being applied to achieve the required dry film thickness for each coat.

    b) Each coat is inspected to ensure that the dry film thickness has been achieved and also to ensure that all areas have been properly coated (i.e. Without bubbles,

    straining, sagging Ietc), if not remedial action is carried out to ensure compliance with the specification. 6.4.2 Wet film Thickness (WFT)

    a) Wet film thickness shall be measured with WFT Comb in accordance with requirements of paint Data Sheets.

    b) Wet film thickness should be sufficient to achieve dry film thickness as per clause 4.0 of this procedure.

    c) Acceptance Standard shall be ISO 2808 method No. 7B. d) Wet film thickness shall be measured in every shift.

    6.4.3 Dry film Thickness (DFT)

    a) Dry film thickness shall be measured by calibrated instrument (Elcometer) that has been calibrated against master-calibrated Shims in accordance with requirements of Data Sheets.

    b) Dry film thickness shall be as per paint clause 4.00 of this procedure. c) Acceptance Standard shall be SSPC PA2. d) Dry film thickness shall be measured in every shift as per ISO 2808 method No.6.

  • WWW.UNGERSTEEL.COM

    PAINTING / GALVANIZING PROCEDURE

    Page 5 of 6

    6.4.4 Adhesion Test The adhesion of primer to the steel substrate and the inter coat adhesion of the subsequent coat(s) after curing shall be determined by the application of either a cross-cut test in accordance with ISO 2409 or a pull-off test described in ISO 4624 in a separate test specimen at first batch of production paint application. 6.5 Inspection Record

    Air temperature, wet bulb temperature, relative humidity, dew point, steel temperature, surface profile, wet film thickness & dry film thickness shall be measured and the range of measured values for the batch will be recorded in the Painting Report (US-QC-04) [attached in the next page]

  • WWW.UNGERSTEEL.COM

    PAINTING / GALVANIZING PROCEDURE

    Page 6 of 6

  • Page 1 of 4 Revision date:12-02-2008

    Amercoat 132E Zinc Epoxy Primer

    Product Data/ Application Instructions

    An experience-proven metallic zinc epoxy primer EPA compliant in the United Kingdom as a single

    coat protective finish Provides cathodic protection Forms durable coating systems with a wide range

    of topcoats No maximum overcoating time restrictions Easily applied by airless or conventional spray

    Typical Uses In combination with suitable topcoat systems Amercoat 132E can be used for the following applications. INDUSTRIAL - Structural steel, machinery, pipes and tank exteriors in paper mills, oil refineries, power plants, desalination plants, chemical process and waste treatment plants. MARINE - Decks, topsides and superstructures of ships, barges and workboats. Piers, offshore platforms and related structures. An interior of dry cargo holds.

    Outstanding Characteristics Amercoat 132E is a polyamide cured zinc epoxy primer. The zinc content provides a cathodic protection if the film is damaged. Applied as part of a coating system Amercoat 132E provides excellent performance in a wide range of aggressive environments. With the suitable topcoats, withstands splash or spillage of water, solvents, chemicals and petroleum products.

    Qualifications Complies with the compositional requirements for SSPC Paint 29

    Typical systems: First coat Intermediate

    coating options Finish coat options

    Amercoat 132E Amercoat 370 Amercoat 385

    Amercoat 450 series Amercoat 229

    Amercoat 132E Amerlock series Amercoat 383H

    Amercoat 450 series

    Physical Data

    Finish ..................................... matt

    Colour .................................... grey

    Components .......................... 2

    Mixing ratio (by volume) resin ..................................... 5 parts cure...................................... 1 part

    Curing mechanism ................ solvent release and reaction between components

    Volume solids ........................ 60% (ISO 3233)*

    VOC** EC SED 1999/13/EC ........... 206 g/kg (410 g/l) UK PG6/23(92) Appendix 3 . 350 g/l l

    Dry film thickness .................. 50-75 m per coat (2-3 mils)

    Number of coats .................... 1

    Calculated coverage .............. 12 m/l (at 50 m) 489 f2/gal (at 2 mils)

    Allow for application losses, surface irregularities, etc.

