RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision...

138
RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of Murray Bridge RCMB

Transcript of RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision...

Page 1: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

RURAL CITY

OF

MURRAY BRIDGE

Engineering Guidelines

For the

Provision of Infrastructure

February 2014

Prepared by: Engineering and Assets

Rural City of Murray Bridge RCMB

Page 2: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of
Page 3: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

DISTRIBUTION LIST

Control Copy Job Title Company

1 General Manager of Infrastructure and Environment RCMB

2 General Manager of Sustainable Communities RCMB

3 Manager, Engineering and Assets RCMB 4 Manager, Operations RCMB 5 Manager, Planning RCMB 6 Team Leader, Engineering RCMB 7 Development Assessment Officer RCMB 8 Depot Administration RCMB

*Uncontrolled once printed

Rural City of Murray Bridge, V 1.0 iii

Page 4: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

PREFACE

Every effort and care has been taken by the Rural City of Murray Bridge (RCMB) to verify that the contents of this document are consistent with RCMB endorsed Plans and adopted Policies to reflect RCMB’s current requirements. In the case of an inconsistency, requirements of the RCMB endorsed Plan, adopted Policy or decision of the authorised RCMB Delegate in relation to a specific matter may over-ride this document. The use of this document requires professional interpretation and judgement. Appropriate design procedures and assessment must be applied to suit particular circumstances under consideration. The proponent must not assume that development approval will be automatically granted even if the development proposal may appear to comply with this document. Where a particular situation so warrants, this document may be departed from at discretion of the authorised RCMB Delegate with written notification and rationale being provided to the proponent. This document will be revised and updated on a continuing basis as new information and techniques become available. Feedback from users would be most welcome and indeed considered essential to the continued relevance of this document. Feedback is welcome via electronic mail to: [email protected] or via written correspondence to: The Manager Engineering and Assets Rural City of Murray Bridge 2 Seventh Street (PO Box 421) Murray Bridge SA 5253 Special Thanks Special thanks are extended to the following contributors who provided existing specification and guideline documentation for RCMB’s use. This kind gesture has provided a solid foundation for RCMB in preparation of its own ‘Residential Subdivision Guidelines’ document. The District Council of Mount Barker

SA Department for Planning, Transport, and Infrastructure (DPTI)

Rural City of Murray Bridge, V 1.0 iv

Page 5: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

REFERENCE DOCUMENTS The following documents are referred to in the guideline. They consist of RCMB endorsed plans and policies relevant to subdivision design, Planning SA guidelines, and industry guidelines produced by relevant authorities.

• RCMB endorsed plans and policies: Development Plan, December 2012 Integrated Water Resources Management Plan, 2013 Environmental Management Plan 2013 Local Area Bicycle Plan, July 2001 Stormwater Management Plan, May 2007

Property Identification Policy – Road Naming and Road/Street Numbering – SF141, April 2010

Disability Discrimination Act Policy – C: 7, August 2008

• Planning SA guidelines Good Residential Design SA: A resource for planning, designing and developing neighbourhoods and homes, Government of South Australia, 1999. Water Sensitive Urban Design Technical Manual for the Greater Adelaide Region, Government of South Australia, 2009

• Environment Protection Authority South Australia (EPA) publications Stormwater Pollution Prevention Code of practice for the Building and Construction Industry, EPA 1999

• AUSTROADS Guide to Road Design -

Part 4: Intersections and Crossings – General Part4A: Unsignalised and Signalised Intersections Part 4B: Roundabouts Part 6A Pedestrians and Cyclist Paths

• AUSTROADS Guide to Traffic Management –

Part 8 Local Area Traffic Management

Refer to the AUSTROADS web site http://www.austroads.com.au/ to confirm current standards

• Other AUSTROADS publications Austroads Design Vehicles and Turning Path Templates, 2006 Austroads Guide to Pavement Technology Part 2: Pavement Structural Design

• Australian Standards AS2890.1:2004 Off-Street Car parking AS1428:2010 Design for Access and Mobility Set

Rural City of Murray Bridge, V 1.0 v

Page 6: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

AS3600:2009 Concrete Structures AS1370:2007 Specification and Supply of Concrete AS4671:2001 Steel Reinforcing Materials AS1742 Manual of Uniform Traffic Control Devices

Set AS1158 Lighting for roads and public spaces Set AS4058 Precast Concrete Pipes AS1597 Parts 1 & 2 Precast Reinforced Concrete Box Culverts AS3725 Design for installation of buried concrete

pipes AS4198 Precast concrete access chambers for

sewerage applications AS4139 Fibre reinforced concrete pipes and fittings AS1254 PVC-U pipes and fittings for stormwater and

surface water applications AS2032 Installation of PVC pipe systems AS3996 Access covers and Grates AS1289Parts 5 & 6 Methods of testing soils for engineering

purposes AS1726: Geotechnical Site Investigations AS3500.1 Plumbing and Drainage - Water Services

• Institute of Engineers Australia publications Australian Rainfall and Runoff, a guide to flood estimation Volume 1, Current Edition (AR & R). Australian Runoff Quality, a guide to water sensitive urban design, 2006 (ARQ).

• Concrete Masonry Association of Australia (CMAA) Concrete Segmental Pavements guidelines

Guide to Specifying (T44) Design Guide for Residential Access ways and Roads (T45)

• Department for Transport, Energy and Infrastructure (DTEI), Contracts & Procurement Section standard specifications

Part 215 Supply of Pavement Materials Part 227 Supply of Asphalt Part 225 Supply of Bituminous Materials Part 207 Under Road Boring Part 206 Trench Excavation and Reinstatement Part 208 Pavement Reinstatement Pavement Reinstatement Configuration Diagrams

These specifications can be obtained from SA Department for Transport, Energy and Infrastructure website; http://www.dtei.sa.gov.au/documents/contractsandtenders/specifications_-_division_2_roadworks

Rural City of Murray Bridge, V 1.0 vi

Page 7: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

TABLE OF CONTENTS

PREFACE……………………………………………………………………………II

1 INTRODUCTION: .................................................................................. 1-1

1.1 Introduction ................................................................................................................................ 1-1

2 APPLICANT RESPONSIBILITIES: ....................................................... 2-1

2.1 Applicant Responsibilities ......................................................................................................... 2-1 2.1.1 Engaging Consultants ......................................................................................................... 2-1 2.1.2 Service Authorities ............................................................................................................. 2-2

2.2 Land Division Approval Process............................................................................................... 2-3 2.2.1 Prior to Development Approval ......................................................................................... 2-4 2.2.2 Pre-Construction ................................................................................................................. 2-6 2.2.3 Prior to Section 51 Clearance ............................................................................................. 2-8

2.3 Final Works Acceptance .......................................................................................................... 2-10

2.4 Liabilities and Insurances ....................................................................................................... 2-10

3 ROAD NETWORK ASSETS ................................................................. 3-1

3.1 Introduction ................................................................................................................................ 3-1

3.2 Documentation Requirements................................................................................................... 3-1

3.3 Road Hierarchy and Geometry ................................................................................................. 3-2 3.3.1 Street Definitions ................................................................................................................ 3-2 3.3.2 Street Pattern ...................................................................................................................... 3-4 3.3.3 Roads within Community Title Land ................................................................................. 3-4 3.3.4 Carriageways and Road Reserve Widths ............................................................................ 3-5 3.3.5 Design Speeds .................................................................................................................... 3-5 3.3.6 Longitudinal Gradient ........................................................................................................ 3-5 3.3.7 Traffic Control Devices ...................................................................................................... 3-7 3.3.8 Intersections........................................................................................................................ 3-7 3.3.9 Roundabouts ....................................................................................................................... 3-7 3.3.10 Car Parking .................................................................................................................... 3-7 3.3.11 Provision for Buses ........................................................................................................ 3-8 3.3.12 Local Widening ............................................................................................................. 3-8 3.3.13 Driveways ...................................................................................................................... 3-8

3.4 Road Construction Standards ................................................................................................... 3-9 3.4.1 Pavement Design ................................................................................................................ 3-9 3.4.2 Road Materials ................................................................................................................... 3-9 3.4.3 Pavement Construction ..................................................................................................... 3-10 3.4.4 Kerb and Gutter ................................................................................................................ 3-11 3.4.5 Concrete ........................................................................................................................... 3-12 3.4.6 Block Paving .................................................................................................................... 3-13

3.5 Footpaths and Cycleways ........................................................................................................ 3-14 3.5.1 Footpaths .......................................................................................................................... 3-14 3.5.2 Provision for Cyclists ....................................................................................................... 3-15

Rural City of Murray Bridge, V 1.0 vii

Page 8: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

3.5.3 Footpaths and Cycleways Construction Standards ........................................................... 3-16

3.6 Signs, Pavement Marking & Public Lighting ........................................................................ 3-17 3.6.1 Road Signs ........................................................................................................................ 3-17 3.6.2 Pavement Marking............................................................................................................ 3-17 3.6.3 Street Names..................................................................................................................... 3-17 3.6.4 Public and Street Lighting ................................................................................................ 3-18

3.7 Verges ........................................................................................................................................ 3-19

3.8 Service Installations within Road Reserves ........................................................................... 3-19

4 STORMWATER DRAINAGE ASSETS ................................................. 4-1

4.1 Introduction ................................................................................................................................ 4-1

4.2 Documentation Requirements................................................................................................... 4-2

4.3 Stormwater Drainage Design .................................................................................................... 4-4 4.3.1 Design Principles ................................................................................................................ 4-4 4.3.2 Site Discharge Limits ......................................................................................................... 4-5 4.3.3 Water Quality Improvement ............................................................................................... 4-5

4.4 Detailed Design ........................................................................................................................... 4-6 4.4.1 Hydrological and Hydraulic Calculations .......................................................................... 4-6 4.4.2 Major System Criteria ........................................................................................................ 4-7 4.4.3 Minor System Criteria ........................................................................................................ 4-7 4.4.4 Existing Watercourses ........................................................................................................ 4-8 4.4.5 Detention and Retention ..................................................................................................... 4-9 4.4.6 Outlet Design .................................................................................................................... 4-10 4.4.7 Residential Allotment Connections .................................................................................. 4-11 4.4.8 Drainage Easements ......................................................................................................... 4-11

4.5 Drainage Construction Standards .......................................................................................... 4-12 4.5.1 Stormwater Pipes .............................................................................................................. 4-12 4.5.2 Side Entry Pits and Manholes ........................................................................................... 4-13 4.5.3 Rear of Allotment (ROA) Drainage ................................................................................. 4-13 4.5.4 Pipe Connection to Council Infrastructure ....................................................................... 4-14

5 EARTHWORKS DESIGN ...................................................................... 5-1

5.1 Earthworks Design ..................................................................................................................... 5-1 5.1.1 Geotechnical Investigations ................................................................................................ 5-1 5.1.2 Site Regrading Design Requirements ................................................................................. 5-2 5.1.3 Earthworks Construction .................................................................................................... 5-3

6 LANDSCAPING AND OPEN SPACE ................................................... 6-1

6.1 Introduction ................................................................................................................................ 6-1

6.2 Documentation Requirements................................................................................................... 6-2

6.3 Landscape Design Principles ..................................................................................................... 6-3 6.3.1 Landscape Design Principles .............................................................................................. 6-3 6.3.2 Integration with Stormwater Management ......................................................................... 6-4 6.3.3 Existing Trees ..................................................................................................................... 6-5 6.3.4 Street Trees ......................................................................................................................... 6-6

Rural City of Murray Bridge, V 1.0 viii

Page 9: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

6.3.5 Trees in Reserves ................................................................................................................ 6-8 6.3.6 Grassing .............................................................................................................................. 6-8 6.3.7 Traffic Islands and Roundabouts ........................................................................................ 6-8 6.3.8 Fencing ............................................................................................................................... 6-9 6.3.9 Irrigation ........................................................................................................................... 6-10 6.3.10 Furniture ...................................................................................................................... 6-11 6.3.11 Paths ............................................................................................................................ 6-11 6.3.12 Lighting ....................................................................................................................... 6-11 6.3.13 Entrance Statements..................................................................................................... 6-11

7 SITE MANAGEMENT ............................................................................ 7-1

7.1 Introduction ................................................................................................................................ 7-1

7.2 Construction Management Plan ............................................................................................... 7-1

7.3 Soil Erosion and Drainage Management Plan ......................................................................... 7-1

7.4 Existing Trees ............................................................................................................................. 7-2

7.5 Working Hours........................................................................................................................... 7-2

7.6 Site Access ................................................................................................................................... 7-2

8 QUALITY ASSURANCE REQUIREMENTS .......................................... 8-1

8.1 Submission of Plans ................................................................................................................... 8-1

8.2 Minimum Drafting Requirements ............................................................................................ 8-1

8.3 Inspection and Testing ............................................................................................................... 8-1 8.3.1 Hold Points ......................................................................................................................... 8-2 8.3.2 Testing and Certification Requirements ............................................................................. 8-2

8.4 Tolerances on finished works .................................................................................................... 8-4

8.5 Retention Monies & Bonding Arrangements .......................................................................... 8-4

APPENDIX 1 - WATER QUALITY IMPROVEMENT PLANS ........................... I

APPENDIX 2 – CCTV PIPE SURVEYS ............................................................ I

APPENDIX 3..................................................................................................... I

MEETING CHECKLISTS .................................................................................. I

APPENDIX 4 - RAINFALL DATA ..................................................................... I

APPENDIX 5 – ................................................................................................. 1

RCMB TYPICAL DRAWINGS ......................................................................... 1

Rural City of Murray Bridge, V 1.0 ix

Page 10: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

CHAPTER ONE

Introduction

Page 11: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

1 Introduction:

1.1 Introduction RCMB’s Residential Subdivision Guidelines document has been prepared to encompass the following goals: Provide guidance on engineering documentation requirements for residential land development projects

Assist Developers, and other practitioners/professionals to meet RCMB expectations in the design, specification and construction of residential subdivisions

Maintain a consistent quality management framework in which RCMB and developers can operate. The document is divided into 7 sections; Applicant Responsibilities, Road Network Assets, Stormwater Drainage Assets, Earthworks Design, Landscaping and Open Space, Site Management, and Quality Assurance Requirements. The section on Applicant responsibilities has been provided to guide the Applicant on their responsibilities during the different stages of the land division process. -Its objective is to provide a quick reference or checklist for each step, to assist in meeting RCMB expectations and requirements. Subsequent sections provide guidance on documentation requirements, design, and construction of particular assets. The aim of each section is to provide clear direction on suitable design standards for infrastructure. Requirements are based on local experience and industry guidelines. Section 7 refers to Site Management and aims to highlight the developer/contractors responsibilities for compliance with relevant acts during the construction phase of works. RCMB requests that the information is forwarded to them for their records; however they do not assume responsibility for checking all documentation for compliance with relevant legislation. Quality Assurance Requirements are detailed in Section 8. Assets are to be designed and certified by appropriately qualified persons, and documentation provided to professional standards. Hold Points and submission of testing results are to be included in an Inspection and Testing Plan prepared specifically for the works. Test results need to be submitted in appropriate timeframes to ensure completed assets are acceptable. Bonding and Retention Money arrangements are also discussed.

Page 12: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

CHAPTER TWO

Responsibilities

of the

Applicant

Page 13: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

2 APPLICANT RESPONSIBILITIES:

2.1 Applicant Responsibilities

2.1.1 Engaging Consultants The Applicant should engage the services of qualified and experienced consultants for the preparation of designs and supervision of subdivision works to meet all design and construction requirements and conditions specified by RCMB for the purposes of the development proposal. For construction of roads, bridges, drains and services, required as a condition of land division consent, the Development Act 1993 and Development Regulations, 2008 require detailed construction plans and specifications to be signed by a professional engineer, or at the discretion of the council, a licensed surveyor, and approved by council before the commencement of work. A professional engineer means a person who is eligible for full membership of the Institute of Engineers Australia or registration on the National Professional Engineering Register. Design and supervision of all Civil Works should be carried out by a professional engineer. In this guideline the nominated professional is referred to as the Principal Consulting Engineer. Design and supervision of Landscaping Works should be carried out by a qualified practicing landscape architect.

Rural City of Murray Bridge, V 1.0 2-1

Page 14: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

2.1.2 Service Authorities The Applicant / Developer are responsible for all liaisons with the relevant Service Authorities in relation to provision of the services to each individual allotment. Requirements of the respective service authority shall be fully met by the Applicant. These services include: -

• water reticulation and services;

• electrical reticulation including service pillars;

• telecommunication;

• street lighting;

• conduits and pits for telecommunication services;

• gas reticulation and services; and

• wastewater treatment and disposal services.

• DPTI

• Railway Authority All public utilities (water supply, sewer, power, gas and telecommunications services) are to be installed underground. In accordance with the Development Regulations, before the roadway of any proposed road is sealed, the applicant must satisfy the council that all connections for water supply and sewerage services, which need to be laid under the surface of the proposed road, have been made. Where it is necessary to provide mains or service connections across existing roads, RCMB’s preferred method of connection is via directional horizontal boring. Any area disturbed during the installation of services is to be reinstated to the satisfaction of RCMB. For further information on reinstatements in the road reserve refer to Section 3.8. RCMB first preference for wastewater disposal is connection to SA Water. Where connection is not available, a concept plan indicating the proposed method to deal with the collection treatment and disposal of sewerage and sewerage waste is required. Developers may need to consider Community Wastewater Management Systems (CWMS). The Wastewater Management section of the Department of Health, SA should be contacted to provide guidance on the most up to date Design standards, Legal Requirements, and Application requirements of CWMS.

Rural City of Murray Bridge, V 1.0 2-2

Page 15: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

2.2 Land Division Approval Process The Land Division approval process involves three stages. The first stage is Development Approval. The second stage is Section 51 Clearance. The applicant is responsible for the final stage, which is submission to the Lands Titles Office. The applicant must obtain a Section 51 Clearance before they can lodge plans with the Lands Titles Office. The Development Approval stage involves two parts. Initially the application is assessed against the relevant provisions of the Development Plan. Once a satisfactory concept is developed, further detail is usually required to complete the assessment of the Land Division, which usually relates more to the engineering requirements. Section 2.2.1 provides guidance on the information requirements that may be required for RCMB to complete its assessment of a proposal. Following approval of the land division the applicant must seek Section 51 clearance. Land division approvals, usually contain a number of land division conditions, relating to the standard of the roads, stormwater system, or other physical improvements to the land. Section 2.2.2 and Section 2.2.3 outline the documentation requirements that RCMB may require to ensure that RCMB can provide Section 51 clearance of land division conditions.

Rural City of Murray Bridge, V 1.0 2-3

Page 16: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

2.2.1 Prior to Development Approval Prior to Granting Development Approval, RCMB’s Engineering Department will need to:

• be satisfied that the development will; a) adequately cater for future vehicular traffic, b) include appropriate provision for non-vehicular traffic such as pedestrians and cyclists, c) make due allowance for major stormwater flow paths and detention or retention areas, d) meet the goals, strategies, and objectives of the RCMS’s Stormwater Management Plan (SMP) and Integrated Water Resources Management Plan (IWRMP).

• have a full appreciation of any potential impacts of the development upon the environment, neighbouring lands, adjoining developments, and existing infrastructure.

• understand the proposed order of development including; a) the staging of the development b) the construction schedule c) the release of land schedule. d) the broader implications of the impact the development will have on the existing stormwater network and other existing infrastructure.

To assist RCMB in its deliberations on these broader scale and long term issues, the Applicant / Developer may be requested to provide: -

• A Site plan showing any existing structures, contours, and proposed

regrading. The details may be incorporated in to the preliminary Road Layout or Stormwater Concept Plan.

