Safe Work Method Pfeiffer Cranespdf.pdf

24
PFEIFFER Cranes Pty Ltd Name of Project _________________________ Safe Work Method Statement For General Crane Lifts

Transcript of Safe Work Method Pfeiffer Cranespdf.pdf

Page 1: Safe Work Method Pfeiffer Cranespdf.pdf

PFEIFFER

Cranes Pty Ltd

Name of Project _________________________

Safe Work Method Statement

For

General Crane Lifts

Page 2: Safe Work Method Pfeiffer Cranespdf.pdf

PFEIFFER Cranes Pty Ltd ABN 53 092 206 721

Prepared by: Reviewed by: Approved by:

Trinity Pfeiffer Jack Pfeiffer Delcie and Fred Pfeiffer OHS Engineer Managing Director Date Date Date

Client:

Project:

Work Activity: Work to be done

Address of Work Activity: Address

Personnel qualifications & experience required:

Operator with appropriate crane licence and suitable experience

Engineering details, Certificates/WorkCover approvals required:

WorkCover Registration of Plant

Legislation, Codes of Practice, Standards applicable:

Workplace Health and Safety Act 2000 Workplace Health and Safety Regulation 2001 AS 2550, AS 1418. Mobile Crane Hire Code of Practice

Supervision and inspection to be provided:

Operator work under Clients Name Site Foreman instructions

Training & induction to be provided:

Site Induction

Plant and equipment to be used:

What crane is going to be used

Maintenance checks to be performed on plant and equipment:

Pre-start inspection check Scheduled maintenance of crane Annual Inspection (Cranesafe)

Protective equipment to be used:

Personal protective clothing, eg. Hard hat, gloves, Steel cap boots etc Other as required by site.

Warning signs & control measures:

Load charts, Computer limit alarms, slew warning lights.

Details of emergency procedures:

Contact Site Foreman or Project Engineer. If incident involves significant injury, contact WorkCover & workers compensation insurance.

List of attachments:

(Any appropriate safety procedures or hazard control plans)

Page 3: Safe Work Method Pfeiffer Cranespdf.pdf

PFEIFFER Cranes Pty Ltd

Table of Contents_____________________________

Activity Steps Page 01 Toolbox Meeting 5 02 Evaluate Weather Conditions 5 03 Site Set Up 5 04 Crane Set Up 5 4.1 Chart for assessing ground conditions 6 4.2 Formula for setting up crane base 7 05 Adequate Operational Zones 7 06 Mobile Crane Operation 7 07 Crane operating within close proximity to power lines 8 08 Communications 9 09 Collision Prevention Procedures 9 10 Using Mobile phone during Crane Operation, Rigging/Dogging 10 11 Unauthorised Personnel 11 12 Lifting Equipment 11 13 Loading – Offloading Trucks 11 14 Manual Handling 11 15 Slinging Loads 15 16 Dual Lift Procedures 16 17 Loose Items 16 18 Using Safety Equipment 16 19 Ladders 16 20 Traffic Control 17 21 Safe use of Rubbish Skips 17 22 Refueling of Plant and Equipment 17 23 Noise 18 24 Heat Stress 18 25 UV Radiation 18 26 Housekeeping 18 27 19 28 19 29 19 30 19 31 19 32 20 33 20 34 20 35 20 36 20 37 20 38 21 39 21 40 21 Minimum Outrigger Pad Area and Ground Pressure Calculations 22 Acknowledgment of Tool Box Talk 23

Page 4: Safe Work Method Pfeiffer Cranespdf.pdf

PFEIFFER Cranes Pty Ltd

Safe Work Method Statement

__________________________________________________________________________________

_______________________________________________ Risk Category (VH) = Very High – (H) = + High – (SR) = Substantial Risk– (M) Moderate Risk – (LR) = Low Risk Page 4 of 24

Page 5: Safe Work Method Pfeiffer Cranespdf.pdf

PFEIFFER Cranes Pty Ltd _Safe Work Method Statement

__________________________________________________________________________________________________________________________________ Risk Category (VH) = Very High – (H) = + High – (SR) = Substantial Risk– (M) Moderate Risk – (LR) = Low Risk Page 5 of 24

Company Name: Project:

Work Task: Principle Contractor: Date of Works:

This SWMS has been approved by: Name: Fred and Delcie Pfeiffer Position: Managing Director Pfeiffer Cranes Launceston ABN 53 092 206 721 1 Donalds Avenue, Prospect, Tasmania 7250 Phone: (03) 63 431 762 Fax: (03) 63 431 728

Resources:

• Trades involved: Riggers, Crane Driver

• Equipment Used: What crane is being used

• Maintenance checks: Current lifting chain test certificates. All Crane log books to be up to date. Safety harnesses checked by competent person.

• Materials Used: Rigging equipment

Work Activity General lifts on site

Qualifications or Competencies

Licensed Crane Operator, Rigger and Dogger

Legislations Workplace Health and Safety Act 1995 Workplace Health and Safety Regulation 1997

Standards AS1418 – Cranes (including hoists and winches)

AS2550 – Cranes – Safe Use AS/NZ 1891 – Industrial fall arrest systems and devices

Page 6: Safe Work Method Pfeiffer Cranespdf.pdf

PFEIFFER Cranes Pty Ltd _Safe Work Method Statement

__________________________________________________________________________________________________________________________________ Risk Category (VH) = Very High – (H) = + High – (SR) = Substantial Risk– (M) Moderate Risk – (LR) = Low Risk Page 6 of 24

ACTIVITY STEPS

(Break the job down into steps) POTENTIAL HAZARDS

and RISKS (What can harm you?)

