RPT ON MAG & VLF-EM SUR COSTELLO LAKE AREA SKEAD TWP€¦ · COSTELLO LAKE AREA, SKEAD TOWNSHIP,...
Transcript of RPT ON MAG & VLF-EM SUR COSTELLO LAKE AREA SKEAD TWP€¦ · COSTELLO LAKE AREA, SKEAD TOWNSHIP,...
31M13NE8029 2.5495 SKEAD 010
RECEIVEDFtB 16 1983
MINING UNDS SECTION
REPORT SK-1
REPORT ON
MAGNETOMETER AND VLF-EM SURVEY
COSTELLO LAKE AREA
SKEAD TOWNSHIP, ONTARIO
by
R.A. MacGregor, P. Eng.
February 9 , 1 983
RECEIVED'M 2 2 1983
MINING UNDS SECTION
COLEX EXPLORATIONS INC. PAGE NO. ^
REPORT ON MAGNETOMETER AND VLF-EM SURVEY
COSTELLO LAKE AREA, SKEAD TOWNSHIP, ONTARIO
INTRODUCTION
Linecutting followed by a magnetometer and VLF-EM
survey was carried out on a block of claims west of Costello
Lake in Skead Township, Ontario. The results are shown on the
accompanying maps. ft
LOCATION, ACCESS AND OWNERSHIP
The claims are located in parts of Lots 9 to 11,
Concession 4; Lots 10 and 11, Concession 3 and Lot 11, Concession
2 in Skead Township, District of Temiskaming, Ontario. Claims
are numbered L57848 to 578355 and L561731 to 561752 all inclusive.
They are recorded in the name of Superior Northwest Inc,, Box Ill6
Sault Ste. Marie, Ontario and Lucien Lacasse, Larder Lake, Ontario.
Access is by logging roads which lead from Highway 624
about 8 miles south of Larder Lake, Ontario.
PREVIOUS EXPLORATION
Previous work has consisted of some pits, trenches and
stripping for which no records could be found.
GEOLOGY
The property is underlain by a volcanic sequence of
rocks, mostly mafic volcanics with narrow felsic volcanic bands
on the west side of the property,- A band of ultramafic rocks runs
through the centre of the claim group, trending north-south to
north-west south-east. On the eastern part of the claims, the
volcanics are overlain by younger sediments of the Cobalt series.
COUEX EXPUORATIONS INC. PAGE NO. 2
SURVEY PROCEDURE
A baseline was cut at approximately N 50 W - S 50 E
from a tie line cut southwest from a baseline at Mageau Lake.
Crosslines were then run at 400-foot intervals normal to the base
lines. All lines were chained and picketed at 100-foot intervals.
Magnetometer readings were taken with a Barringer GM-122
Proton Precession Magnetometer at 100-foot intervals. The looping
method was used for control of diurnal variation. In this method
a base station is selected and readings taken along lines describing
a loop, arriving back at the starting base station in less than two
hours. A second loop is then started using either the same base
station or another which is tied to the previous loop. Readings
are then corrected for diurnal variation by assuming the time
between readings is the same and distributing any variation equally
among the intervening readings. No correction was applied less
than the accuracy of the base station reading.
A VLF-EM survey was carried out using a Phoenix VLF-2
instrument set to the signal from Annapolis, Maryland (21.4 KHz).
Readings were taken at 100-foot intervals using the procedure out
lined in Appendix I. The looping method was used for control of
variation, the same as described for the magnetometer survey,
excepting that the time was noted for each station.
Because of stations being off the air, more than half
of the survey was conducted with a single station and repeated
for the second station.
t * * * t
COLE* EXPLORATIONS INC. PAGE NO.
RESULTS AND CONCLUSIONS
Magnetometer
Magnetic readings are high to the east of the baseline/
which is underlain by ultramafic rocks. The magnetic survey
clearly outlines the areas underlain by ultramafics.
VLF-EM
The VLF-EM survey shows a large number of anomalies
parallel to the trend of the ultramafics. The probable cause of
these anomalies is serpentinization within the ultramafic rocks.
Anomalies along the west part of the claims are in mafic to felsic
volcanic rocks and warrant surface prospecting or checking with
other geophysical methods.
Respectfully submitted
R.A. MacGregor, P. Eng,
February 9, 1983
R. A. MACGREGOR, P.ENG. ' , PAGE NO,
CERTIFICATE
I, Robert A. MacGregor, certify:
1. I am a Mining Engineer residing at 134 PalaceDrive, Sault Ste. Marie, Ontario. I have worked as a.mining engineer and geologist for the past 17 years.
2. I am a member of the Association of Professional Engineers of the Province of Ontario and a member of the Canadian Institute of Mining and Metallurgy.
