SAM Experiment Availability Reports & SAM decomissioning status
sam
-
Upload
p-allen-samuel-ignatius -
Category
Documents
-
view
28 -
download
4
Transcript of sam
HYDRAULIC DESIGN OF DELIVERY CISTERN (Designing cistern as a vertical drop)
Design Data :
Total Discharge = 79.2 Cumecs
No. of Pipes = 2 No's
Dia. of the Pipe = 4 m
Spacing b/w Pipes = 17 m
i. Details of D/S Canal :
F.S.L. = + 588.525 m
C.B.L. = + 585.025 m
Bed width = 17.40 m
Average G.L. = + 588.500 m
FSD = 3.50 m
1. Hydraulic Calculations :
Width of Cistern = 25 m
M.W.L. in Cistern = + 590.275 m
Delivery level for syphon action = + 592.275 m
C.L. of Delivery Pipe in cistern (D.L.) = M.W.L. - Dia. = + 586.275 m
Cistern Floor Level = D.L. - 1.5 * Dia. = 586.275 - 1.5 * 4
= + 580.275 m
Spillway Crest Level = + 588.525 m
Discharge through each pipe = 39.600 Cumecs
Area of the Pipe = 12.566
Velocity in the pipe = 3.15 m/sec
= 0.51 m
= + 588.781 m 586.78
Depth of water (DC) = 10.00 m
= 2.00 m -1.744
Head of water ( DC) = 6.00 m= 17.321 m
Say 17.500 m
2. Check for Straight length :
Jet Length (X) = V ( 2*H / g ) = 3.49 m
m2
Velocity head ( Vh = V2/2g )
T.E.L ( D.L.+ Dia. + Vh )
Head Loss ( HL )
Length of Cistern = 5 * sqrt ( HL * DC )
25
17.40
+ 580.275 m
17.50 m
Plan of Cistern :
MWL + 590.275
Crest + 588.525 FSL + 588.525
+ 586.275
CBL + 585.025
+ 584.025 m
+ 580.275
Longitudianal Section : -2.814
DESIGN OF OGEE SPILLWAY
Discharge Computations :
Discharge to be considered (Q) = 79.20 Cumecs= 2797 Cusecs
MWL = + 590.275 mCrestLevel = + 588.525 mFloor Level = + 580.275 mTWL = + 588.525 m
The discharge over the spillway is calculated as per the following formula
Q =
= (2/3)sqrt(2g)C
Height of the spillway crest measured from the Floor level ( P ) P = Crest Level - Floor Level
= 588.525 - 580.275= 8.25 m
= 1.75MWL = +588.525 + 1.75
= +590.275
Proposing U/S face of the spillway is vertical :
As per fig.3 of IS 6934:1998, for = 8.25 / 1.75= 4.71
C = 0.741 ( As per IS: 6934 fig.3)
= 2/3 x sqrt(2 x 9.81) x0.741
= 2.2
Length of the spillway required to discharge the maximum flood == 15.55 m
However provide length of spillway = 17.4 m
The discharge over the spillway Q == 2.2 * 17.4 * ((1.75) ^1.5)= 88.62 cumecs Hence OK
Effect of tail water on discharge coefficient (Effect of submergence) .As per fig.5A of IS 6934:1998:
= Discharge coefficient as affected by submergence of crest
= Head of overflow= 1.75
h = MWL - tail water level= +590.275 - +588.525= 1.75
h = 1.75
1.75
As per fig.5A of IS 6934:1998, for h = 1.75 / 1.75
= 1.00
= 0.90
Cd L H 3/2
where Cd
Assume design head (Hd)
P/Hd
Cd
Cd
Q/(CdH3/2)
Cd L H 3/2
Cs
Hd
Hd
Hd
Cs
= 0.90 x 2.2= 2.0
By Using the corrected coefficient, the discharge formula
79.2 = 2.2 x L x 1.75
L = 79.2 / (1.98 * (1.75 ^1.5))= 17m
Shape of the Profile :
Upstream quadrant:
The upstream quadrant of the crest may conform to the ellipse:
+ = 1
As per fig.2of IS 6934:1998, for = 4.714
= 0.29
hence = 0.5075
As per fig.2of IS 6934:1998, for = 4.71
= 0.164
hence = 0.287
Upstream co-ordinates:
0.000 0.2870.050 0.286 X1 = 0.5080.100 0.281 Y1 = 0.2870.150 0.2740.200 0.2640.250 0.2500.300 0.2310.350 0.2080.400 0.1770.405 0.1730.508 0.000
