Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and...
Transcript of Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and...
![Page 1: Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and may also be modified by applying Limitations or Exclusions to the particular category](https://reader034.fdocuments.in/reader034/viewer/2022042202/5ea2071ab6b5ef092475790f/html5/thumbnails/1.jpg)
HSE-12-009
May 2013
Safety Requirements
Whilst Working On or Adjacent to
ScottishPower Metered or Un-
Metered Supplies
![Page 2: Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and may also be modified by applying Limitations or Exclusions to the particular category](https://reader034.fdocuments.in/reader034/viewer/2022042202/5ea2071ab6b5ef092475790f/html5/thumbnails/2.jpg)
1
CATEGORIES OF AUTHORISATION FOR WORKING ON UNDERGROUND
CABLE NETWORKS Listed here is a brief description of authorisation categories required for the more common and
routine types of operational activity undertaken on and around cable networks.
Authorisation categories may be applied to one, or more, of five voltage levels (LV; 11kV; 33kV;
132kV; 275/400kV) and may also be modified by applying Limitations or Exclusions to the particular
category at the particular voltage level.
WORK CATEGORIES
Authorisation Categories. Description
WI-1 Allows the holder to work on Isolated Plant and Apparatus including work adjacent to Live Apparatus
WI-2 Allows the holder to do Non-electrical work adjacent to Live Apparatus
WI-3 Allows the holder to work on Isolated protection, telecoms or metering equipment
WI-PS Allows the holder to work under Personal Supervision only to the limit of Supervising Persons "WI"
authorisation (primarily for the purpose of training)
WL-1 Allows the holder to Work on, or near to, Live Apparatus as specified on the accompanying Live Work
Certificate
WL-2 Allows the holder to work as the Accompanying Person for work on, or near to, Live Apparatus
WL-PS Allows the holder to work under Personal Supervision only to the limit of Supervising Persons "WL"
authorisation for training purposes
All persons engaged in work in an operational area/site must hold an appropriate Work Authorisation.
Non-Authorised persons are only permitted in an operational area/site with appropriate Standby supervision.
Persons holding PS (Personal Supervision) Authorisation can only carry out activities to the limits of Persons
Authorisation they are being Personally Supervised by.
LIVE WORK CATEGORIES
Authorisation Categories. Description
WL-1.60 Changing a Single Phase Meter
WL- 1.61 Changing C.T. Operated Meters
OPERATIONAL CATEGORIES
Authorisation Categories. Description
OP-1 Switching (Without Limitation or Exclusion within Voltage Level)
OP-2 Switching (With Limitations)
OP-3 Insert and Remove LV Cut-Out Fuses
OP-PS Switching Under The Personal Supervision To The Limit Of The Accompanying Persons “OP”
Authorisation For Training Purposes
SUBSTATION ENTRY CATEGORIES
Authorisation Categories Description
EN-1 Allows the holder independent entry to substations with exposed Live conductors
EN-2 Allows the holder independent entry to substations with NO exposed Live conductors
Refer to OPSAF-13-001 (PSMSP 5.1) for further information on Authorisation Procedures including all
available categories.
This document shall be reviewed as dictated by business change or at a period no
longer than 5 years from date of issue.
![Page 3: Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and may also be modified by applying Limitations or Exclusions to the particular category](https://reader034.fdocuments.in/reader034/viewer/2022042202/5ea2071ab6b5ef092475790f/html5/thumbnails/3.jpg)
2
Your health and safety are vital to ScottishPower!
Accidents at work can be costly. Each year in the UK, they cause:
• hundreds of deaths • hundreds of thousands of
injuries • enormous pain and
suffering for workers and their families.
And accidents harm everyone financially. They can lead to increased expenses, less profit and less money for pay rises and bonuses.
ScottishPower is
taking steps to help
protect your health and safety.
According to the Health and Safety at Work Act 1974, ‘It shall be the duty of every employer to ensure, as far as is practicable, the health, safety and welfare at work of all his employees’. There are a number of regulations that support the Health and Safety at Work Act 1974, these are compulsory and apply in all situations to which the original Act applies. The two key regulations in this case are The Electricity at Work Regulations 1989 and the Electricity Safety Quality and Continuity Regulations 2002. This booklet is not a substitute for any Regulations, Codes of Practice, or health and safety policy.
![Page 4: Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and may also be modified by applying Limitations or Exclusions to the particular category](https://reader034.fdocuments.in/reader034/viewer/2022042202/5ea2071ab6b5ef092475790f/html5/thumbnails/4.jpg)
3
You play an important role When it comes to establishing and maintaining a safe
working environment.
