SABP-A-033 Materials & Corrosion Control Standards
-
Upload
talha-bin-zubair -
Category
Documents
-
view
1.039 -
download
94
description
Transcript of SABP-A-033 Materials & Corrosion Control Standards
Previous Issue: New Next Planned Update: TBD
Revised paragraphs are indicated in the right margin Page 1 of 52
Primary contacts: Sami M. Al-Ghamdi on 880-9573 and/or Abdelhak Kermad on 880-9529
Copyright©Saudi Aramco 2013. All rights reserved.
Best Practice
SABP-A-033 30 March 2013
Corrosion Management Program (CMP) Manual
Document Responsibility: Materials and Corrosion Control Standards Committee
Saudi Aramco DeskTop Standards
Table of Contents
Foreword…………………………………………..…..….. 2
1 References…………………………………….… 4 2 Definitions…………………………………….…. 6
Part 1: Basic Requirements and Deployment Activities
1 Introduction…………………………………….... 8 2 Policy and Strategies………………..……...… 11 3 Organization…………………………..……….. 14 4 Deployment Methodology…………..………... 18 5 Review………………………………………..… 30 6 Central Engineering Review (Appendix 3)….. 31
Appendix 1 - Plant Information Required…………. 33 Appendix 2 - Corrosion Loops Development…….. 35 Appendix 3 - CMP Checklist for Self and Central Engineering Reviews……..….. 37
Part 2: “Manage Corrosion” Work Processes…...... 42
Introduction………………………………………. 43 Attachment 1 - “Manage Corrosion” at Design.….. 47 Attachment 2 - “Manage Corrosion” at Procurement and Construction………..... 47 Attachment 3 - “Manage Corrosion” at Operate and Maintain……………………. 47 Attachment 4 - “Manage Corrosion” at Decommissioning………………………… 47
Part 3: Damage Mechanism Narratives………..…… 48
Introduction……………………………..……….. 49
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 2 of 52
Foreword
Corrosion management represents a key component of Saudi Aramco’s overall strategy to
safeguard plant integrity, reliability and safety. It is founded on the following integrated elements:
1. Work Processes (Core, Strategic, Tactical, Elemental and Atomic)
2. Risk-Assessment
3. Competency and Training
4. Roles and Responsibilities
5. Technologies
6. Performance Measurement
7. Reviews and Continuous Improvement
The Corrosion Management Program (CMP) is an integral part of Element 5 “Asset Integrity” of
the corporate Safety Management System (SMS). SMS and CMP are integrated tools developed
by Saudi Aramco to manage asset performance and maximize plant reliability and utilization
without compromise to safety and the environment.
This Corrosion Management Program Manual represents the “what” and “how to” for deploying
corrosion management strategies throughout Saudi Aramco operational facilities. It provides
generic guidelines and principles that will require customization to specific plants or units.
Process fluids, operating conditions and materials differ from one plant to another.
Accordingly, appropriate corrosion control and mitigation strategies will be required to manage
corrosion throughout the asset life cycle, i.e., at design, procurement and construction, operation
and maintenance, and at decommissioning. Specifically, this manual addresses the operation and
maintenance phase of the asset life cycle; however, its contents may also be adapted to address
corrosion management during the other phases of the life cycle. It is noted that the biggest
impact a corrosion management program may have on the long-term integrity and reliability of a
plant is during the design phase. Accordingly, Saudi Aramco documents such as SAEP-14
“Project Proposal”, SAEP-122 “Project Records” and SAES-L-133 “Corrosion Protection
Requirements for Pipelines, Piping and Process Equipment” stipulate the development of a CMP
for every new project or capital program at the earliest possible stage, based on established
guidelines and principles given in these documents.
Corrosion failure prevention is best achieved by focusing on the early stages of performance
degradation or incipient failure; these stages, termed “non-critical failures”, will result in “critical
failures” if left unattended or addressed too late. Accordingly, a key theme of CMP is
proactivity; this is evident in the development of proactive leading/lagging indicators and Plant
Integrity Windows (PIW). These performance metrics and variables represent the Dashboard of
corrosion management across Saudi Aramco facilities. Therefore, diligent corrosion prediction
and monitoring technologies play a critical role to safeguard the proactive nature of CMP.
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 3 of 52
CMP development follows the “plan-do-check-act” approach. Essentially, corrosion
management activities must first be rigorously planned; this planning must be according to the
strategies set out by management. Another term for “do” is “strategize”. The plans developed
must then be followed through or implemented. Another term for “do” is “implement”. Once the
plans have been put into action, checks must be carried out to ensure that the desired results are
achieved, i.e., in the context of CMP, this means Manage Corrosion. Another term for “check” is
“analyze”. Finally, if analyses or checks show problematic system performance, then
rectification is required to restore performance to the desired level or target. This final step
would also involve system improvement by deployment of new technologies and updated
knowledge. Another term for “act” is “rectify” or “improve”.
It is well-established that, without an integrated approach to corrosion management, equipment
and piping failures will continue to occur, thus representing potentially major adverse risk to
facilities, personnel, environment and company reputation. It is thus paramount that engineers in
core engineering disciplines such as process/operation, inspection and reliability/maintenance are
conversant with the impact of process operations, inspection and maintenance activities on
corrosion. Work processes together with risk assessment, performance measurement,
competency/training and performance reviews are developed with integration in mind so that
corrosion management becomes everybody’s business.
The essence of a corrosion management program lies in the deployment and management of
procedures and systems to control the day-to-day corrosion related activities. Management of
corrosion operates simultaneously at various levels within our organization/facilities, and
includes:
● a policy and management structure to deal with corrosion issues as part of the overall
management process for the facility,
● documentation and procedures for engineers and managers with responsibility for
corrosion as part of the strategy or corrosion plan for the facility,
● planning and implementation of corrosion control and monitoring activities
● provision of means for the collection and assessment of site inspection and monitoring
data, and
● a system to review corrosion related activities on a regular basis.
These procedures and systems include engineering reviews, adequate quality assurance and
quality control of various aspects of design and construction, recording and trending of
monitoring and inspection data, use of condition based strategies and use or risk assessments.
This document is considered ever-green. Lessons learned shall be captured and anomalies
rectified, thus driving a process of continuous improvement. CMP work processes, technologies,
KPI and PIW targets shall be subjected to periodic reviews to ensure incremental improvement
in this program.
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 4 of 52
1 References
1.1 Saudi Aramco References
Saudi Aramco Engineering Procedures
SAEP-14 Project Proposal
SAEP-20 Equipment Inspection Schedule
SAEP-122 Project Records
SAEP-325 Inspection Requirements for Pressurized Equipment
SAEP-343 Risk-Based Inspection
SAEP-1135 On-Stream Inspection Administration
Saudi Aramco Engineering Standards
SAES-A-007 Hydrostatic Testing Fluids and Lay-Up Procedures
SAES-H-001 Coating Selection and Application Requirements for
Industrial Plants and Equipment
SAES-L-108 Selection of Valves
SAES-L-132 Material Selection for Piping Systems
SAES-L-133 Corrosion Protection Requirements for Pipelines, Piping and
Process Equipment
SAES-L-136 Pipe, Flange and Fitting Material Requirements
SAES-W-011 Welding Requirements for On-Plot Piping
Saudi Aramco Best Practices
SABP-A-001 Polythionic Acid SCC Mitigation
SABP-A-013 Corrosion Control in Amine Units
SABP-A-014 Atmospheric Oil Degassing, Spheroids and Stabilizers
Corrosion Control
SABP-A-015 Chemical Injection Systems
SABP-A-016 Crude Unit Corrosion Control
SABP-A-018 GOSP Corrosion Control
SABP-A-019 Pipeline Corrosion Control
SABP-A-020 Corrosion Control in Sulfur Recovery Units
SABP-A-021 Corrosion Control in Desalination Plants
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 5 of 52
SABP-A-025 Corrosion Control in Vacuum Distillation Units
SABP-A-026 Cooling Systems Corrosion Control
SABP-A-029 Corrosion Control in Boilers
SABP-A-036 Corrosion Monitoring Best Practice
Saudi Aramco Engineering Reports
SAER-2365 Saudi Aramco Mothball Manual
SAER-5573 Crude Distillation Unit Overhead Corrosion Study
SAER-5659 Guidelines for Setting Acceptable, Alarm and Shutdown
Vibration Limits
SAER-5883 Cost of Corrosion in Existing Saudi Aramco Operations
SAER-5942 Ammonium Bisulfide Corrosion in Hydrocracker and
Refinery Sour Water Service
SAER-6403 Corrosion Control Document JNGLF Fractionation and
Treating Modules 1/2/3/4
SAER-6344 Corrosion Control Document - ShGP CCD-1 ShGP Gas
Treating Units 1/2/3/4
SAER-6353 Corrosion Control Document - Yanbu Refinery Continuous
Catalytic Regeneration (CCR) Platformer Plant V11
SAER-6384 Corrosion Control Doc. - ABQ South Stabilizers Plant 120
SAER-6416 Corrosion Control Document JRD Crude Distillation Unit
CDU-2
1.2 Industry Codes and Standards
American Petroleum Institute
API RP 571 Damage Mechanisms Affecting Fixed Equipment in the
Refining Industry
API RP 580 Risk Based Inspection
API PUB 581 Risk-Based Inspection Base Resource Document
API RP 584 Integrity Operating Windows
1.3 Publications
Saudi Aramco Safety Management System, Loss Prevention Department
Qualitative Risk Assessment, Guide Number 02-002-2010, Saudi Aramco Safety
Management Guide, Loss Prevention Department, 24 July 2010
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 6 of 52
Guidance for Corrosion Management in Oil and Gas Production and Processing,
Energy Institute, the Health & Safety Executive (HSE), London, May 2008
2 Definitions
Corrosion Loop (CL): A section of a plant defined mainly on the basis of similar
process conditions, materials of construction or active/potential damage mechanisms.
