RR218 - Peer review of analysis of specialist group ... · HSE Health & Safety Executive Peer...
-
Upload
vuongduong -
Category
Documents
-
view
236 -
download
0
Transcript of RR218 - Peer review of analysis of specialist group ... · HSE Health & Safety Executive Peer...
HSE Health & Safety
Executive
Peer review of analysis of specialist group reports on causes of construction accidents
Prepared by Habilis Ltd for the Health and Safety Executive 2004
RESEARCH REPORT 218
HSE Health & Safety
Executive
Peer review of analysis of specialist groupreports on causes of construction accidents
Liz Bennett BSc PGCE CEng MICE MIOSH FRSA Habilis Ltd
3 Market Place Shipston on Stour
Warwickshire CV36 4AG
The Construction (Design and Management) Regulations 1994 have introduced new duties for designers. It is argued that early intervention by designers and indeed clients can have a significant impact on construction safety during the main building phase and also during maintenance and demolition of structures.
Until the advent of these Regulations the principal blame for any construction site incident was generally laid at the door of the main contractor. The industry has found the cultural changes necessary for proper designer integration difficult to embrace and various projects have been initiated by the Health and Safety Executive to remedy this.
It was believed that an analysis of a series of randomly selected incidents might give evidence, or at least an indication, to a reluctant industry that designers can do more to improve safety and health in construction. The initial stage was to develop a methodology for carrying out this analysis. The secondary stage was to peer review and iteratively agree on those findings. This report is a summary of that review.
The findings very thoroughly underline the fact that the thinking behind the Regulations is sound and that designers can and so arguably should do more.
This report and the work it describes were funded by the Health and Safety Executive (HSE). Its contents, including any opinions and/or conclusions expressed, are those of the authors alone and do not necessarily reflect HSE policy.
HSE BOOKS
© Crown copyright 2004
First published 2004
ISBN 0 7176 2836 1
All rights reserved. No part of this publication may bereproduced, stored in a retrieval system, or transmitted inany form or by any means (electronic, mechanical,photocopying, recording or otherwise) without the priorwritten permission of the copyright owner.
Applications for reproduction should be made in writing to:Licensing Division, Her Majesty's Stationery Office, St Clements House, 2-16 Colegate, Norwich NR3 1BQ or by e-mail to [email protected]
ii
ACKNOWLEDGEMENTS
Acknowledgements are made to Malcolm James whose innovative approach to the analysis of
the accidents reviewed in this study was both stimulating and illuminating.
iii
iv
CONTENTS
1 BACKGROUND……………………………………………...…..11.1 Accident Rates………………………………………………………………………..1
1.2 Construction (Design and Management) Regulations 1994 – CDM……………...1
1.3 CDM Regulation 13 Difficulties for Industry……………………………………...2
1.4 CDM Difficulties for the Health and Safety Executive……………………………2
1.5 Industry Wide Initiatives……………………………………………………………3
2 PROJECT OBJECTIVES AND WORK PHASES…………….5 2.1 Project Objectives
2.2 Work Phases
3 SOURCE DOCUMENTS………………………………………..73.1 Accident Reports…………………………………………………………………… 7
3.2 Original Research Reports………………………………………………………….7
4 AUTHOR’S REMARKS………………………………………...94.1 Author Entry View…………………………………………………………………..9
4.2 Impact Of Fatal Accident Reports………………………………………………….9
5 ASSUMPTIONS AND PROCESSES………………………….11 5.1 Processes and Iterations……………………………………………………………11
5.2 Agreed Assumptions………………………………………………………………..11
6 FINDINGS………………………………………………………13
7 COMMENTARY……………………………………………….21
8 RECOMMENDATIONS……………………………………….25
APPENDIX 1 – CATEGORIES………………………………………27
APPENDIX 2- ACCIDENT ANALYSIS SHEETS………………….29
v
vi
EXECUTIVE SUMMARY
The Health and Safety Executive is committed to making a fundamental reduction in the
number of deaths, injuries and cases of ill health in construction. There is a view held by
some of the industry and underpinned by Regulations that designers could make a significant
difference. The key changes required are for designers to design structures that are safer and
healthier to build, maintain and demolish. Clearly operational issues must be considered as
well since they have a major effect on maintenance capability.
There are many in the industry, and in particular in the design community, who remain
unconvinced by the arguments that designers can and should make a difference to the way
they work. The purpose of this research package was to analyse actual incidents with respect
to designer involvement.
As the research evolved various other potentially useful indicators emerged and additional
requirements for information collection were identified. This research must therefore be seen
as part of an unfolding investigation into the best way to identify some of the key change
points for the industry.
The author has chosen to track personal views of the research for the reader as this was
judged helpful. In particular a certain amount of cynicism towards the arguments for real
intervention by designers was in place at the beginning of the programme. Long before the
end the author became completely convinced of the enormous importance of the need for
radical change amongst the design community.
The original research was modified after discussions between the author and the originator of
the incident summaries. It is recognised that further improvements could be made to the
collection of data and its analysis that could provide significant material for industry.
The original review of the incidents was conducted by Malcolm James, who did the
development of the methodology for the study and also summarised and analysed the
incidents in the first instance. The peer review that is the subject of this report acknowledges
the importance of Malcolm’s work but takes complete responsibility for statements within the
report.
The Report concludes that almost half of all accidents in construction could have been
prevented by designer intervention and that at least 1 in 6 of all incidents are at least partially
the responsibility of the lead designer in that opportunities to prevent incidents were not
taken.
The Report makes no commentary on culpability or the moral and ethical dimensions of
designer failings. These must be decided in other places.
vii
viii
1 BACKGROUND
1.1 ACCIDENT RATES
The United Kingdom construction industry has one of the lowest accident rates in the world
following generally declining rates over recent decades. Latterly, however, a levelling off has
been observed and there remain various categories of seemingly intractable accidents. In 2002
there where 80 fatal accidents in construction, which is nearly seven each month. The cost of
these deaths to the families and friends of those killed is incalculable. The cost to the industry
and the UK at large can more easily be quantified but never accurately assessed. In any case
this price is always too high for all concerned.
1.2 CONSTRUCTION (DESIGN AND MANAGEMENT) REGULATIONS 1994 – CDM
For some years there has been a belief that early contributions to the construction and
building processes from both clients and designers could make a radical improvement to the
construction processes during the whole life of a structure. Anecdotal evidence from industry
showed that the construction and building industry is capable of delivering safe construction
but that it regularly fails to do so. Changing the emphasis of responsibility towards those who
commission, scope and design works so that the end result is seen as a team approach to life
long safety and health management was expected to deliver benefits.
The Temporary and mobile construction sites Directive 89/391/EEC was introduced across
the European Economic Community to change the way construction health and safety is
managed. In the UK this Directive was implemented as two sets of construction regulations:
the Construction (Design and Management) Regulations 1994 – CDM - and the Construction
(Health, Safety and Welfare) Regulations 1996 - CHSW.
CDM put new duties on clients and designers and introduced a new statutory appointment of
Planning Supervisor. The concept behind CDM was one of teams of competent appointees
providing appropriate information throughout the life of the project for use by those who had
the capacity to influence health and safety for good or ill. There was also a requirement to
allow for adequate resources in all senses to achieve the same ends.
The opportunities presented by CDM would seem to be clearly apparent, based as they are on
sound project management philosophy and holistic risk management.
The regulations were, however, generally considered by consultants and advisors in their
narrowest sense and frequently not read or applied in conjunction with the CHSW or other
relevant regulations, without which their application becomes meaningless.
Further, the Regulations were not so ordered as to make duty holders’ duties easily apparent
to the vast numbers of those who were obliged to wrestle with legal terminology for the first
time.
Designers’ duties are generally encapsulated in Regulation 13, which is often considered as
stand alone, though there are significant implied duties for designers embedded in other
regulations, mainly to do with competence, communication, co-ordination and co-operation.
Regulation 13 has two key aspects to it. Regulation 13 (i) essentially requires designers to
1
ensure that clients are aware of their duties, allowing the non-expert client to be kept
informed by professionals. Regulation 13(ii) can be summarised as a requirement to
contribute to the designing out of hazards and risks of downstream contractor processes.
1.3 CDM REGULATION 13 DIFFICULTIES FOR INDUSTRY
The requirements of CDM Regulation 13 have not been effectively managed by some parts of
industry. Various reasons for this may exist.
· The wording of the regulation is insufficiently precise to set standards in relation to
legal duties.
· There has been an assumption that CDM could stand alone without an understanding
of building, construction and maintenance processes, including demolition, and of
other requirements such as operational constraints. These other factors are often
overlooked to the detriment of decision making.
· Many designers are either unaware of, or not up to date in, modern construction and
building processes. For them to make any real contribution to safety and health they
clearly need to understand where the challenges are that face those who will
construct.
· There has been an assumption that the regulation demanded risk assessment now
commonly referred to as DRA or Design Risk Assessment. Generally the teaching of
CDM to the industry has been conducted by health and safety professionals with
experience in contractor risk assessments. They have tended to translate this across to
the design community. In fact the Regulation makes no reference to risk assessment
nor is the Regulation 13 (2) duty best approached by the same methods as contractor
risk assessments, being rather a design process. Most DRAs are poorly conducted,
retro-fitted, contractor risk assessments.
· Many of the procurement routes, particularly those facing architects, make early
intervention difficult from a commercial perspective.
· Civil law is at odds with CDM in that case law exists that states that responsibility for
safety and health on site is the responsibility for the constructor alone. Such civil law
is in place at every contract while the criminal law of health and safety may only
present as a challenge to this where there is, for whatever reason, enforcer
intervention.
· The fear of criminal action has resulted in production of excessive paperwork as an
attempt to manage liability. In fact such paper trails are generally of poor quality and
do little other than add to costs. They do not reduce liability unless they are effective.
1.4 CDM DIFFICULTIES FOR THE HEALTH AND SAFETY EXECUTIVE
· The HSE cannot visit every site and must select those most appropriate to deliver
cultural change to a diverse industry. While large projects are an obvious target the
smaller projects, frequently under resourced in terms of competent advice, continue to
be the places where many of the accidents happen.
· HSE field inspectors are experts in the law of health and safety and its enforcement.
Design is, however, a complex professional discipline requiring years of training and
experience. For inspectors to challenge decisions taken by designers or to ask why
alternatives have not been considered is not possible except for those inspectors with
a specialist background in the appropriate discipline. Even within the industry there is
a considerable range of specialist disciplines at work and the provision of competent
inspectors to match every such situation is not tenable.
· Many of the difficulties that exist for industry also exist for inspectors.
· A ten year fatal accident high set challenges to the thinking behind CDM. Many
questioned whether CDM had done anything but add costs to industry.
2
1.5 INDUSTRY WIDE INITIATIVES
The Deputy Prime Minister, John Prescott, held a construction health and safety summit
where he challenged industry to make commitment to improvement. Several strategic
initiatives were launched to bring the construction industry together and improve performance
across all aspects of the construction process.
Rethinking Construction and its daughter report, Rethinking Health and Safety in
Construction were produced.
Designers were challenged to make a more positive contribution to health and safety in
construction.
3
4
2 PROJECT OBJECTIVES AND WORK PHASES
2.1 PROJECT OBJECTIVES
The objectives of the whole project were to examine a randomly selected sample of specialist
inspector reports to establish:
· Whether the case for CDM can be supported
· Whether designers are really missing opportunities to contribute to health and safety
in construction
· How HSE can best engage in driving change at field enforcement level
2.2 WORK PHASES
2.2.1 Phase 1: Initial research by Malcolm James
A random selection of 91 construction specialist inspectors reports were taken and analysed.
Those that were clearly not to do with design were set aside but included in the final
numerical computations. The categories selected for this analysis were in the first instance
iteratively developed by Malcolm James, who also assigned scores to most categories. These
categories are listed in Appendix 1.
Each report was summarised, assessed according to categories and notes made in relation to
such matters as design failings.
A table was developed that set the opportunity presented to the designer against the
opportunity taken by that designer in relation to intervention to prevent realisation of an
incident. Colour coding was used for ease of recognition at the request of the HSE.
2.2.2 Phase 2: Peer review of research by Liz Bennett of Habilis
Each report was reassessed without reference to the initial summaries but using the same
categories. The two results were then compared. Where differences occurred the second
assessment reconsidered the data and original assessor’s remarks to gain clearer
understanding of the reasons for disparity.
Outstanding differences were discussed at a meeting between the two reviewers. One of the
difficulties encountered was that in some examples different assumptions had been made. In
others more than one designer could have had an influence. Unless reviewers had selected the
same designer the opportunity assessment could easily differ.
Keywords were a further area of difficulty since these depended on a range of variables. Their
use to facilitate later search was however agreed.
2.2.3 Phase 2: Amended review and agreed forward strategy
An agreed forward strategy was developed as follows:
A list of standard keywords would be established for selection by assessors. This is seen as
important for future analysis of findings in relation to particular work activities or common
failings as it will facilitate a general search enquiry.
5
Almost all the reports predate CDM and focus largely on construction processes. This means
that Temporary Works Designers feature in a way that is likely to be disproportionate to the
potential contribution to be made by other designers. It was agreed that a separate analysis of
each designer should also be made so that temporary works may be selected out to consider
other designer aspects or included in if that is more pertinent to the point being made.
The analysis was to consider the current project only and not any design or construction for
the original works. From time to time where the original design had been a clear contributing
factor, say to later maintenance, this would be noted but not scored.
It was agreed that in areas of doubt assessors should err in favour of the designer.
In certain instances assumption would need to be made and stated about stakeholder
competence ie the competence of the designer in specialist design areas. This would allow
clearer understanding by readers of the reviewer thought processes.
The designer effort assessment can be taken as a rough indicator of designer costs. It was
noted that designer effort is frequently a cost centre for designers even when economic
benefits accrue to the project. These benefits are generally delivered to the contractor and/or
the client unless contractual arrangements also deliver economic benefit to designers.
It was agreed that for the third iteration the forms would be redesigned, slightly reordering the
existing sections and providing opportunity to assess separately the different designers
contributing to a project. It was anticipated that this would be particularly useful for future
analysis.
It was recognised that what the designer should have done encompasses moral, professional,
economic and statutory obligations. It was agreed that the review should concentrate on what
the designer could have done set against what was done, without making judgements about
duty and responsibility, which, in relation to statutory duties, would be a matter for the courts
to decide.
It was agreed that while a ten point separation was useful during the analysis phase this
should be grouped for the final table into five double sections. The final table is thus
presented as 5x5 rather than 10x10
It was agreed that the scales should be more closely prescribed in the introduction to reduce
the variation amongst assessors. This is to echo the level of detail given in the accident
severity scale.
It was accepted that neither assessor had been entirely consistent in considering industry
today and had from time to time included industry opportunities. Such comment adds value
but assumptions need to be clearly identified.
Some of the reports assessed advisory visits. It was agreed that where there was a report there
was a potential for harm and inclusion of such reports was thus valid as they described
opportunities for all parties to a project.
All of the incidents were reassessed in light of the above decisions.
Only the final iteratively agreed results are included in the Appendix 1 to avoid confusion.
The text describing the incidents is almost entirely that of the original assessor, Malcolm
James, with occasional additional remarks by Liz Bennett of Habilis, where it was felt that
these added greater clarity or useful comment.
6
3 SOURCE DOCUMENTS
3.1 ACCIDENT REPORTS
When an accident occurs it is usually the local HSE Enforcement Officer who attends in the
first instance. If it is likely that specialist construction expertise is required the case or
elements of the case may be passed to the construction specialist for additional input to the
enquiry. Where the report relates to request for specialist advice, this is referred to an
inspector with the necessary competence.
All construction specialist reports are stored together, being sorted by type of activity and
date. Thus roof work incidents are kept in sequential order. Ground works are similarly
sorted.
For the purposes of this research handfuls of specialist inspector reports were removed from
the store ensuring that there were examples from each general category but otherwise making
a random selection of bundles of reports.
At first review those reports that clearly did not have anything to do with design were sifted
out and set aside. The iterative process described in section 2 above were then applied to the
residual majority. It is important to recognise that these incident reports relate to real
happenings affecting the lives of many people. Because the documents must remain
confidential for legal reasons they are not included in this report except in sanitised summary.
Similar incidents to those described happen regularly in construction and readers will often be
able to recognise from their own experience incidents that relate closely to those reported.
3.2 ORIGINAL RESEARCH REPORT
The original research conducted by Malcolm James did not reach publication prior to this
additional work being conducted because it clearly needed external validation. His
preliminary work, however, set the scene for the whole of this report.
