S24 Current Corridor Studies LTC2013

download S24 Current Corridor Studies LTC2013

of 31

Transcript of S24 Current Corridor Studies LTC2013

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    1/31

    Corridor Studies

    LA 415 and LA 73

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    2/31

    Project Approach for Both Corridors

    1. Data Collection

    2. Data Summary

    3. Traffic Analysis

    4. Micro-Simulation modeling

    5. Generation of alternatives

    6. Modeling alternatives

    7. Recommended alternative

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    3/31

    LA 415 Lobdell Avenue in West Baton Rouge Parish

    LA 415

    I-10

    US 190

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    4/31

    LA 415

    North-south state highway between I-10 and US 190

    Southern end classified as a urban arterial between I-10and Rosedale Road

    5 lane section with a continuous two-way left turn lane (TWLTL)

    Multiple commercial developments and driveways on both sides ofLA 415.

    Northern end classified as suburban arterial between RosedaleRoad and US 190.

    Four lane section with a depressed median (42-45 feet wide)

    Numerous median openings

    Mostly farmland along this section of LA 415

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    5/31

    LA 415

    Major intersections along corridor I-10 ramps

    Commercial Drive

    Court Street

    Rosedale Road

    Lafiton Lane

    Signalized intersections

    Court Street

    Rosedale Road

    Provide connection between LA 415 and Port Allen

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    6/31

    LA 415

    LA 415 and US 190 are used as alternative routes to getinto and/or out of Baton Rouge when there is an incidenton I-10 MRB

    During an incident on the I-10 MRB, LA 415 and US 190

    become heavily congested

    Proposed LA 1 toll road connector to the south of I-10 maygreatly effect traffic volumes at the LA 415 / I-10interchange

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    7/31

    Data Collection LA 415

    Seven day 24-hour classification counts (2 locations)

    24-hour approach counts (4 locations)

    Turning movement counts (4 locations)

    Driveway Counts (35 locations)

    Corridor Travel Times

    Spot Speeds

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    8/31

    Travel Time Comparison LA 415

    51

    215

    235

    51

    224

    242

    0

    50

    100

    150

    200

    250

    300

    Between I-10 & Court Street Between Plantation Drive &Court Street

    Between I-10 & Plantation Drive

    TravelTime(se

    c)

    Corridor Sections

    AM Peak Period Travel Times

    Southbound

    Northbound

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    9/31

    85th Percentile Speeds LA 415

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    10/31

    Speed Distribution LA 415

    0%

    5%

    10%

    15%

    20%

    25%

    1-15 16-20 21-25 26-30 31-35 36-40 41-45 46-50 51-55 56-60 61-65 66-70 71-75 76-999

    #Vehicles

    Speed (mph)

    Average weekday SB speed distribution - b/w Court St and I-10(Segment A)

    AM Peak

    Noon

    PM Peak

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    11/31

    Crash Data LA 415

    Crash reports for three previous years for two control

    sections

    Crash data acquired from DOTD database

    Analyzed types and severity of crashes at intersections

    and along the corridorLeft

    Turn-e, 9 Left Turn-f,19

    LeftTurn-g, 7

    Non Coll,

    22

    Rear End,70

    RightTurn-i, 1

    RightTurn-h, 2

    RightAngle,

    40

    SideSwipe,

    21

    Crashes by Reported Type

    0%

    5%

    10%

    15%

    20%

    25%

    30%

    35%

    40%

    LeftTurn-e

    LeftTurn-f

    LeftTurn-g

    NonColl

    RearEnd

    RightTurn-i

    RightTurn-h

    RightAngle

    SideSwipe

    Control-Section 013-01 between logmile

    0.000 and 3.298Reported Crash Type

    State Avg-Rural 4-Ln Divided Control Section%

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    12/31

    LA 73 Jefferson Highway in East Baton Rouge Parish

    LA 73

    I-12

    US 61

    I-10

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    13/31

    LA 73

    Jefferson Highway is a state highway that runs northwest-southeast located in center of Baton Rouge

    Classified as a urban arterial:

    5 lane section with a continuous two lane left turn lane (TWLTL)

    through out the corridor. Turn lanes at most of the signalized intersections.

    7 lane section at major signalized intersections.

    Multiple commercial developments and driveways on both sides ofLA 73.