Corrosion Loop Diagram (CLD): A Process Flow Diagram (PFD) or Materials
Selection Diagram (MSD) that is color-coded to reflect the developed corrosion loops.
Corrosion Management Program (CMP): Corporate Program developed by
CSD/ME&CCD aimed at reducing company cost of corrosion, predicting and preventing
failures, improving plant availability, optimizing inspection and monitoring methods,
promoting corrosion knowledge management, sustaining and enhancing corrosion
prevention improvement, development and deployment of new and existing technologies,
corrosion talent development and training, integration with other disciplines such as
process, operations, inspection, maintenance and loss prevention.
Damage mechanisms (DM): Types of corrosion and materials degradation a corrosion
loop may be susceptible to potentially or during operations.
Dashboard: Visual display of performance metrics or KPIs with color-codes and drill-
down features.
Key Performance Indicator (KPI): A measure associated with a specific activity;
could be Financial, Internal or Result. Could be categorized as Leading or Lagging.
Management of Change (MOC): A systematic process aimed at evaluating and
documenting all plant changes and their impact on plant safety, integrity and profitability.
Plant Assessment: Engineering review or condition assessment of a specific plant
covering operations, inspection, corrosion, maintenance, pressure vessels, piping, fire
equipment, electrical and reliability practices.
Plant Integrity Window (PIW): A chemical or physical plant parameter with
established minimum and maximum values; may be categorized as Safety PIW,
Operational PIW or Integrity PIW.
Safety Management System (SMS): Corporate document aimed at safeguarding
company assets, personnel safety and the environment throughout the full life cycle;
based on 11 Elements (including Asset Integrity-Element 5) with objectives, expectations
and deliverables
Work Process (WP): Series of activities or steps aimed at achieving a set objective,
with input and output.
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 7 of 52
Part 1: Basic Requirements and Deployment Activities
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 8 of 52
1 Introduction
The Corrosion Management Program (CMP) Manual is structured in three (3) parts as
follows:
● Part 1: Basic Requirements and Deployment Activities
● Part 2: “Manage Corrosion” Work Processes
● Part 3: Damage Mechanism Narratives
1.1 Purpose
The purpose of this manual is to provide guidance to Saudi Aramco operating
organizations and engineers involved in the development and implementation of
corrosion management systems for upstream and downstream facilities.
Effective corrosion management shall result in:
● Improved plant integrity and safety
● Reduced corrosion failures
● Maximum plant availability
● Optimized mitigation, monitoring and inspection expenditure
● Reduced loss profit opportunity
1.2 Scope
This manual addresses both upstream and downstream operational facilities.
In this document, corrosion management is defined as the part of the overall
management system that develops, implements, reviews and maintains the
corrosion management policy and strategy. The policy provides a structured
framework for corrosion risk identification and the development of appropriate
cost-effective mitigation solutions.
Corrosion management addresses the management of threats to mechanical
integrity arising from mechanisms of material degradation, corrosion and failure,
including but not limited to:
● Mechanical and metallurgical failure mechanisms – graphitization,
spheroidization, temper embrittlement, creep, thermal fatigue, vibration-
induced cracking, sigma phase embrittlement, dissimilar metal weld
cracking, brittle fracture, etc.
● Uniform or localized thinning – galvanic corrosion, caustic corrosion, CO2
corrosion, amine corrosion, corrosion-under-insulation, microbiologically-
induced corrosion, etc.
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 9 of 52
● High temperature corrosion – sulfidic corrosion, oxidation, carburization,
metal dusting, fuel ash corrosion, etc.
● Environmental-assisted cracking – chloride/caustic/amine/ammonia stress
corrosion cracking, corrosion fatigue, etc.
These mechanisms are all covered in the damage mechanism narratives given in
Part 3 of this manual.
Importantly, CMP is considered proactive and risk-based. The proactive nature of
this program lies in addressing early signs of mechanisms leading to corrosion or
partial loss of function of the asset. Accordingly, corrosion prediction and
prevention via leading proactive measures or integrity operating windows is
paramount to preventing critical failures (Figure 1).
Figure 1 - Failure Classification
1.3 CMP Framework
It is important that corrosion management activities are carried out within a
structured approach that is visible, understood by all parties and where roles and
responsibilities are clearly defined. This manual focuses on corrosion
management in the “operate & maintain” phase of the life cycle. However, it also
acknowledges the importance of the design phase in planning and implementing
corrosion risk control barriers.
The management system model advocated in this manual (Figure 2) is based on
the Health and Safety Executive (HSE) model for the management of safety-
related activity.
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 10 of 52
The essential elements of this framework are:
1. Clear Policies and Objectives of the organization (Saudi Aramco)
2. Organizational Structure and Responsibilities of managers and staff
within the organization (Central Engineering or Proponent)
3. Corrosion Risk Assessment and Planning of activities according to risk
4. Implementation and Analysis of planned activity and its reported outcome
5. Measure System Performance against pre-determined criteria or targets
6. Systematic and Regular Review of system performance; this provides a
feedback loop to improve performance via making appropriate adjustments to
policies, objectives, organizational structure/responsibilities, planning,
implementation/ analysis or performance measures
The first five steps are concerned with the setting up a basic management system,
whilst reviews, the sixth step, forms part of a verification system. These elements
are addressed in detail in the subsequent sections.
Policy &Strategies
Organization& Responsibilities
Planning& Implementation
PerformanceMeasurement
Review ofPerformance
Risk Assessment
SatisfactoryPerformance
Review, CorrectUpdate
Successful Corrosion Management
Yes No
Best PracticesEngineering StandardsIndustry Standards
AccountabilitiesCompetencyTraining
Likelihood & ConsequencesCriticality
Inspection & Maintenance PlansCorrosion Management Strategy
Monitor TrendsAnomaly TrackingKey Performance Indicators
Managementof Change
Review
Figure 2 - Corrosion Management Program (CMP) Framework
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 11 of 52
2 Policy and Strategies
Effective policy and strategies set a clear direction for the Saudi Aramco organization to
follow, aiming at the elimination of corrosion failures and an improvement of mechanical
integrity and safety. CMP policy reflects the vision of Saudi Aramco and a genuine
commitment to action. Strategies provide the means by which the policy is implemented.
Policy and strategies should be widely communicated in awareness campaigns.
2.1 Saudi Aramco Corrosion Management Policy
Saudi Aramco is committed to preventing and managing corrosion of its plants
and assets to ensure that the Company's vision is to remain the most reliable
supplier of energy to the World and a steward of safety and the environment.
The management of corrosion shall be led by a formalized strategy resulting in an
integrated Corrosion Management Program (CMP). Saudi Aramco will deploy
the most effective and modern predictive, diagnostic and data management
techniques to ensure that the risks associated with the corrosion failure of plant
are fully understood and maintained As Low As Reasonably Practicable
(ALARP) throughout the asset life-cycle.
To achieve this, Saudi Aramco shall ensure that:
● The roles and responsibilities associated with planning, implementing,
maintaining and improving corrosion management are clearly defined.
● The competencies required to perform these roles and discharge these
responsibilities are defined and the staff fulfilling these roles are fully
competent and fully aware of their responsibilities.
● The risks associated with the corrosion failure of plant are identified and
managed so as to remain ALARP.
