Page 1: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

  

  

Capacity Study Brochure   

Rosemary Hills Elementary School Classroom Addition 

   

Prepared for Montgomery County Board of Education   October 2011  

               

JK architects + associates, Inc.                                                                         

Page 2: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                                               Gaithersburg, Maryland 

 ROSEMARY HILLS ELEMENTARY SCHOOL 

CAPACITY STUDY OCTOBER 2011 

  

 SECTION                                PAGE NO.                    

I. CAPACITY STUDY PARTICIPANTS  1 II. SUMMARY  2 III. OPTION 1  3 IV. OPTION 2  7 V. OPTION 3  11 VI. SUMMARY TABLE AND COST COMPARISON  15 

   VII. APPENDIX A:  PROPOSED CONSTRUCTION SEQUENCING  A‐1 VIII. APPENDIX B:  ALL SCHEMES “PROS” & “CONS”  B‐1 IX. APPENDIX C:  SQUARE FOOT SUMMARY  C‐1 X. APPENDIX D:  EDUCATIONAL SPECIFICATIONS  D‐1 

 

Page 3: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                          1                                               Gaithersburg, Maryland 

I. CAPACITY STUDY PARTICIPANTS     

This capacity study was conducted for Montgomery County Public Schools (MCPS) by the architectural firm  JK architects + associates, Inc.  Rosemary Hills Elementary School is located at 2111 Porter Road, Silver Spring, Maryland,  and is part of the Bethesda‐Chevy Chase Cluster.  The capacity study of work was performed under the direction of the  MCPS Department of Facilities Management, Division of Construction.  

CAPACITY STUDY PARTICIPANTS             

Mr. Ralph Viggiano  RHES Principal Ms. Leslie Zimmerman  RHES Assistant Principal Ms. Miranda Bradley   MCPS/ RHES Mrs. Maureen Raines  MCPS/RHES Mrs. Jennifer Williams  Wonders Childcare Ms. Asanki Abeyratne  Wonders childcare Ms. Carolyn Greis  RHES PTA Representative Mr. Mike Shpur  MCPS/Division of Construction Ms. Julie Morris  MCPS/Division of Long‐Range Planning Mr. Saeyin Oh  MCPS/ Division of Construction Mr. Ray Marhamati  MCPS/ Division of Construction Ms. Lori Skolnick  RHES Kindergarten Teacher Mr. Chuck Beard  Silver Spring Team Benchmarks Mr. Michael Avant  YMCA Youth & Family Services Ms. Jeanne Johnson  YMCA Benchmarks Mrs. Isabel Ochoa‐Navas  YMCA Benchmarks Mrs. Florinda Sanchez  YMCA Benchmarks Mrs. Karen M. White  Benchmarks Program Mrs. Ruth Estrada  Benchmarks Program Mr. Olexa Horbachevsky  Parent Mr. Jonathan Rains  Parent  Ms. Sonia Suter  Parent Mr. Ed Kravzc  Parent Ms. Theresa Valencia  Parent Mrs. Debbie Parchment  Parent Mrs. Mona Lisa Dasbach  Neighbor Mr. Joseph Dasbach  Neighbor 

Page 4: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                          2                                               Gaithersburg, Maryland 

II. SUMMARY  

Rosemary Hills Elementary School (RHES)  in Bethesda‐Chevy Chase cluster serves Pre‐K through grade 2.   The original school structure was completed in 1956.  A classroom addition was constructed in 1961.   In 1973, a gymnasium addition was added on the east side of the building.  The latest addition was completed in 1987, which included an addition to the boiler room on the west side and classroom addition on the northeast side connecting to the gymnasium addition and to the original building.  The existing classrooms provide for a program capacity of 477 students.  The Capacity Study process for RHES included a series of five meetings in 2010:  February 18th, March 4th, March 18th, April 8th, and April 29th.  Upon the conclusion of the fifth and final meeting, it was determined that Option 1 will integrate best with the existing conditions of  the site and existing  floor plan  layout.    It meets all  requirements of  the Educational Specifications,  to bring the school up to a capacity of 632 by adding 6 classrooms, a dual purpose room, and support spaces.  As an add‐alternate, the building will also  include a classroom dedicated  to  the Benchmarks program, which  is currently  located  in a relocatable classroom building on site.  The superintendent released the recommended FY2013‐2018 CIP on October 28, 2011 with the following  information:   RHES has been assessed  for modernization and has a completion date of  January 2021 with planning scheduled to begin  in 2015.  The  addition  is  scheduled  to  open  in  fall  2015.    The  schematic  design  of  the  addition  will  include  a  master  planned modernization.  In these meetings, a site study was explored to add more parking spaces to the site, which currently has 58 spaces.    It was determined that an additional 16 parking spaces could be achieved on site without major disturbance to any existing trees on site and on adjacent residential properties. 

