MEMORANDUM OF UNDERSTANDING
SOUTHEAST FLORIDA RAIL PARTNERSHIP
Rail~Volution 2014Minneapolis, Minnesota
Southeast Florida: A Strong Rail History
Henry Flagler
SE FLORIDA: PASSENGER RAIL HORIZON
NORTH
LEGEND
CSX (existing Amtrak route)
CSX/FEC (proposed new Amtrak route)
CSX (existing Tri-Rail route)
CSX/FEC (proposed new commuter rail ~ “Tri-Rail Coastal Link” route
FECI (proposed “All Aboard Florida” route)
Tampa Orlando
Miami
Fort Lauderdale
West Palm BeachEverglades
To Jacksonville
“Tri-Rail” Commuter Rail Service
Palm Beach County
Broward County
Miami-Dade County
Jan 1989
South Florida East Coast Corridor Study
• Began in 2005
• Multi-Agency Steering Committee:
- FDOT (lead) - SFRTA - MPOs - SEFTC - Transit Agencies - RPCs
• Synergy Until Summer 2011
August 2011
SFRTA’s Response: “Fast Start” Proposal
Oct 2011
Can We Find a “Common Track”?
JAN 12: SEFTC Requests TCRPC Evaluation of FDOT & SFRTA Approaches
JUL 12: SEFTC Approves Evaluation & Recommendations to Agencies Re-Establish Project Steering Committee Provide Regular Updates to All Agencies Coordinate Modeling/Data with All Agencies Improve Earlier Coordination with MPOs Continued Oversight by SEFTC FDOT & SFRTA Develop a “Unified Voice”
“All Aboard Florida” Proposal (FEC Industries)
March 2012
Can We Find a “Common Track”?
FALL 12: SEFTC Recommendations Presented to MPOs, SFRTA, RPCs
Southeast Florida Selected to Participate in Sustainable Communities Leadership Academy (Minneapolis, MN)
* FDOT & SFRTA ** FECI * MPOs & SEFTC * County Commissions * RPCs
“THE MINNEAPOLIS ACCORD”
PROJECT COMPONENT AGENCY ROLES & RESPONSIBILITIES
SFECC Study • FDOT to lead; coordinate with Steering Committee• Oversight from SEFTC
NEPA Process • FDOT to lead• Coordinate with SFRTA
Federal Funding Applications
• SFRTA to lead as project sponsor• SFRTA to be “Designated Recipient”
FECI Negotiations • SFRTA and FDOT to jointly negotiate with FECI
Project Financing • SFRTA to lead development of project finance plan (includes capital costs, access fees, & O&M)
Public Outreach • RPCs to lead outreach with “Corridor Coalition”• Coordinate with SEFTC, MPOs, FDOT & SFRTA
ESTABLISHED NOV 2012
All Aboard Florida Stations
LOCAL/REGIONAL RAIL OVERVIEW
MEMORANDUM OF UNDERSTANDING
• Eight Signatory Parties
• Carries Project through Operations
Initiated Dec 2012 Fully Executed May 2013
MEMORANDUM OF UNDERSTANDING
• Emphasis on MPO & SEFTC Approvals
• Establishes New Committee Structure
• Identifies Lead Agency/Phase
• FDOT - Planning / Project Development
• SFRTA – Engineering, Finance, Construction & Operations
• Addresses Joint Negotiations with FECI
NEW COMMITTEE STRUCTURE
“Executive” Steering CommitteeCoordinator: FDOT then SFRTA
Technical Sub-Committee
Coordinator: FDOT
Financial Sub-CommitteeCoordinator: SFRTA
Public Outreach Sub-Committee
Coordinator: RPCs
“Tri-Rail Coastal Link” – Process & Timeline*
Preliminary Project Development
Phase(formerly Alternatives Analysis)
Funding Plan(s)
Fund Project(s)
General Funding Framework
Funding Commitments
FIN
AN
CE
PLA
NO
VER
SIG
HT
AG
ENC
YPR
OJE
CT
PR
OC
ESS
MPO Action:Concurrence with
Alternatives
FTA Decision Point:Approval to enter
Project Development Phase
MPO Action:Program Project
Funds in TIP
FTA Decision Point:
Approval of Full Funding Grant Agreement (FFGA)
FDOT SFRTA* Process & Timeline illustrates South Florida East Coast Corridor (SFECC) Study, anticipated to produce “Tri-Rail Coastal Link” passenger rail service.