Malcolm James experience of the construction industry and of the law of health and safety in
that industry is clear and his comments and notes form a critical part of the completed
document. His development of some ways to assess incidents in a structured manner is very
helpful to both industry and enforcer alike as it provides a framework and breakdown of the
critical elements to be considered by stakeholders in the design process.
Notwithstanding the above, the results presented are only those of the combined iteration as it
was agreed that this would be most helpful for industry. Consequently neither of the main
source document sets is available for public scrutiny.
7
8
4 AUTHOR’S REMARKS
4.1 AUTHOR ENTRY VIEW
The following remarks are provided to give the reader an indication of the mindset of the
reviewer and author of this report throughout the process. They are personal commentary and
provided to give background information to those who may wish to accept or refute the
findings.
Construction industry design professionals are generally taught to be backward focussed,
dependent on codes, standards and experience of similar projects undertaken successfully.
Clearly there are some exceptions to this retrospective approach.
Innovation in itself introduces risk and many clients prefer tried and tested methodology.
The construction industry spans across a great many levels of competence and a range of
sectors and types of activity, some of which have little synergy. No single solution to the
continuing high levels of accident and ill health problem suffered as a result of industry
activity can fit all work.
The author is passionate about reducing harm to at risk groups of people and while convinced
that designers can make a contribution to the process of safe and healthy construction was less
persuaded that this change was worth seeking given the costs to individuals, industry and
society at large. Further, industry wide problems with CDM compliance already experienced
seemed to indicate that the chance of delivering significant added value change to the culture
of a diverse industry was small.
The author was and is also concerned that health and safety professionals still hold the main
power base in terms of delivering advice, training and proposing solutions. While their
contribution to construction health and safety is clearly essential, the special nature of design
means that their lead in this area is likely to devalue the potential contribution designers can
make.
Standards of training and competence for designers have not been established across industry
by those experts in design who could be demonstrating best practice and the added value of
this additional effort. Steps are being taken through the Construction Industry Council and its
member bodies to remedy this.
University courses have not responded to the requirements for educational change in
construction and building design to a sufficient level. There are well rehearsed arguments
relating to this problem and in any case change is also afoot here. It is clear, however, that
undergraduate courses already impose extremely high workloads on staff and students alike.
In summary the entry frame of mind was that the research was likely to be interesting but
arguably only able to deliver skewed results, set out as a politically correct sop to the
requirements of a European Directive.
4.2 IMPACT OF FATAL ACCIDENT REPORTS
Many of the incidents reported were technically interesting. Some did not provide sufficient
information to take any but an overview. Most could have resulted in multiple fatalities,
including multiple fatalities to members of the public. Some of the projects would have
9
required highly competent designers to provide creative solutions or the spending of
considerable time and therefore cost to deliver solutions.
Some of the accidents were simply avoidable. Some of these were fatal or resulted in serious
injury. Reading of incidents that have destroyed lives and had a knock on effect to many
others associated with the victim in whatever way had a very sobering effect.
None of the incidents should have happened. Many could have been prevented very easily.
Many could have been prevented by small actions by someone involved.
Every attempt was made to absolve designers of responsibility. In particular Temporary
Works designers and manufacturers were removed from the main quoted statistics.
The final numbers are not just persuasive but absolutely convincing. Designers can do more.
Designers need to learn how to do better or else be made to do so by whatever means. The
clear message should be one of warning and challenge for the whole design community.
10
5 ASSUMPTIONS AND PROCESSES
5.1 PROCESSES AND ITERATIONS
The process for the research was driven by Malcolm James’ original work, which was slightly
modified in the third iteration.
Each incident was sanitised as a summary description from the report. Various measures were
given quantitative values from what it is agreed must be inadequate information in many
instances. These assessments were validated, however, by peer review and comparison and
the close fit gives confidence to the author of the values placed on the findings.
Many of the assessments made were not of primary interest to the objectives of the report.
These additional values provide some commentary on matters such as design effort/cost, level
of specialist knowledge required etc which enrich the central debate. There is also an
assessment made of whether a Planning Supervisor appointment could have made a
difference to the outcome and likewise whether a site safety supervisor could have prevented
the incident. This was done to provide a minor commentary on the future of the coordination
role at design and site supervision stages.
5.2 AGREED ASSUMPTIONS
The reports used for the research related to incidents prior to CDM and thus generally made
reference to construction products and processes with little reference within those reports to
design and planning aspects of construction. Certain assumptions were made for the purposes
of the research and are listed here for clarification.
· Designers were given the benefit of any doubt.
· The aspects of design considered related to the project in hand. Thus maintenance
work referred to designer contribution to that maintenance but not to the original
design of the structure. Where poor design had led to difficulties with maintenance
this was pointed out in the notes but not given any value in the overall quantitative
assessment.
· Where assumptions about designer competence were critical to the assessment these
are stated.
· Designer effort is judged to be roughly equivalent to designer costs. It should be
recognised that no indication of the procurement route or contract arrangements is
given in the reports and this can have a significant effect on the ability of designers to
contribute effectively.
· It is here assumed that the designer is appointed prior to any design. In some
instances some designers are required to make speculative outline design as part of
the tender process. No allowance is made for such factors.
· No assumptions are made about designer culpability in law, which assessment must
be a matter for the courts.
· Apportionment of responsibility to architects or consulting engineers is in most cases
arbitrary since most reports are silent on the nature of the design professionals
involved. For the final commentary these two groups have been assessed together as
principal designers.
11
12
6 FINDINGS
6.1 Prior to CDM data collection by HSE specialist inspectors concentrated on the facts
at the scene and did not generally detail any significant designer issues except where
these related to temporary works or the design of construction products.
6.2 Identification of procurement routes and contractual relationships was not considered
part of the investigation protocol in any the reports considered.
6.3 The results can only give a general indication of the potential for change but it must
be remembered that the assumption was that any doubts should be resolved in the
designers’ favour. In other words, the results are indicative of the level of potential
change that could be achieved.
6.4 The summary table below collects results from all incidents.
6.5 Tables 2 to 6 select out different groupings that the author judged would add value to
the final output so that new targets can be set for activity by the whole industry to
effect improvements.
13
Table 1 Summary chart
Architect Consultant TW Other
1. 8G Contractor
2. 4J
3. 4G M
4. 6G M
5. 6J M
6. 6G
7. 2E
8. 4J
9. 6J
10. 6J
11. 6J
12. 8E
13. 10J
14. 4E 8E
15. 8J 10E 10J M
16. 6J 8J M
17. 4E 4E 4G M
18. 6E 10J
19. 10J 10J Contractor
20. 4C
21. 6E
22. 8J M
23. 6J 8J M
24. 6G M
25. 4E
26. 4E
27. 10J
28. 2C 10J
29. 10J Scaffolder
30. 10J 10J
31. 10J Scaffolder
32. 10J
33. 10J
34. 6E
35. 8G Contractor
36. 10J
37. 4J Subcontractor
38. 4C 10J
39. 10J
40. 6E
41. 4C
42. 4E
43. 8E 8J
44. 10G
45. 6E M
46. 2C
47. 4E 10J
48. 8G
49. 6G 10J
50. 2C 8E 6C
51. 4C
52. 2C
14
53.
54. 4C M
55. 10G
56.
57.
58. 4E
59. 4E
60.
61. 10J
62. 8J M
63. 6C M
64. 8G
65. 8G
66. 8G
67. 6E 10J
68. -
69. 2A
70. -
71. 8G
72. 4E M/Transport
73. -
TOTALS
TOTAL 10 5 14 13 41
TOTAL 2 5 4 3 13
TOTAL 7 5 5 7 24
TOTAL 2 3 1 0 6
TOTAL 21 18 22 23 84
Notes:
1. There are 73 reports analysed above. In some cases there can be seen to be more than one party with
responsibility for design issues.
2. The summary diagram takes several views of the data. It considers the reports and is the source for the
following tables:
Table 2 – All design: worst case only included;
Table 3 – All design: all contributions to each incident;
Table 4 – Main design only: worst case only included;
Table 5 – Temporary works only; and
Table 6 – Supplier/Manufacturer only.
3. It should be pointed out that it was not always easy to decide who the designer was, an architect or
engineer.
15
Table 2 Summary of designer intervention
All design: Worst case result only taken in each incident
What designers could have done
Very little A bit more Major
contribution
A lot more Critically
significant
0-2 4 6 8 10
Wh
at
desi
gn
er
did
What was
necessary
A 1 0 0 0 0
Something C 2 4 1 0 0
Not enough E 1 6 5 3 0
Not nearly
enough
G 0 2 3 7 2
Nothing J 0 3 4 5 18
Summary by category
Rating & total number Recommended consideration
5 Designer not implicated
18 Designer could improve
9 Designer may be implicated
39 Designer prosecution supportable
Notes
1 Total incidents considered in detail 73
2 Total incidents reported 91
3 The balance were clearly not to do with design but must be taken into sample for comparisons
4 Percentage of incidents likely to be the subject of further investigation of a designer because the
designer has failed to take enough action when such action could have made a major contribution to
accident prevention is 39/91 x 100 = 43% or almost half of all cases reported.
5 A further 9/91 x 100 = 10% may well be asked to make improvements to their systems and be subject to
criticism for taking inadequate steps at the design stage of a project.
16
Table 3 Summary of designer intervention
All design: All contributions to each incident
What designers could have done
Very little A bit more Major
contribution
A lot more Critically
significant
0-2 4 6 8 10
Wh
at
desi
gn
er
did
What was
necessary
A 1 0 0 0 0
Something C 4 5 2 0 0
Not enough E 1 10 6 4 1
Not nearly
enough
G 0 2 4 7 2
Nothing J 0 3 6 6 20
Summary by category
Rating & total number Recommended consideration
6 Designer not implicated
25 Designer could improve
11 Designer may be implicated
42 Designer prosecution supportable
Notes:
1 Total incidents considered in detail 73
2 Total incidents reported 91
3 The balance were clearly not to do with design but must be taken into sample for comparisons
4 Percentage of incidents likely to be the subject of further investigation of one or more designers because
the designer has failed to take enough action when such action could have made a major contribution to
accident prevention expressed as a function of the number of incidents is 42/91 x 100 = 46% or almost
half of all cases reported.
5 A further 11/91 x 100 = 12% may well be asked to make improvements to their systems and be subject to
criticism for taking inadequate steps at the design stage of a project.
17
Table 4 Summary of designer intervention
Main design only: Worst case result only taken in each incident
What designers could have done
Very little A bit more Major
contribution
A lot more Critically
significant
0-2 4 6 8 10
Wh
at
desi
gn
er
did
What was
necessary
A 0 0 0 0 0
Something C 3 3 0 0 0
Not enough E 1 5 3 3 0
Not nearly
enough
G 0 0 2 4 1
Nothing J 0 2 5 1 4
Summary by category
Rating & total number Recommended consideration
4 Designer not implicated
11 Designer could improve
7 Designer may be implicated
15 Designer prosecution supportable
Notes:
1 Total incidents considered in detail 73
2 Total incidents reported 91
3 The balance were clearly not to do with design but must be taken into sample for comparisons
4 Percentage of incidents likely to be the subject of further investigation of lead designer because that
designer has failed to take enough action when such action could have made a major contribution to
accident prevention is 15/91 x 100 = 16% or about 1 in 6 cases.
5 A further 7/91 x 100 = 8% may well be asked to make improvements to their systems and be subject to
criticism for taking inadequate steps at the design stage of a project.
18
Table 5 Summary of designer intervention
Temporary works design
What designers could have done
Very little A bit more Major
contribution
A lot more Critically
significant
0-2 4 6 8 10
Wh
at
desi
gn
er
did
What was
necessary
A 1 0 0 0 0
Something C 0 1 0 0 0
Not enough E 0 3 2 1 1
Not nearly
enough
G 0 0 0 0 1
Nothing J 0 0 0 1 11
Summary by category
Rating & total number Recommended consideration
1 Designer not implicated
6 Designer could improve
1 Designer may be implicated
15 Designer prosecution supportable
Notes:
1 Total incidents considered in detail 73
2 Total incidents reported 91
3 The balance were clearly not to do with design but must be taken into sample for comparisons
4 Percentage of incidents likely to be the subject of further investigation of a temporary works designer
because the designer has failed to take enough action when such action could have made a major
contribution to accident prevention is 15/91 x 100 = 16% or about one in six of all cases reported.
5 A further 1/91 x 100 = 1% may well be asked to make improvements to their systems and be subject to
criticism for taking inadequate steps at the design stage of a project.
19
Table 6 Summary of designer intervention
Supplier or manufacturer
What designers could have done
Very little A bit more Major
contribution
A lot more Critically
significant
0-2 4 6 8 10
Wh
at
desi
gn
er
did
What was
necessary
A 0 0 0 0 0
Something C 0 1 1 0 0
Not enough E 0 1 1 0 0
Not nearly
enough
G 0 2 2 1 0
Nothing J 0 0 1 4 2
Summary by category
Rating & total number Recommended consideration
0 Designer not implicated
6 Designer could improve
2 Designer may be implicated
8 Designer prosecution supportable
Notes:
1 Total incidents considered in detail 73
2 Total incidents reported 91
3 The balance were clearly not to do with design but must be taken into sample for comparisons
4 Percentage of incidents likely to be the subject of further investigation of a manufacturing designer
because the designer has failed to take enough action when such action could have made a major
contribution to accident prevention is 8/91 x 100 = 9% or almost 1 in 10 of all cases reported.
5 A further2/91 x 100 = 2% may well be asked to make improvements to their systems and be subject to
criticism for taking inadequate steps at the design stage of a manufacturing project.
20
7 COMMENTARY
7.1 It must be remembered that the figures relate not to all projects but only to those that
were investigated. This means that the statistics quoted do not indicate that 1 in 6 of
initial designs show designer failure to intervene to prevent accidents but that 1 in 6
of those investigated showed this lack.
7.2 Case law exists that states that consultant engineers and architects should have no
involvement in the construction processes even when the methods chosen by the
constructor threaten safety. There will need to be greater clarity in relation to
legislative changes before designers would be advised to be prescriptive in any great
manner. This attitude of separation of responsibilities clearly pervaded the industry
throughout the period during which the reported incidents took place.
7.3 There were some key themes to the incidents themselves. In particular poor
communication between parties to a contract was often cited as a root cause of an
incident.
7.4 There would seem to be many incidents where a designer had not taken sufficient
notice of existing or adjacent structures nor the likely impact their existence would
have on operator behaviour or ability to access the site with plant and materials.
7.5 In a great many cases the designer had not understood the construction processes nor
taken any account of them in the final design. This was standard practice (See 7.2)
across the industry and remains so to this day for most projects.
7.6 It is to be expected that in an industry where the main duties and liabilities rest with
the principal contractor that the majority of accident reports would reflect this in their
findings. It was for this reason that the incidents that are the responsibility of the
Temporary Works designer or manufacturer have been separated out and dealt with
as a different industry issue.
7.7 Table 2 shows that in almost half of reported cases a designer could have taken steps
to prevent realisation of an accident but failed to take such steps. There is a clear
message here for all of those involved in design, specification and communication of
critical information.
7.8 Table 3 shows much the same as Table 2. It includes multiple responsibility for
incident avoidance but does not give results that are very different from Table 2.
7.9 Table 4 shows the results that are at the heart of this research. It is the number of
main designers who could have, but failed to, intervene to prevent accident
realisation. In approximately 1 in 6 cases the original designer could have done
something to prevent an accident happening but failed to take that opportunity. If this
figure is translated across to the annual accident statistics this means that 1/6x80 = 13
deaths a year could be prevented by designer action. Proportionate savings in injury
and ill health could presumably be made. This clearly is a significant difference by
any measure and well worth setting out a change agenda to achieve. It is particularly
telling when it is remembered that this peer review chose to err in favour of the
designer in the event of doubt and also the fact that the reports did not generally
comment on the original designer activity. Further, maintenance accidents included
did not blame the original designer because it was decided to consider only the
current project. There are, however, several incidents where the original design made
21
maintenance activities difficult and unsafe. It is the view of the author that, because
of the reasons cited above, this figure of 1 in 6 is very conservative.
7.10 Table 5 shows the number of incidents where temporary works designers alone failed
to take the opportunities presented to intervene effectively to prevent accidents. It is
judged likely that this statistic is more accurate since at the time of the reports
temporary works design involvement was more often considered by the investigating
inspector than principal design. In any case there clearly need to be improvements
made by the temporary works community. Common mistakes here included incorrect
assumptions, poor communication and not involving expert designers at the
appropriate time, even when they were available.