     

Page 5: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                          3                                               Gaithersburg, Maryland 

III. OPTION 1  

Option 1 provides the program spaces in a two‐story building addition located on the northwest side of the existing building, adjacent to the existing multi‐purpose room and an existing classroom that will be converted  into a reading room.   The new addition  will  connect  to  the  existing  building  through  a  new  proposed  corridor.    This  option  will  also  include  the  same reconfiguration of a portion of the existing west parking lot area as for Option 3.     Existing Gross Square Footage:                                70,541gsf  Renovated Existing Square Footage:                         1,000gsf New Addition Square Footage:                                16,460gsf Total New and Renovated Square Footage:          17,460gsf  Total New and Existing Square Footage:                87,001gsf  Estimated Building Construction Cost:                 $3,852,000 Estimated Site Construction Cost:                            $868,000 Estimated Total Construction Cost:                      $4,720,000     

    

Page 6: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                          4                                               Gaithersburg, Maryland 

DESCRIPTION OF OPTION 1    

   

Page 7: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                          5                                               Gaithersburg, Maryland 

DESCRIPTION OF OPTION 1                       

Page 8: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                          6                                               Gaithersburg, Maryland 

DESCRIPTION OF OPTION 1     

   

Page 9: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                          7                                               Gaithersburg, Maryland 

IV. OPTION 2  

Option 2 provides the program spaces  in a two‐story building addition  located on the southeast side of the existing building, extending along  the south exterior  face of  the gymnasium and connecting  to  the existing building  through a new proposed corridor.  This option will include a reconfiguration of a portion of the existing west parking lot area.     Existing Gross Square Footage:                                70,541gsf  Renovated Existing Square Footage:                                0gsf New Addition Square Footage:                                14,943gsf Total New and Renovated Square Footage:          14,943gsf  Total New and Existing Square Footage:                85,484gsf  Estimated Building Construction Cost:                $3,154,000 Estimated Site Construction Cost:                           $788,000 Estimated Total Construction Cost:                     $3,942,000       

Page 10: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                          8                                               Gaithersburg, Maryland 

DESCRIPTION OF OPTION 2     

Page 11: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                          9                                               Gaithersburg, Maryland 

DESCRIPTION OF OPTION 2   

   

Page 12: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                          10                                               Gaithersburg, Maryland 

DESCRIPTION OF OPTION 2   

    

Page 13: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                          11                                               Gaithersburg, Maryland 

V. OPTION 3  

Option 3 provides  the program spaces  in  the  form of one‐story building additions  located on  the east and west side of  the existing building.  The addition on the east side will extend along the south exterior face of the gymnasium and connect to the existing building through a new proposed corridor.  The addition on the west side will connect to a proposed corridor adjacent to the existing multi‐purpose room.  An existing classroom located on the west side will be converted into a reading room. This option will also include a reconfiguration of a portion of the existing west parking lot area.     Existing Gross Square Footage:                                70,541gsf  Renovated Existing Square Footage:                         1,000gsf New Addition Square Footage:                                15,205gsf Total New and Renovated Square Footage:          16,205gsf  Total New and Existing Square Footage:                85,746gsf  Estimated Building Construction Cost:                $3,587,000 Estimated Site Construction Cost:                           $802,000 Estimated Total Construction Cost:                     $4,389,000          

Page 14: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                          12                                               Gaithersburg, Maryland 

DESCRIPTION OF OPTION 3         

Page 15: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                          13                                               Gaithersburg, Maryland 

