Ryerson Final Project

29

Transcript of Ryerson Final Project

Page 1: Ryerson Final Project
Page 2: Ryerson Final Project

 

1  

ERIC PALIN HALL   

Group 5 | Cohort’10 

   IIIntroductionII  I. Analysis Objective II. Building Introduction 

 

IIBuilding codes & RegulationsII  I. General and Compliance, Occupant Type, Building Height & Area II. Building Fire Safety III. Plumbing Facilities IV. Barrier‐Free Study  

IIMaterials & MethodsII  I. Building Envelope II. Building Systems III. Building Components  

IIBIMx  I. Worksharing and Collaboration II. Building Systems III. Our Future with BIM IV. Renders & Visualizations  

xCONCLUSIONII   

INTRODUCTION 

Page 3: Ryerson Final Project

 

2  

ERIC PALIN HALL   

Group 5 | Cohort’10 

I. Analysis Objective   To further understand the building components and their 

assembly in addition to synthesizing an understanding of the  building  envelope  and  its  relationship  with  the various building systems 

To  comprehend  the  architects  design  intention  in comparison to their relative success 

To generate a BIM model of the building using Revit 2016, then use  it  to apply  the OBC and Materials & Methods principles 

To further our knowledge of BIM and its applications in a team environment, as well as BIMs  future  initiatives  in the industry 

To come to a conclusion of the buildings conformity and compliance with the OBC 2012 compendium 

 II. Building Introduction 

 The building is named after Eric Palin  English born educator  Canadian National Railway apprentice for 21 years  Trained radar technicians in the military  Involved with Ryerson since early beginnings  1944 developed the School of Electronics  Served  as  both  Associate  Director  and  Assistant 

superintendent to the University  Retired 1968 It was constructed in 2 phases with the first 4 floors constructed in 1971, and the next 2 in 2002. The Sally Horsfall Eaton Centre for Studies in Community Health cost was $21‐million for a 6,480 sqm addition to Eric Palin Hall. 

Name & Location   Eric Palin Hall 87 Gerrard Street East ,Toronto, Downtown East 

Status  Completed 

Year Completed  1971; 2002 

Architects 

Architect: Crang & Boake Architect: Lett/Smith Architects Designed two storey addition, 2002. Architect: Rounthwaite, Dick & Hadley Architects designed 4 storey building 1971 

General use  Educational 

Affiliation  Ryerson University 

Addition Sally Horsfall Eaton Centre for Studies  in Community Health  In 2002, an addition of two storeys on this building was completed, to house the Sally Horsfall Eaton Centre for Studies in Community Health. 

   

INTRODUCTION 

INTRODUCTION 

Page 4: Ryerson Final Project

 

3  

ERIC PALIN HALL   

Group 5 | Cohort’10 

I. General and Compliance, Occupant Type, Building Height and Area  

a) General and Compliance  The main program of the building consists of  indoor classrooms and  laboratories which are considered assembly occupancies according to the definition in Article 1.4.1.2. The building major occupancy type is of Group A Division 2 according to table 3.1.2.1. No changes in major occupancy has been done during the construction of the extension but the occupant 

load was increased by more than 15%. Therefore part 3 of the building code was applicable to the new 

extension. 

Division B Parts 1, 3, 5, 6, 7, 8 and 11 applicable to this building. 

This study was done based on the building current condition. 

 

b) Building Height  

As per Article 1.4.1.2. “Building height means the number of storeys contained between the roof and the floor of the first storey”. Since  the ground  level around Eric Palin Hall  is different  in each elevation,  the below calculations will determine the average grade level of the building: West Elevation: (2.81+1.85)/2x58.8 + (1.85+0)/2x7.2=137.004+6.66=143.664 North Elevation: (2.81+2.81)/2x58.3 = 163.823 East Elevation: (1.08+2.16)/2x49.2 + (2.16+2.81)/2x12.7 = 79.704+31.5595 = 111.2635 South Elevation:  (0+0)/2x34.1 + (0+1.08)/2x24.2 = 13.068 Grade Level: (143.664+163.823+111.2635+13.068)/(66+58.3+61.9+58.3) = 431.8185/244.5= 1.76  

  Based on Article 1.4.1.2 “First storey: means the storey that has its floor closest to grade and its ceiling more than 1.8 m above grade”. The storey ceiling height is 3.9‐1.76‐0.3(slab thickness)=1.84m. Therefore the first floor is considered as a full storey and the building height is of 6 storeys. 