● Assets are designed, procured, fabricated, installed and commissioned in
accordance with approved processes, specifications and standards.
● The handover of new plant to operations is effectively managed through
Management of Change (MOC) processes, including the provision of
appropriate documentation and training requirements required to operate
the plant safely and effectively.
● Plant assets are operated within their design envelope and proactive
detection technologies are utilized to ensure that any deterioration or non-
compliance that could affect the integrity of assets are reported, assessed
and actions taken.
● Activities designed to manage threats to the corrosion of assets are not
unduly compromised by cost, scheduling or production targets.
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 12 of 52
● Management of Change processes are used so that corrosion risks
associated with any changes (e.g., hardware, software, processes,
procedures or manning levels etc.) that might affect the integrity of the
assets are assessed and approved prior to implementation.
● Key Performance Indicators (KPI’s) are developed to model and measure
the effectiveness of the corrosion management processes and facilitate the
implementation of proactive corrosion management methodologies.
● All corrosion failures, incidents or near misses related to corrosion are
thoroughly investigated to determine root causes and any lessons learnt are
communicated across the Company.
● Contractors and manufacturers/suppliers are regularly surveyed and
selected so that they share our corrosion management program goals and
can perform their assigned duties and tasks safely and effectively.
● Corrosion management processes are subject to regular reviews.
● Corrosion data visualization and knowledge management systems are
implemented to allow for both continuous improvement and effective
knowledge sharing.
2.2 Strategies
Most practices and procedures employed for the control of corrosion in
operational facilities involve proven technology that is generally accepted
worldwide. These can be considered as the tactical aspects or corrosion control
options:
● Materials Selection (steels, corrosion resistant alloys, non-metallics)
● Chemical Treatments (caustic, neutralizers, inhibitors, biocides, cleaning)
● Coatings (metallic, non-metallic and organic paints)
● Cathodic Protection (galvanic or impressed current)
● Process & Environmental Control (capacity, flaring, waste water treatment)
● Corrosion Monitoring (coupons, probes, process variables)
Other tactical processes include Failure Analysis to identify root causes of asset
deficiencies and modes of failure, with the objective to prevent failure recurrence.
In addition, risk assessment methods such as Risk-Based Inspection (RBI) are
aimed at inspection optimization based on corrosion risk levels. This practice is
undertaken on new builds to identify corrosion threats and formulate corrosion
mitigation barriers. It is also undertaken on existing facilities for inspection
optimization and risk reduction. Other special assessment methods include
Fitness-For-Service (FFS) and Remaining Life Assessment (RLA); these methods
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 13 of 52
are deployed to assess metal loss, crack/defect significance and predict remaining
useful life of assets operating under time-dependent damage mechanisms.
All above options are used either singly or in combination; the selection depends
on the specific application (the structure/materials & loads, service life) and the
corrosivity of local environments (crude slate, atmosphere, seawater, process
fluids, etc.).
Saudi Aramco corrosion management strategies are mapped out in multi-level
work processes, namely, strategic, tactical, elemental and atomic. The processes
for the “operate & maintain” phase are given in Part 2. Processes for other phases
of the asset life cycle, i.e., design, procurement & construction, and
decommissioning are also included in Part 3 of this manual for appropriate usage.
In addition to the above corrosion control strategies, Saudi Aramco is committed to
ensure that talent development shall play a key role in CMP deployment.
Accordingly, competency maps (CMaps) and career path plans have been
developed to ensure that central and plant corrosion engineers benefit from a rich
program of training, coaching and mentoring to reach specialist development status
after a period of approximately 10 years; this is achieved through the Specialist
Development Program (SDP). Training is regularly offered through the company’s
Professional Engineering Development Division (PEDD). The Corrosion
Engineering Development Program (COE-300) is an all-in corrosion course offered
to Plant Engineers over a period of three months.
Saudi Aramco continuously encourages engineers to obtain certification with
reputable materials and corrosion bodies such as NACE International and
ASM International. Accordingly, engineers are routinely enrolled to obtain
appropriate certifications, as follows:
● Corrosion Specialist - NACE
● Corrosion Senior Technologist - NACE
● Internal Corrosion Technologist - NACE
● Corrosion Technologist - NACE
● Chemical Treatment Specialist - NACE
● Material Selection/Design Specialist - NACE
● Protective Coatings Specialist - NACE/SSPC
● Protective Coating Technologist - NACE/SSPC
● Protective Coating Inspector - NACE/SSPC
● Cathodic Protection Specialist - NACE
● Cathodic Protection Technologist - NACE
● Cathodic Protection Technician - NACE
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 14 of 52
● Cathodic Protection Tester - NACE
● Material Selection and Design - ASM
● Failure Analysis - ASM
● Heat Treatment - ASM
● Non Metallic Testing and Characterization - ASM
● Metallic Coatings - ASM
● Metallography - ASM
● Welding - AWS/TWI(CSWIP)
Knowledge sharing and knowledge management complement the above training
and development activities. Saudi Aramco’s knowledge sharing portal “ShareK”
provides a platform for Communities of Practice (CoP) to discuss and share
corrosion issues and company major corrosion challenges. ShareK also serves as
repository or library for corrosion technical literature, reports and presentation
material. Engineers have also access to multiple electronic materials and
corrosion resources through the company’s Technical Information Center (TIC),
e.g., SAI Global, ASM online, Corrosion Source, Energy Institute, Emerald,
Engineering Encyclopedia, Metalinfo, ScienceDirect, OnePetro; and through
corporate memberships with TWI, EPRI and PRCI. Technical exchange meetings
at local and regional level are also routinely held to allow engineers from central
engineering and plants to network and exchange ideas.
Corrosion technology development is another mature strategy employed at Saudi
Aramco through the company’s technology program. Engineers are encouraged to
develop Technology Items (TIs) via local research and development or via
partnering with outside organizations through single or Joint Industry Projects
(JIPs).
To complement the above strategies, a focus on company major corrosion
challenges is a must. Chronic corrosion issues pausing disruption risks to plant
operations or safety shall be addressed as a matter of priority and
recommendations developed to eliminate these problems and prevent recurrence.
3 Organization
3.1 Introduction
Effective management structure and corrosion management practices are essential
requirements for the delivery of policy and strategies. The establishment of a
vibrant “corrosion culture” invariably leads to improved asset integrity and
personnel safety.
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 15 of 52
The management of corrosion is a concern which extends beyond the
responsibilities of corrosion and materials engineers. Whilst they should provide
advice during both the design and operational phases, they are dependent upon the
co-operation of other disciplines if an installation’s projected design life is to be
achieved. The model below (Figure 3) provides a framework for that co-operation
and for optimizing the contribution the corrosion and materials engineers make to
an organization.
Figure 3 - Corrosion Information Flow in Projects
3.2 Deployment Structure
CMP deployment to operating facilities shall be structured along the guidelines
given below. A CMP deployment organization chart is given in Figure 4 below.
Subject Matter Experts (SMEs) and engineers from the following disciplines shall
be involved, as appropriate:
Central Engineering
● Corrosion
● Materials & Welding
● Coatings
● Chemical Treatment
● Cathodic Protection
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 16 of 52
Proponent
● Corrosion
● Inspection / OSI
● Risk Based Inspection Coordination
● Process & Operations
● Technical Support
Corrosion Management Program (CMP) Champion
(CSD/ME&CCD Division Head)
CMP Team Leader
Corrosion Specialist
Materials & Welding Specialist
Coatings Specialist
Chemical & Water Treatment Specialist
Cathodic Protection Specialist
Plant CMP Leader
Plant Corrosion Engineer
Plant Inspection Engineer/OSI Coordinator
Plant RBI Coordinator
Plant Process/ Operations Engineer
Plant Technical Support Engineer
Figure 4 - CMP Deployment Organization Structure
3.3 Roles and Responsibilities
Central Engineering CMP Team:
● CMP Team Leader – Reports to CMP Champion, tasked with overall
CMP deployment coordination, execution and single point of contact
proponent champion; responsible for delivery of CCD and CMP training
to facility.
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 17 of 52
● Corrosion Specialist (may also play the role of CMP Team Leader) –
Reports to CMP Team Leader; tasked with addressing all corrosion issues;
works with all other engineers on materials / corrosion / welding / coating
/ chemical & water treatment / cathodic protection / inspection / operations
issues, development of corrosion loops, undertaking of plant assessment
and development of recommendations, PIWs, KPIs and dashboard,
customization of damage mechanism narratives and development of CCD.
