Rooley Moor Wind Farm Chapter 7: Hydrology, … Report C532 Control of water pollution from...
Transcript of Rooley Moor Wind Farm Chapter 7: Hydrology, … Report C532 Control of water pollution from...
CPL PAGE i
Rooley Moor Wind Farm Environmental Statement
Rooley Moor Wind Farm
Chapter 7: Hydrology, Hydrogeology and Geology
CPL PAGE i
Rooley Moor Wind Farm Environmental Statement
7. Hydrology, Hydrogeology and Geology ..................................................................................................................................7-3
7.1 Introduction ..................................................................................................................................................................................7-3
7.2 Objectives ....................................................................................................................................................................................7-3
7.3 Statutory, Planning Policy, Legislation and General Guidance ....................................................................................................7-3
Statutory Planning Policy and Legislation ....................................................................................................................................7-3 7.3.1
General Guidance ........................................................................................................................................................................7-4 7.3.2
7.4 Consultation and Scoping ............................................................................................................................................................7-4
7.5 Methodology .................................................................................................................................................................................7-7
Baseline Determination ................................................................................................................................................................7-8 7.5.1
7.6 Baseline Conditions ...................................................................................................................................................................7-13
Study Area .................................................................................................................................................................................7-13 7.6.1
Climate and Topography ............................................................................................................................................................7-13 7.6.2
Statutory Designated Sites .........................................................................................................................................................7-13 7.6.3
Hydrology ...................................................................................................................................................................................7-14 7.6.4
Flood Risk ..................................................................................................................................................................................7-16 7.6.5
Geology and Peat ......................................................................................................................................................................7-18 7.6.6
Groundwater ..............................................................................................................................................................................7-20 7.6.7
Groundwater Dependent Terrestrial Ecosystems ......................................................................................................................7-21 7.6.8
Public Water Supplies and United Utilities Assets .....................................................................................................................7-23 7.6.9
Private Water Supplies (PWS) ...................................................................................................................................................7-24 7.6.10
7.7 Baseline Sensitivity ....................................................................................................................................................................7-25
Overall Surface Water Sensitivity ...............................................................................................................................................7-25 7.7.1
Overall Groundwater Sensitivity .................................................................................................................................................7-25 7.7.2
Overall Geology Sensitivity ........................................................................................................................................................7-25 7.7.3
7.8 Design Evolution ........................................................................................................................................................................7-26
7.9 Standard Practice Measures ......................................................................................................................................................7-26
Development of a Detailed Construction Method Statement (CMS) ..........................................................................................7-26 7.9.1
Development of a Construction Environmental Management Plan (CEMP) ..............................................................................7-26 7.9.2
Drainage Management Plan (DMP) ...........................................................................................................................................7-27 7.9.3
Water Quality Monitoring ............................................................................................................................................................7-27 7.9.4
Provision of an Environmental Clerk of Works (ECoW) .............................................................................................................7-28 7.9.5
7.10 Predicted Impacts ......................................................................................................................................................................7-28
Construction ...............................................................................................................................................................................7-28 7.10.1
Operation ...................................................................................................................................................................................7-33 7.10.2
Decommissioning .......................................................................................................................................................................7-35 7.10.3
7.11 Summary of Potential Impacts and Mitigation Measures ...........................................................................................................7-35
CPL PAGE ii
Rooley Moor Wind Farm Environmental Statement
7.12 Mitigation Measures ...................................................................................................................................................................7-41
Access Tracks ............................................................................................................................................................................7-41 7.12.1
Watercourse Crossings ..............................................................................................................................................................7-42 7.12.2
Wind Turbine Foundations and Hardstandings ..........................................................................................................................7-42 7.12.3
Substation Compound and Temporary Construction Compound ..............................................................................................7-43 7.12.4
Electric Cabling ..........................................................................................................................................................................7-43 7.12.5
Borrow Pits .................................................................................................................................................................................7-44 7.12.6
7.13 Residual Effects .........................................................................................................................................................................7-45
Construction ...............................................................................................................................................................................7-45 7.13.1
Operation ...................................................................................................................................................................................7-46 7.13.2
Decommissioning .......................................................................................................................................................................7-46 7.13.3
7.14 Cumulative Impacts ....................................................................................................................................................................7-46
7.15 Summary and Conclusions ........................................................................................................................................................7-48
Appendix 7.1: Private Water Supply Assessment
Appendix 7.2: Outline Peat Management Plan
Appendix 7.3: Peat Slide Risk Assessment
Appendix 7.4: Mining Risk Assessment
CPL PAGE 7-3
Rooley Moor Wind Farm Environmental Statement
7. Hydrology, Hydrogeology and Geology
7.1 Introduction
7.1. This chapter assesses potential impacts to identified hydrological, hydrogeological and geological and
receptors during the construction, operation and decommissioning of the development and outlines
mitigation measures required to reduce any identified potential impacts of the development.
7.2. Information provided within this chapter is based upon the results of a desk based study utilising
published resources, consultation with relevant stakeholders and statutory bodies, several site visits
and collected field data.
7.3. The chapter is primarily concerned with the Development Area (as described in Chapter 4:
Development Description, and shown in Figure 4.1 and land which is hydraulically connected to the
Development Area.
7.2 Objectives
7.4. Rooley Moor Wind Farm, and outlines mitigation measures required to control the predicted effects of
the Development. Potential effects to hydrology, hydrogeology and geology include:
Changes to drainage patterns;
Changes to flood risk;
Changes to the quality and/or quantity of surface water and groundwater;
Pollution of public water sources and/or private water supplies (PWS); and
Other changes to downstream watercourses including changes in erosion and deposition patterns.
7.3 Statutory, Planning Policy, Legislation and General Guidance
7.5. This assessment has been undertaken with regard to statutory and general guidance, and a range of
environmental legislation including the following:
Statutory Planning Policy and Legislation 7.3.1
EU Water Framework Directive (2000/60/EC);
Environmental Protection Act 1990;
Water Resource Act 1991;
Groundwater (England and Wales) Regulations 2009;
UK Water Quality (Water Supply) Regulations 2000 (amendment) Regulations 2007;
Freshwater Fish Directive (2006/44/EC);
Environment Act 1995;
Land Drainage Act 1991;
Environmental Damage (Prevention and Remediation) Regulations 2009;
Town and Country Planning Act 2012;
CPL PAGE 7-4
Rooley Moor Wind Farm Environmental Statement
Private Water Supply Regulations 2009;
Control of Pollution Act 1974; and
Contaminated Land (England) Regulations 2006.
General Guidance 7.3.2
National Planning Policy Framework, Department for Communities and Local Government (2012);
Environment Agency, Underground, Under Threat, Groundwater protection: policy and practice (GP3)
(2006);
Environment Agency, Piling and Penetrative Ground Improvement Methods on Land Affected by
Contamination: Guidance on Pollution Prevention (2001)
EA Pollution Prevention Guidance (PPG) Notes:
o PPG 1 General guide to the prevention of water pollution (2001);
o PPG 2 Above ground oil storage tanks (2004);
o PPG 3 Use and design of oil separators in surface water drainage systems (2006);
o PPG 5 Works in, near or liable to affect watercourses (2007);
o PPG 6 Working at construction and demolition sites (2003);
o PPG 21 Pollution incident response planning;
o PPG22 Incident Response – Dealing with Spills; and
o PPG23 Maintenance of Structures over Water.
CIRIA Report C532 Control of water pollution from construction sites (2001);
CIRIA Report C692 Environmental good practice on site (third edition) (2010); and
Construction Code of Practice for the Sustainable Use of Soils on Construction Sites (2009).
7.4 Consultation and Scoping
7.6. A summary of scoping and consultation responses in relation to this chapter is detailed in Table 7.1.
Copies of scoping responses received from the consultees can be found in Appendix 2.1.
Table 7.1 Scoping Responses
Authority Response Proposed Action
Environment
Agency (EA)
Flood Risk Assessment (FRA) should be
included.
FRA required – currently not included in
scope of works.
United
Utilities
Initial consultation highlighted concerns
around water quality both from construction
and long term running of the wind farm,
mainly related to colour and suspended
solids.
Water quality monitoring will be essential in
establishing a robust baseline for the
catchments around the wind farm. Peat
Majority of infrastructure to be located off
peat greater than 0.5m depth.
Coronation Power are working with UU and
have agreed that a joint approach to water
quality monitoring could support both the
development of the wind farm site and
assessment of ongoing peatland restoration
work being undertaken by UU. The
CPL PAGE 7-5
Rooley Moor Wind Farm Environmental Statement
Authority Response Proposed Action
discolouration of water supply is a key issue
for UU and presents an expensive on-going
problem to resolve. Any monitoring will need
to include for colour.
collaborative approach will look to share
data and rationalise monitoring and
sampling locations / regimes.
The Coal
Authority
Past coal mining activities and the presence
of surface coal resources should be
considered. This should take the form of a
risk assessment, together with mitigation
measures.
The location and stability of abandoned mine
entries should be considered and the extent
and stability of shallow mine workings,
outcropping coal seams, unrecorded mine
workings, minewater, hydrogeology and
mine gas should be considered.
Consider whether Coal Authority permission
is required to intersect, enter or disturb and
coal or coal workings during site
investigation or development work
If surface coal resources are present,
consider whether prior extraction of the
mineral resource is practicable and viable
Mining risk assessment has been
completed and is included as Appendix
7.4.
Lancashire
County
Council
The site is on Mineral Safeguarding Area
and survey work would need to prove peat
had been worked out and exhausted and
that any proposed development would not
damage the peat land resource.
A Mining Risk Assessment has been
completed and is included as Appendix
7.4.
A Peat Management Plan (PMP), included
as Appendix 7.2 demonstrates that the
proposed development will not result in any
removal of peat from the site and highlights
restoration proposals for excavated peat.
Natural
England Impacts of development on hydrology
together with environmental and erosion
protection
Application falls within a priority habitat,
blanket peat
Requirements for EIA for wind farms on
peat greater than 0.5m provided in
“Investigating the impacts of wind farm
development on peatlands in England:
Part 1 Final Report”
Scope for mitigation of adverse impacts
and opportunities for improved peatland
management to be addressed
Design of the wind farm layout has avoided
peat over 0.5m in depth where possible as
demonstrated by evidence presented in the
Peat Slide Risk Assessment (PSRA)
included as Appendix 7.3. The EIA
assessment contained within this chapter
includes assessment of risk to peatland
resources with respect to potential changes
in hydrogeological regimes, while Chapter
8: Ecology assesses risk to peatland
habitat and Chapter 15: Other Issues
assesses any loss of peat as a function of
the overall carbon balance assessment for
the site.
CPL PAGE 7-6
Rooley Moor Wind Farm Environmental Statement
Authority Response Proposed Action
Compensation for adverse effects may
be possible through peat restoration
measures in the form of habitat
management plans
Functional components of the peat
system as a whole which includes areas
of non-active bog as well as active bog
should be considered.
Impacts on local geological sites should
be considered
Opportunities will be sought in conjunction
with UU for restoring peatland habitat as
detailed in Section 8.10.2 of Chapter 8:
Ecology.
Geological and hydrologically dependant
SSSIs have been identified within the
baseline and assessment reporting of this
Chapter.
Greater
Manchester
Ecology Unit
Comprehensive peat depth and quality
surveys required to inform layout of
turbines and access tracks and mitigate
for damage to peat
Mapping of bare peat, bare mineral
ground and areas partially vegetated
from aerial photographs
Develop a water accumulation indicator
map and wetness index using LiDAR
data
Ground truthing mapping and field
assessment to identify likely causes of
degradation and most appropriate
methods of remediating or restoring
Full details of measures to be taken to
mitigate any possible damage to peat
Hydrological studies should consider
potentially damaging impacts of drying
parts through increased drainage
Particular issues include:
o Constructing tracks on peat and
mineral soils
o Construction of turbine and crane
foundations on peat and mineral soils
o Dealing with surplus peat
o Dealing with surplus mineral
material/soils
o Installing trenches for HV cables
o Stream/drain crossing to avoid scour
and erosion
Surveys of peat depth and quality of peat
have been undertaken to inform PSRA
reporting and are presented in Appendix
7.3.
Best practice and mitigation measures
outlined in Section 7.12 will ensure residual
risk to peat is not significant.
Rochdale Council Should be cross referenced with ecology
chapter in relation to peatland condition
Impact on water quality from peat
The EIA assessment contained within this
chapter includes assessment of risk to
peatland resources with respect to potential
changes in hydrogeological regimes, while
CPL PAGE 7-7
Rooley Moor Wind Farm Environmental Statement
Authority Response Proposed Action
oxidisation and increased turbidity should
be assessed
Definition of deep peat being of a depth
of 2m or greater is flawed.
Reference should be made to
“Investigating the impacts of windfarm
development on peatlands in England:
Part 1 Final Report”
Account to be taken of existing
development at Scout Moor and lessons
learned from disturbance of substrate.
Flood Risk Assessment will be necessary
Coal Authority should be consulted for
mining records. BGS can also provide
relevant detailed information.
Baseline assessment should cross
reference Minerals and Waste DPD’s
covering the PDA, in particular Minerals
Safeguarding Areas.
Chapter 8: Ecology assesses risk to
peatland habitat and Chapter 15: Other
Issues assesses any loss of peat as a
function of the overall carbon balance
assessment for the site.
Mining risk assessment has been
completed and is included as Appendix
7.4.
7.5 Methodology
7.7. This section outlines the methodology adopted to assess the effects impacts of the proposed
Development upon the local hydrological, hydrogeological, geological and peat environments.