BUILDING CODES & REGULATIONS 

Page 5: Ryerson Final Project

 

4  

ERIC PALIN HALL   

Group 5 | Cohort’10 

 c) Building Area 

 According  to Article 1.4.1.2.  “Building area means  the greatest horizontal area of  the building above grade, 

Within the outside surface of exterior walls, or 

Within the outside surface of exterior walls and the center line of firewalls. ”  The areas per floor of Eric Palin Hall are as follow:  

1st Floor: 3417 sqm  2nd Floor: 3448 sqm  3rd Floor: 3420 sqm 

4th Floor: 3430 sqm  5th Floor: 3400 sqm  6th Floor: 3400 sqm 

 Being the greatest area of the building, the 2nd floor area 3448 sqm will be considered as the building area.   

II. Building Fire Safety  

a) Use of combustible and noncombustible materials  Article 3.2.2.24 applies for our building since it is Group A, Division 2, 6 Storeys high and Sprinklered. It should  be  of  noncombustible  construction,  floor  assemblies  shall  be  fire  separations  with  1hr  fire‐resistance rating.  

  

           Load bearing elements such as walls and columns should be of the same fire‐resistance rating of the floor assembly above or below those elements as per Clause 3.2.2.24.(2)(c).  

BUILDING CODES & REGULATIONS 

Page 6: Ryerson Final Project

 

5  

ERIC PALIN HALL   

Group 5 | Cohort’10 

Although  the  building  is  of noncombustible  concrete  structure  for the  first 4  floors  and of noncombustible steel  structure  for  the 5th and 6th  floors, minor  combustible  elements  and components  are  permitted  and  covered by the building code  from Article 3.1.5.2 to 3.1.5.26. for interior finishing elements such as carpet, decorative wood cladding.  b) Limiting Distance and Unprotected Openings  Since  the building  is  sprinklered  and of Group A,  the  Limiting Distance  and  the Area of Unprotected Openings reference table would be table 3.2.3.1.(D) as per Clause 3.2.3.1.(1)(b).xxxxxxxxxxxxxxxxxxxxxx

 As for the construction of the exposing building face mentioned in Article 3.2.3.7. it will be extracted from the table of that same Article. 

 

BUILDING CODES & REGULATIONS 

Page 7: Ryerson Final Project

 

6  

ERIC PALIN HALL   

Group 5 | Cohort’10 

c) Fire Separations and Fire Ratings  The access  to exit according  to Sentence 3.  3.1.3.(1)  shall  conform  to Subsection 3.3.2.  for Assembly Occupancy which requires under Sentence 3.3.2.5.(1) that the corridors used by the public as an access to exit be separated from the rest of the floor by a fire separation having a fire‐resistance rating not less than 1h.  In Sentences 3.3.2.5.(3) and (4), the fire‐resistance rating and the fire separation could be waived if the floors where the corridors are located are sprinklered and the travel distance to an exit does not exceed the permitted limit in Article 3.4.2.5. which in our case is 45m according to sentence (c).  

  

                  Fire‐resistance rating of vertical service space for elevator hoistway shall be a minimum of 1h since the floor assembly fire resistance rating is of 1h too according to Table 3.5.3.1. Same goes for the elevator machine rooms unless they are separated from the rest of the building by a fire separation having a FRR more than 1h. Fire resistance rating of vertical service space shall be  a minimum of  45 minutes  since  the floor  assembly  fire  resistance  rating  is  of  1h according to Table 3.6.3.1. 

BUILDING CODES & REGULATIONS 

Page 8: Ryerson Final Project

 

7  

ERIC PALIN HALL   

Group 5 | Cohort’10 

d) Means of Egress  

As per Subclause 3.2.6.1.(a)(ii) a building is considered “High Building” if  it  is more  than “18m high, measured between grade and  the  floor level of the top storey, and in which the cumulative or total occupant load on or above any storey above grade, other than the first storey, divided by 1.8 times the width in metres of all exit stairs at that storey, exceeds 300 ”  Since the building is higher than 18 m between grade and top floor level, and  in order not to be considered a high building, a 2.5m stairs were added so that the above required calculations results does not exceed 300. This calculation is shown in the image below.   

  The building requires more than 1 exit since it is more than 2 storeys and the occupant load more than 60 according to Sentence 3.4.2.1.(2). The distance between those exits is set by Clause 3.4.2.3.(1)(a) which is more than half the maximum diagonal of the floor area.  