By law, working safely is one of your responsibilities. According to the Health and Safety at Work Act 1974, ‘It shall be the
duty of every employee while at work to take reasonable care of the health
and safety of himself and of other persons who may be affected by his
acts or omissions at work’
ScottishPower, its contractors and your co-
workers are counting on you! It’s up to you to:
Follow all safety rules that relate to your duties and responsibilities.
Minimise the risk of injury to yourself and others.
Minimise the risk of damage to property.
Use protective clothing and safety equipment.
Co-operate with your employer and any other person to ensure health
and safety obligations are met.
Before you act, think! (Risk Assessment) Consider any intended activities, and: Identify possible hazards and understand the measures established
to control these hazards. Assess the risks to your staff, EnergyNetworks staff, other
contractors and the public.
Define steps to control these risks.
Record risk assessments, and communicate your findings to your
working party. Raise any unacceptable risk with your supervisor, and don’t allow
work to start until adequate control measures are established.
![Page 5: Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and may also be modified by applying Limitations or Exclusions to the particular category](https://reader034.fdocuments.in/reader034/viewer/2022042202/5ea2071ab6b5ef092475790f/html5/thumbnails/5.jpg)
4
Typical Ironclad Cablehead and Inspection Requirements
Current Service Equipment and Inspection Requirements
Inspect fuses for any
damage prior to removal and
before insertion
Check for signs of overheating
and or slack terminations also
check condition of the service
cables
Inspect integrity of the casing for any signs of damage
Large deposits of compound
below the sealing chamber
may indicate overheating and or slack terminations
Check security fittings for
intact seals
Service Cable
Check Condition &
Size of Meter Tails
-------
Missing Seals
Damaged Seals
Meter Not Operating
Double
Pole
Switch
Check Seals
100Amp Cut-Out
Sealing Chamber
Earth Block
![Page 6: Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and may also be modified by applying Limitations or Exclusions to the particular category](https://reader034.fdocuments.in/reader034/viewer/2022042202/5ea2071ab6b5ef092475790f/html5/thumbnails/6.jpg)
5
The Risk Assessment will include a
thorough inspection of all
equipment to be worked on. Prior
to work commencing
Work Isolated
Apply Shrouds & Caution Notice @
Point of Isolation
Switch off mains switch to remove load
Via Consumer Unit / Double Pole or Three Pole Switch
Isolate Incoming Supply
Remove Cut-Out Fuses,
Confirm isolation has been achieved and
incoming polarity is correct
Single Phase Meter
Supply
Establish Polarity
at 13 Amp Socket
Complete Risk Assessment
Three Phase Meter
Supply
Confirm Phase
Rotation prior to
isolation
Un-Metered
Supply
Control work areas to prevent
interruptions and protect all third
parties
![Page 7: Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and may also be modified by applying Limitations or Exclusions to the particular category](https://reader034.fdocuments.in/reader034/viewer/2022042202/5ea2071ab6b5ef092475790f/html5/thumbnails/7.jpg)
6
Internal Mains Distribution Fuse Board. Where the flat or premise to be worked in is not clearly marked
in the distribution fuse board (Bemco).
Do not attempt to identify the appropriate supply fuse by
randomly removing fuses from the fuse board.
Any customers who may be affected during the identification
shall be notified of the potential supply interruption prior to work
commencing.
Fuses can be identified with assistance of an approved fuse
finder, this is inserted into a socket within the property and
transmits a signal down the supply cable, which can then be
identified at the distribution fuse board position.
Service terminations
Three Phase Cutout 100amp – Street Lighting Cutout 16amp – Single Phase Cutout 100amp
Isolated Supply
Shroud and Caution
Notice applied at the
point of isolation.
Where reasonably
practicable secure the
door of the Fuse Board
![Page 8: Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and may also be modified by applying Limitations or Exclusions to the particular category](https://reader034.fdocuments.in/reader034/viewer/2022042202/5ea2071ab6b5ef092475790f/html5/thumbnails/8.jpg)
7
Testing
Check for Polartiy
Use Drummond Test Lamps and an independent
earth
or
A Neo Mains Tester to confirm the live conductor as
per the approved procedure within the
Live Working Manual Part 2
Test lamp indications
The Test Lamp must be proved to be working prior to and
following the tests.
Test lamp sequence can be found in Live Working Manual section 2
(OPSAF-12-003).