7.8. The scope of the assessment is to identify:
Constraints on activities due to hydrology, hydrogeology, geology and peat;
Potential effects and risks associated with construction, operation and decommissioning activities that
can be controlled through best practice; and
The significance of residual effects.
7.9. Information provided within this chapter is based upon the results of a desk based study utilising
published resources, consultation with relevant stakeholders and statutory bodies and several site
visits during 2013 and 2014.
Table 7.2 Baseline Data Sources
Topic Source of data and information
Climate and
topography
Ordnance Survey mapping - Landranger Series (1:50,000)
Flood Estimation Handbook (FEH)
Surface water quality
and quantity
Rochdale Council and Rossendale Council
Environment Agency (EA)
United Utilities (UU)
Public water supplies, Rochdale Council and Rossendale Council
CPL PAGE 7-8
Rooley Moor Wind Farm Environmental Statement
Topic Source of data and information
Private water supplies
(PWS)
Property owners (information regarding private water supplies)
Fisheries Environment Agency (EA)
Groundwater
properties
Environment Agency (EA)
Abesser, C, Shand, P. & Ingram, J, 2005. Baseline Report Series 18. The
Millstone Grit of Northern England. British Geological Survey Commissioned
Report No. CR/05/015N.
BGS UK Hydrogeology Viewer Available online at
http://mapapps.bgs.ac.uk/hydrogeologymap/hydromap.html Last accessed 20th
March 2014.
Solid and drift geology BGS GeoIndex Onshore online mapping
Bedrock geology (scale 1:50,000)
Superficial deposits (scale 1:50,000)
Faults and other linear features (scale 1:50,000)
Abstractions and
discharges
Environment Agency (EA)
Rochdale Council and Rossendale Council
Baseline Determination 7.5.1
7.10. The methodology is based upon the collection of information from a wide variety of data sources
including published material and consultation with statutory bodies. Table 7.2 details the data sources
referred to throughout this assessment.
7.11. There are no relevant published guidelines or criteria for assessing and evaluating impacts on
hydrology, hydrogeology or geomorphology within the context of an EIA. This assessment is based on
a methodology derived from the Institute of Environmental Management and Assessment (IEMA)
guidance (2004) (Ref. 7-1). The methodology sets out a list of criteria for evaluating the environmental
impacts, as follows:
The type of impact (i.e. whether it is positive, negative, neutral or uncertain);
The policy importance of the resource under consideration on a scale of sensitivity (i.e. high, medium
or low) as defined within Table 7.3.
The magnitude of the impact in relation to the resource that has been evaluated, quantified using the
scale high, medium, low, or negligible defined within Table 7.4; and
The probability of the impact occurring based on the scale of certain, likely, unlikely, or rarely (Table
7.6 ).
Table 7.3 Definitions of Policy Importance and Sensitivity
Sensitivity Hydrological / hydrogeological / geological definition
High High environmental importance; international or national value including Ramsar sites;
Special Areas of Conservation (SAC); Special Protection Areas (SPAs); and Sites of
Special Scientific Interest (SSSIs);
WFD high/good ‘ecological status’
CPL PAGE 7-9
Rooley Moor Wind Farm Environmental Statement
Sensitivity Hydrological / hydrogeological / geological definition
Public water supplies and principal or highly productive aquifers with high aquifer
vulnerability.
Nationally important fisheries containing protected species such as Freshwater Pearl
Mussel.
Areas with a high risk of flooding.
Medium WFD high/good ‘ecological and chemical status.’
Private water supplies.
Groundwater that supports highly dependent groundwater dependent terrestrial
ecosystems (GWDTE).
Areas with a moderate risk of flooding, with existing flooding being confined to areas
immediately adjacent to watercourses.
Highly productive aquifer with low to medium vulnerability or moderately productive
aquifers with high vulnerability.
Regionally important fisheries.
Pristine or active peat bog habitat; evidence that peat body has an intact hydrological
system/possibility that peat could recover to pristine status.
Low Low environmental importance (e.g. WFD poor/bad ‘ecological status’).
Low productivity/non aquifer.
Private water supplies located within the vicinity of a mains water supply or private
water supplies used for agricultural purposes and not for drinking water purposes.
Degraded fisheries or receptor not important for fisheries.
Low risk of flooding.
Groundwater that supports moderately dependent GWDTE.
Degraded or inactive peat; small isolated areas of peat; soil not sensitive to change,
e.g. degraded/grazed; shallow, evidence of widespread erosion. Significant active
land drainage has occurred resulting in ongoing dewatering of peat.
Table 7.4 Impact Magnitude Criteria
Receptor Magnitude
High Medium Low Negligible
Runoff regime Long term
irreversible change
in overall volume of
runoff from the
whole site and
changes to flow
paths and rates
resulting in change
in flood risk and
erosion potential.
Temporary change
in overall volume of
runoff from the
whole site and
changes to flow
paths and rates
resulting in change
in flood risk and
erosion potential.
Short term change
in volume of runoff
and changes to
flow paths and
rates in localised
areas of the site
resulting in change
in flood risk and
erosion potential to
localised areas
only.
No measureable
change in site
runoff regime
Surface water Measureable
change in water
Measureable
change in water
Measureable
change in water
No measureable
change in surface
CPL PAGE 7-10
Rooley Moor Wind Farm Environmental Statement
Receptor Magnitude
High Medium Low Negligible
quality quality status with
respect to EQS for
more than one
month; long term
irreversible impact
on aquatic
ecosystems.
quality status with
respect to EQS for
less than one
month; temporary
impact on aquatic
ecosystems in the
medium term.
quality but no
change with
respect to EQS. No
significant impact
on aquatic
ecosystems.
water quality.
Water Supply Measurable
change in the
quality or volume of
the available
supply for
abstraction with
respect to The
Water Supply
Regulations;
leading to change
in water pressure
and/or in supply
volumes.
Measurable
change in the
quality or volume of
the supply for more
than 1% of
samples with
respect to The
Water Supply
Regulations;
temporary visual
colouration change
and alteration to
sediment content.
Measurable
change in the
quality or volume of
the supply for less
than 1%, but no
change with
respect to The
Water Supply
Regulations. No
change in pressure
or flow.
No measureable
change in water
supply.
Riverine flow
regime
Measurable
change in riverine
flows resulting in a
change in dilution
capacity or change
in flood risk for
watercourses or
water bodies
directly monitored
under the WFD.
Measurable
change in riverine
flows resulting in a
change in dilution
capacity or change
in flood risk for
smaller
watercourses or
water bodies, not
directly monitored
under the WFD.
Detectable change
in riverine flows but
no measurable
change in dilution
capacity or flood
risk.
No measureable
change in riverine
flow regime.
Geomorphology Permanent change
to geomorphology
over a large scale
including large
changes in erosion
and deposition
regimes.
Permanent change
in geomorphology
over a limited area
including some
changes in erosion
and deposition
regimes.
Temporary change
in geomorphology
over a limited area
including slight
changes in bed
morphology,
sedimentation
patterns and
erosion rates.
No change in
geomorphology.
Groundwater
flow regime
Irreversible or
permanent change
to the recharge,
flow or discharge of
groundwater. May
impact upon
Measurable
change to the
recharge, flow or
discharge of
groundwater. May
impact upon
Short term
reversible changes
to the recharge,
flow or discharge of
groundwater.
Impacts are limited
No measurable
change in the
recharge, flow or
discharge of
groundwater.
CPL PAGE 7-11
Rooley Moor Wind Farm Environmental Statement
Receptor Magnitude
High Medium Low Negligible
licenced
groundwater
abstraction, water
supply to
ecosystem or
groundwater base
flow to a
watercourse such
that it impacts on
WFD criteria or
standards.
licenced
groundwater
abstraction, water
supply to
ecosystem or
groundwater base
flow to a
watercourse but
with no impact on
WFD standards.
Impacts affect
large or multiple
area(s).
to small discrete
areas.
Groundwater
Quality
Permanent or long
term (>one month)
change in
groundwater
quality with respect
to EQS for more
than one month.
Temporary change
in groundwater
quality, changing
site quality with
respect to EQS for
less than one
month.
Measurable but
temporary change
in groundwater
quality, but not
changing status
with respect to
EQS.
No measureable
change in
groundwater
quality.
Peat hydrology
/ Quality /
volume and
extent of peat
Significant
permanent
alteration to peat
hydrology resulting
in the change of
status of the peat
body.
Moderate alteration
to peat hydrology
resulting in
localised changes
in the status of
peat bodies. Any
changes are
largely temporary.
Minor alterations to
peat hydrology.
No measureable
change in peat
hydrology.
7.12. Professional judgement is used to assess the findings in relation to each of these criteria to give an
assessment of significance for each impact. This utilises the sensitivity of identified receptors (using
the criteria in Table 7.3) and the magnitude of potential impacts (using the criteria in Table 7.4).
Potential impacts are then evaluated as to whether they are considered to be of high, moderate, low,
or no significance. As a guide, a table has been developed whereby the combination of sensitivity and
magnitude give the significance of the potential impact (Table 7.5).
Table 7.5 Evaluation of Potential Impact
Receptor
Sensitivity
Magnitude of Impact
Negligible Low Medium High
High Not Significant Moderate Major Major
Medium Not Significant Minor Moderate Major
Low Not Significant Not Significant Minor Moderate
CPL PAGE 7-12
Rooley Moor Wind Farm Environmental Statement
7.13. The likelihood of potential impacts occurring is then assessed. To classify the probability of occurrence
for a potential impact it is necessary to understand how regularly a given event or outcome will come
to pass. This can be assessed in a number of ways including assessments based on historical data,
quantitative analysis, or experience from other similar sites. The likelihood of occurrence (Table 7.6 )
of potential impacts is then assessed against the criteria in ranging from a scale of rarely to certain.
Table 7.6 Definitions of Likelihood of Occurrence
Likelihood of occurrence Definition
Certain
Any consequence that is likely in the medium term and inevitable throughout
the assessment timescale. i.e. the consequence will happen if the
development goes ahead.
Likely There is a high probability that the consequence will be realized within the
lifetime of the development or duration of the activity.
Possible It is possible but unlikely that any consequence would arise during the
lifetime of the development.
Rarely There is a very low probability that any consequence will ever arise within the
lifetime of the development or duration of the activity.
7.14. The likelihood of significant impacts occurring is then combined with the evaluation of potential impacts to
assess likely significant impacts using the matrix in Table 7.7.
7.15. Typically, significant impacts assessed as minor, or less are considered not significant in terms of EIA.
Impacts evaluated as having a moderate or high significance are defined as significant for the purpose of the
EIA. If the assessment results in moderate or high significant impact, then additional mitigation measures
will need to be considered.
Table 7.7 Likely Significant Impact Matrix
Evaluation of
Potential Impact
Likelihood of Occurrence
Rarely Unlikely Likely Certain
Major Minor Moderate Major Major
Moderate Negligible Minor Moderate Moderate
Minor Negligible Negligible Minor Minor
Not Significant Negligible Negligible Negligible Negligible
7.16. The impacts recorded in highlighted cells are ‘significant’ in terms of the EIA Regulations (The Town
and Country Planning (Environmental Impact Assessment) Regulations 2011).
7.17. Mitigation measures to reduce the impact of any identified potential impacts identified to occur during
the construction, operation and decommissioning of the wind farm are then applied. The likelihood of
any residual significant impacts occurring after mitigation measures have been implemented is then
assessed using Table 7.6.
7.18. Table 7.7 is then used again to assess the residual likely significant impact.
CPL PAGE 7-13
Rooley Moor Wind Farm Environmental Statement
7.6 Baseline Conditions
Study Area 7.6.1
7.19. The Development Area mostly comprises open moorland across a high plateau. This study considers
impacts to hydrological, hydrogeological and geological receptors (including peat) within the
Development Area. Impacts to these receptors outside of the site boundary are considered for up to
2km, or further where a hydrological connection deems it necessary.
Climate and Topography 7.6.2
7.20. The average annual catchment rainfall for the area is approximately 1,510mm based on data obtained
from the FEH1, indicating a moderately wet climate having the potential to exhibit a moderately high
runoff regime.
7.21. The study area encompasses the eastern extent of an upland plateau which forms Rooley Moor,
Knowl Moor and Scout Moor. Much of the study area is elevated above 350 metres above ordnance
datum (m aOD) and encompasses three main peaks which form a north-south trending ridge along the
length of the Development Area. These peaks are;
Top of Leach located in the north of the study area, summit elevation 474m aOD;
Hammer Hill located in the centre of the study area, summit elevation 440m aOD; and
Top of Pike located in the south of the site, summit elevation 398m aOD.
7.22. These hills form the crest of a watershed which creates six surface water catchments; these are
described further below.
Statutory Designated Sites 7.6.3
7.23. There are no designated sites within the Development Area.
7.24. There is only one designated site within 1km of the Development Area, the Lee Quarry Site of Special
Scientific Interest (SSSI).
7.25. Lee Quarry is a large disused quarry on the south side of the Rossendale Valley, south of Bacup. The
quarry is a designated Geological SSSI because it is rich in trace-fossil assemblages and good
sedimentary features, making it of great importance to studies of late Carboniferous environments and
palaeogeography. Lee Quarry is now an important tourist attraction since being converted into a
purpose built mountain biking centre by Rossendale Borough Council. As the designation has no
hydrogeological or hydrological component and the quarry is located outside the Development area so
will not be impacted by wind farm activities. This feature is not considered further within this
assessment.