                             

BUILDING CODES & REGULATIONS 

Page 9: Ryerson Final Project

 

8  

ERIC PALIN HALL   

Group 5 | Cohort’10 

At least two egress doorways are required for rooms that have an occupant load more than 60 according to Clause 3.3.1.5.(1)(b). The door swing from a room to the corridor providing an access to exit shall swing in  the direction of  travel  if  the room occupant  load  is more  than 60 as per Clause 3.3.1.10.(2)(a). The distance between those doors should be equal or greater than the 1/3 of the room diagonal according to Sentence 3.3.1.5.(2).  

  Article 3.3.1.9. sets the safety requirements for a corridor used by the  public  and  requires  it  to  be  a minimum  of  1100 mm  and obstructions within 680 mm and 1980 mm from floor level should not protrude more than 100 mm from the wall but can be more under 680 mm.  According  to  Sentence 3.4.3.1.(1)  the width of  the exits will be determined  from  the  occupant  load  of  every  room  or  floor  in conformance with Subsection 3.1.17. This  load will be multiplied by  6.1mm  per  person  according  to  Clause  3.4.3.2.(1)(a)  to determine  the minimum  width  required  for  the  corridors  and doorways: 192 x 6.1 = 1171.2 mm. The existing corridor is 2900mm wide.  The latter must not be obstructed nor diminished by the door width when hung by more than 50mm for each door leaf according to Sentence 3.4.3.4.(2).It is also permitted to have an occupancy in the corridor as long as it doesn’t reduce the unobstructed width of the corridor according to Sentence 3.3.1.9.(5).  

  

BUILDING CODES & REGULATIONS 

Page 10: Ryerson Final Project

 

9  

ERIC PALIN HALL   

Group 5 | Cohort’10 

Clear height of exits over the clear width shall be  not  less  than  2100mm  as  per  Sentence 3.4.3.5.(1). This height is reduced to 2050mm in  stairways  according  to  Sentence 3.4.3.5.(2). Door closers shall not reduce the clear  height  of  a  doorway  to  less  than 1980mm  according  to  Sentence  (5)  of  the same Article.  Since our building complies with Clauses (a) and (b) Sentence 3.4.5.1.(1), exit signs should be placed over or adjacent to all the exit door they  serve.  The  type  of  sign  compliance  is also governed by this same Article. 

 e) Exit Stairs Design 

 The finish of landings and treads shall have a surface that  is slip resistant and a colour contrast between edges  according  to  Clauses  3.4.6.1.(1)(a)  and  (b). Tactile  attention  indicators  shall  be  installed according to Sentence 3.4.6.1.(2).  Landing  and  stairs  should  have  the  same  width according to Sentence 3.4.6.4.(1). Also according to the  previous  Article  Sentence  (3),  the  door  swing must not reduce the exit stairs or landing to less than 750mm.If the stairs width  is more than 1100mm  it shall  have  2  handrails  according  to  Sentence 3.4.6.5.(1). If stairs are more than 2200mm in width, it  shall  have  intermediate  handrails  at  1650mm according to Sentence 3.4.6.5.(2).   Handrail  circular  section  should  have  a  sectional diameter  between  30  and  43  mm  according  to Clause 3.4.6.5.(3)(a). The height of handrail should be  between  865  and  965  according  to  Clauses 3.4.6.5.(5)(a) and  (b).  It should extend horizontally not less than 300mm at the required height beyond the top riser and continue to slope for a depth of one tread beyond the bottom riser followed by a 300mm horizontal  extension  as  per  Subclause 3.4.6.5.(10)(a)(i) and (ii). The clearance between the handrail and any surface behind  it shall not be  less than  50mm  according  to  Sentence  3.4.6.5.(11). Steps treads shall be between 255 and 355 mm and risers between 125 and 200 mm as per Sentences 3.4.6.8.(1)  and  (2).  The nosing  should be  rounded 

BUILDING CODES & REGULATIONS 

Page 11: Ryerson Final Project

 