3. I attended Queen's University for two years in the Mining-Geology course.
4. I personally supervised the fie^d^w.Qrk covered by this report.
DATE
VMTTICAL INTENSITY FLUXGATE MAGNETOMETER MF-1
SPECIFICATIONS
MODEL MF-1
Ranges!
Standard surveying and prospecting magnetometer with self- levelling sensor.
Plus or minus -1000 gammas f, se. Sensitivity; 20 gammas per div, 3000 " 50 "
10,000 " ZOO " 30,000 " 500100,000 " 2000
o 11
Meter: Taut-band suspension. 1000 gamma scale: l V/S'long - 50 div.3000 " " : 111-16" long - 60 div.
Accuracy:
Operating Temperature:
1000 to 10, 000 gamma ranges * 0. 5^o of full scale 30, 000 to 100, 000 gamma ranges ^ J.% of full scale
-4QOC to * 400 C-40 0F to -\ 1000F
Temperature Stability; Less than 2 gammas per OC (l gamma / 0F)
Bucking Adjustments: 10, 000 to 75, 000 gammas by 9 steps of approximately ( Latitude) 8, 000 gammas and fine control by 10 turn potentiometer.
Convertible for Southern hemisphere or * 30, 000 gammas equatorial.
Batteries: 12 x 1 . 5V flashlight batteries ("C" cell type)( AC Power supply available )
Consumption: 50 milliamperes
Dimensions:
Weights:
Instrument: 6 1/2" x 3 1/2" x 12 1/2" - 165 x 90 x 320 mm Battery Pack: 4" x 2" x 7" - 100 x 50 x 180 mm Shipping Container: 10" dia. x 16" -255 mm dia. x 410 mm
Instrument 5 Ibs. 12 oz. - 2. 6 kg, Battery Pack: 2 Ibs. 4 Oz. - l kg. Shipping: 13 Ibs.
MODIFIED FLUXGATE MAGNETOMETERS
MODEL MF-IR Magnetometer equipped with standard -{self-levelling) sensor and additional recording outlet,
Noise Level: l gamma P - P
Long Term Stability; -f l gamma for 24 hours at constant temperature
(34)
1. Range Switch
2. Meter
3. Main Switch
4. Level5. Battery Pack
6". Battery Connector 1 L carrying Strap*
MODEL MF-i.FLUXGATE MAGNETOMETER
st^ E. J. SHARPE INSTRUfrJEHTS OF CANADA LIMITED P.O. Dox 279; Willow dale, Ontario
7. SjlicaGe!
'8. Protection Cap
9. Latitude Adjustment Control Fine
iff. Latitude Adjustment Control Coarse
(35)
MODEL MF-1 FLUXGATE MAGNETOMETEROperotion of the Meter1.) R emove all magnetic objects from operator's person, e.g. keys, coins, buttons, etc.
Zippers should be non-magnetic.2.) Connect Battery Cable, Figure 6, to magnetometer receptacle on bottom of main hous
ing. This connection must be secured by lock-ring.3.) Attach battery pack (Fig. 5) either in back pocket or on belt behind operator.4.) Switch on Main Switch (Fig. 3) to first position, which is the battery check. Indicating
meter needle should rest within red arc. Replace batteries if reading below red arc.5.)Latitude Adjustment -To adjust the latitude setting toread O gammas is a simple operation.
a. After indicating meter needle (f ig.2) shows voltage okay, switch Main Sv itch(Fig.3) to next position which is the positive reading with the Range Switch (Fig. l)set at the 100K step. (100,000 gamma range)
b.If needle goes full arc to le-ft past O, switch main switch (Fig. 3) to last position which is the negative reading range.
c. Figures 10 and 9 indicate the latitude adjustment controls - Coarse control is Fig. 10 and Fine control is Fig. 9. If scale reading is more than 7 ,000 gammas rotate coarse control (Fig. 10) in steps of 7,000 and switch range down to more sensitive range until scale is reading less than i 7,000 gammas. Remove protection cap on fine control (Fig. 8) by pulling straight off. Then rotate fine control switch (Fig. 9) until scale reading is p gammas. Check reading by switching main switch from positive to negative (or vice versa) to ensure Dreading both polarities. Replace fine control protection cap.
6.) Calibration - This meter is calibrated at the factory prior to delivery. Field tests show that only by severe misuse (i.e. constant dropping, roigh handling, improper shipping) can the calibration of this instrument bi effected. It is therefore not necessary to re calibrate in the field and if through misuse calibration becomes necessary, the meter should be returned to the factory. *AII parts are guaranteed against defect for a period ' of one year and will he leplaceo free of charge. --- '
This guarantee does not apply to batteries or the connecting cable.7.*) Trouble Shooting - Under normal conditions the only field problem will be batteries or
the connecting cable. If after completion of step (4) under "Operation of the Meter" the meter still does not indicate voltage, check cable for faulty connection or broken cable. If after this procedure, meter still does not indicate current, return unit immedi ately to your supplier or directly to the factory.