RISK CONTROL MEASURES (What are you going to do to make the job as safe as possible?)

RESPONSIBILITY (Who is going to ensure

this happens?)

01 Toolbox meeting

• Ensure all personnel are fully conversant with the safety precautions.

• Sign the back page.

• Pfeiffer Cranes Management

• Crane Crew

02 Evaluate weather conditions

• Inclement weather eg High Winds, Rain

• Injury to members of the public and site personnel

L • Crane to check the wind speed by either using a hand held air speed anemometer or the cranes anemometer.

• Check the cranes Load Chart and or the Operators Manual and make yourself aware of the wind limitations and shutdown point.

• All actions are to cease if inclement conditions are prevailing or if the operator deems it is unsafe to lift.

• Crane driver and riggers to advise principal Contractor and Pfeiffer Cranes .

• Pfeiffer Cranes Management

• Crane Crew

• Site Management

03 Site set up • Lack of understanding of procedures

• Lack of understanding of SWMS

H • The site manager is to explain task including point loadings and what that relates to on site.

• Crane crews are to hold the appropriate certificate of competency.

• Pfeiffer Cranes Management

• Crane Crew

• Site Manager

04

Crane set up

• Ground conditions insufficient

• Underground services

• Overhead obstructions • Unauthorised personnel

H

• Establish and barricade off adequate exclusion zones around the works (20 meters).

• Ensure crane is set up on firm ground.

• Check the area for underground services ie. Communication cables, sewerage etc.

• Make sure there are no overhead obstructions ie power lines.

• Check crane mechanically fit.

• Work within cranes capabilities and lifting specifications. • Use and adhere to crane warning devices.

• Wear hard-hats at all times.

• Non-essential personnel are kept out of this area.

• Pfeiffer Cranes Management

• Crane Crew

• Site Management

Page 7: Safe Work Method Pfeiffer Cranespdf.pdf

PFEIFFER Cranes Pty Ltd _Safe Work Method Statement

__________________________________________________________________________________________________________________________________ Risk Category (VH) = Very High – (H) = + High – (SR) = Substantial Risk– (M) Moderate Risk – (LR) = Low Risk Page 7 of 24

ACTIVITY STEPS

(Break the job down into steps) POTENTIAL HAZARDS

and RISKS (What can harm you?)

RISK CONTROL MEASURES (What are you going to do to make the job as safe as possible?)

RESPONSIBILITY (Who is going to ensure

this happens?)

4.1

Chart for assessing ground conditions

• Outriggers sinking • Crane rollover

H

• The base timbers of any packing should be closely packed and must cover as large an area as is necessary to safely transmit their load to the ground.

To estimate the area of base necessary to do this, use the formula below. The soil value (“V”) varies, according to surroundings.

• Pfeiffer Cranes Management

• Crane Crew

Page 8: Safe Work Method Pfeiffer Cranespdf.pdf

PFEIFFER Cranes Pty Ltd _Safe Work Method Statement

__________________________________________________________________________________________________________________________________ Risk Category (VH) = Very High – (H) = + High – (SR) = Substantial Risk– (M) Moderate Risk – (LR) = Low Risk Page 8 of 24

ACTIVITY STEPS

(Break the job down into steps) POTENTIAL HAZARDS

and RISKS (What can harm you?)

RISK CONTROL MEASURES (What are you going to do to make the job as safe as possible?)

RESPONSIBILITY (Who is going to ensure

this happens?)

4.2 Formula for setting up crane base

• Crane collapsing H Minimum outrigger pad and ground pressure calculations – go to page 22

If any doubt exists, increase the packing areas. NOTE: When the boom is used over one outrigger, the calculated packing areas should be increased at lease 40 per cent.

• Pfeiffer Cranes Management

• Crane Crew

05 Adequate Operational Zones

• Overhead services • Uncontrolled load

• Fall from heights

• Falling objects • Protection to site staff • Underground services

H • Locate proximity of, and constantly monitor all overhead utilities, wire, pipes etc.

• Ensure the correct lifting methods are used for all loads and are only to be secured by a qualified dogger, rigger.

• Use a tag line for loads that may become difficult to handle.

• Establish and barricades off adequate exclusion zones around works (20 meters)

• Harnesses to be worn and secured

• Non-essential personnel are to be kept out of this area

• Pfeiffer Cranes Management

• Crane Crew

• Site Management

06

Mobile Crane Operation

• Mechanical failure due to lack of routine maintenance.

H

• Daily & weekly service checks to be completed as per the crane log book • Maintain three points of contact when climbing onto and off the crane.

• All lifting gear to be checked as part of the daily inspection.

• The crane operator will ensure that dogger conduct their daily checks.

• Crane operator to complete daily maintenance service sheets. • A major service is to be undertaken every 2500 hours per crane logbook.

• The site manager is to contact service contractor to arrange a time for this service to be undertaken.

• Details of the service and maintenance undertaken are to be recorded in the crane logbook. The copy remains in the crane on site.

• The crane driver is to ensure the navigation lighting (if installed) is functional before leaving site each day.