10  

ERIC PALIN HALL   

Group 5 | Cohort’10 

between 6 and 13 mm as per Sentence 3.4.6.8.(8). The doors shall open in the direction of exit travel as per Sentence 3.4.6.12.(1) and shall have a self‐closing device according to Clause 3.4.6.13.(1)(a).  At least one handrail shall be continuous throughout the length of a stairway as per Sentence 3.4.6.5.(8) and  shall  be  terminated  in  a manner  not  to  obstruct  pedestrian  travel  or  create  hazard  Sentence 3.4.6.5.(9).  f) Firefighting requirements and access  Fire alarm is required in the building according to Sentences 3.2.4.1.(2)(c) and (d) since  it  is more than 3 storeys high and the occupant  load more than 300 and could be a single or two stage system according to Sentence 3.2.4.3.(e).  Since  our  building  is  sprinklered,  no  direct  access  is  required  from  the outdoors  to  every  floor  that  is  below  25m  above  grade  according  to Sentence 3.2.5.1.(1). Access  to roof shall be provided by a stairway or a 550x900 mm  hatch  from  the  “floor  areas  immediately  below”  as  per Sentence 3.2.5.3.(1).  The Access  routes  should  be  provided  since the building  is more  than 3 storeys high and the building area more  than 600 sqm as per Sentence  3.2.5.4.(1)  and  in  our  case will  be located only on the North building face having the  principal  entrance  since  no  other  direct access  is  required  from  the  other  building faces. The Location should be between 3 and 15  meters  from  the  closest  portion  of  the access route and the building face.  The  standpipe  system  is  required  since  the building is more than 3 storeys and more than 14 meters  high  according  to  Article  3.2.9.1. and should be located in either the exit stairs shaft or a vertical  service  shaft having a  fire separation  of  45  minutes  of  fire  resistance rating  according  to  table  3.6.3.1.  The  fire department  connection  to  the  standpipe should not be  located more  than 45m  from the  closest  hydrant  as  per  Sentence 3.2.5.16.(1).  A 65 mm diameter hose connection is required in each storey according to Sentence 3.2.9.3.(2)and shall have a station in each storey according to Sentence 3.2.9.4.(1). This hose station shall be equipped with a hose rack and a 38mm diameter fire hose not longer than 30m according to Sentence 3.2.9.4.(2). 

BUILDING CODES & REGULATIONS 

Page 12: Ryerson Final Project

 

11  

ERIC PALIN HALL   

Group 5 | Cohort’10 

It should be in a hose cabinet that contains hose connections, valves, fire hose, nozzle, horse rack and a fire extinguisher and allow the use of a fire department  standard  hose  key  according  to Sentences (3) and (4) of Article 3.2.9.4.  

  Those hose stations should be clearly visible and located not more than 5m from every exit and can reach all  parts  of  the  building  given  that  the  hose  stream  stretches  3m  from  the  nozzle  as  per  Sentence 3.2.9.4.(5).  

III. Plumbing Facilities  According to Sentence 3.7.4.2.(2), the water closets shall be divided equally between males and females. Water  closets  for  male  can  be  substituted  with urinals but their number cannot be more than 2/3 of the  required water  closets  according  to  Sentence 3.7.4.2.(3) Clause (b). One lavatory shall be provided for one or two required water closets or urinals and one more shall be added for each additional 2 water closets or urinals according to Sentence 3.7.4.2.(5). The number of water closets required is determined by  table  3.7.4.3.A.  The water  closets,  urinals  and lavatories shall not be visible from the entrance door of the room as per Sentence 3.7.4.16.(2).  Drinking water  shall  be  provided within  a  100 m distance  of  any  area  of  the  floor  as  per  Sentence 3.7.4.18.(1).  

BUILDING CODES & REGULATIONS 

Page 13: Ryerson Final Project

 

12  

ERIC PALIN HALL   

Group 5 | Cohort’10 

IV. Barrier‐Free Study  

Since we have 4 pedestrian entrances to the building, the number of barrier‐free entrances required is 2 according to table 3.8.1.2. One of those 2 entrances is required to be the main entrance as per Sentence 3.5.1.2.(2).  As  per  Article  3.8.1.2.  sentences  (4)  and  (5),  those entrances shall be designed  in accordance with Article 3.8.3.3 and  if the entrances have more  than 1 doorway,  then 1 doorway shall be designed in accordance to Article 3.8.3.3.  At  least  2  universal  washrooms  are  required  according  to  Table 3.8.2.3.A. and  the number of barrier  free water  closets  required  is determined by Table 3.8.2.3.B. Doors shall conform to Article 3.8.3.3. minimum width and opening device.  Water closet stalls shall be designed according to Article 3.8.3.8. and 3.8.3.9. and have a clear turning space of 1500 mm in diameter. Toilet seats should be between 460 and 480 mm away from wall with grab bars. 