RL of upstream tangent point (TP) = Crest level - depth of U/s quadrant= + 588.525 - 0.287= + 588.238
Downstream Profile:
The downstream quadrant of the crest may conform to the equation:
= ….(1)
= 4.714
Cd
Cs
X12 Y1
2
A12 B1
2
P/Hd
A1/Hd
A1
P/Hd
B1/Hd
B1
X1 Y1
X21.85 K2 Hd
0.85 Y2
P/Hd
As per fig.2of IS 6934:1998, for = 4.714
Hence = 2.0
Substituting the above values in the equation (1)
= 2.0 x 1.609 x
= 3.218
= 0.311 ….(2)
To get tangent point, differentiating and equating to glacis slope
= 0.311 x 1.85 x
= 0.575
Proposing glacis slope of 0.8 : 1(H) (V)
0.575 = 1 = 1.250.8
= 1.2500 = 2.1740.575
= 2.174 1.176
= 2.494 m
= 0.311 x 2.494 1.85
= 1.686 m
Downstream co-ordinates:
0.000 0.0000.500 0.0861.000 0.3111.500 0.6582.000 1.1202.494 1.685
== 588.5 - 1.686
= + 586.839 m
+ 588.525 OCrest level
0.287+ 588.238 0.508
RL of TP 1.686 m
+ 586.839
2.494 RL of TP1
Base width of spillway at TP1 + 586.839 = 0.508 + 2.494= 3.002 m
P/Hd
K2
X21.85 Y2
X21.85 Y2
Y2 X2 1.85
dy2 / dx2 X2 0.85
dy2 / dx2 X20.85
x20.85
x20.85
X2
X2
Substituting this x2 value in Equation (2) above
Y2
Y2
X2 Y2
R.L. of TP1 Crest level - depth D/s profile (Y2)
R.L. of TP1
Y1
X1
Y2
X2
STABILITY ANALYSIS OF OGEE SPILLWAY :
MWL +590.28
1.81.8 FTL +588.53
0.287
1.686
0.508
8.25 2.494 TWL 588.525
0.8
7.96 1 6.564
8.25
+580.28 θ8.25
0.508 2.494 5.251
8.253
8.253
10.00 8.25
Uplift Pressure diagram
Case 1 : When water is up to crest level @ U/S & No water @ D/STaking moments about "A"
Sl Load Description Force L A MomentH V M
1 0.508 x 7.963 x 2.40 9.699 0.254 2.461
2 2.494 x 6.56 x 2.40 39.289 1.755 68.933
3 0.5 x 5.25 x 6.56 x 2.40 41.363 4.752 196.551
4 0.67 x 2.494 x 1.686 x 2.40 6.728 1.443 9.707
5 0.67 x 0.508 x 0.287 x 2.40 0.233 0.317 0.074
6 0.33 x 0.508 x 0.287 x 1.00 0.049 0.127 0.006
7 0.50 x 8.253 x 8.250 x 1.00 -34.042 2.751 -93.647
8 0.5 x 8.25 x 8.25 x 1.00 34.031 2.750 93.58634.031 97.360 277.671
Lever arm = 277.671 / 97.36= 2.852 m
Eccentricity = 2.852 - 8.253 / 2= 1.274 m
Allowable 'e' = 8.253 / 6 = 1.375 No tensionMaximum stress (at Toe ) = 277.671 / 8.253 x ( 1+ 6 x 1.274 / 8.253 )
64.82 Minimum stress (at heel) = 277.671 / 8.253 x ( 1- 6 x 1.274 / 8.253 )
= 2.47
W7
W5
W6 W4
WH1
WH
WH W1 W2
WH1
W3
WU
W1
W2
W3
W4
W5
W6
WU
WH
å H å V å M
t/m2
t/m2
A
Case 2 : When water is up to MWL @ U/STaking moments about "A"S.No Load Description Force L A Moment
H V H V
1 0.508 x 7.963 x 2.40 9.699 0.254 2.461
2 2.494 x 6.56 x 2.40 39.289 1.755 68.933
3 0.5 x 5.25 x 6.56 x 2.40 41.363 4.752 196.551
4 0.67 x 2.494 x 1.686 x 2.40 6.728 1.443 9.707
5 0.67 x 0.508 x 0.287 x 2.40 0.233 0.317 0.074
6 0.333 x 0.508 x 0.287 x 1.00 0.049 0.127 0.006
7 0.508 1.750 x 2.400 x 1.00 2.132 0.254 0.541
8 0.50 x 8.253 x 10.000 x 1.00 -41.264 2.751 -113.512
9 0.5 x 8.25 x 8.25 x 1.00 34.031 2.750 93.586
10 1.75 x 8.25 x 1.00 14.438 4.125 59.55548.469 58.228 317.902
Lever arm = 317.902 / 58.228= 5.460 m
Eccentricity = 5.46 - 8.253 / 2= 1.333 m
Allowable 'e' = 8.253 / 6 1.375 No tensionMaximum stress (at toe) = 317.902 / 8.253 x ( 1+ 6 x 1.333 / 8.253 )
= 75.86 Minimum stress (at heel) = 317.902 / 8.253 x ( 1- 6 x 1.333 / 8.253 )