● Materials & Welding Specialist (may also play the role of CMP Team
Leader) – Reports to CMP Team Leader; tasked with addressing all
materials & welding issues; works closely with central engineering
corrosion specialist and proponent representatives on matters listed in
3.3.2 above.
● Coatings Specialist – Reports to CMP Team Leader; tasked with
addressing all coating issues; works closely with central engineering
corrosion specialist and proponents representatives on corrosion /
chemical treatment / inspection / maintenance / operations issues.
● Chemical & Water Treatment Specialist – Reports to CMP Team
Leader; tasked with addressing all chemical cleaning and water treatment
issues; works closely with central engineering corrosion specialist and
proponent representatives on corrosion / chemical & water treatment /
inspection / maintenance / operations issues.
● Cathodic Protection Specialist – Reports to CMP Team Leader; tasked
with addressing all cathodic protection issues; works closely with central
engineering corrosion specialist and proponent representatives on
corrosion / inspection / maintenance / operations issues.
Proponent:
● Plant CMP Leader – Reports to Plant CMP Champion and acts as the
single point of contact, tasked with coordination of all CMP deployment
activities in conjunction with the Central Engineering CMP Team Leader;
responsible for delivery of all plant information/data/logistics to Central
Engineering CMP Team Leader and execution/self-review of future CMP
deployment.
● Plant Corrosion Engineer (may also play the role of Plant CMP Leader)
– Reports to Plant CMP Leader; tasked with provision of updated
corrosion documentation and data, development of major corrosion
challenges list, corrosion historical review, joint development of corrosion
recommendations with the central engineering corrosion specialist,
development of PIWs/KPIs/dashboard, participation in corrosion loop
development and RBI study, customization of damage mechanism
narratives, review of CCD and deployment of CMP to other units.
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 18 of 52
● Plant Inspection Engineer/OSI Coordinator – Reports to Plant CMP
Leader; tasked with compiling inspection history review, provision of
updated equipment and piping inspection/OSI data, participation in RBI
study and review of CCD.
● Plant RBI Coordinator – Reports to Plant CMP Leader; tasked with
provision of RBI data and results to the Plant CMP Leader.
● Plant Process/Operations Engineer – Reports to Plant CMP Leader;
tasked with provision with all process information, access to PI system,
participation in corrosion loop development, development of
PIWs/KPIs/Dashboard and review of CCD.
● Plant Technical Support Engineer – Reports to Plant CMP Leader;
tasked with provision of maintenance history, welding repair
recommendations and T&I history.
4 Deployment Methodology
CMP deployment must follow the “Plan-Do-Check-Act” approach so that lessons learned
are captured/exploited and continuous improvement achieved at subsequent deployments.
For this, the corporate CMP Database is designed to capture major corrosion challenges,
potential damage mechanisms, performance measures, corrosion management strategies,
technologies and recommendations. This database also serves as a tracking system for
reviews and recommendation implementation.
Deployment activities are listed below (Figure 7).
4.1 Pre-Deployment
● Appoint team leader
● Form a team
● Assign roles and responsibilities
● Develop scope of work and timeline (Example Gantt chart is given in Figure 5)
● Plan logistics
● Request plant information (Appendix 1)
o Asset list; critical equipment list
o Inspection history, post-T&I reports
o Process Description, PFDs, P&IDs
o Material Selection Diagrams (MSDs), corrosion circuits, corrosion
monitoring reports
o Chemical injection/treatment programs, controls and historical
performance data from chemical alliance
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 19 of 52
o Internal/external/consultant reports
o Incident investigation, failure/root cause analysis reports
o Risk-Based Inspection reports
o Life assessment reports
o Corrosion review reports
● Conduct CMP Introductory Presentation
Prior to deployment, the CMP Team Leader shall conduct an awareness
presentation, covering the following:
o CMP Objectives
o CMP Methodology and Benefits
o CMP Strategies
o CMP Framework
o CMP Deliverable – Unit-specific Corrosion Control Document
o Deployment Plan
o Proponent Requirements
o CMP Deployment Timeline
4.2 Deployment
4.2.1 Work Process Gap Analysis
Perform “Operate & Maintain” work process gap analysis, focusing on:
● Procedures
● Competency
● Roles & Responsibilities
This activity shall contrast existing corrosion management work processes
with those described in Part 2 of this CMP Manual. This exercise shall
involve the participation of Central Engineering and Proponent Engineers
in a workshop discussing all “operate & maintain” work processes and
documenting gaps that may exist at the facility. The deliverable from this
activity shall list all gaps identified and an action plan to address these
gaps. These gaps may consist of procedural rectifications, tools &
technology implementation, performance measurement or human
resources development.
It is noted that some of the “manage corrosion” work processes for
“operate & maintain” include the following:
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 20 of 52
● Develop corrosion management strategy
● Perform corrosion risk assessment
● Plan for process stream monitoring
● Develop corrosion control strategy
● Develop corrosion monitoring strategy
The full work processes are given in process maps in Part 2 of this CMP
Manual.
4.2.2 Plant Information Review
Review plant information, focusing on:
● Major corrosion challenges
● Inspection/Repair/Replacement failure history
● Incident investigations
● Process upsets
● Process variables
● Operational practices
4.2.3 Plant Assessment
Perform plant assessment, focusing on major corrosion challenges,
locations exhibiting corrosion classes 0 and 1 (SAEP-1135), chronic
fouling areas and equipment/piping nearing their end of life. The
following lists key relevant items to check:
● Corrosion monitoring systems, performance reports
● Changes in process operating parameters, capacities and any future
plans regarding feed quality
● Maintenance and reliability reports, bad actor lists, failure reports and
other statistics including replacement frequencies
● Comparative analysis between operating and design parameters
(temperature, pressure, flow and composition, etc.)
● Coatings and non-metallics use and performance
● Cathodic Protection performance
This exercise shall also include trending of critical operational/integrity
variables such as:
● metal temperatures
● process temperatures/pressures/delta T/delta P
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 21 of 52
● flow rates
● water wash rates
● corrosion inhibitor dosage rates
● corrosion/erosion/thinning rates
● excess oxygen for fired equipment
● Stream analysis (pH, H2S, CO2, NH3, Cl-, O2, pH2, salts, etc.)
The deliverable from this plant assessment task shall include appropriate
recommendations addressing proactively all corrosion, materials
degradation and fouling issues encountered in this exercise.
Figure 5 - Example Gantt Chart for a CMP Deployment
4.2.4 Corrosion Risk Assessment
In this CMP Manual, risk and criticality are used interchangeably.
Risk assessment is an integral part of CMP. This permits the prioritization
of assets based on their criticality levels and the development of
appropriate integrity strategies. In assessing risks, the following aspects
shall be considered:
● Safety
● Financial
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 22 of 52
● Environmental
● Reputation
Two methods are proposed to address risk assessment:
● Apply RBI (Quantitative) study results, if available, or
● Apply Loss Prevention Department Qualitative Risk Assessment
Guide No. 02-002-2010. It is noted that this guide is qualitative in
nature and as such considerable corrosion expertise is required to
adequately identify probability of corrosion failure.
A generic 5x5 risk matrix is shown in Figure 6 below. Tables 1 and 2
provide the definition of likelihood and consequence/severity required to
estimate the risks. Table 1 provides guidance for frequency estimation for
each identified hazard that will be based historical data as well as
engineering judgment. Table 2 provides guidance for consequence
estimation of each identified hazard, in terms of impact on people (safety),
environment, financial, reputation, all estimated using engineering
judgment. Once the frequency and consequence are analyzed, a risk level
can be obtained for each hazard, by plotting the frequency and
consequence in the risk matrix. This risk can be compared against risk
criteria given in Table 3, so that its tolerability can be judged.
Figure 6 - Risk Matrix
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 23 of 52
Table 1 - Likelihood / Frequency
Table 2 - Severity / Consequence
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 24 of 52
Table 3 - Risk / Tolerability Criteria (applies to Risk Matrix)
4.2.5 Corrosion Loops (Appendix 2)
Develop corrosion loops as follows:
● Review process, operating/design/start-up/shutdown/catalyst
regeneration/upset conditions, contaminants
● Identify the materials of construction
● Identify active and potential damage mechanisms
● Develop corrosion loops
4.2.6 Plant Integrity Windows (PIWs)
Develop PIWs focusing on mechanical and chemical variables affecting
corrosion/material degradation, e.g., metal temperature, velocity,
differential pressure, pH, contaminant or corrodent concentration
(chlorides, H2S, CO2, caustic, oxygen, ammonium chloride, ammonium
bisulfide, ammonium chloride, hydrogen partial pressure, etc.). Attention
shall also be given to operating conditions at start-up, shutdown or end of
run scenarios which may be life limiting. API RP 584 provides guidance
on PIW or Integrity Operating Windows (IOWs).