Regional Latitude SettingsNormally each unit is pre-set at the factory for the Northern Hemisphere. However, if the unit is required for Equatorial or Southern Hemispheric regions, the unit will be pre-set at the factory for these areas. If a unit is going from one of the above regions to another, reset instructions will be supplied on request. Field Procedure1.) Select Base Control station. This station should be selected in relation to one or
both of two things.1. General magnetic background (i.e. not anomalous) if possible.2. Accessibility in relation to area being surveyed.
2.) Set magnetometer to read between O and 200 gamrcas. (For contouring and to avoid small negative readings, an arbitrary value of 1000-oOOjamma? should be added to all readings.
3.) For effective diurnal control, control staliyns should be permanently marked and read ings should be taken at the same height and location each time; a simple method is to have the control stations' pickets hammered into the ground with the top about waist height. Rest the probe end of the magnetometer on the top of the picket. In barren country,a mound or large piece of rock or some other material should be used.
4.) Continue survey the same, as any othe'. method of magnetic surveying.5.) Remove and replace Silica-Gel (Fip..7) when deteriorated. The silica gel is located
in the removable probe housing. The Silica bag should not be placed on the bottom of the probe housing.
6.) Do not pass powerful magnet closer than l foot to instrument.7.) During winter operation, batteries '-hould bc kept in nocket or under parka. ' Warning: - Do not leave batteries i. battery case when unit is being stored. Always be-
be sure meter is turned off otter use. Disconnect battery cable when meter not in uie.
A Df t n J 'i y I
CRONE GEOPHYSICS LIMITED
3607 WOLFEDALE ROAD, MISSISSAUGA, ONTARIO, CANADA.
Phone: (416) 270-0096
j^^
FIELD STRENGTH meter
BATTERY test and "STEADY" or "KEYED" signal switches
INCLINOMETER
FIELD STRENGTH range switch
VOLUME CONTROL -ON-OFF switch
STATION SELECTOR switch
BATTERY COMPARTMENT (inside)
CONDUCTOR DIRECTION ARROW SPEAKER
This is a rugged, simple to operate, ONE MAN EM unit. It can be used without line cutting and is thus ideally suited for GROUND LOCATION OF AIRBORNE CONDUCTORS and the CHECKING OUT OF MINERAL SHOWINGS. This instrument utilizes higher than normal EM frequencies and is capable of detecting DISSEMINATED SULPHIDE DEPOSITS and SMALL SULPHIDE BODIES. It accurately isolates BANDED CONDUCTORS and operates through areas of HIGH HYDRO NOISE. The method is capable of deep penetration but due to the high frequency used its penetration is limited in areas of clay and conductive overburden.
The DIP ANGLE measurement detects a conductor from a considerable distance and is used primarily for locating conductors. The FIELD STRENGTH measurement is used to define the shape and attitude of the conductor.
SPECIFICATIONS
Source of Primary Field: VLF Communication Stations 12 to 24 KHz
Number of Stations: 7 switch selectable
Stations Available: The seven standard stations are Cutler, Maine, 17.8; Seattle, Washington, 18.6; Collins, Colorado, 20.0; Annapolis, Md., 21.4; Panama, 24.0; Hawaii, 23.4; England, 16.0. Alternative stations which may bc substituted arc: Gorki, Russia, 17.1; Japan, 17.4; England, 19.6; Australia, NWC, 22.3 KHz.
Check that Station is Transmitting: Audible signal from speaker.
Parameters Measured and Means: -(3) DIP ANGLE in degrees, from the horizontal of the magnetic component of the VLF field. Detected by minimum on the field strength meter and read from an inclinometer with a range of 80 0 and an accuracy of Vz 0 .
(2) Field Strength (total or horizontal component) of the magnetic component of the VLF field. Measured as a per cent of normal field strength established at a base station. Accuracy 296 dependent on signal. Meter has two ranges: O 30096 and O 60096. Switch for "keyed" or "F.S." (steady) signal.
(3) Out of Phase component of the magnetic field, perpendicular in direction to the resultant field, measured without sign, as a per cent of normal field strength. This is the minimum reading of the Field Strength meter obtained when measuring the dip angle. Accuracy 296.
Operating Temperature Range: - 20 0 to + 130 0 F.
Dimensions and Weight: 3.5" X 7.5" X 10.5" 6 Ib.
Shipping: ' Foam lined wooden case shipping wt. 15 Ib.
Batteries: 2 of 9 volt: Eveready 216, Burgess 2U6, Mallory M-1604
Average life expectancy 3 weeks to 3 months dependent on amount of usage.
Units Available on a Rental or Purchase Basis. Contract Services Available for Field Surveys.
