SAEP-388

24
Previous Issue: New Next Planned Update: 4 November 2018 Page 1 of 24 Primary contacts: Al-Musalami, Faiz Hijji on +966-13-8809569 and Al-Abdulmohsin, Nader Mohammed on +966-13-8809551 Copyright©Saudi Aramco 2013. All rights reserved. Engineering Procedure SAEP-388 4 November 2013 Cleaning of Pipelines Document Responsibility: Materials and Corrosion Control Standards Committee Saudi Aramco DeskTop Standards Table of Contents 1 Purpose.......................................................... 2 2 Scope………………………………………..…. 2 3 References…………………………………….. 2 4 Responsibilities………………………………… 3 5 Techniques for Cleaning Pipelines.….……… 6 6 Surfactant Cleaning Procedure..…………….. 8 7 Sampling and Acceptance Criteria..……….. 19 8 Evaluating Chemical Cleaning Performance..…………..…… 20 9 Wastewater Disposal……………..…….…… 20 APPENDIX I - Safety Requirements……………..… 21 APPENDIX II - Preparatory Work………………..…. 22 APPENDIX III - Nitrogen Amount Calculation….…. 23 APPENDIX IV - Cleaning of Pipelines Containing Valves………………..…..... 24

description

Chemical cleaning

Transcript of SAEP-388

  • Previous Issue: New Next Planned Update: 4 November 2018

    Page 1 of 24

    Primary contacts: Al-Musalami, Faiz Hijji on +966-13-8809569 and

    Al-Abdulmohsin, Nader Mohammed on +966-13-8809551

    CopyrightSaudi Aramco 2013. All rights reserved.

    Engineering Procedure SAEP-388 4 November 2013

    Cleaning of Pipelines

    Document Responsibility: Materials and Corrosion Control Standards Committee

    Saudi Aramco DeskTop Standards Table of Contents 1 Purpose.......................................................... 2

    2 Scope... 2

    3 References.. 2

    4 Responsibilities 3

    5 Techniques for Cleaning Pipelines.. 6

    6 Surfactant Cleaning Procedure.... 8

    7 Sampling and Acceptance Criteria.... 19

    8 Evaluating Chemical Cleaning Performance.... 20

    9 Wastewater Disposal... 20 APPENDIX I - Safety Requirements.. 21

    APPENDIX II - Preparatory Work... 22

    APPENDIX III - Nitrogen Amount Calculation.. 23

    APPENDIX IV - Cleaning of Pipelines Containing Valves....... 24

  • Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-388

    Issue Date: 4 November 2013

    Next Planned Update: 4 November 2018 Cleaning of Pipelines

    Page 2 of 24

    1 Purpose

    It is necessary to clean pipelines for their efficient operations, corrosion control,

    minimizing black powder formation and reaching the desired pipelines cleanliness

    levels. This specification does not override the pipeline manufacturer's cleaning

    recommendations especially where warranty rights are involved. Differences shall be

    questioned and resolved by the proponent. It is necessary to clean pipelines to meet the

    minimum acceptance criteria stated in SAES-L-388.

    Cleaning contractors are chosen from the CSD-approved list to perform the cleaning

    operations. A cleanliness criterion has been established as a minimum standard for

    evaluating the performance of a chemical cleaning run. Cleaning is accomplished by

    (not necessarily in the sequence listed below):

    Mechanical cleaning (scraping)

    Chemical cleaning

    Combination of listed above methods

    2 Scope

    This procedure defines the responsibilities of various departments involved in the pre

    commission and operational cleaning of pipelines. It outlines methods to determine the

    need for cleaning and the criteria for selecting specific cleaning procedure, and steps

    involved in various cleaning procedure alternatives. Advice is available from

    Consulting Services Department (CSD) and Pipelines Department (PD) to review

    contractors detailed procedures for cleaning specific pipelines.

    The procedures listed herein are applicable to clean undesirable deposits in pipelines.

    For evaluation and recommendation of alternative cleaning procedures not listed herein,

    contact CSD.

    For cleaning pipelines containing valves, contact CSD, see Appendix IV.

    3 References

    The requirements contained in the following documents apply to the extent specified in

    this procedure.

    Saudi Aramco References

    Saudi Aramco Engineering Procedures

    SAEP-302 Instructions for Obtaining a Waiver of a Mandatory

    Saudi Aramco Engineering Requirement

  • Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-388

    Issue Date: 4 November 2013

    Next Planned Update: 4 November 2018 Cleaning of Pipelines

    Page 3 of 24

    SAEP-327 Disposal of Wastewater from Cleaning, Flushing

    and Dewatering Pipelines and Vessels

    SAEP-1662 Cleaning of Heat Exchangers and Unfired Plant

    Equipment

    Saudi Aramco Engineering Standards

    SAES-A-007 Hydrostatic Testing Fluids and Lay-Up Procedures

    SAES-A-104 Wastewater Treatment, Reuse and Disposal

    SAES-B-069 Emergency Eyewashes and Showers

    SAES-L-388 Pipelines Cleanliness Requirements for

    Hydrocarbon Services

    Saudi Aramco Best Practice

    SABP-L-012 Guidelines for On-Stream Scraping of Pipelines

    Saudi Aramco General Instructions

    GI-0002.100 Work Permit System

    GI-0006.012 Isolation Lock Out and Use of Hold Tag

    Saudi Aramco Construction Safety Manual

    Chemical Hazard Bulletin (CHB) # 155

    Saudi Aramco Hazardous Waste Code (SAHWC)

    4 Responsibilities

    4.1 The Project Construction Agency is responsible for the overall cleaning activities

    of new pipelines.

