Salerie Corner Road Safety Audit Additional comment ...
Transcript of Salerie Corner Road Safety Audit Additional comment ...
\\GLOBAL\EUROPE\CARDIFF\JOBS\SAFETY AUDITS\2016 AUDITS\251967 SALERIE CAR
PARK ACCESS (S2-S3)\SALERIE CORNER ROAD SAFETY AUDIT LETTER 14-10-16.DOCX
Ove Arup & Partners Ltd | Registered in England & Wales Registered Number: 1312453 | Registered Address: 13 Fitzroy Street London W1T 4BQ
Your ref
Our ref 251967/TB/AF
File ref
Via Email 63 St Thomas Street Bristol BS1 6JZ United Kingdom
t +44 117 976 5432 f +44 117 976 5433
[email protected] www.arup.com
States of Guernsey
Traffic & Highway Services
PO Box 145
Bulwer Avenue Office
Bulwer Avenue
St. Sampsons, Guernsey
GY2 4LR
4 November 2016
Dear
Salerie Corner Road Safety Audit
We are pleased to be providing you with a draft of our Road Safety Audit Stages 2 and 3
report. In addition to the comments in the report, we would be grateful if you could bring
the following item to the attention of the Design Team.
Additional comment outside the scope of audit
Both caution strips and ladder/tramline
paving are proposed to warn pedestrians/
cyclists of potential hazards.
While the audit team does not see any
specific safety issue with the use of
different materials, it would be preferable
to use the same material throughout the
scheme to avoid confusing pedestrians/
cyclists.
The next stage in the audit process would usually be for the Design Team to prepare a
Response Report (subject to you, as Project Sponsor, requesting any changes to our audit
report). However, we appreciate that road safety audits are not routine procedure on
Guernsey and you may wish to take a different course of action.
We would also note that the report is formatted as required by HD 19/15. Our observations
are represented as “problems” and “recommendations”, and the recommendations are
given as instructions. However, this does not preclude the Design Team from suggesting
alternative mitigation works or rejecting the problem, with appropriate reasoning.
If you would like to discuss the report or have any queries, please do not hesitate to contact
me. We hope that you have found this road safety audit to be beneficial and we would
welcome an opportunity to work with you again.
251967/TB/AF
4 November 2016 Page 2 of 2
\\GLOBAL\EUROPE\CARDIFF\JOBS\SAFETY AUDITS\2016 AUDITS\251967 SALERIE CAR
PARK ACCESS (S2-S3)\SALERIE CORNER ROAD SAFETY AUDIT LETTER 14-10-16.DOCX
Yours sincerely
Senior Engineer
Traffic and Highways Services, States of Guernsey
Salerie Corner, St Peter Port -
Pedestrian and Cycle
Improvements Scheme
Road Safety Audit Stages 2 and 3
2016/6/251697/RSA2-3
Issue | 4 November 2016
This report takes into account the particular
instructions and requirements of our client.
It is not intended for and should not be relied
upon by any third party and no responsibility
is undertaken to any third party.
Job number 251697
Ove Arup & Partners Ltd
63 St Thomas Street
Bristol BS1 6JZ
United Kingdom
www.arup.com
2016/6/251697/RSA2-3 | Issue | 4 November 2016
U:\2016 AUDITS\251967 SALERIE CAR PARK ACCESS (S2-S3)\251697 SALERIE CP RSA2-3 (I).DOCX
Document Verification
Job title Salerie Corner, St Peter Port - Pedestrian and Cycle
Improvements Scheme
Job number
251697
Document title Road Safety Audit Stages 2 and 3 File reference
Document ref 2016/6/251697/RSA2-3
Revision Date Filename 251697 Salerie CP RSA2-3 (D1).docx
Draft 1 14 Oct
2016
Description First draft
Prepared by Checked by Approved by
Name
Signature
Issue 4 Nov
2016
Filename 251697 Salerie CP RSA2-3 (I).docx Description Includes clarifications following discussions with client.