CRONE GEOPHYSICS LIMITED
3607 WOLFEDAl.E ROAD
MISSISSAUGA, ONTARIO
CANADA
PHONE (416) 270-0096
INSTRUCTIONS FOR OPERATION OP THE
RADEM VLF-EM RECEIVER
(1) Transmitter Stations
The VLF Communication Broadcast stations are positioned throughout the world. At present, 12 of these stations broadcast steadily except for maintenance periods usually of 1/2 to 1/3 days per week. The RADEM receives any 1 o f these sitations with selection by means of a switch. The usable range of the stations varies widely with power and transmission conditions but is usually between 1000 and 5000 miles. Two types of signals are broadcast "keyed" (on and off) and "frequency shift" (FM). Frequency shift provides a steady signal and is most suitable for Field Strength measurements, When a "Keyed" signal is used the receiver must be switched to the keyed signal "K" position for Field Strength Measurements.
A station should be selected that is located in the same direction as the regional strike. If in doubt of the geological strike two orthogonal stations should be read.
(2) Field Measurements
(a) Dip Angle of Resultant Field
Technically the angle in degrees, from the horizontal, of the major axis of the polarization ellipse. This is the easiest measurement to make since it is not dependent on changes in signal strength. The dip angle measurement detects a conductor from a considerable distance - from several hundred to several thousand feet. Direct plotting of the dip angles often does not clearly define the shape or position of the conductor. If strong regional effects occur the conductor may not produce a cross-over and may be defined only by a sharp variation in dip angles.
Two methods are available to overcome this defect in the dip angle measurement: (1) Field Strength measurement and (2) treatment of the Dip Angle data by means of a simple process deve loped by D. C. Fraser and described in Geophysics Vol. 34, #6, December 1969.
' ,Field Strength Measurements
These measurements do not detect the conductor until they are almost above it. Thus they are independent of regional trends and accurately define the shape and boundries of the conductor. This is simply achieved by contouring the Field Strength readings. Either the Resultant Field Strength or Horizontal Component of the Field Strength are measured, usually the latter, since it is easier to read.
The Field Strength of a VLF station varies with time thus a base station must be established and drift corrections applied as in a magnetic survey. Drift is particularly rapid during sun rise and sunset (50 % per hour) and reading is not advised during this period. The primary base station is usually located in a non conductive area where the dip angle is near "O" and the out-of-phase signal is also "O" - the Field Strength is set at 100 at this station and this is the Normal Field Strength standard for the survey.
(c) "Out-of-Phase" Field Strength Measurement
This is in effect the out of phase component perpendicular in direction to the resultant field. The measurement is without sign and is sensitive to very low orders of conductivity. It is simply the minimum reading of the Field Strength meter obtained when reading the Dip Angle. It is expressed in terms of percent of the normal Field Strength. It is not usually recorded unless very low orders of conductivity are of interest.
FIELD PROCEDURE:\
(1) Make sure the "Normal" - "K" switch is in the normal position.
(2) Hold the RADEM with the meter faces horizontal. Rotate the instrument in a horizontal plane, by moving the body until a null is observed on the Field Strength meter. This aligns the base of the instrument in the direction of the VLF field and the operator will be facing in the direction of the transmitting station.
(3) Raise the instrument such that the meter faces are vertical and rock it back and forth until a minimum is obtained on the Field Strength meter (switch on 0-300 scale). This minimum is the"0ut-of- Phase" reading. Holding the instrument at the minimum position read the inclinometer for the Dip Angle reading. Note that the arrow through the "o" of Crone points towards the conductor. If this is north then the inclinometer reads 17 0 N and the conductor is towards the north. This convention leaves no doubt as to where the conductor is located. The operator must be able to recognize between a true cross-over and a false cross-over and this convention is established to help simplify this matter.
- 3 -
(4) For a Horizontal Field Strength measurement hold the meter face horizontal and rotate this instrument in a horizontal plane until a maximum reading is obtained. This will be approximately in a direction at right angles to the operator. For a Resultant Field Strength measurement - this is the maximum Field Strength reading obtainable - and is obtained by holding the RADEM at right angles to the operator and inclined at the same angle as the dip angle.
(5) For a Field Strength reading with a "Keyed" VLF signal move the "Normal" - "K" switch to the "K" position. It must be returned to the "Normal" position for the iip angle measurement.
Since the Field Strength varies with time this reading must be tied to a base station with drift corrections applied similar to a magnetometer survey. If possible the primary base station should be established in a non-conductive area where the dip angle is near "O" with out of phase near "O" and where the volume control is adjusted such that the Field Strength reading is "100".