    4.2 Pipelines Department is responsible for cleaning existing pipelines.

    Note: Job Safety Analysis (JSA) shall be performed by the proponent before starting the cleaning activities of a pipeline.

    For existing pipelines,

    4.3 Pipelines Department/Maintenance

    Prepare the pipeline mechanically

    Provide maintenance support during the cleaning operation

    Coordinate cleaning and obtains approved contractor services.

  • Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-388

    Issue Date: 4 November 2013

    Next Planned Update: 4 November 2018 Cleaning of Pipelines

    Page 4 of 24

    4.4 Pipelines Department/Operations Engineering

    Prepare necessary operation procedures, advises the foreman of the facility

    during the cleaning of pipelines.

    Act as a technical representative during pipelines cleaning.

    Ensure adequate safety procedures and precautions are taken. Notifies Loss

    Prevention Department to review safety before and during cleaning of

    pipelines as needed.

    Coordinate and obtain the approval of new cleaning chemicals or techniques

    from CSD.

    Request the presence of specialist personnel from PD and/or CSD as needed.

    4.5 Pipelines/Inspection

    Has the responsibility for inspection before and after cleaning.

    Is responsible to get and keep the cleaning activities records from the

    cleaning contractor

    Maintains history of pipelines cleaning and incorporates relevant reports and

    data into permanent pipelines records

    4.6 Loss Prevention Department

    Audit cleaning operations and permits

    Advise on field safety precautions on request.

    4.7 Research and Development Center (R&DC)

    Evaluate new cleaning chemicals

    Provide specialist/consultant advice and testing on request

    4.8 Regional Laboratories

    Perform cleanliness criteria test (solid loading), chemical analysis, and

    analyses during actual cleaning operations on request.

    Verify chemicals used for chemical cleaning on request.

    4.9 Consulting Services Department

    Maintain and qualify the cleaning chemicals and contractors.

    Review and approve the cleaning procedures and subsequent changes

    mandated by the field conditions.

    Provide specialist/consultant advice on request.

  • Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-388

    Issue Date: 4 November 2013

    Next Planned Update: 4 November 2018 Cleaning of Pipelines

    Page 5 of 24

    Witness the cleaning operation on request.

    4.10 Cleaning Contractor

    The cleaning contractor is selected from the CSD- approved list of pipelines

    cleaning.

    Contractor has the overall responsibility for the planning and execution of

    the chemical cleaning operations.

    Contractors responsibilities shall be stated in the contract. Usually, this include, but not limited to, submittal of procedures and documents, supply of

    chemicals, inhibitors, auxiliary pumping, heating equipment, on line

    monitoring and control of corrosion rates; disposal of all waste water and

    chemical solutions and cleaning pipelines to meet, at least, the acceptance

    criteria outlined in SAES-L-388.

    Provide the required experienced manpower that includes, but not limited to,

    Project Manager

    Project Supervisor

    QA/QC Inspector

    Safety Coordinator

    Work Permit Receiver

    Certified chemist

    Cleaning crew

    4.11 Design Review Requirements for Pipelines Projects and Major Pipelines Upgrade

    Design Basis Scoping Paper (DBSP) and Project Proposal

    The DBSP and Project Proposal packages submitted to CSD for review shall

    specifically state the need for mechanical/chemical cleaning.

    Detailed Design

    The detailed design packages shall provide a cleaning document to be used as a

    basis during the construction phase of the project for preparation of detailed

    cleaning procedures. The cleaning document submitted to CSD for review shall

    include:

    Scope of work

    Proposed cleaning technique(s)

    Cleanliness acceptance criteria

    Equipment lay-out diagram of the cleaning circuit for the line segments

  • Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-388

    Issue Date: 4 November 2013

    Next Planned Update: 4 November 2018 Cleaning of Pipelines

    Page 6 of 24

    Marked-up P&IDs for the line segments

    Drying and lay-up requirements

    5 Techniques for Cleaning Pipelines

    Pipelines are either pre-commission cleaned to remove mill scale, construction debris

    and any form of solids, or post-commission cleaned to remove deposits which

    accumulate while the line is in service.

    Pre-commission cleaning is usually carried out on pipelines. Care during design,

    manufacture, fabrication, storage and installation of pipes can minimize these problems.

    Good storage facilities with end caps on the constructed pipelines, the internal grinding

    of welds where possible and ensuring that weld rods, stones and gloves, etc., are kept

    out of the line are practices which should-be implemented.

    Newly constructed pipelines are to be turned over to the proponent in a clean condition.

    To accomplish this clean condition, these pipelines are typically

    chemically/mechanically cleaned to remove construction debris and any form of solids.

    Existing pipelines in sales gas service are also chemically/mechanically cleaned to

    remove black powder that poses multiple operational problems such as delays in inline

    inspection (ILI) runs, erosion corrosion of control valves, plugged filters, and

    contamination of customer hydrocarbon supply.

