Running in 2012 @ 4 TeV/beam Preamble Is it worth from the Physics point of view? What do we gain in...
-
Upload
augustus-lambert-douglas -
Category
Documents
-
view
216 -
download
2
Transcript of Running in 2012 @ 4 TeV/beam Preamble Is it worth from the Physics point of view? What do we gain in...
R. A
lem
any,
Evi
an 2
011,
Ses
sion
8: 2
012
Running in 2012 @ 4 TeV/beamPreambleIs it worth from the Physics point of view?What do we gain in terms of luminosity?What is the overhead in terms of machine/beam commissioning?
14/1
2/20
11
1/18
Many thanks to: L. Bottura, E. Todesco, J. Wenninger, M. Zerlauth, E. Nebot, 2xB. Holzer, J. Steckert, A. Siemko, M. Brugger, M. Lamont, P. Baudrenghien, E. Shaposhnikova, T. Baer, L. Pape, P. Sphicas, J. Varela, V. Kain, R. Assmann, R. Schmidt, M. Koratzinos
Preamble• Why LHC did not run @ 4 TeV in 2011? Let’s recall Chamonix 2011:
14/1
2/20
11R.
Ale
man
y, E
vian
201
1, S
essi
on 8
: 201
2
2/18
Main argument against running @ 4 TeV Status at the end of 2011
(Un)known number of expected quenches in 2011 (20 in 2010)
HW = 0 quenches Beam = 1 single-magnet spurious quench with beam*
Ref: A. Verweij, Probability of burn-through of defective 13 kA joints at increased energy levels,
Chamonix 2011
* Firing of Quench heater probably due to SEU, but not proven
There is the (≈)same risk associated with
running at 4 TeV and 3.5 TeV down time of 8-12 months
given the present consolidation status
• QPS consolidation work all over the year• Snubber capacitors installed in all dipole circuits• Efficient BLM protection
Is it worth from the Physics point of view?
14/1
2/20
11R.
Ale
man
y, E
vian
201
1, S
essi
on 8
: 201
2
3/18
Ref: P. Sphicas, View on CMS and ATLAS results, APPS 2011, Nov 30 – Dec 02, 2011
gg H (Hϒϒ,ZZ,WW)
Factor ~ 1.2
qq, gg
Factor ~ 1.5
qq, gg, qg
Factor ~ 4
Mx (GeV)
Factor ~ 3.5
R. A
lem
any,
Evi
an 2
011,
Ses
sion
8: 2
012
What do we gain in terms of luminosity?
14/1
2/20
11
4/18
FNfNN
L brev2
21
4
FLL ooTeV
TeV
TeVoTeV LL 5.3
5.3
44
*5.3
4
5.3*4 TeV
TeV
TeVTeV
oTeV
TeV
TeVoTeV LL 5.3
2
5.3
44
F: Xangle factor =f(ϵ,β*)!!
1. Due to ϵ↓: 2. Because ϵ↓ more aperture margin at the IT & TCT we get↓β*:
mTeV 875.0*4
~14% L ↑ for free from ε shrink due to 12.5% E ↑
3E+33
3.5E+33
4E+33
4.5E+33
5E+33
5.5E+33
6E+33
6.5E+33
7E+33
7.5E+33
8E+33
2 2.5 3
L(cm
-2s-1
)
εn (μm rad)
Lumi increase @ IP1/5 Lumi: Xangle factor @ 3.5 TeV
Lumi: Xangle factor+emittance srink @ 4 TeVLumi: Xangle factor+emittance + beta* srink @ 4 TeVLumi: Xangle factor+emittance @4TeV+ beta* = 0.7 m
+23% L increase if β* = 0.7 m0.88
0.89
0.9
0.91
0.92
0.93
0.94
0.95
0.96
0.97
2 2.5 3
Xang
le fa
ctor
εn (μm rad)
30% L ↑ from ε & β* shrink
+23% L ↑ if β*=0.7m
L (c
m-2
s-1)
F
ϵn
10
15
20
25
30
35
40
2 2.5 3
Pile
-up
εn (µm rad)
Pile
-up
ϵn
303540
25201510
Nb=1380N1=N2=1.5 1011 p+/bunch
R. A
lem
any,
Evi
an 2
011,
Ses
sion
8: 2
012
Overhead in terms of HW Commissioning• Main circuits• Extra powering tests today the powering test stops @6000
A; two extra steps @7000 A would be needed:• One cycle• One energy extraction from QPS• Time estimate: ~ 5 hours/circuit (circuit = RB, RQD, RQF)
• Inductance coefficients recalculation (at least 2 ramps one per QPS board) • RB.A78 - ElQA tested up to 1.6 kV instead of 1.9 kV due to bad insulation on
magnet B30.R7 (NC 1060444) --> limited to 4 TeV, veto to be lifted for higher energies
• Things that are not needed • Reconfiguration of energy extraction – not for 4 TeV (certainly needed for 5
TeV) See next slide• Change of nQPS thresholds to adapt to reduced quench margin (not for 4
TeV)• No quench issue expected till ~5 TeV (RB.A78 had a training quench below!)