    Specific gravity ...................... 1.9 kg/l (mixed product)

    Flash points (Closed Cup)...... C F resin .................................... 25 77 cure ..................................... 25 77 Amercoat 18 ....................... 25 77

    Thinner/cleaner ..................... Amercoat 18

    * Volume solids is measured in accordance with ISO 3233. Slight variations 3% may occur due to colour and testing variances.

    ** VOC figures are quoted according to both the EC directive 1999/13/EC which are theoretically calculated figures and the UK PG6/23(92) Appendix 3 which are practically determined figures.

    Amercoat

  • Amercoat 132E

    Page 2 of 4 Revision date:12-02-2008

    Repair Amercoat 132E may be used to repair itself.

    Surface Preparation New steel without pits or depressions should be abrasive blast cleaned in accordance with Sa 2 SIS 05 5900-1967 or ISO 8501-1. Previously painted or pitted steel, blast in accordance with Sa 2 . Note: Blast to achieve a 35 to 65 m profile as determined with Testex Press-O-Film tape or similar instrument. Remove abrasive residues and dust from surface. IMPORTANT - Apply Amercoat 132E as soon as possible after surface preparation to prevent any contamination. Do not leave blasted steel uncoated overnight. In case of contamination, remove contaminants. Spot blast steel if needed.

    Application Equipment The following equipment is listed as a guide and suitable equipment from other manufacturers may be used. Adjustments of pressure and change of tip size may be needed to obtain the proper spray characteristics. AIRLESS SPRAY - Standard airless spray equipment, having a 28:1 or higher pump ratio and a fluid tip with a 0.43 to 0.58 mm (0.017 to 0.023 inch) orifice. CONVENTIONAL SPRAY - Industrial equipment With separate air and fluid pressure regulators, mechanical pot agitator and a moisture and oil trap in the main air supply line are recommended. MIXER - Use power mixer powered by an air motor or an explosion proof electric motor.

    Overcoating For final use the Amercoat 132E is normally overcoated with PPG epoxy coatings or other suitable topcoats. Before overcoating, ensure surface is clean and free from zinc salts and other contamination.

    Application Data

    Substrate ..................... abrasive blasted steel

    Surface preparation ...... abrasive blast to ISO 8501-1 to SA 2

    Application method ....... airless or conventional spray, brush or roller**

    Mixing ratio (by volume) resin ............................ 5 parts cure............................. 1 part

    Environmental conditions surface temperature:... 5-50C (41-122F)

    Surface temperature must be at least 3C (5F) above dew point to prevent moisture condensation on the surface. For optimum performance curing temperature should not be less than 10C.

    Potlife (at 20C/68F) ... 8 hours

    Potlife is dependent on temperature.

    Drying times (C/F)...... 10 20 30 40 Touch dry (minutes).... 60 40 30 20 dry through (hours) ..... 4 2 1 1

    Topcoat times (C/F) ... 10 20 30 40 Minimum (hours)......... 4 2 1 1 Maximum .................... - - - -

    Drying and curing times are dependent on air and steel temperature, applied film thickness, ventilation and other environmental conditions. Times are proportionally shorter at higher temperatures and longer at lower temperatures.

    Thinner/cleaner ............ Amercoat 18

    ** Brush and roller application are only suitable for small areas.

  • Amercoat 132E

    Page 3 of 4 Revision date:12-02-2008

    Application Procedure Amercoat 132E is packaged in the proper mixing proportions of resin and cure. Resin: 8.33 l (2,2 gal) in 10 l can Cure: 1.67 l (0,44 gal) in 2 l can 1. Flush equipment with Amercoat 18 before use. 2. Stir resin (in the larger container) to an even consistency

    with a power mixer. 3. Add cure to resin and continue stirring for 5 minutes.

    Note: Since the potlife is limited and shortened by high temperatures, do not mix more material than will be used in 8 hours at 20C (68F).

    4. Thinning is normally not required for airless spray. For conventional spray, thin only as needed for workability, with up to 10 vol.% of Amercoat 18.

    5. Stir during application to maintain uniformity of material. Apply a wet coat even, parallel passes. Overlap each pass 50% to avoid bare areas, pinholes or holidays.

    6. Double coat all welds, rough spots, sharp edges and corners, rivets, bolts, etc.

    7. Application at 85 m (3,4 mils) wet film thickness will normally provide 50 m (2 mils) dry film, or 125 m (5 mils) wet film for 75 m (3 mils) dry film

    8. Check thickness of dry coating with a non- destructive dry film thickness gauge, such as Mikrotest or Elcometer. If less than specified thickness, apply additional material as needed.