4.2.7 Key Performance Indicators (KPIs)
Develop KPIs relevant to corrosion performance measurement, focusing
on number of critical failures, Thickness Measurement Locations (TMLs)
showing Corrosion Classes 0 and 1, lost profit opportunity,
4.2.8 Damage Mechanism Narratives
The active and potential damage mechanisms derived during the
Corrosion Loop workshop require customization. For this, the generic
damage mechanism narratives given in Part 3 of this CMP Manual shall be
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 25 of 52
used as a basis but modified to address specific asset issues such as
material of construction, corrosion control measures, inspection /
monitoring techniques, KPIs and PIWs.
4.2.9 CMP Dashboard
The CMP Dashboard is a visual display of the KPIs and PIWs showing
targets, compliance, impact of deviations and actions to rectify these
deviations and restore integrity. Ideally, three CMP Dashboards shall be
developed as follows:
● Vice President Dashboard (Highest Level)
● Manager Dashboard (High Level)
● Superintendent Dashboard (Medium Level)
● Supervisor and Engineer Dashboard (Detailed Level)
Examples of previously developed CMP Dashboards are given in
Tables 4 – 7. They show the compliance/deviation of 4 parallel gas
treating (GT) units.
4.2.10 Corrosion Management Strategies and Technologies
Appropriate corrosion management strategies, beyond those already
existing and practiced at the plant, shall be identified together with any
new or existing technologies that will make an impact on the proactive
corrosion management process at the facility. These may include, but not
limited to, corrosion monitoring, corrosion protection (organic coating,
strip lining, weld overlay, thermal spray coating, cathodic protection),
corrosion prediction (software), life assessment, material selection,
statistical analysis, etc.
4.2.11 Closure Presentation
CMP deployment activities at proponent site shall conclude with a closure
technical presentation highlighting to plant management preliminary
findings and the following key points:
● CMP methodology
● Work Process gap analysis findings
● Major historical corrosion challenges
● Key corrosion threats, identified via the corrosion loop workshop
● Risk assessment findings
● Preliminary PIWs/KPIs
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 26 of 52
● Corrosion management strategies & technologies
● Path forward (remaining activities/assessments, action plan to replicate
CMP on other units at facility (including prioritization criteria)
4.2.12 Draft Corrosion Control Document (CCD)
A draft CCD shall be developed and submitted for plant proponent review.
4.2.13 Final CCD - Main CMP Deliverable
Upon receipt of proponent review comments from the draft CCD, a final
CCD shall be developed and submitted to proponent as main CMP
deliverable. This deliverable shall then be posted on Saudi Aramco
Standards website for access within the company and future reference.
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 27 of 52
Figure 7 - CMP Deployment Chart
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 28 of 52
Table 4 - Vice President CMP Dashboard VP Dashboard
# Performance
MeasureTimescale Target Method
GT#
1
GT#
2
GT#
3
GT#
4Deviation Impact
1
% of RBI studies
completed compared
to plan
Yearly 100% Operating Plan Integrity, Safety
2
Lost Profit
Opportunity (LPO)
resulting from
Corrosion Failures
Yearly 0Manufacturing &
PlanningProfitability
Table 5 - Manager CMP Dashboard Manager Dashboard
# Performance
MeasureTimescale Target Method
GT#
1
GT#
2
GT#
3
GT#
4Deviation Impact
1
% of RBI studies
completed compared
to plan
Yearly 100% Operating Plan Integrity, Safety
2
Lost Profit
Opportunity (from
corrosion failures)
($MM)
Semi-
annually 0
Manufacturing &
Planning Profitability
3Corrosion Failures
(critical) (#)
Semi-
annually 0 Inspection Report
Mechanical Integrity, Plant
Utilization, Plant Availability
Table 6 - Superintendent CMP Dashboard Superintendent Dashboard
# Performance
MeasureTimescale Target Method
GT#
1
GT#
2
GT#
3
GT#
4Deviation Impact
1
% of RBI studies
completed compared
to plan
Yearly 100% Operating Plan Integrity, Safety
2
Lost Profit
Opportunity (from
corrosion failures)
($MM)
Semi-
annually 0
Manufacturing &
Planning Profitability
3Corrosion Failures
(critical) (#)
Semi-
annually 0 Inspection Report
Mechanical Integrity, Plant
Utilization, Plant Availability
4PIWs within Limits
(%)Daily 100 PIW Dashboard PIW Dashboard
5TMLs > 5MPY (Class
0, 1, 2) (%)Quarterly 0 UT Scanning
Erosion-Corrosion, Amine
Corrosion, General
Corrosion, Under-Deposit
Corrosion, Sour Water
Corrosion
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 29 of 52
Table 7 - Supervisor/Engineer CMP Dashboard Supervisor/Engineer Dashboard
# Performance
MeasureTimescale Target Method
GT#
1
GT#
2
GT#
3
GT#
4Deviation Impact
1
% of RBI studies
completed compared
to plan
Yearly 100% Operating Plan Integrity, Safety
2
Lost Profit
Opportunity (from
corrosion failures)
($MM)
Semi-
annually 0
Manufacturing &
Planning Profitability
3Corrosion Failures
(critical) (#)
Semi-
annually 0 Inspection Report
Mechanical Integrity, Plant
Utilization, Plant Availability
4PIWs within Limits
(%)Daily 100 PIW Dashboard PIW Dashboard
5TMLs > 5MPY (Class
0, 1, 2) (%)Quarterly 0 UT Scanning
Erosion-Corrosion, Amine
Corrosion, General
Corrosion, Under-Deposit
Corrosion, Sour Water
Corrosion
6
Sour Feed Gas
Throughput
(MMSCFD)
Daily550
(max)Flow Meter Erosion-Corrosion
7Lean DGA Strength
(%)Monthly 50
Acid-Base
TitrationAmine Corrosion
8Rich DGA Strength
(%)Monthly 50
Acid-Base
TitrationAmine Corrosion
9Lean DGA Acid Gas
Loading (mole/mole)Monthly 0.07
Amine Corrosion, Amine
SCC
10Rich DGA Acid Gas
Loading (mole/mole)Monthly 0.4
Amine Corrosion, Amine
SCC
11 Oxygen in DGA (ppb) Monthly 5 Oxygen Sensor Amine Corrosion
12 pH of Lean DGA Monthly 9.5 pH Meter Amine Corrosion
(1) Mainly Sea Water Chemical Treatment
Significant (negative) deviation from target
Moderate (negative) deviation from target
Compliance with or exceeds target
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 30 of 52
5 Review
5.1 Performance Review
Performance review refers to the overall review of the Corrosion Management
Program. Systematic reviews of performance based on data from corrosion
monitoring and other enablers permits Saudi Aramco to continuously improve the
CMP program via constant development of the policy, strategies and work
processes. This will also ensure compliance with the changing business and
operational plans and changing production requirements.
Facilities, via the Plant CMP Leader, are required to conduct periodic (monthly,
quarterly, semi-annually or annually) performance reviews on their facilities.
The scope and frequency of this performance review shall be as follows:
● Performance reviews shall involve all key players, including contractors or
chemical suppliers
● Performance reviews shall include:
o Procedures and work processes
o PIWs deviation and corrective actions
o KPIs deviations and corrective actions
o Talent development/competency/training assessment
o Technology deployment/Corrosion management systems
o Asset condition/integrity
o Documentation and knowledge management
● The benefits of new techniques or technology shall also be considered
● Performance review report shall include all good performance and promote
good practices.
● Performance review report shall include all corrective actions for the program
and feedback into the strategy.
● Performance review report shall be shared with all participants in the
corrosion management activity both down the line and upwards to
management within the facility. The plant manager shall receive a copy of the
report or an executive summary.
● Performance review report shall also be sent to Central Engineering CMP Team
Champion at least 1 month prior to the Central Engineering CMP Review.
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 31 of 52
5.2 Self Review
5.2.1 Perform CMP self-review after 2 years from the first deployment and
every 2 years thereafter, using check-list (Appendix 3). This self-review
shall be carried out by the plant proponent at least 2-months prior to the
Central Engineering review, focusing on:
● CMP Dashboard (KPIs/PIWs) deviation and corrective actions
i. Asset condition/integrity
ii. Proactive performance detection
iii. Plant availability, performance and utilization
● Technology deployment
● Corrosion Human Resource (HR) review
● Documentation and knowledge management
5.2.2 Perform Central Engineering review, focusing on the above items
5.2.3 Issue Central Engineering review report
5.2.4 Update Central Engineering CMP Database
Note: For CMPs deployed locally by facilities themselves, the self-review shall be carried by the plant proponent and the review by Central Engineering.