= 1.18
Stresses @ Case1 Case2
Maximum stress (at heel ) 64.82 75.86Minimum stress (at Toe) 2.47 1.18
Factor of Safety against sliding
F = [((w – u) tan f ) / Ff) + (C.A./Fc)] / P
F = Factor of safety against slidingw = Total mass of the damu = Total uplift force
tan f = Co-efficient of internal frictionC = Cohesion of the material at the plane consideredA = Area under consideration for cohesionFf = Partial factor of safety inrespect of frictionFc = Partial factor of safety inrespect of cohesion andP = Total horizontal force
C = 100 t/m2
f = 30 Tan f = 0.577A = 8.2527 Sqm
Allowable factor of Safety = 1Table-1 of IS 6512-1984
= 1.5
= 3.6
Sl åW P Ff (åW - åU)Tanf/Ff
1 A 97.36 - 1.5 37.474 3.60 - -
2 B 97.36 34.031 1.5 64.907 3.60 229.24 8.643 OK
W1
W2
W3
W4
W5
W6
W7
WU
WH
WH1
å H å V å M
t/m2
t/m2
t/m2 t/m2
O
Ff
Fc
Load Combin
ationFC CA / FC
Factor of
safety
CHECK
3 C 58.23 48.469 1.5 22.412 3.60 229.24 5.192 OK
ENERGY DISSIPATION ARRANGEMENTS ON D/S OF SPILLWAY
Stilling Basin Type energy dissipation arrangement is proposed as per IS:4997: 1985
Spillway Crest level = + 588.525 mCistern Top level = + 591.275 m
Cistern Floor Level = + 580.275 mTWL = + 588.525 mMWL = + 590.275 m
Let
= Depth of overflow over spillway (m)
q =
= Depth of flow entering to Stilling basin =
= Critical water Depth of flow =
= Sequent Depth
= Theoretical velocity of flow in m/s =
= Actual velocity of flow in m/s
= D/s Retrogressed water Level = 588.025 m
Assuming Apron Level = 584.025 m
= 1.8
= + 589.40 - +584.025= 5.375
Q
q = QL
q = 1.98 x 1.8 1.5= 4.584
== sqrt 2 x 9.81 x 5.375= 10.27 m/s
From fig 7 of IS 7365 - 1985
1.750 m and = 5.375 m
= 0.98
= 0.98 x Vt= 0.98 x 10.270= 10.065 m/s
= q
(As per IS : 7365 - 1985 Clause 4.3.2.1)= 4.584
10.065
= 0.46 m
Hd
Discharge intensity per metre width in m3/s/m
d1 q / Va
dc (q2 / g) 1/3
d2
Vt sqrt ( 2 g H2 )
Va
H2 Depth from (FTL+Hd/2) to Apron Level (m)
Hd
H2
= Cd x L x Hd3/2
= Cd x Hd3/2
m3/s/m
Vt sqrt ( 2 g H2 )
for Hd = H2
Va
Vt
Va
d1
Va
d1
( As per IS: 4997-1968 Cla.4.3.2 )
g
= 21.01 = 1.289 m9.81
= 1.29 m
sqrt(g* d1)
= 10.065 = 4.7382.124
From IS : 4997 - 1985 Clause 4.3.2
= sqrt 1 + - 12
= 0.46 13.44 - 12
= 3.157 m=
Level at which jump will form = D/s Retrogressed water level -= + 588.025 - 3.16= + 584.868
say + 584.868 m
Provide Cistern Level at = + 584.025 m
From IS : 4997 - 1985 Clause 4.3.2
= -
4
= 3.157 - 0.464 x 0.46 x 3.16
= 19.625.81
= 3.38 m
Length of Cistern: Length of Cistern = 5 (d2 - d1)
= 5 x 3.16 - 0.460= 14.00 m
As per Cl 4.3.4.2 of IS : 4997 - 1968 and fig 8A (Recommended Length for Basin 1)As per Cl 4.3.5.1 of IS : 4997 - 1968 and fig 9A (Recommended Length for Basin 2)
= 4.738 (Basin 2 stilling basin)
= 4.8
= 4.8 x 3.16= 15.15 m
Critical Depth (dc) = q2 1/3
dc 1/3
dc
Froud Number of jet entering bucket ( Fr1) = Va
Fr1
d2 d1 8 Fr 2
d2
d2
Loss of Head (HL)
HL d2 d13
x d1 x d2
3
HL
For Froude Number (Fr)
Lb
d2
Lb
However provide 16.00 m length of stilling Basin at the level of + 584.025 m
As per Cl 4.3.5.2 of IS : 4997 - 1968 and fig 9B (Recommended Height of Basin blocks)
= 1.5
Height of Basin Blocks = 1.5 x 0.46= 0.69 m
SCHEMATIC DIAGRAM OF BASIN-I