7.11 Table 6 shows that a significant number of incidents could have been prevented, but
were not, by better intervention from the construction products design community. In
particular systems scaffolding incorrectly used, systems building units poorly handled
or inadequately seated and access systems with inferior failure modes or emergency
controls were found to be root causes. Generally the product design community did
not give adequate information about the suitability or otherwise of their products for
particular situations.
7.12 Information collection by the Health and Safety Executive (HSE) inspectors rarely
enquired about designer involvement in buildability. This was appropriate to the
prevailing culture and to the civil law of the time. For the effective delivery of closer
understanding of the potential for designer contribution to accident prevention it will
be necessary for this strategy to change and for enquiry methodologies to incorporate
investigation of complex design processes and decision making. It is likely that this
will need a considerable amount of additional research to be carried out as many front
line HSE inspectors do not have the technical competence in design to make
appropriate enquiry without additional guidance and support.
7.13 Designers rarely provided adequate information to contractors about significant
aspects of their design. There are several reasons for this. Civil law argues that where
a contractor takes on a contract to construct a particular design he is making a
statement about his capability to do so. An integral part of this capability is his
competence and presumably his competence to manage the risks to the safety and
health of his workforce. Designers need clearer advice about the relationship between
competence of contractors and their own increased liability if they instruct
contractors, or may be seen so to do, in methods of building. Clearer information is
needed too about the kind of information that would be of use to a contractor. The
industry has evolved a methodology for this process usually called design risk assessment. In fact designers usually retrofit poor quality contractor risk assessments
to their final design. Many do engage in design decisions that take account of
buildability and maintainability but do not recognise these for what they are, which is
a correct response to statutory duty.
7.14 Designers often did not obtain adequate information about existing site conditions or
the fabric and condition of existing structures. Their duty to obtain clearer
information of sufficient quality to be of use in decision making needs clearer
expression in legal and industry standard documents.
7.15 Designers often did not consider the operational aspects of a structure and the
requirement to maintain that structure during user activity. Not to consider such
matters where information is available is a failure to provide proper design services
even without consideration of the safety aspects of those who will be affected. In
particular access to lighting, services and minor fixtures and fittings continues to
22
cause real problems. Designers need to develop creative solutions to those
requirements.
7.16 The Planning Supervisor potential contribution to accident prevention was also
considered. In every case where the Planning Supervisor could have intervened for
good it would only have been possible if that Planning Supervisor was highly
competent in both design and construction processes and also had the character,
authority and opportunity to intervene at the correct time in the project delivery. No
general electronic or paper based system frequently used by Planning Supervisors
would have been able to pick up on the technical or other potential defects
adequately.
7.17 The Site Safety Supervisor could in some instances have intervened, for example
when system scaffold or building units were not being safely used or installed. In
many cases, however, technical knowledge beyond that of the general site safety
supervisor was needed to make adequate intervention.
7.18 Procurement routes and the costs to the design community are seen as a real barrier to
effective delivery of change. Where health and safety is an early contract requirement
designers and constructors alike can deliver high standards. Where designers would
need to spend considerable sums of unrecoverable money to deliver change it is no
surprise that they fail to take that opportunity. This must be a matter for regulators
and government.
7.19 In many instances contractor design incompetence was a major contributor to an
accident. No designer had been involved at all. It may be necessary to put a
requirement on certain types of project for such specialist intervention in some
manner.
7.20 It is the Author’s very strong conclusion that the case for CDM is made by this
analysis and that the design community can do more to reduce the number of deaths
and injuries in construction. While health could not be considered in this analysis it is
the view of the Author that the case for improvement, through designer intervention,
in workforce health is implicit in these findings.
7.21 There are several opportunities for HSE to improve construction safety through
intervention in the design phase of projects. Methodologies for enforcement
intervention need to be developed.
23
24
8 RECOMMENDATIONS
8.1 The design community needs to learn more about modern methods of construction.
How this is achieved is complex and is likely to be a mixture of reward, through
clearly better project delivery or reduced Professional Indemnity costs, and penalty
through enforcement action. To achieve the latter the revised Regulations or
Approved Code of Practice will need to emphasis the requirements on designers in
this respect and the HSE will need to develop enquiry methodologies that probe the
design process.
8.2 The manner in which designers can intervene effectively needs to be more clearly
expressed in industry standard documentation and training. The culture of acceptance
of poor quality design needs to change.
8.3 It could be extremely helpful to refine this research methodology in the light of new
understanding about barriers to change and opportunities for improvement. The best
means of making proper enquiry of designers by enforcers without the appropriate
depth of technical skills needs to be developed. Engagement with IT data
management could begin to generate systems that can provide a rich source of
downstream information that can readily be searched for a variety of purposes.
8.4 The key words need to be further discussed. The purpose of the selection criteria and
the impact on the data management capabilities need further development. Significant
information could be delivered to the industry, including HSE, through a closer
understanding of what initiating factors tend to cause later incidents. For instance
procurement routes, time for planning, nature of the client, size of design house,
competence of design house etc could be useful to future analysis.
8.5 Every opportunity needs to be explored to engage Clients. Where Clients demand
high qualities of health and safety then procure competent and well resourced
suppliers of design and construction, the industry can deliver radical improvement.
8.6 The issue of designer liability with respect to instructions to contractors to build in a
certain manner needs to be further explored. In particular the tension between the
civil and criminal law in this matter needs to be resolved.
8.7 HSE needs to develop better methodologies for inspector investigation and enquiry,
not just following an accident but also when making routine site visits. The
information so gathered can serve several purposes. It can encourage and require
improvement from the design community; it can provide a better source of data for
future incident review such as this; it can provide better data for appropriate
enforcement action.
25
26
APPENDIX 1 CATEGORIES
Key to categories of incident data and other contributory factors detailed in FCG
reports where a design fault may have led to a failure of some description.
Job refers to the location or nature of the work being done, where:
F Steelwork and steel frame erection
O Roofing
G General construction including scaffolding
R Refurbishment
A Falsework, formwork etc
E Excavations and foundations etc
C Cleaning and maintenance
W Window cleaning
D Demolition
Incident rating refers in sequential rows to potential for incident then for actual harm done,
where:
10 Most severe. Major disaster with members of the public affected as well.
8 Multiple fatalities to workers on site
6 Single fatality to worker
4 Serious injury to worker
2 Minor injury
0 Non injury report or event
Note that property damage almost always has potential to cause harm to people, so will be
picked up in the first listing of incident rating.
Could the designer have done more? This refers to an arbitrary view from information
available relating to potential for prevention or reduction in probability by the named
designer.
10 Designer could probably have prevented 8 Designer could have done a lot more to prevent 6 Designer could have reduced likelihood significantly4 Designer had opportunities to reduce likelihood or prevent 2 Designer may have been able to reduce likelihood 0 Designer could not have done anything
Extent of failure to prevent incident. This refers to an arbitrary view of the lost opportunity
by the designer. Notes on duty to have intervened are in the main text.
J Complete failure to prevent or reduce probability
G Failure to make additional efforts using specialist support
E Failure to research issues and apply them
C General lack of design contribution/communication opportunity
A No designer failings
27
Design effort refers to an estimate of the additional effort and consequently resource likely
for designer to include a suggested feature.
H A lot of effort
M Some effort
L Very little effort
Degree of specialist knowledge refers to an estimate of whether a designer could be expected
to know or to have found out from standard sources, where:
0 Should know at basic designer level
1 Generally expected to know to fulfil defined designer role
2 Should easily be able to find out
3 Would need some research to discover this or higher than general
competence 4 Would need specialist expert help
Cost implications refers to an estimate of increased cost to the project
R Reduction in cost L Little additional cost E Some additional cost S Significant additional cost
Interventions
Two additional boxes are included for interest. These relate to external interventions from
individuals outside the direct line of design or construction. They are the Planning Supervisor
(or equivalent such as Client Advisor) and the Site Safety Advisor/Supervisor. Would such
interventions have prevented the incident or potential incident?
0 No difference 1 Unlikely2 Possibly3 Probably 4 Yes
28
APPENDIX 2 ACCIDENT ANALYSIS SHEETS
The following 73 sheets each summarise an incident that was investigated by the Health and
Safety Executive (HSE) Construction Specialist Group and assign it categories as listed in
Appendix 1.
In most cases the HSE reports were made following an incident but in some cases they were
as a result of requests for advice or followed on from the serving of notices. All categories
were included because it was felt that where HSE had been involved at specialist level there
was an implied potential for an incident. Whether the potential was realised or not and the
extent of that realisation is captured in the summary sheets but was not transferred to the final
analysis.
It is certain that industry will be able to argue about the detail of the findings relating to each
incident reported in summary but the author is confident that the results are fair because of the
very close agreement between the original assessor and the reviewer. Only in a very small
number of cases was there a need for final arbitration and significant adjustment.
In many cases additional information would have assisted the analysis process considerably
and assumptions had to be made.
29
Quick Ref 8F Designer Contractor
Description of incident
An agricultural steel portal framed building collapsed during erection. The columns were not secured to
the ground, there was no bracing in the walls and the temporary bracing was of dynamic fibre ropes
mainly in the across the bay direction. The structure was intended to be stabilised when complete by
having the columns cast into concrete perimeter bund or walls.
Keywords from list Collapse/partial collapse; Erecting structures;
Steel/rc frame
Job nature – type of activity F
Incident rating – potential 8
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved N/A N/A N/A Contractor
Could the designer have done
more?
8
Did the designer miss the
opportunity to do more?
G
Design effort L
Designer specialist knowledge 0
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
4
Could site supervision at
construction/ site detail have
made a difference?
3
Remarks
No consideration appears to have been given to temporary instability problems during construction that
could have been within the design remit.
The report notes that the structure was to be built similarly to a previous one and that consequently
there were no separate drawings or calculations in this case. However there is no information in the
report concerning the provisions against collapse in the design for the original structure.
The design effort is unlikely to have been any greater than the loss of time experienced on site due to
that effort not being made.
HSE Peer review: Ref 4467/R33.115 30 Case worksheet HAB 01H
Quick Ref 4J/4G Designers Consultant
Manufact.
Description of incident
A U-shaped [in plan] runway beam was being installed as a new steel framed building was being
constructed. This runway beam was in two halves joined at the centre of the U, i.e. each half was J-
shaped in plan and was spanning 2 bays of the steel frame. The runway beam halves had approx. 1.5m
pedestals bolted to their top flange which were to be the means the beam was to be secured to the
rafters. When one half was being lifted a temporary clamp providing a lifting anchorage for the slings
apparently slipped and possibly dislodged a steel erector who was about to secure it. The erector was
wearing a safety harness but it was not secured.
Keywords from list Fall from height; Erecting structures;
Steel/rc frame
Job nature – type of activity F
Incident rating – potential 8
Incident rating – actual 6
Reference category Architect Consulting
Engineer
TW Designer Other
(Specify)
Designers involved N/A ü N/A Manufacture
Could the designer have done
more?
4 4
Did the designer miss the
opportunity to do more?
J G
Design effort L L
Designer specialist knowledge 2 1
Cost implications L L
Could external intervention at
design stage (PS) have made a
difference?
3 3
Could site supervision at
construction/ site detail have
made a difference?
1 0
Remarks
While the general lack of enforcement of securing the safety harnesses by the contractor was an
important contributing factor. Better design consideration for the need to provide secure lifting
positions and means of anchorage for the safety harnesses was also a factor. There could have been a
problem with the stability of such an unsymmetrical shape while lifting, although the report notes that
when lifted later it hung perfectly. The report does question the suggested slipping of the temporary
anchorage point although the beam was possibly basically unstable because of the two pedestals and its
plan shape.
HSE Peer review: Ref 4467/R33.115 31 Case worksheet HAB02H
Quick Ref N/A Designers N/A
Description of incident
This is the same incident as HAB 03H but includes the further research into manufacturers
capability to intervene. This aspect is incorporated in HAB 02H.
This report looks at the clamps used to provide lifting points for the roof trusses. The manufacturers of
these would have only been happy with them being used where there was no lateral force being
imposed. In this case they should have been used with a lifting beam.
Keywords from list
Job nature – type of activity
Incident rating – potential
Incident rating – actual
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved
Could the designer have done
more?
Did the designer miss the
opportunity to do more?
Design effort
Designer specialist knowledge
Cost implications
Could external intervention at
design stage (PS) have made a
difference?
Could site supervision at
construction/ site detail have
made a difference?
Remarks
There appears to have been a lack of communication between the manufacturer and the user of these
clamps.
The users appear to have been unaware of the limitations on the use of the clamps which could have
been easily dealt with by the use of spreader/lifting beams. This could have been dealt with by
attaching a warning to the clamps.
While the clamps must have been capable of taking some lateral load the manufacturers did not appear
to want to take any responsibility for such use.
HSE Peer review: Ref 4467/R33.115 32 Case worksheet HAB03H
Quick Ref 6G Designers Manufact
Description of incident
A temporary roof edge barrier blew off the edge of a single storey ‘bridge’ link between two other
buildings. No one was injured.
The barrier should have had uprights at no more than 2m centres held down by 30kg sandbag ballast.
The uprights had been placed at 4.3m centres and no ballast had been used.
However the report comments on the likely possibility that the ‘bridge’ was in an exposed position and
subject to funnelling effects so that ballast weighing 50kg would have been required to give a suitable
FOS in this case.
Keywords from list Falls from height off edge; Struck by falling object; Roof work;
Job nature – type of activity O
Incident rating – potential 10
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü possibly ü possibly ü possibly ü Manufact
Could the designer have done
more?
6
Did the designer miss the
opportunity to do more?
G
Design effort M
Designer specialist knowledge 2
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
3
Could site supervision at
construction/ site detail have
made a difference?
4
Remarks
The designers of the temporary barriers had failed to deal with the possibility that they could have been
used in more severe situations than that envisaged. They also failed to appreciate that where a
contractor was expected to obtain other equipment (i.e. sandbag ballast) then there was a real
possibility that these would be omitted.
Part of the answer to the design faults would have been to have provided better advice on the spacing
of the uprights and their ballast weights, ideally permanently attached to the equipment. The failure
could also possibly have been avoided by having designated ballast weights as part of the kit.
Information is only given in the report about system edge protection. It may have been possible for
other design professionals to have intervened to the extent that such system protection was not needed.
This cannot be presumed, however, so is not included in statistics.
HSE Peer review: Ref 4467/R33.115 33 Case worksheet HAB04H
Quick Ref 6J Designers Manufact
Description of incident
A prefabricated building was being dismantled and moved to another location. The building was
constructed from a series of 2.74m pre-clad portal frames spanning 12m and consisting of two portal
frames, which would be bolted to adjacent sections to form the full length of the building. Each section
was handled by being slung from two lifting points on the roof requiring the slinger(s) to walk on the
roof to attach the lifting slings.
Each side of the roof portal had a plastic roof-light that occupied a significant percentage of the total
roof area.
Keywords from list Falls from height; Lifting Machinery; Roof work
Job nature – type of activity O
Incident rating – potential 6
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved Manufacturer
Could the designer have done
more?
6
Did the designer miss the
opportunity to do more?
J
Design effort L
Designer specialist knowledge 2
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
3
Could site supervision at
construction/ site detail have
made a difference?
1
Remarks
While it is possible that the lifting points were at the edge of each section this would still mean that
someone would have to go on the roof to remove the slings or reattach them on relocation along at least
one edge. In addition someone would have to work along the ridge to install or remove the flashings at
this point.
Therefore, as it appears, the building was intended to be easily relocated, it would have been reasonable
to ensure the whole roof was non-fragile and perhaps even build in facilities for edge protection.
The report does not state the nature of the lifting points but it has been assumed that there were 2 on
each edge of the sections.
The building appears to be one that had been designed to facilitate easy relocation. Therefore, the
incidence of someone working over the roof could have been something that frequently occurred. If it
was intended to be readily reassembled then ensuring that this could be simply and safely achieved
should have been part of the designers brief.
HSE Peer review: Ref 4467/R33.115 34 Case worksheet HAB05H
Quick Ref 6G Designers Consultant
Description of incident
A fairly standard sandwich skin roof was being installed that had roof-lights in it. The inner skin was
being installed ahead of the outer skin and a roofer fell through an unsecured section of the inner skin
roof-light.
Keywords from list Falls from height through; Roof work; Commercial building
Job nature – type of activity O
Incident rating – potential 6
Incident rating – actual 4
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved N/A ü N/A N/A
Could the designer have done
more?