DESCRIPTION OF OPTION 3    

Page 16: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                          14                                               Gaithersburg, Maryland 

DESCRIPTION OF OPTION 3  

   

   

Page 17: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                          15                                               Gaithersburg, Maryland 

VI. SUMMARY TABLE AND COST COMPARISON  Gross Square Footage:         OPTION 1 (Preferred)        OPTION 2        OPTION 3 Existing                                             70,541                               70,541                70,541New Construction                                           16,460                         14,943                    15,205Modernization Renovation                                             1,000                 1,000Demolition (Total)   Existing to Remain                                    69,541                              70,541               69,541Total Gross Square Feet                                  87,001                                85,484                  85,746   Total Construction Cost  $                                             4,720,000  $                              3,942,000  $                                4,389,000

    PDF Feasibility Study Cost Outline (000’s)  

Construction Cost Estimate  $                                          4,720Planning Cost  $                                             395Contingency and Related Costs  $                                             421Future and Equipment  $                                             170   Totals  $                                          5,706

  The cost estimate in this feasibility study is based on current construction market conditions for both building and site.  The estimates will be revised to reflect market conditions and prevailing construction costs when the project is included in the Capital Improvements Program request for architectural and construction funding.

Page 18: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                         A‐1                                               Gaithersburg, Maryland 

VII. APPENDIX A:     PROPOSED CONSTRUCTION SEQUENCING  

OPTION 1 OPTION 2 OPTION 3 PHASE I (WEST SIDE & EAST SIDE) – PRIOR TO START OF CONSTRUCTION DEMO 1. REMOVE EXISTING CLASSROOM PORTABLE BUILDINGS (NIC). 2. RELOCATED EXISTING BENCHMARK/ COMMUNITY CENTER

PORTABLE TO SOUTHEAST CORNER OF SITE (TEMPORARY DURING CONSTRUCTION) (NIC).

NEW 1. PROVIDE FOUR NEW PORTABLE CLASROOMS ON EAST SIDE

(TEMPORARY DURING CONTRUCTION) (NIC); REMOVE AFTER COMPLETION OF ALL CONSTRUCTION.

2. NEW LOCATION OF EXISTING BENCHMARK/ COMMUNITY CENTER ON SOUTHEAST CORNER OF SITE (TEMPORARY DURING CONSTRUCTION).

PHASE II (WEST SIDE & EAST SIDE) – MAR. 2014 TO AUG. 2015 (OR EARLIER) DEMO 1. CUT & REMOVE PORTION OF EXISTING FENCE AND CONCRETE CURB

& SIDEWALK FOR TEMPORARY GRAVEL APRON/ ENTRANCE FOR TEMPORARY PARKING LOT TO BE USED DURING CONSTRUCTION.

2. REMOVE PORTIONS OF EXISTING WEST PARKING LOT. 3. RELOCATE EXISTING GENERATOR. 4. REMOVAL MODIFICATIONS WITHIN THE SCHOOL RELATED TO THE

NEW TWO STORY WEST CLASSROOM ADDITION (DURING SUMMER OF 2014).

NEW 1. PARKING (TEMPORARY DURING CONSTRUCTION). 2. NEW FENCE ENCLOSURE FOR EXISTING GENERATOR. 3. RECONFIGURE EXISTING PARKING LOT. 4. NEW RETAINING WALL. 5. BUILD NEW TWO STORY WEST CLASSROOM ADDITION. 6. NEW MODIFICATIONS WITHIN THE SCHOOL RELATED TO THE WEST

CLASSROOM ADDITION. 7. NEW SIDEWALKS AND LANSCAPING. PHASE II (WEST SIDE & EAST SIDE) – MAR. 2014 TO AUG. 2015 (OR EARLIER) DEMO 1. REMOVE PORTIONS OF EX. FRONT PARKING & ENTRY DRIVE (NIC). NEW 1. RENOVATE PORTIONS OF EX. FRONT PARKING & ENTRY DRIVE (NIC). 