• Pfeiffer Cranes Management

• Crane Crew

• Riggers

• Site Manager

Page 9: Safe Work Method Pfeiffer Cranespdf.pdf

PFEIFFER Cranes Pty Ltd _Safe Work Method Statement

__________________________________________________________________________________________________________________________________ Risk Category (VH) = Very High – (H) = + High – (SR) = Substantial Risk– (M) Moderate Risk – (LR) = Low Risk Page 9 of 24

ACTIVITY STEPS

(Break the job down into steps) POTENTIAL HAZARDS

and RISKS (What can harm you?)

RISK CONTROL MEASURES (What are you going to do to make the job as safe as possible?)

RESPONSIBILITY (Who is going to ensure

this happens?)

06

Mobile Crane Operation

• Mechanical failure due

to lack of routine maintenance.

H

• For Breakdowns, the operator is to assess to the best of his ability, the cause of the malfunction, and immediately contact the Site Managers Office for further instructions.

• If there is any reason to suspect that the crane may not be safe to operate, the crane is to be shut down until expert advice is obtained.

• In the case of an emergency, the crane operator is to assess to the best of his ability the situation, and take the necessary measures to ensure the safety of the people on site.

• Immediately contact the Site Manager and await instructions.

• The working load limit switches are set and operational at project commencement.

• Under no circumstances are the load limit switches to be tampered with or made inoperable.

• The load indicator limit is to be tested with an approved weight test every six (6) months.

• Over lifting of the crane during normal operations is not permitted under any circumstances.

• Operation is to be undertaken in a controlled steady manner. • Excessive speed and dangerous operational practices is not tolerated.

• Pfeiffer Cranes

Management

• Crane Crew

• Riggers • Site Manager

07

Crane operating within close proximity to power lines

• Striking power lines

• Electrocution

• Fire • Explosion

• Burns

• Various injuries • Load falling Specific site procedures must be drafted and signed

H

• The operator must not operate the crane in any position where the machine or any part of its load can come within 3 metres of overhead power lines and 6-8 metres of power lines on transmission towers

• Crane Crew (Rigger, Dogger, Crane Operator) to be on constant guard against boom of crane, chains and loads coming into close proximity with external power lines.

• A Spotter to be allocated if working in NO-GO-ZONE (up to 3 meters of power lines).

• If unsure of proximity to power lines and safe work procedures, consult with local authority before commencing work.

• Doggers are to act as constant spotters for close proximity to no go zone.

• Rigger/Dogger

• Crane Operator

• Spotter • Project Manager

• Site Safety Officer

Page 10: Safe Work Method Pfeiffer Cranespdf.pdf

PFEIFFER Cranes Pty Ltd _Safe Work Method Statement

__________________________________________________________________________________________________________________________________ Risk Category (VH) = Very High – (H) = + High – (SR) = Substantial Risk– (M) Moderate Risk – (LR) = Low Risk Page 10 of 24

ACTIVITY STEPS

(Break the job down into steps) POTENTIAL HAZARDS

and RISKS (What can harm you?)

RISK CONTROL MEASURES (What are you going to do to make the job as safe as possible?)

RESPONSIBILITY (Who is going to ensure

this happens?)

07

Crane operating within close proximity to power lines

off by the Doggers and Crane Operators.

• Striking power lines • Electrocution

• Fire • Explosion • Burns

• Various injuries

• Load falling Specific site procedures must be drafted and signed off by the Doggers and Crane Operators.

H

• Specific site procedures are to be followed for power lines.

• All crane movement must be performed with extra caution and slow speed to ensure full control of the hook or load when operating inside the buffer zone (3 meters).

• Pfeiffer Cranes Supervisor will ensure that at least one or more of the following additional controls are used, prior to working within the 3 metre exclusion zone: o Spotters o Tiger tails o De-energising of power lines o Re-routing of power lines

Note Doggers cannot operate as professional electrical spotters without a specific electrical spotter’s ticket. A qualified spotter must be available on site at all times if a crane has a chance of coming into close proximity to power lines, less than 3 meters.

• Rigger/Dogger • Crane Operator

• Spotter

• Project Manager

• Site Safety Officer

08 Communication • Loss of communication

• Failure to understand direction

H • Explain procedure.

• Ensure everyone understands.

• Use hand and whistle signals. • Use two way radios in necessary.

o Check that the batteries are fully charged o Do a radio check o Charging of batteries must be done at the end of shift or sooner if

required. o Batteries must be fully discharged prior to being recharged to retain

battery lift.

• Pfeiffer Cranes Management

• Crane Crew

09

Collision Prevention Procedures

• Crane boom’s coming into contact

• Injuries to people

• Damage to property • Damage to equipment

H

Dogger and designated spotter are to keep a visual check of the position of the crane, and the other plant and keep the operator informed of the position of his crane in relation to the other plant operator or other people.

• Doggers are to watch closely for any change in boom location and inform

• Pfeiffer Cranes Management

• Crane Crew

• Site Management

Page 11: Safe Work Method Pfeiffer Cranespdf.pdf

PFEIFFER Cranes Pty Ltd _Safe Work Method Statement

__________________________________________________________________________________________________________________________________ Risk Category (VH) = Very High – (H) = + High – (SR) = Substantial Risk– (M) Moderate Risk – (LR) = Low Risk Page 11 of 24

ACTIVITY STEPS

(Break the job down into steps) POTENTIAL HAZARDS

and RISKS (What can harm you?)

RISK CONTROL MEASURES (What are you going to do to make the job as safe as possible?)