• A Road Layout Plan. The degree of documentation will vary depending on the nature and size of the proposed development. For a guide on the minimum requirements see Section 3.2.

• A statement and if necessary a plan, listing estimated traffic flow

figures for the development. This statement or traffic impact plan should be prepared by a suitably qualified person.

• A report on the geotechnical investigations undertaken for the site.

The degree of investigation required will vary depending on the site and the proposed development. For a guide on the minimum requirements for geotechnical investigations see section 5.1.1.

Rural City of Murray Bridge, V 1.0 2-4

Page 17: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

• A Conceptual Stormwater Management Plan and a Water Quality Improvement Plan. The degree of documentation will vary depending on the nature and size of the proposed development. For a guide on the minimum requirements see Section 4.2.

• A Concept Open Space Plan for the whole development setting out

the location type and size of the area for all proposed public open space and proposed function.

• A landscaping concept plan addressing streetscape, site conditions,

design intent, and irrigation demand and source.

• An Existing Trees Survey Plan setting out the location of all existing trees with diameter in excess of 400mm on the development site and within 5 metres of the site boundary. For a guide on the information to be included on the Existing Trees Survey Plan refer to Section 6.3.3.

• A Concept Plan indicating the proposed method to deal with the

collection, treatment and disposal of sewerage, and sewerage waste (including wastewater) from the site.

• Details of the construction staging and an indicative timetable.

Rural City of Murray Bridge, V 1.0 2-5

Page 18: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

2.2.2 Pre-Construction Prior to commencement of construction the developer will need to obtain approval from RCMB of the proposed construction details and specifications for the project, and complete the Pre-Start Meeting Process. The Pre-Start Meeting Process is part of RCMB's quality management framework. The process involves completing a checklist, to verify that all necessary procedures and documentation have been undertaken prior to commencement of works, and a site meeting to provide an opportunity to go through the approved documentation and clarify the relevant conditions and construction requirements. Once approval of construction details has been obtained from RCMB, the Principal Consulting Engineer should complete the Pre-Start Meeting Checklist and submit to Council at least 7 days prior to commencement of works. A copy of the Pre-Start Meeting Information Checklist is included in Appendix 3. Prior to commencement of any work on site the following data as being relevant to a specific stage, must be submitted to RCMB:

• Final road construction drawings including road layout and geometry, signs and linemarking, pavement design, lighting, footpath and shared paths, and special driveways. For further information see Section 3.2

• Final Stormwater Construction Plans, including detailed construction

drawings for all stormwater infrastructure for the stage. For further information see Section 4.2

• A detailed Landscaping and Open Space Plan incorporating

construction details, planting schedules, and a technical specification. For further information see Section 6.2.

• An Irrigation Management Plan. For further information see Section

6.3.8

• A Soil Erosion and Drainage Management Plan. For further information see Section 7.3.

• A copy of the final electrical reticulation drawings, showing the

locations of all transformers, HV switching cubicles and street lighting.

• Technical Specifications and Tender Details.

Rural City of Murray Bridge, V 1.0 2-6

Page 19: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

• Construction Schedule, Inspection and Testing Plan (refer Section 8.3), and Construction Management Plan (refer Section 7.2).

A work permit via the RCMB Application form - Authorisation to alter a public road, must be obtained prior to any work being undertaken within or on RCMB’s road reserve area. A separate agreement form may be required with The Department of Planning, Transport and Infrastructure (DPTI) where works will occur on or adjacent to a road under the care and control of the Commissioner of Highways. It is the Applicant’s responsibility to seek and, if necessary, comply with such an agreement. The applicant is also responsible for obtaining any approvals necessary for the works from other authorities such as the Environment Protection Authority or the Murray-Darling Basin Natural Resources Management Board. The Applicant / Developer shall also submit for each stage of the development a Combined Services Plan (hard copy, presented at a scale 1: 1,000 or larger, and an electronic copy in pdf format). The combined services plan shall clearly show all cadastral information and locations of services including water, sewer, stormwater, and street lighting details.

Rural City of Murray Bridge, V 1.0 2-7

Page 20: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

2.2.3 Prior to Section 51 Clearance Prior to Section 51 Clearance the developer will need to complete the Engineering Clearance Process. The Engineering Clearance Process is part of RCMB's quality management framework. The process involves completing a checklist, to verify that all necessary procedures and documentation have been undertaken, and a site meeting to review and discuss the various components of the works. A copy of the Engineering Clearance Meeting Information Checklist is included in Appendix 3. The Principal Consulting Engineer should only request Engineering Clearance once all the relevant requirements in the check list are complete. The Checklist should be completed and submitted to RCMB at least 7 days prior to the requested meeting date. Prior to granting Engineering Clearance, the Applicant/ Developer will be required to supply the following information to the satisfaction of RCMB:

• An A1 hard copy of the “As Constructed” Drawings for all civil works. All deviations and changes from the For Construction drawings are to be noted and certified by the Principal Consulting Engineer.

• An electronic copy on labeled CD of the “As-Constructed” drawings for

all infrastructure assets in an AutoCAD format supplied in GDA94 MGA Zone 54 and in accordance with the following;

• Separate layers for Roads Assets, Stormwater Assets, Property and

Easement Boundaries, and any other infrastructure.

• The Roads Assets layer shall include the Gazetted road names, Road Centreline, Kerbs, and Footpaths. Attributes of all elements shall be included, such as width, type and materials.

• The Stormwater Assets layer shall include location of all surface

inlets, structures, pits, pipes and outlet structures. Attributes of all elements shall be included, such as Depths, size, and materials.

• A schedule or register of all the infrastructure that will become the

property of RCMB in tabular Excel format listing for each element the location, dimensions, materials, construction date, design life, and maintenance requirements.

• Specifications, Manuals, and Maintenance schedules for any

stormwater quality improvement devices (such as constructed wetlands or ponds, Gross Pollutant Traps, and infiltration systems) detailing the expected ongoing maintenance activities required for the asset.

Rural City of Murray Bridge, V 1.0 2-8

Page 21: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

• Any outstanding Quality Assurance Requirements as detailed in Section 8

• An allotment plan showing the extent and the depth of filling on all

allotments together with a site re-classification for residential footing design, from a suitably qualified professional engineer.

• Certification from the Principal Consulting Engineer, responsible for the supervision of the project, that the development has been constructed in accordance with RCMB approved plans and specifications.

• Copies of all easements to be provided to RCMB and all other Service Authorities.

Bank Guarantees, retention monies for the defects liability period, and bonding arrangements or monetary contribution agreements must be resolved and finalised prior to any Section 51 Clearance being issued by RCMB for the development. For further information regarding bonding and retention monies refer to Section 8.5.

Rural City of Murray Bridge, V 1.0 2-9

Page 22: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

2.3 Final Works Acceptance At the conclusion of the defects liability period the Final Completion Process is carried out. The Final Completion Process is part of RCMB's quality management framework. The process involves completing a checklist, and a Joint Final Inspection. A copy of the Final Completion Meeting Information Checklist is included in Appendix 3. The Principal Consulting Engineer should only request a meeting once all the relevant requirements in the check list are complete. The Checklist should be completed and submitted to RCMB at least 7 days prior to the requested meeting date. Once Final Completion requirements have been satisfied, the developer needs to apply for transfer of ownership of assets to RCMB, and the return of retention monies. The RCMB will execute the termination of the bonding (retention monies) agreement and issue a Certificate of Transfer for the assets. The Final Completion Meeting Information Checklist requires submission of CCTV Footage of internal inspection of all stormwater pipe networks. For specific requirements of CCTV Footage of internal inspection of all stormwater pipe networks see Appendix 2 CCTV Pipe Surveys.

2.4 Liabilities and Insurances

In accordance with Section 245A of the Local Government Act the developer may be required to enter in to a bonding agreement for repairing any damage caused to Council footpaths, roads, kerbing and stormwater pits by inappropriate use of trucks, excavators and other heavy equipment while entering and exiting the construction site. The Developer is responsible for all damage to existing facilities, services and structures sustained as a result of the development of the subdivision, whether those damaged items are in public or private ownership. All damage is to be promptly reinstated to an equivalent standard acceptable to the owner. RCMB will require the Developer to take out all necessary insurance policies to indemnify and protect it and RCMB against any claims that may arise in undertaking the development, until Final Works Acceptance has been obtained from RCMB.

Rural City of Murray Bridge, V 1.0 2-10

Page 23: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

CHAPTER 3

ROAD NETWORK ASSETS

Page 24: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

3 ROAD NETWORK ASSETS

3.1 Introduction The road network assets associated with a residential subdivision need to fulfil several functions. Street layout and design should create “A hierarchal street network, which provides for safe and convenient movement, accommodates public utility services and drainage systems, and creates an attractive environment.” - Good Residential Design SA: A resource for planning, designing and developing neighbourhoods and homes, Government of South Australia, 1999. The RCMB Development Plan provides a range of objectives and principles of development control relating to road network assets. Particular reference should be made to the general sections relating to Transportation and Access and Land Division.

3.2 Documentation Requirements Access arrangements are to be submitted with development proposals and should show as a minimum;

• Road hierarchy; • Typical cross sections showing the carriageway widths and the proposed location of services; • Connections to existing streets; • Pedestrian paths and crossings; • Parking provisions (on street and off street where applicable); • Any physical traffic control devices; • Bicycle routes and shared paths;

Proposals that include the construction of public roads will need to provide evidence of consultation with the Public Transport Division of the Department of Planning, Transport and Infrastructure (DPTI) regarding bus routes and bus stops. Prior to commencement of work Final Road Construction Drawings and a specification prepared specifically for the works under consideration, are to be submitted to and approved by RCMB.

Rural City of Murray Bridge, V 1.0 3-1

Page 25: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

Final Road Construction Drawings should detail;

• Road layout and geometry including Plan views and longitudinal sections, Cross sections, Intersection details and traffic management measures.

• Signs and linemarking • Site regrading details including the extent of any site filling and cutting,

and how these will be treated at the boundary of the road reserve. • Road pavement design including all design criteria

• Parking and driveway plan (including the location and width of splays in

relation to driveway openings at the boundary of each allotment).

• Detailed drawings of any special treatments including pavement widening, special driveways.

• Lighting Plan with luminary, light poles and standard of design details,

and SA Power Networks public lighting agreement document completed by the designer.

• Footpath and shared path details.

3.3 Road Hierarchy and Geometry RCMB has adopted the street classification system detailed in Table 3.3: Standard Residential Road Design Elements. This table sets out the general minimum standard of design elements for the various road classifications.

3.3.1 Street Definitions

• Access Lane An Access Lane can be used for access to a small number of allotments, and should be restricted to a maximum length of 50m. It would typically be a short cul-de-sac. RCMB Typical Detail Drawing No. 2012-5006-001 located in Appendix 5 Drawings depicts the typical cross section of an Access Lane.

Rural City of Murray Bridge, V 1.0 3-2

Page 26: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

• Access Road An Access Road is dominated by the residential environment. The number of dwelling units served should not exceed 30 and the layout of the subdivision should be designed to limit the length of the street to less than 150m. RCMB Typical Detail Drawing No. 2012-5006-002 located in Appendix 5 Drawings depicts the typical cross section of an Access Road.

• Local Streets

A Local Street is one in which the residential environment is dominant, traffic is subservient. The number of dwelling units served should not exceed 100. Speed and volume are low, with a footpath required on at least one side of the road. Vehicle speeds are typically controlled by street length and /or alignment. RCMB Typical Detail Drawing No. 2012-5006-003 located in Appendix 5 Drawings depicts a typical cross section of a Local Street

• Collector Road

Typically a Collector Road is used to concentrate local traffic to an outlet to the Arterial Traffic Road System, without attracting through traffic itself. It will often be designated as a bus route. It will also have wide verges to accommodate pedestrian or shared paths on both sides of the road. There should be no pedestrian movement across it other than at controlled crossing locations. RCMB Typical Detail Drawing No. 2012-5006-004 and 2012-5006-005 located in Appendix 5 Drawings depicts a typical cross sections of a Collector Road. • Rural Road A Rural Road is used in a country or rural environment where the allotment size is considered large enough not to require a concrete kerb and channel. Swale drains are required both sides, with box culverts to service each driveway. Intersections and cul-de-sac’s shall be sealed with an approved AC treatment (Hot Mix). Footpaths are generally not required on a Rural Road, however the RCMB will assess its merit during the development assessment phase. RCMB Typical Detail Drawing No. 2014-500-001 located in Appendix 5 Drawings depicts a typical plan view and cross sections of a Rural Road.

Rural City of Murray Bridge, V 1.0 3-3

Page 27: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

3.3.2 Street Pattern The various street types defined above should be arranged in a logical pattern relative to their respective hierarchy in recognition of the inter-relationship between the various residential types and functions. Further guidance on design of street pattern can be found in “Good Residential Design SA: A resource for planning, designing and developing neighbourhoods and homes”, Government of South Australia, 1999.

3.3.3 Roads within Community Title Land Community Title developments are required to provide access for pedestrians and vehicles, including all those expected to service the development, such as garbage trucks, furniture removal trucks, and fire control vehicles. Adequate treatments will need to be incorporated in the internal access arrangements to enable all vehicles servicing the development to enter and exit in a forward direction. RCMB garbage service vehicles will not normally enter community title developments as the roadways are on private land, not public roads. Exceptions to this may be negotiated between the developer and RCMB where the roads are designed and formed to RCMB specifications to carry garbage vehicles and the owner indemnifies RCMB against any damage to the roadway. Where a developer does not wish to construct roads capable of accommodating the regular garbage service vehicle, they may be required to provide a collection area within the common property of the development and evidence of an arrangement with a private contractor for provision of a garbage collection service. Details of internal roads including layout and pavement design shell be provided during the assessment phase.

Rural City of Murray Bridge, V 1.0 3-4

Page 28: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

3.3.4 Carriageways and Road Reserve Widths Minimum carriageway widths for all road classifications are shown in Table 3.3: Standard Residential Road Design Elements. All road reserves shall be able to accommodate the requirements for footpaths, landscaping, drainage, underground services, street lighting columns, and safe vehicle entry and egress from every individual property. Application of Water Sensitive Urban Design principles is to be considered at all times. Where WSUD approaches are used, flush kerbing is to be provided, as a minimum, to protect the edge of pavement. The street network, including all intersections and T-junctions, must be able to accommodate the AUSTROADS 12.5 metre Single Unit Truck (Austroads Design Vehicles and Turning Path Templates, 2006) without the need for the mounting of kerbs by leading or trailing wheels. Local widening may be required on small radius bends. Cul-De-Sac head layout is to be in accordance with RCMB Typical Detail Drawing No. 2013-5002-001. The design vehicle used is the current garbage service vehicle which has a turning circle of 17.5 metres and a swept path of 18.6 metres. Cross fall on street pavements is to be a minimum of 3.0%. One way cross-fall may be permitted on slopes where one way cross-fall will reduce the amount of earthworks required or for WSUD cross sections. Where the Developer proposes to use geometry that differs from those in the appendix 5 (2012-5006-001 to 2012-5006-005), full details will need to be presented to RCMB for consideration.

3.3.5 Design Speeds The general urban speed limit in RCMB is 50km/hr. Subdivision layout and the use of appropriate traffic control devices in street design should be used to limit speeds to those defined in Table 3.3: Standard Residential Road Design Elements

3.3.6 Longitudinal Gradient Longitudinal gradient is to conform to the limits as shown in Table 3.3: Standard Residential Road Design Elements. Vertical curves are to be used on all changes in grade exceeding 1%.

Rural City of Murray Bridge, V 1.0 3-5

Page 29: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

Table 3.3: Standard Residential Road Design Elements

Street Type Access Lane Access Road Local Streets Collector Road

Absolute Minimum Reserve Width

13.0m 14.2 m 15.7 m 24.2 m

Traffic Catchment (max)

6 Lots 30 lots 100 lots N/A

Traffic volume 0-60vpd 60-300vpd 300-1000vpd 1000-3000+ vpd *Target Maximum Speed

30km/h 40km/h 40 km/h 50 km/h

Maximum length 50 metres 150 metres NA NA Minimum Carriageway Width

6.0 m

7.0m

7.2m

7.2m 10m (with cycle lanes)

Parking Provision Carriageway – One side only

Carriageway – Both sides

Carriageway – Both sides

Indented parking bays

Footpaths One side - width 1.5m One side - width 1.5m One side - width 1.5m Both sides – width 1.5 Cycle provision On carriageway On carriageway On carriageway Shared path on verge or cycle lane on

carriageway Maximum Grade

16% 12%

12%

4.6% 10% where not a bus route

Public Transport NA NA NA Indented bus stops, seating and sheltered areas on bus routes

Sight distance (min) 50m 50m 50m 70m * This is the intended maximum speed at which most drivers will travel given the inbuilt environmental speed controls created by the street layout and design. It is not a design speed for sight distance, cornering or other geometric properties of the carriageway.

Page 30: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

3.3.7 Traffic Control Devices Traffic control devices must comply with the “Code of Technical Requirements for the Legal Use of Traffic Control Devices in South Australia” and should be designed in accordance with the requirements of the AUSTROADS “Guide to Traffic Management - Part 8 Local Area Traffic Management”.

3.3.8 Intersections All intersections are to be designed in accordance with AUSTROADS “Guide to Road Design – Part 4: Intersections and Crossings - General” and Part 4A Unsignalised and Signalised Intresections. The minimum design vehicle is the AUSTROADS 12.5 metre Single Unit Truck. Intersections are to be designed without the need for the mounting of kerbs. In some instances RCMB or DPTI may require larger vehicles to be accommodated. All kerb returns should have a minimum radius of 8m. Provision for footpath and kerb ramps is also to be taken in to consideration. All T junction pavements must intersect at 90 degrees and the straight leg of the T must be at least 8 metres long.

3.3.9 Roundabouts

Roundabouts should be designed and constructed to comply with the requirements of AUSTROADS “Guide to Road Design Part 4B: Roundabouts” and the “Code of Technical Requirements for the Legal Use of Traffic Control Devices in South Australia”

3.3.10 Car Parking

On-street car parking provision for residential developments are to be in accordance with provisions of the Development Plan. Estimates of the number of car park spaces provided by the design proposal should,

• not include bays which intrude upon the driveway swept path requirements, and

• make provision for a minimum of 3.0 metres lane width available to moving traffic, between a parked vehicle and a median, or between two parked vehicles.

The on-street car park for any given allotment should be no further than 20m from the front boundary of that allotment.

Rural City of Murray Bridge, V 1.0 3-7

Page 31: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

3.3.11 Provision for Buses Appropriate provision is to be made for buses and associated or affected infrastructure, as determined in conjunction with the Public Transport Division of the Department of Transport, Energy and Infrastructure. All work at bus stops should comply with the requirements of the Disability Discrimination Act, RCMB’s Disability Discrimination Act Policy (August 2008) and meet the needs of the Public Transport Division of the Department of Transport, Energy and Infrastructure.

3.3.12 Local Widening The minimum carriageway and reserve widths should be widened locally and/or generally as required to accommodate traffic control devices as well as providing for buses and associated public transport infrastructure.

3.3.13 Driveways Consideration should be given to constructing sealed access during subdivision works for multiple lots, battleaxe allotments, and where grades exceed 1 in 6 from the boundary of the road reserve to the future allotment. Provision is to be made for passing for multiple lots. Conduits for internal allotment services should be provided adjacent to, and for the whole length, of the driveway. The design and finish of driveways are to be approved by RCMB prior to construction, and be generally in accordance with RCMB Typical Detail Drawing 2012-5000-001 or 2012-5000-002. Where a gradient in excess of 1 in 6 exists from the boundary of the road reserve to the future allotment the Developer should design and construct the driveway in accordance with AS2890.1 2004 to accommodate the B85 design vehicle. The provision for vehicle crossovers and the reinstatement of existing crossovers not required by the development are to be carried out by the Developer to the satisfaction of RCMB. A work permit via the RCMB Application form - Authorisation to alter a public road, must be obtained prior to any work being undertaken within or on RCMB’s road reserve area.