Prepared by Checked by Approved by
Name
Signature
Filename Description
Prepared by Checked by Approved by
Name
Signature
Filename
Description
Prepared by Checked by Approved by
Name
Signature
Issue Document Verification with Document �
Traffic and Highways Services, States of Guernsey Salerie Corner, St Peter Port - Pedestrian and Cycle Improvements SchemeRoad Safety Audit Stages 2 and 3
2016/6/251697/RSA2-3 | Issue | 4 November 2016
U:\2016 AUDITS\251967 SALERIE CAR PARK ACCESS (S2-S3)\251697 SALERIE CP RSA2-3 (I).DOCX
Contents Page
1 Introduction 1
2 Scheme Details 2
2.1 Context 2
2.2 Scheme Description 3
2.3 Accident Data 3
3 Scope of Audits 4
4 Items Raised at the Stage 2 Audit 5
4.1 General 5
4.2 Signs and Markings 5
4.3 Non-Motorised Users 9
5 Items Raised at the Stage 3 Audit 11
6 Audit Team Statement 15
Figures
Figure 2.1: Site Location
Appendices
Appendix A
List of Documents and Drawings
Appendix B
Audit Plan
Traffic and Highways Services, States of Guernsey Salerie Corner, St Peter Port - Pedestrian and Cycle Improvements SchemeRoad Safety Audit Stages 2 and 3
2016/6/251697/RSA2-3 | Issue | 4 November 2016
U:\2016 AUDITS\251967 SALERIE CAR PARK ACCESS (S2-S3)\251697 SALERIE CP RSA2-3 (I).DOCX
Page 1
1 Introduction
This report is the Stages 2 and 3 Road Safety Audit for the junction improvement
scheme at Salerie Corner, St Peter Port, Guernsey. The audit was requested by the
Overseeing Organisation: Traffic and Highways Services, States of Guernsey. A
Road Safety Audit Brief was supplied by the Overseeing Organisation and the
Project Sponsor approved the audit team membership as follows:
IEng, MICE, AMCIHT
Ove Arup & Partners
(Certificate of Competency awarded March 2016)
MEng (Hons), MCIHT
Ove Arup & Partners
A site visit was conducted jointly by the audit team in the afternoon of
Wednesday 5 October 2016. The weather was dry and sunny but windy, and
traffic flows were moderate. The audit team was joined on site by:
States of Guernsey
States of Guernsey
Roads Policing Unit, Guernsey Police
The audit team returned to the site later in the day on Wednesday 5 October when
it was dark, and the audit team leader visited the site independently in the morning
of Thursday 6 October. The main purpose of this last visit was to observe traffic
flows during the rush hour.
The audit was undertaken in accordance with the brief provided by the Overseeing
Organisation and comprised the site visit and an examination of the documents
listed in Appendix A. The locations of identified problems are indicated on the
plans included at Appendix B.
The terms of reference are described in HD 19/15 Road Safety Audit (Highways
England, 2015) and the audit team meets the training and experience requirements
set out therein. The team has examined and reported only on the road safety
implications of the scheme as presented and has not examined or verified the
compliance of the designs to any other criteria. However, to clearly explain a
problem or recommendation, the audit team may occasionally refer to design
standards without engaging in technical audit.
The audit team has reviewed the documents listed in Appendix A and identified
potential hazards relating to the road layouts contained therein. Road Safety Audit
is based upon a qualitative risk assessment process and there is no measure of the
success achieved by any recommendations. Whilst the Road Safety Audit process
is proven to enhance the safety performance of the scheme under consideration, it
cannot guarantee its safe operation as accidents are rare and random events. Road
traffic accidents are largely caused by factors outside the audit team’s influence,
Traffic and Highways Services, States of Guernsey Salerie Corner, St Peter Port - Pedestrian and Cycle Improvements SchemeRoad Safety Audit Stages 2 and 3
2016/6/251697/RSA2-3 | Issue | 4 November 2016
U:\2016 AUDITS\251967 SALERIE CAR PARK ACCESS (S2-S3)\251697 SALERIE CP RSA2-3 (I).DOCX
Page 2
such as driving behaviour and to a lesser extent vehicle condition. The audit team
has used reasonable skill, care and diligence in the performance of its services.