EXAMPLE OF FIELD SHEET
Station L 6+OOW
Out of Phase-%
Dip Angle Degrees Reading
Field Strength Time Drift Corr. Remarks
10N-Base10+50HUN11+50N12N12+50N13N13+50N14 N14+50NXlON-Base
22O O O 4 6 6 O O
O O2N6N
12N22N20N8NIS
12S
10010099
101102118185263247164
114
:00.02.04.06.08.10.12.14.17.20
00-1-1— o—2-2— -i-3-4
10010098
100100116187260245162
Lake Lake
Road
X'over
TRANSMITTER STATION SHUT DOWN TIMETABLE
MondayTuesdayWednesdayThursdayFriday
8:12:7:
11:- 9:
0000000000
a.a.a.a.a.
m.m.m.m.m.
tototototo
25171
* t
B *
4*
* t
**
0000000000
p.p.P'p.p.
mmmmm
*
9
t
*
*
10:10 -14 100
(All times Eastern Standard)
Annapolis, Maryland HawaiiBalboa, Panama Seattle, Washington Cutler, Maine
BATTERIES
For units up to ft10O - 2 of 9 volt batteries required. For units above #100 - l only battery is required but plugs for 2 batteries are supplied for cold weather operation.
Ministry*
{j|jj!jces ^F
Report of Work(Geophysical. Geological. Geochemical and Expenditures)
3IM13NE0029 2.5495 SKEAD
The Mir.900
Type of Survey(s)
Electromagnetic MagnetometerClaim Holder(s)
Lucien LacassaSurvey Company Survey Oatei
Col ex Explorations Ino. Day wfiName and Address of Author (of Geo-Technical report)
Township or Area
SkeadProspector's Licence No.
K- 182 34(linecuttlng to office)
| 81 Day 2io. | 83
'
Total Miles of line Cut
Special Provisions Credits RequestedInstruction*
For first survey:Enter 40 days. (This includes line cutting)
For each additional survey: using the same grid:
Enter 20 days (for each)
Geophysical
- Electromagnetic
- Magnetometer
- Radiometric*
- Other
Geological
Geochemical
Dayt per Claim
20
20i *
Man DaysInstructions
Complete reverse side and enter total (s) here
Geophysical
- Electromagnetic
- Magnetometer
- Radiometric
- Other
Geological
3 IGeochemical
Days per Claim
Airborne Credits
Note: Special provisions credits do not apply to Airborne Surveys.
-Electromagnetic
Magnetometer
Radiometric
Expenditures (excludes power stripping)
Days per Claim
Type of Work Performed
Performed on Claim(s)
Calculation of Expenditure Days Credit*
Total Expenditures
|s *hs|Total
Days Credits
1Instructions
Total Days Credits may be apportioned at the claim holder's choice. Enter number of days credits per claim selected In columns at right.
Report CompletedDate of Report
Feb. 9/83________Certification Verifying Report of Work
iolderor Agcnf (Signature)
Mining Claims Traversed (List in numerical sequence)
7 TdYal number of mining claims covered by this report of work. ______i Mining Redqr&er
l hereby certify that l have a personal and intimate knowledge of the facts set forth in U'e Report of Work annexed hereto, having performed the work or witnessed same during and/or after its completion and the annexed report is true.
Name and Postal Address of Penon Certifying
R.A. MacGregor, 134 Palace Dr. S..S. Mar J g f ^"- J .Date
Teb. 9/83Cer tifjed b V^( S i 8 na t u re)rUJiedby:
1362 (81/2)
Ministry ol
Ontarj
Report of Work(Geophysical, Geological, Geochemical and Expenditures)
("*t
REPORT SK-l
The Mining Act
Instructions: Please type or print.- H number of mining ci a i m* tiuvtuto
exceeds space on this form, attach a list.Noti: Only days credits calculated in t ho
"Expenditures" section may be enteredIn the "Expend. Days Cr." columns.
- Do not use shaded areas below.Type of Survey(s)
E le ct romagne tio MagnetometerClaim Holder(s)
Superior Northwest Inc.Survey Company Survey C
Colex Explorations Inc. o*y l
Township or Area
Skead{Prospector's Licence No.| T-626
tates (llnteunlng to office)
4. \ "611 Day J Mj. | ^8-3
Total Miles of lin* Cut
Name and Address of Author (of Geo-Technlcel report)R. A. MaoGregor, 134 Palace Dr* , Sault Ste* Marie, Ontario
Special Provisions Credits RequestedInstruction!
For first survey:
Enter 40 days. (This includes line cutting)
For each additional survey: using the same grid:
Enter 20 days (for each)
Geophysical
- Electromagnetic
- Magnetometer
- Radiometric i
- Other
Geological
Geochemical
Days per Claim
20
Man DaysInstructions
Complete reverse side and enter total (s) here
Geophysical
- Electromagnetic
- Magnetometer
- Radio-metric
- Other
Geological3 3
Geochemical
Days per Claim
Airborne Credits
Note: Special provisionscredits do not apply - to Airborne Surveys.