PHASE I (EAST SIDE) – MAR. 2014 TO MAY 2015 (OR EARLIER) DEMO 1. REMOVE THREE TREES. 2. RECONFIGURE EXISTING STORMWATER MANAGEMENT SYSTEM. 3. REGRADE FOR NEW ADDITION AND NEW SITEWORK. 4. REMOVAL MODIFICATIONS WITHIN THE SCHOOL RELATED TO THE

NEW TWO STORY EAST CLASSROOM ADDITION (DURING SUMMER OF 2014)

NEW 1. BUILD NEW TWO STORY EAST CLASSROOM ADDITION. 2. NEW GUARDRAIL AND LOW RETAINING WALL. 3. NEW SIDEWALKS AND STEPS. 4. NEW MODIFICATIONS WITHIN THE SCHOOL RELATED TO THE EAST

CLASROOM ADDITION (DURING SUMMER OF 2014). PHASE II (WEST SIDE) – DURING SUMMER OF 2015 DEMO 1. REMOVE EXISTING CLASSROOM PORTABLE BUILDINGS (NIC) (AFTER

COMPLETION OF NEW TWO STORY CLASSROOM ADDITION). 2. REMOVE PORTIONS OF EXISTING WEST PARKING LOT. 3. REMOVE PORTIONS OF EX. FRONT PARKING & ENTRY DRIVE (NIC). NEW 1. RECONFIGURE EXISTING PARKING LOT. 2. NEW SIDEWALK AND LANDSCAPING. 3. RENOVATE PORTIONS OF EX. FRONT PARKING & ENTRY DRIVE (NIC).

PHASE I (EAST SIDE) – MAR. 2014 TO NOV. 2014 (OR EARLIER) DEMO 1. REMOVE THREE TREES. 2. RECONFIGURE EXISTING STORMWATER MANAGEMENT SYSTEM. 3. REGRADE FOR NEW ADDITION. 4. REMOVAL MODIFICATIONS WITHIN THE SCHOOL RELATED TO THE

NEW ONE STORY EAST CLASSROOM ADDITION (DURING SUMMER OF 2014).

5. CUT & REMOVE PORTION OF EXISTING FENCE AND CONCRETE CURB & SIDEWALK FOR TEMPORARY GRAVEL APRON/ ENTRANCE FOR TEMPORARY PARKING LOT TO BE USED DURING CONSTRUCTION.

NEW 1. BUILD NEW ONE-STORY EAST CLASSROOM ADDITION. 2. NEW MODIFICATIONS WITHIN THE SCHOOL RELATED TO THE EAST

CLASSROOM ADDITION (DURING SUMMER OF 2014). 3. NEW GUARDRAIL AND LOW RETAINING WALL. 4. NEW SIDEWALKS AND STEPS. 5. PARKING (TEMPORARY DURING CONSTRUCTION OF PHASE II). PHASE II (WEST SIDE & EAST SIDE) – DEC. 2014 TO AUG. 2015 (OR EARLIER) DEMO 1. REMOVE EXISTING CLASSROOM PORTABLE BUILDINGS (NIC) (DURING WINTER BREAK OF 2014). 2. REMOVE AND RELOCATE EXISTING BENCHMARK/ COMMUNITY

CENTER PORTABLE TO EXISTING PAVED PLAY AREA ON EAST SIDE (TEMPORARY DURING CONSTRUCTION) (DURING WINTER BREAK OF 2014).

3. REMOVE PORTIONS OF EXISTING WEST PARKING LOT. 4. RELOCATE EXISTING GENERATOR. 5. REMOVALS WITHIN THE SCHOOL RELATED TO THE NEW ONE STORY

WEST CLASSROOM ADDITION (DURING SUMMER OF 2015). NEW 1. PROVIDE TWO NEW PORTABLE CLASSROOMS ON THE EAST SIDE

(NIC) (DURING WINTER BREAK OF 2014). 2. RECONFIGURE EXISTING PARKING LOT. 3. NEW FENCE ENCLOSURE FOR EXISTING GENERATOR. 4. NEW LOCATION OF EXISTING BENCHMARK/ COMMUNITY CENTER ON

THE EAST SIDE (TEMPORARY DURING CONSTRUCTION) (DURING WINTER BREAK OF 2014).