2 Scheme Details
2.1 Context
One of the objectives of the States approved Integrated Transport Strategy is to
improve infrastructure for both cyclists and pedestrians, with the aim being to
encourage modal shift to more sustainable transport methods such as walking and
cycling. There are a number of measures approved in relation to cycling
infrastructure provision, including significant improvements to the main east coast
cycle path.
A review of the plans for the eastern cycle path was undertaken by Sustrans, a
leading UK charity, which is recorded and summarised in their report Active
Transport in Guernsey (February 2016). Traffic and Highway Services considered
the report and the Design Team devised a recommendation for Salerie Corner.
The scheme is located at the Salerie car park access at its junction with Glategny
Esplanade, which is part of Guernsey’s Inter Harbour Route and carries a high
volume of traffic in Guernsey terms. Figure 2.1 shows the site location.
Figure 2.1: Site Location
Traffic and Highways Services, States of Guernsey Salerie Corner, St Peter Port - Pedestrian and Cycle Improvements SchemeRoad Safety Audit Stages 2 and 3
2016/6/251697/RSA2-3 | Issue | 4 November 2016
U:\2016 AUDITS\251967 SALERIE CAR PARK ACCESS (S2-S3)\251697 SALERIE CP RSA2-3 (I).DOCX
Page 3
2.2 Scheme Description
The project involves installing a 4.5m long raised table across the full width of the
Salerie car park entrance. Motorists entering/exiting the car park will be required
to give way to cyclists and pedestrians. The application is also to provide a
realigned footway and cycle path linking to the proposed new raised table.
The reason for the raised table is to slow vehicles down when entering and exiting
the car park and to visually highlight a crossing point, to increase safety, primarily
for cyclists but also for pedestrians.
The following works are also being undertaken as part of the improvements:
a) Alteration of kerbing along the road edge in order to improve inter-visibility
between cyclists and motorists, to reduce vehicle and cyclists speeds;
b) Provision of four areas for low level planting;
c) Slight reduction in length of central traffic island to ensure traffic manoeuvres
into Salerie car park from the south can be undertaken satisfactorily;
d) Continued provision of recycling area as shown on the plan;
e) Provision of an area for people to drop off recycling items near the table
(outside the scope of the audits);
f) Removal of the bus shelter and bus layby currently situated within the cycle
path and the creation of a new bus stop in the road;
g) Installation of a small tarmacked waiting area within the planted area for
passengers to get on/off the bus;
h) Installation of an overrun island with a 50mm height kerb that will
accommodate larger vehicles turning.
2.3 Accident Data
Details of road traffic accidents at the Salerie junction occurring in the last
36 months have been provided with the audit brief. Four accidents are reported,
two of which involved cyclists. One of the cyclist collisions was a fatality at the
southern access to the Salerie car park and bollards are now in place to prevent
vehicular access. The other cyclist collision was with a pedestrian on Glategny
Esplanade. The two remaining accidents involved cars/vans only: one a nose-to-
tail collision, and one a side impact that may have been due to excessive speed
since a vehicle was flipped on its roof.
There are too few accidents to draw any conclusions as to causation or risk, but
the rate of incidence for cyclists is disproportionately high. Cyclists are involved
in 50% of collisions but represent less than 10% of traffic.
Traffic and Highways Services, States of Guernsey Salerie Corner, St Peter Port - Pedestrian and Cycle Improvements SchemeRoad Safety Audit Stages 2 and 3
2016/6/251697/RSA2-3 | Issue | 4 November 2016
U:\2016 AUDITS\251967 SALERIE CAR PARK ACCESS (S2-S3)\251697 SALERIE CP RSA2-3 (I).DOCX
Page 4
3 Scope of Audits
States of Guernsey do not generally require road safety audits for highway
schemes and a Stage 1 Road Safety Audit had not been carried out.