Electromagnetic
Magnetometer
Radiometric
Days per Claim
Expenditures (excludes power stripping)Type of Work Performed
Performed on Claim(s)
Calculation of Expenditure Days Credits
Total Expenditures
S 4- 1
Instructions Total Days Credits may be apportioned c choice. Enter number of days credits per in columns at right.
Total Days Credits
B . ^
t the claim holder's claim selected
Report CompletedDate of Report
Feb. 9/83or AgeXrXSignature)
Certification Verifying Report of Work !/
Mining Claims Traversed (List in numerical sequence)
For Office Use Only /^Total Days Cr Recorded
3*0
late Recorded l
Mtt^-Ui'ykDate Approved as Recorded
Total number of mining claims covered by this report of work.
Mining Recorder!
ReBiOnal/Brancfiuirector
l hereby certify that l have a personal and intimate knowledge of the facts set forth in the Report of Work annexed hereto, having perfom-e-d in; i-,ork or witnessed same during and/or after its completion and the annexed report is true.
Name and Postal Address of Person Certifying
R.A. MacGregor, 134 Palace Dr., Sault Ste Marie, OntarioDate.Certifled.- -.Feb. 9/83
Cerjtfifid tu^iS gneturn?
1362 (81/2)
/J^5\ Ministry ot Technical Assessi1 TT 1 Natural ,., , ~ ^ yVJ Resources Work CreditsOntaJfc
nnent v F'ie 2*1495
Date Mining Recorder t Report of1983 08 16 workfio.55 A 56
Recorded Holder LUCIEN LACASSE
Township or Area ^^ ̂ ^
Type of survey and number of Assessment days credit per claim
Geophysical PflElerttrnmagnntir tV days
Rndinmfttrir , days
IncHucoH pnlnriTptinn . ,. . days
Other riays
Section 77 (19) See "Mining Claims Assessed" column
Gfinlngir.al riays
Rerv.hftmiral days
Man days D Airborne D
Special provision G Ground H
[D Credits have been reduced because of partial coverage of claims.
D Credits have been reduced because of corrections to work dates and figures of applicant.
Mining Claims Assessed
For Electromagnetic only
L 561731 to 52 1ncl 578348 to 55 1ncl
For Magnetometer only:
L 561792 to 36 1ncl 578348
Special credits under section 77 (16) for the following mining claims
5 days credit, magnetometer:
L 561731 578349
No credits have been allowed for the following mining claims
LJ not sufficiently covered by the survey 1 _ 1
For magnetometer only:
L 561737 to 52 1ncl 578350 to 55 1ncl
t.
Insufficient technical data filed
The Mining Recorder may reduce the above credits if necessary in order that the total number of approved assessment days recorded on each claim does not exceed the maximum allowed as follows: Geophysical BO; Geological 40; Geochemical 40; Section 77(19) 60:
828 (83/6)
Ontario
Ministry ofNaturalResources 8-3
Your file:
1983 08 16 Ourfile: 2 .5:495
Mining RecorderMinistry of Natural Resources4 Government Road EastP.O. Box 984Kirkland Lake, OntarioP2N 1A2
Dear Sir:
Enclosed are two copies of a Notice of Intent with statements listing a reduced rate of assessment work credits to be allowed for a technical survey. Please forward one copy to the recorded holder of the claims and retain the other. In approximately fifteen days from the above date, a final letter of approval of these credits will be sent to you. On receipt of the approval letter, you may then change the work entries on the claim record sheets.
For further information, if required, please contact Mr. F.W. Matthews at 416/965-1380.
Yours very truly,
E.F. AndersonDirectorLand Management Branch
Whitney Block, Room 6450Queen's ParkToronto, OntarioM7A 1W3Phone: 416/965-1316
R. P1chette:sc
Ends:
cc: Superior Northwest IncSault Ste Marie, Ontario CC!
cc: Mr. R.A MacGregorSault Ste. Marie, Ontario
cc: G.H. FergusonMining S Lands Commissioner Toronto, Ontario
845
Exploration Incorporated Palace Drive
Sault Ste. Marie, Ontario P6B 5H5
Ministry ofNaturalResources
Notice of Intent
for Technical ReportsOntario
1983 08 16
2.5495
An examination of your survey report indicates that the requirements of The Ontario Mining Act have not been fully met to warrant maximum assessment work credits. This notice is merely a warning that you will not be allowed the number of assessment work days credits that you expected and also that in approximately 15 days from the above date, the mining recorder will be authorized to change the entries on his record sheets to agree with the enclosed statement. Please note that until such time as the recorder actually changes the entry on the record sheet, the status of the claim remains unchanged.