5. BUILD NEW ONE STORY WEST CLASSROOM ADDITION. 6. NEW MODIFICATIONS WITHIN THE SCHOOL RELATED TO THE WEST

CLASSROOM ADDITION (DURING SUMMER OF 2015). 7. NEW SIDEWALKS AND LANDSCAPING. 8. BASE BID: RELOCATE EXISTING BENCHMARK/ COMMUNITY CENTER TO WEST SIDE. PHASE III (WEST SIDE) – DURING SUMMER OF 2015 DEMO 1. REMOVE PORTIONS OF EX. FRONT PARKING & ENTRY DRIVE (NIC). NEW 1. RENOVATE PORTIONS OF EX. FRONT PARKING & ENTRY DRIVE (NIC).

Page 19: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                         B‐1                                               Gaithersburg, Maryland 

VIII. APPENDIX B:     ALL SCHEMES “PROS” & “CONS”  

SCHEME “PROS” “CONS”

OPT

ION

1

• BENCHMARK’S SPACE IS HIGHLY VISIBLE FROM PARKING LOT.

• LESS VISUAL IMPACT TO NEIGHBORHOOD THAN OPTION 2 & OPTION 3.

• LESS EXISTING LAND DISTURBANCE.

• FUTURE PORTABLES COULD BE ACCOMMODATED BETTER WITHOUT TAKING PAVED PLAY AREA.

• COMMUNITY CENTER BACK IN THE BUILDING, NO LONGER IN PORTABLE.

• MAINTAINS LESS DISRUPTIVE PATH FROM EXISTING MULTI-PURPOSE ROOM TO RECESS (WITHOUT HAVING TO GO THROUGH EX. SCHOOL PAST CLASSROOMS).

• PROVIDES THE MOST FLEXIBILITY FOR AESTHETICALLY BLENDING THE NEW ADDITION WITH THE MODERNIZATION OF THE EXISTING BUILDING.

• TWO STORY MASSING, DIFFERENT FROM THE EXISTING SCHOOL.

• REQUIRES NEW HANDICAPPED LIFT FOR HANDICAPPED ACCESS TO EXISTING SECOND GRADE WING.

• NEED TO RECONFIGURE THE GENERATOR ENCLOSURE AND GENERATORS.

• ADDITION IS FARTHEST FROM THE EXISTING PLAY AREAS.

• LESS PARKING SPACES THAN IN OPTION 2.

• NOISE ISSUE, SINCE WINDOWS OF SOME OF THE CLASSROOMS WOULD BE FACING THE EXISTING TRAIN TRACKS - ADDRESS THE NOISE.

• REMOTE ACCESS TO EXISTING PLAY AREAS.

• MORE FLOOR AREA COMPARED TO OPTION 2 & OPTION 3.

• FUTURE PORTABLES WOULD TAKE MUCH OF THE EX. PAVED PLAY AREA & WOULD REQUIRE RECONFIGURING OF EXISTING PLAYGROUND.

OPT

ION

• GOOD SITE ACCESS FOR CONSTRUCTION.

• SUBSTANTIAL INCREASE IN PARKING SPACES COMPARED TO OTHER SCHEMES.

• DO NOT HAVE TO RECONFIGURE THE GENERATOR ENCLOSURE & GENERATORS.

• DUAL- PURPOSE ROOM IS CLOSEST TO THE EXISTING ART ROOM & MUSIC ROOM .

• LESS EXISTING LAND DISTURBANCE.

• CAN PHASE THE REMOVAL OF EXISTING QUAD PORTABLE UNTIL COMPLETION OF CONSTRUCTION OF THE ADDITION.

• DO NOT HAVE TO RELOCATE TEMPORARY PORTABLE CLASSROOMS DURING CONSTRUCTION OF NEW CLASSROOM ADDITION.

• ONLY OPTION WHICH DOES NOT REQUIRE TEMPORARY PARKING DURING CONSTRUCTION.

• EXTREME DISTURBANCE TO SITE, REQUIRES SIGNIFICANT STORMWATER MANAGEMENT.

• TWO STORY MASSING, DIFFERENT FROM THE EXISTING SCHOOL.

• MASSING HAS THE GREATEST VISUAL IMPACT TO THE SURROUNDING NEIGHBORHOOD.