7.26. There is only one designated site within 2km of the Development Area; a Local Nature Reserve Site,
Healy Dell which is located approximately 1km from the Development Area in Spodden Valley on the
Rochdale-Whitworth border. The nature reserve has been designated for its natural beauty and
archaeological feature. No hydrological, hydrogeological or geological features have been identified as
relating to this designation and this feature is not considered further within this assessment.
1 FEH (Flood Estimation Handbook) CD-ROM 3 produced by the CEH (Centre for Ecology and Hydrology, 2009)
CPL PAGE 7-14
Rooley Moor Wind Farm Environmental Statement
Hydrology 7.6.4
Surface Water Catchments
7.27. The study area drains five surface water catchments. These catchments ultimately drain to the River
Irwell (north and west), the River Spodden (east) or Nadden Brook (south) (see Figure 7.1). Several of
the catchments contain United Utilities public water supply reservoirs which receive surface water
inputs from many of the watercourses located within the upper parts of the catchments. Outflow from
the reservoirs into the lower catchments is controlled by a series of sluice gates, these are further
described in Section 7.6.9.
Catchments draining to River Irwell
7.28. Cowpe Moss catchment is located towards the far north-west of the study area and contains the
Cowpe Moss reservoir, a raw water reservoir operated by United Utilities. The reservoir has been
constructed in the base of a very steep valley and is primarily fed by three, un-named surface water
sources which rise on the steep cliff above the reservoir. Ordnance survey mapping marks the
presence of numerous springs and wells above the reservoir, suggesting that groundwater may also
contribute water to the reservoir. Cowpe Reservoir also likely receives some runoff from the up
gradient Cowpe Moss area. The reservoir is stocked with trout and is a popular destination for local
angling groups and ultimately drains to the River Irwell located to the north. There are no surface
water courses which rise within Development Area and flow into Cowpe Moss catchment; the
Development Area runs along the watershed boundary of the catchment which means there is no
direct hydraulic connection between the site and Cowpe Moss catchment.
7.29. Greens Moor catchment drains the north of the site and is the only catchment which does not contain
a reservoir. The main surface watercourse is Well Clough and associated tributaries which rises within
the Development Area and flows north and discharges directly into the River Irwell c.1km north of the
Development Area. Lower in the catchment, typically below an elevation of 360m aOD, numerous
springs are mapped as emerging from the steep hillside which in turn feed a network of small streams
that ultimately discharge into the River Irwell. The nearest spring is over 250m down gradient of the
northern tip of the site boundary. Several disused quarries are located on the mid slopes of Greens
Moor catchment, including the Lee Quarries and associated SSSI.
Catchments draining to River Spodden
7.30. Cowm catchment is located in the north-east of the study area, a small (0.38km2) lobe of the
Development Area extends into the catchment. The Cowm catchment contains the Cowm Reservoir;
the reservoir is a United Utilities asset and is currently used as a recreational space. It is not used for
water supply. The Cowm catchment is drained by several surface water courses, namely:
Walstead Clough which rises near Old Slink Stack near the top of the catchment within the application
boundary and flows directly into Cowm Reservoir;
Cowm Brook (and nearby, un-named watercourses) rise mid-way down the Cowm catchment, over
185m down gradient of the site boundary and flow towards the former quarrying area, Britannia
quarries. The Britannia quarries contain several, artificial water bodies within the flooded quarry
working areas.
7.31. As for the Cowpe Moss catchment, OS mapping indicates the presence of numerous groundwater
springs emerging on the steep mid-slopes of the catchment.
CPL PAGE 7-15
Rooley Moor Wind Farm Environmental Statement
7.32. Spring Mill and Prickshaw catchment is located on the eastern side of the Development Area. The
catchment contains the Spring Mill Reservoir and the Prickshaw Reservoir, both United Utilities assets
operated as a public water supply. All surface water courses in the upper part of the catchment drain
into the reservoirs.
7.33. Spring Mill reservoir receives flow from:
the Prickshaw Brook which rises towards the top of the catchment, outwith the Development Area; and
The Fern Isle Brooks, which is a major tributary of the Prickshaw Brook and the confluence is located
approximately 300m up gradient of the reservoir. The headwaters of the Fern Isle Brook rise within
the Development Area near the disused Bagden Quarry.
7.34. The Prickshaw Reservoir comprises three small water bodies which are fed by one main, un-named
surface water course which rises within the Development Area near Prickshaw Slack.
Catchments draining to Naden Brook
7.35. Naden and Greenbooth Reservoir catchment is the largest of the study area catchments at 10km2
and drains into a series of reservoirs before discharging into the Naden Brook 1km to the south of the
Development Area. Much of the western half of this catchment is located within the Development
Area.
7.36. Little Ding and Ding Clough surface watercourses rise within the Development Area, just below the
disused Ding Quarry. Both streams flow due south and discharge into the Naden Higher Reservoir.
7.37. An un-named stream with five tributaries flows into the Naden Higher Reservoir on its eastern bank.
The headwaters of the stream rise within the Development Area;
7.38. An un-named stream flows into the Naden Middle Reservoir on its eastern bank. The headwaters of
the stream rise within the Development Area;
A small spring watercourses rises at Forsyth Brow, close to the Development Area and flows east and
discharges into the Greenbooth Reservoir;
A further two small spring fed watercourses rise at Forsyth Brow and flow south, ultimately discharging
into the Naden Brook 1km to the south of the Development Area.
Surface Water Quality
7.39. As part of the requirements for the Water Framework Directive (WFD), the EA has described the
general quality of watercourses within each river basin district and the pressures the water
environment faces. The study area falls within Irwell Catchment in the North West river basin district.
The surface watercourses identified within the Development Area have not been assessed by the EA
as they are too small, however, the three main receiving watercourses, the River Irwell, River Spodden
and Nadden Brook have been assessed and a summary of their current and future predicted status
(using criteria defined under the WFD) is presented in Table 7.7.
Table 7.7 Summary of Surface Water Quality2
WFD Parameter River Irwell River Spodden Naden Brook
Hydromorphological Status Heavily modified Heavily modified Heavily modified
2 Data from Environment Agency, available online at http://maps.environment-agency.gov.uk/wiyby/wiyby Last Accessed 20th
March 2014.
CPL PAGE 7-16
Rooley Moor Wind Farm Environmental Statement
WFD Parameter River Irwell River Spodden Naden Brook
Current Ecological quality Moderate Potential Moderate Potential Moderate Potential
Current Chemical Quality Good *DRA *DRA
2015 predicted ecological quality Moderate Potential Moderate Potential Moderate Potential
2015 predicted chemical quality Good *DRA *DRA
Overall Risk At risk At Risk At Risk
Biological Quality
Overall biological quality Poor *NA Moderate
Diatoms *NA Good *NA
Fish Poor Good Good
Macro-invertebrates Moderate Moderate
General Physico Chemical Quality
Ammonia High High High
Dissolved Oxygen High High High
pH High High High
Phosphate Good High High
Specific Pollutants Quality
Ammonia High High High
Copper High High High
Iron High High High
Zinc High High High
* DRA = Does Not Require Assessment
* NA = Not Assessed
7.40. In summary, chemical water quality for all three receiving watercourses is high despite only the River
Irwell requiring assessment for chemical quality.
Flood Risk 7.6.5
Fluvial Flood Risk
7.41. Indicative flood mapping published by the EA3 shows the Development Area is located entirely outside
the mapped floodplain, indicating that this risk is negligible.
3 Data from Environment Agency, available online at http://maps.environment-agency.gov.uk/wiyby/wiyby Last Accessed 20th
March 2014.
CPL PAGE 7-17
Rooley Moor Wind Farm Environmental Statement
Surface Water Flood Risk
7.42. Indicative surface water flood risk mapping published by the EA3 suggests the risk of flooding is
generally very low. Areas of medium and high surface water flood risk do occur within the
Development Area and wider study area; these areas are concentrated along existing surface water
flow paths and topographic lows such as gullies or former quarry areas.
7.43. During rainfall events, flows pass overland following topographic grades to gullies in peat, watercourse
channels or tributaries down-slope and eventually into the receiving catchment watercourses as
defined in the surface water section above. It is likely that once flows are in these channels, they will
travel relatively quickly off the steep hillsides. Potential exists for localised surface ponding of water
during or following these conditions; however, flooding is likely to be shallow and only inundate some
isolated low lying areas, for instance in the areas directly adjacent to watercourses.
Artificial Drainage Systems
7.44. The existing Rooley Moor Road public bridleway and other minor public paths cross several minor
watercourses within the Development Area. Culverts are generally used to convey flow under the
tracks, the majority of which were observed to be in good condition and free of debris. Plate 1 and
Plate 2 below detail an example of an existing crossing on Rooley Moor Road on a tributary of Higher
Naden Reservoir, at NGR 385745 418172.
Plate 1 Rooley Moor Road existing crossing Plate 2 View downstream from existing crossing
7.45. Topography and indicative flood risk mapping provided by the EA shows the Development Area to be
generally at low risk of inundation mainly limited to a risk during high rainfall conditions causing
overland flow and minor isolated ponding in some areas, particularly around areas which are saturated
under normal conditions, i.e. stream margins and boggy areas.
Tidal Flood Risk
7.46. The Development Area is over 350m above sea level at its lowest point; therefore this risk does not
apply.
CPL PAGE 7-18
Rooley Moor Wind Farm Environmental Statement
Groundwater Flood Risk
7.47. Groundwater flooding is not considered to be a risk to the development. This is due to the steep
topography of the site and the relative depth to the regional water table (springs mapped from 360m
aOD), over 50m below the minimum site elevation.
Geology and Peat 7.6.6
Superficial Geology
7.48. British Geological Survey (BGS) 1:50,000 scale superficial mapping shows superficial deposits are
largely absent from much of the Development Area and there are large areas where the bedrock
outcrops at the surface. However, areas of superficial deposits have been mapped; Glacial Till
comprising stiff grey brown sandy silty clay with occasional gravel and cobbles is shown across the
very southern part of the Development Area and locally around Prickshaw in the south and east. A
small, isolated area of Head deposits is shown around the Rooley Moor Brow area comprising glacially
derived materials.
Bedrock and Structural Geology
7.49. The bedrock on site and in the wider study area comprises rocks from the Upper Carboniferous period
(Figure 7.2). The outcrop in the northern and central part of the Development Area comprises the
Namurian Millstone Grit (NMG) series which are overlain by the Westphalian Pennine Lower Coal
Measures (PLCM) in the southern part of the Development Area. Towards the north, the NMG is
faulted against the PLCM in a series of normal faults.
7.50. The NMG comprises a thick succession of interbedded sandstones, siltstones, mudstones and
subordinate thin coals and seat earths. The PLCM comprises alternating sandstone and shale strata
and several significant coal seams which were extensively mined in the past.
7.51. The study area is located on the crest of a large south-west trending open fold of the Rossendale
Anticline. The oldest rocks of the NMG are exposed in the core of the anticline in the centre of the site.
The bedrock geology is faulted by many north-west to south trending normal faults. These faults have
formed a series of graben and half graben blocks across the area.
Peat
7.52. BGS 1:50,000 scale superficial geological mapping shows the presence of peat deposits in the
northern, eastern and western areas of the site (see Figure 7.3). The southern half of the site is
mapped as being peat free. Peat probing was carried out across the study area at 348 locations on a
100m grid, the detailed results of this exercise are recorded in Appendix 7.3. The occurrences of peat
correspond well with published geological mapping. Recorded peat depths ranged from 0.0m to 2.1m,
where peat was encountered the average depth was between 0.5m and 1.0m depth. Some 123 peat-
free locations were identified, several of which were associated with spoil heaps or located in the
southern regions of the site. Peat depths of 1.75m or greater were recorded at eight locations,
predominantly located in the north of the site, north of Ding Quarry near the summit of Top of Lench
hill.
7.53. NVC mapping identified that the majority of the peat land in the Development Area was vegetated by
degraded/modified mire communities such as M20 and M25. Chapter 8: Ecology suggests that the
peat would have formerly been dominated by blanket mire vegetation. Blanket mire develops in areas
of high rainfall, and has an ombrogenous (that is, water-fed by rainfall) hydrological regime, however
due to the influence of continuous heavy grazing (perhaps coupled with burning and atmospheric
CPL PAGE 7-19
Rooley Moor Wind Farm Environmental Statement
pollution) the original bog vegetation becomes modified to such to lower ecological value habitats.
Much of the peat land across the Development Area, south of Ding quarry, around Ding Clegg and
further east around Hamer Hill is therefore considered to be degraded.
7.54. The findings of the ecology study are supported by peat characteristic analysis; Von Post
humidification scores for the acrotelm were generally H6-H7, indicating moderately to highly
decomposed peat with a very indistinct plant structure. These scores are higher than would be
expected for a healthy, actively peat-forming acrotelm (which should be less decomposed) suggesting
that the acrotelm layer in the study area is degraded. The interpretation that the peaty acrotelm is
degraded across much of the site is reflected in the moisture Von Post scores which were typically B2-
B3, indicating a low to moderate moisture content in the peat. Dip-well levels from piezometers
installed in the peat around turbine locations indicate that average water table depth across the site is
0.25m, below the acrotelm layer. The acrotelm needs to be saturated in order to support the bog
plants which in turn form peat and help stabilise it.