The proposed works were under construction at the time of the site visit, but not
progressed far enough to conduct a full Stage 3 audit. It was agreed with the
Project Sponsor that the audit would look at both Stage 2 and Stage 3 issues:
Stage 2 Recommendations relative to the detailed design that could
be addressed during construction.
Stage 3 Recommendations relative to the works as constructed so far
at the time of the site visit.
Problems and recommendations for Stage 2 represent a full audit of the detailed
design for the improvement scheme. However, Stage 3 problems and
recommendations are a partial audit because only construction of the raised table
and new traffic island was complete. Given that the majority of the works (kerbs,
street lighting, signs and markings) were still being built, the audit team is unable
to comment on the completed scheme.
No details of swept path analysis or drainage were made available for audit
although the Design Team Leader advises that both were addressed during the
scheme design.
Traffic and Highways Services, States of Guernsey Salerie Corner, St Peter Port - Pedestrian and Cycle Improvements SchemeRoad Safety Audit Stages 2 and 3
2016/6/251697/RSA2-3 | Issue | 4 November 2016
U:\2016 AUDITS\251967 SALERIE CAR PARK ACCESS (S2-S3)\251697 SALERIE CP RSA2-3 (I).DOCX
Page 5
4 Items Raised at the Stage 2 Audit
4.1 General
PROBLEM 1
Drg No: 6796/013 Rev E
Location: A: car park exit approach to raised table
Summary: Planting could restrict inter-visibility between road users and
pedestrians/cyclists
The proposed screening strip would extend from the edge of the carriageway,
and would therefore sit within the visibility splay. A maximum planting height
of 450mm is proposed for a distance of about 4m from the edge of the
carriageway, after which the height increases to over 450mm.
If the planting exceeds 450mm height near to the carriageway, either because
it's the wrong type or not maintained, there is a risk that car drivers exiting the
car park may not be able to see cyclists or pedestrians that are approaching the
crossing from the south. A pedestrian or cyclist may continue onto the crossing
and be hit by the motor vehicle that has not given way.
RECOMMENDATION 1
The screening strip should be realigned so that it follows the recycling bank,
instead of following the edge of the footway.
4.2 Signs and Markings
PROBLEM 2
Drg No: 6796/013 Rev E
Location: A and B: car park exit and entry approaches to the raised table
Summary: Drivers familiar with the junction may fail to notice that they are
now required to give way to pedestrians and cyclists
Traffic and Highways Services, States of Guernsey Salerie Corner, St Peter Port - Pedestrian and Cycle Improvements SchemeRoad Safety Audit Stages 2 and 3
2016/6/251697/RSA2-3 | Issue | 4 November 2016
U:\2016 AUDITS\251967 SALERIE CAR PARK ACCESS (S2-S3)\251697 SALERIE CP RSA2-3 (I).DOCX
Page 6
The proposed raised table is a significant change from the existing priority,
whereby pedestrians/cyclists give way to road users, and is the first scheme of
this type on Guernsey. Drivers familiar with the existing junction layout may
fail to notice that they are now required to give way to pedestrians and cyclists
at the crossing.
There is a risk of collision if both a road user and pedestrian/cyclist attempt to
use the raised table at the same time.
RECOMMENDATION 2
Provide temporary signs to diagram 7014 with the variant 'CHANGED
PRIORITIES AHEAD' on all approaches to the crossing for a period of three
months following completion of works. We recommend that the temporary
signs should be installed at the crossing itself, and they could also be installed
in advance of the crossing.
PROBLEM 3
Drg No: 6796/013 Rev E
Location: A and B: car park exit and entry approaches to the raised table
Summary: Road users may think the crossing is for pedestrians only and fail
to give way to cyclists
Give way road markings are proposed on the car park entry and exit approaches
to the raised table but there is no signage to indicate to road users that the table
is shared use. It may not be clear to road users that the table caters for
pedestrians and cyclists and that they need to give way to both users.