6
Did the designer miss the
opportunity to do more?
G
Design effort L
Designer specialist knowledge 2
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
3
Could site supervision at
construction/ site detail have
made a difference?
4
Remarks
The designer could have avoided the separate installation of inner and outer roof skins. In addition The
designer could have ensured (at a cost) that each skin was none fragile and that there was provision at
the eaves for the installation of edge protection.
Finally the designer could have included in the specification for the works a provision for suitable edge
protection.
While the contractor can provide means to install these types of roof the reliability of any such
protective systems would be improved where the designers had planned for safe access or facilitated its
provision.
HSE Peer review: Ref 4467/R33.115 35 Case worksheet HAB 06H
Quick Ref 2E Designers Consultant
Description of incident
A roofer fell through an inner lining sheet. This had only been secured by one fixing at its top edge
instead of the recommended 3 because a curved ridge/crown sheet was still to be installed requiring the
removal of the single fixing.
The roofer had walked over the inner liner as an easy way to get to an electrical junction box.
Keywords from list Falls from height through; Roof work; Commercial building
Job nature – type of activity O
Incident rating – potential 6
Incident rating – actual 2
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved N/A ü N/A N/A
Could the designer have done
more?
2
Did the designer miss the
opportunity to do more?
E
Design effort L
Designer specialist knowledge 2
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
2
Could site supervision at
construction/ site detail have
made a difference?
2
Remarks
The sequence of fixing the roof sheets appears to have made some contribution to the accident although
the greater part was due to poor site management and a ‘mistake’ on the part of the roofer.
A small contribution to this accident also came from the design. If this had allowed different types of
sheets to be fixed independently of others then the accident could have been avoided.
Clearer details or sufficient details from the designer could have helped prevent this accident.
Properly fixed the inner skin of the roof construction was non-fragile. However, the safety of those
installing the roof depended on them keeping off the liner sheets until they were fixed; the planning of
the work should have ensured this.
HSE Peer review: Ref 4467/R33.115 36 Case worksheet HAB 07H
Quick Ref 4J Designers Consultant
Description of incident
An accident occurred when two men fell from a steel roof frame while they were unslinging a pack of
roof sheets with no means of protection.
Keywords from list Falls from height off edge; Structural erection; Steel frame
Job nature – type of activity O
Incident rating – potential 8
Incident rating – actual 8
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved Unlikely ü N/A N/A
Could the designer have done
more?
4
Did the designer miss the
opportunity to do more?
J
Design effort L
Designer specialist knowledge 0
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
3
Could site supervision at
construction/ site detail have
made a difference?
3
Remarks
While the major contributory factor to this accident was a failure of site management and unreasonable
behaviour by the roofers involved, it could have been possible for the designer of the building to have
provided some form of anchorage for those carrying out this necessary and foreseeable operation.
The designer could have encouraged the use of safety lines or nets in designing suitable anchorages for
this type of equipment.
HSE Peer review: Ref 4467/R33.115 37 Case worksheet HAB 08H
Quick Ref 6J Designers Consultant/
Architect
Description of incident
A bricklayer fell through a 1.2m square PVC domed roof-light.
Keywords from list Falls from height through; Refurbishment; Commercial
Job nature – type of activity O
Incident rating – potential 6
Incident rating – actual 4
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü Possibly in ü Possibly in N/A N/A
original only site
investigation
Could the designer have done 10 6
more?
Did the designer miss the
opportunity to do more?
J J
Design effort L L
Designer specialist knowledge 0 0
Cost implications L L
Could external intervention at 3 3
design stage (PS) have made a
difference?
Could site supervision at 3 3
construction/ site detail have
made a difference?
Remarks
The designer contributed to this accident by specifying the use of a fragile roofing element.
The contractor should have been aware of this and could have taken various types of precautions. In
addition it is possible that the bricklayer was particularly careless or deliberately stood on the roof-
light.
Habilis assessment assumes this is refurbishment so not due to architect or engineer as original
designer. (Assume err in favour of designer). As a result only engineer as refurbishment designer taken
to summary at top of page. Note that this could have been an architect rather than an engineer.
HSE Peer review: Ref 4467/R33.115 38 Case worksheet HAB 09H
Quick Ref 6J Designers Architect
Description of incident
A new church was under construction having steeply pitched roofs to a maximum height of 13m. No
provision had been made to safeguard those working on the roof and a PN was issued.
Keywords from list Falls from height off edge; Erecting structure; Access
Job nature – type of activity O
Incident rating – potential 6
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü Possibly N/A N/A
Could the designer have done
more?
6
Did the designer miss the
opportunity to do more?
J
Design effort M
Designer specialist knowledge 2
Cost implications E
Could external intervention at
design stage (PS) have made a
difference?
3
Could site supervision at
construction/ site detail have
made a difference?
3
Remarks
The designer could have included features in his design to support a working platform and/or to
provide anchorages for safety lines.
The provision of anchors to support a safety line or similar facility could have been done by the
designer working alone. However the installation of means to support working platforms would have to
be done in consultation with the contractor.
HSE Peer review: Ref 4467/R33.115 39 Case worksheet HA 10H
Quick Ref 6J Designers Architect
Description of incident
A roofer helping to build a new cattle shed adjacent to an older, and 1m lower, cattle shed. The older
building was clad with single skin corrugated asbestos sheets while similar new sheets were being
installed on the new shed.
The roofer stepped down from the higher new roof and fell through the older sheets. The report is not
clear whether there was a temporary barrier at the point where the roofer fell.
Keywords from list Falls from height through; Roof work
Job nature – type of activity O
Incident rating – potential 6
Incident rating – actual 4
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü Possibly ü Possibly N/A N/A
Could the designer have done
more?
6
Did the designer miss the
opportunity to do more?
J
Design effort L
Designer specialist knowledge 1
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
2
Could site supervision at
construction/ site detail have
made a difference?
2
Remarks
While control of this risk lay chiefly with the contractor, the designer should have flagged up the real
risks of someone stepping or falling down onto the old roof. This could have encouraged the
construction of effective protective measures.
Control of this risk lay chiefly with the contractor. However, designing a building adjoining to a lower
one should have flagged up the risks of someone stepping or falling down onto the old roof. It is
possible that increased production resulting from a proper edge protection system could have been
greater than the original design effort.
This was a cattle shed either an architect or an engineer could have been retained. Architect assumed
here after discussion. Initial site inspection would have indicated access difficulties that required
additional attachments or similar to be included.
HSE Peer review: Ref 4467/R33.115 40 Case worksheet HAB 11H
Quick Ref 8E Designers Architect
Description of incident
An old warehouse was being converted into flats. The roof was completely stripped leaving the old
roof trusses. These were of a substantial construction, spanning 13m, standing 5.5m high and weighing
an estimated 1.3 tonnes. Some longitudinal 100mm x 50mm timbers had been nailed between the
trusses at approx. 1/3 their height using 2 – 100mm nails at each truss.
The masonry against the ends of the trusses was being removed to allow checks to be made on the
condition of the timber at the time when a moderate to fresh gale was blowing and 8 trusses fell over.
Keywords from list Partial collapse; Refurbishment
Job nature – type of activity O/R
Incident rating – potential 8
Incident rating – actual 4
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü N/A N/A N/A
Could the designer have done
more?
8
Did the designer miss the
opportunity to do more?
E
Design effort L
Designer specialist knowledge O
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
3
Could site supervision at
construction/ site detail have
made a difference?
1
Remarks
The designer would know that the roof was to be stripped and that effective temporary bracing would
be required. Therefore, he should have anticipated that the method of stripping the roof would have
left, at some stage, the old trusses standing without covering and perhaps the bracing. He should have
provided details of how the trusses should have been stabilised, including the strength of the fixings.
Even if the collapse had been avoided, it is probable that the increase in production would have paid for
the slightly additional design effort.
HSE Peer review: Ref 4467/R33.115 41 Case worksheet HAB 12H
Quick Ref 10J Designers Architect
Description of incident
A cradle runway was installed on the roof of a hospital for the use of window cleaners. The roof
however had only a very low parapet that would not give any protection to anyone using or maintaining
the cradles.
In addition the cradles were intended to be worked by one man but could only be accessed by this
person from the roof. This meant that this person would have to step over the parapet down into the
cradle.
There was a risk that someone could fall off the roof.
Keywords from list Falls from height off edge; Maintenance; Cradles
Job nature – type of activity O
Incident rating – potential 6
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü
Could the designer have done
more?
10
Did the designer miss the
opportunity to do more?
J
Design effort M
Designer specialist knowledge 3
Cost implications E
Could external intervention at
design stage (PS) have made a
difference?
3
Could site supervision at
construction/ site detail have
made a difference?
1
Remarks
The cradles could have been designed so that they could be landed on the roof of the hospital to allow
the window cleaner to gain access and then be driven from inside the cradle over the parapet.
A suitable system of protecting persons working on or around the cradle tracks would need to be
provided.
This is a case where inadequate design resulted not only in a risk of serious falling accidents but also
resulted in increased operational costs.
HSE Peer review: Ref 4467/R33.115 42 Case worksheet HAB 13H
Quick Ref 8E/4E Designers TW/A
Description of incident
A proprietary scaffold had been erected completely around the site of a new building, which was to be
built from prefabricated timber sections lifted over the scaffold into position, followed by a
considerable amount of work for follow-up trades to complete the façade.
There were problems with the scaffolding concerning: flexing under load, decking members springing
free, unauthorised removal of members and difficulties in maintaining a ‘safe’ gap between the inner
edge of the scaffold and the new building.
Keywords from list Scaffold; Access
Job nature – type of activity G
Incident rating – potential 8
Incident rating – actual 4
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü N/A ü N/A
Could the designer have done
more?
4 8
Did the designer miss the
opportunity to do more?
E E
Design effort M M
Designer specialist knowledge 1 3
Cost implications L E
Could external intervention at
design stage (PS) have made a
difference?
2 0
Could site supervision at
construction/ site detail have
made a difference?
2 3
Remarks
With a building design such as this there is an even closer relationship between the building panels and
the façade access system if a safe, efficient and effective construction method is to be devised.
It was therefore important for the panel design to be linked to the design of the access system being
fully integrated by the designer.
It is possible that this type of scaffold was not intended for moderate or heavy duties and therefore it
had been a poor choice. However the manufacturers/suppliers claims for this equipment would tend to
suggest that it could give an economic performance in such applications. Therefore some investigation
and consideration would be needed to ensure the job operated properly.
Had this been done then the economic benefit would have almost certainly exceeded the additional
design effort.
HSE Peer review: Ref 4467/R33.115 43 Case worksheet HAB 14H
Quick Ref 8J(A)
10E(C)
10J(M) Designers Various
Description of incident
Two 30m long, 44 tonne ‘Y7’ bridge beams overturned shortly after being placed.
Their lifting arrangement, accepted by the manufacturer, was via end diaphragm holes, which were
approx. 200mm lower than the beam centre of gravity. This and the lack of adjustment in the lifting
arrangements probably resulted in the beam being set unevenly on its bearings.
The temporary propping of the beams was ad-hoc and inadequate and could not stop the beams rolling
over.
Keywords from list Erection of structures; Temporary Works; Material handling
Job nature – type of activity G
Incident rating – potential 8
Incident rating – actual 6
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved N/A ü ü Manufacturer
(Consulted)
Could the designer have done
more?
8 10 10
Did the designer miss the
opportunity to do more?
J E J
Design effort L M L
Designer specialist knowledge 1 1 1
Cost implications L L L
Could external intervention at
design stage (PS) have made a
difference?
3 1 N/A
Could site supervision at
construction/ site detail have
made a difference?
1 1 N/A
Remarks
The satisfactory, and safe, handling of such large and ungainly units, particularly when set on sliding
bearings, depends very much on the on the proper design followed by proper preparation & planning,
on site, of all associated temporary works.
There was no reason why the beams could not have been designed with proper lifting hooks so that the
centre of gravity was below the lifting sling making the handling of the beams easier and reducing the
risk of rotation. In addition, the temporary propping arrangement was inadequate and should have been
properly designed.
The losses in this case for not doing this almost certainly far outweighed the effort of carrying such a
proper design. Even if the beams had not failed the time lost in trying to position the beams and trying
to sort out some form of temporary stabilisation would possibly still have been greater than the time
required to prepare a proper design.
HSE Peer review: Ref 4467/R33.115 44 Case worksheet HAB 15H
Quick Ref 6J(C)
8J(M) Designers C & M
Description of incident
A workman was levering a pre-cast floor slab into position while standing on the top flange of a steel
support beam. The bar he was using slipped and he fell from the exposed edge suffering injuries.
Keywords from list Fall from height from; Erection of structures; Pre-cast units
Job nature – type of activity G
Incident rating – potential 6
Incident rating – actual 4
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved N/A ü N/A Manufacturer
Could the designer have done
more?
6 8
Did the designer miss the
opportunity to do more?
J J
Design effort L L
Designer specialist knowledge 1 1
Cost implications L L
Could external intervention at
design stage (PS) have made a
difference?
2 2
Could site supervision at
construction/ site detail have
made a difference?
3 3
Remarks
Designers who specify pc units should be aware that they often require levering into position on site.
Therefore, they should specify for the manufacturer to design in anchorage points for lanyards.
The same applies to the manufacturer. If this was a standard design issue, it would be done as a matter
of course.
The additional handling described is a feature of the product and failure to build in suitable facilities to
support this could be argued that the manufacturer’s products are not fully complete. It is unlikely that
such additions to the slabs would be very expensive and given the large number of units manufactured
even small production gains made during erection could make these cost effective.
HSE Peer review: Ref 4467/R33.115 45 Case worksheet HAB 16H
Quick Ref 4E(A/C)
4G(M) Designers Various
Description of incident
A worker stepped or fell off a perimeter scaffold onto a pre-cast beam and block floor and either fell
through a hole in the floor or his impact broke out the in-fill blocks so forming a hole through which he
fell.
The in-fill blocks had poor/minimal seatings in some cases due to slight displacement of the beams and
those that fell had virtually no seating at all. In addition the blocks had not been grouted in and were
incapable of carrying much load.
Keywords from list Fall from height through;
Job nature – type of activity R
Incident rating – potential 8
Incident rating – actual 4
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü or C ü or A Manufacturer
Could the designer have done
more?
4 4 4
Did the designer miss the
opportunity to do more?
E E G
Design effort L L M
Designer specialist knowledge 2 2 3
Cost implications L L L
Could external intervention at
design stage (PS) have made a
difference?
2 2 N/A
Could site supervision at
construction/ site detail have
made a difference?
1 1 N/A
Remarks
The main responsibility for this accident lies with the contractor: he failed to ensure that the pre-cast
beams were accurately positioned and that the floors were grouted immediately they were laid.
However, as the creator of the hazard, the designer should have informed the Contractor about the
residual hazard. Not doing this represented a design failure.
The manufacturer has designed a system with an obvious safety deficiency: the risk highlighted by this
accident would also exist for the person grouting up.
It might have been possible to incorporate or provide a gauge to ensure that the pre-cast beams were
correctly placed.
It is possible that the provision of a suitable gauge would be cost effective as it could provide a limited
production benefit.
HSE Peer review: Ref 4467/R33.115 46 Case worksheet HAB 17H
Quick Ref 6E(C)
10J(T) Designers Various
Description of incident
A sloping rc floor was being cast on profiled metal deck sheeting laid to varying slopes. One area of
decking failed and a worker fell through the hole.
The framework supporting the decking was at varying slopes therefore, the decking could not always
sit properly on its support. In addition, while the concrete being placed did, in some cases,
significantly overload the decking.
A consulting engineer had had involvement on the site but does not appear to have had complete
control over the works. A sub-contractor who may not have understood the structural significance of
the decking’s limitations carried out the actual choice and installation of the decking in this area.
Keywords from list Falls from height through; Pre-cast units
Job nature – type of activity A
Incident rating – potential 8
Incident rating – actual 4
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved N/A ü ü ü See note
Could the designer have done
more?
6 10
Did the designer miss the
opportunity to do more?
E J
Design effort L M
Designer specialist knowledge 3 2
Cost implications E E
Could external intervention at
design stage (PS) have made a
difference?
2 3
Could site supervision at
construction/ site detail have
made a difference?