Project Development
Phase(2 years max. per MAP-21)
MPO Action:Approval of LPA
FTA Decision Point:
Issuance of ROD
MPO Action:Inclusion of Project in
Cost-Feasible Plan
FTA Decision Point:
Approval to enterEngineering Phase
Engineering Phase
ConstructionPhase
FTA Decision Point:
FFGA Compliance
Operations Phase
Fund Operations
“Tri-Rail Coastal Link” – Process & Timeline*
Preliminary Project Development
Phase(formerly Alternatives Analysis)
Funding Plan(s)
Fund Project(s)
General Funding Framework
Funding Commitments
FIN
AN
CE
PLA
NO
VER
SIG
HT
AG
ENC
YPR
OJE
CT
PR
OC
ESS
MPO Action:Concurrence with
Alternatives
FTA Decision Point:Approval to enter
Project Development Phase
MPO Action:Program Project
Funds in TIP
FTA Decision Point:
Approval of Full Funding Grant Agreement (FFGA)
FDOT SFRTA* Process & Timeline illustrates South Florida East Coast Corridor (SFECC) Study, anticipated to produce “Tri-Rail Coastal Link” passenger rail service.
Project Development
Phase(2 years max. per MAP-21)
MPO Action:Approval of LPA
FTA Decision Point:
Issuance of ROD
MPO Action:Inclusion of Project in
Cost-Feasible Plan
FTA Decision Point:
Approval to enterEngineering Phase
Engineering Phase
ConstructionPhase
FTA Decision Point:
FFGA Compliance
Operations Phase
Fund Operations
TRI-RAIL COASTAL LINK PARTNERSHIPMOU ADOPTION PROGRESS
ENTITY DATE (TIME) LOCATION STATUS
SEFTC April 22, 2013 Hollywood Approved
SFRTA April 26, 2013 Pompano Beach Approved
SFRPC May 6, 2013 Key Largo Approved
Broward MPO May 9, 2013 Fort Lauderdale Approved
Palm Beach MPO May 16, 2013 West Palm Beach Approved
TCRPC May 17, 2013 Stuart Approved
Miami-Dade MPO May 23, 2013 Miami Approved
Florida Rail Enterprise (FDOT)
May 30, 2013 Tallahassee Approved
5/16/2013
TREASURE COASTREGIONAL PLANNING COUNCIL (TCRPC)
SOUTH FLORIDAREGIONAL PLANNING COUNCIL (TCRPC)
SOUTH FLORIDA REGIONAL TRANSPORTATION AUTHORITY (SFRTA)
4/22/2013
SOUTHEAST FLORIDA TRANSPORTATION COUNCIL (SEFTC)
MIAMI-DADE METROPOLITAN PLANNING ORGANIZATION (MPO)
PALM BEACH METROPOLITAN PLANNING ORGANIZATION (MPO)
FLORIDA RAIL ENTERPRISE(FDOT)
5/9/2013
BROWARD METROPOLITAN PLANNING ORGANIZATION (MPO)
4/22/20135/23/2013
5/17/2013 5/6/2013
4/26/2013
2014 Progress
🚄 Kept updated meeting schedule. 🚄 SFRTA completed a draft TRCL Finance Plan 🚄 Jointly requested entry into Project Development 🚄 Agreed on Operating Plan 🚄 High level access fee negotiations being held
Questions & Comments