RESPONSIBILITY (Who is going to ensure

this happens?)

the crane operator(s) by radio

• Work may continue within the Total exclusion/no go zone, providing all parties are in agreement and fully aware of the situation, and a person designated as a spotter is present, not the dogger.

• Work will not re-commence until the situation is resolved.

• Pfeiffer Cranes Management

• Crane Crew • Site Management

10 Using mobile phone during crane operation, rigging and dogging

• Persons distracted. • Loads incorrectly rigged

up and secured.

• Loads not being directed safely.

• Unsafe operation of the crane.

VH • Mobile phones are prohibited during the following activities; o While communication of instructions are being actioned between

the crane crews. o During the rigging of material loads and equipment. o During the dogging of loads and while the load is on the hook. o At any time when the crane has a load on the hook.

• The crane crew is to make sure that there are no unwarranted distractions that may effect the safe lifting and crane operation procedures.

• Pfeiffer Cranes Management

• Crane Crews

11 Unauthorised personnel Failure to prevent members of the public or other persons entering the site.

• Injuries of various kinds M • Erection and maintenance of barricades, signs and warning lights (if warranted in accordance with the risk)

• Back filling and covers over trenches and excavations.

• Security patrols (usually by Contract Management) • Community awareness, such as public notices (usually by Contract

Management).

• Pfeiffer Cranes Management

• Crane Crew

• Site Management

12 Lifting Equipment

• Falling objects • Fall from heights

• Cuts and Bruises

• Stains and Sprains

• Mechanical Failure

H • Correct slinging techniques are to be used at all times. • All lifting equipment must be checked and tagged current.

• The dogger will ensure that all the lifting gear is checked daily, and is in good working order.

• Any faults to the lifting gear, the dogger is to advise PFEIFFER CRANES immediately.

• Pfeiffer Cranes Management

• Crane Crews

13 Loading – Offloading trucks

• Fall from rear of truck M • When loading or offloading equipment from a truck or van, employees are encouraged to be constantly aware when stepping backwards especially when carrying a load.

• Pfeiffer Cranes Management

• Crane Crews

Page 12: Safe Work Method Pfeiffer Cranespdf.pdf

PFEIFFER Cranes Pty Ltd _Safe Work Method Statement

__________________________________________________________________________________________________________________________________ Risk Category (VH) = Very High – (H) = + High – (SR) = Substantial Risk– (M) Moderate Risk – (LR) = Low Risk Page 12 of 24

ACTIVITY STEPS

(Break the job down into steps) POTENTIAL HAZARDS

and RISKS (What can harm you?)

RISK CONTROL MEASURES (What are you going to do to make the job as safe as possible?)

RESPONSIBILITY (Who is going to ensure

this happens?)

• Site Management 14 Manual

Handling • Sprains

• Muscle strains • Tendon and ligament

damage

• Spinal damage

M • Adopt good Manual Handling techniques eg straight back and bend knees, clear access ways etc

• Team lifts

• Use other devices that assist moving loads Seek assistance if required.

• Pfeiffer Cranes Management

• Crane Crews

• Site Management

15

15

Slinging Loads Slinging Loads

• Falling objects • Cuts and Bruises

• Stains and Sprains

• Fall from heights • Striking objects • Stuck by objects

• Electrocution

• Caught between objects

• Falling objects

• Cuts and Bruises

• Strains and Sprains • Fall from heights

• Striking objects • Struck by objects • Electrocution

• Caught between objects

• Heat Stress

H

H

• No Crane Movement (Including movement of chains), Prior to Communication with Dogger.

• Correct slinging techniques are to be used at all times.

• 4 chains are to be used on rubbish skips and lifting containers.

• Safety/back up slings are to be used on Pre-cast concrete. • Safety pins are to be inserted in brick cage tines.

• Smooth steel bar is to be double wrapped in the chains.

• Screw jacks are to be lifted in bins or are to be stacked neatly on a pallet and strapped in place using steel wrapping.

• Bricks and blocks are to be wrapped in plastic or adequately strapped prior to lifting with the brick cage.

• Synthetic fiber sandbags are not to be lifted by the handles, a brick cage or bin is to be used.

• All loose items are to be lifted in as approved lifting container. Eg bolts, plates, small miscellaneous items.

• If the dogger believes a load is unsafe to lift, it is to be re-stacked by the contractor responsible or the dogger to the doggers satisfaction prior to lifting.

• All lofting devices (bins, kibbles, cages containers etc) must display their self weight (SW) and their safe working load limit (SWL).

• Form work components such as shutters and column boxes must be fitted with approved lifting lugs.

• The appropriate ratings must be displayed on the approved lifting devices prior to slinging a load.

• All loads (that is concrete, building materials etc) to enter site, and unloading will be from within the site (or from an approved designated demarcated area – traffic controllers to be used if needed).

• At no time will loads be lifted outside the site confines – (area of site

• Pfeiffer Cranes Management

• Crane Crew

• Site Management

• Pfeiffer Cranes Management

• Crane Crew • Site Management

Page 13: Safe Work Method Pfeiffer Cranespdf.pdf

PFEIFFER Cranes Pty Ltd _Safe Work Method Statement

__________________________________________________________________________________________________________________________________ Risk Category (VH) = Very High – (H) = + High – (SR) = Substantial Risk– (M) Moderate Risk – (LR) = Low Risk Page 13 of 24

ACTIVITY STEPS

(Break the job down into steps) POTENTIAL HAZARDS

and RISKS (What can harm you?)