1 1
Remarks
The limitations in the decking could have been dealt with in a variety of ways either by themselves or
in combinations. These include using stronger decking, using appropriate wedges to give adequate
seating, using temporary supports to back prop the floor until the in-situ concrete had gained sufficient
strength, placing additional reinforcement in the thick in-situ concrete.
The selection of the most appropriate system should have been done by a suitably competent designer
In this case the designer was the sub-contractor who was not competent to appreciate the structural
significance of what he was doing.
The cost of the failure was clearly far greater than the cost of a competent person carrying out the
necessary calculations.
HSE Peer review: Ref 4467/R33.115 47 Case worksheet HAB 18H
Quick Ref 10J(A)
10J(Con)
Designers Various
Description of incident
A person was injured when a section of pc flooring together with supporting lintel and block work
collapsed.
The flooring was being installed and was not grouted in. It was resting at one end on a steel lintel
spanning onto the block work reveals at the side of a window opening. The floor was heavily loaded
with blocks in the area of the failure.
The lintel was grossly under-designed and possibly could not have supported its service load. The
block work reveal was also severely overloaded. No calculations had been prepared for this work.
Keywords from list Collapse of structure; Pre-cast flooring
Job nature – type of activity G
Incident rating – potential 8
Incident rating – actual 4
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü N/A N/A ü Contractor
modification
Could the designer have done
more?
10 10
Did the designer miss the
opportunity to do more?
J J
Design effort M M
Designer specialist knowledge 2 2
Cost implications R R
Could external intervention at
design stage (PS) have made a
difference?
2 2
Could site supervision at
construction/ site detail have
made a difference?
1 1
Remarks
Appropriate calculations by a competent person should have easily prevented this incident.
While the pre-cast floor used was a substitute for in-situ concrete on permanent shuttering, this would
not have solved the overloading problem although could have resulted in a greater distribution of the
loads.
The accident could have been avoided by normal (pre CDM) procedures a safety appraisal should have
indicated that suitable calculations had not been carried out.
HSE Peer review: Ref 4467/R33.115 48 Case worksheet HAB 19H
Quick Ref 4E Designers Consultant
Description of incident
A design change required a section of a suspended concrete floor to be omitted. The method of work
for the installation of ceiling ducts to the upper floor required the use of a mobile access tower and the
gap in the floor prevented this tower from being moved along the line of the ducts.
Spandecks were laid across the void and a tower was placed on these. Possibly due to either a worker
climbing down the outside of the tower or because the tower was being pushed along the Spandeck and
perhaps pushed this off its seating, the tower and one Spandeck fell into the void.
Keywords from list Falls from height through; Pre-cast flooring; Access
Job nature – type of activity G
Incident rating – potential 6
Incident rating – actual 4
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved C
Could the designer have done
more?
4
Did the designer miss the
opportunity to do more?
E
Design effort L
Designer specialist knowledge 2
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
2
Could site supervision at
construction/ site detail have
made a difference?
2
Remarks
The designer had only a small part in this accident but the incident does illustrate the possible
consequences of design changes, especially structural ones.
When the change was made the designer should have checked, through the planning supervisor, its
impact on the method statements for the work surrounding the new hole and ensured these were revised
as necessary.
The consequences, both from an accident prevention and a financial point of view, of not following
through on the consequences of design changes can be very significant and far outweigh the minimal
effort usually required to check these out.
HSE Peer review: Ref 4467/R33.115 49 Case worksheet HAB 20H
Quick Ref 6E Designers Architect
Description of incident
A putlog scaffold was being used to build a cavity wall dividing two roof spaces. The scaffold was up
to two lifts high and supported only on one skin of block work. The other skin was to be built
separately. Possible wind loading caused the block wall and scaffold to collapse.
Keywords from list Collapse of structure; Scaffold
Job nature – type of activity G
Incident rating – potential 8
Incident rating – actual 4
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü
Could the designer have done
more?
6
Did the designer miss the
opportunity to do more?
E
Design effort L
Designer specialist knowledge 0
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
1
Could site supervision at
construction/ site detail have
made a difference?
2
Remarks
Knowledge of the vulnerability of thin block walls to a variety of loads is known equally by contractors
and designers. However as the designer created the hazard: lightweight walls, it should have been his
responsibility to emphasise the restrictions on progressing one leaf ahead of the other. Was the wall
checked for wind loads?
Following the same argument by expressly giving such instructions would be a normal means of
ensuring the quality and therefore minimising the cost of the project.
HSE Peer review: Ref 4467/R33.115 50 Case worksheet HAB 21H
Quick Ref 8J Designers Manuf.
Description of incident
A roller shutter door previously fitted into a building collapsed killing a person. It was found that the
door had been secured by Rawlbolts of the correct size and number. However these had been placed
into oversize holes, some into mortar joints only and others penetrating into the voids caused by laying
bricks with frogs upside down.
Keywords from list Collapse onto; Building products;
Job nature – type of activity C
Incident rating – potential 6
Incident rating – actual 6
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved Manufacturer
Could the designer have done
more?
8
Did the designer miss the
opportunity to do more?
J
Design effort L
Designer specialist knowledge 1
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
0
Could site supervision at
construction/ site detail have
made a difference?
0
Remarks
The construction products were too heavy for the fixing available with no means of external inspection.While the supplier of the doors had specified suitable bolts no details appear to have been provided ontheir installation. Had this been done then possibly the accident would not have occurred. While the size of the bolts is important this cannot be separated from a clear specification of the natureof the anchorage holes and materials. Without the two sets of information a reliable fixing cannot beassured. This means that such a failure could have both economic and safety consequences.
HSE Peer review: Ref 4467/R33.115 51 Case worksheet HAB 22H
Quick Ref 6J Designers Architect
Description of incident
A 3-storey building was being rendered off an external scaffold erected all around the building. There
were no ties between the scaffold and the building because of the need to give clear areas for the
rendering to proceed. Therefore, the scaffold was generally stabilised by the end returns. The scaffold
on one elevation was removed and a section along the return wall where a gin wheel was being used,
collapsed.
Keywords from list Scaffold collapse
Job nature – type of activity G
Incident rating – potential 8
Incident rating – actual 4
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü
Could the designer have done
more?
6
Did the designer miss the
opportunity to do more?
J
Design effort L
Designer specialist knowledge 1
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
2
Could site supervision at
construction/ site detail have
made a difference?
2
Remarks
The designer specified the render and it should have been clear that the scaffold could not be tied to the
building or that ties would have to be moved and not replaced. Therefore, the designer should have
provided suitable anchorage points in the façade.
While it would not be normal for the designer to get involved with scaffold design and use, in this case
the scaffold could have seriously affected work that had been specified. It was therefore in the client’s
interest for the scaffold to be designed and arranged so as not to impair the harling work.
HSE Peer review: Ref 4467/R33.115 52 Case worksheet HAB 23H
Quick Ref 8G Designers Manuf.
Description of incident
Three men were preparing to install ducting working from suspended ceiling panels. The panels failed;
2 men fell 5.9m. The ceiling sat in 33x33x1.8 aluminium angles. In some cases only two 3mm rivets
secured this angle to the wall section. It was found that some of the rivets had been badly placed, were
subject to both bending and shear and had in fact sheared or were missing. The rivets connecting the
suspended panels to the angles had failed in tension pulling out of the panel. The suspended panels
were supported by an inverted top hat section hung by M12 threaded bars from the concrete roof
structure.
No signs had been posted about the safe working conditions for the panels and the panel manufacturer
supplied no fixing instructions on the basis that this was something the installer should deal with.
Keywords from list Collapse of access platform;
Job nature – type of activity R
Incident rating – potential 8
Incident rating – actual 4
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved Manufacturer
Could the designer have done
more?
8
Did the designer miss the
opportunity to do more?
G
Design effort L
Designer specialist knowledge 2
Cost implications R
Could external intervention at
design stage (PS) have made a
difference?
2
Could site supervision at
construction/ site detail have
made a difference?
0
Remarks
There were three major failings: (1) The manufacturers had not calculated the sorts of loads that could
be imposed on the fixings that could be used to support their product; (2) They had not provided clear
information to the installers or the owners/users of the product on the design and load limitations
relevant to it; and (3) They failed to provide typical installation details. As a consequence no one, the
manufacturers, installers or owners/users of the product, was aware of how safe the product was when
used for access purposes.
From the report it appears that their was a variety of fixing arrangements, some quite nominal, which is
hardly surprising given the lack of consideration given by the manufacturer.
HSE Peer review: Ref 4467/R33.115 53 Case worksheet HAB 24H
Quick Ref 4E Designers TW
Description of incident
A temporary platform that had been slung under a motorway bridge was being lowered when it broke
in two and a scaffolder who was on it fell. The platform was found to have been overloaded with
access boards and tubes, was being carried at its extreme ends instead of 2m in as required by the
design, and had been manufactured from some materials that were defective. The decision to move the
suspension points out was taken by a site foreman, without consulting the designer. Investigations
showed that the platform was failed for three reasons: (a) it was overloaded, (b) it was slung
incorrectly, which exacerbated (a), and (c) there was a defective [weak] component in the failed joints.
Keywords from list Access; Cradle collapse
Job nature – type of activity G
Incident rating – potential 8
Incident rating – actual 6
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved N/A N/A ü But not
involved
Could the designer have done
more?
4
Did the designer miss the
opportunity to do more?
E
Design effort L
Designer specialist knowledge 1
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
0
Could site supervision at
construction/ site detail have
made a difference?
2
Remarks
The temporary platform would possibly not have failed if any of the three weaknesses had not been
present i.e. if it had been properly slung, not been overloaded and not had defective materials in its
manufacture. However the possibilities of both overloading and slinging at excessive spans are typical
forms of misuse for this type of equipment therefore requiring increased factors of safety.
Perhaps the designer could have anticipated misuses (a) and (b).
There is a need to ensure that all components in a modular temporary access system are manufactured
to a high standard as there can be no guarantee that weak items won’t be used in highly stressed
positions.
HSE Peer review: Ref 4467/R33.115 54 Case worksheet HAB 25H
Quick Ref 4E Designers Consultant
Description of incident
A temporary work platform had been created by placing 3 floor boards across the stub ends of timber
joists which had been left in place after the joists themselves had been removed. Although the stub
ends of the joists were built into the wall this was only one brick wide and there was no brickwork
above the joist ends, which could have held them down. Three men stood on this platform to move a
staging towards a mobile access platform and the stub ends of the joists broke free.
Keywords from list Access collapse
Job nature – type of activity R
Incident rating – potential 8
Incident rating – actual 6
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü
Could the designer have done
more?
4
Did the designer miss the
opportunity to do more?
E
Design effort L
Designer specialist knowledge 2
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
2
Could site supervision at
construction/ site detail have
made a difference?
2
Remarks
In refurbishment work unexpected situations occur. While it is largely up to the site staff to deal with
these, designers can assist by encouraging the contractor to adopt a safe methodical approach to the
work.
However it appears that there was a major site supervision failing through first allowing the stub ends
of the joists to remain in place once the rest of the joists had been removed and secondly in not
preventing the workers using such a hazardous form of access.
HSE Peer review: Ref 4467/R33.115 55 Case worksheet HAB 26H
Quick Ref 10J Designers TW
Description of incident
Work in converting an old chapel built within a row of terraced houses required that the cellar floor
should be lowered. This was being done without the use of any shoring and a party wall collapsed.
Keywords from list Collapse of structure; Shoring
Job nature – type of activity R
Incident rating – potential 8
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved N/A ü ü N/A
Could the designer have done
more?
TW aspects of
design are key
10
Did the designer miss the
opportunity to do more?
J
Design effort M
Designer specialist knowledge 2
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
3
Could site supervision at
construction/ site detail have
made a difference?
3
Remarks
Underpinning work and excavation work adjacent to walls should be carried out to a suitable design
that will ensure that the structure will always remain stable. Such a design should have been provided
in this case.
Underpinning and similar work is a highly skilled job and requires that those involved in it, particularly
those managing and supervising it, are experienced, competent and reliable.
HSE Peer review: Ref 4467/R33.115 56 Case worksheet HAB 27H
Quick Ref 10J(T)
1C(A) Designers
Description of incident
While a roll of lead was being hauled to a roof by means of a gin wheel attached to a 9m high scaffold,
the scaffold partly overturned. The scaffold was tied to the building partly by rakers and partly by
reveal ties. However the number and quality of both these types of support was less than that required
by the code of practice. In addition the joints in the scaffold tubes were not staggered making the
scaffold less able to resist rotating.
Keywords from list Scaffold collapse; Material handling
Job nature – type of activity R
Incident rating – potential 8
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü ü
Could the designer have done
more?
2 10
Did the designer miss the
opportunity to do more?
C J
Design effort L L
Designer specialist knowledge 0 0
Cost implications L L
Could external intervention at
design stage (PS) have made a
difference?
0 2
Could site supervision at
construction/ site detail have
made a difference?
2 2
Remarks
The designer could have detailed secure positions to provide tie anchorage points, especially as the
design required to installation of new building materials which would have to be hoisted to the roof of
the building. Alternatively other means could have been specified for lifting materials etc.
The lifting of new materials to roof level etc, was part of the design which required that effective lateral
supports would be required if the access scaffold was to be used to mount lifting equipment.
HSE Peer review: Ref 4467/R33.115 57 Case worksheet HAB 28H
Quick Ref 10J Designers Scaffolder
Description of incident
The taller of two adjacent adjoining buildings needed its exposed gable re-pointing. A narrow access
scaffold was erected on the pavement as the local authority would not allow further obstruction. In
addition, the owners refused to allow the scaffold to be tied to the building. When ordinary ladder was
supported on the working platform on the scaffold and laid up the lower roof i.e. it was not hooked
over the ridge the reaction from the ladder pushed the scaffold over.
Keywords from list Access constraints; Scaffold collapse
Job nature – type of activity R
Incident rating – potential 8
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved Scaffolder
Could the designer have done
more?
10
Did the designer miss the
opportunity to do more?
J
Design effort L
Designer specialist knowledge 1
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
0
Could site supervision at
construction/ site detail have
made a difference?
2
Remarks
Scaffold design has not generally been considered to be part of Reg 13 except where it is temporary
works or very substantial but it is a serious matter in most cases.
Both the local authority and the owners had taken some responsibility for the design of the scaffold by
imposing conditions on its layout.
HSE Peer review: Ref 4467/R33.115 58 Case worksheet HAB 29H
Quick Ref 10J Designers Architect
TW
Description of incident
A flat roofed section of corridor was being altered. This required the roof to be lifted higher and the
sidewalls, originally of timber framed glass panels, to be replaced by block-work. The original
sidewalls had been fixed to the ground cill and “portalised” with the roof joists, to resist rotational
forces. There was nothing in the new design to provide lateral restraint. In addition, the flat roof itself
was being used as a working platform. The structure collapsed as the second sidewall was being
replaced.
Keywords from list Structural collapse
Job nature – type of activity R
Incident rating – potential 10
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü ü
Could the designer have done
more?
10 10
Did the designer miss the
opportunity to do more?
J J
Design effort L L
Designer specialist knowledge 0 0
Cost implications E E
Could external intervention at
design stage (PS) have made a
difference?
2 2
Could site supervision at
construction/ site detail have
made a difference?
2 2
Remarks
The new design did not make any allowances for lateral restraint either during the construction phase
or after completion.
While the method of construction made no provision for supporting any lateral forces, which would be
created when working on top of the roof, this only compounded a principle design failure. Therefore
even if the builders had used bracing during the refurbishment, the building could still remain unstable
to some degree after completion.
HSE Peer review: Ref 4467/R33.115 59 Case worksheet HAB 30H
Quick Ref 10J Designers Contractor
Description of incident
A prefabricated temporary roof was being used which had plastic sheets fixed to aluminium trusses
supported at each end by a scaffold. This system would be unlikely to fail under wind loading as the
plastic panels would rip open before the loads became so high. However while the suppliers of the
equipment recommend that each installation is designed, this was not the case with this structure.
Keywords from list Temporary structure; Collapse
Job nature – type of activity R
Incident rating – potential 8
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved N/A N/A N/A Contractor
scaffold
design
Could the designer have done
more?
10
Did the designer miss the
opportunity to do more?
J
Design effort M
Designer specialist knowledge 2
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
0
Could site supervision at
construction/ site detail have
made a difference?
1
Remarks
A full design of each installation is recommended by the manufacturer/supplier and while the structure
has a tendency to fail to safety, not carrying out a design check could open the way for problems to
occur.
Although not mentioned in the report the design of the temporary roof requires the erectors to climb
along the roof trusses fixing the plastic sheets. This in itself is a design weakness.