C.N.E (TNCS)
Combined Neutral &
Earth
S.N.E (TNS)
Separate Neutral &
Earth
Or
![Page 9: Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and may also be modified by applying Limitations or Exclusions to the particular category](https://reader034.fdocuments.in/reader034/viewer/2022042202/5ea2071ab6b5ef092475790f/html5/thumbnails/9.jpg)
8
Testing Continued
Testing a single phase LV Cut Out 230
volts.
Confirming polarity using a Neo Mains
Tester on a single phase LV cut out 230 volts
Earth loop impedance values
S.N.E Separate neutral earth
0.8 ohms (TNS)
C.N.E Combined neutral earth
0.35 ohms (TNCS)
0.8 ohms
0.35ohms
![Page 10: Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and may also be modified by applying Limitations or Exclusions to the particular category](https://reader034.fdocuments.in/reader034/viewer/2022042202/5ea2071ab6b5ef092475790f/html5/thumbnails/10.jpg)
9
Street Lighting Networks
Fifth core supply using mains distributor in conjunction with
street lighting equipment.
Live supply direct from mains distributor.
11kV
Transformer
230 / 415 volts
400amp
16 amp Fuse
Main Supply Cable
Street Lighting
Column Permanent
Live Supply. Lamp
controlled by Cell
on top of column
Substation
Typical Network
11kV
230 / 415 volts
400amp
Street Lighting Control Pillar
230 / 415 volts
100amp
Cutout
30 or 60 amp
Street Lighting Bar
Fifth Core
16 amp Fuse
Main Supply Cable
Street Lighting Column Fifth Core Supply
Substation
Transformer
Network Pillar
ON
OFF
![Page 11: Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and may also be modified by applying Limitations or Exclusions to the particular category](https://reader034.fdocuments.in/reader034/viewer/2022042202/5ea2071ab6b5ef092475790f/html5/thumbnails/11.jpg)
10
Current Transformer (C.T.) Metering
Inspect equipment for general condition and the
environment where it is positioned, prior
to commencing work.
Confirm the panel indications are lit and
the metering is operational.
Determine whether or not there are
exposed live conductors contained within
the panel.
Where live conductors or busbars are
present, they are required to be
shrouded with the approved neoprene
material using the approved insulated
gloves.
Confirm all three CTs are fitted
correctly (direction of load)
CTs should never be left open circuit.
Not shorting out the CTs can cause overheating, fire
risk & electric shock.
Current
Transformers
mounted on
exposed
copper bars
![Page 12: Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and may also be modified by applying Limitations or Exclusions to the particular category](https://reader034.fdocuments.in/reader034/viewer/2022042202/5ea2071ab6b5ef092475790f/html5/thumbnails/12.jpg)
11
Low Voltage CT Metering Muticore Connections
High Voltage CT Metering Muticore Connections
12 Core 2.5mm2
Multicore
7 Core 2.5mm2
Multicore
![Page 13: Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and may also be modified by applying Limitations or Exclusions to the particular category](https://reader034.fdocuments.in/reader034/viewer/2022042202/5ea2071ab6b5ef092475790f/html5/thumbnails/13.jpg)
12
Excavation Work
Prior to any excavation work commencing, the
following requirements shall be met.
Clear work instructions are
issued.
Correct utility records
are provided.
A calibrated cable location device is
available.
Confirm actual location of work site
using work instructions and cable
records.
![Page 14: Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and may also be modified by applying Limitations or Exclusions to the particular category](https://reader034.fdocuments.in/reader034/viewer/2022042202/5ea2071ab6b5ef092475790f/html5/thumbnails/14.jpg)
13
Consideration should also be given to the location or
position of other utilities.
Assess the area to identify inspection covers, water
valve covers and other electrical service pillars.
Haldo pillar (for bus shelter supply) & Water valve &
BT inspection covers in pavement
All excavation work shall comply with HSG 47 “Safe
Digging Practices”. Hand digging shall be carried out to
identify all utilities i.e. water,
gas and power.
No excavation equipment for
example mini excavator or JCB
shall be used within 500mm of
a potential live cable. This
work shall be carried out with
the aid of an appointed banksman.
Note:- All equipment that generates vibration, for
example vibro plates, whackers, rollers etc must be
fitted with anti vibration damping systems. This type of
equipment also has a time limited operation due to the
vibration effects on the body.
![Page 15: Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and may also be modified by applying Limitations or Exclusions to the particular category](https://reader034.fdocuments.in/reader034/viewer/2022042202/5ea2071ab6b5ef092475790f/html5/thumbnails/15.jpg)
14
Where a Risk Assessment has identified the need for
shoring, a trained competent
person shall be required to
install shoring.