    Pipelines are cleaned by scraping and/or chemical cleaning.

    5.1 Mechanical Cleaning (Scraping)

    Scraping is a mechanical cleaning method for pipelines cleaning. Scrapers are

    generally made of polyurethane foam and shaped like oversized bullets.

    They are inserted into a pipeline by a specially designed launcher which is

    connected to a high pressure medium to propel the scrapers. The polyurethane

    material used for the scrapers is sufficiently flexible that it will negotiate bends

    in the line. Since scrapers have been known to get stuck in lines the contractor

    should be questioned as to how blocked scrapers will be located. At the outlet, a

    scraper receiver is employed to recover the emerging scrapers and debris.

    Depending on the deposit present, scraper design can be hard rubber, silicon

    carbide, hardened steel wire, or gel. Sometimes balls with scraper chains are

    used. A series of scrapers, in larger sizes, is run through the line until all the

    fouling is removed.

    Scraping is manpower intensive and requires much field supervision. In many

    cases, lines not originally designed for scraping cannot be cleaned by this

    method. Scrapers usually contain spring-loaded metal blades which are centered

  • Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-388

    Issue Date: 4 November 2013

    Next Planned Update: 4 November 2018 Cleaning of Pipelines

    Page 7 of 24

    in the pipeline and pulled by cable or propelled by hydraulic pressure.

    To clean existing pipelines in service, refer to SABP-L-012 Guidelines for On-Stream Scraping of Pipelines.

    For cleaning newly constructed pipelines and existing off stream pipelines, refer

    to SABP-L-012 Guidelines for On-Stream Scraping of Pipelines. The scrapers will be propelled by Nitrogen, dry gas or dry hydrocarbon medium using the

    cleaning contractor equipment.

    Note: brushes in all supplied scrapers are recommended to be made of brass

    material to eliminate sparks due to friction between the scrapers brushes and the

    pipe inner wall.

    5.2 Chemical Cleaning

    The chemical cleaning operation is typically done while the pipeline is in service

    or out of service and will be specified by Pipelines Department. The chemical

    cleaning methods typically fall under two methods: 1) use of chemicals with

    diesel or 2) use of chemicals with gel. Water is not to be used as a mixing

    medium when surfactants are used. The chemical cleaning train that contains

    the chemicals compartment is typically propelled with dry air or nitrogen.

    If air is used to propel the chemical cleaning train, a nitrogen buffer zone

    between the chemical train and air is to be utilized. This nitrogen buffer zone

    shall be placed immediately upstream and downstream of the chemical cleaning

    train. The nitrogen length on each side shall be no less than 10% of the total

    length of the pipeline section being chemically cleaned to ensure that diesel and

    air do not mix.

    Deposits normally include black powder, rust, scale, grease, weld spatter, stones,

    etc. Scales and grease are chemically soluble but beads of weld metal are not,

    although it is possible for a chemical cleaning operation to loosen these by

    undercutting. In this state, they may become detached while the line is in service.

    In practice, chemical cleaning should be used to remove soluble scale and grease

    but should be followed by multiple scrapers. The line should also be dried as

    specified under SAES-A-007 to prevent subsequent corrosion immediately after

    cleaning. In the case of pipelines, these shall be filled with nitrogen, dry gas or

    dry crude as soon as possible after cleaning. Due to the network length of

    piping involved, communication between members of the cleaning crew can be

    difficult, and shall be addressed prior to start of the job. Lines containing iron

    sulfide will release H2S gas when contacted with acid and suitable precautions

    have to be taken as per Chemical Hazard Bulletin (CHB) # 155.

  • Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-388

    Issue Date: 4 November 2013

    Next Planned Update: 4 November 2018 Cleaning of Pipelines

    Page 8 of 24

    Cleaning Chemicals

    There are mainly two chemical categories used for pipelines cleaning:

    1. Acids

    For detailed chemical cleaning procedure using acids, refer to

    SAEP-1662 Cleaning of Heat Exchangers and Unfired Plant Equipment.

    2. Surfactants

    Surfactants chemicals are non-corrosive compounds that lower the

    surface tension of a liquid, the interfacial tension between two liquids,

    or that between a liquid and a solid. Surfactants may act as detergents,

    wetting agents, emulsifiers, foaming agents, and dispersants.

    For the approved list of surfactants, or approval of new ones, refer to CSD.

    6 Surfactant Cleaning Procedure

    For newly constructed pipelines, contractors, Pipelines Department and/or Saudi

    Aramco Project Management Team (SAPMT) shall submit their respective procedures

    covering their area of responsibilities during the chemical cleaning operations.

    The procedure shall include the work activities and responsibilities before, during, and

    after the chemical cleaning operations.

    The contractor, their submitted procedure shall include the following:

    Safety requirements (Appendix I)

    Responsibilities

    Site Access and work permit

    Preparatory work (Appendix II)

    Equipment layout

    Chemical cleaning schedule

    Detailed chemical cleaning procedures

    The chemical cleaning procedure shall include the valve arrangements before, during, and

    after each chemical cleaning run. It shall also include the detailed chemical train

    launching procedure, the monitoring and tracking of the chemical train, and the receiving

    procedure. The procedure shall also include the data monitoring such as upstream and

    downstream pressure of the chemical train, its velocity, and any other important data.

  • Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-388

    Issue Date: 4 November 2013

    Next Planned Update: 4 November 2018 Cleaning of Pipelines

    Page 9 of 24

    Equipment Layout:

    VALVE DESCRIPTION:

    VALVE DESCRIPTION

    MIV Main Isolation Valve

    A Chemical/Diesel Injection Valve

    B N2/Air Main Injection Valve

    C N2/Air Branch Injection Valve

    D N2/Air Branch Injection Valve

    V1 Launcher Vent

    V2 Launcher Vent

  • Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-388

    Issue Date: 4 November 2013

    Next Planned Update: 4 November 2018 Cleaning of Pipelines

    Page 10 of 24

    Detailed Surfactant Cleaning Procedure

    Before performing surfactant cleaning, rigorous mechanical scarping operation shall be

    performed to remove as much solids as possible from the pipeline.

    Surfactant cleaning of the pipeline shall be executed to ensure the removal of any sand,

    corrosion products such as iron carbonate, iron oxides and iron sulfide, metallic iron, weld

    spatter, salt and scale generated during the dewatering and swabbing.

    Specific chemical cleaning train should be designed for the entire pipeline in the scope of

    the procedure. The segment of pipeline from permanent launcher to permanent receiver

    trap is to be chemically cleaned by two (2) cleaning train/runs with additional optional runs

    if required. Refer to Figure 1 Chemical Cleaning Train for its configuration.

    Pre-requisites:

    Prior to start the surfactant cleaning train run, an initial back pressure of minimum 40 psig

    shall be ensured in order to perform the run in controlled manner and within the required

    velocity.

    The medium to build up the back pressure and to propel the chemical cleaning train shall be

    with nitrogen and dry air having a minimum dew point -1C. Record log of the dry air dew

    point shall be maintained during the back pressure build up and the train run. Dew point

    reading shall be taken as the dry air entering into the pipeline every 4 hours.

    A slug of nitrogen will be injected upstream and downstream of the cleaning train to create

    a buffer zone between the dry air and the cleaning train.

    Please refer to Table 1 Chemical Train Composition and Run Duration for its volume. The specified gallons of nitrogen provided in Table 1 is equivalent to at least 20% of the

    pipeline length that will be cleaned (10% before that cleaning train and 10% after the

    cleaning train).

    Whenever the surfactant cleaning is completed as per the approved chemical cleaning

    procedure, then the pipeline as required shall be purged and pressurized to a minimum

    pressure of 30 psig (Nitrogen) in preparation to the introduction of the transported media.

    The planned cleaning run for the pipeline segment along with the expected amount of

    chemicals and diluents are to be shown in Table 1.

  • Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-388

    Issue Date: 4 November 2013

    Next Planned Update: 4 November 2018 Cleaning of Pipelines

    Page 11 of 24

    Table 1 - Cleaning Train Composition and Run Duration

    Pipeline

    From To

    1st

    and 2nd

    Surfactant Cleaning Runs**

    Dry Air

    First Scraper High Density Foam

    N/A

    1st

    Batch of Nitrogen

    N2 Gallons XXX

    Second Scraper High Density Foam

    N/A

    1st

    Batch Detergent Gallons XXX

    Diesel Gallons XXX

    Third Scraper Conical Scraper Brush

    2nd

    Batch Detergent Gallons XXX

    Diesel Gallons XXX

    Fourth Scraper Scraper Brush

    2nd

    Batch of Nitrogen

    N2 Gallons Chemical

    Fifth Scraper High Density Foam

    N/A

    Dry Air

    *Estimated run duration Hrs. XXX

    * Estimated travel time is based on dry air velocity of 1.0 kilometer per hour. Velocity, volumes of chemicals and diluents and type of chemicals may be adjusted depending on the gathered results from the previous runs.

    ** Optional Run Only When Required.

    Vacuum Truck will be used on a regular interval to empty the tanks and dispose

    it to an approved waste disposal site/company.

    Note: Refer to Appendix III for nitrogen amount calculation.

  • Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-388

    Issue Date: 4 November 2013

    Next Planned Update: 4 November 2018 Cleaning of Pipelines

    Page 12 of 24

    Figure 1 - Surfactant Cleaning Train

    Surfactant cleaning will be performed as per the sequence described as follows:

    Steps Description

    1 Rig up equipment for both Launcher and Receiver

    2 Deploy hoses supply line for connection

    3 Pressurize hose against closed valve for 5 minutes to confirm connection leak test

    4

    Nitrogen purity entering the pipeline should be checked by the contractor using a hand held Nitrogen analyzer and as

    per approved pureness of 95% minimum.

    Volume and sequence will be as per Table 1 Pipeline Chemical Train Composition and Run Duration

    5

    Prepared the chemical required quantity base on Contractor concentration of diluents slug. Volume and sequence

    will be as per Table 1 Pipeline Chemical Train Composition and Run Duration. Collect one set of sample per batch as per Section 7.

    6 As per pre-requisite, verify and confirm that the line is pack to a minimum 40 psig of nitrogen.

    Re-packed when necessary.