Rural City of Murray Bridge, V 1.0 3-8

Page 32: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

3.4 Road Construction Standards Where relevant, any products used shall be installed in accordance with the manufacturer’s instructions. The minimum standard for road construction within the area of the RCMB is demonstrated in RCMB Typical Detail Drawing 2012-5006-002

3.4.1 Pavement Design Road pavements are to be designed and constructed in accordance with:

• AUSTROADS Guide to Pavement Technology Part 2 - Pavement Structural Design.

Design traffic estimation is to be based on a 40 year pavement design life. Assessment of subgrade CBR is to be based on laboratory testing on a minimum of 3 samples for each road, compacted to 95% maximum dry density (standard). CBR values for un-soaked and 4 day soaked are to be determined to characterise variations due to moisture changes during service life. Assumptions on subgrade CBR values are to be re-evaluated once works have progressed to subgrade level. All roads shall be surfaced with a minimum of 35mm Asphaltic Concrete wearing course and have a minimum 100mm base course and a total pavement thickness of not less than 300mm.

3.4.2 Road Materials

Roads shall be constructed using material conforming to the requirements of the DPTI, contract specifications; Part 215 “Supply of Pavement Materials” Part 227 “Supply of Asphalt” Part 225 "Supply of Bituminous Materials" Base shall comply with PM 1 / 20QG. Sub-base shall comply with PM 2 / 20QG, PM 2 / 30QG or PM 2 / 40QG. Asphalt shall conform to the requirements of RCMB specification for the Supply of Asphalt.

Rural City of Murray Bridge, V 1.0 3-9

Page 33: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

3.4.3 Pavement Construction The specifications for the works shall provide full details of the proposed pavement construction procedures. When earthworks have progressed to a stage where the nature of subgrade material can be assessed, design assumptions shall be reviewed and any additional testing requirements undertaken. All pavement layers shall be uniformly compacted to the full depth and over the full width. Proof rolling shall be undertaken to ensure a uniform density has been achieved. The surface of the pavement layers shall be uniformly tight and free of loose uncompacted material, segregated or 'bony' material or soft, over wet areas and free of roller indentations.

Minimum compaction requirements for each layer of the pavement are detailed in Table 3.1. Compaction requirements should be stated on the drawings and/or in the specification. The frequency of compaction testing shall be two tests per 1000 square metres per layer, with a minimum of 2 tests per layer. The Principal Consulting Engineer is required to verify that the pavement layers conform to the figures and dimensions on the Drawings and tolerances are in accordance with Table 3.1

Layer Thickness

(mm) Level (mm) Width (mm) *Minimum

Compaction %

Sub Grade - + 10 - 30

+ 150 - 0

95

Sub Base + 15 - 10

+ 10 - 20

+ 150 - 0

98

Base + 10 - 0

+ 10 - 10

+ 100 - 0

98

Table 3.1 Tolerances on Pavement Layers

*Minimum compaction shall be based on Maximum Dry Density achieved by Test 5.2.1 AS1289 (modified)

Rural City of Murray Bridge, V 1.0 3-10

Page 34: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

3.4.4 Kerb and Gutter Concrete Kerb and Gutter shall be provided on both sides of all roads except as otherwise approved by RCMB. Where Water Sensitive Urban Design treatments are incorporated in designs flush kerb shall be provided as a minimum to all pavements. All concrete Kerb and Gutter provided will be Mountable except on Collector routes, bus routes and along the edges of reserves where Barrier Kerb shall be used. Kerbs details are provided in RCMB Typical Detail Drawing No. 2012-5002-001 and 2012-5002-002 for Kerb Details. . Where WSUD treatments are used adjacent reserves bollards are to be installed to prevent vehicular access. A galvanised steel kerb adaptor shall be provided for each allotment to facilitate the disposal of stormwater from the property. Each adaptor shall be cast into the kerb on the downstream side of the allotment situated approximately 1 metre from the alignment of the adjoining property boundary. Kerb Ramps shall be provided at every corner radius where footpaths are proposed, and include Warning Tactile Ground Surface Indicators. The location is to be approved by the RCMB. Kerb ramps shall comply with AS1428 standards, refer to RCMB Typical Detail Drawing 2012-5001-001 for details.

Rural City of Murray Bridge, V 1.0 3-11

Page 35: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

3.4.5 Concrete

All concrete works shall comply with the requirements of AS 3600 in all particulars. Ready mixed concrete shall comply with AS 1379. Reinforcing bar and mesh and hard drawn steel wire shall comply with AS4671. Concrete shall have a maximum aggregate size of 20mm. The following grades of concrete shall be used for works in new subdivisions for the following applications

• Kerb and gutter, spoon drains, etc. - N25 • Drainage pits and structures - N32 • Concrete paths, paving (not road pavements) - N25 • Other non structural concrete - N20

All concrete work shall be designed and constructed so that long term shrinkage cracking occurs at controlled joints and locations. Appropriate provision shall be made for thermal expansion. Cover to reinforcing steel, surface finishes, and curing of concrete shall all comply with the respective requirements of AS 3600. Roundabout islands, splitter islands, other small traffic islands shall be provided with stencilled concrete, “flagstone” pattern, in a colour nominated by the RCMB, 150mm thick, reinforced with RF82 mesh with 40mm of top cover. Alternative treatments are to be presented to RCMB for approval.

Rural City of Murray Bridge, V 1.0 3-12

Page 36: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

3.4.6 Block Paving

Concrete Segmental Paving Units within road pavements shall be interlocking, minimum 80mm thick, complying with the requirements of Concrete Masonry Association of Australia (CMAA) code “Concrete Segmental Pavements – Guide to Specifying” (T44). A Herringbone laying pattern shall be used. The shape and colour of individual units shall be approved by RCMB, and be readily available from local suppliers. They shall be embedded in a 20mm thick layer of Paving Bedding Sand which shall form part of a road pavement with a minimum thickness of 300mm, subject to detailed design. Paving bedding sand shall comply with the DPTI standard specification Part 215 “Pavement Materials” – Sa - A. The material used for filling between pavers shall comply with CMAA code “Design Guide for Residential Accessways and Roads” (T45) Table 6 Grading Envelope for Joint Filling Material. Edge restraint and detailing shall be submitted to RCMB for approval. The finished levels of the block paving shall be to an even and plane surface to within +3 mm, -0 mm from the design levels shown on the drawings. Particular care shall be taken to ensure that the levels of adjoining units correspond and that the units along the edges are between 5 and 10mm above the lip of the adjacent concrete gutter to provide proper drainage of the pavement. The skid resistance of the final block paved surface shall be at least equal to that of the adjoining asphalt surfaces.

Rural City of Murray Bridge, V 1.0 3-13

Page 37: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

3.5 Footpaths and Cycleways

3.5.1 Footpaths New development should seek to complete or enhance the existing footpath network by developing efficient walking links, particularly to adjacent key destinations such as schools, shops, bus stops, and reserves. Emphasis is to be placed on ensuring compliance with the Disability Discrimination Act where footpaths form part of a link to RCMB or Community facilities. Footpaths are to be provided along the road network in accordance with Table 3.3: Standard Residential Road Design Elements. Footpaths shall be a minimum of 1.5m wide in accordance with RCMB Typical Detail Drawing 2012-5001-001 and 2013-5000-001. Grades shall be designed in accordance with AS1428. Kerb Ramps shall be provided at every corner radius where footpaths are proposed, and include Warning Tactile Ground Surface Indicators. The location is to be approved by the RCMB. Kerb ramps shall comply with AS1428 standards. For further guidance on design of footpaths refer to AUSTROADS “Guide to Road Design Part 6A: Pedestrian and Cyclist Paths” and “Cycling Aspects of Austroads Guides”.

Rural City of Murray Bridge, V 1.0 3-14

Page 38: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

3.5.2 Provision for Cyclists New development shall incorporate and support the existing bicycle route network, and any other relevant proposals or requirements of the RCMB Local Area Bicycle Plan, June 2001. Detailed design shall be in accordance with AUSTROADS “Guide to Road Design Part 6A: Pedestrian and Cyclist Paths”. Bicycle lanes, or an approved equivalent facility, shall be provided where the daily two-way traffic volume exceeds or is likely to exceed 3000 vehicles per day. The desirable minimum width is 1.5m for cycle lanes on carriageways. Signs and line marking are to be provided in accordance with the provisions of AUSTROADS Part 6A: Pedestrian and Cyclist Paths and DPTI Pavement Marking Manual. The needs of Cyclists shall be considered in relation to the design of traffic management devices and at intersections. Facilities for cyclists not located on the carriageway, shall be designed as Shared Paths. Guidance on the design of Shared paths is also contained in AUSTROADS Part 6A: Pedestrian and Cyclist Paths.

Rural City of Murray Bridge, V 1.0 3-15

Page 39: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

3.5.3 Footpaths and Cycleways Construction Standards Footpaths and Cycleways shall be constructed in concrete with a minimum thickness of 100mm, reinforced with F62 mesh (placed above the centre of the slab, top cover 30mm, 50mm cover at joints), control joints placed a maximum of 6m apart, in accordance with RCMB Typical Detail Drawing 2012-5001-001 and 2013-5000-001 The thickness of concrete Footpaths and Cycleways adjacent to all development sites with a planned commercial or industrial land use shall be 150mm thick, reinforced with F82 steel reinforcing mesh (placed above the centre of the slab, minimum top cover 30mm, 50mm cover at joints), control joints placed a maximum of 6m apart. Specific approval of detailing is required for the use of Concrete Segmental Paving Units on Footpaths or Cycleways. Pavers shall have a minimum thickness of 60mm, complying with the requirements of CMAA code “Concrete Segmental Pavements – Guide to Specifying” (T44). Pavers shall be laid on a minimum thickness of 75mm of compacted quarry rubble free of clay and deleterious materials, and embedded into a 20mm layer of Paving Bedding Sand. Detailing and edge restraint is to be submitted to RCMB for approval. The width of Footpaths and Cycleways shall not be obstructed by street furniture, lighting poles, bus shelters, street trees etc. Where Footpaths and Cycleways are proposed to be constructed along residential street frontages a 100mm diameter “Sewer Grade” UPVC stormwater sleeve shall be provided under the path adjacent to each respective kerb adaptor to facilitate the disposal of stormwater from the property. The installation of the pipe should ensure a minimum fall of 1 in 100 towards the kerb.

Rural City of Murray Bridge, V 1.0 3-16

Page 40: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

3.6 Signs, Pavement Marking & Public Lighting

3.6.1 Road Signs All traffic signs shall be installed in accordance with the requirements of the “Code of Technical Requirements for the Legal Use of Traffic Control Devices” and AS 1742 Manual of Uniform Traffic Control Devices. The plans depicting road signage arrangements (for placement on both new and existing roads) shall be approved by RCMB before installation.

3.6.2 Pavement Marking

All pavement marking, rumble bar medians, etc. shall comply with the requirements of AS 1742 Manual of Uniform Traffic Control Devices, the “Code of Technical Requirements for the Legal Use of Traffic Control Devices”, and conforming to the requirements of the DPTI, Contract Specifications; Part 245 “Pavement Marking Materials” Part 246 “Pavement Marking Manual” Kerbing for median strips and the central and splitter islands of roundabouts etc. shall also be painted as set out in those publications.

3.6.3 Street Names All streets are to be named in accordance with RCMB’s Property Identification Policy – (Road Naming and Road/Street Numbering) – C17. Street name signs shall be provided at the threshold of each new road and opposite T junctions. Street name signs are to be installed in accordance with AS 1742.5 Street Name and Community Facility Name Signs and the following provisions,

• The sign is to be mounted on a 3000mm long, 50mm nominal bore galvanised steel post, the bottom 600mm of which will be inserted into a galvanised steel sleeve suitably anchored into the ground.

• The sign blade shall be Sign-Flextm polycarbonate compound or

similar approved high quality vandal proof product, 1000mm long (Maximum), and 150mm high with a square end.

• Where two lines of text is required e.g. “No Through Road’ following

the street name the sign will be 1000mm long (Maximum), 200mm high.

• The sign shall be mounted to the post using aluminium brackets with

anti vandal bolts.

Rural City of Murray Bridge, V 1.0 3-17

Page 41: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

3.6.4 Public and Street Lighting Public lighting is to be provided in all streets and roads to the boundary of the development. Public lighting shall also be required in reserves where access to structures within the park is a feature, or paths within the park form a linear link. The level and standard of lighting shall be determined according to AS 1158 Series and Table 3.6. Location Category* Access Road, P5 Minimum Local Street P4 Minimum Collector Road P3 Minimum Any residential street adjacent reserves & open space, local shops or community facilities

P3 Minimum

Footpaths, shared use paths & Cycleways located outside road reserve

P3 Minimum

Table 3.6 Minimum lighting standards

*Higher classification may be requested based on criteria of AS1158 Lighting on public roads will only be approved if compliant with SA Power Networks Standard Tariff requirements. For further guidance refer to SA Power Networks Utilities public lighting web page: http://www.sapowernetworks.com.au/centric/home.jsp The selection and design of Public lighting in Public Open Space should be energy efficient and environmentally sustainable. Proposed methods of lighting are to be submitted to RCMB for approval. Solar powered lighting is the preferred method. RCMB may require lighting to be compliant with SA Power Networks Standard or CLER Tariff requirements. All fixtures and fittings shall be readily available from local suppliers. Street Light Columns are to be located in accordance with SA Power Networks Technical Standard.

Rural City of Murray Bridge, V 1.0 3-18

Page 42: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

3.7 Verges All verges shall slope down from the property boundary to the top of kerb level. The maximum slope shall be 5%, and the minimum slope shall be 2%. For properties which fall away from the road reserve, the verge shall have a minimum fall from the property boundary to the adjacent kerb of 2%. Any resulting differences between the finished surface and natural surface at the property alignment shall be handled by battering up or down to the natural surface level, external to the road reserve. Such batters shall have a maximum slope of 1 Vertical to 4 Horizontal on future allotments, and a maximum slope of 1 Vertical to 6 Horizontal on future public reserves. Where it is proposed to use retaining walls, to modify natural surface levels a separate Development Approval may be required to assess the visual impact on the future streetscape. All verges shall be excavated to a depth of 75mm below the surface of the footpath and the top of kerb and backfilled with RCMB approved topsoil to provide a growing medium with a raked finish and containing no material with a particle size greater than 20mm. All disturbed areas within the road reserve shall be hydro mulched, turfed or seeded to the satisfaction of RCMB. Refer to RCMB Typical Detail Drawing 2013-5000-001 for details.

3.8 Service Installations within Road Reserves Under road boring is the preferred method for the installation of services in existing road pavements. Boring is to be carried out in accordance with the requirements of the DPTI, contract specification; Part 207 “Under Road Boring”. Wherever it is not possible to carry out boring and it is necessary to excavate trenches through existing RCMB roads, all disturbed areas within the road reserve, including pavement, footpath and verge areas, shall be reinstated in accordance with the requirements of the DPTI, contract specifications; Part 206 “Trench Excavation and Reinstatement” Part 208 “Pavement Reinstatement” Pavement Reinstatement Configuration A work permit via the RCMB Application form - Authorisation to alter a public road, must be obtained prior to any work being undertaken within or on RCMB’s road reserve area.

Rural City of Murray Bridge, V 1.0 3-19

Page 43: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

CHAPTER 4

Stormwater Drainage Assets

Page 44: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

4 STORMWATER DRAINAGE ASSETS

4.1 Introduction Stormwater management forms an integral part of any development. The RCMB (May 2007) ‘Stormwater Management Plan’ (SMP) and the RCMB (July 2008) ‘Integrated Water Resources Management Plan’ (IWRMP) are the strategic framework, in terms of planning for and managing stormwater and runoff from existing and future developments within RCMB. General factors noted for the Murray Bridge area include:

• Flooding has been a major issue in areas of Murray Bridge over recent years with the major 100 year ARI event being exceeded with an estimated 200-300 year ARI event;

• Seasonal and annual variability in rainfall; and

• High rates of evaporative losses. These factors should be considered in planning and designing stormwater management systems, and the selection and design of stormwater quality improvement devices.

Rural City of Murray Bridge, V 1.0 4-1

Page 45: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

4.2 Documentation Requirements Prior to finalising the assessment of a proposed development RCMB must ensure that the approved development will be provided an adequate degree of flood protection, and that the stormwater management system will adequately treat and dispose of any stormwater generated by the development. The nature of the proposed development will determine the level of information required to be submitted as part of the development application. For all developments, site plans submitted as part of a Development Application should show the following:

• Existing site levels or contours with adjacent road, kerb and drainage invert levels.

• Finished surface levels relative to estimated flood levels. • Proposed levels and grading of pavement. • Conceptual layout of the proposed drainage system and outlet. • The location, positioning and type of proposed Stormwater Quality

Improvement Devices (SQID). • Delineation and area of all sub-catchments. • Minor stormwater flow paths (minQ5), and flow path for the major

event (Q100) A Water Quality Improvement Plan (WQIP) will also be required. Section 4.3.3 discusses the requirements of WQIP's. Engineering calculations may also be required to demonstrate that sufficient space has been allocated to stormwater management infrastructure. In relation to any proposed permanent water bodies predictive modelling will be required of the impacts of the proposed basin on both groundwater quality and water table levels, and geotechnical data upon which the modelling is based. Prior to commencement of any works on site detailed construction plans and specifications are to be submitted to and approved by RCMB. Final Stormwater Construction Drawings should include:

• A General layout plan at a suitable scale showing, Catchment Area, Design Contours, and the general layout of the drainage system, including all drainage easements, reserves and natural water courses.

• A drainage system layout plan at a suitable scale showing pipeline

location, drainage pit location and number, road centreline chainage, and the location of any basins and SQID.

• The drainage system longitudinal sections showing the pipe size, type

and class, road chainages, pipeline grade and hydraulic grade line.

Rural City of Murray Bridge, V 1.0 4-2

Page 46: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

• Detail plans at a suitable scale for all non-standard pits, open channel

designs, and SQID.

• Details of any temporary works, drains or banks proposed as part of the development project.

Engineering calculations may be requested for audit should it be deemed necessary by RCMB.

Rural City of Murray Bridge, V 1.0 4-3

Page 47: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

4.3 Stormwater Drainage Design The following goals, as detailed in the SMP apply to stormwater drainage design in the RCMB. Goal 1: Flood Management • Provide and maintain an adequate degree of flood protection to existing and future development. Goal 2: Water Quality Improvement • Improve water quality to meet the requirements for protection of the receiving environment and downstream water users. Goal 3: Water Use • Maximise the use of stormwater runoff for beneficial purposes while ensuring sufficient water is maintained in creeks and wetlands for environmental purposes. Goal 4: Amenity, Recreation & Environmental Enhancement • Where possible, develop land used for stormwater management purposes to facilitate recreation use, amenity & environmental enhancement. Goal 5: Asset Management • Ensure the condition of stormwater infrastructure is suitable for its intended purpose.

4.3.1 Design Principles The drainage system is to be designed in accordance with the requirements of the Institution of Engineers, Australia publication, “Australian Rainfall and Runoff, a guide to flood estimation Volume 1” Current Edition (AR & R). The design shall cater for the major storm event as well as minor storm events. The overall planning and design of the stormwater management system is to be in accordance with the recommendations of, Department of Planning and Local Government, “Water Sensitive Urban Design Technical Manual for the Greater Adelaide Region”, Government of South Australia, Adelaide, 2009 and Institution of Engineers, Australia publication, “Australian Runoff Quality, a guide to water sensitive urban design” 2006.