7.55. Two larger areas of M3 bog pool communities were mapped to the north of Ding Quarry (12.36ha) and
on Brandwood Moor (13.3ha). According to the JNCC (2010)4, M3 is typically found in areas of shallow
peat in acidic environments and is commonly associated with eroded blanket mire in north-west f
Britain. It is reported to represent a seral stage in the redevelopment of active mire vegetation
disruption. Water levels in the peat in this area were at ground level, indicating total saturation through
the peat profile. In addition, some small bog pools were observed. In conclusion, these areas of peat
land represent active but not pristine areas bog with a relatively intact hydrological regime.
7.56. A comprehensive multi-factor approach was adopted to identify peatslide prone areas within the
Rooley Moor site. A total of 348 positions on a 100m grid pattern were examined in detail and the
results of the study were used to establish constraints to avoid areas identified as potentially
vulnerable to ground movements. Peat slide risk across the majority of the Development Area was
found to be low, however, some isolated areas of moderate risk were identified. No areas of high peat
slide risk were identified.
Quarrying and Mining
7.57. A separate Mining Risk Assessment Report5 (which is presented in Appendix 7.4) identified that the
Development Area and wider study area has been subjected to extensive mining and quarry activity in
the past. There are currently no active workings. The report found 33 recorded mine entries within the
Development Area; of these, only 6 have been treated or capped. The report also found evidence for
extensive coal mining of seams at numerous locations within the Development Area which have not
been officially recorded.
7.58. OS mapping shows numerous small sandstone quarries within the site boundary with larger quarries
located in the wider study area (such as Ding Quarry or Lee Quarry). Several of the smaller quarries
have been completely backfilled to an unknown standard whilst the rest remain open or partially
backfilled. The mining risk assessment found that the Development Area had an overall Medium to
High risk of mining related subsidence with respect to the Development. As such, all known and
suspected constraints relating to mining activity have been mapped and are shown in Figure 3.1.
7.59. Areas with historical mining activity have in some cases led to a decrease in groundwater quality; as
shown in
4 National Vegetation Classification: field guide to mires and heaths. Joint Nature Conservation Committee (2010). Available online
at http://jncc.defra.gov.uk/pdf/mires_heaths.pdf Last accessed 18/06/14. 5 Mining Risk Assessment Report: Rooley Moor Wind Farm. Prepared by SKM, March 2012.
CPL PAGE 7-20
Rooley Moor Wind Farm Environmental Statement
7.60. Plate 3, below. Groundwater springs contaminated with ferric iron deposits colloquially known as
‘ochre’ are observed emerging within the study area.
Groundwater 7.6.7
Aquifers
7.61. The EA online mapping tool6 indicates that no Source Protection Zone’s (SPZ) are located within the
Development Area or wider study area.
7.62. There are no superficial aquifers located within the Development Area, however, superficial aquifers
are identified along the River Spodden, River Irwell and Nadden Brook watercourses, these likely
comprise recent alluvial deposits.
7.63. EA mapping shows that the bedrock beneath the Development Area is a Secondary A aquifer. This
classification refers to both the NMG series and the PLCM formation. A secondary A aquifer
classification refers to permeable layers of rock capable of supporting water supplies at a local rather
than strategic scale. In some cases these aquifers can form an important source of baseflow to rivers.
7.64. The NMG forms a multi-layered aquifer system in which persistent, thick sandstone horizons act as
separate aquifers with intervening mudstones and shales acting as aquicludes and aquitards7. The
sandstones are generally well cemented and groundwater storage and transport is restricted largely to
joints and fractures.
7.65. A number of perched water tables occur in the multi-layered aquifer system meaning that the depth to
groundwater within the aquifer at any location is difficult to define. Springs are reported to be common
at the base of sandstone layers and at junctions between shale and sandstone horizons7. Numerous
springs and wells are mapped on the hillsides below Rooley Moor (and the main development area)
suggesting that this is an important spring line.
7.66. The PLCM formation is described8 as a moderately productive, multi-layered aquifer. As for the NMG,
it is the sandstone layers which form aquifers and springs are common features.
Groundwater Quality
7.67. The EA online mapping tool 9 indicates that groundwater within the NMG and PLCM has been
assessed under the WFD as having ‘good’ quantitative status. The predicted quantitative status
remains good for 2015. The qualitative status is assessed under the WFD as being ‘poor’, with this
assessment remaining for 2015. Based on observations made during site visits, it is considered likely
this status is related to the mine workings in the area and the impact on groundwater quality.
7.68. The water quality in areas which have been mined is often poor as oxidation of sulphurous mine water leads to the creation of conditions for Acid Mine Drainage (AMD) and the formation of characteristic ochre deposits. This was observed at a spring which emerges at Snipe Barn Farm to the east of the Rooley Moor Development Area (see Error! Reference source not found. below). However, in areas
6 Data from Environment Agency, available online at http://maps.environment-agency.gov.uk/wiyby/wiyby Last Accessed 20th
March 2014 7 Abesser, C, Shand, P. & Ingram, J, 2005. Baseline Report Series 18. The Millstone Grit of Northern England. British Geological
Survey Commissioned Report No. CR/05/015N. 8 BGS UK Hydrogeology Viewer Available online at http://mapapps.bgs.ac.uk/hydrogeologymap/hydromap.html Last accessed 20th
March 2014. 9 Data from Environment Agency, available online at http://maps.environment-agency.gov.uk/wiyby/wiyby Last Accessed 17th June
2014
CPL PAGE 7-21
Rooley Moor Wind Farm Environmental Statement
naffected by mining, water quality is often very good and many springs are utilised locally as potable private water supplies.
Plate 3 Ochre deposits in spring at NGR 387186 416374
Groundwater Dependent Terrestrial Ecosystems 7.6.8
7.69. The Water Framework Directive (WFD) establishes a framework for the protection of groundwater
which prevents further deterioration and protects and enhances the status of groundwater dependent
terrestrial ecosystems and wetlands regardless of whether they are designated or not. Good
groundwater status (both quantitative and chemical) with respect to wetlands and groundwater is
dependent upon there being no ‘significant damage’ to Groundwater Dependent Terrestrial
Ecosystems (GWDTE) caused by alterations to either the flow of groundwater or groundwater
quality. The impact to GWDTE within the Development Area therefore needs to be considered within
this ES.
7.70. There is no specific guidance relating to the identification and assessment of GWDTE habitats on
wind farms in England. As a result, GWDTE habitats on Rooley Moor have been identified using
methodologies outlined in UK Technical Advisory Group (UKTAG, 2009)10 and SEPA’s LUPs11
best
practice guidance for identifying GWDTE and assessing those that are at risk of significant damage.
7.71. The methodology can be summarised as follows; both guidance documents advocate the
identification of GWDTE through National Vegetation Classification (NVC) mapping of the proposed
development area. Detailed NVC mapping of the development area has been undertaken and is fully
10 Guidance on the identification and risk assessment of groundwater dependent terrestrial ecosystems Version 5, Annex 1 (2009)
Available online at http://www.wfduk.org/resources%20/risk-assessment-groundwater-dependent-terrestrial-ecosystems: Last accessed 16th June 2014 11 Land Use Planning System SEPA Guidance Note 4, version 6. Issued March 2012.
CPL PAGE 7-22
Rooley Moor Wind Farm Environmental Statement
reported in Chapter 8: Ecology. Once the mapping has been collated, each NVC community is
assigned a groundwater dependency score.
7.72. The UKTAG (2009) guidance gives NVC communities a score between 1 and 3 on a scale of likely
groundwater dependency with the following definitions:
1. High. Strong dependency on groundwater discharge from bedrock or superficial aquifers at the
majority of sites;
2. Moderate. Likely to be some dependency on groundwater discharge at most sites – either direct
from recognised aquifers or indirectly as recharge from minor aquifers in superficial deposits.
Water from other sources (surface runoff, overbank flooding, etc) may also be very important; and
3. Low. Groundwater discharge usually irrelevant. Site fed by other water sources. This may also
include components of ombrogenous systems with intrinsic groundwater systems fed by rain such
as blanket bog. NVC communities with a score of 3 have not been taken forward in this
assessment as they are not considered to be GWDTE.
7.73. Those habitats which have a GWDTE score of 1 or 2 and are located within 250m of borrow pits and
turbines and/or 100m of access tracks and construction compounds are considered to be ‘at risk’ from
the proposed development and therefore require assessment within an ES and may require mitigation
to offset impacts. The sensitivity of these habitats is considered in Table 7.8.
7.74. NVC mapping has identified wetland plant communities such as mires, acidic flushes and bogs within
the development area, these are typically located in the northern half of the site in areas underlain by
varying thicknesses of peat deposits. The majority of the northern portion of the site is covered in M20,
M25 and M3 habitats which are peat forming bog and mire communities and are sustained by
rainwater inputs. By definition, these habitats are not groundwater dependent. In amongst the areas of
bog and mire habitats, small acidic flushes (M6) and rush pasture (M23) plant communities have been
mapped. These communities are considered to have some groundwater dependency and are
identified as GWDTE in Table 7.8.
7.75. Non wetland plant communities such as U4, U5 grassland and U20 bracken dominate in the southern
portion of the site where peat is thin or absent.
Table 7.8 GWDTE habitats within Development Area
NVC
Category
Description UKTAG 2009
GWDTE
Score
M6 –
flush/mire
Sixteen discrete flushes of M6 covering an area of 6.26ha have been mapped
within the Development Area. The M6 mostly forms discrete flushes orientated
parallel to slope contours. All the occurrences of M6 are coincident with peat
deposits suggesting outflow/seepage from this habitat is important in
maintaining saturation. Other inputs will come from direct rainfall recharge,
hillside runoff and shallow groundwater fluxes.
The main exception is a 2.2ha polygon containing M6 and M3, an
ombrogenous bog pool habitat near Prickshaw Slack. It is unlikely this M6
receives significant groundwater inputs and is likely sustained rising and
falling water levels within the peat body.
1 = High
M23 – rush
pasture
Five flushes of M23 covering an area of 2.5ha have been mapped within the
Development Area. These flushes are orientated parallel to slope contours to
the east and west of the existing Rooley Moor track. These habitats have
2 = Moderate
CPL PAGE 7-23
Rooley Moor Wind Farm Environmental Statement
NVC
Category
Description UKTAG 2009
GWDTE
Score
formed in gullies and shallow valleys where surface water runoff flows are
concentrated. Peat depths beneath these habitats are generally low (<50cm)
so groundwater seepage is likely to be an important source sustaining these
habitats.
A 4.9ha area of M23/M25 has also been mapped. M25 is not considered to be
GWDTE at this site and it is noted that both the M23/M25 polygons have
formed over deeper peat which has an ombrogenous regime and are by
definition, not groundwater dependent.
M25 – mire The UKTAG 2009 guidance considers M25 to have a low likelihood of
dependence on ground water movement; though in some circumstances
moderate dependency is possible. The M25 within the Development Area is
typically associated with peat deposits <50cm which have formed as part of
an ombrogenous regime. M25 is widespread across the development area
and is more associated with peat deposits than localised areas (like M6 and
M23) which are more likely to be fed by groundwater seeps and flushes. It is
considered that the M25 in the development area has a low groundwater
dependency.
3 = Low
U6 -
grassland
The UKTAG 2009 guidance considers U6 to have a moderate dependency on
groundwater.
2 = Moderate
M3 – bog
pool
community
UKTAG 2009 considers this wetland habitat to have a low dependency on
groundwater as it forms as part of an ombrogenous bog regime.
3 = Low
M20 – raised
mire
M20 blanket bog is considered to have a low likelihood of dependence on
groundwater movement (UKTAG 2009).
3 = Low
U4 –
grassland
Not a wetland habitat. Located in south of site where peat deposits are
absent.
Not Wetland
habitat so not
classified.
U5 –
grassland
Not a wetland habitat. Located in south of site where peat deposits are
absent.
Not Wetland
habitat so not
classified.
U20 Bracken
community
Not a wetland habitat. Not Wetland
habitat so not
classified.
7.76. Given the local, small scale nature of the possible sensitive GWDTEs, the sensitivity of GWDTEs
within the application boundary is considered to be Medium.
Public Water Supplies and United Utilities Assets 7.6.9
7.77. There are no public water supplies located within the Development Area; however, the site sits
between five reservoir catchments (see Figure 7.1) which are United Utilities (UU) assets supplying
drinking water to Rochdale, Rawtenstall and Bacup. These reservoirs are:
CPL PAGE 7-24
Rooley Moor Wind Farm Environmental Statement
Greenbooth Reservoir,
Naden Reservoirs (#3),
Spring Mill Reservoir,
Prickshaw Reservoirs;
Cowm Reservoir (although understood to currently not be supplying drinking water); and
Cowpe Reservoir and Cragg High Level Tank.
7.78. In addition to the reservoirs, UU have an extensive network of silt traps and settling structures within
the reservoir boundaries. These structures are generally restricted to the north of the site area
between Cowpe Reservoir and Cragg High Level Tank. There is also a culvert structure feeding
Cowm Reservoir from Walstead Clough in the east.
7.79. Consultation with UU indicates that deteriorating raw water quality is a concern for all reservoirs. It is
understood that this is due to increased erosion of peaty soils from the Rooley moor area leading to
soiley runoff into the reservoirs. UU are actively restoring peatland within their reservoir catchments,
including land within or downgradient of the Development Area.
7.80. The sensitivity to public water supplies is considered to be High.
Private Water Supplies (PWS) 7.6.10
7.81. Properties with PWS within the located within 3km of the Development Area were identified through
consultation with Rochdale County Council (RCC) and Rossendale Borough Council (RBC)
undertaken in 2014; the consultation identified 144 properties with registered PWS. Due to the number
of properties identified, a separate PWS study was completed with a view to establishing which
supplies may have a direct hydraulic connection with the Development and which properties could be
scoped out at an early stage. The PWS Assessment is presented as Appendix 7.1 of this chapter.