    9. Small damaged or bare areas and random pinholes or holidays can be touched up by brush. Repair larger areas by spray.

    10. In confined areas ventilate with clean air during application and drying until all solvents are removed. Temperature and humidity of ventilating air must be such that moisture condensation will not form on surface.

    11. Clean all equipment with Amercoat 18 immediately after use or at least at the end of each working day or shift. When left in spray equipment, Amercoat 132E will cure and cause clogging.

    Before using the product, read the label on the can and consult the Material Safety Datasheet.

    Shipping Data

    Packaging resin ............................... 8.33 l (2,2 gal) in 10 l can cure ................................ 1.67 l (0,44 gal) in 2 l can

    Shipping weight resin ............................... approx. 20 kg cure ................................ approx. 2.2 kg

    Shelf life ............................ 1 year from shipment date when stored indoors in unopened, original containers at 5 to 40C (41-104F).

  • Amercoat 132E

    PPG Industries Netherlands BV Tel +(31) 345 587 200

    www.ppgpmc.com

    Page 4 of 4 Revision date: 12-02-2008

    Caution This product is flammable. Keep away from heat and open flame. Keep container closed. Use with adequate ventilation. Avoid prolonged and repeated contact with skin. If used in confined areas, observe the following precautions to prevent hazards of fire or explosion or damage to health: 1. circulate adequate fresh air continuously during

    application and drying; 2. use fresh air masks and explosion proof equipment; 3. prohibit all flames, sparks, welding and smoking. Do not empty into drains. Take precautionary measures against static discharges. For specific information on hazardous ingredients, required ventilation, possible consequences of contact and safety measures see Safety Data Sheet.

    Safety Since improper use and handling can be hazardous to health and cause of fire or explosion, safety precautions included with Product Data/Application Instruction and Material Safety Data Sheet must be observed during all storage, handling, use and drying periods.

    Warranty PPG warrants its products to be free from defects in material and workmanship. PPGs sole obligations and Buyers exclusive remedy in connection with the products shall be limited, at PPGs option, to either replacement of products not conforming this warranty or credit to Buyers account in the invoiced amount of the non-conforming products. Any claim under this warranty must be made by Buyer to PPG in writing within five (5) days of Buyers discovery of the claimed defect, but in no event later than the expiration of the applicable shelf life, or one year from the delivery date, whichever is earlier. Buyers failure to notify PPG of such non-conformance as required herein shall bar Buyer from recovery under this warranty.

    PPG makes no other warranties concerning the product. No other warranties, whether express, implied or statutory, such as warranties of merchantability or fitness particular purpose, shall apply. In no event shall PPG be liable for consequential or incidental damages.

    Any recommendations or suggestion relating to the use of the products made by PPG, whether in its technical literature, or response to specific enquiry, or otherwise, is based on data believed to be reliable; however, the products and information are intended for use by Buyers having requisite skill and know-how in the industry, and therefore it is Buyer to satisfy itself of the suitability of the products for its own particular use and it shall be deemed that Buyer has done so, as its sole discretion and risk. Variation in environment, changes in procedures of use, or extrapolation of data may cause unsatisfactory results.

    Limitation of Liability PPGs liability on any claim of any kind, including claims based upon PPGs negligence or strict liability, for any loss or damage arising out of, connected with, or resulting from the use of the products, shall in no case exceed the purchase price allocable to the products or part thereof which give rise to the claim. In no event shall PPG be liable for consequential or incidental damages. Due to PPGs policy of continuous product improvement, the information contained in this Product Data/Application Instructions sheet is subject to change without notice. It is the Buyers responsibility to check that this issue is current prior to using the product. For the most up-to-date Product Data/Application Instructions always refer to the PPG Protective & Marine Coatings website at www.ppgpmc.com To avoid any confusion that may arise through translation into other languages, the English version of the Product Data/Application Instructions will be the governing literature and must be referred to in case of deviations with product literature in other languages.

    Condition of Sale All our transactions are subject to our Terms and Conditions of Sale.

    Ameron Coatings has become part of PPG Industries