If you are of the opinion that these changes by the mining recorder will jeopardize your claims, you may during the next fifteen days apply to the Mining and Lands Commissioner for an extension of time. Abstracts should be sent with your application.
If the reduced rate of credits does not jeopardize the status of the claims then you need not seek relief from the Mining and Lands Commissioner and this Notice of Intent may be disregarded.
If your survey was submitted and assessed under the "Special Provision-Performance and Coverage" method and you are of the opinion that a re-appraisal under the "Man-days" method would result in the approval of a greater number of days credit per claim, you may, within the said fifteen day period, submit assessment work breakdowns listing the employees names, addresses and the dates and hours they worked. The new work breakdowns should be submitted direct to the Lands Management Branch, Toronto. The report will be re-assessed and a new statement of credits based on actual days worked will be issued.
846 (82/5)
Ministryof GeotechnicalResources Report
omario Approval
File
Mining Lands Comments
To: Geophysics
Comment*
.pproved [~] Wish to see again with correctionsSignature
To: Geology - Expenditures
Comments
|~J Approved |~| Wish to see again with corrections
D
Date Signature
To: Geochemistry
Comments
L
f] Approved | | Wish to see again with correctionsDate Signature
To: Mining Lands Section, Room 6462, Whitney Block. (Tel: 5-1380)
1593 ( 81/10)
1983 04 29
55 4 56
2.5495
Mining RecorderMinistry of Natural Resources4 Government Road EastP.O. Box 984Kirkland Lake, OntarioP2N 1A2
Dear Sir:
We have received the reports and maps for a Geophysical (Electromagnetic and Magnetometer) Survey submitted under Special Provisions (credit for Performance and Coverage) on Mining Claims L 561731 to 52 Inclusive and 578348 to 55 Inclusive In the Township of Skead.
This material will be examined and assessed and a statement of assessment work credits will be Issued.
Yours very truly,
E.F. AndersonDirectorLand Management Branch
Whitney Block, Room 6450Queen's ParkToronto, OntarioM7A 1W3Phone: 416/965-1380
A. Barr:se
cc: Luden LacasseLarder Lake, Ontario
cc: Superior Northwest Inc Sault Ste. Marie, Ontario Attn: Mr. R.A. MacGregor.
1983 09 09 2.5495
Mining RecorderMinistry of Natural Resources4 Government Road FastP.O. Box 984Kirkland Lake, OntarioP2N 1A2
Dear Sir:
RK: Geophysical (Electromagnetic i Magnetometer) Survey on Mining Claims L 561731 to 52 Inclusive and 578348 to BS Inclusive 1n the Township of Skead.
Tho Geophysical (Electromagnetic b Magnetometer) Survey assessment work credits as listed with my Notice of Intent dated August 16, 1983 have been approved as of the above date.
Please Inform the recorded holder of these mining claims and so Indicate on your records.
Yours very truly,
E.F. AndersonDirectorLend Management Branch
Whitney Block, Room 6450Queen's ParkToronto, OntarioH7A 1W3Phone: 41G/965-131U)
R. P1chette:sc
cc: Superior Northwest Ine Sault Ste. Marie, Ontario
cc: Colfcx Exploration Incorporated Sault Ste. Marie, Ontario
Mr. R. A. MacGregorSault Ste. Marie, Ontario
cc: Resident GeologistSault Ste. Marie, Ontario
Ontario
Ministry of Natural Resources
GEOPHYSICAL - GEOLOGICAL - GEOCHEMICAL TECHNICAL DATA STATEMENT
File.
TO BE A1TACHED AS AN APPENDIX TO TECHNICAL REPORTFACTS SHOWN HERE NEED NOT BE REPEATED IN REPORT
TECHNICAL REPORT MUST CONTAIN INTERPRETATION, CONCLUSIONS ETC.
Type of Survey(s) MAGMEIQHETim-AND VLF-EM
Z OW V) P
IK O
Township or Area -
Claim Holder(s)
Skead Township
Lucien LacsBsoSurvey Company ^ ,.Author of Report .
Address of Author ..
Covering Dates of Surv
Total Miles of Line Cu
Colex Explorations Inc.R. \ r MacGragor134 Palace Dr, B . B. Marie
cy June 19 81- February 9, 1983(linecutting to office)
l .......... __ -......-^
SPECIAL PROVISIONS DAYS CREDITS REQUESTED r.™K,,.;,,.i "" daim
ENTER 40 days (inc line cutting) for first survey.
ENTER 20 days for additional survey usi same grid.
--klrrtrnmagnrtir 20ludcs
- Mapnrtnmpter /O
-Radiometric.each -Other
"g Rrolngiral
Geor.hemiral.
AIRBORNE CREDITS (Special provision credits do not apply to airborne surveys)
Magnetometer
DATE:. Feb * 9/'
Res. Gcol.. .