    7

    1st Batch of Nitrogen:

  • Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-388

    Issue Date: 4 November 2013

    Next Planned Update: 4 November 2018 Cleaning of Pipelines

    Page 13 of 24

    Steps Description

    VALVE START-UP POSITION:

    VALVE STATUS DESCRIPTION

    MIV CLOSED Main Isolation Valve

    A CLOSED Chemical/Diesel Injection Valve

    B CLOSED N2/ Air Main Injection Valve

    C CLOSED N2/Air Branch Injection Valve

    D CLOSED N2/Air Branch Injection Valve

    V1 CLOSED Launcher Vent

    V2 CLOSED Launcher Vent

    Launch 1st Scraper and Inject Nitrogen

    De-pressurize Launcher Trap by opening V1 and V2 vent valve.

    Check scraper tracking device prior to insertion.

    Open Trap Door and insert Scraper (High Density Foam No Brush) up to launcher reducer. Close Launcher Trap Door.

    Crack Open Valve C to purge upstream of the scraper through V1

    Once purged, Closed V1 and inject max 3 psi of nitrogen to have a positive pressure upstream of the scraper. Closed Valve C.

    Crack Open Valve D to purge downstream of the scraper through V2.

    Once purged, close Valves V2 and D.

    Pressurize trap to equal line pressure by opening Valve C.

    Open main isolation valve (MIV) and Launch scraper by nitrogen.

    Continue pumping nitrogen till the required amount has been injected.

    Close C and MIV valve.

    Launch 2nd

    Scraper:

    De-pressurize Launcher Trap by opening V1 and V2 vent valve.

    Open Trap Door and insert 2d Scraper (High Density Foam No Brush) up to launcher reducer. Close Launcher Trap Door.

    Crack Open Valve C to purge upstream of the scraper through V1.

    Once purged, Closed V1 and inject max 3 psi of nitrogen to have a positive pressure upstream of the scraper. Closed Valve C.

    Crack Open Valve D to purge downstream of the scraper through V2.

    Once purged, close Valves V2 and D.

    Pressurize trap to equal line pressure by opening Valve C.

    Open MIV valve and Launch 2d scraper by nitrogen.

    After the scraper passes the MIV valve and injection point (Valve A), immediately close C and MIV valve.

    VALVE ENDING POSITION

    VALVE STATUS DESCRIPTION

    MIV CLOSED Main Isolation Valve

    A CLOSED Chemical/Diesel Injection Valve

    B OPENED N2/ Air Main Injection Valve

    C CLOSED N2/Air Branch Injection Valve

    D CLOSED N2/Air Branch Injection Valve

    V1 CLOSED Launcher Vent

    V2 CLOSED Launcher Vent

  • Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-388

    Issue Date: 4 November 2013

    Next Planned Update: 4 November 2018 Cleaning of Pipelines

    Page 14 of 24

    Steps Description

    8

    Cleaning Train

    Diesel and Surfactant Injection I Scraper Loading and Launching Sequence.

    FIRST BATCH CHEMICAL

    VALVE START-UP POSITION:

    VALVE STATUS DESCRIPTION

    MIV CLOSED Main Isolation Valve

    A CLOSED Chemical/Diesel Injection Valve

    B CLOSED N2/ Air Main Injection Valve

    C CLOSED N2/Air Branch Injection Valve

    D CLOSED N2/Air Branch Injection Valve

    V1 CLOSED Launcher Vent

    V2 CLOSED Launcher Vent

    Insert 3rd

    Scraper

    De-pressurize Launcher Trap by opening V1 and V2 vent valve.

    Open Trap Door and insert 3rd Scraper (Conical with Brush) up to launcher reducer. Close Launcher Trap Door.

    Crack Open Valve C to purge upstream of the scraper through V1.

    Once purged, Closed VI and inject max 3 psi of nitrogen to have a positive pressure upstream of the scraper. Closed Valve C.

    Crack Open Valve D to purge downstream of the scraper through V2.

    Once purged, close Valves V2 and D.

    Inject 1st Batch of Chemical and Diesel

    Open Valve A and inject the required amount of surfactant followed by the required amount of diesel. Refer to Table 1 for the batch volume.

    Once fully injected, close Valve A.

  • Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-388

    Issue Date: 4 November 2013

    Next Planned Update: 4 November 2018 Cleaning of Pipelines

    Page 15 of 24

    Steps Description

    Launched 3rd

    Scraper

    Pressurize trap to equal line pressure by opening Valve C.

    Open MIV valve and Launch 3rd scraper by nitrogen.

    After the scraper passes the MIV valve and injection point (Valve A), immediately close C and MIV valve.

    VALVE ENDING POSITION

    VALVE STATUS DESCRIPTION

    MIV CLOSED Main Isolation Valve

    A CLOSED Chemical/Diesel Injection Valve

    B CLOSED N2/ Air Main Injection Valve

    C CLOSED N2/Air Branch Injection Valve

    D CLOSED N2/Air Branch Injection Valve

    V1 CLOSED Launcher Vent

    V2 CLOSED Launcher Vent

    9

    SECOND BATCH

    VALVE START-UP POSITION:

    VALVE STATUS DESCRIPTION

    MIV CLOSED Main Isolation Valve

    A CLOSED Chemical/Diesel Injection Valve

    B CLOSED N2/ Air Main Injection Valve

    C CLOSED N2/Air Branch Injection Valve

    D CLOSED N2/Air Branch Injection Valve

    V1 CLOSED Launcher Vent

    V2 CLOSED Launcher Vent

  • Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-388

    Issue Date: 4 November 2013

    Next Planned Update: 4 November 2018 Cleaning of Pipelines

    Page 16 of 24

    Steps Description

    Insert 4th

    Scraper

    De-pressurize Launcher Trap by opening V1 and V2 vent valve.