7.82. The assessment identified the following PWS as being potentially at risk from the Development. These
properties are identified on Figure 7.1.
Table 7.9 PWS at Risk from Proposed Development
PWS ID Property (ies) supplied by
Source
Source
Type
Description
2 Doldrums Farm and Jubarn Well Council has advised this property is supplied by a
well, abstraction volume <10m3/d. No response
received to questionnaire issued April 2014. The
exact nature of the source is unknown but a
conservative assumption would be that the well is
fed by a shallow spring which received some surface
water runoff.
14 Snipe Barn Spring Property is supplied by two sources. Source 1 is
spring which emerges on the hillside above the
property, this spring also receives hillside runoff.
This source is used for livestock and is directed into
Prickshaw Dams.
The second source which provides domestic water
to Snipe Barn has been scoped out in the
CPL PAGE 7-25
Rooley Moor Wind Farm Environmental Statement
assessment due to the groundwater source being
hydraulically remote from any influence of the
proposed development.
15 Broadley Fold and Tobey
Cottage
Spring Spring source taken below Prickshaw Dams.
Supplies Broadley Fold and possibly Tobey
Cottages.
17 Lower Dunisbooth Cottage Spring Property is supplied by a shallow well intercepting a
spring. The well is located 15m upgradient of the
property and the supply is gravity fed into a holding
tank which supplies the house. There is no water
treatment. The source of the spring is unknown. The
owner has stated the water contains a lot of iron and
has ochre (orange) deposits in it.
23 House O’Th Hill Spring Spring See below.
24 Lower Fold Head Farm,
1 Fold Head Cottages,
3 Fold Head Cottages
Fold Head Farm
Spring Spring up gradient of Fold Head Farm, supplies
other local properties. Spring emerges from hillside
above property. The spring flows along an open
channel and receives surface water runoff, including
House O’Th Hill.
7.7 Baseline Sensitivity
7.83. The overall sensitivity of surface water, groundwater and geology are influenced by the sensitivity of
individual receptors. This is summarised below.
Overall Surface Water Sensitivity 7.7.1
7.84. The sensitivity of the surface water environment in the Cowpe Moss, Cowm, Spring Mill and
Prickshaw and Naden and Greenbooth catchments is considered to be High. This is primarily due to
the presence of surface water reservoirs used for public water supply.
7.85. The sensitivity of water receptors in the Greens Moor catchment and the sensitivity of surface water
PWS around the site are considered to be Medium due to the sensitivity of PWS in this catchment.
7.86. Whilst it is recognised differing receptors within the Development Area have different sensitivities, a
conservative approach has been taken and an overall High sensitivity rating will be used in the
assessment for all surface water receptors.
Overall Groundwater Sensitivity 7.7.2
7.87. The overall sensitivity of the groundwater environment to the Development is considered to be
Medium. This is because of the good quantitative status and poor qualitative status of the NMG and
PLCM aquifers. This classification also includes the presence for multiple PWS sourced from
groundwater springs/wells around the site.
Overall Geology Sensitivity 7.7.3
7.88. The overall sensitivity of the geological environment to the Development is considered to be Medium.
In summary, this is primarily due to presence of peat up to 2.1m depth. Much of this peat is degraded
although some active areas have been identified.
CPL PAGE 7-26
Rooley Moor Wind Farm Environmental Statement
7.8 Design Evolution
7.89. The baseline assessment identified a variety of important features related to hydrology, hydrogeology
and geology within the study area that are sensitive to potential adverse impacts from the
Development. As a result it was recognised at an early stage that avoidance of certain areas of the
Development Area would be necessary to avoid significant impacts. Of key importance during the
design stage was;
The maintenance of a 50m buffer around identified watercourses so as to minimise the potential for
pollution of streams and rivers through sediment mobilisation or by spills or leaks of fuel, concrete or
other substances;
The maintenance of a 500m buffer around all public water supply reservoirs so as to minimise the
potential for pollution of streams and rivers through sediment mobilisation or by spills or leaks of fuel,
concrete or other substances;
Maintaining a safe topple distance from all United Utilities infrastructure;
The siting of infrastructure off areas with deeper peat (<50cm) where possible ;
The siting of infrastructure off areas of highly groundwater dependent habitat; and
The early identification of the sources of PWS within the study area also helped avoid these important
and sensitive receptors. PWS sources were identified and tracks have been positioned at least 100m
from the sources and excavations at least 250m away.
7.9 Standard Practice Measures
7.90. Standard practice measures will be implemented during construction across the Development Area,
and for the construction of specific components of the Development. Some of the key best practice
guidelines are referred to in Section 7.3, Policy, Legislation and Guidance. These have been taken
into account when assessing the potential impact and the likelihood of significant environmental
impacts and effects.
7.91. Such site-wide measures will include the following components:
Development of a Detailed Construction Method Statement (CMS) 7.9.1
7.92. Prior to construction commencing, a CMS will be produced outlining specific construction
methodologies to be used for the construction of all components including foundations, tracks,
watercourse crossings, laydown areas and buildings, taking into account the method of excavation
and the location for placing and storing excavated material to ensure that these operations do not give
rise to slope or site instability. A CMS will be provided with the Construction Environmental
Management Plan (CEMP).
Development of a Construction Environmental Management Plan (CEMP) 7.9.2
7.93. Prior to construction commencing, a detailed CEMP will be produced. A draft CEMP has been
prepared as part of this application and is presented as Appendix 4.1. Good working practices and
measures to protect the water environment in accordance with those set out within the EA and
CIRIAs’ PPG notes will be implemented. The Principal Contractor will be responsible for ensuring that
the plan is adhered to during construction. As well as a commitment to and details of best practice,
this will address specific mitigation measures (in addition to standard practice measures). This
CPL PAGE 7-27
Rooley Moor Wind Farm Environmental Statement
document will be presented Rochdale Council, Rossendale Council, the EA and United Utilities for
their approval, prior to construction commencing.
7.94. Specific elements with direct relevance to this chapter that will be included in the CEMP are:
Emergency and Incident Response Plan for any pollution events/spills;
An inventory of pollution sources associated with construction and specific pollution prevention;
Measures to reduce the likelihood of contamination from identified sources to downgradient surface
watercourses from fuels, oils and other contaminants. Control measures described in EA PPG notes
and CIRIA guidance will be formalised within the CEMP;
A waste management plan;
Proposed measures for noise management;
Watercourse crossing plans; and
Details of excavation and reinstatement.
Drainage Management Plan (DMP) 7.9.3
7.95. There is potential for the generation of turbid or coloured runoff from works areas throughout the
Development Area including the construction of turbines, tracks, watercourse crossings, borrow pits,
buildings and other infrastructure to enter surface watercourses and waterbodies particularly via
drainage channels or watercourses that are directly adjacent to or downgradient of works. Therefore a
DMP will be put in place, which will form part of the CEMP. An outline DMP has been prepared and is
presented as Appendix 4.4. This will provide a range of site-wide measures to reduce the generation
of sediment laden or coloured runoff and transport of any runoff to watercourses. Further specific
mitigation measures which are in addition to best practice measures outlined in this section will be
included in this plan.
7.96. The DMP will consist of the following:
A series of plans presenting the site infrastructure, existing natural drainage patterns and man-made
drainage structures;
Geology for assessment of likely permeability and infiltration;
Sensitive receptors including distance to watercourses, PWS;
Topography;
A description of the drainage considerations, sensitive areas of the site, procedures and control
structures to be employed for the various sections of the site;
A layout of the required drainage arrangements, upgradient diversion channels, culvert frequency,
H bars on tracks, check dams, silt fencing and other sediment control structures; and
An appendix of the methodology for the installation of the sediment control structures.
Water Quality Monitoring 7.9.4
7.97. Water quality will be monitored upstream and downstream of key construction works prior to, during
and following construction. Monitoring locations will take account of the construction of watercourse
crossings, access tracks, turbine foundations and borrow pits and will also take place at control sites
(outside the influence of works). A robust baseline of water quality in surface watercourses/drainage
channels downstream of construction works will be established prior to construction commencing. The
CPL PAGE 7-28
Rooley Moor Wind Farm Environmental Statement
purpose of this is to provide a comparison of ‘natural’ conditions against conditions potentially
impacted by construction. Regular monitoring during construction and in the early phases of operation
will be used to ascertain whether there are impacts occurring to watercourses and whether
implemented mitigation measures are being effective. During the early phase of operation, monitoring
will continue to assess the quality of watercourses, comparing against baseline data. The plan will
include specific actions to be taken upon triggering environmental standards.
7.98. An agreement in principal has been reached with UU over the proposed water quality monitoring and
how this monitoring can interface with and mutually enhance and/or be enhanced by proposed and
ongoing water quality monitoring in support of peat restoration schemes sponsored by UU. More
detail about the peatland restoration schemes are contained within Chapter 8: Ecology.
Provision of an Environmental Clerk of Works (ECoW) 7.9.5
7.99. An ECoW will be appointed to undertake/manage the following tasks during construction:
Implementation of peat minimisation protocol (refer to the outline PMP in Error! Reference source
not found.);
Oversee the implementation of the Habitat Management Plan (HMP) (refer to the outline HMP in
Chapter 8: Ecology);
Operate permit to dig and permit to pump systems, etc;
Water quality monitoring;
Emergency response;
Monitor drainage and sediment control; and
Monitor and ensure compliance with best practice guidance.
7.100. In addition to the above key best practice tools, individual infrastructure best practice and standards
are discussed below.
7.10 Predicted Impacts
7.101. When assessing predicted impacts of the Development standard practice measures that will be
incorporated into the construction of the wind farm have been taken into account. In addition the
measures that were taken during the design phase to avoid areas sensitive to potential impacts have
significantly reduced the potential impacts arising from the Development.
7.102. Whilst the incorporation of these measures/design features helped to reduce the magnitude or
likelihood of some potential impacts occurring, it was not possible to avoid all potential impacts. The
potential significant impacts of the Development during construction, operation and decommissioning
prior to specific mitigation measures being applied are summarised in Table 7.12.
Construction 7.10.1
Access Tracks
7.103. The Development incorporates an estimated 6.8km of new tracks. With the exception of watercourse
crossings, new sections of access tracks have been located a minimum distance of 50m from the OS
mapped watercourses on the site. The construction of watercourse crossings will be within this buffer
and the risks associated with these works are addressed in the Watercourse Crossings (Section 0)
section below. New tracks are proposed to be constructed within the following catchments:
CPL PAGE 7-29
Rooley Moor Wind Farm Environmental Statement
Spring Mill and Prickshaw;
Naden and Greenbooth;
Cowm; and
Greens Moor;
7.104. There are no new tracks proposed in the Cowpe Moss catchment.
7.105. Construction of access tracks and their continued use during the construction phase may potentially
generate turbid runoff, which could follow topographic grades to surface watercourses and associated
receptors. Any potential impacts to surface watercourses are expected to be localised and short term
only. Pollution prevention and sediment and drainage control measures described in EA PPG notes
and CIRIA guidance will be formalised within the CEMP; a draft CEMP is presented as Appendix
4.1.The contractors will be required to comply with this document. The document will specifically
outline how surface water runoff will be managed during construction. Design of drainage will seek to
mimic existing local surface water runoff regimes, such that there will be no change in quantity of
runoff into downstream receiving watercourses.
7.106. The routes of access tracks are confined to the top of sub-catchment areas, crossing watershed areas
of the sub-catchments identified above. Construction of access tracks and their continued use during
the construction phase may potentially generate turbid runoff, which could follow topographic grades
to surface watercourses, waterbodies and associated receptors, resulting in a temporary decrease in
water quality. Any potential effects to surface watercourses are expected to be localised and short
term only. Design of drainage as outlined in Appendix 4.4 will seek to mimic existing local surface
water runoff regimes, such that there will be no change in quantity of runoff into downstream receiving
watercourses.
7.107. The access tracks are located well over 100m from all PWS, however, there may be some impacts to
water quality at PWS. The source of the impacts will be restricted to the upgraded section of the
existing track as no new tracks are proposed directly upgradient of PWS supplies.
7.108. Overall, the peat slide risk across the site is generally low, however, localised medium risk areas of
peat instability have been identified (see Figure 12 of Appendix 7.3) and adequate control measures
will need to be incorporated during construction works to protect any vulnerable watercourses. A peat
slide caused as the result of access track construction could result in the release of peat sediments
into down gradient watercourses. Tracks will be either of ‘excavated’ type tracks, (estimated 5.0km)
constructed on areas with less than 1.0m depth or ‘floating’ type tracks (estimated 1.8km) constructed
on areas of peat greater than 1.0m depth. This track design minimises the volume of peat excavated
during construction, minimises the mobilisation of peat fines from excavation areas and preserves
unimpeded subsurface flow.
7.109. The track layout has been designed to avoid areas of active peat, however total avoidance has not
been possible. The new access track is proposed in areas of active bog to provide access to turbines
T18, T16, T15 and T14. The track could disrupt hydraulic continuity within the bog habitat, resulting in
indirect loss down gradient of the track. These indirect losses of habitat could occur if hydraulic
continuity is not maintained down gradient of the access track.