Rural City of Murray Bridge, V 1.0 4-4

Page 48: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

4.3.2 Site Discharge Limits The RCMB’s SMP is based on an assumed level of development across the specific catchment area. Development requirements are specified in Section 5 of the SMP for specific catchments. Onsite Detention / Retention performance standards for catchments and zones are specified to manage stormwater discharge to a level that can be accommodated by downstream infrastructure. The peak discharge for the post development state needs to be calculated and appropriate mitigation methods used to reduce the post development peak discharge to the site discharge limit. For areas where performance measures are not specified post development conditions will need to match pre-development conditions, unless it can be demonstrated that there will be no adverse impacts on downstream properties or infrastructure. Where a catchment has no outlet, site discharge volumes will also need to be considered.

4.3.3 Water Quality Improvement Prior to development approval a Water Quality Improvement Plan (WQIP) is required. The objective of the WQIP is to present a conceptual design, supported by sufficient design data, to demonstrate that the objectives of the RCMB Development Plan and SMP will be achieved, in relation to Water Quality. The RCMB Development Plan requires stormwater quality to be of a physical, chemical and biological condition equivalent to or better than its pre-developed state. SMP objectives for Water Quality Improvement include;

• Improve the quality of stormwater discharged downstream, with particular emphasis given to nutrients and suspended solids.

• Minimise the quantity of gross pollutants discharged to the River to

improve amenity and safety.

• Intercept and/or separate pollutants at source from land uses and activities having a high potential for pollutant generation.

The WQIP is to Address these objectives. A suggested methodology is that presented in Chapter 3, Department of Planning and Local Government, “Water Sensitive Urban Design Technical Manual for the Greater Adelaide Region”. It should be noted that for small scale developments, not all steps in the process may be required. The development of a WQIP is discussed further in Appendix 1.

Rural City of Murray Bridge, V 1.0 4-5

Page 49: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

4.4 Detailed Design

4.4.1 Hydrological and Hydraulic Calculations Drainage is to be designed to accommodate runoff from lots based on current available zoning information or proposed future zonings, where applicable. The impervious site coverage of residential lots should be based on Table 4.1.

Lot Size (m2)

Impervious Site Area (m2)

Fraction Impervious (%)

<500 90> 500 300 60 800 360 45

1200 450 37.5 1500 500 33

2000 or greater 30

Table 4.1 Impervious Site Area based on Lot Size Road reserves are to be assumed 100% impervious for the pavement area and 50% impervious for verge areas. Rainfall Intensity-Frequency-Duration data for RCMB is included in Appendix 4. For continuous simulation modelling the designer shall seek confirmation from RCMB on the suitability of hydrological data. For rational method calculations the maximum time of concentration used in urban areas should be 20 minutes unless sufficient evidence is provided to justify a greater time. The minimum time of concentration in an urban area used for calculations is to be 5 minutes. For hydraulic analysis, the highest value is to be adopted of the top of the outlet pipe, or the 1 in 100 yr ARI flood level for downstream water surface levels. Where engineering calculations are requested for audit by RCMB they are to be submitted in the following format; For the Minor Drainage system

• Hydrological calculation summary sheets in the form of the example given in Technical Note 6 of AR & R.

• Hydraulic calculation summary sheets in the form of the example given

in Technical Note 9 of AR & R.

Rural City of Murray Bridge, V 1.0 4-6

Page 50: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

Major Drainage system design will normally be undertaken with the aid of computer software programs. It is the designers’ responsibility to provide the RCMB with sufficient information to confirm that the adopted software and assumptions are suitable. As a minimum the following information will need to be provided;

• Name and version of software package. • Full details of the modelling assumptions. • Review of model calibration and sensitivity analysis. • Copy of the model’s “error listing” output file.

4.4.2 Major System Criteria The major storm event is the 1 in 100 year ARI; however in some instances a higher ARI may be required for specific infrastructure. The overland flow path must be contained within reserves a minimum of 10 metres wide, and not enter into private property. The maximum allowable depth of water is 0.2 metres and the maximum velocity x depth product is to be limited to 0.4m2/s. RCMB Development Plan requires 300mm freeboard between the 1 in 100 year ARI flood level and all floor levels. In conjunction with the design of the major drainage system consideration is to be given to ensuring lot levels provide suitable building conditions to achieve this requirement. Where existing overland flow paths exist, developments are to be planned to ensure that the capacity of the existing overland flow path is maintained, and there are no adverse impacts on adjoining properties. RCMB will not permit the use of levees in new developments.

4.4.3 Minor System Criteria The Minor drainage system is to be designed to accommodate the 1 in 5 year ARI. The desirable maximum Inlet Pit depth is 1.5m to facilitate maintenance. Inlet Pits are to be located to satisfy the following;

• Gutter flow widths limited to 2.5m for the 1 in 5 year ARI • Maximum pit spacing 90m where flow widths are not critical. • At the mid-point of allotment frontages to minimise conflict with

service conduits and future driveways. • Upstream of pedestrian paths and kerb ramps. • Swale depths limited to 200mm

Rural City of Murray Bridge, V 1.0 4-7

Page 51: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

Junction pits/Manholes are to be provided:

• At all changes in direction and grade. • At junctions • To enable access for maintenance.

Piped systems are to be designed to satisfy the following;

• Maximum water level to be 150mm below the surface level of pits • Reductions in pipe sizes for downstream pipes are not permitted. • Flow velocities between 0.6m/s and 5m/s. • All pipe sections are to be designed to be free draining.

The design of the minor drainage system should incorporate Water Sensitive Urban Design (WSUD) elements to provide for the deceleration, detention, infiltration and cleansing of stormwater.

4.4.4 Existing Watercourses The Major drainage system should be based on the existing system of natural watercourses. The treatment and rehabilitation of existing watercourses is dependent on their condition, and the site context. The choice of treatment should be based on a review of the site, catchment and receiving waters. Refer to “Australian Runoff Quality” (ARQ) Chapter 12 Urban Waterways for guidance on the selection of appropriate treatment and rehabilitation. For the localised modification of alignment and cross section, and reinforcement at specific locations, the use of ‘soft’ engineered solutions is encouraged. Solutions must be adequately designed and established to ensure long term stability. Designs should consider the use of geotextiles and plantings to provide erosion resistance where possible. Where rock armour is required, partially embedded or grouted natural rocks/boulders should be used, with planting between rocks to soften visual impacts. Where site constraints limit the available space for channel rehabilitation, Gabion Mattresses are to be used. Concrete lining is generally unacceptable. An extended maintenance period (i.e. greater than the minimum 12 month defects liability maintenance period often specified) may be required until the channel has sufficiently stabilised and vegetative cover is well established.

Rural City of Murray Bridge, V 1.0 4-8

Page 52: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

4.4.5 Detention and Retention Detention and retention of stormwater may be required to ensure that runoff does not exceed pre-development flow rates, and volumes. Water Sensitive Urban Design involves retention-based stormwater management. At the subdivision scale this includes stormwater harvesting and reuse, and maintaining soil moisture through infiltration measures incorporated in the drainage system. Detention implies holding of runoff for relatively short periods of time to reduce peak flows. Detention should only be adopted under the following situations;

a) where soil types or topography are unsuited to retention technologies, b) where maximum yield from runoff is desirable with control of peak

flows, c) or to supplement retention strategies when sufficient land area Is not

available. Initial sizing of detention and retention may be undertaken using manual techniques in order to determine the order of magnitude of the storage required. The final sizing however, should be completed with the aid of computer models, and water balance calculations. In addition to local catchment analysis, an assessment should also be made of the impact on a catchment wide basis. Detention and retention storages may have multiple uses such as pollution control, environmental enhancement, aesthetics, as well as hydraulic functions. Large systems must be incorporated in subdivision design, and located in a drainage reserve, or Public Open Space (POS). They may incorporate elements such as sedimentation basins, constructed wetlands, and ponds. Their design is to consider the following provisions;

• Side slopes are to be a maximum of 1 vertical to 6 horizontal • Depth indicators provided indicating maximum depth in the basin • Unfenced landscape areas limited to 100 year ARI ponded depth of

1.2m. • The outlet/inlet grates designed such that any child will be able to crawl

away from the grate under all operating conditions. • A stormwater pollutant trap should be installed upstream.

Detention and retention can be incorporated at the street scale, to minimise the requirements of a major detention/retention structure. They may incorporate elements such as Swales, infiltration devices, and small basins.

Rural City of Murray Bridge, V 1.0 4-9

Page 53: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

Smaller systems may be located in POS, road verges, in medians or traffic islands, or on private land. Their design is to consider the following provisions;

• Detailed assessment of soil types and potential impacts on adjoining structures and infrastructure

• Pre-treatment of stormwater is required prior to entering infiltration devices

• Landscaping should be low maintenance • Emptying time limited to 12 hours for ARI of 1 year or less, 1.5 days

ARI 5 years, 3.5 days ARI 100 years Systems located on Private land will require the registered proprietor(s) of the lot(s) to enter into a covenant pursuant to Section 97A of the Land Title Act 1994, to ensure management of the system is in accordance with the approved report and plans.

4.4.6 Outlet Design Connection to existing RCMB infrastructure should be based on a survey undertaken for the works. Outlets into natural watercourses and open channels are required to incorporate works designed to provide protection from local scouring and undermining of the outlet structure, and include measures to dissipate the outflow velocity. Vegetated swales may be required downstream from piped outlets to achieve water quality improvement targets. Where the outlet is to Public Open Space (POS), the requirements of the Development Plan for POS need to be considered. The opportunity to construct or enhance a natural self sustaining drainage channel (as opposed to enclosed pipe drainage) is encouraged. Where the stormwater discharge is across POS designated for active recreation, piped drainage must be provided for a 1in 1 year ARI event to ensure that the function or the amenity is not diminished.

Rural City of Murray Bridge, V 1.0 4-10

Page 54: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

4.4.7 Residential Allotment Connections A stormwater connection point is required for each allotment in a subdivision. Where allotments grade away from the street frontage rear of allotment (ROA) drainage shall be provided. All ROA drains shall be contained within easements. Such drains shall be designed to accommodate a 1 in 10 year ARI event. ROA stormwater drainage shall also be provided where the allotments back onto reserves. Land divisions in the Country Living Zone may be exempt from requiring ROA drainage provided; site conditions are suitable for on-site disposal, all allotments are greater then 2000 square metres, and any existing dwellings and outbuildings are provided with detention/retention capable of treating and disposing of the 1in 100 year ARI 3 hour duration runoff volume.

4.4.8 Drainage Easements

Easements need to be provided over all drains in any allotments not being a road reserve. Unless otherwise required by RCMB such easements are to be a minimum of 3 metres wide. The width of easements will need to be increased where the easement contains more than one drain, pipes are located deeper than 1.5m, or pipe diameters are greater than 450mm. Where a development relies on an adjoining property to provide back of allotment drainage or an outlet for the proposed drainage system, a Deed of Agreement signed by benefited and burdened parties is required prior to development approval. The Deed of Agreement shall set out the requirements for the creation and piping of the easement, including construction and maintenance activities, and facilitate future access to the drainage network by RCMB.

Rural City of Murray Bridge, V 1.0 4-11

Page 55: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

4.5 Drainage Construction Standards

4.5.1 Stormwater Pipes Stormwater drainage pipes and box culverts shall be of reinforced concrete construction conforming to AS1597 and AS4058 respectively, and in accordance with the following.

• Minimum pipe size of 375mm, rubber ring joint, minimum Class 2 • Minimum box culvert size of 450mm x 300mm • Minimum clear cover over pipes or culverts shall be 600mm in

general or in accordance with the manufacturers’ specification, AS3725 or otherwise approved by RCMB.

• The minimum vertical and horizontal clearances between a stormwater pipe and any other pipe or service conduit shall be 150mm.

Alternative products are to be submitted to RCMB for approval.

Rural City of Murray Bridge, V 1.0 4-12

Page 56: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

4.5.2 Side Entry Pits and Manholes Side entry pits shall be of reinforced concrete construction in accordance with RCMB Typical Detail Drawing No. 2012-5003-001 and 2012-5003-002 located in Appendix 5 Manholes/Junction pits shall be of reinforced concrete construction a minimum of 900 x 900 mm internal dimension, in accordance with RCMB Typical Detail Drawing No. 2012-5011-001 located in Appendix 5 Alternative details are to be shown on construction plans, submitted to RCMB for approval. All pre-cast pits are to be reinforced concrete construction conforming to AS4198. Circular pits shall be a minimum of 1050mm diameter.

4.5.3 Rear of Allotment (ROA) Drainage The minimum diameter of the pipe for ROA drains shall be 150mm and each allotment shall be provided with a minimum 450mm x 450mm grated inlet pit/junction box, located at the lowest corner of each respective allotment. Junction pits shall be provided at all changes in direction and grade. Longitudinal grades shall be a minimum of 1%. ROA drainage shall be constructed from either fibre reinforced concrete drainage pipe, reinforced concrete pipe, or PVC-U pipe which shall conform respectively to the requirements of AS4139, AS4058 and AS1254. Cover shall be a minimum of 0.6 metres in accordance with the requirements of AS3725, or AS2032. Pits shall comply with AS4198, be constructed of concrete, and have tamper proof lids suitable for sustaining expected loads, in accordance with AS3996.

Rural City of Murray Bridge, V 1.0 4-13

Page 57: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

4.5.4 Pipe Connection to Council Infrastructure Prior to backfilling, the works at the connection must be inspected by RCMB Engineering Department for approval Connection to existing stormwater pipe This method can be used where the diameter of the entry pipe is 375mm or less, and the host pipe diameter is at least 3 times larger than the entry pipe diameter. The connection shall be made in the middle third of the host pipe with a 300mm long stub. Reinforcement in the host pipe is to be cut and formed into a collar, and the stub concreted in to the collar, providing 150mm concrete all round the joint, and rendering the inside of the joint. Inspection of the joint by RCMB is required prior to connection of the entry pipe. Connection to existing side entry pit or manhole An assessment of the required pit modification is to be undertaken at the design stage, to ensure hydraulic properties will not be adversely affected. The connection shall only be made through the wall of the pit (not through a corner) and a minimum of 150mm clearance is required between the outside face of the pipe and the pit corner. The pipe must be sealed using cement mortar and finished flush with the internal wall. Where the entry pipe diameter exceeds 200 mm, the pipe must be installed at the pit invert. A minimum 150 mm clear distance is required between the inlet pipes. Other Connections For complex manholes, or for larger diameter entry pipes, new manholes must be constructed.

Rural City of Murray Bridge, V 1.0 4-14

Page 58: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

CHAPTER 5

DESIGN OF EARTHWORKS

Page 59: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

5 Earthworks Design

5.1 Earthworks Design Existing site conditions need to be determined to identify any potential risks, and plan future works. In some cases site regrading may be required to provide suitable building conditions for residential development. Developers, consultants, builders etc. should contact RCMB Engineering Department for advice on the requirements of any geotechnical investigations, and building floor levels during the concept and planning stage of proposed new developments.

5.1.1 Geotechnical Investigations Prior to development approval, or as part of detailed design, a geotechnical investigation will be required to identify possible impacts or design issues associated with the development. The investigation should include, as a minimum the details set out below;

• Test pitting over the site to minimum depths of 2.5m to establish and

record the presence of any possible rock or groundwater.

• Classification of all different soils encountered on the site, using visual tactile methods by an experienced technician or engineering geologist and verified if necessary by NATA registered laboratory testing.

• Preparation of a stratigraphical model for the site, including a

description of the underlying geology, and soil formation processes, and identification of any potential slip zones, or areas subject to riverbank collapse.

• Definition of the extent of any fill encountered.

The above information shall form the basis of the design of, drainage, and earthworks, associated with the development. Where potential slip zones or areas of possible river bank collapse are identified development may be restricted, based on the level of risk. It should be noted that for sites that involve filling of clay soils at depths greater than 0.4m and sand soils greater than 0.8m a detailed geotechnical investigation is required, prior to development approval, in accordance with AS1726 – Geotechnical Site Investigations. The report shall be certified by a chartered professional engineer registered with the geomechanics society.

Rural City of Murray Bridge, V 1.0 5-1

Page 60: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

5.1.2 Site Regrading Design Requirements Consideration should be given to future building requirements in the design of site regrading. Generally allowing 300mm from the invert of the gutter to the finished ground level at the building line will accommodate future building requirements. Site regrading details are to be approved in conjunction with submission of other engineering details. Normally the detail will be incorporated in Road Design Plans; however in some cases a separate plan may be required. Where site regrading is proposed details shown on plans shall include;

• the depth of cut and fill, • grades of batters and their finished treatment, • location and details of any earth retaining structures, • volumes of any excess or deficiency in material.

Filling on allotments shall be undertaken in a controlled manner, to enable re-classification of the site to support standard residential footings designed in accordance with AS2870. Batters shall be a maximum grade of 1 vertical to 4 horizontal on private property, or otherwise determined by geotechnical investigations. On public land, batters shall be a maximum of 1 vertical to 6 horizontal to accommodate future maintenance requirements. Retaining walls over 1 metre in height are required to undergo separate development approval unless included in the original development application. No earth retaining structures are permitted in the verge area.

Rural City of Murray Bridge, V 1.0 5-2

Page 61: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

5.1.3 Earthworks Construction The specifications for the works shall provide full details of the proposed earthworks construction procedures. All top soil is to be stripped, stockpiled and re-spread to provide a minimum of 75mm of topsoil to all disturbed areas. All disturbed areas should be stabilised within 14 days of completion of earthworks, and revegetated in accordance with a Soil Erosion and Drainage Management Plan (refer Section 7.4). Where significant earthworks movements are proposed agreement is to be sought with RCMB on suitable haulage routes. The payment of a bond may be required by the contractor/developer where RCMB has some concern about the ability of a haul road to sustain loads without undue damage or maintenance requirements. Where imported fill is to be used the supplier of that material is to provide a written statement of the source of the material and that it is clear of known contaminants.

Rural City of Murray Bridge, V 1.0 5-3

Page 62: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

CHAPTER 6

LANDSCAPE AND OPEN SPACE

Page 63: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

6 LANDSCAPING AND OPEN SPACE

6.1 Introduction Landscaping of residential subdivisions includes consideration of the Streetscape, and Public Open Space (POS) elements of a development proposal. The configuration of POS and Streetscape should aim to provide pleasant, functional and accessible open spaces providing a range of physical environments for active and passive recreational opportunities. Design of landscaping should be closely linked with stormwater management to ensure a coordinated approach to managing stormwater quality, and meeting irrigation demand. The Development Act requires contribution for POS either as land or monetary payment or a combination of the two. Where a Developer is proposing to make a monetary payment for Public Open Space, in lieu of land, discussions should be held with the RCMB at the concept plan stage.

Rural City of Murray Bridge, V 1.0 6-1

Page 64: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

6.2 Documentation Requirements Concept plans for Landscaping and Open Space should address;

• the location, type, and size of all proposed public open space (POS)

• functional requirements of all proposed POS • streetscape • site conditions, including existing trees • design intent • Irrigation demand and source

Following RCMB approval of the landscape concept plan design but prior to construction, the Developer shall provide a detailed Landscaping and Open Space Plan incorporating construction details, planting schedules, and a technical specification. The Landscaping and Open Space Plan shall be prepared by a qualified landscape architect and lodged with the RCMB in hard copy and electronically. Typically, Landscape Design Plans will identify:

• Existing elements to be removed / retained • Site grading and drainage • Surface treatments and layout • Planting design • Construction details • Irrigation design • A plant schedule listing the botanical name, the container size and

the quantity/density of planting. Typically, the Technical Specification will comprise:

• Site preparation and demolition • Earthworks and cultivation • Irrigation • Concrete works, and paving • Planting schedule and turf specification • Park and Street Furniture and Fencing • Lighting • Maintenance requirements and Schedules • Landscape Work Schedules.