    Open Trap Door and insert 4th Scraper (With Brush) up to launcher reducer. Close Launcher Trap Door.

    Crack Open Valve C to purge upstream of the scraper through V1.

    Once purged, Closed V1 and inject max 3 psi of nitrogen to have a positive pressure upstream of the scraper. Closed Valve C.

    Crack Open Valve D to purge downstream of the scraper through V2.

    Once purged, close Valves V2 and D.

    Inject 2nd

    Batch of Chemical and Diesel

    Open Valve A and inject the required amount of surfactant followed by the required amount of diesel. Refer to Table 1 for the batch volume.

    Once fully injected, close Valve A.

    Launched 4th

    Scraper and Inject 2nd

    Batch of Nitrogen

    Pressurize trap to equal line pressure by opening Valve C.

    Open MIV valve and Launch 4th scraper by nitrogen.

    Continue pumping nitrogen required volume has been injected.

    Close C and MIV valve.

    VALVE ENDING POSITION

    VALVE STATUS DESCRIPTION

    MIV CLOSED Main Isolation Valve

    A CLOSED Chemical/Diesel Injection Valve

    B OPENED N2/ Air Main Injection Valve

    C CLOSED N2/Air Branch Injection Valve

    D CLOSED N2/Air Branch Injection Valve

    V1 CLOSED Launcher Vent

    V2 CLOSED Launcher Vent

  • Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-388

    Issue Date: 4 November 2013

    Next Planned Update: 4 November 2018 Cleaning of Pipelines

    Page 17 of 24

    Steps Description

    10

    5th

    Scraper

    VALVE START-UP POSITION

    VALVE STATUS DESCRIPTION

    MIV CLOSED Main Isolation Valve

    A CLOSED Chemical/Diesel Injection Valve

    B OPENED N2/ Air Main Injection Valve

    C CLOSED N2/Air Branch Injection Valve

    D CLOSED N2/Air Branch Injection Valve

    V1 CLOSED Launcher Vent

    V2 CLOSED Launcher Vent

    Insert 5th Scraper

    De-pressurize Launcher Trap by opening V1 and V2 vent valve.

    Check scraper tracking device prior to insertion.

    Open Trap Door and insert Scraper (High Density Foam No Brush) up to launcher reducer. Close Launcher Trap Door.

    Crack Open Valve C to purge upstream of the scraper through V1.

    Once purged, Closed V1 and inject max 3 psi of nitrogen to have a positive pressure upstream of the scraper. Closed Valve C.

    Crack Open Valve D to purge downstream of the scraper through V2.

    Once purged, close Valves V2 and D.

    Pressurize trap to equal line pressure by opening Valve C.

    When pressure is equalized, close Valve C.

    Close Valve Band disconnect NGU and connect the air dryer's outlet hoses to the manifold.

  • Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-388

    Issue Date: 4 November 2013

    Next Planned Update: 4 November 2018 Cleaning of Pipelines

    Page 18 of 24

    Steps Description

    Launch 5th

    Scraper

    Open Valve B, followed by Valve C.

    Open the MIV valve and Launched 5th scraper by dry air.

    VALVE ENDING POSITION

    VALVE STATUS DESCRIPTION

    MIV OPENED Main Isolation Valve

    A CLOSED Chemical/Diesel Injection Valve

    B OPENED N2/ Air Main Injection Valve

    C OPENED N2/Air Branch Injection Valve

    D CLOSED N2/Air Branch Injection Valve

    V1 CLOSED Launcher Vent

    V2 CLOSED Launcher Vent

    11 Continue pumping dry air to propel the chemical slug train until it reach to receiver trap.

    12 Dew Point and line pressures are to be recorded on an hourly basis at launcher and receiver stations as well as the

    scraper movements.

    13

    With a positive back pressure monitored, station contractor crew leader shall control Valve E and/or Valve F and

    release pressure in a controlled manner, maintaining a balance between dry air injection and release for

    smooth/intact surfactant train movement having an average of 1 to 1.5 km/hr speed.

    14

    All liquid/solid slurry shall be received in temporary tanks.

    Note: Vacuum Truck will be used on a regular interval to empty the tanks and dispose it to an approved waste

    disposal site/company.

    15 During the arrival of the Cleaning Train into the receiver, collect liquid samples from the two compartments of the

    chemical cleaning train.

    16 Once all the scrapers are inside the receiver trap, close the 30 main isolation valve.

    17 Ensure that the receiver is free of pressure by venting the Receiver trap from the vent provided that Saudi Aramco

    representative in on location. The receiver may be opened and scrapers retrieved.

    18 Stop air injection

    19 Repeat steps 7 to 18 for the 2

    nd run.

    And 3rd

    run if the result requires additional runs.

    After the scrapers have been received from the final cleaning run, the remaining collected sludge or waste

    materials from the fractionation tanks will be transferred and disposed via vacuum tanker to an approved waste

    disposal site/company.

