Safe Machine Parameters in LHC

23
Safe Machine Parameter System MPP Internal Review B. Todd 17-18 th June 2010 0v3 Towards Nominal Beams

description

Safe Machine Parameters in LHC. Safe Machine Parameters in LHC. …ENERGY…. Energy Implementation 2010. Energy Implementation 2010. switch between A and B. Energy Implementation 2010. switch between A and B. ≈ 0.5 Hz cross-check - PowerPoint PPT Presentation

Transcript of Safe Machine Parameters in LHC

Page 1: Safe Machine Parameters in LHC

Safe Machine Parameter System

MPP Internal ReviewB. Todd 17-18th June 2010

0v3

Towards Nominal Beams

Page 2: Safe Machine Parameters in LHC

CERNCERN

[email protected] Machine Protection Panel - Internal review - 17-18 th June [email protected]

CERNCERN

Machine Protection Panel - Internal review - 17-18 th June 2010

Safe Machine Parameters in LHC

DATA RECEIVERMachineEnergy LHC

Safe Machine

ParameterController

DATA RECEIVERBeam Intensity

Beam Mode

LHC Beam Presence Flag 1

LHC Set-up Beam Flag 2LHC Set-up Beam Flag 1

LHC Beam Intensity 1LHC Machine Energy

LHC Beam Intensity 2Moveable Devices Allowed In

Stable Beams FlagDirectly Transmitted

Broadcast

DATA RECEIVERBeam Presence

LHC GeneralMachineTiming

LHC Beam Presence Flag 2LHC Beam Presence Flag 1

LHC Set-up Beam Flag 2LHC Set-up Beam Flag 1

LHC Beam Presence Flag 2

Page 3: Safe Machine Parameters in LHC

CERNCERN

[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 3

Safe Machine Parameters in LHC

DATA RECEIVERMachineEnergy LHC

Safe Machine

ParameterController

DATA RECEIVERBeam Intensity

Beam Mode

LHC Beam Presence Flag 1

LHC Set-up Beam Flag 2LHC Set-up Beam Flag 1

LHC Beam Intensity 1LHC Machine Energy

LHC Beam Intensity 2Moveable Devices Allowed In

Stable Beams FlagDirectly Transmitted

Broadcast

DATA RECEIVERBeam Presence

LHC GeneralMachineTiming

LHC Beam Presence Flag 2LHC Beam Presence Flag 1

LHC Set-up Beam Flag 2LHC Set-up Beam Flag 1

LHC Beam Presence Flag 2

…ENERGY…

Page 4: Safe Machine Parameters in LHC

CERNCERN

[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 4

Energy Implementation 2010

BETS LBDS

LHCSafe

MachineParameterController

Dipole Currents

BETS

Energy 1B

Energy 2AEnergy 2B

Collimation

Injection Kickers

BLM

LBDSBeam-1

LBDSBeam-2

Energy 1A

LHC GeneralMachineTiming

LHC Machine Energy

Page 5: Safe Machine Parameters in LHC

CERNCERN

[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 5

Energy Implementation 2010

BETS LBDS

Dipole Currents

BETS

Energy 1B

Energy 2AEnergy 2B

Collimation

Injection Kickers

BLM

LBDSBeam-1

LBDSBeam-2

Energy 1A

LHC GeneralMachineTiming

LHC Machine Energy

switch between A and B

Page 6: Safe Machine Parameters in LHC

CERNCERN

[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 6

Energy Implementation 2010

≈ 0.5 Hz cross-check dipole currents must be equivalent to BLM energy reading (1%)

BETS LBDS

Dipole Currents

BETS

Energy 1B

Energy 2AEnergy 2B

Collimation

Injection Kickers

BLM

LBDSBeam-1

LBDSBeam-2

Energy 1A

LHC GeneralMachineTiming

LHC Machine Energy

EnergyConsistency

Check

SIS

switch between A and B

Page 7: Safe Machine Parameters in LHC

CERNCERN

[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 7

Intensity Implementation 2010

LHCSafe

MachineParameterController

Intensity 1B

Intensity 2AIntensity 2B

DCBCTSystems

Intensity 1A

LHC GeneralMachineTiming

LHC Beam-1 IntensityLHC Beam-2 Intensity

AB

Beam-1 Current

AB

Beam-2 Current LHC Setup Beam Flag 1

LHC Setup Beam Flag 2

Page 8: Safe Machine Parameters in LHC

CERNCERN

[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 8

Intensity 1B

Intensity 2AIntensity 2B

DCBCTSystems

Intensity 1A

LHC GeneralMachineTiming

LHC Beam-1 IntensityLHC Beam-2 Intensity

AB

Beam-1 Current

AB

Beam-2 Current LHC Setup Beam Flag 1

LHC Setup Beam Flag 2

Intensity Implementation 2010

switch between A and B

no cross-check

SMP 3v0 – 2011 will implement complete redundancyEnergy and Intensity will be from multiple sources