6 Central Engineering Review (Appendix 3)
The purpose of the reviews is to ensure that the CMP is efficient, effective and reliable,
and that the work processes and activities are being implemented in accordance with the
procedures. Review findings shall be used to improve the CMP and, where appropriate
the corrosion management strategies.
6.1 The scope of the reviews should provide:
● Assurance that the CMP includes all essential elements as stipulated in this
CMP Manual
● Assurance that the implemented activities provide suitable barriers to the
corrosion threats and suitable monitoring to measure performance
● Assurance that the CMP activities are implemented in accordance with their
documented procedures, and
● Input into reviews of performance.
6.2 Reviews shall be carried out in accordance with the checklist given in Appendix 3
and on the basis of objective evidence of compliance.
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 32 of 52
6.3 Both internal and contractor led activity, e.g., chemical vendor, should be subject
to this review.
6.4 Self-reviews shall be carried out by the Plant CMP Leader or plant corrosion
engineer.
6.5 Reviews shall be carried by the Central Engineering CMP Team Leader or
Corrosion Subject Matter Expert assisted by another engineer, both with
competence in review practice and understanding of corrosion management
strategies.
6.6 The Central Engineering CMP review team shall be independent of both
operational and functional teams that are directly involved in implementing the
CMP for the facility concerned.
6.7 Reviews shall be carried out on a planned schedule developed by Central
Engineering CMP Champion, as follows:
● Reviews shall be carried out every 2 years
● Self-reviews shall also be carried out every 2 years, 2 months prior to the
review by Central Engineering.
6.8 Central Engineering may bring forward a review if there is evidence of serious
non-compliance that poses a threat to the effectiveness of the CMP and safety.
In the event that non-compliance is detected, corrective action shall be agreed
with the plant CMP leader or corrosion engineer and their management.
6.9 Review reports shall be made available to the facility management and Central
Engineering CMP Champion, his management, i.e., in this case Consulting
Services Department (CSD) Manager and supervisors of the review team.
6.10 Corrective action shall be recorded in the Central Engineering CMP Database that
enables implementation, overdue actions and close out to be identified and
tracked. Facility management and those responsible for actions shall receive
regular reports from the Central Engineering CMP Champion on progress towards
close out.
Revision Summary
30 March 2013 New Saudi Aramco Best Practice.
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 33 of 52
Appendix 1 - Plant Information Required
A1. Materials, Welding and Corrosion
Periodic Corrosion Control and Chemical Treatment Vendor Reports
Corrosion Monitoring Locations/Data
Fitness for Service / Life Assessment Study Reports
Listing of PIW or Integrity Operating Windows (IOW) with targets
Corrosion, Cracking and Fouling Problems
Historical CP Surveys
Coatings Performance and Repair
Boiler Condition Assessment reports
Corrosion loops, annotated with damage mechanisms
Leakage history
Injection point program
Corrosion Under Insulation (CUI) strategy and plan
List of past failures associated with materials, welding or corrosion
A2. Inspection Requirements
Critical Piping list
List of Piping class
Equipment inspection history and piping replacement
Documentation for all inspection programs, dead legs, small bore piping/nipples and
drains, corrosion under insulation
Access to SAIF & corrosion isometrics drawings
Inspection unit audit reports
Post/Latest T&I reports
A3. Process Engineering
Operating Manuals and process description
Design feed characteristics
Product specifications and properties
Material and Heat Balances
Battery limit conditions
Process upset history
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 34 of 52
A4. General
Process Flow Diagrams (PFD), P&IDs
Plant Equipment List
Equipment technical information, SIS, design drawings, as built drawings
Complete list of changes made in system within the past 5-10 years.
Failure Analysis Reports
Incident Investigations and near miss reports
Risk Based Inspection/Assessments Studies
Due Diligence Reports
Engineering Service Agreement Reports
Insurance Survey Reports
Integrity and Reliability Studies
Bad Actor/Problem List
Critical Equipment Plans
Previous assessment reports
Historical Capacity/Process Changes
Previous engineering recommendations and status of implementation
Loss Prevention Compliance Reviews
Safety Management System Reports
HAZOP Studies
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 35 of 52
Appendix 2 - Corrosion Loops Development
A1. Definition
A corrosion loop (CL) is a section of a plant defined mainly on the basis of:
similar process conditions or
materials of construction or
active/potential damage mechanisms
Thus, a CL may contain different materials of construction and operational conditions, but
common damage mechanisms.
On the other hand, a damage mechanism (DM) is a type of corrosion and materials
degradation a CL may be susceptible to potentially or during operations. The damage
mechanisms (DMs), defined in Part 3 of this CMP Manual, are applicable to Saudi Aramco
are based on international standards but were customized to account for our operational
experiences and to include other Saudi Aramco upstream processes.
During CMP deployment, damage mechanisms are usually customized to account for
individual unit’s process streams, metallurgy, operating conditions, and inspection findings.
Since there are continuous efforts to enhance our plants’ safety and profitability, the
CLs/DMs need to be evergreen (continuously reviewed and updated) to account for these
changes to be effective.
A2. Use of Corrosion Loops
Corrosion Loops are used by Corrosion, Inspection and Process Engineers to assure
Mechanical/Operational integrity of the plant, more specifically to aid in developing and
deploying CMP. They are also used in Risk-Based Inspection (RBI), Plant Integrity
Windows (PIW), On-Stream Inspection (OSI) Optimization and Saudi Aramco Chemical
Optimization Program (SACOP).
A3. When is a Corrosion Loops developed?
Since 2009, the development of corrosion loops has been mandated, as part of new projects’
Corrosion Management Program, as mandated in SAES-L-133 “Corrosion Protection
Requirements for Pipelines, Piping and Process Equipment.” For facilities existing prior to
2009, Central Engineering CMP Team is developing/reviewing the corrosion loops in two
(2) units per year with the intent to train Plant CMP Team to develop the corrosion loops
and deploy CMP in other major units within their facilities.
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 36 of 52
A4. Corrosion Loop Development
Corrosion loops are considered the heart of CMP. The corrosion loop methodology is
implemented at Saudi Aramco to break down a plant into manageable sections that can also
be used in a RBI study, PIW development, OSI optimization and SACOP. For each
corrosion loop, information is provided addressing the following:
Brief process description (fluids, corrosives, temp., pressures, control measures, etc.)
Corrosion loop description
Major equipment and piping’s materials of construction
Listing of all applicable damage mechanisms
A corrosion loop diagram (CLD) is a color-coded drawing of the unit showing main process
streams, major equipment/piping, materials of construction, and applicable damage
mechanism. An example of a typical CLD is shown in Figure A1 below. For examples of
corrosion loops, please refer to already developed online Corrosion Control Documents
(SAER-6344, SAER-6353, SAER-6384, SAER-6403, and SAER-6416).
Figure A1 - Example Corrosion Loop Diagram (CLD)
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 37 of 52
Appendix 3 - CMP Checklist for Self and Central Engineering Reviews
This section details the process of self and central engineering reviews of the CMP. The purpose of
the reviews is to ensure that the CMP is efficient, effective and reliable, and that the work
processes and activities are being implemented in accordance with the procedures. Review findings
shall be used to improve the CMP and, where appropriate the corrosion management strategies.
A1. The scope of the reviews should provide:
Assurance that the CMP includes all essential elements as stipulated in this CMP
Manual
Assurance that the implemented activities provide suitable barriers to the corrosion
threats and suitable monitoring to measure performance
Assurance that the CMP activities are implemented in accordance with their
documented procedures, and
Input into reviews of performance.
A2. Reviews shall be carried out in accordance with the checklist given in Table A1 and on the
basis of objective evidence of compliance.
A3. Both internal and contractor led activity, e.g., chemical vendor, should be subject to this
review.
A4. Self-reviews shall be carried out by the plant CMP Leader or plant corrosion engineer.
A5. Reviews shall be carried by the Central Engineering CMP Team Leader or Corrosion
Subject Matter Expert assisted by another engineer, both with competence in review
practice and understanding of corrosion management strategies.
A6. The Central Engineering CMP review team shall be independent of both operational and
functional teams that are directly involved in implementing the CMP for the facility
concerned.
A7. Reviews shall be carried out on a planned schedule developed by Central Engineering CMP
Champion, as follows:
Reviews shall be carried out every 2 years
Self-reviews shall also be carried out every 2 years, 2 months prior to the review by
Central Engineering.