    20 PURGING AND FINAL LAYUP Nitrogen Generating unit should be prepared and hooked-up prior to starting swabbing.

    Scraper Loading and Launching Sequence:

    VALVE START-UP POSITION

    VALVE STATUS DESCRIPTION

    MIV CLOSED Main Isolation Valve

    A CLOSED Chemical/Diesel Injection Valve

    B OPENED N2/ Air Main Injection Valve

    C CLOSED N2/Air Branch Injection Valve

    D CLOSED N2/Air Branch Injection Valve

    V1 CLOSED Launcher Vent

    V2 CLOSED Launcher Vent

  • Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-388

    Issue Date: 4 November 2013

    Next Planned Update: 4 November 2018 Cleaning of Pipelines

    Page 19 of 24

    Insert Foam Scraper

    Perform foam scraping runs, following completion of chemical cleaning operation, to remove residual chemicals left

    in the pipeline.

    De-pressurize Launcher Trap by opening V1 and V2 vent valve.

    Open Trap Door and insert Foam Scraper (with No Brush) up to launcher reducer. Close Launcher Trap Door.

    Crack Open Valve C to purge upstream of the scraper through VI.

    Once purged, Closed VI and inject max 3 psi of nitrogen to have a positive pressure upstream of the scraper. Closed Valve C.

    Crack Open Valve D to purge downstream of the scraper through V2.

    Once purged, close Valves V2 and D.

    Pressurize trap to equal line pressure by opening Valve C.

    Open MIV valve and Launch Foam scraper by nitrogen.

    VALVE ENDING POSITION

    VALVE STATUS DESCRIPTION

    MIV OPENED Main Isolation Valve

    A CLOSED Chemical/Diesel Injection Valve

    B OPENED N2/ Air Main Injection Valve

    C OPENED N2/Air Branch Injection Valve

    D CLOSED N2/Air Branch Injection Valve

    V1 CLOSED Launcher Vent

    V2 CLOSED Launcher Vent

    21 Continue pumping nitrogen to propel the swabbing train until it reach to receiver trap.

    22 Dew Point and line pressures are to be recorded on an hourly basis at both launch and receiving stations.

    23 With positive back pressure monitored, manipulate Valve E and/or Valve F and release pressure in a controlled

    manner, maintaining a balance between nitrogen injection and dry air release.

    24 Once the scraper is inside the receiver trap, close the main isolation valve.

    25 Ensure that the receiver is free of pressure by venting the Receiver trap from the vent, and provided that a company

    representative is on location. The receiver may be opened and scrapers retrieved.

    26 Stop nitrogen injection.

    27

    Nitrogen Purging and Final Lay-up (as Per SAES-A-007 Section 5.2.3.6)

    Continue purging the line with nitrogen, once the required dew point (-1C or lower) and N2 purity are reached at

    the discharge vent, the vent will be closed and packing of the pipeline to 30 psig will commence.

    28 When the line is at the required pack pressure, the N2 purity will be confirmed at the discharge valve and at all

    required valves along the length of the pipeline.

    29 Stop nitrogen injection.

    7 Sampling and Acceptance Criteria

    Sampling of cleaning batch (before injection) will be taken at the launching (from

    tanks) and receiving locations (from scraper trap) in order to monitor the surfactant

    cleaning run.

    7.1 Clean containers will be used to collect the samples and they shall be clearly

    identified with the following information:

    o Pipeline Name, Date, Location (KM), and Batch Number

  • Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-388

    Issue Date: 4 November 2013

    Next Planned Update: 4 November 2018 Cleaning of Pipelines

    Page 20 of 24

    o Samples will be sent to a laboratory for their solid in suspension counting (% in Volume).

    o Pipeline will be considered clean enough if it meets the cleanliness criteria stated in SAES-L-388.

    7.2 Sampling at the Receiver

    1. Control the surfactant discharging flow rate by throttling the discharge valve.

    2. A clean container should be placed under the sample valve.

    3. Open the sampling valve and flush at least 500 ml of fluid through the

    valve. Do not close the valve after flushing.

    4. Place the sample bottle under the valve and collect fluid. Do not touch the

    valve whilst taking the sample as this could cause particles to loosen and be

    released from the valve.

    5. Withdraw the sample bottle leaving the valve open. Rinse the inner surface

    to the bottle with fluid and discard the fluid. Repeat Steps 4 and 5 for all

    the bottles to be used.

    6. Repeat the above without closing the valve and collect two (2) liquid

    samples per chemical compartment.

    7. One sample of fluid will be analyzed by the cleaning contractor to obtain

    solids contain per volume. Second sample shall be given to Saudi Aramco

    Operations Representative for any future required confirmation of results.

    8 Evaluating Chemical Cleaning Performance

    Refer to SAES-L-388.

    9 Wastewater Disposal

    Disposal of all wastewater, and spent cleaning chemicals shall be in accordance with

    SAEP-327, SAES-A-104 and Saudi Aramco Hazardous Waste Code (SAHWC).

    The disposal of effluents outside Saudi Aramco facilities shall be sent to an approved

    wastewater disposal facility provided by the Environmental Protection Department,

    Dhahran. For the disposal of effluents outside Saudi Aramco facilities, the chemical

    cleaning contractor shall submit a waste disposal manifest to Saudi Aramco Project

    Construction Agency in case of new pipelines or Pipelines Department for existing

    pipelines.