7.110. The access track layout has avoided all areas of highly groundwater dependent habitats (M6).
Upgraded sections of access track along Rooley Moor road to cross areas of M23, moderately
dependent GWDTE. The presence of tracks can disrupt shallow groundwater flows, impounding water
on the upgradient side of track, resulting in indirect habitat loss up to 100m from tracks. However, as
this M23 is already located on either side of the track, this suggests its presence is unaffected or even
enhanced by the presence of the track. One area of new track, near water crossing no.4 (see Section
CPL PAGE 7-30
Rooley Moor Wind Farm Environmental Statement
0) will bisect a flush of M23 which leads onto a flush of M6. Mitigation will be required to ensure
hydraulic continuity is maintained at this point and maintain GWDTE habitats down gradient.
7.111. Furthermore, indirect loss of the above mentioned habitats could occur as a result of the access track
construction. Impacts relating to direct loss of ecological habitat are covered in Chapter 8: Ecology.
Watercourse Crossings
7.112. There are a total of two new and one upgraded watercourse crossing proposed to be constructed over
surface watercourses and drainage channels within the Development Area, shown on Figure 7.1 and
described in Table 7.10. These crossings are proposed in the following catchments:
Table 7.10 Proposed and Upgraded Water Crossings
Crossing
ID
Type Location
(NGR)
Catchment Description
1 Upgraded 386948
416085
Spring Mill and
Prickshaw
Upgraded watercrossing beneath existing Rooley
Moor Road. No direct discharge to reservoir.
2 New 385631
418048
Naden and
Greenbooth
New crossing over stream which discharges
directly into the Naden and Greenbooth Reservoir.
3 New 385665
418086
Naden and
Greenbooth
New crossing over stream which discharges
directly into the Naden and Greenbooth Reservoir.
Upgradient of crossing 2.
7.113. During the construction of all watercourse crossing culverts, potential impacts include:
Constriction of fluvial flow resulting in increased flood risk;
Disturbance to stream banks and/or substrate which could lead to increased erosion and local
changes to fluvial geomorphology, direct loss or damage to aquatic habitats or species or a local
increase in suspended sediment concentrations causing a temporary decrease in local water quality;
Disturbance to stream banks and shallow groundwater flows, resulting in indirect loss or degradation
to adjacent/down gradient GWDTE habitats;
Sediment contamination of the watercourse from plant movement near the works; and
Spillages or leaks of other contaminants such as fuels or oils which could enter the watercourse.
Wind Turbine Foundations and Crane Hardstandings
7.114. The Development includes the construction of 12 wind turbines and associated crane hardstandings.
Turbines are proposed to be constructed in the following surface water catchments:
Naden and Greenbooth catchment (9);
Watershed of Naden and Greenbooth and Spring Mill and Prickshaw catchment (1); and
Greens Moor catchment (2).
7.115. To reduce the potential for turbid runoff or other contaminants such as fuels or oils (used in
construction) from entering surface watercourses, wind turbines and associated crane hardstandings
have all been located a minimum distance of 50m away from all OS mapped watercourses. The wind
turbines will be supported on concrete foundations, measuring up to 3m in depth and up 20m width,
(see Figure 4.3). Construction of the turbine foundations will involve the excavation of peat and
CPL PAGE 7-31
Rooley Moor Wind Farm Environmental Statement
subsoil, which will either be bunded and stored prior to the in-situ casting of a steel-reinforced
concrete slab. Surplus peat will be used for habitat restoration (see the outline PMP in Appendix 7.2),
and to batter the edges of tracks and platforms, or landscaping local to each turbine. Excavation areas
will have sides that are 'battered' back to ensure that they remain stable during construction. Each
foundation is expected to require approximately 390m3 of concrete and 55 tonnes of steel reinforcing.
Hardstanding areas will be constructed adjacent to each turbine, orientated to make best use of
topography and prevailing wind conditions, with an area of approximately 25m by 40m (33m by 40m, if
turbine is located at the end of an internal track).
7.116. There is potential for concrete spillages during turbine foundation construction, which could migrate
into groundwater or to down gradient surface water features. Concrete is highly alkaline and corrosive
and any spillage can adversely affect water quality. Concrete is only mobile for a short period of time
before it sets and therefore the potential for migration of concrete into groundwater would only occur
for a short duration until it begins to set.
7.117. The areas of unconfined bedrock aquifers may be at risk of contamination from concrete in the event
of a spillage. The potential risk will be confirmed by an intrusive ground investigation prior to works
commencing. Controls will be required to prevent mobilisation of any concrete spills overland to
surface water features and into groundwater.
7.118. It is recognised that not all turbines are situated on topographical high points and some turbine
locations will be subject to ephemeral surface runoff pathways which will convey runoff during rainfall
events during construction. A draft Drainage Management Plan (DMP) is presented as Appendix 4.4
and a final DMP will be presented post consent, prior to any construction activity. This document will
describe how to manage flows across the Development Area during construction and this will include
management of flows at each turbine location, during and post construction. This plan will take into
account the potential for flows from up gradient areas as well as managing runoff from the turbine
location. Design of drainage will seek to mimic existing local surface water runoff regimes, such that
there will be no change in quantity of runoff into downstream receiving watercourses.
7.119. When excavating for construction of the turbine foundations, it is possible that groundwater will be
encountered. Excavations may need to be dewatered to lower groundwater levels and ensure that wet
working and direct contact of cement material with groundwater does not occur. This will mean that
there is potential for loss of recharge and interruption of existing groundwater regimes in the
immediate locality.
7.120. The impact on any PWS is not expected to be significant as the placement of turbines has avoided
PWS sub-catchment areas.
7.121. The PSRA (Appendix 7.3) identifies areas of moderate peat slide risk located close to Clegg ding,
Red Pits and the Top of Leach; these have been largely avoided where practical. Turbines T4 and T8
are located in areas of moderate peat slide risk and turbine T10 is located on the up gradient
periphery of an area of moderate risk. A peat slide in this location has the potential to cause a release
of peat sediments into the Naden and Greenbrook catchment resulting in a significant reduction in
surface water quality. Additional mitigation will be required to reduce the risk of peat slide in this area.
7.122. The majority of turbines have been located off areas of deeper peat and active bog. The placement of
turbines T18, T16, T15 and T14 are in areas of M3 bog pool community which is considered to be
active. The placement of the turbines will result in direct loss of habitat (considered in Chapter 8:
Ecology). During the construction phase, turbine foundation excavations will locally dewater the peat
body and physically deteriorate the peatland structure leading to erosion and runoff pf peat mater into
downstream water bodies. The continued presence of turbines during the operational phase will also
result in disruption to hydraulic continuity in the peat body. Mitigation will be required to ensure
CPL PAGE 7-32
Rooley Moor Wind Farm Environmental Statement
disruption to this habitat is minimised and secondary impacts, such as peat drying and erosion are
effectively managed.
7.123. The placement of turbines has avoided all moderate and highly groundwater dependent habitats and
therefore there will be no impact to these receptors.
Electric Cables
7.124. Electric cables for the Development will be installed within small trenches (approximately 1.8m wide
and 0.5m deep) that will run alongside the access tracks. The majority of the cable route will be
located on bedrock, with some shorter sections crossing areas of peat.
7.125. There is potential for cable trenches to transport turbid water from works areas to drainage channels
and surface watercourses down gradient.
Substation Compound and Control Building
7.126. The proposed location of the control building and substation compound is shown on Figure 4.9. The
building will be situated within a 35m x 25m compound, incorporating car parking and storage yard.
The control building and substation compound will be located in the south of the site and built directly
onto the PLCM bedrock, there is no peat in this area. As a result, there will be no significant impact on
peat.
7.127. Both the substation and control buildings are located over 50m up gradient of the nearest watercourse
which flows towards the east through the Snipe Barn Farm PWS sub-catchment. During the
construction phase, excavation of bedrock and soils stripping may generate sediment laden runoff.
Furthermore, any spillages of concrete or other contaminants such as fuel or oils may impact upon
groundwater quality.
7.128. It is unlikely that the excavation of foundations would result in any significant dewatering as foundation
depths are estimated to be up to a maximum of 1.0m below ground level.
Temporary Construction Compound
7.129. An indicative layout for the construction and laydown compound is shown in Figure 4.10. The
compound will have dimensions of approximately 85m x 65m. The area will be prepared by carefully
stripping soil and peat in accordance with best practice guidance, laying down geotextile material and
then a working surface of stone. The stripped material will be stored adjacent to the site for
subsequent use in reinstatement and screening.
Borrow Pits
7.130. Borrow pits will be constructed to provide stone for the wind farm infrastructure. No stone will be
bought onto site. The proposed borrow pit locations have been selected because of their morphology,
accessibility from existing or new access tracks, orientation and the expected proximity of rock to the
surface. It is proposed to construct two borrow pits, details are listed in Table 7.12 below.
Table 7.11 Borrow Pit Details
Borrow Pit ID Location Surface Area Max Depth Volume Extracted
Borrow Pit 1 386458, 416930 250m x 68m 3.5m 40,000m3
Borrow Pit 2 386104, 417915 137m x 105m 7m 60,000m3
CPL PAGE 7-33
Rooley Moor Wind Farm Environmental Statement
7.131. Without appropriate mitigation measures the construction of borrow pits results in the following
potential to impacts to water resources by:
Excavating and disruption of peat resources;
Disruption of groundwater storage and flow through excavation below the water table;
Generation of suspended solids to surface water;
The disruption to established drainage patterns through extraction/stockpiling activities; and
Surging of surface run off which has collected in excavated borrow pit areas.
7.132. Upon completion, the borrow pits will be partially reinstated. This will involve the reworking of faces to
stabilise them, partial infilling with surplus material and landscaping with peat (where there was
originally peat habitat) and soils excavated during the wind farm construction. There may also be the
potential for environmental enhancement by creating small wetlands or other desirable habitats.
Operation 7.10.2
7.133. This section provides a summary of potential impacts prior to mitigation measures being implemented,
but on the basis that good site practices will be employed. It is based on an assessment of activities
that will occur during the operational phase of the Development which are presented below.
7.134. The potential impacts (and the likelihood of them occurring) to identified sensitive receptors during the
operational phase are summarised in Table 7.12, along with an assessment of their significance.
Access tracks and Watercourse Crossings
7.135. The tracks are designed to last for the life of the Development and only limited maintenance is
envisaged during operation. The tracks will be constructed from compressed aggregate, which could
be eroded by surface water over time. There will be low volumes of traffic throughout the operational
phase (see Chapter 12 Access, Traffic and Transport).
7.136. Potential effects during operation of the Development from the presence of access tracks and
watercourse crossings include:
Increased sediment loading in surface watercourses from runoff from tracks caused by traffic
movement or the erosion of tracks;
The potential for spills and leakages of potentially polluting substances such as fuels and oils from
plant and vehicles which could migrate to surface watercourses or groundwater;
Increased flood risk due from watercourse crossings and tracks; and
Change in local groundwater flow regimes with may reduce recharge to sensitive areas located down
gradient of tracks.
7.137. The likelihood of spillages or leaks of fuels or oils will be much reduced during the operational phase,
compared with during construction. Sources will be limited to fuel from vehicles visiting the
Development Area, lubricants and oils used in the turbines substation and transformers and foul
drainage produced by the limited numbers of staff visiting the application site. To further reduce the
likelihood of spills occurring and to reduce any impacts if spills do occur, similar best practice
measures that were applied during construction will be implemented.
7.138. All tracks and watercourse crossings are outside floodplain areas, however their presence has the
potential to increase flood risk during the operational phase. The presence of tracks will slightly
decrease the overall permeability of the Development Area, resulting in slight increases in runoff rates
CPL PAGE 7-34
Rooley Moor Wind Farm Environmental Statement
during rainfall events. However, even when combined with other hardstanding areas within the
Development Area, the increase in hardstanding area represents negligible proportion of the total area
of the surface water catchments within and downstream of the application site. Therefore, the
presence of tracks is unlikely to result in a measurable increase in surface water runoff rates from the
Development Area.
7.139. Watercourse crossings have the potential to constrict the watercourses resulting in flows backing up
and increasing the risk of flooding upstream. The design of watercourse crossing culverts will reduce
the likelihood of channels becoming constricted or crossings becoming blocked, with the actual design
of crossings to be agreed at the detailed design stage.
Control Building, Substation and Hardstanding Areas
7.140. Potential impacts from the control building, substation building and hardstanding areas during
operation are not considered to be high or likely. The buildings will be visited infrequently during
operation of the wind farm and are located outside of a floodplain area. The small quantity of sewage
arising from visits of maintenance staff will be stored in septic tanks and removed periodically by a
licensed contractor.
7.141. Rainwater collection systems would be installed to provide water for flushing which, if necessary,
would be topped up with water brought to site in containers. Excess rainwater falling on the roof of the
buildings will be discharged to an infiltration drain or other SUDS based drainage system around the
compounds. The buildings will not be of a size to intercept significant quantities of water and no
impact is expected to groundwater/surface water at the application site.
7.142. No impacts are anticipated as a result of the presence of this infrastructure.
Wind Turbines, Foundations and Crane Hardstandings
7.143. The physical presence of turbine foundations may locally change groundwater flow regimes. Runoff
over turbine bases will be directed back to undisturbed ground using toe drains where necessary, and
there will be a negligible loss of recharge. Cut-off drains will also be used to direct runoff to ground.
These measures will be designed not to act as preferential migration pathways.
7.144. The impact on any PWS is not expected to be significant as the placement of turbines has avoided
PWS sub-catchment areas.