A road user who is unaware that both cyclists and pedestrians have right of way
may fail to see cyclists intending to proceed over the crossing. There is a risk of
collision if both a road user and cyclist attempt to use the raised table at the
same time. A pedestrian approaching the crossing will be travelling at about
4-5kph but a cyclist will be travelling at about 10-15kph. If a driver is not
intending to stop, there is a greater risk of collision with a cyclist than there is
with a pedestrian.
RECOMMENDATION 3
Provide warning 'cycle route' signs to Diag 950 on both the car park entry and
exit approaches to the raised table. It is recommended that a plate with the
legend "Cycles crossing" is also provided subject to avoiding over-provision of
Traffic and Highways Services, States of Guernsey Salerie Corner, St Peter Port - Pedestrian and Cycle Improvements SchemeRoad Safety Audit Stages 2 and 3
2016/6/251697/RSA2-3 | Issue | 4 November 2016
U:\2016 AUDITS\251967 SALERIE CAR PARK ACCESS (S2-S3)\251697 SALERIE CP RSA2-3 (I).DOCX
Page 7
signs and street clutter. We recommend that these signs should be installed at
the crossing itself.
PROBLEM 4
Drg No: 6796/013 Rev E
Location: A and B: car park exit and entry approaches to the raised table
Summary: Reduced impact of safety-critical GIVE WAY sign
The GIVE WAY signs and hump warning signs are proposed to be mounted on
the same post.
Mounting the GIVE WAY sign below the hump warning sign reduces its
impact and may increase the risk of drivers failing to give way to cyclists and
pedestrians, leading to collisions.
RECOMMENDATION 4
Locate the GIVE WAY road signs on their own posts in advance of the
crossing, say 1.5m but such that approaching drivers can see both the give way
and hump/cycle and signs.
PROBLEM 5
Drg No: 6796/013 Rev E
Location: C and D: Inter Harbour Route approaches to the car park access
Summary: Road users may not realise they need to give way leading to
sudden braking
Give way road markings are proposed at the car park entry on approach to the
raised table but there is no advance signage to indicate to road users that they do
not have priority at the table. It may not be clear to road users until the last
minute that they need to give way to pedestrians and cyclists.
A road user entering the car park and unaware that they may need to give way
at the table could brake suddenly when they realise that they do not have
Traffic and Highways Services, States of Guernsey Salerie Corner, St Peter Port - Pedestrian and Cycle Improvements SchemeRoad Safety Audit Stages 2 and 3
2016/6/251697/RSA2-3 | Issue | 4 November 2016
U:\2016 AUDITS\251967 SALERIE CAR PARK ACCESS (S2-S3)\251697 SALERIE CP RSA2-3 (I).DOCX
Page 8
priority. There is a risk of collision if both a road user and pedestrian/cyclist
attempt to use the raised table at the same time.
RECOMMENDATION 5
Provide advance warning 'cycle route' signs to Diag 950 on the Inter-Harbour
Route approaches to the table with plates bearing the legend "Cycles crossing"
and arrows. The signs would also benefit from a distance as well.
PROBLEM 6
Drg No: 6796/013 Rev E
Location: C and D: Inter Harbour Route approaches to the car park access
Summary: An entry queue at the give way could lead to blocking back onto
the main road
During the site visit, it was observed that car park users can enter in a platoon,
although at the time a contraflow was in place and this may not be a regular
occurrence during normal traffic conditions. A queue of two or more vehicles
would extend back into the main flow of traffic.
Vehicles blocking the through route may lead to sudden braking and nose-to-
tail collisions.
RECOMMENDATION 6
Provide advance warning 'cycle route' signs to Diag 950 on the Inter-Harbour
Route approaches to the table with plates bearing the legend "Cycles crossing"
and arrows. This recommendation is the same as Recommendation 5 above but
mitigates a different problem, and therefore the recommendation is repeated.