    Revision Summary

    4 November 2013 New Saudi Aramco Engineering Procedure.

  • Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-388

    Issue Date: 4 November 2013

    Next Planned Update: 4 November 2018 Cleaning of Pipelines

    Page 21 of 24

    APPENDIX I - Safety Requirements

    All personnel shall be aware of emergency procedures and will attend contractor

    safety/site introduction meetings on a daily basis before the start of any work or as

    required to ensure that everyone understands his responsibility and what to do in case of

    emergency.

    First aid and fire protection equipment shall be kept on the site (launcher and receiver)

    Minimum of 2 dry powder fire extinguishers (30 lb) shall be available on both sites.

    All involved personnel on site shall wear proper protective equipment (PPE).

    This includes fire resistance coveralls, Neoprene, PVC or NBR gloves or nitrile rubber,

    Safety Glasses and Steel Toed Shoes/chemical resistant boot.

    Prior to commencing chemical cleaning operations, warning signs indicating Cleaning is On-going shall be posted at launcher and receiving ends and along the pipeline section corridor particularly at road crossings. Barriers shall indicate the limits of a

    pipeline leaning area. Warning signs, in English and Arabic, shall be placed in

    permanent locations.

    Use of mobile phones and smoking within the scraper trap areas are prohibited.

    Any leaks and repairs identified shall only be corrected when the system under test has

    been depressurized to zero.

    Provide an effective eye wash station and emergency shower per SAES-B-069 on both

    launching and receiving station.

    If chemicals are needed, chemical Material Safety Data Sheets (MSDS) should be

    attached with the chemical containers and fully understand by all personnel handling it.

    Disposal of cleaning waste shall be as per SAEP-327.

    Job Safety Analysis (JSA) shall be performed by the proponent before starting the

    cleaning activities of pipelines. For more chemical cleaning safety information, refer to

    SAEP-1662.

  • Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-388

    Issue Date: 4 November 2013

    Next Planned Update: 4 November 2018 Cleaning of Pipelines

    Page 22 of 24

    APPENDIX II - Preparatory Work

    For new pipelines cleaning, SAPMT to identify the overall responsible scraping and

    cleaning activity coordinator. This coordinator shall ensure that all steps in this

    procedure are followed. He should also ensure all safety measures are implemented.

    The implementation of this procedure shall be under the direction and supervision of the

    operation site coordinator. During the entire cleaning operations, Project inspection

    shall be present at all times on site to ensure the monitoring of the chemical cleaning

    operations and that it is going according to plan. Constant communications by

    personnel on site on the conditions of the chemical cleaning operations shall be done.

    For existing pipelines cleaning, the above mentioned responsibilities will be under

    Pipelines Department.

    The work shall be carried out in accordance with company Standards and General

    Instructions. These will include, but not limited to the following:

    GI-0002.100 - Work Permit System

    GI-0006.012 - Isolation Lock Out and Use of Hold Tag

    Check to ensure that all scraper traps' isolation valves and all pertinent branch valves

    are not passing. If valves are passing, perform the necessary maintenance to stop the

    passing valves.

  • Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-388

    Issue Date: 4 November 2013

    Next Planned Update: 4 November 2018 Cleaning of Pipelines

    Page 23 of 24

    APPENDIX III - Nitrogen Amount Calculation

    NITROGEN GAS CALCULATIONS

    V1 = volume of liquid nitrogen (Gallons)

    T2 = Final Nitrogen gas Temperature (Kelvin)

    P2= Final Nitrogen gas pressure (atm.)

    Vg= final volume of Nitrogen gas (ft3)

    Example:

    The volume of liquid nitrogen you need to fill 36 pipeline with a length of 1 km at pressure of 60 psi

    and temperature of 40C:

    r = 18 = 0.4572 meters

    l = 1000 meters

    Vg = volume of pipe = 3.14 * (0.4572)2 * 1000 = 656.3 m

    3 = 23,177 ft

    3

    P2 = 60 psi = 4.08 atm

    T2 = 40C = 313 K

    Then: =

    =

  • Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-388

    Issue Date: 4 November 2013

    Next Planned Update: 4 November 2018 Cleaning of Pipelines

    Page 24 of 24

    APPENDIX IV - Cleaning of Pipelines Containing Valves

    For cleaning of pipelines containing valves, contact CSD. In general,

    It is always recommended not to operate the valve in a dry condition since it can cause

    damage to the seat area. In order to avoid such failure it always recommended to top up the valve prior to any cycling: This will also help to push away any foreign debris that may have become stuck in the grease from the seal face. Any abrasive

    contaminants will do far less damage if well lubricated.

    The compatibility of the used chemical with valve soft insert to be checked and

    confirmed.

    Avoid stroking the valve during the pipeline cleaning to avoid any exposure to the valve

    seating area: In case the valve cavity filling is required, then a Jumper Hose Assembly

    Method is recommended where jumpers hose assembly from the pipeline to the valve

    body cavity through the body drain/vent valve.

    At the end of the cleaning process, selected valves might be removed for visual

    inspection and seat testing if required. If this is not practical then an inside-out air seat

    test to be performed on line to ensure that there was no damage to the valve due to the

    commissioning activities.