                                                  Universal washrooms  should  be  able  to  fit  an  810x1830 mm  clear  space  for  adult‐size  change  table according  to Sentence 3.8.3.12.(3) and a 760x1500 mm clear space parallel to the  table as per Clause 3.8.3.12.(5)(c). 

V. Summary  

TITLE  COMPLIANCE % 

MATERIAL COMBUSTIBILITY  100 

LIMITING DISTANCES AND UNPROTECTED OPENINGS  100 

FIRE SEPARATIONS AND FIRE RATINGS  100 

MEANS OF EGRESS  100 

EXIT STAIRS DESIGN  60 

FIREFIGHTING REQUIREMENTS AND ACCESS  90 

PLUMBING FACILITIES  80 

BARRIER‐FREE STUDY  60 

OVERALL COMPLIANCE  86 

 

BUILDING CODES & REGULATIONS 

Page 14: Ryerson Final Project

 

13  

ERIC PALIN HALL   

Group 5 | Cohort’10 

I. Building Envelope  “The envelope has to respond both to natural forces and human values. The natural forces include rain, snow, wind and sun. Human concerns include safety, security, and task success. The envelope provides protection  by  enclosure  and  by  balancing  internal  and  external  environmental  forces.  To  achieve protection it allows for careful control of penetrations. A symbol of the envelope might be a large bubble that would keep the weather out and the interior climate in.“  Richard Rush, The Building Systems Integration Handbook 

 

   

MATERIALS & METHODS 

Page 15: Ryerson Final Project

 

14  

ERIC PALIN HALL   

Group 5 | Cohort’10 

 

 

II. Building Systems  

 

 

 

MATERIALS & METHODS 

Page 16: Ryerson Final Project

 

15  

ERIC PALIN HALL   

Group 5 | Cohort’10 

a) Structural 

  

 

b) Moisture protection   

   

MATERIALS & METHODS 

Page 17: Ryerson Final Project

 

16  

ERIC PALIN HALL   

Group 5 | Cohort’10 

  

      c) Foundation System   Reinforced  concrete  foundation  footings were used  in  tandem with  the post  and beam  concrete 

structure for the first 4 floors  In 2002 with the addition of the 5th and 6th floor, shoring was needed to strengthen the foundations 

and structural system  An additional shaft, caisson and bell were added in concrete  

 

MATERIALS & METHODS 

Page 18: Ryerson Final Project

 

17  

ERIC PALIN HALL   

Group 5 | Cohort’10 

III. Building Components  a) Roof Structural Assembly 

  Tie Joists are used to provide lateral support to the steel members they’re connected to  An additional web system of alternating vertical and diagonal members was added as the roof joist is 

over 24”  This allows mechanical services to be threaded through the joists in a transverse direction   

   b) Wall Structural Assembly   Concrete structural walls were cladded with aluminium spandrel to cover certain walls  Ribbed metal was used for other walls also cladded to the concrete structural wall  A curtain wall system was imbedded in a steel z‐gurt system for the 5th and 6th floors  Columns on the last two floors were aluminium cladded   

MATERIALS & METHODS 

Page 19: Ryerson Final Project

 

18  

ERIC PALIN HALL   

Group 5 | Cohort’10 

   

 

MATERIALS & METHODS 

Page 20: Ryerson Final Project

 

19  

ERIC PALIN HALL   

Group 5 | Cohort’10 

a)  Structural Shear Walls  

Several walls were utilized as shear walls to assist in the structural loads of the building  The walls were assessed and altered during the second phase of construction in 2002  

 

 

   

MATERIALS & METHODS 

Page 21: Ryerson Final Project

 

20  

ERIC PALIN HALL   

Group 5 | Cohort’10 

b) Slab Structural Assembly   Steel beams make up the structural core of the slab  A substructure of decking is added to the I‐beam to support a concrete bed  Spray fireproofing with polyutherene foam acts as the protective fire proofing for the structure  

 

c) Interior Assemblies  

 

MATERIALS & METHODS 

MATERIALS & METHODS 

Page 22: Ryerson Final Project

 

21  

ERIC PALIN HALL   

Group 5 | Cohort’10 

I. Worksharing and Collaboration   Ahad ‐ BIM Manager: 

Foundations, columns, slabs, roof, envelope, site & context, façade details, renders, materials, building pad, wall reveals 

Hasti: Beams,  interior doors & windows,  section annotation,  interior walls 3rd, 5th and 6th,    room  tags, annotations & details, stairs 