7.145. In addition there is the potential to decrease the water quality of down gradient surface watercourses
due to spills or leaks from oil or other potentially polluting substances. However, the likelihood of this
occurring is low and volumes of any spills are not expected to be substantial. To reduce the likelihood
of spills or leaks from turbines, each turbine will be designed with fluid catch basins and containment
systems to prevent accidental releases from leaving the nacelle. Any accidental gear oil or other fluid
leaks from the wind turbines would be contained inside the towers as they are sealed around the
base, with the entrance situated above ground level.
7.146. The design of the foundations will ensure that there are no water quality impacts to downstream
surface watercourses or groundwater from the use of concrete. Foundations will be constructed using
sulphate resistant concrete, which will ensure no degradation or subsequent pollution when in contact
with acidic water during the lifetime of the Development.
7.147. The reinstatement of the turbine foundation area (comprising back filling the foundation area over the
subsurface foundations with excavated soil and re-vegetating to allow for the natural infiltration of
surface water) will assist in the reinstatement of groundwater recharge mechanisms and will ensure
no significant change to overall groundwater regimes.
CPL PAGE 7-35
Rooley Moor Wind Farm Environmental Statement
Borrow Pits
7.148. Borrow pits will have been decommissioned and partially reinstated in the construction phase so no
impact is expected during this phase.
Decommissioning 7.10.3
7.149. The Development will have a planned operational life of up to 25 years. At the end of this period,
unless permission for continued operation as a wind farm is granted, it will be decommissioned. The
ultimate decommissioning methods will be agreed with Rochdale Metropolitan and Rossendale
Borough Councils and other appropriate regulatory authorities (e.g. DEFRA, Natural England). The
site will be reinstated post decommissioning through a programme of habitat restoration, in
accordance with an agreed decommissioning plan.
7.150. It can be anticipated the decommissioning process will comprise:
Wind turbines: To be dismantled, removed from the site and disposed of appropriately;
Foundations: The majority will be left in-situ. The top metre of the base will be removed and disposed
of appropriately. The area re-surfaced with topsoil or peat and restored appropriately;
Underground cabling: These will be left in-situ or removed for recycling;
Access tracks and hardstandings: These will be left in-situ to be used by the landowner;
Water Crossings: these will be left in suit as they are integrated into access tracks;
Anemometry masts: These will be dismantled, removed from the site and disposed of appropriately.
The foundations will remain in-situ. The top metre of the base will be removed, disposed of
appropriately, then covered with top soil or peat and restored;
Site access: All access tracks will be left in-situ; and
Wind farm control building, substation and compound: The equipment will be removed and disposed
of appropriately. The building will be demolished and the material removed from the site. The top 1m
of the foundations will be removed then covered over with topsoil or peat and restored appropriately.
7.151. Potential impacts during the decommissioning phase will reflect the impacts predicted for construction,
however substantially less activity is anticipated during this period. There will be some limited
earthworks associated with the removal of turbines, buildings and the anemometry masts. The
removal of site infrastructure has the potential to cause a temporary decline in water quality from the
generation of turbid runoff migrating to down gradient surface watercourses and associated receptors,
and it is assessed that the likely potential impact would be moderate.
7.152. There is also potential for minor impacts associated with a temporary decrease in water quality from
spills or leakage of fuels, oils or other potentially polluting substances from vehicular and plant
movement on site, the storage and use of chemicals and the maintenance of plant. To reduce the
likelihood of spills occurring and to reduce any impacts if spills do occur, similar best practice
measures that were applied during construction will be implemented.
7.11 Summary of Potential Impacts and Mitigation Measures
7.153. Potential impacts prior to mitigation during construction, operation and decommissioning are
summarised in Table 7.12 Summary of Predicted Impacts. An indication of whether additional
mitigation is required or not is also included.
CPL PAGE 7-36
Rooley Moor Wind Farm EIA
Table 7.12 Summary of Predicted Impacts
Activity Potential impact Receptor Sensitivity
of receptor
Magnitude of
potential
impact
Evaluation
of potential
impact
Likelihood
of
occurrence
Likely
potential
impact
Mitigation
required?
CONSTRUCTION
Construction
of site
infrastructure
A temporary decrease in
water quality from the
generation of turbid or
discoloured runoff
migrating to down
gradient surface
watercourses and
associated receptors
Surface water
(all surface
water
catchments)
High Moderate Moderate Possible Moderate
Construction
of
watercourse
crossings
Disturbance to stream
banks causing changes in
erosion rates and local
morphology
Surface water
(Springmill &
Prickshaw,
Naden &
Greenbooth
catchments
only)
High Medium Moderate Likely Moderate
Blockage or constriction of
watercourses causing an
increase in flood risk
Surface water
(Springmill &
Prickshaw,
Naden &
Greenbooth
catchments
only)
High Medium Moderate Possible Moderate
Construction
of
hardstanding
areas such as
Increase in runoff rates
causing an increase in
flood risk
Surface water
(all surface
water
High Low Minor Possible Minor
CPL PAGE 7-37
Rooley Moor Wind Farm EIA
Activity Potential impact Receptor Sensitivity
of receptor
Magnitude of
potential
impact
Evaluation
of potential
impact
Likelihood
of
occurrence
Likely
potential
impact
Mitigation
required?
tracks,
compounds,
turbine
foundations
and buildings.
catchments)
Vehicular and
plant
movement
onsite;
storage and
use of oils and
chemicals;
maintenance
of plant
A temporary decrease in
water quality from spills or
leakage of fuels, oils or
other potentially polluting
substances
Surface water
(all surface
water
catchments)
High High Major Possible Moderate
Groundwater Medium Medium Moderate Likely Moderate
Construction
of the access
tracks and
turbine
foundations
Disruption of PWS
supplies
Groundwater
and Surface
water
Medium Medium Moderate Rarely Negligible
Disruption to peat
hydrology and consequent
degradation of peat
Geology Medium Medium Moderate Likely Moderate
Decrease in water quality
of watercourses located
down gradient of a peat
slide occurrence.
Surface water
(all surface
water
catchments)
High Medium Major Rarely Minor
Dewatering of
groundwater
in the
construction
A temporary decrease in
water quality from the
generation of turbid runoff
migrating to down
Surface Water
(Springmill and
Prickshaw
only)
High Medium Major Possible Moderate
CPL PAGE 7-38
Rooley Moor Wind Farm EIA
Activity Potential impact Receptor Sensitivity
of receptor
Magnitude of
potential
impact
Evaluation
of potential
impact
Likelihood
of
occurrence
Likely
potential
impact
Mitigation
required?
of foundations
and borrow
pits
gradient surface water
receptors including PWS
Loss of groundwater
recharge and change of
local groundwater regimes
potentially causing indirect
loss of PWS
Groundwater Medium Medium Moderate Likely Moderate
Disruption to peat
hydrology and draining of
peat
Geology Medium High Moderate Likely Moderate
Excavation of
peat during
the
construction
of site
infrastructure
Disturbance and
degradation of peat Geology Medium Medium Moderate Likely Moderate
OPERATION
Vehicular use
of tracks and
watercourse
crossings /
other site
activities
A temporary decrease in
water quality from the
generation of turbid runoff
migrating to down
gradient surface
watercourses and
associated receptors
Surface water
(all surface
water
catchments)
High Medium Major Rarely Minor
A temporary decrease in
water quality from spills or
leakage of fuels, oils or
Surface water
(all surface
water
High Medium Moderate Possible Minor
CPL PAGE 7-39
Rooley Moor Wind Farm EIA
Activity Potential impact Receptor Sensitivity
of receptor
Magnitude of
potential
impact
Evaluation
of potential
impact
Likelihood
of
occurrence
Likely
potential
impact
Mitigation
required?
other potentially polluting
substances
catchments)
Groundwater Medium Low Low Rarely Negligible
Presence of
watercourse
crossings
Blockage or constriction of
watercourses causing an
increase in flood risk
Surface water High Low Moderate Rarely Minor
Presence of
turbine
foundations
Changes to local
groundwater flow regimes
resulting in drying out of
peat resources down
gradient
Geology Medium Low Minor Likely Minor
Changes to surface water
runoff patterns and rates
which could increase flood
risk
Surface water High Low Moderate Rarely Minor
Use of control
building and
substation
A temporary decrease in
water quality from spills or
leakage of fuels, oils or
other potentially polluting
substances such as
sewage
Surface water High Medium Moderate Rarely Minor
Groundwater Medium Medium Low Rarely Negligible
Reinstatement
of Borrow pits
Reinstatement of borrow
pits with peat to create
new bog wetland areas
Geology Medium Medium Moderate Likely Moderate (positive
effect)
DECOMMISSIONING
Removal of
site
A temporary decrease in
water quality from the
generation of turbid runoff
Surface water High Medium Major Possible Moderate
CPL PAGE 7-40
Rooley Moor Wind Farm EIA
Activity Potential impact Receptor Sensitivity
of receptor
Magnitude of
potential
impact
Evaluation
of potential
impact
Likelihood
of
occurrence
Likely
potential
impact
Mitigation
required?
infrastructure migrating to down
gradient surface
watercourses and
associated receptors
Vehicular and
plant
movement
onsite;
storage and
use of oils and
chemicals;
maintenance
of plant
A temporary decrease in
water quality from spills or
leakage of fuels, oils or
other potentially polluting
substances
Surface water High Medium Major Possible Moderate
Groundwater Medium Medium Low Rarely Minor
CPL PAGE 7-41
Rooley Moor Wind Farm Environmental Statement
7.12 Mitigation Measures
Access Tracks 7.12.1
7.154. Tracks will be either of ‘excavated’ type tracks (estimated 5.0km proposed), constructed on areas
with less than 1.0m depth of peat, or ‘floating’ type tracks (estimated 1.8km proposed) constructed
on areas of peat greater than 1.0m depth. This design of tracks is proposed in order to minimise
the volume of peat excavated during construction, minimise the mobilisation of peat fines from
excavation areas and preserve unimpeded groundwater flow.
7.155. Construction of access tracks and their continued use during the construction phase may
potentially generate turbid runoff, which could follow topographic grades to surface watercourses
and associated receptors. Any potential impacts to surface watercourses are expected to be
localised and short term only. Pollution prevention and sediment and drainage control measures
described in EA PPG notes and CIRIA guidance will be formalised within the CEMP. The
contractors will be required to comply with this document. The document will specifically outline
how surface water runoff will be managed during construction.
7.156. Trackside drains will be provided to control runoff from construction areas especially during heavy
rainfall events. Trackside drainage will comprise either buffer strips or infiltration trenches which will
be unlined to allow the standing water to infiltrate back into the ground. Tracks will have a camber
to encourage runoff adjacent to trackside drains. The drains will have the potentially to convey
entrained sediments within runoff and will discharge into a swale or buffer area of adequate
capacity to prevent discharge directly into any surface watercourse. There will be no direct
discharge of construction drainage to any existing watercourse.
7.157. To mitigate any potential reduction to groundwater recharge from track construction and to allow
the passage of any sub-surface flows, constructed tracks will comprise a semi-permeable surface
to allow some infiltration.
7.158. To limit potential pollution impacts from either hardcore and/or excavated material entering
watercourses, or increased sediment levels within surface water runoff, the principle contractor will
be required to adhere to measures and controls set out in the CEMP and PMP during construction.
These measures will include, but not be limited to:
Any excavated soil/peat that will be used in the construction of access tracks (e.g. to dress the
sides of the tracks once backfilled) are to be temporarily placed on the furthest side away from any
identified watercourse or drain;
The provision of buffer strips around watercourses or drainage channels on sections of track
adjacent to watercourse crossings;
Procedures during excavations and soil handling for both routine working and during any
environmental emergencies to control and mitigate both erosion and dust generation; and
Trackside ditches will be unlined to allow water to soak back into the ground resulting in no
significant loss to groundwater recharge.
7.159. The degree of disturbance and degradation of peat resources has been minimised in the design of
the track. This has minimised the direct loss of peat resources. Further details regarding the
excavation, storages and reinstatement procedures are presented in the outline PMP (Error!
Reference source not found.). The majority of the site’s access tracks will be constructed using a
cut and fill methodology. Excavated peat from cut and fill sections of access tracks will be used for
dressing the side slopes of track sections and potentially for landscape screening bunds. Peat
turves will also be replaced on constructed roadside drainage channel embankments where
possible. Only peat turf and fibrous peat is likely to be suitable for battering road verges. When
constructing tracks rapid restoration will be undertaken as track construction progresses.
Immediately following construction some turves will be replaced along the road edges to allow
quicker re-vegetation and soften the road edges
CPL PAGE 7-42
Rooley Moor Wind Farm Environmental Statement
7.160. The design and construction of tracks on peat will be done in such a way so as to reduce impacts
on and maintain the existing peat hydrology at the site. The built track will allow for the
transmittance of water, so natural drainage can be maintained as much as possible.
7.161. Floating tracks avoid the need to excavate the peat and re-fill with imported rock. However, the
weight of the track structure can cause compression of the underlying acrotelm resulting in reduced
transmittance of water, resulting in pond of water upgradient of tracks and derogation of water
supply down gradient of tracks. Drainage through the floating track will be maintained using drains
constructed at regular points through the peat.