14/1
2/20
11
5/18
R. A
lem
any,
Evi
an 2
011,
Ses
sion
8: 2
012
Energy Extraction System
14/1
2/20
11
6/18
** nQPS SymQ Thresholds will have to be recalculated for 6800 A ?
OK
to g
o
Ref: J. Steckert, Implication of increased beam energy on QPS, EE, Time Constants, Chamonix 2011
τ (time constant)
Limit=150
Limit=|15.5|
**
R. A
lem
any,
Evi
an 2
011,
Ses
sion
8: 2
012
Overhead in terms of HW Commissioning
• Inner Triplets:• All commissioned up to 5 TeV except:• IT.R1 weak electrical insulation of QH YT1121 to coil
and/or ground (NC 1017174) --> limited to 3.5 TeV without QH reconfiguration (high capacitance PS)• Dedicate Quench Heater Power Supply under
construction to be installed and ready for start up with beam
14/1
2/20
11
7/18
R. A
lem
any,
Evi
an 2
011,
Ses
sion
8: 2
012
Overhead in terms of HW Commissioning• IPQ/IPD• The current powering test commissions them
up to 3.5 TeV. What has to be done is, simply, to extend the last powering test to I_PNO corresponding to 4 TeV.
• Others• 600 A 5 TeV• 120 A 5 TeV• 60 A 7 TeV
Total Estimated Overhead 3 days
14/1
2/20
11
8/18
R. A
lem
any,
Evi
an 2
011,
Ses
sion
8: 2
012
UFOs: Energy Extrapolation
14/1
2/20
11
9/18
17 dumps by UFOs in 2011: 11 MKI UFOs 4 UFOs @Experiments 2 Arc UFOs
Ref: T. Baer, UFOs at LHC, Evian Workshop 2011
3 dumps at 4 TeV
by Arc UFOs
Losses of all arc UFOs in 2011 are scaled up = f(energy Eduardo’s IPAC’11 paper) and compare to the BLM thresholds at the corresponding energy
(MKI UFOs scale similarly with energy)
• Signal/threshold for UFOs is about 55% higher at 4TeV than at 3.5 TeV. Hence, we would have had 3 dumps if we were running at 4TeV this year, compared to 2 dumps which we actually had.
• For >1000 bunches the UFO rate ~ kte energy dependence takes over > 5 TeV
• Not included (margin between BLM thresholds and actual quench limit, 25ns bunch spacing, intensity increase, beam size, scrubbing)
Data 14.04. and 31.10.2011
R. A
lem
any,
Evi
an 2
011,
Ses
sion
8: 2
012
SEU Evolution 2011
14/1
2/20
11
10/18
Ref: G. Spiezia, M. Brugger, M. Calviani, J. Mekki for R2E, Overview of R2E related events during 2011, CERN-R2E Review 12.11.11
Ref: G. Spiezia, R2E – experience and outlook for 2012, Evian 2011
• 50% of the events are located in the Dispersion Suppression elements and are dominated by QPS
• The most critical areas are UJ14/UJ16 where 50% of the events provoked a beam dump
By Equipment• QPS SEU: Reiner’s talk on
Monday mitigation measures during Xmass’11 shut down to keep the SEU kte regardless the luminosity
• Cryo SEU: Serge’s talk on Monday mitigation measures during Xmass’11
22% of STABLE BEAMS fills were dumped by SEU Markus’ talk on Monday
480b768b
912b1092b
1236b1380b
R. A
lem
any,
Evi
an 2
011,
Ses
sion
8: 2
012
SEU: Summary & Forecast
14/1
2/20
11
11/18
Ref: G. Spiezia, M. Brugger, M. Calviani, J. Mekki for R2E, Overview of R2E related events during
2011, CERN-R2E Review 12.11.11
LHC
Ref: J. Christiansen, SEE’s In the LHC experiments, CERN-R2E Review 12.11.11
EXPERIMENTS
2012 predictionNo mitigation With mitigation
150 SEU 45 SEU
Ref: G. Spiezia, R2E – experience and outlook for 2012, Evian 2011
R. A
lem
any,
Evi
an 2
011,
Ses
sion
8: 2
012
BLM
14/1
2/20
11
12/18
X axis = dump threshold for 40 μs RSY axis = maximum noise observed in each monitor during a period of NO BEAM
• Ideally everything should stay below 10% we have some margin and we are confident that we would not dump on noise spikes.