PROBLEM 7
Drg No: 6796/013 Rev E
Location: E: foot/cycleway east of crossing
Traffic and Highways Services, States of Guernsey Salerie Corner, St Peter Port - Pedestrian and Cycle Improvements SchemeRoad Safety Audit Stages 2 and 3
2016/6/251697/RSA2-3 | Issue | 4 November 2016
U:\2016 AUDITS\251967 SALERIE CAR PARK ACCESS (S2-S3)\251697 SALERIE CP RSA2-3 (I).DOCX
Page 9
Summary: Lack of centre line implies shared space that may lead to
pedestrians stepping into the path of cyclists
Pedestrians and cyclists are segregated at the crossing and the foot/cycleway
east of the junction. A short section of path between the crossing and the route
to the east is shown as shared space.
The lack of a centre-line may lead to pedestrians meandering into the path of
cyclists, leading to a collision and injury.
RECOMMENDATION 7
Provide a continuous centre-line to Diag 1049 along the length of the
segregated foot/cycleway.
4.3 Non-Motorised Users
PROBLEM 8
Drg No: 6796/013 Rev E
Location: F and G: foot/cycleway approaches to crossing
Summary: Incorrect use of tactile paving may confuse blind or partially-
sighted pedestrians
Tactile paving on the approaches to the crossing is specified as "corduroy". The
correct type of paving that should be used in this location is ladder and tramline
across the footway and cycleway respectively.
Incorrect use of tactile paving conveys misleading information to blind and
visually impaired pedestrians about the nature of the path, increasing the risk of
them being struck by a cyclist.
RECOMMENDATION 8
Provide ladder and tramline paving with a cross-section as detailed in Guidance
on the Use of Tactile Paving (Department for Transport UK, 2007).
Traffic and Highways Services, States of Guernsey Salerie Corner, St Peter Port - Pedestrian and Cycle Improvements SchemeRoad Safety Audit Stages 2 and 3
2016/6/251697/RSA2-3 | Issue | 4 November 2016
U:\2016 AUDITS\251967 SALERIE CAR PARK ACCESS (S2-S3)\251697 SALERIE CP RSA2-3 (I).DOCX
Page 10
PROBLEM 9
Drg No: 6796/013 Rev E
Location: F and G: foot/cycleway approaches to crossing
Summary: Width and location of ladder and tramline paving may be
hazardous to cyclists
Tactile paving on the approaches to the crossing would be a width of 2.4m and
on a bend.
Cyclists would be turning whilst traversing the tramline paving, and the pattern
of the tramlines can lead to loss of control and particularly in wet weather.
RECOMMENDATION 9
Relocate the tactile paving such that is away from the bend and reduce the depth
to a minimum of 800mm.
PROBLEM 10
Drg No: 6796/013 Rev E
Location: H: interface between bus stop and shared use path
Summary: Pedestrians stepping off a bus could walk straight into the path of
oncoming cyclists
Short lengths of caution strips are proposed at the interface between the bus
stop and cycleway.
If passengers alighting a bus fail to see or do not understand the caution strips,
they may step into the cycleway and cause a collision. Blind or partially sighted
bus users would be particularly at risk.
RECOMMENDATION 10
Replace the short caution strips with corduroy paving, which will be more
noticeable to both fully sighted and blind or partially sighted pedestrians.
Locate the corduroy paving such that it does not encroach into the expected
path of cyclists.
Traffic and Highways Services, States of Guernsey Salerie Corner, St Peter Port - Pedestrian and Cycle Improvements SchemeRoad Safety Audit Stages 2 and 3
2016/6/251697/RSA2-3 | Issue | 4 November 2016
U:\2016 AUDITS\251967 SALERIE CAR PARK ACCESS (S2-S3)\251697 SALERIE CP RSA2-3 (I).DOCX
Page 11
PROBLEM 11
Drg No: 6796/013 Rev E
Location: J: cycleway approach to raised table from the north
Summary: Drivers may fail to see and give way to a cyclist approaching
from the north-west
The cycleway follows a sinuous route on approach to the crossing, presumably
to mitigate cyclist speeds. However, this combined with the alignment of
Glategny Esplanade/St George's Esplanade means that a driver approaching the
crossing would have to check for cyclists behind his/her left shoulder.