0.47355 DentatedSill
0.6314
2.0 : 1
16.00 m
hb
d1
hb
Calculation of Uplift Pressure and Floor Thickness :
MWL +590.281.75
Crest +588.53
+588.5258.25
0.8 4.500
1 0.460 0.10 m thick wearing coat
+580.28 + 584.0250.51 2.494 5.2512 0.80
3.00 1.90
3.00+577.28 1
0.5581.03
0.5 8.253 8.000 8.000 0.5Solution :
Discharge over the Spillway = 79.2 CumecsLength of Spillway = 17.4 mWidth of Canal = 17.4 m
d2 =
d1=
Scour Depth Calculations :1. At Upstream side :
Discharge per m width of canal, q = Q/b = 79.2 / 17.4= 4.551724 cumecs/m
Silt factor,f = 2
Mean Scour depth , R = 1.34 x ( 4.552 ^2 / 2 ) ^ (1/3) ) = 2.921 m
1.5 x 2.921 = 4.382 m
= 590.275 - 4.382 585.893Depth of cut-off = 580.275 - 585.893 = -5.62 m
Depth of U/S Curtain wall = U/S FSD /3 10 / 3 = 3.333 m
However provide 3.000 m below the U/S bed level
2. At Downstream side :Discharge per m width of canal, q = Q/b = 79.2 / 17.4
= 3.958 cumecs/m
Silt factor , f = 2
Mean Scour depth,R = 1.34 x ( 3.958 ^2 / 2 ) ^ (1/3) ) = 2.661 m
2.0 x 2.661 = 5.322 m
= 588.525 - 5.322 =583.20Depth of cut-off = 584.025 - 583.2 = 0.822 m
Depth of D/S Curtain wall = D/S FSD / 2 = 4.5 / 2 = 2.250 mHowever provide 3.000 m below the D/S bed level
Mean Scour depth R = 1.34 x (q2 / f )1/3
Max Scour depth , Rmax = 1.5 R =
Scour Level = MWL - Rmax
Mean Scour depth R = 1.34 x (q2 / f )1/3
Max Scour depth , Rmax = 2.0 R =
Scour Level = MWL - Rmax
d = Depth of D/s cut-off = 3.000 mH = 8.250 m
b = floor length 0.5 +8.253+ 8 + 8 + 0.5 = 25.253 mα = b/d = = 8.418
= 4.738
= 0.402 Re
i). At U/S cutt off wall :α = b/d = 25.2527 / 3 = 8.418
= 4.738
= 30 .4%
= 70 %
ii). At D/S cut off wall :α = b/d = = 8.418
= 4.738
= 30%
25.25 30 %
70% D/s cut-offafter Prejump length
D/S of Body wall 8.500U/s cut-off 16.500
Calculation of Floor Thickness :1. At D/S Body wall :i. Overflow condition :Uplift presure at the D/S of body wall = 30 + ( 70 - 30 ) x 16.5 / 25.253
= 56 %The Cistern is resting on Impermeable foundations, hece we consider 50% of uplift pressure.
50 % Uplift Pressure = 28 % Pressure head = ( H + d - d2 ) = 8.25 + 1.75 - 4.5
= 5.50 mEffective uplift = Pressure Head x Uplift = 5.5 x 28
100= 1.540 m
Thickness of floor required = 1.54 / 1.4= 1.10 m
ii. Non-Overflow condition : Pressure head = H = 8.25Effective uplift = Pressure Head x Uplift = 8.25 x 28
100= 2.311 m
Thickness of floor required = 2.311 / 2.4= 0.96 m
Floor Thickness is provided for Maximum of above 2 conditions .Thickness of floor provided = 2.00 m including wearing coat
EXIT GRADIENT (GE)
λ ={1+sqrt(1+α2)}/2
GE = 1x H/(sqrt(λ)xΠxd
Uplift Pressures :
λ ={1+sqrt(1+α2)}/2
ØE =(1/Π) x cos-1 x ((λ-2)/λ)
Øc1 = 100-ØE =
λ ={1+sqrt(1+α2)}/2=
ØE =(1/Π) x cos-1 x ((λ-2)/λ) =
2. After Prejump length :Uplift presure at after prejump length = 30 + ( 70 - 30 ) x 8.5 / 25.253
= 43.59 %The Cistern is resting on Impermeable foundations, hece we consider 50% of uplift pressure.
50 % Uplift Pressure = 22 % Pressure head = ( H + d - d2 ) x U = 8.25 + 1.75 - 4.5
= 5.500 mEffective uplift = 5.5 x 21.8
= 1.199 mThickness of floor required = 1.199 / 1.4
= 0.856 mThickness of floor provided = 0.90 m including wearing coat