• A few monitor go above 10% of the threshold and it will be studied whether or not need new thresholds.
• Data from 34 hours starting on 2011-11-07 07:00:00 (last technical stop)
NOISE at 100% of dump thresh.NOISE at 10% of dump thresh.
• 450 GeV• 3.5 TeV• 4 TeV
Dump Threshold 40 μs RS (Gy/s) (from simulations)
Noi
se (G
y/s)
E. Nebot
R. A
lem
any,
Evi
an 2
011,
Ses
sion
8: 2
012
LBDS
• XPOC BLM limits extrapolated to 4.0 TeV from 2011 measurements at energies up to 3.5 TeV • (Likely) to be fine tuned during operation when data
with high intensity dumps at 4.0 TeV are available.• Abort gap cleaning validation at 4.0 TeV needed• but probably this will be requested any way if 3.5 TeV
after the winter TS• The energy of the LBDS is presently clamped at 5.0 TeV
(in the Beam Energy Interlock) no changes to be made at 4.0 TeV• TCDQ functions to be extended to 4.0 TeV (like all the
other collimators)
14/1
2/20
11
13/18
BTVDD B1 1380 bunches @ 3.5 TeV
R. A
lem
any,
Evi
an 2
011,
Ses
sion
8: 2
012
Machine Protection Validation
• Standard MP tests to be done irrespective of the energy• The exact details also depend on changes that are
made in the stop (that may be unrelated to the energy itself !). • Tests at 4 TeV take a bit longer since the ramp
will be longer (84 s!)• Settings @4 TeV will be different (BLMs, etc) to
be checked more carefully (since the values change), but most of this will be transparent
14/1
2/20
11
14/18
RF: Longitudinal stability
15/18
Broadband stability criteria
Narrow-band stability criteria
Without blow-up the threshold quickly decreases during the acceleration ramp
With a blow-up that keeps bunch length constant, the threshold increases linearly with the RF voltage
Thanks to the longitudinal blow-up, the stability is actually improved during the acceleration ramp as the voltage rises
At constant bunch length and voltage, it is independent of energy
Ref: E. Shaposhnikova, Longitudinal Beam Parameters during acceleration in the LHC, LHC Project Note 242, Dec 2000
14/1
2/20
11R.
Ale
man
y, E
vian
201
1, S
essi
on 8
: 201
2
Courtesy of P. Baudrenghien & E. Shaposhnikova
R. A
lem
any,
Evi
an 2
011,
Ses
sion
8: 2
012
Chromaticity Control @ 4 TeV
14/1
2/20
11
16/18Ref: N. Aquilina, E. Todesco, Decay of chromaticity at injection and operation at 4 TeV,
LMC 07.12.2011
N. Mounet, Impedance effects on beam stability, Evian S7
We learnt the importance of keeping the chromaticity under
control next year if tight collimator settings.
R. A
lem
any,
Evi
an 2
011,
Ses
sion
8: 2
012
Re-commissioning in 2012
14/1
2/20
11
17/18
Ref: M. Lamont, Operational Overhead of Moving to Higher Energies, Chamonix 2011
2012
2
R. A
lem
any,
Evi
an 2
011,
Ses
sion
8: 2
012
Conclusion
• No show-stoppers from equipment point of view• Total commissioning overhead half a week• ~ Same Probability of burn-through of defective 13 kA
joints as for 3.5 TeV• Risk @ 3.5 TeV ≈ Risk @ 4 TeV down-time 8-12 months
• Important Gain in cross-section & luminosity ( L ~ 30%)
Running @ 4 TeV in 2012 is WORTH DOING!