A8. Central Engineering may bring forward a review if there is evidence of serious non-
compliance that poses a threat to the effectiveness of the CMP and safety. In the event that
non-compliance is detected, corrective action shall be agreed with the plant CMP leader or
corrosion engineer and their management.
A9. Review reports shall be made available to the facility management and Central Engineering
CMP Champion, his management, i.e., in this case Consulting Services Department (CSD)
Manager and supervisors of the review team.
A10. Corrective action shall be recorded in the Central Engineering CMP Database that enables
implementation, overdue actions and close out to be identified and tracked. Facility
management and those responsible for actions shall receive regular reports from the Central
Engineering CMP Champion on progress towards close out.
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 38 of 52
Table A1 - CMP Review Checklist
Corrosion Management Program Review
Date: Facility: By:
Item Question Yes/No Supporting evidence/ references and comments
A. Corrosion Management System
A1 Is there a documented corrosion system based on the corporate strategic work process “Manage Corrosion” at operate & maintain phase of life cycle?
A2 Are you aware of the Corrosion Management Program policy defined in the CMP Manual?
B. Corrosion Competency
B1 Is there a trained and experienced corrosion engineer at your facility?
B2 Are you using a Competency Map (CMap) to monitor development, training and competency of your corrosion engineer?
B3 Does your facility have a plan of succession for your corrosion engineer?
C. Risk Assessment
C1 Has your facility developed corrosion loops and identified the damage mechanisms for all your plants/units?
C2 Does your facility perform corrosion risk assessments?
C2 Does your facility conduct investigations to identify root cause of all corrosion incidents?
C3 Has your facility adopted a risk-based inspection (RBI) program?
C4 Does your facility have a trained RBI facilitator?
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 39 of 52
Item Question Yes/No Supporting evidence/ references and comments
C5 Does your facility maintain a list of critical equipment and piping?
D. Corrosion Monitoring
D1 Does your facility have a Computerized Corrosion Management System (CMS)?
D2 Does your facility monitor corrosion using:
D3 Process variables (physical, chemical)?
D4 Probes?
D5 Coupons?
D6 In-Line Inspection/Smart Pigging?
D7 Does your facility maintain a fully functional SAIF system?
D8 Does your facility trend corrosion rate data and report this to management on a regular basis, e.g., monthly, quarterly, semi-annually, annually?
D9 Has your facility developed and makes use of Plant Integrity Windows to monitor corrosion management performance?
E. Chemical Treatment
E1 Does your facility monitor chemical and water injection rates and correlate with thinning/failure rates?
E2 Do you hold regular (weekly, monthly, quarterly, annually) review meetings with your Chemical Vendor?
E3 Are there KPIs targets defined for your Chemical Vendor?
E4 If yes, is your Chemical Vendor meeting the KPI targets?
E5 Do you investigate Chemical Vendor KPI target deviation?
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 40 of 52
Item Question Yes/No Supporting evidence/ references and comments
F. Corrosion Protection
F1 Does your facility have a coating (internal & external) and lining management program?
F2 Does your facility maintain a cathodic protection system?
G. Inspection
Does your facility maintain the following inspection programs:
G1 a. Injection Point?
G2 b. Corrosion under Insulation?
G3 c. Dead Leg?
G4 d. Positive Material Identification?
G5 e. Welding inspection?
G6 Does your facility apply the appropriate inspection method to the relevant damage mechanism?
G7 Are your Thickness Measurement Locations (TMLs) adequately defined and subject to periodic reviews?
H. Technology
H1 Do you think your facility has deployed sufficient/relevant technologies to manage corrosion?
I. Key Performance Indicators (KPIs)
I1 Has your facility developed and makes use of key performance indicators to manage corrosion failures?
J. Knowledge Management (KM)
J1 Is there a Corrosion Knowledge Management Program at your facility?
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 41 of 52
Item Question Yes/No Supporting evidence/ references and comments
J2 Does your facility share failures or good corrosion engineering practices with other facilities?
K. Documentation
K1 Does your facility maintain an electronic document management system (inspection reports, post-T&I reports, failure analysis reports, corrosion monitoring/trending, reports, etc.)?
Does your facility keep updated documents, as follows?
K2 a. SIS sheets
K3 b. PFDs
K4 c. P&IDs
L. Management of Change (MOC)
L1 Do you include all modifications (equipment, piping, water wash rate, inhibitor injection rate, welding repair, material changes, etc.) impacting corrosion in your MOC procedure?
M. Reviews
M1 Does your facility initiate a failure analysis request (to CSD) for all corrosion/mechanical failures?
M2 Does your facility keep an updated corrosion-related recommendation and technical alert tracking system?
M3 Does your facility perform internal periodic corrosion reviews to monitor compliance and eliminate corrosion failures?
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 42 of 52
Part 2: “Manage Corrosion” Work Processes
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 43 of 52
Introduction
This part describes the “Manage Corrosion” work processes. Although the current CMP
Manual addresses the “operate & maintain” phase of the asset life cycle (Attachment 3), work
processes for all phases of the life cycle are included in this part, i.e., Design, Procurement &
Construction, Decommissioning. These are presented here for completeness and future
reference. However, for the gap analysis task at commencement of CMP Deployment, only the
“operate & maintain” work processes (Attachment 3) shall be used.
It is noted that work processes were developed in 2010 by Saudi Aramco subject matter experts
in conjunction with an outside consultant. This exercise was undertaken to develop a corporate
asset integrity management system initially referred to as “Plant Integrity Assurance
Framework” (PIAF), then later changed to “Asset Performance Management” (APM).
Four strategic work processes were initially developed for the following disciplines, as depicted
below in Figure 8:
● Inspect Assets (Inspection) – SWP-04-03
● Maintain Assets (Maintenance & Reliability) – SWP-04-04
● Manage Corrosion (Materials & Corrosion) – SWP-04-05
● Manage Operations (Process/Operations) – SWP-04-06
For ease of understanding of the process maps in Attachments 1 – 4, the nomenclature and
descriptions used are illustrated in Figures 9 & 10.
Figure 8 - Strategic Work Processes
These work processes (highest level) are then decomposed into Tactical (TWP), Elemental
(EWP) and Atomic (AWP) (lowest level), as depicted in the process maps given in
Attachments 1 – 4. For systematic purposes, these processes are structured to follow the Plan-
Do-Check-Act format to ensure continuous improvement. These work processes will require
periodic updating to ensure alignment with other company work processes and business needs.
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 44 of 52
An example of work process gap analysis is shown in Table 8 for illustrative purposes. The gap
analysis workshop shall be carried at commencement of every CMP Deployment as follows:
1. “Operate & Maintain” work process maps are shown on screen projector in sequential
format.
2. Central Engineering CMP Team Leader describes the steps in the first work process to
CMP participants and asks Proponent CMP Leader and other plant participants whether
the subject work process or similar work process exists at the plant.
3. Plant participants provide comments and share their work process or procedures if these
exist.
4. Gaps are then identified and documented for inclusion in the CMP Corrosion Control
Document (CCD).
5. Recommendations are then developed to address these gaps and improve corrosion
management at the plant. These recommendations shall be documented in the CCD.
Note: Work processes may be categorized as either fully performed, partially performed or not performed.
Table 8 - Example Work Process Gap Analysis
Work Process Gap Identified at Plant X Gap Identified in CMP
EWP 04-05-03-01
Corrosion Data
Assessment
• This work process is not fully
reflected in RTR activities.
However, Failure Analysis is
performed by CSD; RCA is
performed by RTR
systematically as given by GI
using TAPROOT and
metallurgical examinations are
performed on a certain
percentage.
• The SARCOP quarterly review
considers interrelated factors and
unusual data
• There is no corporate procedure
reflecting this WP.
• There is a gap in procedure for
the quality checking of all data.
EWP 04-05-03-02
Corrosion
Management
Review
• There is no comprehensive
Corrosion Review but OSI data
is reviewed periodically
• Best practices should be
integrated with the PIW team
• The two WPs (Data Assessment
and Management Review)
should be combined.
• There is no standard for a
comprehensive corrosion
management review. (Though
there is a quarterly SARCOP
review).
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 45 of 52
Plant Integrity Assurance Framework
Map Key and Glossary
Work Process Symbols Work Process Hierarchy
Start / Finish
Process
Process Activity
Informed Addressee(s)
Action Addressee
Activity Number
Decision?