Contractor should have designed protective scaffold.
HSE Peer review: Ref 4467/R33.115 60 Case worksheet HAB 31H
Quick Ref 10J Designers TW
Description of incident
A wide, up to 2m, scaffold was erected around a church tower for maintenance and refurbishment. The
scaffold was about 24m high and erected around each of the four 12m wide faces of the tower. The
scaffold probably had some original faults that were not particularly serious but had then been altered
by the contractors carrying out the work as well as increasing the loading on the scaffold. The scaffold
was not tied at any point to the tower.
Keywords from list Scaffold; Alterations; Refurbishment
Job nature – type of activity R
Incident rating – potential 8
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü
Could the designer have done
more?
10
Did the designer miss the
opportunity to do more?
J
Design effort M
Designer specialist knowledge 3
Cost implications E
Could external intervention at
design stage (PS) have made a
difference?
3
Could site supervision at
construction/ site detail have
made a difference?
2
Remarks
Scaffolds of this size and configuration, particularly because of being unusually wide and not being
tied back to the tower, need to be designed and carefully detailed. Such a design should carefully
consider both the self-weight of the scaffold and the maximum imposed loads to ensure that the
buckling strength was adequate.
The unusual width of the scaffold was something that could have reduced the mutual support provided
by each of the standards, increasing their slenderness ratio. The scaffold design therefore needed to be
checked by an experienced scaffold designer. This is something that the client or architect should have
realised.
HSE Peer review: Ref 4467/R33.115 61 Case worksheet HAB 32H
Quick Ref 10J(A/C) Designers Consultant
Description of incident
Steel beams 305mm deep, to support to roof trusses, were positioned on the top of slender brick
columns [215x185] approx. 2.17m high, but were not fixed in place. There were gaps of varying depths
between the top of the steel beams and the underside of the trusses. The design intention was for the
beams to be trapped under the roof trusses by their increased deflection from the increased deadweight
of the roof as it was completed. In one position the beam had apparently been dislodged and fallen onto
a person.
Keywords from list Collapse of structure; Erection; Steelwork; Material handling
Job nature – type of activity G
Incident rating – potential 6
Incident rating – actual 4
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü If used
rather than
Engineer
ü
Could the designer have done
more?
10
Did the designer miss the
opportunity to do more?
J
Design effort L
Designer specialist knowledge 2
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
3
Could site supervision at
construction/ site detail have
made a difference?
2
Remarks
The seating of the beams was inadequate, because the design intention ignored the reality of the
construction process. Consequently, the beams were vulnerable to movement in a variety of scenarios.
Had the beams been designed so that they were securely held in place in their temporary condition then
the accident would not have occurred. This could have been achieved by either bolting them onto the
brick columns or by using a temporary fixing to the trusses, which would still allow them to deflect.
The space between the beam and the truss varied to an extent that it is possible that some of the trusses
may not have fully settled onto the beam.
HSE Peer review: Ref 4467/R33.115 62 Case worksheet HAB 33H
Quick Ref 6E Designers TW
Description of incident
A slung scaffold was to be hung over a parapet of a tall office building, surrounded by public rights of
way. The scaffold was to be used to remove defective tiles at the top of the building and had 3 working
platforms. While the design of the scaffold was acceptable, measures to protect the public below were
required.
Keywords from list Falls of objects from height; Scaffolding
Job nature – type of activity R
Incident rating – potential 10
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü
Could the designer have done
more?
6
Did the designer miss the
opportunity to do more?
E
Design effort L
Designer specialist knowledge 0
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
3
Could site supervision at
construction/ site detail have
made a difference?
3
Remarks
The design for the work should have included all its aspects including full details for protecting the
public.
While to measures for protecting the public may have been picked up by the contractor when the work
commenced not including them in the design could have resulted in omissions or unsatisfactory ad hoc
solutions being used
HSE Peer review: Ref 4467/R33.115 63 Case worksheet HAB 34H
Quick Ref 8G Designers Contractor
Description of incident
A Victorian house was being refurbished. Concerns were raised about some temporary & some
permanent structural provisions being made in the course of these works. These arrangements appear to
have been organised without any comprehensive design work being carried out.
Keywords from list Temporary Works; Structural collapse
Job nature – type of activity R
Incident rating – potential 8
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved Contractor No
formal design
Could the designer have done
more?
8
Did the designer miss the
opportunity to do more?
G
Design effort L
Designer specialist knowledge 1
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
4
Could site supervision at
construction/ site detail have
made a difference?
3
Remarks
The report indicates that the works had not been designed properly. Proper detailing of all permanent
structural features should be carried out. Suitable planning of temporary structural requirements should
be undertaken relative to the complexity and significance of the loads to be supported.
The description of the conditions found strongly suggests that things were getting out of hand and there
was little or no effective management/supervision.
These problems should have been obvious to the designer of the project on site visits prompting
remedial works or a change of contractor.
HSE Peer review: Ref 4467/R33.115 64 Case worksheet HAB 35H
Quick Ref 10J Designers TW
Description of incident
A badly laminated and friable rock face was being stabilised by casting up to 2m thick concrete against
it. The formwork being used was held in place by rock anchors drilled into the friable rock at 0.7m
centres. While casting the concrete the pressures created by vibrating and placing it caused the anchors
to fail pushing over the formwork and adjoining access scaffolding.
No attempt seems to have been made to assess the pull-out strengths of the anchors.
Keywords from list Rock face; Formwork;
Job nature – type of activity A
Incident rating – potential 8
Incident rating – actual 4
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü
Could the designer have done
more?
10
Did the designer miss the
opportunity to do more?
J
Design effort M
Designer specialist knowledge 1
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
2
Could site supervision at
construction/ site detail have
made a difference?
1
Remarks
Designers are aware that concrete needs to be retained until it has hardened. Tests should have been
carried out to check whether the pull-out strengths on the anchors was adequate. Calculations should
have been made by a competent person to assess the pressures that could be exerted by the concrete
and controls put in place to ensure that such pressures did not become excessive.
In this situation the concrete pressure could be affected by the moisture content, the rate of pouring, the
amount of vibration used and any surcharges from men or materials. All these are features that could
have required control in the design.
The nature of the rock surfaces suggests that frequent testing of the rock anchors would be required as
the pull-out strengths could be significantly affected depending on the strata the anchors were being
drilled into. Again this is a feature that the design should have dealt with.
HSE Peer review: Ref 4467/R33.115 65 Case worksheet HAB 36H
Quick Ref 4J Designers Subcontr
Description of incident
Following a commercial dispute a sub-contractor started to remove the shoring to a building’s façade.
This could have become unstable if much of the support offered by the shoring had not been available.
Keywords from list Structural instability; Temporary Works
Job nature – type of activity A
Incident rating – potential 10
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved Sub contractor
Could the designer have done
more?
4
Did the designer miss the
opportunity to do more?
J
Design effort L
Designer specialist knowledge 3
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
0
Could site supervision at
construction/ site detail have
made a difference?
0
Remarks
No temporary supporting structures should be interfered with while the structures they are supporting
have not been strengthened in other ways without careful assessment of the likely consequences of
such an action.
HSE Peer review: Ref 4467/R33.115 66 Case worksheet HAB 37H
Quick Ref 10J Designers TW
Description of incident
During its 14th
pour the roof section of a reinforced concrete box culvert collapsed. The work was
under the direction of a city council acting on behalf of a water authority. The formwork sub-contractor
had employed consulting engineers to design the falsework and formwork. The roof slab was 550mm
thick x 6m wide. An inspection of similar adjoining falsework revealed a series of inadequacies
including no bracing, eccentrically loaded props and missing base plates.
The design had been carried out in accordance with the code for the structural use of timber and not
that for falsework. The design did not include any horizontal loading usually assumed from placing the
concrete.
Keywords from list Falsework; Temporary works
Job nature – type of activity A
Incident rating – potential 8
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü ü
Could the designer have done
more?
4 10
Did the designer miss the
opportunity to do more?
C J
Design effort L M
Designer specialist knowledge 1 1
Cost implications L L
Could external intervention at
design stage (PS) have made a
difference?
3 3
Could site supervision at
construction/ site detail have
made a difference?
1 1
Remarks
There was a serious failure by both the design engineer for the temporary works and the supervising
engineer. The temporary works design was not to the appropriate code and suggests the engineer was
not experienced in this type of work. The supervising engineer should have been aware of the gross
shortcomings in the design and construction of the temporary works.
The works probably suffered through the length of the chain of authority both for the client and for
work on site. This could have resulted in each level of the construction hierarchy paying little attention
to how the others carried out their work.
In particular there appears to be a lack of competence as far as the design and construction of the
temporary works is concerned. For instance the 3 tiers of support to the formwork seem unnecessary
and should have prompted questions by the supervising staff.
HSE Peer review: Ref 4467/R33.115 67 Case worksheet HAB 38H
Quick Ref 10J Designers TW
Description of incident
A 225 thick rc floor slab collapsed as it was being poured. The slab spanned 5.7m between steel beams.
The formwork was plywood sheets on telescopic centres, which were carried on the beam shutters and
a central 150x75 timber bearer layed on its side, which was carried by telescopic props at 0.75 – 1.20m
centres. The props were not laced or braced and, in some cases, were up to 125 out of plumb. In
addition, there were instances of poor foundations to the props.
Checks revealed that in places the centre supporting timber and the props were up to 4 times
overloaded sufficient to explain the flexural failure of this timber and the buckling of some props.
The work had been carried out by a formwork sub-contractor without any design being undertaken.
Keywords from list Collapse; Formwork
Job nature – type of activity A
Incident rating – potential 8
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü
Could the designer have done
more?
10
Did the designer miss the
opportunity to do more?
J
Design effort M
Designer specialist knowledge 1
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
3
Could site supervision at
construction/ site detail have
made a difference?
1
Remarks
The failure could have been prevented if a proper design had been undertaken and a suitably competent
person had supervised the works.
The failings were quite basic and should have raised questions by anyone having a reasonable
knowledge of these types of temporary works.
Telescopic props are made with a large reserve of strength and the fact that some buckled indicates a
serious degree of overloading. However, this large reserve of strength does tend to encourage abuse by
incompetent persons as does therefore require proper control.
HSE Peer review: Ref 4467/R33.115 68 Case worksheet HAB 39H
Quick Ref 6E Designers
Description of incident
A proprietary falsework system was being dismantled. The materials used to build the non-standard
falsework and access ways around the system, were scaffold materials and plywood. This resulted in
tripping hazards which compounded the absence of guard rails in some instances.
There was a potential for persons to fall over 5m due to the ad hoc nature of the temporary works
which had not been dealt with in the design.
Keywords from list Falsework; Access
Job nature – type of activity A
Incident rating – potential 8
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü
Could the designer have done
more?
6
Did the designer miss the
opportunity to do more?
E
Design effort L
Designer specialist knowledge 1
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
3
Could site supervision at
construction/ site detail have
made a difference?
1
Remarks
Temporary works should be designed so that they are safe to erect, use and then dismantle. The design
of this falsework system did not consider the needs for access during each of these stages. This should
have been dealt with when arranging the layout of the proprietary equipment and associated make-up
areas and formalised in the method statement.
The use of proprietary equipment, which incorporates ‘typical’ solutions for access etc., can lead to a
false sense of security. This is because the difficulties that can arise when dealing with the non-
standard areas around the proprietary system can be forgotten, meaning that the contractor must do the
best he can.
The quality and suitability of the resulting in-fill will then depend on the experience and reliability of
those doing the work and on the materials or equipment that is at hand.
HSE Peer review: Ref 4467/R33.115 69 Case worksheet HAB 40H
Quick Ref 4C Designers T/W
Description of incident
A large steel reinforcement cage, approx. 4.25m highx4.1m long backed by a 2.1m wide and 1.6m deep
chamber area, was being prefabricated prior to being lifted into an existing sewage tank but collapsed
before the work had been completed. No additional bracing or strengthening had been incorporated
within the cage either to support it while being prefabricated or when being lifted into position. No
access had been provided for the steel fixers who therefore climbed the steel bars and rigged some
100mm wide timbers to stand on.
The work was being done by a specialist steelwork and formwork sub-contractor for the main civil
engineering sub-contractor who was working for the main contractor.
Keywords from list Reinforcement cage; Bracing; Temporary works
Job nature – type of activity G
Incident rating – potential 8
Incident rating – actual 4
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü
Could the designer have done
more?
4
Did the designer miss the
opportunity to do more?
C
Design effort L
Designer specialist knowledge 1
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
1
Could site supervision at
construction/ site detail have
made a difference?
1
Remarks
The re-ordering of the construction sequence by the sub-contractor was a sensible decision but did
involve structural issues.
The decision to prefabricate the reinforcement was taken by the re-Ø sub-contractor but should have
involved a full design review. Additional materials were required over the minimum necessary for the
original design which envisaged the reinforcement being erected in place against the formwork wall
shutter.
HSE Peer review: Ref 4467/R33.115 70 Case worksheet HAB 41H
Quick Ref 4F Designers Contractor
Description of incident
Steel re-Ø was being placed for a 45m long x 7.3m high x 0.6m thick wall. The work was nearing
completion except for the upper 3.3m section at the end 9m of wall. The reinforcement partly collapsed
when an access ladder, fixed to it for use by the steel fixers, was removed. A full collapse was probably
averted because of the stiffening effect of the starter bars from the concrete kicker and because at one
end of the wall the reinforcement returned onto a section of wall that had already been cast. As a result
the heavier reinforcement at the lower section of the outside face of the wall remained in place. The
reason for such a large length of wall was being worked on was because delivery of water bars had
prevented the casting of a shorter length of wall.
Keywords from list Reinforcement; Temporary works
Job nature – type of activity G
Incident rating – potential 8
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved Contractor
Could the designer have done
more?
4
Did the designer miss the
opportunity to do more?
F
Design effort M
Designer specialist knowledge 1
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
1
Could site supervision at
construction/ site detail have
made a difference?
0
Remarks
The reinforcement cage was a substantial structure in itself and contained over 22 tonnes of steel. The
erection of such structures requires proper consideration, particularly when unusual circumstances
come into play, and this should have flagged up the need for effective lateral supports.
Apparently the reinforcement cage appeared to be quite stable before the collapse and both faces of the
cage were well tied together. The collapse was attributed to the removal of a ladder from the
uncompleted end which may have pulled on the reinforcement initiating the collapse.
There was also a failing on the part of the site supervision that they failed to react and question the
stability of such a large structure.
HSE Peer review: Ref 4467/R33.115 71 Case worksheet HAB 42H
Quick Ref 8E(C)
8J(T) Designers Consultant
TW
Description of incident
A 12m long x 330mm wide block wall was being used as an external shutter for a 4.7m high mass
concrete filling, to be done in 3 lifts. During the pouring of the upper lift the block wall failed and the
wet concrete cascaded down onto a railway line below, forcing its temporary closure.
The concrete density had been increased without reference to the designer and was also very fluid.
However the design had not made proper allowance for the fluidity of the original concrete mix and
had not required any temporary supports to the block wall.
Keywords from list Falsework; Concrete;
Job nature – type of activity A
Incident rating – potential 8
Incident rating – actual 4
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü ü
Could the designer have done
more?
8 8
Did the designer miss the
opportunity to do more?
E J
Design effort M M
Designer specialist knowledge 1 1
Cost implications L L
Could external intervention at
design stage (PS) have made a
difference?
3 3
Could site supervision at
construction/ site detail have
made a difference?
1 1
Remarks
The design seems to have been carried out by someone who was not sufficiently experienced to
temporary works design and who mistakenly assumed that the loads, pressures and situations can be
narrowly predicted. Errors or omissions in the original design meant that there was insufficient
allowance for the possibility of site variations in concrete pressure, from changes in the density and
fluidity of the concrete, instigated on site. However, these changes alone should not have led to failure
if the original design had been sound.
The consequences of a shutter failure on this site could have been extremely serious. Therefore, the
design of the shutter should have been extremely detailed and adhered to.
HSE Peer review: Ref 4467/R33.115 72 Case worksheet HAB 43H
Quick Ref 10G Designers TW
Description of incident
The reinforcement for large 12 – 15m high walls was being fixed in a 97mx47m building that also had
a central spine wall. While some walls in this building had been concreted, most consisted only of the
reinforcement cage. The walls were 1.6m wide with 3 layers of vertical re-Ø EF & 3 layers of
horizontal re- Ø EF: mostly 32mm diam. bars at 174mm c/c, with frequent laps, which meant that high
wind pressures could develop. Generally, the two opposite faces of the cage were tied together, but at
one length only the reinforcement to the internal face had been erected.