Page 9: Safe Machine Parameters in LHC

CERNCERN

[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 9

1. Remove an external ROM – HWSBF glitch - MPP 2010-25

http://lhc-mpwg.web.cern.ch/lhc-mpwg/MPP-Meetings/No25-19032010/MPP_190310_minutes.docx

HW

Outstanding Issues - SMP 2v0

2. Force SBF False at the start of every normal ramp – / / / .Improve SBF safety - modification authorised Evian 2010

http://indico.cern.ch/contributionDisplay.py?contribId=6&sessionId=3&confId=76921

ready

ready ready ready waitingHW FESA JAVA SEQUENCER

3. The Setup Beam Flag - HW / FESA / JAVAThe limit is too low for some studies

study in progress

Page 10: Safe Machine Parameters in LHC

CERNCERN

[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 10

GMT

BeamEnergy

Tracking System

BeamCurrent

Transformers

ENERGY

INTENSITY

FlagGenerator

Direct to Extraction Controller

SBF ADATA

RECEIVER

BeamEnergy

Tracking System

DATA RECEIVER

BeamInterlockController

SBF A

SBF ASBF BSBF

ThresholdROM

ENERGY THRESHOLD

Generating the Setup Beam Flag

If (INTENSITY < THRESHOLD) SBF = TRUE

Else SBF = FALSE

End if

Page 11: Safe Machine Parameters in LHC

CERNCERN

[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 11

GMT

BeamEnergy

Tracking System

BeamCurrent

Transformers

ENERGY

INTENSITY

FlagGenerator

Direct to Extraction Controller

SBF ADATA

RECEIVER

BeamEnergy

Tracking System

DATA RECEIVER

BeamInterlockController

SBF A

SBF ASBF BSBF

ThresholdROM

ENERGY THRESHOLD

x4 Timer

Generating the Setup Beam Flag

Page 12: Safe Machine Parameters in LHC

CERNCERN

[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 12

1. Remove an external ROM – HWSBF glitch - MPP 2010-25

http://lhc-mpwg.web.cern.ch/lhc-mpwg/MPP-Meetings/No25-19032010/MPP_190310_minutes.docx

HW

Outstanding Issues - SMP 2v0

2. Force SBF False at the start of every normal ramp – / / / .Improve SBF safety - modification authorised Evian 2010

http://indico.cern.ch/contributionDisplay.py?contribId=6&sessionId=3&confId=76921

4. Filter the Beam Presence Flag – HW / FESA / JAVAExtraction Denial of Service - MPP 2010-26

http://lhc-mpwg.web.cern.ch/lhc-mpwg/MPP-Meetings/No26-16042010/MPP_160410_minutes.docx