RISK CONTROL MEASURES (What are you going to do to make the job as safe as possible?)

RESPONSIBILITY (Who is going to ensure

this happens?)

15

Slinging Loads

• Falling objects • Cuts and Bruises

• Strains and Sprains • Fall from heights

• Striking objects

• Struck by objects

• Electrocution • Caught between objects

• Heat Stress

H

control)

• The doggers should take particular attention and advise the crane driver of the hook locality so as to ensure under all circumstances that lifts are to be within the site confines.

• The doggers will ensure that all the lifting gear is checked daily, and is in good working order. Should any of the lifting gear require attention, the doggers are to be advise PFEIFFER CRANES immediately.

• The ground doggers should maintain a clean, general lifting area at all times.

• At all times doggers should be conscious of attaching lifting chains, or rigging in such a way that there is no likelihood of the load becoming loose and falling on co-workers.

• COLUMNS to be lifted from approved and designated areas. Storage of columns should be such that they cannot fall. Doggers are to ensure bolts on lifting loop are maintained and are correct type.

• LIFT WELLS Doggers are to ensure that they know the weight of form work shutters prior to lifting; all shutters should have their weights clearly marked on them, and lifting points only. Doggers must familiarize themselves with the form work procedures, prior to lifting any form work.

• The lift box should have it’s weights clearly marked on it, and for stripping

purposes should be totally free from the concrete walls prior to lifting (Prior to attaching chains). The crane driver should not winch the crane more than half a tonne, above the weight of the box (due to restriction of load). It is up to form workers to free the load.

• Doggers are to study the steel schedule prior to attaching chains and identify bundles of steel to satisfy themselves that the weights are within the crane’s capacities.

• FORMWORK SHUTTERS INSTALLATION/REMOVAL. Climbing on shutters or column boxes is not allowed. Doggers will not lift prefabricated panels or cages unless correct procedures have been followed.

• Wall shutters should not be lifted from designated lifting point. (as per engineering drawings)

• Prior to lifting shutters, the dogger is to check that there is no loose

• Pfeiffer Cranes Management

• Crane Crew

• Site Management

Page 14: Safe Work Method Pfeiffer Cranespdf.pdf

PFEIFFER Cranes Pty Ltd _Safe Work Method Statement

__________________________________________________________________________________________________________________________________ Risk Category (VH) = Very High – (H) = + High – (SR) = Substantial Risk– (M) Moderate Risk – (LR) = Low Risk Page 14 of 24

ACTIVITY STEPS

(Break the job down into steps) POTENTIAL HAZARDS

and RISKS (What can harm you?)

RISK CONTROL MEASURES (What are you going to do to make the job as safe as possible?)

RESPONSIBILITY (Who is going to ensure

this happens?)

H

material on shutter (ie concrete, timber, etc). At the discretion of the dogger, a tag line is to be attached to the bottom part of the shutter during the installation when it clears the concrete.

• To dislodge shutter from concrete, and remove bars/bolts, apply load of approximately 20% more that weight of shutter. Prior to lifting, the dogger is to ensure there is no loose material on the shutter (ie concrete spills or y-bars etc).

• At the discretion of the dogger, the tag line is to be attached to the bottom of the shutter when it is clear of the concrete.

• If wind conditions are suitable not exceeding 25kph then the shutter/formwork can be lifted, or placed in position. (This condition is subject to variables of wind direction, position of lift etc.)

• The decision to lift the shutter/formwork is to be made by the dogger and crane driver in consultation with the Project Management. (Laying the shutter flat, may reduce the wind resistance).

• When a tag line is used to stabilize the shutter, the dogger is to guide it into position, making sure the immediate area is clear of personnel.

• After lowering the shutter to the appropriate area for storage, the dogger is to ensure that the shutter is stored into its nominated rack, and that it is stable and safe, prior to releasing the chains.

• GENERAL. Concrete kibble is to be lifted from the shutter on the bridle. If the vibrator is to be carried out with the kibble, then it should be attached to the kibble by a chain of a least 7mm in diameter. The kibble should be cleaned thoroughly after every use.

• False work frames should be stacked in an approved manner. When bundles of frames are lifted, the chains should be put around the main chords, and between the bracing so that if the frames slip they are captive within the chains.

• Bundles of plywood should be lifted with two chains. The chains should be choked around the bundles of ply.

• Stacks of timber should also be lifted with two chains, and choked around the pack. Packs of timber should be strapped, or have a piece of ply wood nailed to the top to maintain the integrity of the pack.

• Pfeiffer Cranes Management

• Crane Crew • Site Management

Page 15: Safe Work Method Pfeiffer Cranespdf.pdf

PFEIFFER Cranes Pty Ltd _Safe Work Method Statement

__________________________________________________________________________________________________________________________________ Risk Category (VH) = Very High – (H) = + High – (SR) = Substantial Risk– (M) Moderate Risk – (LR) = Low Risk Page 15 of 24

ACTIVITY STEPS

(Break the job down into steps) POTENTIAL HAZARDS

and RISKS (What can harm you?)

RISK CONTROL MEASURES (What are you going to do to make the job as safe as possible?)

RESPONSIBILITY (Who is going to ensure

this happens?)

15

Sling Loads

VH

• Blocks should be lifted using a block cage. Care should be taken that the block cage is lowered centrally over the pall blocks. When the cage is removed from the blocks, care should be taken to ensure the tynes are placed in the correct position for the return journey.