14/1
2/20
11
18/18
R. A
lem
any,
Evi
an 2
011,
Ses
sion
8: 2
012
Dipole B30R7
14/1
2/20
11
19
QUALIFICATION VOLTAGE1600 V = 600 V (EE+PC) + 1000 V
(Voltage inside the coil)
Simulated MIITS by A. Verweij
Main arc dipole Voltage developed in the coil
1000 V
6771 A ~ 4 TeV
Only a change in the energy extraction resistors = decay time constant during a FPA, could release the veto on the 4 TeV, however at Chamonix 2011 this
solution was not considered safe
RB.A78 - ElQA tested up to 1.6 kV instead of 1.9 kV due to bad insulation on magnet B30.R7 (NC 1060444). Fault inside the cold mass, no possible to repair in situ the Emax for which the use of this magnet is still safe is 4 TeV, above this energy the magnet should be replaced.
R. A
lem
any,
Evi
an 2
011,
Ses
sion
8: 2
012
Preamble• What has radically reduced the number of spurious quenches in 2011:• QPS consolidation work all over the year• Snubber capacitors installed in all dipole circuits• Efficient BLM protection
14/1
2/20
11
20Ref: F. Bordry, LHC Energy in 2012 3.5 TeV or 4 TeV, LMC 30th Nov 2011
Preamble• Possibility asynchronous dump with multiple quenches (S56&S67)
Possibility of bus bar quenches + blindness of the nQPS SymQ if > 15 magnets quench
• 1 in 2010***, 0 in 2011 (N.B. S56-65 good sectors in terms of Rspl,max)
14/12/2011R. Alemany, Evian 2011, Session 8: 201221
Limit=150
Limit=|15.5|
**
** nQPS SymQ Thresholds will have to be recalculated for 6800 A
OK
to g
o
Ref: J. Steckert, Implication of increased beam energy on QPS, EE, Time Constants, Chamonix 2011
***2010: faulty power MOSFET in one of the trigger fan-out units qith ion pilot beam; no losses.
τ (time constant)
R. A
lem
any,
Evi
an 2
011,
Ses
sion
8: 2
012
FLUKA Studies of the asynchronous beam dump effects on LHC point 6
14/1
2/20
11
22
quenches have to be expected
quenches are possible
quenches are unlikely to happen
12
3
4 5
MQY.4R61, MQY.5R62, MB.A8R63, MB.B8R64, MQML.8R65
5 magnets will quench for sure+ 3 possible = 8 magnets
Energy deposition in bus bars ~ tenth mJ cm-3; but for bus bars in cell C8.R6 peaks a factor 10 higher are expected
Systematic uncertainties = factor 5 to 10!
Ref: R. Versaci et al, FLUKA Studies of the Asynchronous Beam Dump Effects on LHC Point 6, CERN-ATS-2011-236
Eb = 4.5 TeV 150 MJ50 ns bunch spacing, 42 bunches are swept from ideal trajectory = ~5 1012 p+
R. A
lem
any,
Evi
an 2
011,
Ses
sion
8: 2
012
Preamble• On top of this: the analysis of pyramid tests and ~375 ramps to 3.5 TeV
allowed to consolidate the Maximum Splice Resistance (Rspl,max) knowledge in a Bus Segment over LHC and so far, no degradation with time has been observed
14/1
2/20
11
23
Splice Type Magnet Rspl,max (nΩ)
Comments
Bus segment RB,RQD/F 0.3±0.8 Few ~ 3 nΩ
Intramagnet*
RB 3.3±0.9 8 dipoles
Intramagnet*
QRD/F 1.2±0.8 3+2 quad
* Intramagnet splices are less dangerous than bus segment splices, since the former are protected by the diodes. Additionally, all intramagnet splices have already been exposed to quenches.
Ref: Z. Charifoulline, Current Status & Long Time Evolution of Main Splice Resistances at 1.9K, 2nd LHC Splice Review, 29.11.2011
However, the knowledge of th
e
copper stabilize
rs status in the
machine has not changed
Preamble
14/1
2/20
11R.
Ale
man
y, E
vian
201
1, S
essi
on 8
: 201
2
24
s12 s23 s34 s45 s56 s67 s78 s81100
120
140
160
180
200
220
240
260
280
300RRR of busbar
RBRQ
The error bars are the RMS spreads of the distributions
Mean RRR of the copper busbar of the machine: 250±50
All sectors measured
Ref: F. Bordry, LHC Energy in 2012 3.5 TeV or 4 TeV, LMC 30th Nov 2011