Approval of RCMB for any variations to the approved plans and specifications during the development stage must be sought by the landscape architect.

Rural City of Murray Bridge, V 1.0 6-2

Page 65: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

6.3 Landscape Design Principles

6.3.1 Landscape Design Principles

Developers will need to consider a range of general design principles when planning streetscapes and open space designs. Reference to “Water Sensitive Urban Design” (WSUD), will assist designers to meet Councils open space objectives. Refer to the Technical Manual, Greater Adelaide Region which is available on Council’s web site.

http://www.murraybridge.sa.gov.au/

Considerations should be given but not limited to;

• The configuration of open space to complement existing vegetation to attract and support fauna native to the local area and to provide a buffer between development and viable ecosystems.

• Integration of streetscapes, parks, reserves and habitat corridors, to provide linear connections within and external to the development.

• Identify opportunities for the retention and/or re-introduction of plant species that are native to the site.

• Establishment of plant material of appropriate structure and species composition.

• Future maintenance of landscape works and ensuring that works are to the appropriate standard, of durable materials and low maintenance design.

• Conservation of irrigation water by using designs appropriate to the climate and utilising water-wise plant selection.

• Maximise opportunities for water re-use where opportunities present themselves.

• Ensuring that the design and development of the site does not increase the rate of surface run-off and that opportunities to improve the quality of surface water before leaving the site are examined.

• Incorporation of on-site detention/retention of stormwater and collection for re-use into the design where opportunities present themselves.

• Increasing the scope of infiltration by minimising sealed surfaces and maximising the use of porous surfaces.

• Utilising appropriate planting to reduce the velocity of stormwater runoff and ensure even flow distribution to avoid erosion.

Rural City of Murray Bridge, V 1.0 6-3

Page 66: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

• Planned landscapes being complimentary to building structures, and, to maximise the efficiency of buildings, plantings should be established to demonstrate maximum solar gain.

• Plantings being designed to reduce the deleterious effects of wind and other natural climatic events, to provide shade, and promote air circulation to assist the management of the micro climate.

• Using landscape design to create an attractive visual setting for buildings, relative to the scale of the built form.

• Using landscape design to provide an overall character and identity of the streetscape to reinforce the function and character of existing surrounds.

• The orientation of the subdivision design should consider incorporation of frontages to open space to promote natural surveillance and community ownership.

• Design of street lighting and public open space lighting to provide adequate illumination, taking into account the effect of vegetation growth and any other potential obstructions.

6.3.2 Integration with Stormwater Management Best Practice Stormwater Management involves the integration of Public Open Space and Stormwater Management. Natural watercourses should be retained and enhanced where possible, and integrated with linear open space networks to create multiple use corridors. The design of Streetscape offers many opportunities to incorporate Water Sensitive Urban Design Elements to create an attractive and sustainable urban environment.

Rural City of Murray Bridge, V 1.0 6-4

Page 67: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

6.3.3 Existing Trees An “Existing Tree Survey Plan” should accompany the land division plan and be submitted at the time of lodgement. The following information must be clearly shown;

• identification of the species including the botanical name of the tree; • the location of the tree accurately indicated, and; • the height and canopy of the tree and girth of the trunk. • Indicate trees to be retained and removed

Where it is proposed to remove Native Vegetation a proposal may require referral to other agencies for assessment and approval. If necessary, the establishment of a Land Management Agreement protecting significant trees may be required.

Rural City of Murray Bridge, V 1.0 6-5

Page 68: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

6.3.4 Street Trees Street tree planting should be located at the centre of allotments at a rate of one (1) per allotment. Refer to Table 6.1 Suitable Tree Species for RCMB for selection of appropriate species. Alternative Tree Species can be selected in consultation with the RCMB. Trees should have a minimum height of 2 metres at the time of planting, be double staked with 50mm hardwood stakes installed parallel to the road and loose tied. Trees should be planted in a mulched 1 metre diameter bowl with 100mm agricultural drain looped under the root zone to facilitate watering. Street trees are to be planted within the RCMB verge in accordance with RCMB Typical Detail Drawing Numbers 2012-5006-001 to 2012-5006-005 Consideration is to be given to incorporating stormwater harvesting to meet irrigation demand for street trees and water quality improvement targets. RCMB encourages innovative design proposals for stormwater source control, such as diverting stormwater from the Kerb and Gutter for watering Street Trees. The trees shall be maintained in good health by the applicant for a period of 12 months from the date of the issue of a certificate of practical completion. Any dead, diseased and damaged trees shall be replaced during this period.

Rural City of Murray Bridge, V 1.0 6-6

Page 69: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

Street Tree or Reserves Suitable for Reserves Only Local Native Species Euc. Calicogona Brachychiton populensis Euc gracilis Acacia pendula Euc sociali Callitris preissii Euc porosa Euc incrassata Euc odorata Other Native Species Euc. Landsdowneana ‘albopurpurea’ Euc cneorifolia Euc salubrus Euc Campaspe Euc cladacalyx ‘nana’ Euc robusta Euc stricklandi Euc platypus Euc spathulata Euc maculate Euc ethronema Euc diversifolia Euc botryoides Angophera costata Geuirgera parvifolia Melaleuca lanceolata Callistermon viminalis “harkness” Non Native Species Jacaranda mimosifolia Fraxinus ‘Raywood’ Pyrus ussuriensis Koelrutaria paniculate Fraxinus excelsior Melia azedarach (low seeding form) Cupaniopsis anarcdiodes Platanus occidentalis Qurcus robur Pistacio chinensis

Alternative tree may be selected in consultation with The RCMB

Table 6.1 Suitable Tree Species for RCMB

Rural City of Murray Bridge, V 1.0 6-7

Page 70: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

6.3.5 Trees in Reserves Tree planting in reserves shall include a mix of native and selected exotic species to reflect existing plantings in nearby and surrounding areas. For guidance on species selection refer to Table 6.1 Suitable Tree Species for RCMB. The following should also be taken in to consideration;

• Existing trees on the site • Soil stabilisation needs • Accessible shade • Ease of future maintenance • Proximity of fences and pathways (trees should not be planted

closer to fences that abuts private property than their mature height). • Bushfire risk minimisation • General aesthetic quality

Reserve areas should be designed via consultation with RCMB’s Environmental Officer.

6.3.6 Grassing All grassed areas shall:

• Be provided a minimum depth of 150mm of suitable topsoil to provide a satisfactory growing medium.

• At the end of the maintenance period be fully established with

Kikuyu. If seeding is used a mixture of 95% Rye and 5% Kikuyu is recommended.

6.3.7 Traffic Islands and Roundabouts Proposals for landscaping of traffic islands and roundabouts shall be submitted to RCMB for consideration. Proposals need to demonstrate minimal maintenance requirements, and will generally only be permitted as part of a Stormwater Quality Improvement Device.

Rural City of Murray Bridge, V 1.0 6-8

Page 71: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

6.3.8 Fencing Discussion with RCMB on specific requirements is required. Generally reserves shall be fenced with 1800mm capped Colourbond fencing with galvanised posts and rails facing into the adjacent allotment. Alternate fencing may be selected in consultation with the RCMB Where a reserve incorporates a children’s playground, full or part fencing may be appropriate, e.g. a half fence closer to a road or car park to define or partly separate the playground. In general, playgrounds should be considered for fencing if:

• The playground is located close to a busy road and there is no fence around the reserve

• The playground is close to a busy a car park • The playground is near a permanent or potential water body

(alternatively there could be a barrier around the water body) • There may be a need to separate the playground from other

activities, such as an active sports field • There is a demand for a dedicated enclosure for children and

families, e.g. a playground for toddlers where fencing and the safety of children is a desired feature.

Rural City of Murray Bridge, V 1.0 6-9

Page 72: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

6.3.9 Irrigation An Irrigation Management Plan for the reserves is required by RCMB prior to installation. The plan needs to encompass best water management practices and it should incorporate the following features;

• Irrigation demand is to be met by alternative water sources, such as recycled stormwater, River Murray Irrigation, or reclaimed effluent, supplemented by a SA Water supply.

• All licensing and approvals required from other authorities are to be

submitted with detailed design plans • Where demand is to be met with River Murray Irrigation Water

arrangements are to be made for purchase of water licences in the name of RCMB, and integration with RCMB existing irrigation main network.

• Species selection is to minimise irrigation requirements

The following requirements need to be addressed

• An appropriately sized service connection and water meter are required to all open spaces and reserves with a suitable backflow prevention device fitted to comply with AS 3500.1 section 7and SA Water requirements.

• valves, fittings and backflow prevention devices suitable for

automatic operation and, capable of utilising reclaimed water (class A) and mains water.

• The installation of an irrigation system to all landscaped traffic

islands and roundabouts is mandatory Irrigation systems are to be installed to RCMB satisfaction in accordance with RCMB’s Irrigation Design and Installation Standards.

Rural City of Murray Bridge, V 1.0 6-10

Page 73: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

6.3.10 Furniture Park furniture including seats, tables, litter bins, bike racks, drinking fountains etc will be of a type and manufacture approved by RCMB. Seats should have arm rests to assist people who are frail and have difficulty lowering and raising themselves. Tables should be of a design that is accessible and inclusive, with greater capacity at the ends for forward approach by a person using a mobility aid. Materials are to be durable and require minimal maintenance for their intended life. The use of timber elements is not encouraged due to ongoing maintenance requirements.

6.3.11 Paths All facilities in POS should be provided with a continuous accessible path of travel to facilitate independent, safe and equitable access to ensure compliance with RCMB Disability Discrimination Act Policy. Paths within reserves should create pedestrian and/or bicycle links to existing paths in the vicinity of the development. Refer to Section 3.4 for detailed design requirements. For reserve areas it should be noted that 600mm on both sides of the footpath should be at the same grade and flush with the path.

6.3.12 Lighting Public lighting may be required in reserves where paths or access to other structures are features of the park. For more information regarding Public Lighting see section 3.6.4.

6.3.13 Entrance Statements All entry statements and walls require separate Development Approval. Installation shall only occur once construction and landscaping details have been approved in accordance with conditions set out in a development approval.

Rural City of Murray Bridge, V 1.0 6-11

Page 74: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

CHAPTER 7

SITE MANAGEMENT

Page 75: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

7 SITE MANAGEMENT

7.1 Introduction The Developer and contractors are responsible for ensuring compliance with the Environment Protection Act 1993, and its various policies, and the requirements of any other relevant statute, by-law, standard or policies relating to Occupational Health Safety & Welfare (OHS & W), Environmental Protection, and protection of the River Murray under the River Murray Act.

7.2 Construction Management Plan A Construction Management Plan (CMP) prepared specifically for the works shall be provided to Council. The CMP is to address in detail how the site will be managed to minimise disruption to adjoining properties and demonstrate how compliance with the Environmental Protection Act will be achieved. The CMP shall detail OHS&W, (including Risk Assessments & Job Safety Analysis), traffic management, and any other matters that are relevant to the site and maintaining amenity in adjoining areas. It should also consider the broader objectives of material recycling, waste management and environmental initiatives, including water conservation.

7.3 Soil Erosion and Drainage Management Plan A Soil Erosion and Drainage Management Plan (SEDMP) needs to be submitted as part of engineering design plans. The plan should include a site layout together with a written procedure and implementation plan. The SEDMP should be prepared in accordance with the Environment Protection Agency Code of Practice 'Stormwater Pollution Prevention Code of Practice for the Building and Construction Industry'. Environment Protection Authority, March 1999, and cover all stages of works including maintenance of the site up to the end of the defects liability period. The SEDMP should also clearly indicate areas that are not to be disturbed. These areas are to be clearly marked on site to ensure construction activities do not affect areas to an extent greater than is necessary. Where plant pest species are present on the site the SEDMP should also address management and control of its' spread.

Rural City of Murray Bridge, V 1.0 7-1

Page 76: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

7.4 Existing Trees All existing trees to be retained shall be protected during construction activities. The following tree protection measures shall be undertaken;

• All construction drawings including the landscape design plan, earthworks, and drainage and service drawings shall show the trees to be retained and their protection zones.

• Each tree is to be physically protected by providing a fence defining

the Tree Protection Zone and shall remain in place until all works are completed.

• There is to be no storage of materials or machinery or site

office/sheds, nor is cement to be mixed or chemicals spilt/disposed of in the area, soil levels altered or excavations undertaken, or stockpiling of soil or rubble within the tree protection zone.

The applicant shall contact RCMB to arrange a site inspection to verify that tree protection measures have been installed prior to commencement of excavation. In some instances a Land Management Agreement may apply to the protection of Existing trees. The Developer shall ensure that the provisions of the Land Management Agreement in respect to trees are complied with.

7.5 Working Hours The contractor is required to comply with relevant policies under the Environment Protection Act. Within the area of RCMB it is recommended that construction activities on the development site shall only be carried out between the following hours;

• Monday to Saturday - 7am to 5pm, • Sunday and Public Holidays - no work should be undertaken other

than necessary watering for dust control. RCMB Engineering Department and affected residents should be notified if works are planned outside of these times.

7.6 Site Access Where more than one street abuts the development site RCMB will nominate the location and street from which access to the site is obtained. Developers are required to obtain RCMB’s consent for the location of working access points to the site. Consent is to be obtained through the RCMB Engineering Department.

Rural City of Murray Bridge, V 1.0 7-2

Page 77: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

CHAPTER 8

QUALITY ASSURANCE REQUIREMENTS

Page 78: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

8 Quality Assurance Requirements

8.1 Submission of Plans All engineering and landscape drawings or plans are to be presented to RCMB’s engineering department for approval. Each set of plans should be accompanied by a Transmittal Record and a statement on compliance with the requirements of this document. All aspects of the design which do not meet requirements or tolerances set out in this document should be noted. Revised or amended drawings are to note and ‘revision cloud’ the specific amendment on the drawing plan and be submitted to RCMB with an updated Document Register. RCMB shall be provided with 2 A1 Copies, pdf files, and a Document Register for all drawings issued for construction.

8.2 Minimum Drafting Requirements Design plans should be definitive and clearly set out so as to present the design concepts in such a way that the project can be understood, specified for construction and satisfactorily built. Drawings are to be on A1 size sheets, and shall not rely on colour printing or colour wash to impart information, and be suitable for black and white copying and photo reduction to A3 paper size without loss of clarity. All design plans should be clearly numbered, including revisions by the designer with separate sheets numbered as part of a set. All drawing sheets should specify in the title block along the bottom right-hand corner the development proposal’s full site address and DAC File Number (e.g. 415/D000/09).

8.3 Inspection and Testing An Inspection and Testing Plan shall be included with the construction schedule submitted prior to commencement of works. The inspection and testing plan needs to include Hold Points and specify the timing and frequency of testing required.

Rural City of Murray Bridge, V 1.0 8-1

Page 79: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

8.3.1 Hold Points Works are to be held, and the RCMB Engineering Department notified for the purpose of inspection, at the following stages Prior to commencement of earthworks:

• At completion of preservation measures for trees, vegetation or heritage sites.

• At completion of installation of erosion and sediment control measures.

During the course of earthworks:

• After clearing and preparation of subgrade. • At completion of earthworks prior to re-establishment of finished lots,

verge areas, and landscaped areas.

During the course of road and drainage construction:

• After preparation of the sub-grade, for proof rolling, prior to application of sub-base.

• After preparation of the base-course, for proof rolling, prior to sealing.

• After the construction of drains and drain structures, prior to the

backfilling of trenches.

• After connection to the existing RCMB drainage system (where applicable) prior to backfilling.

All inspections require at least 24 hours notification in writing to the RCMB officer nominated in the Pre-Start Meeting.

8.3.2 Testing and Certification Requirements This list of testing requirements is not exhaustive and shall be the minimum requirements to verify compliance with RCMB specifications. Site Inspection Records Pavement Levels – A site inspection report verified by the Principal Consulting Engineer shall be submitted to verify the finished levels of each layer of pavement. Levels shall be taken at 10m intervals on both sides of Roads at the location of Face of Kerb, and Road Centreline. Inspection reports shall be submitted to RCMB prior to the next stage of works proceeding.

Rural City of Murray Bridge, V 1.0 8-2

Page 80: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

Compaction Tests All compaction testing shall be carried out by an approved National Accredited Testing Authority (NATA) registered testing laboratory. Certified test results shall be submitted to RCMB prior to the next stage of works proceeding. All tests must pass: Road Pavements - Two tests per thousand square metres in each layer (subgrade, subbase, and basecourse) with a minimum of two tests per layer. The RCMB may specify additional testing requirements at specified locations if the quality of workmanship is suspected of not being satisfactory. Compaction test results shall be submitted prior to commencement of the next pavement layer. Trenches in Roads – Compaction tests shall be undertaken at one test per each layer for each material every 30 metres of trenching. One test per trench for each service trench to each property. Compaction test results shall be submitted prior to commencement of the next stage of works. Proof Rolling RCMB Engineering Staff shall be present for proof rolling of subgrade, and basecourse. Proof rolling shall be carried out with a fully laden water cart. There shall be no visible deflection of pavement. Construction Materials Pavement Materials - Weigh bridge dockets or other suitable record shall be provided to verify the material used for pavement construction, and corresponding supplier test certificates demonstrating compliance with the specification. Asphaltic Concrete – Copies of contractor record sheets and corresponding supplier test certificate demonstrating compliance with the specification. All properties tested shall conform to the limits set out in RCMB Supply of Asphaltic Concrete Specification. Kerbing - Copies of contractor record sheets and corresponding supplier test certificate demonstrating compliance with the specification. Linemarking - Linemarking record sheets completed on the day of works. Pre-cast Drainage Products – Record of supplier and corresponding supplier test certificates demonstrating compliance with the specification. Concrete – Site delivery docket and corresponding supplier test certificates demonstrating compliance with the specification. Pipe Survey Drainage CCTV – CCTV Footage of internal inspection of all stormwater pipe networks to verify satisfactory condition, in DVD format in accordance with

Rural City of Murray Bridge, V 1.0 8-3

Page 81: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

Appendix 2. Inspection shall be carried out at the end of the defects liability period.

8.4 Tolerances on finished works Infrastructure will only be accepted when it meets the tolerances listed below. The tolerances represent an acceptable level of service for the associated infrastructure. All other tolerances shall be as set out in the specification. Works that do not conform to the tolerances will not be accepted by RCMB. Kerb – 0 or -5mm to adjacent seal Seal finish - No more than 5mm departure from 3m straight edge. Dense even surface. Footpaths & Shared paths– No more than 5mm departure from 3m straight edge. Verges – No more than plus or minus 20mm in any location Batter slopes – No point shall vary from batter slope line by more than plus or minus 150mm. Stormwater Pipes – Within 10mm of design invert levels and within 25mm of the correct alignment. Gully Pits – Tolerance on location within 20mm and finished level within 0 or minus 5mm of adjacent kerb/pavement level.

8.5 Retention Monies & Bonding Arrangements There are three bonding arrangements associated with the land division process. Local Government Bond - A bond required prior to commencement of construction work to cover any damage that may be caused to RCMB infrastructure. Early Section 51 clearance Bond – A developer may wish to apply for early clearance by bonding outstanding works. Retention Monies – A percentage of the contract price paid to RCMB at the completion of works for rectification of defects in the work during the maintenance period. Bonding arrangements shall be provided in the form of a Bank Guarantee undertaken with a financial institution to Council’s satisfaction, or cash. All bonding arrangements shall be finalized prior to Section 51 clearance.