Consider soil conditions, depth
of excavation and proximity of
any watercourse.
All excavations on the public
highway must comply with the
New Roads and Street Works
Act.
These are
examples of general road works signs
![Page 16: Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and may also be modified by applying Limitations or Exclusions to the particular category](https://reader034.fdocuments.in/reader034/viewer/2022042202/5ea2071ab6b5ef092475790f/html5/thumbnails/16.jpg)
15
While carrying out excavations assess the equipment
being exposed:-
Cable types whether conventional or plastic.
Presence of pilot cables possible indication of HV
cables.
Tiles or marker tapes can be used as an indication of
the presence of utilities
Confirm number of cables present using cable records
Ensure all cables within the work area are exposed to
assist in identification.
If required track to the nearest service / mains
connection to positively identify the LV mains cable.
Third party utilities drawings should be available to
confirm presence of other services.
Check for manholes, service duct access points, water
or gas main stop valves and previous excavations. These
will all give an indication of the route of services or
utilities.
![Page 17: Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and may also be modified by applying Limitations or Exclusions to the particular category](https://reader034.fdocuments.in/reader034/viewer/2022042202/5ea2071ab6b5ef092475790f/html5/thumbnails/17.jpg)
16
Always obey safety signs and symbols. They are there to protect you and your colleagues.
Prohibition (red and white)
They mean 'Don't do'.
Safe condition (green and white)
They tell you the safe way to do
something or give first aid
information.
Warning (yellow and black)
They warn you that a hazard exists.
Danger tape
This tape is used to
designate a Safety
Exclusion Zone when
removing or replacing
poles.
Mandatory (blue and white)
They instruct you that you must
observe the safety precautions
shown.
![Page 18: Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and may also be modified by applying Limitations or Exclusions to the particular category](https://reader034.fdocuments.in/reader034/viewer/2022042202/5ea2071ab6b5ef092475790f/html5/thumbnails/18.jpg)
17
As a Competent or Authorised person.
Before work begins
Make sure that you are familiar with
the work to be done.
Do not start work begin until all
documentation has been completed i.e.
Risk Assessments & Method
Statements.
Brief the working party on the work to
be done and any hazards, controls or
limitations of the work.
Ensure that the working party is fully
aware of the hazards, control measures and the limitations of work.
It is the responsibility of the Competent or Authorised person to ensure
that all member of his working party are accounted for at all times.
Make sure all members of the working party know which equipment is to
be worked on and that it has been correctly identified.
Be sure working conditions are as you would expect and that you can
carryout the necessary work within the limits specified in the work
instruction.
Only carry out the work described on the work instruction.
Ensure that a safe working environment and work methods are maintained
at all times. Use the correct/approved tools and equipment for the job.
Make sure people in the vicinity are not put in Danger from your work
activity.
Make sure safe means of access and egress are identified, utilised and
maintained throughout the work.
![Page 19: Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and may also be modified by applying Limitations or Exclusions to the particular category](https://reader034.fdocuments.in/reader034/viewer/2022042202/5ea2071ab6b5ef092475790f/html5/thumbnails/19.jpg)
18
Always remember to wear the appropriate Personal
Protective Equipment For access to certain areas, you and your working party will need
to wear personal protective equipment (PPE). This may include:
If you have any doubts about the PPE you need to wear at a
particular site, ask the site supervisor. It is the responsibility of
the wearer to inspect all PPE before use and obtain a
replacement if any item is found to be defective.
Insulated Rubber
Gloves 7.5kV Class 1
Full face visor or light eye
protection
To protect your hearing
Coveralls
![Page 20: Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and may also be modified by applying Limitations or Exclusions to the particular category](https://reader034.fdocuments.in/reader034/viewer/2022042202/5ea2071ab6b5ef092475790f/html5/thumbnails/20.jpg)
19
Be aware of the harmonised cable core identification
colours:
EXISTING HARMONISED
Hybrid service
Waveform main
Two core armoured PVC
Paper Insulated Lead Covered Cables (PILC)
Wire Armour
Tape Armour
Corrugated
Aluminium
(Coral)
Metering and Earth Cable
![Page 21: Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and may also be modified by applying Limitations or Exclusions to the particular category](https://reader034.fdocuments.in/reader034/viewer/2022042202/5ea2071ab6b5ef092475790f/html5/thumbnails/21.jpg)
20
Jointing
Safe access to and from the point of work.
Ensure a safe means of access and egress is
established prior to commencement of work and
maintained during the work.