Strong winds blew this reinforcement over which dragged adjoining large areas of the fully erected
cage and large sections of access scaffolding.
Keywords from list Wind loading; Reinforcement; Stability
Job nature – type of activity G
Incident rating – potential 8
Incident rating – actual 6
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü
Could the designer have done
more?
10
Did the designer miss the
opportunity to do more?
G
Design effort H
Designer specialist knowledge 4
Cost implications S
Could external intervention at
design stage (PS) have made a
difference?
0
Could site supervision at
construction/ site detail have
made a difference?
0
Remarks
Even after the event the specialist researchers could not agree the cause of the failure. With such huge
areas of free-standing re- Ø it is reasonable to expect design checks to be made on the stability of such
structures. This is especially true where only one face of the reinforcement was being erected. It
appears that the approach adopted on site was little different from when erecting reinforcement against
wall shutters for relatively short lengths, medium height walls and not realising that they had moved
into a very different league. There are a variety of provisions that could have been made to reduce the
risk of collapse. These include welding the faces of the cages together so ensuring that they acted
together, using the access scaffold to prop the reinforcement effectively significantly increasing the
overall width of this temporary structure, or by limiting the area of reinforcement that would be
exposed to wind loading. This latter provision would include making use of the corners as a strong
point, casting these first to provide rigid anchors to hold the adjoining rebar cages.
HSE Peer review: Ref 4467/R33.115 73 Case worksheet HAB 44H
Quick Ref 6E Designers Manuf
Description of incident
A proprietary formwork system consisted of waffle moulds resting on a framework of beams and in-
filler beams. These were supported by a system of props, lacing tubes and braces.
One of the beams had not been correctly fitted into position, possibly because one end had been
damaged, and in the same area the bracing to the prop heads had been omitted. This possibly allowed
the prop heads to move slightly and allowed the beam to fall.
Keywords from list System formwork; Structural erection
Job nature – type of activity G
Incident rating – potential 6
Incident rating – actual 6
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved Manuf
Could the designer have done
more?
6
Did the designer miss the
opportunity to do more?
E
Design effort H
Designer specialist knowledge H
Cost implications E
Could external intervention at
design stage (PS) have made a
difference?
1
Could site supervision at
construction/ site detail have
made a difference?
2
Remarks
The design of proprietary systems should take account of the possibility of erector error and limited
component damage. The end fixing for the beams should be designed so that they are either correctly
located or cannot be fitted at all. Being able to use a damaged/incorrectly fitted item is a recipe for
disaster. Any damage that could be significant but would not be easily recognised presents a serious
hazard. Items should be so designed that any defects that could be a problem are easily recognised.
HSE Peer review: Ref 4467/R33.115 74 Case worksheet HAB 45H
Quick Ref 2C Designers Consultant
Description of incident
A proprietary falsework system was being used to support plywood formwork. Areas between the
proprietary system were being individually supported on props.
The falsework was being stripped without ensuring that the plywood formwork was also removed. In
one area a hole for a duct had been formed in the slab although the plywood formwork continuously
covered the area. This area of plywood also remained in place after the supporting falsework and props
had been removed.
A person stood on the plywood that then collapsed.
Keywords from list System falsework
Job nature – type of activity A
Incident rating – potential 6
Incident rating – actual 6
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü
Could the designer have done
more?
2
Did the designer miss the
opportunity to do more?
C
Design effort L
Designer specialist knowledge 1
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
2
Could site supervision at
construction/ site detail have
made a difference?
3
Remarks
The main circumstances that contributed to this incident were due to failures by the site management.
However had a detailed design procedure been provided it is possible that some of these circumstances
would not have occurred.
HSE Peer review: Ref 4467/R33.115 75 Case worksheet HAB 46H
Quick Ref 10J(T)
4E(A) Designers TW/Arch
Description of incident
An existing 3-storey building was being completely stripped for conversion into offices. This work also
included excavating in the basement area requiring temporary propping to the ground. The fabrication,
standard of construction and design of these earth retaining structures was very suspect, as was the
means of access into the ground works and a PN was issued.
Keywords from list Refurbishment; Temporary stability; Ground stability
Job nature – type of activity R
Incident rating – potential 8
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü ü
Could the designer have done
more?
4 10
Did the designer miss the
opportunity to do more?
E J
Design effort M M
Designer specialist knowledge 3 2
Cost implications E E
Could external intervention at
design stage (PS) have made a
difference?
4 4
Could site supervision at
construction/ site detail have
made a difference?
3 3
Remarks
The arrangements required to support ground which is in the vicinity of load bearing walls needs
careful assessment and the temporary works necessary to support the ground needs to be designed by
an experienced engineer having the relevant competencies in this type of work.
No mention is made of the need to fully investigate the loads on the walls being left in place and
particularly the depth of their footings in relation to the depth of the excavation.
HSE Peer review: Ref 4467/R33.115 76 Case worksheet HAB 47H
Quick Ref 8G Designers Consultant
Description of incident
A brick wall surrounding a site collapsed after some excavations had taken place close to it. The site
area was 2-3m below the adjoining street level and the wall foundation extended another metre below
the general site level. An earth embankment formed on its side facing the site supported the wall. This
embankment was being modified to form an access way to road level by cutting part of it away and
depositing the removed material lower down the ramp.
While the wall itself was reasonably sound it had been underpinned at some time with 2-3m concrete.
This was in a poor condition with its vertical and horizontal casting joints in a very poor condition. The
exposed face of the concrete had been rendered partially hiding the condition of the concrete.
Keywords from list Excavations; Structural stability; Adjacent structures
Job nature – type of activity E
Incident rating – potential 10
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü
Could the designer have done
more?
8
Did the designer miss the
opportunity to do more?
G
Design effort M
Designer specialist knowledge 1
Cost implications E
Could external intervention at
design stage (PS) have made a
difference?
4
Could site supervision at
construction/ site detail have
made a difference?
3
Remarks
When retaining old structures, facades, etc, designers should ensure that their true conditions are
known. In this case, the condition of the of the wall should have been checked and measures designed
in or information provided, to ensure that it remained stable.
Any situation where major forces could occur and especially where some interference will be made to
materials that support buildings, roads, railways or major services, should be thoroughly examined
before starting work.
HSE Peer review: Ref 4467/R33.115 77 Case worksheet HAB 48H
Quick Ref 10J(T)
6G(A) Designers TW/Arch
Description of incident
An excavation was being carried out beside an existing retaining wall into a sandy soil. The wall was
570mm thick, some 1.2 – 1.5m above the lower ground level with the u/side of its foundations 1.2 -
1.5m below lower ground surface. The trench had been excavated to a depth of 0.65 – 1.2m below the
wall’s foundations. Approx. 7.4m length of wall collapsed into the trench.
Keywords from list Excavation; Collapse of structure
Job nature – type of activity E
Incident rating – potential 8
Incident rating – actual 2
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü ü
Could the designer have done
more?
6 10
Did the designer miss the
opportunity to do more?
G J
Design effort M M
Designer specialist knowledge 4 1
Cost implications L L
Could external intervention at
design stage (PS) have made a
difference?
3 3
Could site supervision at
construction/ site detail have
made a difference?
1 1
Remarks
The design required the excavation adjacent to the wall therefore, the effects of this process on the
stability of the wall should have been investigated. Effective temporary ground support should have
been installed against the wall before excavation started, driven to such a depth so as to prevent the
wall collapsing. To be able to do this effectively proper ground investigations should have been carried
out.
While there was a design failing in not providing information on the nature and depth of the wall those
carrying out the excavation work should have realised there could be a potential problem when they
first exposed the bottom of the retaining wall.
HSE Peer review: Ref 4467/R33.115 78 Case worksheet HAB 49H
Quick Ref 2C(A)
8E(C)
6C(M) Designers A/C/M
Description of incident
Excavations were being carried out in clay soil, the upper 1.2m generally being disturbed material:
generally, the exc’s were 1.2m deep but at one location 2.7m. The sides of the trenches were being
lined with polystyrene sheets to protect the new structure from clay heave. A person went into the
deepest part of the trench to secure these sheets when one side of the excavation partly collapsed.
Keywords from list Excavations; Trench work
Job nature – type of activity E
Incident rating – potential 6
Incident rating – actual 2
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü ü Manufacturer
Could the designer have done
more?
2 8 6
Did the designer miss the
opportunity to do more?
C E C
Design effort L L L
Designer specialist knowledge 2 2 1
Cost implications R R R
Could external intervention at
design stage (PS) have made a
difference?
2 2 2
Could site supervision at
construction/ site detail have
made a difference?
3 3 3
Remarks
The principal error was by the contractor and the individual.
HSE Peer review: Ref 4467/R33.115 79 Case worksheet HAB 50H
Quick Ref 4C Designers Consultant
Description of incident
A worker was setting up a laser target in a trench approx. 3.1m below ground level [Approx. 1.1m of
made up ground overlying a sandy clay] when he was struck by falling earth. The trench had near
vertical sides 1.75m high and then battered back at less than 450. A trench box was on site but had not
been installed at the time of the accident. Trial pits had been dug in the vicinity of the works that
clearly revealed the nature of the ground. The excavation had been opened at least the day before the
accident.
Keywords from list Excavation; Trench collapse
Job nature – type of activity E
Incident rating – potential 6
Incident rating – actual 4
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü
Could the designer have done
more?
4
Did the designer miss the
opportunity to do more?
C
Design effort L
Designer specialist knowledge 2
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
2
Could site supervision at
construction/ site detail have
made a difference?
3
Remarks
The designer should have highlighted the risk of falling debris in the DRA.This type of ground is well known to be very suspect, particularly as the trench was quite deep. Thisinformation was available to the ‘designer’ even if he did not commission it.
HSE Peer review: Ref 4467/R33.115 80 Case worksheet HAB 51H
Quick Ref 2C Designers Consultant
Description of incident
A labourer was working in a 1.5m trench with near vertical sides. No support was provided to the
trench and while the labourer was crouched over his work earth material fell on him causing serious
injuries. The ground was formed from a top 600mm layer of made ground overlaying coarse sand and
gravel.
Keywords from list Excavation; Trench collapse
Job nature – type of activity E
Incident rating – potential 6
Incident rating – actual 4
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü
Could the designer have done
more?
2
Did the designer miss the
opportunity to do more?
C
Design effort L
Designer specialist knowledge 2
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
1
Could site supervision at
construction/ site detail have
made a difference?
3
Remarks
The designer should have highlighted the risk of falling debris in the DRA.Although the ground was not particularly deep its nature made it particularly susceptible to falls.However as the ground was covered by fill material it required trial pits to be dug to investigate thegrounds true character.
HSE Peer review: Ref 4467/R33.115 81 Case worksheet HAB 52H
Quick Ref N/A Designers
Description of incident
A light fitting, one of around 200 was being changed in a college dining room with a 6.15m high
ceiling. A ladder was being used for access resting on a smooth marble floor area and resting against
the side of a polished concrete drop beam.
The ladder slipped. After the accident a small portable hydraulic vertical lift access platform was used.
Keywords from list Ladder work;
Job nature – type of activity C
Incident rating – potential 6
Incident rating – actual 6
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved N/A N/A N/A N/A
Could the designer have done
more?
Did the designer miss the
opportunity to do more?
Design effort
Designer specialist knowledge
Cost implications
Could external intervention at
design stage (PS) have made a
difference?
Could site supervision at
construction/ site detail have
made a difference?
Remarks
Where there are items that could need maintenance at frequent intervals more permanent access
provision should be made than for items that are unlikely to need much or any maintenance. Any
systems provided should be appropriate to the likely skills of those who would use them.
HSE Peer review: Ref 4467/R33.115 82 Case worksheet HAB 53H
Quick Ref 4C Designers Manuf
Description of incident
A suspended access platform was being used for repairs on a block of flats when the power supply
failed causing the automatic locking system to activate and trap the persons using the equipment on the
platform.
No means had been provided for the workers to signal for help and they were not aware of how to
release the locking mechanism.
Keywords from list Access; Fail safe
Job nature – type of activity C
Incident rating – potential 8
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved Manufacturer
Could the designer have done
more?
4
Did the designer miss the
opportunity to do more?
C
Design effort L
Designer specialist knowledge 1
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
0
Could site supervision at
construction/ site detail have
made a difference?
2
Remarks
It is important that the design of the system, especially the systems of control, is very obvious to the
persons who are likely to use those systems. It is common for persons with little or no experience or
knowledge of the mechanics of powered suspended access platforms to be expected to use them. The
means of using this type of equipment should therefore be very obvious. A large part of this problem
was that the occurrence was rare and the workers on the platform had either forgotten or not been told
how to deal with it. In addition the initiation of the failure through a damp and loose electrical
connector suggests that the maintenance of the access platform was suspect.
HSE Peer review: Ref 4467/R33.115 83 Case worksheet HAB 54H
Quick Ref 10G Designers Architect
Description of incident
A cleaner climbed into a spirally wound overhead ducting to clean it out. A 3m approx. length, which
was supported directly at only one end collapsed at a point where an inspection hatch had been
installed. The structural supports to the ducting were noted as being completely inadequate.
Keywords from list Cleaning
Job nature – type of activity C
Incident rating – potential 6
Incident rating – actual ?
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü
Could the designer have done
more?
10
Did the designer miss the
opportunity to do more?
G
Design effort L
Designer specialist knowledge 2
Cost implications E
Could external intervention at
design stage (PS) have made a
difference?
3
Could site supervision at
construction/ site detail have
made a difference?
2
Remarks
The designer should have been aware that the ducting would need cleaning from time to time, most
likely by someone working inside it The supports to the ducting, and possibly the ducting, were not
strong enough to support the weight of the cleaner. This should have been obvious to anyone concerned
with the design.
Although it is probable that the ducting was designed and installed by someone who would have little
appreciation of the cleaning needs of the site, this should have been obvious to the architect.
HSE Peer review: Ref 4467/R33.115 84 Case worksheet HAB 55H
Quick Ref N/A Designers
Description of incident
A 100-year old 33m high building was being repainted. The working platforms for the painters were on
a light duty scaffold secured to the building with ring ties. The scaffold had been built in sections and
was moved progressively around the building as the work proceeded, with the section of the scaffold
being dismantled carried around and stored on an adjoining section prior to rebuilding it. The weight of
the stored scaffold materials overloaded the scaffold and it collapsed. Some of the ring ties failed in
shear and others pulled out og the building’s façade.
Keywords from list Access; Scaffolding
Job nature – type of activity G
Incident rating – potential 10
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved N/A N/A N/A N/A
Could the designer have done
more?
Did the designer miss the
opportunity to do more?
Design effort
Designer specialist knowledge
Cost implications
Could external intervention at
design stage (PS) have made a
difference?
Could site supervision at
construction/ site detail have
made a difference?
Remarks
Facilitating routine maintenance by some form of permanent feature(s) will vary in practicality
according to both the frequency of the maintenance and the cost effectiveness in supplying the feature.
For instance if this is complex and expensive to install then it could be cost effective to make it
permanent even if the maintenance frequency was low. On the other hand even a simple, low cost
feature required for very regular work could be permanently installed so as to be cost effective. All
such measures are likely to be more reliable than temporary ones.
HSE Peer review: Ref 4467/R33.115 85 Case worksheet HAB 56H
Quick Ref N/A Designers
Description of incident
A maintenance worker was looking for the source of a water leak by standing on/crossing over a
suspended ceiling. This was only designed for very light use such as carrying insulation material, and it
failed. The area above the ceiling contained ducting and air conditioning equipment and there was
evidence that occasional access took place over the suspended ceiling.
Keywords from list Access; Maintenance
Job nature – type of activity C
Incident rating – potential 6
Incident rating – actual 6
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved N/A N/A N/A N/A
Could the designer have done
more?
Did the designer miss the
opportunity to do more?
Design effort
Designer specialist knowledge
Cost implications
Could external intervention at
design stage (PS) have made a
difference?
Could site supervision at
construction/ site detail have
made a difference?
Remarks
Any ceiling or platform that has any sort of plant/equipment above it and is relatively easily accessed
can be almost guaranteed to be used as an access or working place. Consequently the only practical
solutions of ensuring persons cannot fall through them is to either make them strong enough or make
access impossible.