Rural City of Murray Bridge, V 1.0 8-4

Page 82: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

Local Government Bond The bond is held by RCMB until the completion of construction activities. At the end of the construction period any damage shall be remedied by the developer, or the cost of the repairs determined by RCMB, and the amount being deducted from the bond, and the remaining credit returned to the developer. The specifics of the agreement will be set out in accordance with the requirements of section 254A of the Local Government Act.

Early Section 51 clearance Bond RCMB will only allow the developer to enter in to a bonding arrangement with RCMB for the completion of works, when construction has been substantially completed (all services and kerb and gutter installed). Bonding amounts shall be generally based on sums included in the contract, as agreed by RCMB plus twenty (20) percent. Where a contract sum is not available for the component of work, the rates shall be as determined by RCMB based on current construction costs plus twenty (20) percent. Retention Monies Construction work will be guaranteed for a minimum period of twelve (12) months from the date of Practical Completion. The guarantee shall be in the form of a legally binding agreement between RCMB and the developer. The agreement shall set out the commencement date, length of guarantee period and retention monies for specific infrastructure components such as roads, stormwater, footpaths, and landscaping, performance criteria, and dispute resolution procedures. The value of the retention monies shall represent between five (5) and ten (10) percent of the total Contract price, based on the risk of failure, and the likely costs of remediation.

Rural City of Murray Bridge, V 1.0 8-5

Page 83: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

Appendix 1

Water Quality Improvement Plans

Page 84: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

APPENDIX 1 - Water Quality Improvement Plans Water Quality Improvement Plans The RCMB Development Plan requires that all sites shall incorporate some level of water quality improvement. Applicants will be required to demonstrate how each stage of the treatment train will be addressed. It is recommended that the Water Sensitive Urban Design Technical Manual for the Greater Adelaide Region, Government of South Australia, 2009, be used for guidance on design. A simplified approach is considered sufficient for small development proposals, on sites smaller than 5000 square metres, up to a maximum of 8 future lots. For larger sites developers will need to undertake water quality modelling to assess the effectiveness of the proposed treatment train Site area less than 5000 square metres, and up to a maximum of 8 lots The opportunities for incorporating WSUD are limited at this scale. To satisfy water quality improvement targets a site will generally need to incorporate vegetated areas or a filtration system to cleanse stormwater runoff from roads and driveways. This can either be done through the use of conveyance measures such as replacing conventional kerb and guttering with swale drains, or incorporating filtration systems prior to discharge. To demonstrate compliance with the RCMB development plan the design and layout of drainage infrastructure shall satisfy the following; Existing dwellings are to be retrofitted with a 2KL rainwater tank for every 100m2 of roof area. Overflows are to be directed to a soakage trench or infiltration device. Where new access way or road construction is required; Road and access way Drainage shall be conveyed using grassed swales designed to treat the 1 in 3 month ARI peak flow rate, with an allowance for runoff from residential driveways. Or Road and access way Drainage shall be directed through a filtration system, sized to treat the volume of a 1 in 3 month event for the contributing sub-catchment area, based on a design storm duration equal to 2 times the sub-catchment time of concentration.

Rural City of Murray Bridge, V 1.0 i

Page 85: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

Filtration systems include bio-retention systems, rain gardens, and infiltration systems. The one in three month event shall be taken as half the 1 in 1 yr ARI average rainfall intensity. The objective of this approach is to promote the use of the road reserve for detention and infiltration, by incorporating treatments such as landscaped basins, swales, and bio-retention. Community title developments should locate the treatment measures on communal land adjacent the access driveway to provide for ease of access for maintenance purposes. Site area greater than 5000 square metres, and land divisions of more than 8 lots Land division of this size will normally present sufficient opportunities to develop a full treatment train approach to water quality improvement. Water Sensitive Urban Design Technical Manual for the Greater Adelaide Region, Government of South Australia, 2009, outlines the process of developing a WSUD plan for a site. Table 3.1 provides a scoring system to determine the potential risk to the effective implementation of Water Sensitive Urban Design (WSUD) on a subject site. It is suggested that this table be completed and included in the WQIP. Table 3.2 can be used as a guide for the indicative information requirements that need to be included in the WQIP. Objectives should be drawn from RCMB Development Plan, SMP, and IWRMP. Default targets developed by the EPA and Murray Darling Natural Resource Management Board are listed in Table 1.

Pollutant Description Retention Criteria

Litter/gross pollutants

Paper, plastic, metals, glass and organic materials

Retention of litter greater than 50mm for flows up to the 3 month ARI peak flow

Total Suspended Solids

80% reduction of average annual pollutant load

Coarse Sediment Coarse sand (=0.5mm) 80% of load for particles 0.5mm or less

Fine Particles Fine Sand (=0.05mm) 50% of the load for particles 0.1mm diameter or less

Nutrients Total Phosphorus and Total Nitrogen

45% retention of the load for each

Hydrocarbons, Motor Spirit, Oil and Grease

Anthropogenic hydrocarbons that can be emulsified

No visible oils for flows up to the 3 month ARI peak flow

Table 1: Pollutant Retention Criteria for Stormwater Treatment Train

Rural City of Murray Bridge, V 1.0 ii

Page 86: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

Hydrocarbon and Gross Pollutant targets apply to land uses where there is a significant export of litter and oil and grease and generally only apply to commercial and industrial areas. To demonstrate compliance with these targets stormwater quality modelling needs to be undertaken.

Rural City of Murray Bridge, V 1.0 iii

Page 87: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

Appendix 2

CCTV Pipe Surveys

Page 88: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

APPENDIX 2 – CCTV Pipe Surveys Pipe surveys are required to determine the pipe condition at the end of the defects liability period, prior to acceptance by RCMB. The Applicant must submit both a hardcopy report and a video display of the closed circuit television camera (CCTV) inspection. The CCTV inspection report and video must be reviewed by the supervising engineer prior to submission of the report and video to Council. For any defects identified remedial measures shall be recommended by a suitably qualified engineer and submitted to RCMB for approval. Once the remedial measures have been completed, a follow up survey is required to demonstrate that they have been carried out to Council’s satisfaction. All costs to undertake the above process will be borne by the Applicant. Any person entering a Council stormwater drain must fulfil requirements of the current Workplace Health and Safety Act; such as confined space training. Survey Protocol The CCTV pipe survey must provide a CD/DVD quality video report achieved by using the Wincam CCTV data capture and asset management software or similar standard of presentation, allowing easy interpretation of the pipe survey and report. If longitudinal cracks are observed at the obvert of the pipe, particular attention should be paid to the invert and the 3 o’clock and 9 o’clock positions for evidence of crushing. All cracks should be closely monitored whilst the camera is in motion. All joints should be fully scanned (over 360°) whilst the camera is stationary. The video display and hardcopy report should show all the faults, features and connections in the line. A typical example given below illustrates the reporting format required; Pit 18 → Pit 17 (upstream), 375 mm RCP. Distance:

• 0.0 m - start survey, joint satisfactory • 2.4m to 25m – no defects and all joints satisfactory • 26.9 m - minor longitudinal crack, position 12 o’clock, minor tree roots

up to 25%. • 45.0m – survey completed.

Rural City of Murray Bridge, V 1.0 i

Page 89: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

APPENDIX 3

Meeting Checklists

Page 90: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

Pre-Start Meeting Process

Only works that have been ‘Approved’ by the RCMB can be submitted for the Pre-Start process and meeting. These works must incorporate all aspects of the Planning Approval including any public consultation (which may be required) and any correspondence from concurrence agencies. This document is in three parts and must be attached to all supporting documentation. The shaded areas identified in parts 1and 2 and are to be completed by the applicant and submitted to RCMB to initiate the Pre-Start process. Parts 2 and 3 will be used by the RCMB during the site meeting. Failure to provide the required information in sufficient detail and in a timely manner may delay the RCMB’s ability to hold a Pre-Start meeting and permit works to proceed.

Accuracy of Submission

i. RCMB’s examination of documents should not be taken to mean that the documents have been checked in detail and RCMB takes no responsibility for their accuracy. If during construction, inadequacies of the design are discovered, it is the responsibility of the Principal Consulting Engineer to resubmit amended plans to RCMB for approval and rectify works accordingly.

ii. Notwithstanding any approval given to engineering documents,

where a discrepancy occurs between these documents and RCMB’s standards, then RCMB’s standards shall apply. All works must be performed in accordance with RCMB standards and relevant laws and guidelines.

iii. If in fact there are errors, omissions or insufficient detail on the plans

for the purpose of construction, these deficiencies shall be made good during construction and RCMB reserves the right to withhold approval of construction until such deficiencies are made good to its satisfaction.

Rural City of

Murray Bridge Works Depot

21 Hindmarsh Rd Murray Bridge

Engineering and

Assets

Ph: (08) 8539 1160 Fax: (08) 8531 0170

Pre-Start meeting template v170610 1

Page 91: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

PART 1: Pre-Meeting Requirements Check List

PROJECT NAME: DA NUMBER:

Shaded areas to be completed by the Principal Consulting Engineer and returned to the Development Engineering Unit of the RCMB in order to arrange a joint site meeting

1.1 Contact details of the Principal Consulting Engineer for the works: Name of Engineer

Name of Company

Telephone Number (s) Office: Mobile:

Email address

Out of Hours Tel. No.

NPER or MIE Aust No. 1.2 Contact details of the Principal Contractor for the works:

Name of Contractors Representative

Name of Company

Telephone Number (s) Office: Mobile:

Email address

Out of Hours Tel. No.

1.3 Person to be contacted in regard to any matter relating to the construction of the works, day-to day queries, complaints etc. (if different from the above): Name of Engineers Representative

Name of Company

Telephone Number (s) Office: Mobile:

Email address

Out of Hours Tel. No.

1.4 RCMB CONTACTS Development Engineering:

TBA, Team Leader Infrastructure Work tel: Mobile: Fax: email:

Paul Holmes, Team Leader Infrastructure Work tel: 08 8539 1172 Fax: 08 8531 0170 email: [email protected]

RCMB Depot Administration Officer Work tel: 08 8539 1160 Fax: 08 8531 0170 email:

Pre-Start meeting template v170610 2

Page 92: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

PART 1: Pre-Meeting Requirements Check List (Continued) 1.5 Intended date for commencement of works / / 20…... 1.6 Expected date for completion of works / / 20…...

The following information to be provided to the RCMB prior to the site meeting in order to allow assessment of the scope of works and reduce any possible delays in reviewing documentation and the granting of Approvals for the commencement of works.

Item Detail Checked & agreed by the

Principal Consulting

Eng. Y / N ?

Date presented to Council / Comments

1.7 Development and Engineering Plan Approvals: Current Development and Engineering Approvals have been granted.

Development Approval Notice file number:

…../…/…... & date of Notice … / .. / 20 .. RCMB Engineering Approval Letter ref number

…../…/…... & date … / .. / 20 ..

Y / N

1.8 Preservation of Existing Environment Features The Contractor and Principal Consulting Engineer are aware of the measures required to preserve and protect environmentally significant areas and/or trees, and are aware that measures must be implemented prior to commencement of earthworks.

Y / N

1.9 Soil Erosion Drainage Management Plan The Contractor and Principal Consulting Engineer have made arrangements to implement measures prior to Earthworks Commencing.

Y / N

1.10 Notice of Intention to commence Work i. Letters have been sent to adjoining owners

informing them of the intention to commence works

ii. Public consultation requirements have been met. (Pre-requisite on work permit form.)

Y / N

Y / N

NA

Pre-Start meeting template v170610 3

Page 93: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

PART 1: Pre-Meeting Requirements Check List (Continued)

Item Detail Checked &

agreed by the Principal / Consulting

Eng. Y / N ?

Date presented to Council / Comments

1.11 Public Liability and other Insurances Copies provided to RCMB (Refer Section 2.3 subdivision guidelines)

Y / N

1.12 Tender Details and Specifications Copies provided to RCMB and any changes to approved specifications noted.

Y / N

1.13 Contractors Construction Management Plan OHS&W,(including Risk Assessments & Job Safety Analysis), water conservation, Weed management, waste management and any other environmental management issues to be detailed.

Copies provided to RCMB

Y / N

1.14 Concurrence Agencies: Written approval has been obtained for any proposed works relating to concurrence agency conditions. For example, Murray Darling Basin Natural Resource Management Board, Environment Protection Authority, Department of Environment and Heritage – copies attached.

Y / N

1.15 Work Permit and Workzone Traffic Management Plans Details of approvals and permits for working on RCMB roads and DTEI roads where applicable. Copies attached

Y / N

1.16 QA Documentation including Inspection and Testing Plan. Copies provided to RCMB to identify project specific works.

Y / N

1.17 Bonding: Payment made in accordance with RCMB policy, for bonding for duration of works on RCMB assets that may be affected such as road surface, kerb, stormwater pits etc along frontage of site.

Photos of existing condition of infrastructure to be provided and any defects noted.

Y / N

Y / N

1.18 Composite Services Plan: Hard copy and electronic version provided to RCMB

Y / N

Pre-Start meeting template v170610 4

Page 94: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

PART 1: Pre-Meeting Requirements Check List (Continued) Item Detail Checked &

agreed by the Principal / Consulting

Eng. Y / N ?

Date presented to Council / Comments

1.19 Additional Information not identified above: Additional information has been submitted to support the application, and is attached to this document.

Detail: ………………………………………………

………………………………………………..……

…………………………………………………..…

Y / N

1.20 Request for Meeting: Date requested for Pre-Start meeting:

Proposed time of meeting (Ideally between 09:00-16:00 hrs)

(Note: The RCMB usually requires SEVEN days written notice of the proposed meeting date. The Principal Consulting Engineer should only make the request when all of the appropriate documentation is available. RCMB will inform applicant if date is acceptable.)

___ /___ /20___

______ AM / PM

Pre-Start meeting template v170610 5

Page 95: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

PART 2: Pre-Start Meeting (Shaded areas to be completed by the Engineer, prior to the meeting)

ATTENDANCE REGISTER Project:

Location:

RCMB File Ref: / /

Principal Consulting Engineer:

Date: / /

Meeting Held at:

Chaired by:

Meeting Commenced: am / pm

APOLOGIES:

ATTENDEES:

Name Company Title Phone / Mobile

Email

Engineer (i)

Engineer (ii) (Optional)

Contractor (i)

Contractor (ii) (Optional)

Paul Holmes

RCMB Team Leader Infrastructure

8539 1172

Pre-Start meeting template v170610 6

Page 96: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

PART 2: Pre-Start Meeting (Continued) – To be completed by Council representative 2.2 PURPOSE OF THE MEETING To provide an opportunity for all parties to meet and to go through Part 2 of this document, and for RCMB to clarify the relevant conditions and construction requirements. 2.3 PRE-MEETING DOCUMENTATION All documentation, drawings, plans and fees as identified in Part 1 of the Pre-Start Meeting template document have / have not been provided to the RCMB’s satisfaction prior to the meeting. Details of any non-compliance issues or incomplete documentation are to be identified in the meeting. 2.4 SITE SAFETY PROCEDURES & HOLD POINT INSPECTIONS:

a) RCMB officers will report to a site representative for an initial site safety induction and prior to each site inspection.

b) The Developers site representative or Engineer is to liaise with RCMB officers in order

to arrange joint ‘Hold Point’ inspections. The inspections required are in accordance with Section 8.3 RCMB Subdivision development guidelines.

Any other requirements are as listed:

2.5 SITE ACCESS & SIGNAGE

a) Vehicular access to the site for construction and demolition is via: {street name }

b) Signage and appropriate fencing must be provided to the site to control public access.

c) Other site access conditions (if applicable):

d) Work sites and surrounding areas must be left in a safe condition at all times.

2.6 ENVIRONMENTAL PROTECTION

a) A temporary construction exit is to be provided at the access point to the site, a minimum of 3m wide incorporating a shaker and gravel pad (75mm dia), a minimum of 200mm thick and 15m long.

Pre-Start meeting template v170610 7

Page 97: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

b) Where considering proximity of existing homes, noise, dust and work hours should be

properly addressed.

c) Council’s required method of vegetation disposal is by chipping / shredding on site. d) The extent of the works and area to be left undisturbed is to be clearly identified and

understood by all parties. e) No works are to proceed in any adjoining properties without the prior, written consent of

the registered landowner being received by the Council. Q: Are any works expected on adjoining properties? Yes / No. Q: If “Yes” have consents been received? Yes / No. Comments:

f) All areas opened up to construction must be protected from wind and water erosion.

Failure to have all reasonable and relevant SEDM measures in place, in the event of environmental harm being caused as a result of works being undertaken on this site, may result in action being taken by RCMB and/or the SA Murray Darling Basin Natural Resource Management Board (SAMDBNRMB). All SEDM measures must be inspected, maintained and where necessary improved, expanded or reinforced regularly and after every storm event.

g) If any declared weeds are, or have been identified on the site, the SAMDBNRMB are to

be notified immediately for advice on what action needs to be taken. h) Any land which contains environmentally significant areas, significant trees, trees with

Preservation Declarations placed upon them, or areas specifically identified for protection and preservation as part of the Development Approval Notification must be discussed at the meeting. The RCMB representative(s) must be satisfied that the Developer is aware of such features and has/will take appropriate measures to protect them prior to works commencing and throughout the duration of the project.

To assist in this process, photographs may be taken of all significant features and stored in Council records. Photos taken: YES / NO

2.7 INSPECTIONS BY RCMB/ CONCURRENCE AGENCIES

a) RCMB may undertake random visits to site during construction, and may also take photographs of the various work activities in progress.

b) Paul Holmes / Team Leader Infrastructure will conduct inspections, and will be the

RCMB’s point of contact for day-to-day issues. c) Concurrence Agencies must be called to inspect all works that relate to their conditions.

RCMB must receive a copy of their comments and approval prior to the commencement of works, and/or hold point inspections.

Pre-Start meeting template v170610 8

Page 98: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

2.8 RCMB REQUIREMENTS – DEVELOPMENT APPROVAL CONDITIONS Refer to any specific Development Notice paragraphs:

Additional conditions shown at the end of Section 2.10: yes / no 2.9 CONSTRUCTION REQUIREMENTS – OPERATIONAL WORKS APPROVAL

CONDITIONS

a) Working Hours - Work involving machinery of any description should only be carried out on site from:

a. 7am to 5pm, Monday to Saturday;

b. With no work on Sundays or Public Holidays other than dust control.

RCMB and adjoining residents are to be notified if works are planned outside of these times.

b) Street Lighting – Street lighting is to be installed prior to the Practical Completion

Inspection, or subject to conditions imposed by the RCMB.

c) Cultural Heritage – The RCMB must be informed immediately, should any works uncover evidence of Aboriginal culture.

d) Additional Operational Works conditions for discussion (if any):

Pre-Start meeting template v170610 9

Page 99: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

2.10 OTHER BUSINESS

a) Earthworks for this project have been designed to be: {Balanced / in surplus / imported} If surplus or imported, approximate quantities expected …………………T / m3

b) Additional comments (if any):

Pre-Start meeting template v170610 10

Page 100: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

PART 3: AGREEMENT – To be completed by Council representative Based on the submitted information and the points discussed in the meeting, the RCMB representative

Paul Holmes / Team Leader Infrastructure does / does not permit works to proceed. Should works not be permitted, or additional information required, the following items must be addressed and presented to the RCMB for approval.

The set of notes produced from the meeting are to be presented to the Principal Consulting Engineer for information and or action. Should the Principal Consulting Engineer or developer not agree with this record of the meeting, this must be advised to the RCMB by Email or Fax within 48 hours of receipt. If this is the case, the RCMB may call another meeting and works may need to stop until all parties have reached agreement. Meeting closed at …. : ……Hrs .