Drivers may fail to see and give way to a cyclist approaching from the north-
west. There is a risk of collision if both a road user and cyclist attempt to use
the raised table at the same time.
RECOMMENDATION 11
Realign the cycleway such that it is adjacent to the footway on the approach to
the crossing, to minimise the angle which a driver is obliged to look over their
shoulder.
5 Items Raised at the Stage 3 Audit
PROBLEM 12
Drg No: 6796/013 Rev E
Location: J: raised table crossing
Summary: Pedestrians and cyclists may be hit by road users if drivers
cannot see them when it is dark
There are existing lighting columns near to the junction but these may not
adequately illuminate the new road crossing. The audit team was informed
during the site visit that additional lighting columns were being installed but no
plans have been provided.
Traffic and Highways Services, States of Guernsey Salerie Corner, St Peter Port - Pedestrian and Cycle Improvements SchemeRoad Safety Audit Stages 2 and 3
2016/6/251697/RSA2-3 | Issue | 4 November 2016
U:\2016 AUDITS\251967 SALERIE CAR PARK ACCESS (S2-S3)\251697 SALERIE CP RSA2-3 (I).DOCX
Page 12
Inadequate street lighting may lead to road users failing to see pedestrians or
cyclists on the crossing, leading to a collision. Pedestrians/cyclists could be
particularly vulnerable if they are wearing dark clothing or, in the case of
cyclists, not using front/rear lights.
RECOMMENDATION 12
Review the existing street lighting and provide additional illumination if
necessary.
PROBLEM 13
Drg No: 6796/013 Rev E
Location: J: raised table crossing
Summary: Road users may think the crossing is for pedestrians only and fail
to give way to cyclists
Two different types of pavers/setts have been used to construct the raised table
but the colours are similar. It may not be clear to road users that the crossing
caters for pedestrians and cyclists and that they need to give way to both types
of user.
A road user that is unaware that both cyclists and pedestrians have right of way
may fail to see cyclists intending to proceed over the crossing. There is a risk of
collision if both a road user and cyclist attempt to use the raised table at the
same time.
Traffic and Highways Services, States of Guernsey Salerie Corner, St Peter Port - Pedestrian and Cycle Improvements SchemeRoad Safety Audit Stages 2 and 3
2016/6/251697/RSA2-3 | Issue | 4 November 2016
U:\2016 AUDITS\251967 SALERIE CAR PARK ACCESS (S2-S3)\251697 SALERIE CP RSA2-3 (I).DOCX
Page 13
RECOMMENDATION 13
Provide 'cycle route' symbols to Diag 1057 on the crossing itself, which will
both guide cyclists and alert drivers and pedestrians to the presence of cyclists.
PROBLEM 14
Drg No: 6796/013 Rev E
Location: K: cycleway entry to raised table from the north
Summary: Cyclists entering the table at a skew angle may not see a road
user that is not giving way until it is too late to stop
The drawing shows the cycleway on approach to the road crossing at a right
angle. However, although construction was incomplete at the time of the site
visit, it did appear that the angle of approach was skew.
If the cycleway approach to the crossing is skew, a cyclist's line of vision will
not be towards the crossing. The collision risk caused by a road user not
intending to give way will be worsened by the cyclist’s skewed vision, where
they don’t see the potential hazard in time to stop.
Traffic and Highways Services, States of Guernsey Salerie Corner, St Peter Port - Pedestrian and Cycle Improvements SchemeRoad Safety Audit Stages 2 and 3
2016/6/251697/RSA2-3 | Issue | 4 November 2016
U:\2016 AUDITS\251967 SALERIE CAR PARK ACCESS (S2-S3)\251697 SALERIE CP RSA2-3 (I).DOCX
Page 14
RECOMMENDATION 14
Realign the kerbs to provide a right-angled approach to the crossing.
PROBLEM 15
Drg No: 6796/013 Rev E
Location: L: traffic island on Glategny Esplanade
Summary: Lack of illuminated bollard leading to vehicles overrunning
kerbed island
The existing island has been shortened and the illuminated bollard removed. No
replacement bollard is indicated on the drawings and a non-illuminated bollard
was in place during the site visit.
Drivers may fail to see the kerbed island and overrun the island leading to loss
of control incidents, vehicular damage and damage to the island.
RECOMMENDATION 15
Provide an illuminated bollard on the island, with a 'keep left' arrow to Diag 610
on the north-facing aspect.
Traffic and Highways Services, States of Guernsey Salerie Corner, St Peter Port - Pedestrian and Cycle Improvements SchemeRoad Safety Audit Stages 2 and 3
2016/6/251697/RSA2-3 | Issue | 4 November 2016
U:\2016 AUDITS\251967 SALERIE CAR PARK ACCESS (S2-S3)\251697 SALERIE CP RSA2-3 (I).DOCX
Page 15
6 Audit Team Statement
We certify that this audit has been carried out in accordance with HD 19/15.
AUDIT TEAM LEADER
IEng MICE AMCIHT
Senior Engineer
Ove Arup and Partners Ltd
63 St Thomas Street
Bristol
BS1 6JZ
Signed:
Date: 4 November 2016
AUDIT TEAM MEMBER
MEng (Hons), MCIHT
Engineer
Ove Arup & Partners
Blythe Gate
Blythe Valley Park
Shirley
Solihull
B90 8AE
Signed:
Date: 4 November 2016
Traffic and Highways Services, States of Guernsey Salerie Corner, St Peter Port - Pedestrian and Cycle Improvements SchemeRoad Safety Audit Stages 2 and 3
2016/6/251697/RSA2-3 | Issue | 4 November 2016
U:\2016 AUDITS\251967 SALERIE CAR PARK ACCESS (S2-S3)\251697 SALERIE CP RSA2-3 (I).DOCX
Page A1
The Road Safety Audit Brief that defined the scope and details of the scheme
included the following documents and drawings.
Title Reference
Active Transport in Guernsey, Summary Report (Sustrans) 310-08-SW-RE-01
Revision number A,
February 2016
Salerie Car Park – Block Plan, Proposed Cycle/Pedestrian Table
Original proposal – priority to motorists
6796/013 Rev C
Superseded by Rev E
Salerie Car Park – Block Plan, Proposed Cycle/Pedestrian Table 6796/013 Rev E
Salerie Car Park – Block Plan, Proposed Cycle/Pedestrian Table
Marked-up plan with signs and road markings
6796/013 Rev E
Received 7 October 2016
Salerie Car Park – Raised Table, Proposed Cycle/Pedestrian Table 6796/014 Rev E
Salerie Car Park – Location Plan, Proposed Cycle/Pedestrian Table 6796/015 Rev C
Salerie Car Park – Cyclepath Details, Proposed Cycle/Pedestrian
Table
6796/019 Rev A
Salerie car park cycle/pedestrian improvements, letter of support
from Traffic and Highway Services to Planning Services
16 August 2016
Priority status at Salerie Crossing Point, emails from Traffic and
Highways Services to Guernsey Police
23 September 2016
Priority status at Salerie Crossing Point, emails from Traffic and
Highways Services to States Members
20 September 2016
Details of Road Traffic Accidents at the Salerie Junction in the last
36 months, Traffic and Highways Services
Undated
Traffic Flow Count 2-8 March 2015
Manual Classified Count 12 May 2015 and
13 June 2016
Traffic and Highways Services, States of Guernsey Salerie Corner, St Peter Port - Pedestrian and Cycle Improvements SchemeRoad Safety Audit Stages 2 and 3
2016/6/251697/RSA2-3 | Issue | 4 November 2016
U:\2016 AUDITS\251967 SALERIE CAR PARK ACCESS (S2-S3)\251697 SALERIE CP RSA2-3 (I).DOCX
Page B1
A
B
C
D
E
F
G
J
H
I
K
L