Route 7 Corridor Projects
Fairfax County Transportation Advisory Commission
April 15, 2014
Leonard (Bud) Siegel Jr., PEVirginia Department of Transportation
Presentation Overview
Route 7 Corridor General Remarks
Three Active Projects:• Rt. 7 Improvements (Rolling Holly Dr. – Reston Ave.)• Rt. 7 Bridge Rehab/Capacity Improvement (over DTR)• Rt. 7 Improvements (Reston Ave. – Jarrett Valley Dr.)
Questions & Answers
2
3
Rt. 7 ImprovementsRolling Holly Dr. – Reston Ave.
Rt. 7 ImprovementsRolling Holly Dr. – Reston Ave.
Status: In Construction
Schedule:• May 23, 2013: Start of Construction • Nov. 12, 2015: Substantial Completion • Dec. 16, 2015: Final Completion
Cost:
4
Phase Cost
Engineering (PE) $5.8M
Property Rights (ROW) & Utilities $3.6M
Construction $24.9M
Total $34.3M
Rt. 7 Bridge Rehab/Capacity Improvement over
Dulles Toll Road (DTR)
5
Rt. 7 Bridge Rehab/Capacity Improvement over
Dulles Toll Road (DTR)
Status: Preparing for Design/Build (D/B) Delivery
Schedule:• Feb. 20, 2014: Public Hearing• May 2014: Advertise D/B RFQ• Aug. 2014: Advertise D/B RFP
Cost:
6
Estimated Costs
Engineering $1.7M
Property Rights (ROW) & Utilities $0.6M
Construction $32.1M
Total $34.4M
7
Rt. 7 Improvements (Reston Ave. – Jarrett Valley Dr.)
Rt. 7 ImprovementsReston Ave. - Jarrett Valley Dr.
Schedule:• Nov. 6, 2013: Citizen Information Meeting• Late 2014/Early 2015: Public Hearing
Cost:
8
Estimated Costs
Engineering $30M
Property Rights (ROW) & Utilities $50M
Construction $220M
Total $300M
Thank You!
Questions & Answers