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    14/31

    LA 73

    Major intersections with heavy volumes:

    Corporate Boulevard / Old Hammond Highway

    Essen Lane

    Drusilla Lane

    Bluebonnet Boulevard

    3.5 mile section

    10 signalized intersections

    25+ unsignalized intersections

    Over 100 driveways

    Issues:

    Heavy delays during peak hours

    Safety issues with high density of driveways

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    15/31

    Data Collection LA 73

    Seven day 24-hour classification counts (4 locations)

    24-hour approach counts (10 locations)

    Turning movement counts (10 locations)

    Driveway Counts (150 locations)

    Corridor Travel Times

    Spot Speeds

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    16/31

    Travel Time Comparison LA 73

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    17/31

    85th Percentile Speeds LA 73

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    18/31

    Speed Distribution

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    19/31

    Crash Data LA 73

    Crash reports for three previous years

    Crash data from DOTD database

    Analyzed types of crashes at intersections along studycorridor

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    HeadOn

    LeftTurn-e

    LeftTurn-f

    LeftTurn-g

    NonColl

    RearEnd

    RightTurn-h

    RightTurn-i

    RTAngle

    SSwipe(OD)

    SSwipe(SD)

    Control Section 077-05 from logmile 0 and 3.71- Reported Crash Type

    State Avg Urban 4-Ln Divided Control Section%

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    20/31

    Alternative Pyramid

    After Draft Technical Memo approval:

    Begin alternative analysis 5 initial alternatives developed

    Of the 5 alternatives 2 are eliminated and the remaining3 are modeled in Vissim for comparative benefits.

    From comparative analysis 1 final alternative is chosen.

    The final alternative is segmented into constructablesegments and preliminary engineering costs (ROW, utility

    relocation, and construction costs) are estimated. LA 415 investigate potential alternative corridor for I-10 /

    US 190 connection.

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    21/31

    Constructability

    LA 415

    biggest challenge not to disrupt the truck trafficwhich greatly effects the interstate ramps.

    Additionally connection with US 190 with the at graderail crossing.

    LA 73 maintenance of traffic during construction,especially at key locations at I-12, Essen Lane, and Old

    Hammond Hwy / Corporate Boulevard

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    22/31

    LA 73 and LA 415 Goals

    Safety

    Improve safety and reduce number of accidents.

    Mobility Make movement of traffic along the corridor moreefficient.

    Accessibility Utilize access management techniques andstrategies to reduce the number of direct openings on to thestudy corridors.

    Intelligent Design Use innovative techniques and designs tofor smooth traffic flow (Super-streets, J-turns, etc.,)

    Future uses A design that would sustain future growth andtraffic needs.

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    23/31

    Difference in approach

    Purpose for studying the corridors LA 415 a primary goal is to maintain the integrity of the corridor for

    smooth traffic flow in case of emergency I-10 closure.

    LA 73 goal is to improve safety and traffic flow.

    Urban (LA 73) vs. Rural (LA 415)

    Available ROW to make improvements

    Not much available ROW for LA 73. Expensive to buy surroundingland.

    Existing ROW available for LA 415.

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    24/31

    Difference in approach

    Nearby networkArea around LA 73 is mostly built out with not many possibilities of

    alternate routes or options for changing the alignment.

    Less complicated for LA 415 to achieve the project goals.

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    25/31

    Modeling Tools

    SYNCHRO HCM methodology

    Easy to understand output for Traffic engineers to makeassessments

    Quick

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    26/31

    Modeling Tools

    VISSIM micro simulation: Stochastic

    Time step model

    Pseudo-physical car following algorithm

    Ability to simulate and analyze unconventional designs

    Wide variety of MOEs

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    27/31

    Public/Local Official Involvement

    During the course of the alternative design

    visits to localofficials are planned to involve leadership in the designprocess

    Alternative workshops will take place to review the

    alternatives and solicit input to the alternatives to form astrong work relationship with local agencies and officials

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    28/31

    Final Deliverables Vissim model (LA 415)

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    29/31

    Vissim Model - LA 73

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    30/31

    Final Deliverables

    VISSIM model of the final design

    Final design alternate with associated construction andROW costs

    Constructible build segments Final report which explains design methodology used,

    alternative choice matrices, and final alternativepreliminary layout

  • 7/29/2019 S24 Current Corridor Studies LTC2013

    31/31

    QUESTIONS ?

    Contact Information

    Karl F. Rothermel, P.E., [email protected]

    (225) 751-3012

    mailto:[email protected]:[email protected]