Pre-Start meeting template v170610 11

Page 101: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

Engineering Clearance Process

This document provides a brief outline of the requirements for Engineering Clearance for works required as conditions of consent for land division projects. The Engineering Clearance Process must be completed prior to Section 51 clearance. Only works that have been ‘Approved’ by RCMB can be submitted for Engineering Clearance. These works must incorporate all aspects of the Planning Approval, together with any requirements of concurrence agencies. Once the Engineering Clearance Process has been completed the defects liability period shall commence, and RCMB Technical Services section will notify the Planning section that it is satisfied with the works, and the Section 51 clearance process can proceed. At the end of the defects liability period the Final Completion Process will be carried out. This document is in three parts and all supporting documentation should be attached. Parts 1a and 1b are to be completed by the applicant and submitted to RCMB to request a meeting for Works Acceptance at least 7 days prior to the requested Joint Site Meeting date. RCMB will carry out inspection of the works and complete Part 2 prior to the Joint Site Meeting. The Joint Site Meeting will be to discuss the various components of the works. The notes of the meeting will be forwarded to the applicant identifying completion of requirements, or areas that need to be addressed prior to Engineering Clearance.

Rural City of

Murray Bridge Works Depot

21 Hindmarsh Rd Murray Bridge

Engineering and

Assets

Ph: (08) 8539 1160 Fax: (08) 8531 0170

Engineering Clearance meeting template v170610 1

Page 102: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

PART 1A: Pre-Meeting Requirements Check List

PROJECT NAME: DA NUMBER:

A joint site meeting is required between the Principal Consulting Engineer for the project, the Contractor and Council representative(s). The following documents will need to be made available for Council inspection prior to the arrangement of a mutually agreeable meeting date and time.

Item Detail Checked & agreed by

the Principal

Consulting Eng. Y / N

Date presented

to Council / Comments

1.1 As Constructed Survey: Survey undertaken by a registered surveyor and submitted to and accepted by RCMB. Any departures from design plans noted by Principal Consulting Engineer.

Y / N

1.2 Schedule of Assets A schedule of all infrastructure that will become the property of RCMB has been submitted to RCMB and accepted.

Y / N

1.3 Specifications, Manuals and maintenance schedules for Stormwater Quality Improvement Devices Any stormwater quality improvement devices such as GPT's, Constructed Wetlands, Swales etc provided with specifications, manuals and maintenance schedules submitted to RCMB and accepted.

Y / N

1.4 Site Reclassification Where fill has been placed lots have been re-classified in accordance with AS2870

Y / N

NA

1.5 Easements All arrangements for easements have been finalised and documentation prepared for registration with the Land Titles Office. Copies have been submitted to RCMB.

Y / N NA

Engineering Clearance meeting template v170610 2

Page 103: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

PART 1A: Pre-Meeting Requirement Check List (Continued)

1.6 Certification by Principal Consulting Engineer All works have been constructed in accordance with the approved drawings and design, or have been subject to approval by RCMB subsequent commencement of works.

Any defects or requests to rectify defective works, or to remove works which have not been approved, have been complied with.

Y / N

NA

1.7 Approval of Other Landowners, Authorities & Concurrence Agencies Works have been completed and written approval has been provided to Council from the appropriate person/authority for any works on adjoining land. All imposed concurrence agency conditions have been complied with.

Comments:

………………………………………………………………………

………………………………………………………………………

………………………………………………………………………

Y / N

NA

1.8 Local Government Bond Any damage to RCMB assets has been repaired in accordance with conditions of the bonding arrangements. The following remedial works have been undertaken:

………………………………………………………………………

………………………………………………………………………

………………………………………………………………………

Y / N

NA

1.9 Early Section 51 Clearance Bond In exceptional circumstances, the RCMB may accept a Bond for Uncompleted Works for items such as road sealing and verge treatments.

Details of Uncompleted Works:

………………………………………………………………………

………………………………………………………………………

………………………………………………………………………

Attach a fully priced schedule of uncompleted works.

Y / N

NA

1.10 Retention Monies An agreement has been prepared and submitted to RCMB for approval for guarantee of construction work for the defects liability period.

Engineering Clearance meeting template v170610 3

Page 104: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

PART 1B: Compliance with QA requirements All testing and certification requirements must be completed and submitted to RCMB prior to the Joint Site Meeting.

Item Detail Date presented to Council / Comments

1.11 Compaction Tests

i. Subgrade

ii. Sub-base

iii. Base-course

iv. Service Trenches

v. In-situ AC compaction

1.12 Site Inspection Records An inspection report verified by the Principal Consulting Engineer is required to verify the finished levels of each layer of pavement

i. Subgrade

ii. Sub-base

iii. Base-course

1.13 Construction Materials Test certificates are required for construction materials to verify compliance with the RCMB specifications.

i. Pavement Materials - Source and specification compliance

Sub-base

Basecourse

ii. Asphaltic Concrete - Source and specification compliance

Contractor Record Sheets

Supplier Test Certificate

Engineering Clearance meeting template v170610 4

Page 105: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

iii. Kerbing

Contractor Record Sheets

Compressive Strength Test Certificates

iv. Linemarking

Contractor Record Sheets

v. Pre-cast Drainage products - Compliance with Australian Standards

Supplier

Supplier Test Certificates

vi. Concrete Works

Site delivery Dockets

Compressive Strength Test Certificates

1.14 Other Testing Requirements ………………………………….................................

………………………………….................................

………………………………….................................

………………………………….................................

………………………………….................................

………………………………….................................

1.15 Request for Meeting:

Date requested for Joint Site Meeting:

Proposed time of meeting (preferably between 09:00-16:00 hrs)

(Note: The Council usually requires SEVEN days notice of the proposed meeting date, which must be at a time acceptable to Council.)

The request should only be made by the Principal when all of the appropriate documentation is available and works associated with the process have been completed on the site.

___ /___ /200___

____: ____ Hrs

Engineering Clearance meeting template v170610 5

Page 106: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

PART 2: Joint Site Meeting (Shaded areas to be completed by the Engineer, prior to the meeting)

ATTENDANCE REGISTER Project:

Location:

RCMB File Ref: / /

Principal Consulting Engineer:

Date: / /

Meeting Held at:

Chaired by:

Meeting Commenced: am / pm

APOLOGIES:

ATTENDEES:

Name Company Title Phone / Mobile

Email

Engineer (i)

Engineer (ii) (Optional)

Contractor (i)

Contractor (ii) (Optional)

Paul Holmes

RCMB Team Leader Engineering

8539 1172

Engineering Clearance meeting template v170610 6

Page 107: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

PART 2: JOINT SITE MEETING (Continued..)

Site Condition Notes - (To be completed by Council Officer)

ITEM GENERAL TOPIC AREAS

2.1 ALLOTMENTS & EARTHWORKS:

2.2 STORMWATER:

2.3 LIGHTING:

2.4 ROAD PAVEMENT:

Engineering Clearance meeting template v170610 7

Page 108: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

PART 2: JOINT SITE MEETING (Continued..)

Site Condition Notes - (To be completed by Council Officer)

ITEM GENERAL TOPIC AREAS

2.5 PATHWAYS, BIKEWAYS & VERGES:

2.6 CONCRETE WORKS:

2.7 EROSION & SEDIMENT CONTROL:

2.8 LANDSCAPING FEATURES & TREES:

Engineering Clearance meeting template v170610 8

Page 109: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

PART 2: JOINT SITE MEETING (Continued..)

Site Condition Notes - (To be completed by Council Officer)

ITEM GENERAL TOPIC AREAS

2.9 PARKS & EQUIPMENT:

2.10 Other Matters:

Engineering Clearance meeting template v170610 9

Page 110: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

PART 3: AGREEMENT – To be completed by Council representative Based on the submitted information and the points discussed in the meeting, the Council representative

Paul Holmes / Team Leader Engineering does / does not accept that the works and/or documentation permit Engineering Clearance. Should the site not be acceptable, or additional information required, the following items must be addressed and presented to the Council for approval.

The set of notes produced from the meeting are to be presented to the Principal Consulting Engineer for information and or action. Should the Principal Consulting Engineer or developer not agree with this record of the meeting, this must be advised to the RCMB by Email or Fax within 48 hours of receipt. If this is the case, the RCMB may call another meeting and works may need to stop until all parties have reached agreement. Meeting closed at …. : ……Hrs .

Engineering Clearance meeting template v170610 10

Page 111: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

Final Completion Process

This document provides a brief outline of the requirements of the Final Completion Process. The Final Completion Process is carried out at the end of the defects liability period. During the defects liability period, it is the responsibility of the Developer to rectify any works found to be defective or found to exhibit faults attributed to the design of the works and/or the performance of the construction activities in terms of quality and conformance with the design and specifications. This document is in three parts and all supporting documentation should be attached. Part 1 is to be completed by the applicant and submitted to RCMB to request a meeting for Joint Final Inspection at least 7 days prior to the requested meeting date. RCMB will carry out inspection of the works and complete Part 2 prior to the Joint Final Inspection. The notes of the meeting will be forwarded to the applicant identifying Final Completion, or areas that need to be addressed prior to Final Completion. Once Final Completion requirements have been satisfied, the developer shall apply for transfer of ownership of assets and the return of retention monies. The RCMB will execute the termination of the bonding (retention monies) agreement and issue a Certificate of Transfer for the assets.

Rural City of Murray Bridge

Works Depot 21 Hindmarsh Rd

Murray Bridge

Engineering and Assets

Ph: (08) 8539 1160

Fax: (08) 8531 0170

1

Page 112: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

PART 1: Pre-Meeting Requirements Check List PROJECT NAME: DA NUMBER:

A Joint Final Inspection is required between the Principal Consulting Engineer for the project, the Contractor and Council representative(s). The following documents will need to be made available for Council inspection prior to the arrangement of a mutually agreeable meeting date and time. Item Detail Checked

& agreed by the

Principal Consulting Eng. Y /

N ?

Date presented to Council

/ Comments

1.1 CCTV Inspection of Stormwater Pipework: Survey undertaken in accordance with the requirements of Appendix 2 of RCMB Subdivision Guidlines, Submitted to and accepted by RCMB. Y / N

1.2 Early Section 51 Clearance Bond Any works bonded at Works Acceptance stage are now completed to the satisfaction of RCMB and application is to be made for return of bond monies.

Comments:

………………………………………………………………………

................................................................................................

................................................................................................

Y / N

NA

1.3 Defects All infrastructure has been inspected and any defects identified have been repaired. The following repairs have been carried out;

………………………………………………………………………

................................................................................................

................................................................................................

Y / N

2

Page 113: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

1.4 Request for Meeting:

Date requested for Joint Final Inspection:

Proposed time of meeting (preferably between 09:00-16:00 hrs)

(Note: The RCMB usually requires SEVEN days notice of the proposed meeting date, which must be at a time acceptable to RCMB.)

The request should only be made by the Principal Consulting Engineer when all of the appropriate documentation is available and works associated with the process have been completed on the site.

___ /___ /200___

____: ____ Hrs

3

Page 114: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

PART 2: Joint Site Meeting (Shaded areas to be completed by the Engineer, prior to the meeting)

ATTENDANCE REGISTER

Project:

Location:

RCMB File Ref: / /

Principal Consulting Engineer:

Date: / /

Meeting Held at:

Chaired by:

Meeting Commenced: am / pm

APOLOGIES:

ATTENDEES:

Name Company Title Phone / Mobile

Email

Engineer (i)

Engineer (ii) (Optional)

Contractor (i)

Contractor (ii) (Optional)

Paul Holmes

RCMB Team Leader Engineering

8539 1172

4

Page 115: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

PART 2: SITE MEETING (Continued..)

Site Condition Notes - (To be completed by Council Officer)

ITEM GENERAL TOPIC AREAS

2.1 ALLOTMENTS & EARTHWORKS:

2.2 STORMWATER:

2.3 LIGHTING:

2.4 ROAD PAVEMENT:

5

Page 116: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

PART 2: SITE MEETING (Continued..)

Site Condition Notes - (To be completed by Council Officer)

ITEM GENERAL TOPIC AREAS

2.5 PATHWAYS, BIKEWAYS & VERGES:

2.6 CONCRETE WORKS:

2.7 EROSION & SEDIMENT CONTROL:

2.8 LANDSCAPING FEATURES & TREES:

6

Page 117: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

PART 2: SITE MEETING (Continued..)

Site Condition Notes - (To be completed by Council Officer)

ITEM GENERAL TOPIC AREAS

2.9 PARKS & EQUIPMENT:

2.10 Other Matters:

7

Page 118: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

PART 3: AGREEMENT – To be completed by Council representative Based on the submitted information and the points discussed in the meeting, the Council representative Paul Holmes / Team Leader Engineering does / does not accept that works and/or documentation meet the requirements for the transfer of assets to RCMB*. Should the site not be acceptable, or additional information required, the following items must be addressed and presented to the Council for approval.

The set of notes produced from the meeting are to be presented to the Principal Consulting Engineer for information and or action. Should the Principal Consulting Engineer or developer not agree with this record of the meeting, this must be advised to the RCMB by Email or Fax within 48 hours of receipt. If this is the case, the RCMB may call another meeting and works may need to stop until all parties have reached agreement. Meeting closed at …. : ……Hrs . *The developer needs to make formal application for transfer of assets and return of retention monies once agreement has been reached that requirements have been satisfied.

8

Page 119: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

APPENDIX 4 - Rainfall Data

Rainfall Intensity For Murray Bridge, SA Average Recurrence Interval (years)

Duration 1 2 5 10 20 50 100 5m 41.3 56 79 95 117 150 179 6m 38.5 52 73 88 109 139 165 7m 36.1 48.7 69 83 102 130 155 8m 34.1 46.0 65 78 96 123 145 9m 32.4 43.7 61 74 91 116 137

10m 30.9 41.7 58 70 86 110 131 11m 29.6 39.9 56 67 82 105 124 12m 28.4 38.2 53 64 79 101 119 13m 27.3 36.8 51 62 76 96 114 14m 26.4 35.4 49.5 59 73 93 110 15m 25.5 34.2 47.7 57 70 89 106 16m 24.6 33.1 46.1 55 68 86 102 17m 23.9 32.1 44.7 54 66 83 99 18m 23.2 31.1 43.3 52 64 81 95 19m 22.5 30.3 42.1 50 62 78 92 20m 21.9 29.4 40.9 49 60 76 90 21m 21.4 28.7 39.8 47.7 58 74 87 22m 20.8 27.9 38.8 46.4 57 72 85 23m 20.3 27.3 37.8 45.3 55 70 83 25m 19.4 26 36 43.1 53 67 79 30m 17.5 23.5 32.4 38.7 47.2 60 70 45m 13.8 18.4 25.3 30.1 36.6 46.1 54 1hr 11.5 15.4 21 25 30.3 38.1 44.6

1.5hr 8.67 11.6 15.8 18.7 22.6 28.4 33.3 2hr 7.04 9.38 12.8 15.2 18.3 23 27 3hr 5.24 6.98 9.49 11.2 13.6 17 19.9 6hr 3.16 4.20 5.69 6.72 8.12 10.2 11.9 12hr 1.9 2.53 3.42 4.03 4.86 6.07 7.08 18hr 1.43 1.90 2.56 3.01 3.62 4.51 5.26 24hr 1.17 1.55 2.08 2.44 2.93 3.65 4.24 48hr 0.7 0.92 1.23 1.44 1.72 2.13 2.47 72hr 0.5 0.66 0.87 1.02 1.22 1.50 1.74

i

Page 120: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

APPENDIX 5 –

RCMB TYPICAL DRAWINGS

1

Page 121: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

3000 MINIMUM

6000 MAXIMUM

0.50.5

EDGE OF BITUMEN

WATER TABLE

TOP OF KERB

CONSTRUCTION JOINTCONSTRUCTION JOINT

1

0.2

0.4

F 82 CENTRAL

PM2 30G (OR EQUIVALENT)

COMPACTED TO 98% STANDARD

1

SECTION

PLAN

BACK OF KERB

-

-

DRAWING NUMBER

CODESCALE AT A1

REV

Bridge to Opportunity

The Rural City of

MANAGER

DESIGN

DRAWN

CHECKED

SIGNATURES DATE

REV

REV

AC

0

NTS

SD001

2012-5000-001

TYPICAL DETAIL

VEHICLE CROSS OVER

RCMB

NOTES :

1. ALL JOINS TO EXISTING KERBS SHALL BE SAW CUT

PRIOR TO REMOVAL OF CONCRETE

2. CONCRETE STRENGTH SHALL BE 25MPa

3. MINIMUM 50MM COVER FOR ALL REINFORCEMENT

Page 122: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

3000 MINIMUM

6000 MAXIMUM

0.5

EDGE OF BITUMEN

WATER TABLE

TOP OF KERB

CONSTRUCTION JOINT

CONSTRUCTION JOINT

1

PLAN

WHERE REQUIRED CONCRETE

FOOTPATH SHALL BE RECONSTRUCTED

TO MATCH INTO DRIVEWAY

\ \ \ \ \\ \ \ \ \ \ \ \ \

PROPERTY BOUNDARY

FOOTPATH

WIDTH VARIES

CONSTRUCTION JOINT WHERE

DRIVEWAY AND FOOTPATH MEET

0.2 0.4

F 82 CENTRAL

PM2 30G (OR EQUIVALENT)

75MM THICK COMPACTED

TO 98% STANDARD

1

SECTION

RESIDENTIAL CROSSING

BACK OF KERB

EXPANSION JOINT

PR

OP

ER

TY

B

OU

ND

AR

Y

SLOPE VARIES

1% MIN - 2.5% MAX

0.2 0.4

F 82 CENTRAL

PM2 30G (OR EQUIVALENT)

150MM THICK COMPACTED

TO 98% STANDARD

1

SECTION

COMMERCIAL CROSSING

BACK OF KERB

EXPANSION JOINT

PR

OP

ER

TY

B

OU

ND

AR

Y

SLOPE VARIES

1% MIN - 2.5% MAX

100MM MIN THICK CONCRETE SLAB

WITH F82 LOCATED CENTRALLY

150MM MIN THICK CONCRETE SLAB

WITH F82 LOCATED CENTRALLY

DRAWING NUMBER

CODESCALE AT A1

REV

Bridge to Opportunity

The Rural City of

MANAGER

DESIGN

DRAWN

CHECKED

SIGNATURES DATE

REV

REV

AC

0

NTS

SD001

2012-5000-002

TYPICAL DETAIL

VEHICLE CROSS OVER

RCMB

NOTES :

1. ALL JOINS TO EXISTING KERBS SHALL BE SAW CUT

PRIOR TO REMOVAL OF CONCRETE

2. CONCRETE STRENGTH SHALL BE 25MPa

3. MINIMUM 50MM COVER FOR ALL REINFORCEMENT

4 REFER TO RCMB DRAWING 2012-5001-001FOR FOR

STANDARD FOOTPATH DETAIL

Page 123: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

CONSTRUCTION JOINTS

SECTION

NTS

NTS

CONSTRUCTION JOINTS

NTS

40mm RAD

FOOTPATH

NOMINAL NOMINAL

FOOTPATH LEVEL

TOP OF KERB

KERB INVERT

1500

FACE OF KERB

SECTION

1400 CLEAR LANDING FROM TOP OF RAMP TO ANY OBSTRUCTION

TYPICAL PRAM CROSSING

4

5

°

D

E

S

I

R

A

B

L

E

300

REFER TO NOTE 3

APPROVED SUBGRADE

75mm THICK

REFER TO NOTE 3

F62 OR F82 CENTRALLY LOCATED

QUARRY RUBBLE BASE COURSE

SECTION

NTS

NTS

REFER TO NOTE 4

CONTROL JOINT CONTROL JOINT

6000

1.5

MIN

TYPICAL CONCRETE FOOTPATH PLAN

1500

MAXIMUM

1200 MIN

1520 MAX

1000

MINMUM

DRAWING NUMBER

CODESCALE AT A1

REV

Bridge to Opportunity

The Rural City of

MANAGER

DESIGN

DRAWN

CHECKED

SIGNATURES DATE

REV

REV

AC

1

NTS

SD001

2012-5001-001

TYPICAL DETAIL

KERB RAMP & FOOTPATH

RCMB

NOTES:

1. CONCRETE STRENGTH SHALL BE 25Mpa

2. MINIMUM FOOTPATH WIDTH SHALL BE 1500

3. TGSIs SHALL BE INSTALLED

4. RESIDENTIAL 100mm THICK, COMMERCIAL

150mm THICK

5. MESH TYPICALLY F62, FOR INDUSTRIAL AND

COMMERCIAL LAND MESH SHALL BE F82

1 19/8/14 UPDATED DRAWING

Page 124: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

110 40

200

150

MIN

LEVEL TO CORRESPOND

TO PAVEMENT EDGE LEVEL

AS SHOWN ON PLANS

PA

VE

ME

NT

25mm

RAD

ALL DIMENSIONS

TAKEN TO FACE

NTS

OF KERB

150

75mm MIN. CLASS 2 FCR

BEDDING COMPACTED TO 95%

MODIFIED RELATIVE COMPACTION

BARRIER KERB (3)

150

RAD

15mm

RAD

225mm

RAD

75mm

300110 190

40

150

275 M

IN

150 600

MIN

PA

VE

ME

NT

OF KERB

TAKEN TO FACE

ALL DIMENSIONS

CHAMFER

25x25mm

AS SHOWN ON PLANS

TO PAVEMENT EDGE LEVEL

LEVEL TO CORRESPOND

SEMI-MOUNTABLE KERB AND CHANNEL (4)

NTS

75mm MIN. CLASS 2 FCR

BEDDING COMPACTED TO 95%

MODIFIED RELATIVE COMPACTION

125

DRAWING NUMBER

CODESCALE AT A1

REV

Bridge to Opportunity

The Rural City of

MANAGER

DESIGN

DRAWN

CHECKED

SIGNATURES DATE

REV

REV

AC

0

NTS

SD001

2012-5002-001

TYPICAL DETAIL

CONCRETE KERB

RCMB

Page 125: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

300110 40

10

140

300

25mm

RAD

75mm MIN. CLASS 2 FCR

BEDDING COMPACTED TO 95%

MODIFIED RELATIVE COMPACTION

KERB AND TRAY (2)

150 450

MIN

PA

VE

ME

NT

LEVEL TO CORRESPOND

TO PAVEMENT EDGE LEVEL

AS SHOWN ON PLANS

25x25mm

CHAMFER

ALL DIMENSIONS

TAKEN TO FACE

OF KERB

NTS

MODIFIED RELATIVE COMPACTION

KERB AND CHANNEL (1)

OF KERB

NTS

TAKEN TO FACE

ALL DIMENSIONS

RAD

25mm

CHAMFER

25x25mm

PA

VE

ME

NT

AS SHOWN ON PLANS

TO PAVEMENT EDGE LEVEL

LEVEL TO CORRESPOND

BEDDING COMPACTED TO 95%

75mm MIN. CLASS 2 FCR

MIN

450150

300

150

40

40110 300

DRAWING NUMBER

CODESCALE AT A1

REV

Bridge to Opportunity

The Rural City of

MANAGER

DESIGN

DRAWN

CHECKED

SIGNATURES DATE

REV

REV

AC

0

NTS

SD001

2012-5002-002

TYPICAL DETAIL

CONCRETE KERB

RCMB

Page 126: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

600

PIT WIDTH

WATER TABLE

EDGE OF BITUMEN

TOP OF KERB

1800

PIT LENGTH

125 MIN

1

Dia.

I.P.

I.P.

LIFTING

POINT

PAVEMENT

SEAL

5mm GAP

CONCRETE

FRAME

1

SECTION

130

MIN

1200 MIN - 2000 MAX

TRANSITION

600

200

300

D

E

F

L

E

C

T

O

R

S

W

H

E

N

N

O

T

E

D

1200 MIN - 2000 MAX

TRANSITION

F62 CENTRAL

150

MIN

150

MIN

40

TRANSITION

50

110

40

TRANSITION

2

SECTION

CONSTRUCTION JOINTCONSTRUCTION JOINT

FLOW

CONSTRUCTION JOINT

CONSTRUCTION JOINT

210

2150

2160

CONCRETE

FRAME

850

PLAN

300 LAP MIN

TYP

DRAWING NUMBER

CODESCALE

REV

Bridge to Opportunity

The Rural City of

MANAGER

DESIGN

DRAWN

CHECKED

SIGNATURES DATE

REV

REV

AC

1

NTS

SD001

2012-5003-001

TYPICAL DETAIL

DOUBLE SEP UPRIGHT KERB

RCMB

NOTES:

1. SEP COVER IS A MOUNT BARKER DOUBLE AS SUPPLIED BY BIANCO PRECAST

2. CONCRETE STRENGTH SHALL BE 25Mpa

3. DEFLECTORS SHALL BE CONSTRUCTED ONLY IF REQUIRED REFER TO

CONSTRUCTION DRAWINGS

4. DEFLECTORS SHOWN ARE FOR ILLUSTRATION PURPOSES, DEFLECTORS

WHEN REQUIRED SHALL EXTEND ACROSS ENTIRE LENGTH OF PIT INVERT

5. MINIMUM 50MM COVER FOR ALL REINFORCEMENT

6. REFER TO RCMB DRAWING 2012-5002-002 FOR UPRIGHT KERB DETAIL

1 5/11/12_INCLUSION OF NOTE 4

Page 127: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

600

PIT WIDTH

WATER TABLE

EDGE OF BITUMEN

TOP OF KERB

1800

PIT LENGTH

125 MIN

1

Dia.

I.P.

I.P.

LIFTING

POINT

PAVEMENT

SEAL

5mm GAP

CONCRETE

FRAME

1

SECTION

130

MIN

1200 MIN - 2000 MAX

TRANSITION

700

200300

D

E

F

L

E

C

T

O

R

S

W

H

E

N

N

O

T

E

D

1200 MIN - 2000 MAX

TRANSITION

F62 CENTRAL

150

MIN

150

MIN

40

TRANSITION

50

110

F62 CENTRAL

2

SECTION

CONSTRUCTION JOINTCONSTRUCTION JOINT

FLOW

CONSTRUCTION JOINT

CONSTRUCTION JOINT

210

2150

2160

CONCRETE

FRAME

850

40

TRANSITION

PLAN

300 LAP MIN

TYP

300

TRANSITION

300

TRANSITION

LIFTING

POINT

DRAWING NUMBER

CODESCALE

REV

Bridge to Opportunity

The Rural City of

MANAGER

DESIGN

DRAWN

CHECKED

SIGNATURES DATE

REV

REV

AC

1

NTS

SD001

2012-5003-002

TYPICAL DETAIL

DOUBLE SEP MOUNTABLE KERB

RCMB

NOTES:

1. SEP COVER IS A MOUNT BARKER DOUBLE AS SUPPLIED BY BIANCO PRECAST

2. CONCRETE STRENGTH SHALL BE 25Mpa

3. DEFLECTORS SHALL BE CONSTRUCTED ONLY IF REQUIRED REFER TO

CONSTRUCTION DRAWINGS

4. DEFLECTORS SHOWN ARE FOR ILLUSTRATION PURPOSES, DEFLECTORS

WHEN REQUIRED SHALL EXTEND ACROSS ENTIRE LENGTH OF PIT INVERT

4. MINIMUM 50MM COVER FOR ALL REINFORCEMENT

5. REFER TO RCMB DRAWING 2012-5002-001 FOR MOUNTABLE KERB DETAIL

1_5/11/12_INCLUSION OF NOTE 4 & 300 TRANSITION

Page 128: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

6000

1000

MIN

PR

OP

ER

TY

BO

UN

DA

RY

12500 MIN - 16000 MAX

ROAD RESERVE

3%

1500MIN

FOOTPATH

1000

MIN

1000

MIN

PR

OP

ER

TY

BO

UN

DA

RY

3%

C

L

NOTES:

1. REFER TO TYPICAL DETAIL DRAWING NO.

2012-5002-001 AND 2012-5002-002 FOR KERB AND

WATER TABLE DETAIL

2. REFER TO TYPICAL DETAING DRAWING NO.

2011-5001-001 FOR FOOTPATH DETAIL

3. TREES TO BE APPROVED BY PARKS AND GARDENS

TEAM LEADER

DRAWING NUMBER

CODESCALE AT A1

REV

Bridge to Opportunity

The Rural City of

MANAGER

DESIGN

DRAWN

CHECKED

SIGNATURES DATE

REV

REV

AC

A

NTS

SD001

2012-5006-001

TYPICAL DETAIL

ACCESS LANE

RCMB

Page 129: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

7000 - 7500

CARRIAGEWAY

1500 MIN

FOOTPATH

1500

MIN

1000

MIN

1500

MIN

PR

OP

ER

TY

BO

UN

DA

RY

PR

OP

ER

TY

BO

UN

DA

RY

1500 MIN - 18000 MAX

ROAD RESERVE

3%

3%

C

L

NOTES:

1. REFER TO TYPICAL DETAIL DRAWING NO.

2012-5002-001 AND 2012-5002-002 FOR KERB AND

WATER TABLE DETAIL

2. REFER TO TYPICAL DETAING DRAWING NO.

2011-5001-001 FOR FOOTPATH DETAIL

3. TREES TO BE APPROVED BY PARKS AND GARDENS

TEAM LEADER

DRAWING NUMBER

CODESCALE AT A1

REV

Bridge to Opportunity

The Rural City of

MANAGER

DESIGN

DRAWN

CHECKED

SIGNATURES DATE

REV

REV

AC

A

NTS

SD001

2012-5006-002

TYPICAL DETAIL

ACCESS ROAD

RCMB

Page 130: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

7200 - 8000

CARRIAGEWAY

1500 MIN.

FOOTPATH

1500

MIN

1000

MIN

1500

MIN

PR

OP

ER

TY

BO

UN

DA

RY

PR

OP

ER

TY

BO

UN

DA

RY

15700 MIN - 20000 MAX

ROAD RESERVE

3%

3%

C

L

NOTES:

1. REFER TO TYPICAL DETAIL DRAWING NO.

2012-5002-001 AND 2012-5002-002 FOR KERB AND

WATER TABLE DETAIL

2. REFER TO TYPICAL DETAING DRAWING NO.

2011-5001-001 FOR FOOTPATH DETAIL

3. TREES TO BE APPROVED BY PARKS AND GARDENS

TEAM LEADER

DRAWING NUMBER

CODESCALE AT A1

REV

Bridge to Opportunity

The Rural City of

MANAGER

DESIGN

DRAWN

CHECKED

SIGNATURES DATE

REV

REV

AC

A

NTS

SD001

2012-5006-003

TYPICAL DETAIL

LOCAL STREET

RCMB

Page 131: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

2400 MIN

CARPARK

7000

1500

MIN

PR

OP

ER

TY

BO

UN

DA

RY

25000 MIN

ROAD RESERVE

3%

3%

1200

BIKE LANE

C

L

PR

OP

ER

TY

BO

UN

DA

RY

1500 MIN

FOOTPATH

1500 MIN

FOOTPATH

2400 MIN

CARPARK

1200

BIKE LANE

1500

MIN

NOTES:

1. REFER TO TYPICAL DETAIL DRAWING NO.

2012-5002-001 AND 2012-5002-002 FOR KERB AND

WATER TABLE DETAIL

2. REFER TO TYPICAL DETAING DRAWING NO.

2011-5001-001 FOR FOOTPATH DETAIL

3. TREES TO BE APPROVED BY PARKS AND GARDENS

TEAM LEADER

4. MAY NOT REQUIRE PARKING ON BOTH SIDES IN

ALL CASES

1500

MIN

1500

MIN

DRAWING NUMBER

CODESCALE AT A1

REV

Bridge to Opportunity

The Rural City of

MANAGER

DESIGN

DRAWN

CHECKED

SIGNATURES DATE

REV

REV

AC

A

NTS

SD001

2012-5006-004

TYPICAL DETAIL

COLLECTOR

RCMB

Page 132: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

2400 MIN

CARPARK

7000

1500

MIN

PR

OP

ER

TY

BO

UN

DA

RY

25000 MIN

ROAD RESERVE

3%

3%

C

L

PR

OP

ER

TY

BO

UN

DA

RY

3000 MIN

SHARED PATH

3000 MIN

SHARED PATH

2400 MIN

CARPARK

1500

MIN

NOTES:

1. REFER TO TYPICAL DETAIL DRAWING NO.

2012-5002-001 AND 2012-5002-002 FOR KERB AND

WATER TABLE DETAIL

2. REFER TO TYPICAL DETAING DRAWING NO.

2011-5001-001 FOR FOOTPATH DETAIL

3. TREES TO BE APPROVED BY PARKS AND GARDENS

TEAM LEADER

1500

MIN

1500

MIN

DRAWING NUMBER

CODESCALE AT A1

REV

Bridge to Opportunity

The Rural City of

MANAGER

DESIGN

DRAWN

CHECKED

SIGNATURES DATE

REV

REV

AC

A

NTS

SD001

2012-5006-005

TYPICAL DETAIL

COLLECTOR WITH SHARED PATH

RCMB

Page 133: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

DRAINAGE KERB OUTLET FOR UPRIGHT KERB

DRAWING NUMBER

CODESCALE

REV

Bridge to Opportunity

The Rural City of

MANAGER

DESIGN

DRAWN

CHECKED

SIGNATURES DATE

REV

REV

AC

0

NTS

SD001

2012-5012-001

TYPICAL DETAIL

KERB DRAIN ADAPTER

RCMB

Page 134: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

VA

RIE

S200

200 REFER PLAN

GATIC CLASS D - 301C SERIES IN PAVEMENTS.

PCP (OR EQUIVALENT) PRECAST CONCRETE

COVER AND FRAME IN ALL OTHER AREAS.

GRATED INLET PITS TO BE FITTED WITH HOT

DIPPED GALVANISED FLOOR GRATE IN 100mm

REINFORCED CONCRETE SURROUND.

REFER TO STORMWATER

PLAN AND LONGITUDINAL

SECTIONS FOR PIPE

DETAILS AND LAYOUT

RE

FE

R P

LA

N200

200 REFER PLAN

NTS

JUNCTION PIT (JP) & GRATED INLET PIT (GIP)

-

1

PLAN

1

-

SECTION

MIN

200

MIN

MIN

MIN

200

MIN

MIN

200

MIN

DRAWING NUMBER

CODESCALE

REV

Bridge to Opportunity

The Rural City of

MANAGER

DESIGN

DRAWN

CHECKED

SIGNATURES DATE

REV

REV

AC

0

NTS

SD001

2012-5011-001

TYPICAL DETAIL

JUNCTION PIT

RCMB

Page 135: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

3500

MIN

200

BO

UN

DA

RY

ALLOTMENTS ON

HIGH SIDE

Ø100mm SEWER CLASS PIPE

REFER TO NOTE 3

FOOTPATH 1500 MIN

REFER TO NOTE 1

2100

MIN

BARRIER KERB

REFER TO NOTE 2

2.5% MAX

2.0% MIN

5.0% MAX

DRAWING NUMBER

CODESCALE AT A1

REV

Bridge to Opportunity

The Rural City of

MANAGER

DESIGN

DRAWN

CHECKED

SIGNATURES DATE

REV

REV

AC

0

NTS

SD001

2013-5000-001

TYPICAL DETAIL

VERGE CROSS SECTION

RCMB

NOTES:

1. REFER RCMB TYPICAL DETAIL DRAWING NO. 2012-5001-001

FOR FOOTPATH DETAIL

2. REFER RCMB TYPICAL DETAIL DRAWING NO. 2012-5002-001

AND 2012-5002-002 FOR KERB DETAIL

3. Ø100mm SEWER CLASS PIPE SHALL BE LOCATED UNDER

FOOTPATH AND IN LINE WITH KERB ADAPTERS (WHERE

FOOTPATHS ARE LOCATED ON HIGH SIDE OF THE ROAD)

Page 136: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

PERFORATED AG DRAIN PIPE

50mm TO 100mm LAYER OF MULCH

50mm TO 100mm SPACE BETWEEN TRUNK AND MULCH

GENTLY COMPACT BACKFILL,

USE WATER TO SETTLE SOIL

AROUND ROOT BALL

ROOT BALL PLACED ON FIRMLY COMPACTED

SOIL TO PREVENT SETTLING

TRUNK FLARE

EXPOSED

ROOT GUARD/BARRIER 500mm MINIMUM FROM

TREE TRUNK, INSTALLED PARALLEL TO KERB

AND/OR FOOTPATH ONLY, AT A DEPTH OF 300mm MIN.

DRAWING NUMBER

CODESCALE AT A1

REV

Bridge to Opportunity

The Rural City of

MANAGER

DESIGN

DRAWN

CHECKED

SIGNATURES DATE

REV

REV

AC

0

NTS

SD001

2013-5001-001

TYPICAL DETAIL

TREE PLANTING

RCMB

1. REMOVE POT, ALL WRAPPING,WIRE AND TIES

NOTES:

Page 137: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

R9.0 MIN RESIDENTIAL

R15.0 MIN COMMERCIAL

CONCRETE KERB AND CHANNEL

PROPERTY BOUNDARY

PROPERTY BOUNDARY

CONCRETE KERB AND CHANNEL

VARIES - REFER TO NOTE 3

DRAWING NUMBER

CODESCALE AT A1

REV

Bridge to Opportunity

The Rural City of

MANAGER

DESIGN

DRAWN

CHECKED

SIGNATURES DATE

REV

REV

AC

A

NTS

SD001

2013-5002-002

TYPICAL DETAIL

CUL - DE - SAC

RCMB

NOTES:

1. REFER TO RCMB TYPICAL DETAIL DRAWING NO.

2012-5002-001 AND 2012-5002-002 FOR KERB DETAIL

2. REFER TO RCMB TYPICAL DETAIL DRAWING NO.

2013-5000-001 FOR VERGE DETAIL

3. REFER TO RCMB TYPICAL DETAIL DRAWING NO.

2012-5006-001 TO 2012-5006-005 FOR ROAD CROSS

SECTION DETAIL

Page 138: RURAL CITY OF MURRAY BRIDGE...RURAL CITY OF MURRAY BRIDGE Engineering Guidelines For the Provision of Infrastructure February 2014 Prepared by: Engineering and Assets Rural City of

7000 - 8000

CARRIAGEWAY

5

1

1500 MIN

SHOULDER

4000 MIN

SWALE DRAIN

300x225 BOX CULVERT

APPROVED COMPACTED FILL

FOR DRIVEWAY

150mm BALLAST

20000 MIN

ROAD RESERVE

SWALE INVERT

SHOULDER

EDGE OF BITUMEN

CENTRE LINE

SWALE INVERT

PROPERTY BOUNDARY

EDGE OF BITUMEN

SHOULDER

PROPERTY BOUNDARY

100

MIN

5

MIN

5

MIN

150mm BALLAST DRIVEWAY300x225 BOX CULVERT

DRAWING NUMBER

CODESCALE AT A1

REV

Bridge to Opportunity

The Rural City of

MANAGER

DESIGN

DRAWN

CHECKED

SIGNATURES DATE

REV

REV

AC

A

NTS

SD001

2014-5000-001

TYPICAL DETAIL

RURAL ROAD

RCMB