Marwa: Furniture, wall reveals, room tags 

Nina: File setup, worksets, interior walls 1st, 2nd, 4th  

 

Envelope: includes exterior walls (including insulation build‐up and finish), curtain walls, windows, exterior doors and roofs.  Interiors: includes interior partitions, glazing   Structural: includes columns, core walls, shaft walls and foundation   Suites: includes separate Suites in building    Site & Context: includes all ramps, soil and earthwork surrounding the site and its context  Shared levels & Grids: contains the grid lines and levels that pertain to the entire project   

  

 

BIM 

Page 23: Ryerson Final Project

 

22  

ERIC PALIN HALL   

Group 5 | Cohort’10 

II. Team Challenges and Reflection on BIM  Challenging areas using software & proposed solutions 

 

Discrepancy of Information – Most of the drawings were not available in CAD format thus slowing down 

the modelling process; a lot of details regarding materiality and detailing was also missing  

Maintaining the accuracy ‐ as different team members were working on various levels of the vertical 

building. Solution – The envelope was created first and the various team members aligned their levels to 

it 

Ensuring the integrity of the central file model; utilizing the local files separate local files for the various 

team members were created and synchronized regularly with the saved central model – thus preserving 

its integrity and eliminating any room for error 

Maintaining the workset components ‐ Elements drawn by the team members had to be initially set on 

the correct worksets; constant reminders were needed 

Ensuring proper wall geometry; wall join. We had an issue with the alignment of the wall joints; they 

were not properly adjoining at the corners; fellow peers in adjacent groups were consulted for 

suggested solution, and when the challenge could not be overcome – we turned to the internet as a 

resource 

Improper task sequencing. The tasks assigned 

during the phases of constructing the BIM model 

were not optimized, which in turn disrupted the 

process of the work as finalized tasks would need to 

be revisited out of order 

 

Working with VAPPS – advantages & disadvantages  

Accessibility Working virtually through the network 

enabled the team to work from anywhere, and for 

longer hours on our respective local files, even 

when/if our computers did not have the Revit 

software installed 

Delays & file instability As we progressed with the 

modeling, the file got significantly larger. It became 

quite unstable and very slow when working through 

VAPPS, and at one point working off‐campus became 

redundant 

 

 

 

 

   

BIM 

Page 24: Ryerson Final Project

 

23  

ERIC PALIN HALL   

Group 5 | Cohort’10 

III. Our Future with BIM  

How is BIM changing the industry:  Waste = Non‐value added effort (wasted effort) Information inaccuracy causing regathering several times through the life of the project 2008 design and construction spending projections by Engineering News‐Record comes out to nearly $400B annually The owner is the primary beneficiary despite being lethargic in pushing for change  2D Renditions ‐ 3D Modeling & Visualization ‐ 4D Time ‐ 5D Cost The future of BIM modelling is to include more of the lifecycles of the building Organizations have taken initiatives to develop a US National BIM standard   Government (US Naval Forces, US Airforce, US Army)  Organizations (Building Smart Alliance, 7Group, AIA) Corporations (Construction industry, WBDG)       

 

BIM 

Page 25: Ryerson Final Project

 

24  

ERIC PALIN HALL   

Group 5 | Cohort’10 

IV. Renders & Visualizations   

 

 

 

 

   

BIM 

Page 26: Ryerson Final Project

 

25  

ERIC PALIN HALL   

Group 5 | Cohort’10 

Conclusion 

The building addition in 2002 created several challenges that had to be mitigated from both a materials 

and method standpoint as well as from an OBC perspective. The designers and consultants overcame 

these challenges by addressing the foundations, structural elements, and new enclosure systems. They 

also had to accommodate the additional building loads, uses and fire safety standards. 

There was not much effort made towards sustainability, for example natural ventilation techniques 

were not incorporated (all windows are non‐operable), solar panels, green roof, etc. ‐ the buildings net 

energy is not as low as it could be.  The future of design is headed towards a zero‐net energy, and this 

issue could later be improved upon in further renovations. 

As of this degree of analysis, the building is compliant 86% with Ontario’s current building code, and its 

building systems all serve their purpose quite well 

 

                     Resources & References  National Institute of building sciences  Building  Enclosure Technology & Environment Council  Whole  Building Design Guide  NIBS  National BIM Standard Committee

CONCLUSION 

Page 27: Ryerson Final Project
Page 28: Ryerson Final Project
Page 29: Ryerson Final Project