• REMOVAL OF MATURE EVERGREEN TREES.

• PROXIMITY TO BALL FIELDS - POTENTIAL DAMAGE FROM FOUL BALLS.

• RETAINS EXISTING BENCHMARK BUILDING (NO ADD ALTERNATE OPPORTUNITY FOR PROVIDING NEW BENCHMARK/ COMMUNITY CENTER SPACE WITHIN NEW ADDITION).

OPT

ION

• RETAINS THE ONE-STORY MASSING OF THE EXISTING SCHOOL - FRIENDLIER TO NEIGHBORHOOD.

• COMMUNITY CENTER BACK IN THE BUILDING, NO LONGER IN PORTABLE (ONLY IF ADD ALTERNATE #1 IS SELECTED).

• EXTREME CONSTRUCTION PHASING AND STAGING AREA CHALLENGE.

• FUNCTIONING OF NEW SPACES IS DIVIDED.

• MAJOR DISRUPTION TO DAILY SCHOOL ACTIVITIES DURING CONSTRUCTION.

• EXTREME DISTURBANCE TO SITE, REQUIRES SIGNIFICANT STORM WATER MANAGEMENT.

• PROXIMITY TO BALL FIELDS - POTENTIAL DAMAGE FROM FOUL BALLS.

• REQUIRES NEW HANDICAPPED LIFT FOR HANDICAPPED ACCESS TO EXISTING SECOND GRADE WING.

• REMOVAL OF MATURE EVERGREEN TREES.

• NEED TO RECONFIGURE THE GENERATOR ENCLOSURE AND GENERATORS.

• WEST WING HAS REMOTE ACCESS TO EXISTING PLAY AREAS.

• LESS PARKING SPACES THAN IN OPTION 2.

• NOISE ISSUE, SINCE WINDOWS OF SOME OF THE CLASSROOMS ON WEST WING WOULD BE FACING THE EXISTING TRAIN TRACKS.

• INCREASED DISTANCES FOR CIRCULATION WITHIN THE BUILDING.

• LIMITS OPTIONS FOR FUTURE MODERNIZATION.

Page 20: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                         C‐1                                               Gaithersburg, Maryland 

IX. APPENDIX C:     SQUARE FOOT SUMMARY  

 

                   

 

Page 21: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                         D‐ 1                                               Gaithersburg, Maryland 

X. APPENDIX D:     EDUCATIONAL SPECIFICATIONS  

   

Page 22: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                         D‐ 2                                               Gaithersburg, Maryland 

EDUCATIONAL SPECIFICATIONS (Continued)    

Page 23: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                         D‐ 3                                               Gaithersburg, Maryland 

EDUCATIONAL SPECIFICATIONS (Continued)                      

Page 24: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                         D‐ 4                                               Gaithersburg, Maryland 

EDUCATIONAL SPECIFICATIONS (Continued)                      

Page 25: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                         D‐ 5                                               Gaithersburg, Maryland 

EDUCATIONAL SPECIFICATIONS (Continued)                      

Page 26: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                         D‐ 6                                               Gaithersburg, Maryland 

EDUCATIONAL SPECIFICATIONS (Continued)                      

Page 27: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                         D‐ 7                                               Gaithersburg, Maryland 

EDUCATIONAL SPECIFICATIONS (Continued)                      

Page 28: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                         D‐ 8                                               Gaithersburg, Maryland 

EDUCATIONAL SPECIFICATIONS (Continued)                      

Page 29: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                         D‐ 9                                               Gaithersburg, Maryland 

EDUCATIONAL SPECIFICATIONS (Continued)                      

Page 30: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                         D‐ 10                                               Gaithersburg, Maryland 

EDUCATIONAL SPECIFICATIONS (Continued)                      

Page 31: Rosemary Hills Elementary School Classroom Addition · The Capacity Study process for RHES included a series of five meetings in 2010: February 18th, March 4th, March 18th, April

 

ROSEMARY HILLS ELEMENTARY SCHOOL                                                                                                                         JK architects + associates, Inc.                          Capacity Study                                                                                         D‐ 11                                               Gaithersburg, Maryland 

EDUCATIONAL SPECIFICATIONS (Continued)