• Scaffolding should be lifted on stillages, and chains should choke the scaffold items around the pallet. If scaffolding pies are to be lifted with a pallet, then it needs to be doubly wrapped.

• Alloy mobile scaffolding are NOT to be lifted (it is illegal). • The procedure for lifting/operation of Man Boxes (with personnel) is:

1. Prior to lifting the Man Box, a zoned area is to be demarcated, and (if the procedure dictates), a spotter allocated to the area, and no personnel are allowed into the area whilst the lift work is in progress

2. All personnel in the Man Box by a harness, (connected to the main rig). All tools are to be secured to prevent them from falling out of the Man Box.

3. Man Boxes should be lifted with four chains on the lifting loops. If the dog box is emptied from the rear loops, four chains should be re-attached to the dog box, so it can be positioned in the required area.

Lifting procedures: Prefabricated Reinforcement Steel Mats & Column Cages.

• You are instructed not to lift any reinforcement steel mats or column cages in a vertical position, unless;

• A competent person (ie. Structural Engineer) has assessed and certified the lifting system of each wall mat or column cage or

• Consultation between the dogger and Pfeiffer Cranes site representative and

• Lifting of wall mats or column cages can only occur if the dogger has assessed the load of rigging requirements prior to the lift and it is safe to do so.

Refer: Pfeiffer Cranes – Crane Dogging Safe Work Procedures for further

• Pfeiffer Cranes Management

• Crane Crew • Site Management

Page 16: Safe Work Method Pfeiffer Cranespdf.pdf

PFEIFFER Cranes Pty Ltd _Safe Work Method Statement

__________________________________________________________________________________________________________________________________ Risk Category (VH) = Very High – (H) = + High – (SR) = Substantial Risk– (M) Moderate Risk – (LR) = Low Risk Page 16 of 24

ACTIVITY STEPS

(Break the job down into steps) POTENTIAL HAZARDS

and RISKS (What can harm you?)

RISK CONTROL MEASURES (What are you going to do to make the job as safe as possible?)

RESPONSIBILITY (Who is going to ensure

this happens?)

procedures on Man Box safety, and the Safe Work Method Statement for lifting and working from a man box. Before lifting PRE-CAST PANELS, ensure onsite procedures are in place and adequate for the job.

16

Dual Lift Procedures

• Crane tip over.

• Injuries to people

• Damage to property

• Damage to equipment

H • Decrease the load chart capacities by 20% for each crane.

• The lift weights of both cranes in relation to the load are to be calculated and a working procedure drawn up between the two crane operators and riggers concerned. The procedure is to be signed by all concerned.

• The doggers/riggers are to be attaching the chains to the load in preparation for the lift.

• One rigger is to take control of the lift, (and both cranes), at this stage.

• The rigger in control is to instruct the both crane operators to hoist up, approximately 1 meter off the deck.

• The rigger at this stage is to check with both crane operators for each crane’s actual hook weight, to ensure cranes are in their capacity to move the load.

• If the actual hook weights are too heavy the load is to be placed back on the ground and the chains re-located until in correct position.

• Once both cranes have the correct weight for the radius the control rigger is to signal the hoist up and control the lift to it’s set down position.

• Pfeiffer Cranes Management

• Crane Crew

• Site Management

17

Loose Items • Impact injuries • Crushing injuries

• Damage to property

• Damage to equipment

SR • Loads of loose items such as scaffold clips must be raised improperly constructed boxes branded with the Safe Working Load (SWL).

• Do not lift loads of the kind in 200 litre drums because: o These drums have no rates lifting capacity. o It is not possible to know the condition of the base of the drum.

(They have usually been discarded because they are unfit to hold liquid).

o The holes cut into the sides for the sling or hooks often pull through under the weight.

o The sharp edges of the holes can cut through a sling.

• Pfeiffer Cranes Management

• Crane Crew

• Site Management

18 Using safety equipment

• Incorrect use & type safety equipment

H • The correct type of safety equipment is to be used for the specific job

• Ear muffs are to be used in place of ear plugs, if the noise level exceeds

• Pfeiffer Cranes Management

Page 17: Safe Work Method Pfeiffer Cranespdf.pdf

PFEIFFER Cranes Pty Ltd _Safe Work Method Statement

__________________________________________________________________________________________________________________________________ Risk Category (VH) = Very High – (H) = + High – (SR) = Substantial Risk– (M) Moderate Risk – (LR) = Low Risk Page 17 of 24

ACTIVITY STEPS

(Break the job down into steps) POTENTIAL HAZARDS

and RISKS (What can harm you?)

RISK CONTROL MEASURES (What are you going to do to make the job as safe as possible?)

RESPONSIBILITY (Who is going to ensure

this happens?)

• Accidents

• Serious injury • Death

(95 decibels) over a continuous period or the frequency of sound is high.

• Safety glasses are to be worn in areas of high risk to eyes.

• Face shields are to be worn when grinding or cutting steel. • Hard hats are to be worn in all designated risk areas.

• Safety boots are to be worn in all work areas.

• Gloves and other safety equipment are to be worn and used when required.

• Crane Crew

• Site Management

19 Ladders • Falls due to an unsecured or faulty ladder.

• Incorrect use of harness

• Electrocution due to the use of wrong type of ladder.