External
Process
Document
Record to be
maintained
2Off-page Reference for
Navigation
SAIF
SAIF Data Management
System
SAP
SAP Data Management
System
GWP
XX-XX-XX
Title
TWP
XX-XX-XX
Title
SWP
XX-XX-XX
Title
EWP
XX-XX-XX
Title
AWP
XX-XX-XX
Title
Global
Strategic
Tactical
Elemental
Atomic
STWP
XX-XX-XX
Title
SSWP
XX-XX
Title
SEWP
XX-XX-XX
Title
SAWP
XX-XX-XX
Title
Support Global Work
Process
Support Strategic Work
Process
Support Tactical Work
Process
Support Elemental Work
Processes
Support Atomic Work
Processes
SGWP
XX
Title
Figure 9 - Process Map Nomenclature
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 46 of 52
3
TWP-03-03-01: Plan Inspections during Procurement & Construction
SWP
03-03
Manage
Inspection
during P&C
TWP
03-03-02
Implement
Inspections
during P&C
EWP
03-03-01-01
Plan Inspection on
Supplier premises
during Fabrication
VID*/
PMT
1
EWP
03-03-01-02
Plan Inspection on
Receipt of Materials at
Aramco Construction/
Installation Site
PQM2
EWP
03-03-01-03
Plan Inspection during
Construction on
Aramco Site
PQM
/PMT
3
Plan On-Stream
Inspection during
Commissioning
OIU5
3.1.1
3.1.2
3.1.3
3.1.5
3.2
SAEP-1150
Inspection
Coverage on
Projects
OSI Administration
Inspection
Schedule
Inspection
Schedule
A
A
A
A
SAER-1972
Project Proposal/
Detailed Design
A
On-Stream
Inspection
Schedule Reports
Inspection
Schedule
Requests For
Inspection
Requests For
Inspection
Project Quality
Plan
SWP
02-03
Establish
Inspection
Strategy
Inspection
Strategy
Schedule Q
Manage QA
SA Inspection
Procedures
OIU Operations Inspection Unit
PID Projects Inspection Division
PMT SA Project Management Team
VID Vendor Inspection Division
*VID/QA for Vendor/SUP/Manufacturer qualification
VID – QC for Cat B
VID – QM for monitoring in Supplier Premises of Cat A
Supplier/
Contractor Quality
Plan
Draft SATIP
EWP
03-03-01-04
Plan Pre-
Commissioning
Inspection
PQM/
PMT
4
3.1.4
Review Certificates
and Documentation
from Supplier
VID_
QC
7
Type of
Equipment?
Cat A - MPA
Cat B
SAP
Cat C
Aramco Approval
of Equipment
Cat S
Reference of the
next process in the
sequence
This is an out-going link to the next process. This link is
not provided if the process flow returns to the parent
Incoming links for
navigation purposes
Reference link to the Strategic Process from
which this Tactical Process flows
The next level of process is an EWP
This process is a Tactical Process so label is ‘TWP’ and its title
is at the top of the page
This is a simple
step so does not
have a process
numberThis is an output
from the process
it is connected to
These are inputs
to the steps they
are linked to
Responsible for
process
Figure 10 - Process Map Items Description
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 47 of 52
Attachment 1 - “Manage Corrosion” at Design
(Double click to open the PDF document)
Adobe Acrobat Document
CorManPro Design_10 integrated 1
Attachment 2 - “Manage Corrosion” at Procurement and Construction
(Double click to open the PDF document)
Adobe Acrobat Document
CorManPro_PCC_8 1
Attachment 3 - “Manage Corrosion” at Operate and Maintain
(Double click to open the PDF document)
Adobe Acrobat Document
CorManPro_14 integrated 1
Attachment 4 - “Manage Corrosion” at Decommissioning
(Double click to open the PDF document)
Adobe Acrobat Document
Manage Integrity during Decommissioning 1
Note: These attachments may only be downloaded if you are connected to the network. If you wish to read these attachments offline, you are required to download them from the network to view later.
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 48 of 52
Part 3: Damage Mechanism Narratives
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 49 of 52
Introduction
This part describes generic narratives for damage mechanisms encountered or likely to be
encountered at Saudi Aramco upstream and downstream facilities. These are provided here for
use at future CMP deployments; however, these require customization to actual plant service
conditions. These narratives have been derived from API RP 571 and other Saudi Aramco /
Industry documents. They have been structured to address the damage description, the affected
materials, control methodology, corrosion monitoring and inspection techniques.
A full listing of the narratives is given in Table 9. These have been assigned an SA (Saudi
Aramco) reference number as well as the actual number given in API RP 571, as appropriate.
The damage mechanism narratives are given in the PDF attachment below:
(Double click to open the PDF document)
Adobe Acrobat Document
Damage Mechanism Narratives
Note: This attachment may only be downloaded if you are connected to the network. If you wish to read this attachment offline, you are required to download it from the network to view later.
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 50 of 52
Table 9 - Damage Mechanism Narrative List
SA # Description API RP 571 #
1 Sulfidic Corrosion (Sulfidation) 1
2 Wet H2S Damage (Blistering/HIC, SOHIC, SSC) 2
3 Creep/Stress Rupture 3
4 High Temp H2/H2S 4
5 Polythionic Acid Cracking 5
6 (NA) Naphthenic Acid Corrosion 6
7 Ammonium Bisulfide Corrosion 7
8 Ammonium Chloride Corrosion 8
9 HCl Corrosion 9
10 High Temperature H2 Attack 10
11 Oxidation 11
12 Thermal Fatigue 12
13 Sour Water Corrosion (Acidic) 13
14 (NA) Refractory Degradation 14
15 Graphitization 15
16 Temper Embrittlement 16
17 Decarburization 17
18 Caustic Cracking 18
19 Caustic Corrosion 19
20 Erosion/Erosion Corrosion 20
21 Carbonate SCC 21
22 Amine Cracking 22
23 Chloride Stress Corrosion Cracking (Cl-SCC) 23
24 Carburization 24
25 Hydrogen Embrittlement 25
26 Steam Blanketing 26
27 Thermal Shock 27
28 Cavitation 28
29 Graphitic (see De-alloying) 29
30 Short Term Overheating 30
31 Brittle Fracture 31
32 Sigma Phase Embrittlement 32
33 885°F Embrittlement 33
34 Softening (Spheroidization) 34
35 Reheat Cracking 35
36 Sulfuric Acid Corrosion 36
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 51 of 52
SA # Description API RP 571 #
37 Hydrofluoric Acid Corrosion 37
38 Flue Gas Dew Point Corrosion 38
39 Dissimilar Metal Weld (DMW) Cracking 39
40 Hydrogen Induced Cracking in HF 40
41 Dealloying 41
42 CO2 Corrosion 42
43 Corrosion Fatigue 43
44 Fuel Ash Corrosion 44
45 Amine Corrosion 45
46 Corrosion under Insulation (CUI) 46
47 Atmospheric corrosion 47
48 Ammonia Stress Corrosion Cracking (SCC) 48
49 Cooling Water Corrosion 49
50 Boiler Water/Condensate Corrosion 50
51 Microbiologically Induced Corrosion (MIC) 51
52 Liquid Metal Embrittlement 52
53 Galvanic Corrosion 53
54 Mechanical Fatigue 54
55 Nitriding 55
56 Vibration Induced Fatigue 56
57 Titanium Hydriding 57
58 Soil Corrosion 58
59 Metal Dusting 59
60 Strain Aging 60
61 Sulfate Stress Corrosion Cracking 61
62 Phosphoric Corrosion 62
63 Phenol (carbolic acid) Corrosion 63
64 Ethanol Stress Corrosion Cracking 64
65 Oxygen-enhanced Ignition and Combustion 65
66 Organic Acid Corrosion of Distilled Tower Overhead System 66
67 General Corrosion NA
68 Pitting Corrosion NA
69 Crevice Corrosion NA
70 Sweet Corrosion NA
71 Weight Loss Sour Corrosion NA
72 Acid Corrosion (Acidization) NA
73 Oxygen Corrosion NA
74 Elastomer Failure NA
Document Responsibility: Materials and Corrosion Control Standards Committee SABP-A-033
Issue Date: 30 March 2013
Next Planned Update: TBD Corrosion Management Program (CMP) Manual
Page 52 of 52
SA # Description API RP 571 #
75 Heat Checking NA
76 Thread Failure (Mech. F) NA
77 Tensile Overload (Mech. F) NA
78 Collapse (Mech. F) NA
79 Top of the line Corrosion NA
80 Under-deposit Corrosion NA
81 Acid Condensate Corrosion NA
82 Elemental Sulfur Corrosion NA
83 Casing Wear NA
84 Fretting Corrosion NA
85 Overlay Disbonding NA
This color denoted that the damage mechanism narrative is under development.