5. Improve the Beam Presence FlagFast Beam Current Transformer is currently the limiting factor….

ready

ready ready ready waiting

ready ready ready

It’s complicated

HW FESA JAVA SEQUENCER

HW FESA JAVA

3. The Setup Beam Flag - HW / FESA / JAVAThe limit is too low for some studies

study in progress

Page 13: Safe Machine Parameters in LHC

CERNCERN

[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 13

Beam Presence Flag Signal Path

Beam Current Transformer System

Beam Current Transformer System

Beam Currents

LHC Point 4

BPF_1BPF_2

Page 14: Safe Machine Parameters in LHC

CERNCERN

[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 14

Beam Presence Flag Signal Path

Beam Current Transformer System

Beam Current Transformer System

Beam Currents

LHC Point 4LHC

Safe Machine Parameters Controller

Control Room

BPF_1BPF_2

BPF_1

BPF_2

Page 15: Safe Machine Parameters in LHC

CERNCERN

[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 15

Beam Presence Flag Signal Path

Beam Current Transformer System

Beam Current Transformer System

Beam Currents

LHC Point 4LHC

Safe Machine Parameters Controller

Control Room

BPF_1BPF_2

Extraction Interlock

ControllerSPS East Area

Extraction Interlock

Controller

SPS West Area

BPF_1

BPF_2

ExtractionPermit

ExtractionPermit

Page 16: Safe Machine Parameters in LHC

CERNCERN

[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 16

Beam Presence Flag Signal Path

Beam Current Transformer System

Beam Current Transformer System

Beam Currents

LHC Point 4LHC

Safe Machine Parameters Controller

Control Room

BPF_1BPF_2

Extraction Interlock

ControllerSPS East Area

Extraction Interlock

Controller

SPS West Area

BPF_1

BPF_2

ExtractionPermit

ExtractionPermit

LHC General Machine Timing

Non-Critical Timing Users

BPF_1BPF_2

Page 17: Safe Machine Parameters in LHC

CERNCERN

[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 17

Beam Presence Flag Signal Path

Beam Current Transformer System

Beam Current Transformer System

Beam Currents

LHC Point 4LHC

Safe Machine Parameters Controller

Control Room

BPF_1BPF_2

Extraction Interlock

ControllerSPS East Area

Extraction Interlock

Controller

SPS West Area

BPF_1

BPF_2

ExtractionPermit

ExtractionPermit

LHC General Machine Timing

Data Interchange

Protocol

Non-Critical Timing Users

Non-Critical DIP Users

BPF_1BPF_2

Page 18: Safe Machine Parameters in LHC

CERNCERN

[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 18

Beam Presence Flag Signal Path

Beam Current Transformer System

Beam Current Transformer System

Beam Currents

LHC Point 4

BEAM_PRESENCE_LIMIT

LHCSafe Machine Parameters Controller

Control Room

BPF_1BPF_2

Extraction Interlock

ControllerSPS East Area

Extraction Interlock

Controller

SPS West Area

BPF_1

BPF_2

ExtractionPermit

ExtractionPermit

LHC General Machine Timing

Data Interchange

Protocol

Non-Critical Timing Users

Non-Critical DIP Users

BPF_1BPF_2

Thresholds Definitionhttps://edms.cern.ch/document/883620/

Page 19: Safe Machine Parameters in LHC

CERNCERN

[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 19

Beam Presence Flag Signal Path

LHCSafe Machine Parameters Controller

Control Room

BPF_1BPF_2

Extraction Interlock

ControllerSPS East Area

Extraction Interlock

Controller

SPS West Area

BPF_1

BPF_2

ExtractionPermit

ExtractionPermit

LHC General Machine Timing

Data Interchange

Protocol

Non-Critical Timing Users

Non-Critical DIP Users

BPF_1BPF_2

From end of September 2010

Page 20: Safe Machine Parameters in LHC

CERNCERN

[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 20

Beam Presence Flag Signal Path

Beam Position Monitor Hardware

Beam Position Monitor Hardware

Beam Position

LHC Point 4LHC

Safe Machine Parameters Controller

Control Room

BPF_1BPF_2

Extraction Interlock

ControllerSPS East Area

Extraction Interlock

Controller

SPS West Area

BPF_1

BPF_2

ExtractionPermit

ExtractionPermit

LHC General Machine Timing

Data Interchange

Protocol

Non-Critical Timing Users

Non-Critical DIP Users

BPF_1BPF_2

From end of September 2010

Page 21: Safe Machine Parameters in LHC

CERNCERN

[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 21

Beam Presence Flag Signal Path

Beam Position Monitor Hardware

Beam Position Monitor Hardware

Beam Position

LHC Point 4

BEAM_PRESENCE_LIMIT

LHCSafe Machine Parameters Controller

Control Room

BPF_1BPF_2

Extraction Interlock

ControllerSPS East Area

Extraction Interlock

Controller

SPS West Area

BPF_1

BPF_2

ExtractionPermit

ExtractionPermit

LHC General Machine Timing

Data Interchange

Protocol

Non-Critical Timing Users

Non-Critical DIP Users

BPF_1BPF_2

From end of September 2010

+ fibres to be pulled+ new hardware from BI

+ testing and commissioning

Page 22: Safe Machine Parameters in LHC

CERNCERN

[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 22

For high intensity beams we need to…Upgrade the operational controller → Ben & SMP Team

When: next technical stop?

Release a new GUI → Ivan & SMP TeamWhen: next technical stop?

Add a sequencer task → OPWhen: MPP to decide

Improve Beam Presence Flag safety• fibres in UA47 → Bruno & Fibre team

• New BPM hardware unit → BI• Testing and Commissioning → BI & SMP Team

When: Ready for end of September

Make the SBF more flexible → MPP & MIWhen:?

Complete redundancy SMP 3v0 → many When: January 2011

Page 23: Safe Machine Parameters in LHC

CERNCERN

[email protected] Machine Protection Panel - Internal review - 17-18 th June [email protected] 23Machine Protection Panel - Internal review - 17-18 th June 2010

CERNCERN

Fin