• Incorrect use of ladder

H • Ladders used shall be designed in accordance with AS1892, Portable ladders, Part 1 Metal and Part 2 Timber Ladders

• Ladders will be constructed are to have a load rating no less than 120kg and marked “Industrial Use Only”.

• Fall arrest systems are to be used when people are using a ladder as a working platform when working above 2 meters.

• Ladders constructed on site for fixed platforms, walkways or stairways shall comply with AS1657, Fixed platforms, walkways, stairways and ladders.

• Ladders may be used to dog a load, provided they are properly secured and tied off or secured at the bottom and checked by another person.

• Whilst on the ladder individuals must have three points of contact, this includes at least one hand.

CAUTION: A person ascending or descending a ladder is not to carry any items of equipment or tools. Equipment and tools will be hauled up only after secured by a fall-prevention system.

• Pfeiffer Cranes Management

• Crane Crew

• Site Management

20 Traffic Control • Falling objects

• People being injured

M • Erect signs restricting access to all, except authorized personal

• A spotter to be provided with appropriate identification. • The spotter to make sure no one walks under loads being lifted.

• The spotter is to make sure the access under all loads remains clear of unauthorized personal until the lift has been deemed secure by the designated load controller.

• Pfeiffer Cranes Management

• Crane Crew

• Site Management

Page 18: Safe Work Method Pfeiffer Cranespdf.pdf

PFEIFFER Cranes Pty Ltd _Safe Work Method Statement

__________________________________________________________________________________________________________________________________ Risk Category (VH) = Very High – (H) = + High – (SR) = Substantial Risk– (M) Moderate Risk – (LR) = Low Risk Page 18 of 24

ACTIVITY STEPS

(Break the job down into steps) POTENTIAL HAZARDS

and RISKS (What can harm you?)

RISK CONTROL MEASURES (What are you going to do to make the job as safe as possible?)

RESPONSIBILITY (Who is going to ensure

this happens?)

21

Safe Use of Rubbish Skips

• Crushing injuries

• Pinching injuries • Impact injuries

• Caught between objects

H

• Rubbish bins should have proper lifting lugs and be branded with there Safe Working Load (SWL)

• Overloaded bins must not be lifted • Secure the load before lifting to avoid rubbish being blown out or spill out

from the bin.

• Sling rubbish bins with four legged sling.

• To tip the bin release the two front slings and raise the bin with two back slings.

• Do not stand on the edge of the main rubbish bin or behind a bin when tipping rubbish out. It could whip back suddenly as it clears the ground. The dogger is to be on the ground during unloading.

• If the rubbish is stuck in the bin use a safe method to dislodge the rubbish eg a piece of timber, metal bar. Keep well clear of possible falling rubbish.

• Re-hook the bin when it is emptied, by the four lifting lugs after it has been placed back on the ground.

• Pfeiffer Cranes Management

• Crane Crew • Site Management

22 Refueling of plant and equipment. Refueling is to be carried out as stated in these procedures.

• Explosion

• Burns to re-fuelers, doggers, crane operator and site employees.

• Exposure to diesel fumes

H

• Fuel hose is to be unwound from fuel tank.

• Fuel tank hose nozzle to be connected up to the fuel tank outlet pipe. • Fuel tank tap is to be turned “on”.

• Switch crane engine off. • Nozzle to be placed in fuel tank of crane and fueled up using the self

acting nozzle.

• Once crane fuel tank is full, the self acting nozzle shall be closed before being removed from fuel tank to crane and any fuel wiped from the nozzle.

• Fuel hose nozzle to be hooked back out to hang from the outlet pipe on fuel tank.

• Start crane up.

• Pfeiffer Cranes Management

• Crane Crew • Site Management

23

Noise Short term effects

• Headache

• Irritability

M • Isolate plant from majority of employees in the areas.

• Rotate workers who are exposed to the noise source.

• Insulate the noise source

• Pfeiffer Cranes Management

• Crane Crew

Page 19: Safe Work Method Pfeiffer Cranespdf.pdf

PFEIFFER Cranes Pty Ltd _Safe Work Method Statement

__________________________________________________________________________________________________________________________________ Risk Category (VH) = Very High – (H) = + High – (SR) = Substantial Risk– (M) Moderate Risk – (LR) = Low Risk Page 19 of 24

ACTIVITY STEPS

(Break the job down into steps) POTENTIAL HAZARDS

and RISKS (What can harm you?)

RISK CONTROL MEASURES (What are you going to do to make the job as safe as possible?)

RESPONSIBILITY (Who is going to ensure

this happens?)

• Nausea

• Temporary hearing loss

Permanent noise induced

• Hearing loss

• Wear hearing protection • Site Management

24 Heat Stress • Various heat related illnesses such as: o Heat rash o Heat cramps o Heat exhaustion o Heat stroke

• Potentially some can be fatal

M • Access to cool drinking water and adequate intake of it.

• Regular rest breaks. • Hot heavy tasks to be carried out in early morning or late afternoon

• Awareness of signs of heat illnesses

• Education about personal factors that effects there ability to cope with heat such as: o Fitness o Weight o Diet o Cardio-vascular disease or metabolic disorder o Heat acclimatization o Medication

• Pfeiffer Cranes Management

• Crane Crew

25 UV Radiation • Skin damage such as: o Sunburn o Premature aging o Cancer

• Eye damage such as: o Inflammation o Swelling o Sensitivity to light o Permanent

damage to the cornea and lens

M • Provision for overhead shade protection

• Provision for Personal Protective Equipment such as: o Sunglasses o Safety helmet with brim and flap o Long sleeve shirt o Long pants

• Sunscreen to be applied regularly to all exposed areas of the body as recommended.