Consideration should be given to providing ease
of access and egress to the work location for
example stepping one side on the excavation/joint
bay.
The excess excavated material shall be either
removed or placed clear of the excavation to avoid
collapse.
![Page 22: Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and may also be modified by applying Limitations or Exclusions to the particular category](https://reader034.fdocuments.in/reader034/viewer/2022042202/5ea2071ab6b5ef092475790f/html5/thumbnails/22.jpg)
21
During jointing work the appropriate precautions
shall be taken:-
Low Voltage Assess cable condition prior to and
throughout the stripping process.
Apply continuity strap.
Carry out work using only approved
Live Working Procedures and Approved
insulated tools and materials.
Equipment
Inspect Approved LV test lamps and testers for
condition and correct operation.
Neo Mains Tester
![Page 23: Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and may also be modified by applying Limitations or Exclusions to the particular category](https://reader034.fdocuments.in/reader034/viewer/2022042202/5ea2071ab6b5ef092475790f/html5/thumbnails/23.jpg)
22
Continuity
Strap
Inspect Insulated tools for
condition and suitability for
work. Report any damages or
defects and arrange for
replacements.
Inspect Instruments are in good condition, fit for purpose and
are supplied with fused leads.
Ensure that all instruments carry a current inspection or
calibration label.
Multimeter – ensure fused leads are used Megger
Tong tester - Earth Loop Impedance Tester - Phase rotation tester
![Page 24: Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and may also be modified by applying Limitations or Exclusions to the particular category](https://reader034.fdocuments.in/reader034/viewer/2022042202/5ea2071ab6b5ef092475790f/html5/thumbnails/24.jpg)
23
In case of emergency If all persons involved do their part to ensure safety,
accidents should not happen. But know how to respond
just in case.
If plant comes into contact with any Live equipment the
operator should jump clear without making contact with
the plant and ground at the same time. Control the area
to prevent access until the situation has been made safe
Call for help right away
Call the emergency services where appropriate and
contact the SAP for assistance immediately.
Ensure your personal safety
Do not try to rescue someone unless it is safe to do so,
if in doubt don’t.
Provide first aid treatment
If you have been properly trained, help the
person until medical assistance arrives. (Find
out about first aid courses if you have not
been properly trained).
![Page 25: Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and may also be modified by applying Limitations or Exclusions to the particular category](https://reader034.fdocuments.in/reader034/viewer/2022042202/5ea2071ab6b5ef092475790f/html5/thumbnails/25.jpg)
24
Secure the site
Limit access to the site until the SAP/Site Supervisor
arrives and takes control of the emergency. Prior to
giving access to the site, provide information to the
Emergency Services of the hazards and controls on site.
Ensure safe and controlled access is provided for
Emergency Services at all times.
Report the incident to
EnergyNetworks staff as
soon as possible
Provide the following
information:
The address and site
location.
The name of the
injured person and his or her employer.
When the emergency services arrived on site.
Specific details about the accident or incident.
Emergency Telephone numbers for
life or limb incidents only OCC Scotland 0141 776 2877
NMC Manweb 0151 609 4999
![Page 26: Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and may also be modified by applying Limitations or Exclusions to the particular category](https://reader034.fdocuments.in/reader034/viewer/2022042202/5ea2071ab6b5ef092475790f/html5/thumbnails/26.jpg)
25
Persons on the site have responsibilities
too!
Store materials,
equipment and
tools properly.
This should be
done as soon as
you've finished
with them. Tools
and equipment left lying around can
cause injury.
Never take
chances or
short cuts.
Report any
Health and
Safety
hazards. This
must be done
immediately.
Follow the
relevant
established
site
emergency
procedures.
Make proper use of PPE
And don't interfere with equipment
provided for Health and Safety.
Control the work site.
Control
the work
area to
prevent
third
party
access. Never try to
perform work you
are not trained
and qualified to
carryout.
Ask for help if
you are unsure
about any
procedures.
Follow all
relevant
EnergyNetwork
s Health and
Safety policies.
You should keep
up to date with
any revisions,
new
requirements or
regulations. This will include
compliance with the Safety Rules.
![Page 27: Safety Requirements Whilst Working On or Adjacent to … · 2018-02-05 · 132kV; 275/400kV) and may also be modified by applying Limitations or Exclusions to the particular category](https://reader034.fdocuments.in/reader034/viewer/2022042202/5ea2071ab6b5ef092475790f/html5/thumbnails/27.jpg)
26
How safely do you work?
Use the checklist to find out! The next time you're at work, be
sure that you: