Page 1 of 1TAKENAKA (MALAYSIA) SDN BHD
GROUNDING RESISTANCE FOR POWER
Project Name :Date of Measurement :Model no. of Measure :Building HeightBuilding Structure
(m) / PoleGrounding Electrode Rod
Grounding Electrode PlateSort of Soil / Water level
Lightning Rod Top Lebel from ground/material
Lightning Grounding Electrod Depth
Page 1 of 1TAKENAKA (MALAYSIA) SDN BHD
GROUNDING RESISTANCE FOR POWER Grounding Resistance for Power / Telephone / Lan (mark circle your choice)
Grounding Resistance for Power / Telephone / Lan (mark circle your cho
Project Name : TESCO-EXTRA,PLENTONG Measured by : WH Choong (TM)/ LC Siong (CBH)
: 9/5/2008
: KYORITSU Earth Tester Model 4106 alibration due date : 5/1/2009
Building Height 17,370 Meter
Record
No. location
Building Structure Metal Roofing on RC Column. 1 GL/AA-3 4
(m) / Pole 2 GL/AA-4 4
mmφ mmL nos19 × 1500 × 3
mm mm nos
× × ×
Clay Earth / 6.275m 2.8
2 x 4.5 m Grounding Constractor CBH Engineering Sdn bhd
Remarks
layout drawing
direction N
Remarks
electrical works
Date of Measurement
Model No. of Measure
Grounding Resistance(Ω)
Total Resistance(Ω)
Lightning Rod Top Lebel from ground/material Grounding Electrode Rod
Grounding Electrode Plate
(thickness)mm
Sort of Soil / Water level
Lightning Grounding Electorode Depth
(top of electrode)
Grounding Resistance for Power / Telephone / Lan (mark circle your cho
Project Name : TESCO-EXTRA,PLENTONG Measured by : WH Choong (TM)/ LC Siong (CBH)
: 9/5/2008
: KYORITSU Earth Tester Model 4106 alibration due date : 5/1/2009
Building Height 17,370 Meter
Record
No. location
Building Structure Metal Roofing on RC Column. 1 3.5 & 4.0
(m) / Pole 2 4.0 & 4.0
mmφ mmL nos3 3.0 & 3.5
19 × 1500 × 3mm mm nos
4 3.0 & 3.0× × ×
Clay Earth / 6.275m 0.9
8 x 4.5 m Grounding Constractor CBH Engineering Sdn bhd
Remarks
layout drawing
direction N
Remarks
electrical works
Date of Measurement
Model No. of Measure
Grounding Resistance(Ω)
Total Resistance(Ω)
GL/L-18 (2sets)
Lightning Rod Top Lebel from ground/material
GL/M-18 (2sets)
Grounding Electrode Rod
GL/N-18 (2sets)
Grounding Electrode Plate
(thickness)mmGL/O-18 (2sets)
Sort of Soil / Water level
Lightning Grounding Electorode Depth
(top of electrode)
Lightning Grounding Resistance Measurement
Project Name : TESCO-EXTRA,PLENTONG Measured by : WH Choong (TM)/ LC Siong (CBH)
: 9/5/2008
: KYORITSU Earth Tester Model 4106 alibration due date : 5/1/2009
Building Height 17,370 Meter
Record
No. location
Building Structure Metal Roofing on RC Column. 1 GL/AA-6 5
3 (m) / Pole 2 GL/AA-12 4
mmφ mmL nos3 GL/Q-6 5
19 × 1500 × 3mm mm nos
4 GL/Q-12 5× × ×
Clay Earth / 6.275m 5 GL/Q-15 5
5 x 4.5 m Grounding Constractor CBH Engineering Sdn bhd
layout drawing
layout drawing
direction N
electrical works
Date of Measurement
Model No. of Measure
Grounding Resistance(Ω)
Total Resistance(Ω)
Lightning Rod Top Lebel from ground/material Grounding Electrode Rod
Grounding Electrode Plate
(thickness)mm
Sort of Soil / Water level
Lightning Grounding Electorode Depth
(top of electrode)
Illumination Photometry (emergency lighting) measure unit: lux
Project Name : Measured by :
: 00/00/2007
: Calibration due date : 00/00/2007
Floor Room name or Locationlighting fitting
measurementfluorescent incandescent(W)×nos (W)×nos Max Min
× ×
× ×
× ×
× ×
× ×
× ×
× ×
× ×
× ×
× ×
× ×
× ×
× ×
× ×
× ×
× ×
× ×
× ×
× ×
× ×
× ×
Remarks
Date of Measurement
Model No. of Measure
electrical works
measure unit: lux
00/00/2007
Remarks
Remarks
electrical works
Illumination Photometry (general lighting) Measure unit: Lux
Project Name : TESCO-EXTRA,PLENTONG Measured by: WH Choong (TM)/ Ben Chua (CBH)
: 12/6/2008
Measure : KYORITSU ILLUMINOMETER (Model 5200) Calibration due date : 19/4/2008
Floor Design Lux Remarks
Grd Façade 15 80 100 150
Grd External Carpark 75 30 36 50
Grd Internal Carpark 200 100 120 175
Grd M & E Room 15 300 360 350
Grd Staircase 8 150 180 160
Grd Lift Lobby 10 300 360 335
Grd Mall Area 40 500 600 550
Grd Toilets 9 500 600 510
Grd Food Court 24 500 600 650
1st M & E Room 20 300 360 325
1st Staircase 15 150 180 200
1st Lift Lobby 8 300 360 500
1st Mall Area 75 500 600 550
1st Toilets 15 500 500 510
1st Bazaar 20 500 600 570
1st Sales Area 120 900 1080 1100
1st Prep.Area 40 900 1080 920
1st BOH 70 150 180 185
1st Warehouse 50 150 180 185
1st Office 150 500 600 600
1st Canteen 20 300 360 550
1st Loading Bay 25 100 120 200
Remarks
electrical works
Date of Measurement
Room nameor location
Value ofmeasurement point
Design Primary Lux
Measurement(average) *
* measurement height must follow design condition(desigh calculation height).
Insulation Resistance Measuerment Record (lighting DB :
Project Name : Measured by:
: 00/00/2007
Measure : Calibration due date : 00/00/2007
DB name :
circuit name No. Diagram No. circuit name
DB name :
circuit name No. Diagram No. circuit name
measure unit: MΩ
Date of Measurement
Measurement(MΩ)
Measurement(MΩ)
Remarks
electrical works
00/00/2007
circuit name
circuit name
measure unit: MΩ
Measurement(MΩ)
Measurement(MΩ)
Remarks
electrical works
Insulation Resistance Measuerment Record (power panel
Project Name : TESCO-EXTRA,PLENTONG Measured by: FC Wong (TM) / LC Siong (CBH)
: 3/6/2008 ~ 13/6/2008
Measure : KYORITSU ( Isulation Tester )Model 3165 alibration due date : 5/1/2008
DB name Load name interlocking Remarks
OK/NG OK/NG OK/NG OK/NG OK/NG
SSB/G/LP DB-G/L 1000 OK OK OK - - Good
to DB-G/P 1000 OK OK OK - - Good
SSB-FC 500 OK OK OK - - Good
SSB-UPS DB-INV 500 OK OK OK - - Good
to DB-SALE 600 OK OK OK - - Good
DB-UDB/F1 500 OK OK OK - - Good
DB-UDB/F2 500 OK OK OK - - Good
SSB/EG/LP DB-EG/L 1000 OK OK OK - - Good
to DB-EG/P 1000 OK OK OK - - Good
SSB-EFC 400 OK OK OK - - Good
400 OK OK OK - - Good
400 OK OK OK - - Good
Remarks
*1 : measure secondary side of electromagnetic switch
electrical works
Measure unit: MΩ
Date of Measurement
Insulation resistance
load/unload
indication
trouble indication
manual operation
automatic operation
(MΩ) *1
60A Travellator Isolator
60A Travellator Isolator
Page 1 of 1TAKENAKA (MALAYSIA) SDN BHD
INSULATION RESISTANCE MEASUREMENT RECORD (FEEDER)
PROJECT NAME : AEON STATION 18 IPOHMeasured by :
LOR KUAN CHUANDate of measurement : 12 APRIL 2012Measure : KYORITSU 3001B Calibration due date :
FEEDER NAME WIRING METHOD
MSB-C1 (Located at Electrical Room No.1) R-Y Y-B B-R R-N Y-N B-N R Y B N
SSB-TGV 12X300mm2/1C XLPE/PVC (Al) 200 200 200 200 200 200 200 200 200 200
CP-TGV CHILLER 12X300mm2/1C XLPE/PVC (Al) 200 200 200 200 200 200 200 200 200 200
REMARKS
Witnessed by:
*1: Fill in measurement of high voltage feeder onlyElectrical Works
measurement unit: MΩ
Insulation resistance between each phase
Insulation resistance each phase to grounding
After voltage proof
testing *1
Page 1 of 2TAKENAKA (MALAYSIA) SDN BHD
INSULATION RESISTANCE MEASUREMENT RECORD (FEEDER)
PROJECT NAME : AEON STATION 18 IPOHMeasured by :
Date of measurement :Measure : KYORITSU 300TB Calibration due date : 17 JAN 2012
FEEDER NAME WIRING METHOD
R-Y Y-B B-R R-N Y-N B-N R Y B N
REMARKS
Witnessed by:
*1: Fill in measurement of high voltage feeder onlyElectrical Works
measurement unit: MΩ
Insulation resistance between each phase
Insulation resistance each phase to grounding
After voltage proof
testing *1
Page 2 of 2TAKENAKA (MALAYSIA) SDN BHD
INSULATION RESISTANCE MEASUREMENT RECORD (FEEDER)
measurement unit: MΩ
PROJECT NAME : AEON STATION 18 IPOHMeasured by:
Date of Measurement :Measure : KYORITSU 300TB Calibration due date :
FEEDER NAME WIRING METHOD
R-Y Y-B B-R R-N Y-N B-N R Y B N
REMARKS
Witnessed by:
*1: Fill in measurement of high voltage feeder onlyElectrical Works
Insulation resistance between each phase
Insulation resistance each phase to grounding
After voltage proof
testing *1
Page 1 of 3TAKENAKA (MALAYSIA) SDN BHD
INSULATION RESISTANCE MEASUREMENT RECORD (FEEDER)
PROJECT NAME : AEON STATION 18 IPOHMeasured by :
Date of measurement :Measure : KYORITSU 300TB Calibration due date : 17 JAN 2012
FEEDER NAME WIRING METHOD
R-Y Y-B B-R R-N Y-N B-N R Y B N
REMARKS
WItnessed by:
*1: Fill in measurement of high voltage feeder onlyElectrical Works
measurement unit: MΩ
Insulation resistance between each phase
Insulation resistance each phase to grounding
After voltage proof
testing *1
Page 2 of 3TAKENAKA (MALAYSIA) SDN BHD
INSULATION RESISTANCE MEASUREMENT RECORD (FEEDER)
measurement unit: MΩ
PROJECT NAME : AEON STATION 18 IPOHMeasured by:
Date of Measurement :Measure : KYORITSU 300TB Calibration due date :
FEEDER NAME WIRING METHOD
R-Y Y-B B-R R-N Y-N B-N R Y B N
REMARKS
Witnessed by:
*1: Fill in measurement of high voltage feeder onlyElectrical Works
Insulation resistance between each phase
Insulation resistance each phase to grounding
After voltage proof
testing *1
Page 3 of 3TAKENAKA (MALAYSIA) SDN BHD
INSULATION RESISTANCE MEASUREMENT RECORD (FEEDER)
PROJECT NAME : AEON STATION 18 IPOHMeasured by :
Date of measurement :Measure : KYORITSU 300TB Calibration due date : 17 JAN 2012
FEEDER NAME WIRING METHOD
R-Y Y-B B-R R-N Y-N B-N R Y B N
REMARKS
Witnessed by:
*1: Fill in measurement of high voltage feeder onlyElectrical Works
measurement unit: MΩ
Insulation resistance between each phase
Insulation resistance each phase to grounding
After voltage proof
testing *1
Page 1 of 4TAKENAKA (MALAYSIA) SDN BHD
INSULATION RESISTANCE MEASUREMENT RECORD (FEEDER)
PROJECT NAME : AEON STATION 18 IPOHMeasured by :
Date of measurement :Measure : KYORITSU 300TB Calibration due date : 17 JAN 2012
FEEDER NAME WIRING METHOD
R-Y Y-B B-R R-N Y-N B-N R Y B N
REMARKS
WItnessed by:
*1: Fill in measurement of high voltage feeder onlyElectrical Works
measurement unit: MΩ
Insulation resistance between each phase
Insulation resistance each phase to grounding
After voltage proof
testing *1
Page 2 of 4TAKENAKA (MALAYSIA) SDN BHD
INSULATION RESISTANCE MEASUREMENT RECORD (FEEDER)
measurement unit: MΩ
PROJECT NAME : AEON STATION 18 IPOHMeasured by:
Date of Measurement :Measure : KYORITSU 300TB Calibration due date :
FEEDER NAME WIRING METHOD
R-Y Y-B B-R R-N Y-N B-N R Y B N
REMARKS
Witnessed by:
*1: Fill in measurement of high voltage feeder onlyElectrical Works
Insulation resistance between each phase
Insulation resistance each phase to grounding
After voltage proof
testing *1
Page 3 of 4TAKENAKA (MALAYSIA) SDN BHD
INSULATION RESISTANCE MEASUREMENT RECORD (FEEDER)
PROJECT NAME : AEON STATION 18 IPOHMeasured by :
Date of measurement :Measure : KYORITSU 300TB Calibration due date : 17 JAN 2012
FEEDER NAME WIRING METHOD
R-Y Y-B B-R R-N Y-N B-N R Y B N
REMARKS
Witnessed by:
*1: Fill in measurement of high voltage feeder onlyElectrical Works
measurement unit: MΩ
Insulation resistance between each phase
Insulation resistance each phase to grounding
After voltage proof
testing *1
Page 4 of 4TAKENAKA (MALAYSIA) SDN BHD
INSULATION RESISTANCE MEASUREMENT RECORD (FEEDER)
PROJECT NAME : AEON STATION 18 IPOHMeasured by :
Date of measurement :Measure : KYORITSU 300TB Calibration due date : 17 JAN 2012
FEEDER NAME WIRING METHOD
R-Y Y-B B-R R-N Y-N B-N R Y B N
REMARKS
Witnessed by:
*1: Fill in measurement of high voltage feeder onlyElectrical Works
measurement unit: MΩ
Insulation resistance between each phase
Insulation resistance each phase to grounding
After voltage proof
testing *1