• Pfeiffer Cranes Management

• Crane Crew • Site Management

26 Housekeeping • Various injuries L • Material/plant/equipment to be stored in defined areas. • Waste material to be placed in designated area/receptacles

27 • Crane Crew

Page 20: Safe Work Method Pfeiffer Cranespdf.pdf

PFEIFFER Cranes Pty Ltd _Safe Work Method Statement

__________________________________________________________________________________________________________________________________ Risk Category (VH) = Very High – (H) = + High – (SR) = Substantial Risk– (M) Moderate Risk – (LR) = Low Risk Page 20 of 24

ACTIVITY STEPS

(Break the job down into steps) POTENTIAL HAZARDS

and RISKS (What can harm you?)

RISK CONTROL MEASURES (What are you going to do to make the job as safe as possible?)

RESPONSIBILITY (Who is going to ensure

this happens?)

• Site Management

28

• • Crane Crew

• Site Management

29

• • Crane Crew

• Site Management

30 • • Crane Crew

• Site Management

31

• • Crane Crew • Site Management

Page 21: Safe Work Method Pfeiffer Cranespdf.pdf

PFEIFFER Cranes Pty Ltd _Safe Work Method Statement

__________________________________________________________________________________________________________________________________ Risk Category (VH) = Very High – (H) = + High – (SR) = Substantial Risk– (M) Moderate Risk – (LR) = Low Risk Page 21 of 24

ACTIVITY STEPS

(Break the job down into steps) POTENTIAL HAZARDS

and RISKS (What can harm you?)

RISK CONTROL MEASURES (What are you going to do to make the job as safe as possible?)

RESPONSIBILITY (Who is going to ensure

this happens?)

32

• • Crane Crew

• Site Management

33

• • Crane Crew • Site Management

34

• • Crane Crew

• Site Management

35

• • Crane Crew • Site Management

36

• • Crane Crew • Site Management

37

• • Crane Crew

• Site Management

Page 22: Safe Work Method Pfeiffer Cranespdf.pdf

PFEIFFER Cranes Pty Ltd _Safe Work Method Statement

__________________________________________________________________________________________________________________________________ Risk Category (VH) = Very High – (H) = + High – (SR) = Substantial Risk– (M) Moderate Risk – (LR) = Low Risk Page 22 of 24

ACTIVITY STEPS

(Break the job down into steps) POTENTIAL HAZARDS

and RISKS (What can harm you?)

RISK CONTROL MEASURES (What are you going to do to make the job as safe as possible?)

RESPONSIBILITY (Who is going to ensure

this happens?)

38

• • Crane Crew

• Site Management

39

• Crane Crew • Site Management

40

• Crane Crew

• Site Management

Page 23: Safe Work Method Pfeiffer Cranespdf.pdf

PFEIFFER Cranes Pty Ltd Safe Work Method Statement

__________________________________________________________________________________ Page 23 of 24

Maximum ground pressure applied to the ground, when lifting above an outrigger pad/float;

Maximum pressure applied by pad area size selected =

MINIMUM OUTRIGGER PAD AREA/GROUND PRESSURE CALCULATIONS

Example:

P. out = 0.65 x (Cm + L)

Area

When crane mass (Cm) = 42 tonnes

Load to be lifted SWL in Chart Range (L) = 15 tonnes

Timber outrigger pad area in contact with the ground = 1m long x 1m wide = Area lm2

P.out = 0.65 x (42t + 150) = t.p. per sqm. 1m2

ANS = 37 tonnes pressure per m2 (maximum pressure exerted)

P. out = 0.65 x (total crane mass + the load to be lifted)

(Individual outrigger area)

Minimum area for outrigger pad base support when lifting directly above an outrigger;

To determine the minimum area required to be covered under the outrigger pad support is

calculated using the following rule of thumb formula;

Ground Pressure Chart

Ground Type Maximum permissible ground pressure, P max. (tonnes per m2)

Hard rock

Shale rock and sandstone

Compacted f!l'8vel (sand < 20%)

Asphalt

Stiff clay (dry)

Soft clay (dry)

Loose sand

Wet clay

200

80

40

20

20

10

10

10<

To find the minimum area and dimensions required under each outrigger;

Area = 0.65 x (Cm + L)

P max.

Example

When crane mass (Cm) = 60 tonnes

Load to be lifted (SWL in Chart Range) (L) = 20 tonnes

Where maximum permissible ground pressure e.g. P max = 40 P.max

Area = 0.65 x (60t + 2Ot) = sq. m 40t per m2

Page 24: Safe Work Method Pfeiffer Cranespdf.pdf

PFEIFFER Cranes Pty Ltd _Safe Work Method Statement

__________________________________________________________________________________________________________________________________ Risk Category (VH) = Very High – (H) = + High – (SR) = Substantial Risk– (M) Moderate Risk – (LR) = Low Risk Page 24 of 24

We, the undersigned, acknowledge that we have attended the toolbox meeting and are fully conversant with the safety precautions included in this Safe Work Method Statement. We understand that we are required to be in a fit state to work on site. We agree to keep a copy of this statement in each tower crane at all time as a point of reference and to allow review and revision as necessary.

Name Signature Date Name Signature Date