File No. Type
Klprtromapnetic RaHiomptrir(enter days per claim) /y 7
f Author of Reportor'Xgent
i i Qualifications , '
Date Claim Holder
MINING CLAIMS TRAVERSED List numerically
P57?348 L561744(prefix) (number)
J** j y o *5 H * Ti5j51i4l^
ij j * v r n V JM M Jv J* i *L M
W7WU X.5W747
Iv57J835^ LS/5X74LB
1*7*35* L5C1749
I/r/5354. L5C17-50M7B555 VUG17U
iSfl731 L5C17S?L561732
L561733
1,561734
L5C1735 ,L561736 KECil^ -
L5C1737 FtBl61963
L56 1738 MJNJNQ LANDS SI,., C
L5^1?39
L561740
...mru............................................
L5C1743
TOTAL CI, A IMS
.sili *r
IM
iS3
837 (6/79)
GEOPHYSICAL TECHNICAL DATA
GROUND SURVEYS If more than one survey, specify data for each type of survey
Number of Stations 310____________________Number of Readings 310_____
Station interval_____100 feet________________Line spacing________400 feetf\
Profile scale _______L"—aContour interval _____10OQ gammas
Instrument ________Barringer GM-12?-^.^—yH Accuracy — Scale constant ____l ̂ JfilQITlS———..^——^—W^j Diurnal correction method ____Looping Method——.^5? Base Station check-in interval (Hours) 2 hourn or less
Base Station location and value ____Various! along basa line
rt Coil configuration X,O
W
Instrument _______PhoenJX-VLE^ 12—
Coil separation ———————— N/A
Accuracy ____________ ~ _ .-2.- __ . ___ - — ________ -- ______ _ .— __ — —————— ————— Method: Ci Fixed transmitter Q Shoot back d In line CD Parallel line
Frequency ______ —Annapol JUa Ma ry l and 4 21 ̂ 4 K Hg ) ———— —— —————————(specify V.L.F. station)
Parameters measured ___ . -Dip -Angle^of -tloe -Tesultaitt-f iold __ - ———— ———————^—
Scale constant _ . __ . ..
H
O
Corrections made
Base station value and location
Elevation accuracy _____ ....... _ . ___ —. __ .
Instrument
XQ
P
O
OD
X,
Method D Time Domain C J Frequency Domain
Parameters - On time __ .^ . __ .... __ ̂ ___________ .. __ Frequency _- Off time __ ,. _ . _________ — ___ ____ __ Range ^..,. .^ ........
-- Delay time _____________ . . ______ . _ .. -——
- Integration time ___ .... _ ..., ___ .. _ .. _ ,-, __ ...—
Power ____ .. ....... -.. .Electrode array Electrode spacing ___ — Type of electrode ___ .
og
ae
row
ieT
er
3u
,r v
*yC
OS
TE
LL
O
LA
KE
G
RID
SK
EA
D
TO
WN
SH
IP
SC
ALE
l"
* 400 '
J *
UJ
(O
M
UJ
CO *-
CM
UJ
CO
O)
CM
UJ
CO 10
UJ
CO o CNJ
UJ
CO
CM
i i
UJ
CO (P
UJ
CO o CM
UJ
CO
CM IO
UJ
CO t CM
UJ
CO CO to
UJ
CO o
UJ
CO CM in
UJ
CO (D m
UJ
CO
OD UJ
CO
CO
UJ
CO
UJ
CO CM
Scale
:
f in
cn
to
50 m
iles
B. L.
- UJ
CO GO
CO
UJ
CO oUJ
CO CD
10
UJ
CO
C0 in
UJ
CO CM
!0
UJ
CO o CDUJ
CO CO CM
UJ
CO *- CD
UJ
CO OJ
i i
i
UJ
CO
CD
CD
31M
13N
Eaa29
2.5
43
5
SK
EA
D2
00
UJ
CO
CD
j___
_j_
___
L.
LU O)
j__
__
l__
__
L.
UJ
CO ^r 00
J____J____L.
UJ
CO CD
CO
UJ
CO CM
O)
j__
__
t J^
B.
L - 2
UJ
CO rg
O)
UJ
CO
CD
CO
UJ
CO * CO
VL F
-EM
S
UR
VE
Y
CO
ST
EL
LO
L
AK
E
GR
I D
*S
KE
AD
T
OW
NS
HIP
SC
AL
E
l"*
400 '
INS
TR
UM
EN
T:
PH
EO
NIX
V
LF
'
2
ST
AT
ION
* A
NN
AP
OL
IS,
MA
RY
LA
ND
(2
1.4
KH
z)
o c - O
u a
T
7
Sca
le:
l in
ch
to
S
Om
ilss
•- o
Id
(O 00
GO
Ui
CO ^f OD31M13NEe029 2.5495 SKEAD
210