HSE Peer review: Ref 4467/R33.115 86 Case worksheet HAB 57H
Quick Ref 4E Designers Architect
Description of incident
Scaffold walkways were being installed over the fragile ceiling to a swimming pool. One length of tube
fell through the ceiling and hit a swimmer below. The area above the ceiling was a plant room for the
pool. The ceiling itself had quite a complex shape which would be a major discouragement for persons
to stand directly on it.
Keywords from list Access; Fragile ceiling
Job nature – type of activity G
Incident rating – potential 10
Incident rating – actual 4(public)
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü
Could the designer have done
more?
4
Did the designer miss the
opportunity to do more?
E
Design effort L
Designer specialist knowledge 1
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
3
Could site supervision at
construction/ site detail have
made a difference?
3
Remarks
HSE Peer review: Ref 4467/R33.115 87 Case worksheet HAB 58H
Quick Ref 6E Designers Architect
Description of incident
A building was being refurbished and in the course of this staircase balustrade and handrails had been
removed and plastic warning tape placed around the stair well. Upholsters were working on the upper
floor in the neighbourhood of the stairs and one fell down the stair. well.
Keywords from list Access; Unprotected edge
Job nature – type of activity R
Incident rating – potential 6
Incident rating – actual 4
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü
Could the designer have done
more?
6
Did the designer miss the
opportunity to do more?
E
Design effort L
Designer specialist knowledge 1
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
3
Could site supervision at
construction/ site detail have
made a difference?
4
Remarks
The sequence of installing new balustrading after the removal of the old should have been strictly
controlled and suitable temporary barriers should have been installed in the meantime.
The more complex the maintenance or refurbishment works the greater the need to plan and design it to
minimise errors. This planning and design would clearly require contributions from all those involved.
HSE Peer review: Ref 4467/R33.115 88 Case worksheet HAB 59H
Quick Ref N/A Designers
Description of incident
An electrician was installing cabling on a 5m high cable tray, which rested on a small beam. The floor
below was mostly filled by plant and the electrician was using a portable ladder to gain access to the
cable tray. There were faults with the ladder feet and the floor was of a sealed concrete making the
coefficient between ladder and floor quite low. The ladder apparently slipped while the electrician was
on it and he fell.
Keywords from list Ladder access; Original design
Job nature – type of activity C
Incident rating – potential 6
Incident rating – actual 6
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved N/A N/A N/A N/A
Could the designer have done
more?
Did the designer miss the
opportunity to do more?
Design effort
Designer specialist knowledge
Cost implications
Could external intervention at
design stage (PS) have made a
difference?
Could site supervision at
construction/ site detail have
made a difference?
Remarks
The problem here was congestion in the area under the cable-tray. Perhaps it could have been installed
in an area where access could have been more easily provided. Alternatively hooks could perhaps have
been fitted to the tray or supporting beam to allow a ladder to be engaged on them for added security.
Using a ladder at this height and in a poor condition would be a gamble which would be made worse
by only having the small depth of the supporting beam to rest against. As ladders can only be altered in
length by approx. 220mm increments, the opportunities of arranging the ladder in the limited floor
space, at a reasonable angle and against the beam would be limited
HSE Peer review: Ref 4467/R33.115 89 Case worksheet HAB 60H
Quick Ref 10J Designers Architect
Description of incident
A new building that partly extended over a motorway had arrangements for the window cleaners where
they worked off mesh walkways and were secured by a waist high safety line to which they were
attached via lanyards and harnesses. There were no guard-rails or other form of barrier. Little provision
had been made, through the use of toe-boards etc, to prevent the fall of materials to the pedestrian areas
and motorway below.
Keywords from list Edge protection; Access; Falls of materials
Job nature – type of activity W
Incident rating – potential 10
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü
Could the designer have done
more?
10
Did the designer miss the
opportunity to do more?
J
Design effort L
Designer specialist knowledge 1
Cost implications E
Could external intervention at
design stage (PS) have made a
difference?
3
Could site supervision at
construction/ site detail have
made a difference?
0
Remarks
The designer tried to minimise the visual impact of the access and protective systems for the window
cleaners. Although it should have ensured that the window cleaners were safe and that people below
were protected from falling objects, it did not.
This is an example where a safe system of work can be provided which still does not meet the legal
requirements.
HSE Peer review: Ref 4467/R33.115 90 Case worksheet HAB 61H
Quick Ref 8J Designers Manuf
Description of incident
A luffing screw on a window-cleaning cradle broke allowing the cradle jib to drop onto the roof
parapet. The screw had become stiff at a fixing position causing a rotational failure.
Keywords from list Equipment failure; Access
Job nature – type of activity W
Incident rating – potential 10
Incident rating – actual 4
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved Manufacturer
Could the designer have done
more?
8
Did the designer miss the
opportunity to do more?
J
Design effort M
Designer specialist knowledge 1
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
0
Could site supervision at
construction/ site detail have
made a difference?
0
Remarks
No facilities were provided in the design to allow access, for routine inspections, to the area where the
failure of a safety-critical item occurred.
All surfaces of items that are subject to abrasion, loosening or corrosion should be capable of being
properly inspected, serviced and lubricated.
HSE Peer review: Ref 4467/R33.115 91 Case worksheet HAB 62H
Quick Ref 6C Designers Manuf
Description of incident
The roof rig of a permanent window-cleaning cradle became dislodged off the roof runway beam. The
problem occurred where a turntable had been installed to allow the rig to be moved off the perimeter
runway beam into a parking bay. It was found that the turntable had a guard plate to prevent the rig run
off, over the turntable but this was on the wrong side. In addition the rail on the turntable was not
correctly aligned with the perimeter rail when the turntable was locked into position ready for use.
Keywords from list System access cradle
Job nature – type of activity W
Incident rating – potential 10
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved Manufacturer
Could the designer have done
more?
6
Did the designer miss the
opportunity to do more?
C
Design effort L
Designer specialist knowledge 2
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
2
Could site supervision at
construction/ site detail have
made a difference?
2
Remarks
While the main part of the fault probably lies with the construction of the rig runway, the design was
not as foolproof as such a vulnerable system should be.
The cradle rig was fairly simple to use and it is probable that the rig was used previously across the
turntable without incident through not going too far. The failure occurred when the rig travelled too far
and should have been stopped by guard plate if it had been in the right place. The incorrect alignment
of the turntable rail only compounded the problem. An effective inspection after the rig was installed
should have revealed the problem.
HSE Peer review: Ref 4467/R33.115 92 Case worksheet HAB 63H
Quick Ref 8G Designers Architect
Description of incident
Advice was given on two window cleaning systems. In the first case cradles were to be slung from a
permanent beam fixed at eaves level. The fixings for this beam were to be largely hidden behind a
fascia panel making inspection difficult. Advice was given for the inspection to be at more frequent
intervals. In the second case a powered gantry was to climb a 300 glass atria roof and the cradle for the
cleaners would have to be manhandled to its different faces. It was recommended that some form of
trolley should be provided to help with this. Installing the cradle was quite complicated and required
the cleaners to be well trained.
Keywords from list Window cleaning system; System access
Job nature – type of activity W
Incident rating – potential 10
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü
Could the designer have done
more?
8
Did the designer miss the
opportunity to do more?
G
Design effort M
Designer specialist knowledge 2
Cost implications E
Could external intervention at
design stage (PS) have made a
difference?
3
Could site supervision at
construction/ site detail have
made a difference?
0
Remarks
The advice given dealt with necessary precautions and these should have been obvious to the designer
without requiring the HSE Inspector to intervene. In addition the atria gantry cradle should have been
designed to be more easy to use.
The decision to provide a relatively complicated mechanical system for use by window cleaners could
lead to problems and training costs. Window cleaners regularly change jobs and are often recruited
from the bottom of the employment ladder. This could mean that there would be a steady turnover of
trained cleaners requiring a continual commitment to train new staff.
All fixings for suspended or slung equipment should be readily observable so that any deterioration or
damage will be quickly seen.
HSE Peer review: Ref 4467/R33.115 93 Case worksheet HAB 64H
Quick Ref 8G Designers Architect
Description of incident
Suspension wires for overhead tramway cables were to be fixed to a building that had its windows
cleaned through the use of a suspended cradle. It was found that the travel of the cradle could not easily
interfere with the suspension wires but to be sure projecting ‘stops’ were fixed to the building to
prevent the cradle moving too close to them.
Keywords from list Access equipment
Job nature – type of activity W
Incident rating – potential 10
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü
Could the designer have done
more?
8
Did the designer miss the
opportunity to do more?
G
Design effort M
Designer specialist knowledge 2
Cost implications E
Could external intervention at
design stage (PS) have made a
difference?
3
Could site supervision at
construction/ site detail have
made a difference?
0
Remarks
During the lifetime of most buildings, especially those in busy areas, there will be frequent and
numerous demands for alterations and changes. It is part of the designers job to facilitate such changes
as simply as possible
HSE Peer review: Ref 4467/R33.115 94 Case worksheet HAB 65H
Quick Ref 8G Designers Manuf
Description of incident
A window-cleaning cradle collapsed when a stainless steel bolt failed. This had been made by welding
a head onto the shaft rather than turning it down from larger diameter bar. The manufacturers of the
bolt had not been informed of the critical nature of the bolt.
Keywords from list Acc equipment failure;
Job nature – type of activity W
Incident rating – potential 10
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved Manufacturer
of cradle, not
pin
Could the designer have done
more?
8
Did the designer miss the
opportunity to do more?
G
Design effort L
Designer specialist knowledge 1
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
0
Could site supervision at
construction/ site detail have
made a difference?
0
Remarks
It is probable that a more structurally reliable component would have been produced if the
manufacturers had been aware of its critical nature and how it was to be loaded.
The designer had two options that could have helped to avoid this incident. The first was to have
provided details on how the bolt was to be used, the second to have provided a detailed specification of
how it should be tested. By not doing either the design failed as insufficient information was provided
to allow the bolt to be properly manufactured.
HSE Peer review: Ref 4467/R33.115 95 Case worksheet HAB 66H
Quick Ref 6E(A)
10J(T) Designers A/T
Description of incident
The insides of two adjoining buildings were being demolished prior to their renovation. One building
had been extensively vandalised and left open to the weather for approx. 2 years causing deterioration
to the internal timbers. As the demolition progressed one floor collapsed causing other floors below to
fail. Subsequent investigation showed that the joists were rotten and that the structural arrangement of
the floors was not as straightforward as could be assumed without detailed investigation.
The façade of the buildings was being retained to a design prepared by an engineering consultant.
Keywords from list Structural collapse; Demolition
Job nature – type of activity D
Incident rating – potential 8
Incident rating – actual 2
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü ü
Could the designer have done
more?
6 10
Did the designer miss the
opportunity to do more?
E J
Design effort M M
Designer specialist knowledge 2 1
Cost implications S S
Could external intervention at
design stage (PS) have made a
difference?
4 4
Could site supervision at
construction/ site detail have
made a difference?
4 4
Remarks
The state of the buildings should have been carefully surveyed prior to work starting and detailed plans
drawn up to ensure the stability of the structural components as each level was removed. Such a survey
should have investigated both the structural format of the buildings and the condition of the various
structural components.
In designing any temporary support work it would be necessary to allow for the accumulation of debris
etc. following the removed of upper levels.
HSE Peer review: Ref 4467/R33.115 96 Case worksheet HAB 067H
Quick Ref N/A
Designers N/A
Description of incident
Collapse of a series of 48 roof trusses during erection. Bracing had been specified but not fixed in the
main and in any case inadequately fixed.
Keywords from list Bracing; Roof truss erection collapse
Job nature – type of activity O
Incident rating – potential 8
Incident rating – actual 4
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved N/A
Contractor
management
Could the designer have done
more?
Did the designer miss the
opportunity to do more?
Design effort
Designer specialist knowledge
Cost implications
Could external intervention at
design stage (PS) have made a
difference?
0
Could site supervision at
construction/ site detail have
made a difference?
3
Remarks
While this matter was not designer related in the main it could have been that had additional
information been provide on the drawings that the sub-sub-contractor used would have been less likely
to make the omissions made. The information may have been in place and benefit is given to the
designer in this case.
HSE Peer review: Ref 4467/R33.115 97 Case worksheet HAB 68H
Quick Ref 2A Designers TW
Description of incident
Special pin jointed roof truss installation in difficult site. Report based on prior test of erection method.
This summary based on future project as well.
Keywords from list Access; Roof truss erection
Job nature – type of activity O
Incident rating – potential 8
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü
Could the designer have done
more?
2
Did the designer miss the
opportunity to do more?
A
Design effort L
Designer specialist knowledge 1
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
1
Could site supervision at
construction/ site detail have
made a difference?
1
Remarks
This was a significant project in a public place so additional resources had been applied to manage risk.
HSE Peer review: Ref 4467/R33.115 98 Case worksheet HAB 69H
Quick Ref N/A Designers
Description of incident
Fall through a fragile roof. Crane driver giving advice to contractor regarding slinging of gable end
section of a building.
Keywords from list Fall from height through; Fragile roof
Job nature – type of activity O
Incident rating – potential 6
Incident rating – actual 4
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved Contractor
management
Could the designer have done
more?
Did the designer miss the
opportunity to do more?
Design effort
Designer specialist knowledge
Cost implications
Could external intervention at
design stage (PS) have made a
difference?
Could site supervision at
construction/ site detail have
made a difference?
Remarks
The only moot point here is whether a designer should have provided information to the contractor
about the nature of the roof lights. It would however have been just as dangerous for the designer to
have established this fact unless a desk study could have provided the information. All roof lights
should be assumed to be fragile unless otherwise indicated.
HSE Peer review: Ref 4467/R33.115 99 Case worksheet HAB 70H
Quick Ref 8G Designers Consultants
Description of incident
This report relates to steel work erection requiring tandem lifts due to design.
Keywords from list Structural erection; Lifting operations
Job nature – type of activity O
Incident rating – potential 8
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved ü
Could the designer have done
more?
8
Did the designer miss the
opportunity to do more?
G
Design effort M
Designer specialist knowledge 2
Cost implications L
Could external intervention at
design stage (PS) have made a
difference?
3
Could site supervision at
construction/ site detail have
made a difference?
1
Remarks
Designers could have designed in such a manner that tandem lifts were not required. Further difficult
marrying of two elements required by design introduced unnecessary hazards.
HSE Peer review: Ref 4467/R33.115 100 Case worksheet HAB 71H
4E M
Quick Ref
Designers
Description of incident
Failure of pre-cast, pre-stressed floor slab under its own weight. Report states that the units may have
been damaged in transit or during erection. No information available to inform in relation to product
quality.
Keywords from list Structural failure; Pre-cast units
Job nature – type of activity G
Incident rating – potential 8
Incident rating – actual 0
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved Manufacturer
Handler
Could the designer have done
more?
4
Did the designer miss the
opportunity to do more?
E
Design effort M
Designer specialist knowledge 1
Cost implications E
Could external intervention at
design stage (PS) have made a
difference?
1
Could site supervision at
construction/ site detail have
made a difference?
0
Remarks
Manufacturers of system building products should expect some mishandling in transit and during
fabrication. If this is critical to safety and stability of their product, specifiers and users should be
alerted to the need for caution.
HSE Peer review: Ref 4467/R33.115 101 Case worksheet HAB 72H
Quick Ref N/A Designers
Description of incident
Collapse of floor slabs during construction of a block of flats. The pre-cast slabs rested on lintels that
showed excessive deflection. The slabs were propped with timber which subsequently failed leading to
progressive collapse of structural elements. The lintel was a replacement element that had been selected
by an individual with no technical training together with a builder’s merchant.
Keywords from list Structural failure; Pre-cast units
Job nature – type of activity G
Incident rating – potential 8
Incident rating – actual 4
Reference category Architect Engineer TW Designer Other
(Specify)
Designers involved Contractor
Could the designer have done
more?
Did the designer miss the
opportunity to do more?
Design effort
Designer specialist knowledge
Cost implications
Could external intervention at
design stage (PS) have made a
difference?
Could site supervision at
construction/ site detail have
made a difference?
Remarks
Such “on the hoof” solutions to problems of supply or construction are very common. Where they
succeed in solving a problem they tend to be commended. Where they do not they are roundly
criticised. Clearly design input was needed and was not used.
HSE Peer review: Ref 4467/R33.115 102 Case worksheet HAB 73H
Printed and published by the Health and Safety ExecutiveC30 1/98
Printed and published by the Health and Safety Executive C1.10 04/04
ISBN 0-7176-2836-1
RR 218
78071 7 628360£25.00 9