Watercourse Crossings 7.12.2
7.162. All watercourse crossings on site are considered to be minor crossings (i.e. narrow watercourse,
relatively flat gradients, low velocity flows), all of which will be crossed via culverts. It is proposed
these crossings will be formed from plastic or pre-cast concrete culverts, with the size based on the
calculation of peak flow from the upstream catchment to enable a 0.5% AEP flow (including an
allowance for climate change on future rainfall intensities) to be passed through the culvert. The
actual design of each culvert will be agreed at the detailed design stage, with all culverts designed
and constructed in accordance with EA and CIRIA good practice guidance and the designs agreed
with EA prior to construction. The design of each crossing will take into consideration overland flow
routing in the event of a blockage and to enable flow to be directed back into the watercourse
downstream of any obstruction.
7.163. It is proposed culverts will be embedded so that the base is at grade with the streambed or lower to
maintain bed form processes and minimise disruption to wildlife migration. The need for ledges to
enable the movement of mammals through the pipe will be assessed at the design stage and
incorporated as necessary.
7.164. Disruption to channel banks during the construction of crossings will be minimised by the use of
cofferdams and over-pumping if the channel exhibits potential for high flows during the construction
period. Pollution prevention measures as outlined in the CEMP will be implemented to reduce the
likelihood of sediment or other contaminants entering adjacent watercourses
Wind Turbine Foundations and Hardstandings 7.12.3
7.165. To reduce the potential for turbid runoff or other contaminants such as fuels or oils (used in
construction) from entering surface watercourses, wind turbines and associated crane
hardstandings have all been located a minimum distance of 50m away from all OS mapped
watercourses.
7.166. It is recognised however not all turbines are situated on topographical high points and some turbine
locations will be subject to ephemeral surface runoff pathways which will convey rainfall runoff
during rainfall events. A site drainage plan will be specified within the CEMP to manage flows
across the site and this will include management of flows at each turbine location, during and post
construction. This plan will take into account the potential for flows from up gradient areas as well
as managing runoff from the turbine location.
7.167. When excavating for construction of the turbine foundations, it is possible that groundwater will be
encountered. If this occurs, excavations will be dewatered to lower groundwater levels and ensure
that wet working and direct contact of cement material with the groundwater does not occur. This
will mean that there is potential for loss of recharge and interruption of existing groundwater
regimes in the immediate locality, potentially affecting sensitive peat habitats. Any water will be
pumped out and passed to a settling lagoon to allow suspended sediment to settle. Treated water
will be discharged to an area of vegetated ground designated for drainage allowing seepage into
the ground. There will be no direct discharge of pumped groundwater to adjacent watercourses or
drainage channels. Further details on this will be included within the CEMP and will be agreed with
the EA prior to construction commencing.
CPL PAGE 7-43
Rooley Moor Wind Farm Environmental Statement
7.168. Excavations will remain open for the shortest time practical to limit the effect of any dewatering.
There will be no discernible overall loss of recharge to groundwater; however some areas will
experience minor localised change to flow regimes through excavations and the introduction of
turbine foundations. Recharge from drainage channels will compensate for localised reduction in
infiltration as a result of the presence of the foundations acting as a barrier to groundwater flow.
7.169. There is potential for concrete spillages during turbine foundation construction, which could migrate
into groundwater or surface water. Concrete is highly alkaline and corrosive and any spillage can
have adversely affect water quality. To minimise the likelihood of spillages, concrete will be brought
to site ready mixed and the wagons will enter and leave the site through a designated site
entrance, and all vehicle washouts will take place off-site. Temporary bunds will be placed
downslope of pouring operations to contain any spillages. In the event of a spillage, an incident and
emergency response plan will be initiated. This will be detailed in the CEMP.
7.170. It is understood that migration of concrete in groundwater can occur in highly fractured and fast
flowing groundwater environments (Environment Agency, 2001). Prior to pouring concrete within
turbine excavations, the degree of weathering or fracturing of bedrock will be assessed. If the
bedrock is highly fractured, it may be necessary to form a barrier within the excavation to ensure
liquid concrete does not come into contact with underlying groundwater. Either a geotextile liner or
a sand layer would restrict the flow of concrete into the surrounding groundwater. This will be
determined by an intrusive ground investigation prior to works commencing. It should be noted that
once concrete is poured it is only mobile for a short period of time before it sets and therefore the
potential for migration of concrete in such groundwater conditions would only occur for a short
duration until it begins to set.
7.171. Measures of the disturbance and degradation of peat resources during and after the construction of
turbine foundations and hardstanding areas are detailed in the outline PMP (Error! Reference
source not found.). It is envisaged that the majority of the excavated peat materials from turbine
foundation excavations will be reused for the purpose of borrow pit restoration, which will be
restored to create bog habitats. Some peat will be replaced around the turbine base excavations,
and re-turfed. Peat will also be spread over the areas disturbed by turbine construction activities,
around the crane hardstandings, rotor assembly hardstandings and other areas used in the
construction phase. Where appropriate, excess peat turves may be used for screening bunds,
landscaping or as material for use as part of the HMP, in conjunction with reseeding.
Substation Compound and Temporary Construction Compound 7.12.4
7.172. During construction of the substation and temporary construction compounds, a surface layer of
vegetation and topsoil will be removed and a shallow foundation will be dug. The cleared area will
be filled with aggregate and then a temporary surface (e.g. geotextile) placed on top. During
construction, oil, fuel and other substances will be stored in a storage area within the compound.
The area will also be used as a base for refuelling of equipment.
7.173. Indicative floodplain mapping provided by EA shows that all infrastructure are completely within
areas of low risk of fluvial inundation. However, there may be localised surface water flows
(particularly during rainfall events) that may need to be diverted around this area. This will be
particularly important because oil, fuel and other substances will be stored within the building
temporary construction compound. Drainage management including the control of runoff in this
area will be included in the CEMP. Surface water flows in the area will be further managed by the
use of crushed and compacted granular stone in the foundations. This will allow water to infiltrate
the foundations, thereby reducing peak surface water flows from the area.
Electric Cabling 7.12.5
7.174. There is potential for cable trenches to transport turbid water from works areas to drainage
channels and surface watercourses down gradient. To prevent this, where possible, trenches will
be dug during dry weather. This will reduce the likelihood of any excavated material being
CPL PAGE 7-44
Rooley Moor Wind Farm Environmental Statement
mobilised in the trenches. Sand will be placed in the trenches, with the cables placed over the top.
To prevent water tracking along trenches, clay plugs or appropriate plugging material will be used
in short (typically 1m) sections, with the distance between plugs dependent on the track slope.
7.175. Excavated material will then be replaced as quickly as possible to reduce the period of time that
trenches are open. While the trenches are open, impermeable barriers (made of clay or other
impermeable material) will be placed at intervals along the open length of the trench. This will
reduce the likelihood of trenches becoming preferential flow paths and their capacity to transport
turbid runoff to downstream
Borrow Pits 7.12.6
7.176. A system of drainage ditches or temporary interception bunds will be constructed to intercept any
surface run off from entering the borrow pit areas. Intercepted surface water runoff will be diverted
away to open ground and allowed to discharge. No intercepted/dewatered water will be allowed to
discharge directly to surface watercourses.
7.177. Consideration will be given to the stability of surface soils where collected surface
water/groundwater is diverted and water collected within borrow pit areas would be treated in the
same way. Furthermore, consideration will be given to ensure that water is not discharged to
ground directly up gradient or within the sub-catchment of sensitive PWS.
7.178. Where necessary, surface water and groundwater will be passed through temporary settlement or
silt traps before being discharged to ground (e.g. silt busters or settlement tanks). All interception
bunds and drainage ditches will be fully reinstated once extraction from the borrow pits is
completed. Water entering the borrow pits will need to be removed by either gravity drainage
design or pumping depending on the overall morphology of the pit. The general topography in the
areas identified is conducive to gravity drainage owing to the moderate to steep slopes. All
discharges of groundwater will follow advice set out in PPG 6: Working at Construction and
Demolition sites. If, following detailed design, dewatering of any of the borrow pits is considered
necessary, all dewatering would be designed in accordance with CIRIA guidance C532 entitled
“Control of Water Pollution from Construction Sites (2001)”
7.179. It is not anticipated that there will be widespread groundwater present when the borrow pits are
being excavated due to the elevation of the proposed structures relative to local springs. Any
collection and discharge of groundwater would be dealt with in a similar way to surface water;
being passed through a settlement trap before being discharged to ground. Prior to excavation of
the rock all surface soils and peat will be removed and stockpiled for use in the reinstatement of the
borrow pits. The stockpiles will be located and battered so as to limit instability and erosion. Silt
fences and mats will be used to minimise sediment levels in runoff from the stockpiles.
7.180. Following detailed design of the dewatering operations for any given borrow pit, the EA and the
local council will be consulted to confirm the environmental acceptability of any dewatering
proposals to be provided in the CEMP.
7.181. Prior to any construction or extraction taking place all details relating to the borrow pit will be
detailed in the CEMP that will be circulated to the EA and the local authorities for approval before
works can commence. This plan will detail how the Development would be constructed and all the
necessary mitigation measure to be put in place to mitigate environmental impacts. This would
include the general approach to the works and also site specific actions to deal with highlighted
risks. In addition this plan will document all environmental monitoring works and emergency
response procedures. This plan would typically include information such as:
An emergency response plan with key contact list for emergency services and emergency
procedures clearly defined;
A site drainage plan;
A site chemical product and waste inventory;
CPL PAGE 7-45
Rooley Moor Wind Farm Environmental Statement
A site waste management plan;
A protocol of environmental monitoring procedures and employment of suitable qualified
environmental staff; and
Details on compliance with PPGs and CIRIA guidance and any imposed planning conditions.
7.182. Measures to the disturbance and degradation of peat resources during and after the construction of
borrow pits will be detailed in the PMP (Appendix 7.2). Borrow pit design, including design of the
restoration, will take account restoration objectives relating to habitat and environment. In particular
they will be designed such that water levels within the restored habitat can be maintained at ground
level, to allow water-logged conditions to be maintained. This can be achieved by excavating the
borrow pits downslope where possible, allowing the downslope worked face to retain high water
levels within the restored area thus preventing reinstated peat from drying out.
7.13 Residual Effects
7.183. Potentially significant impacts prior to mitigation (either moderate or high) (as described in Section
7.10) have been carried forward for the assessment of residual effects. Those impacts of minor or
negligible significance have not been taken forward to this stage. Likely potential significant
impacts (prior to mitigation) during construction are limited to only moderate impacts to surface
water and geology. During operation, likely potential significant impacts (prior to mitigation) are
limited to minor impacts on surface water, which are not considered to be significant and therefore
have not been brought forward to this section.
Construction 7.13.1
Surface Water
7.184. Likely significant potential effects prior to mitigation that were taken forward for the assessment of
residual effects to surface water include the following moderate effects:
A temporary decrease in water quality from the generation of turbid runoff migrating to down
gradient surface watercourses, downstream public water supply reservoirs and PWS which may
receive surface water runoff from the construction of site infrastructure;
Disturbance to stream banks causing changes in erosion rates and local morphology from the
construction of watercourse crossings; and
A decrease in water quality of watercourses located down gradient of a peat slide occurrence.
7.185. Following the implementation of mitigation measures, the likelihood of potential effects has been
reduced from moderate to minor and therefore no residual significant effects remain to surface
water during construction.
Geology
7.186. Likely significant potential effects prior to mitigation that were taken forward for the assessment of
residual effects to geology include moderate effects to peat including:
The disruption to peat hydrology and consequent degradation of peat down gradient of access
tracks;
The disruption of peat hydrology and the draining of peat due to the dewatering of groundwater
during the construction of turbines and borrow pits; and
The disturbance and degradation of peat due to excavation of peat for the construction of site
infrastructure.
CPL PAGE 7-46
Rooley Moor Wind Farm Environmental Statement
7.187. Following the implementation of mitigation measures, the likelihood of potential effects has been
reduced from moderate to minor and therefore no residual significant effects remain to geology
during construction.
Groundwater
7.188. There are no likely significant potential effects taken forward for the assessment of residual effects
and therefore no residual effects to groundwater remain.
Operation 7.13.2
Surface Water
7.189. Prior to mitigation, there are potential moderate impacts to surface water from the vehicular use of
tracks and site activities during operation. After mitigation, the likelihood of potential impacts
occurring is reduced to possible and only minor residual effects are expected.
Groundwater and Geology
7.190. There are no significant negative potential impacts to groundwater or geology expected during
operation. Ecological enhancement and peatland restoration measures set out within the HMP
(Chapter 8: Ecology) and the restoration of the borrow pit areas are anticipated to result in a
moderate positive effect over time as ecology re-establishes.
Decommissioning 7.13.3
Surface Water
7.191. Likely significant potential effects prior to mitigation that were taken forward for the assessment of
residual effects to surface water include moderate effects limited to a temporary decrease in water
quality from the generation of turbid runoff migrating to down gradient surface watercourses and
associated receptors from the removal of site infrastructure.
7.192. Following the implementation of mitigation measures, the likelihood of potential effects has been
reduced from moderate to minor and therefore no residual significant effects remain to surface
water during decommissioning.
Groundwater and Geology
7.193. There were no significant negative potential effects to groundwater and geology taken forward for
the assessment of residual effects and therefore no residual effects to groundwater or geology
remain during decommissioning. Restoration measures set out within the HMP should continue to
enhance the ecological environment including peatland habitat throughout and beyond the
decommissioning phase.
7.14 Cumulative Impacts
7.194. The potential for cumulative effects relates to proposed or existing developments which are either
hydraulically connected to the Development Area, or which drain to the same receiving
environment. Potentially significant cumulative hydrological, hydrogeological or geological impacts
are usually only likely if wind farms are to be constructed/decommissioned at the same time as the
majority of potentially significant impacts occur during construction/decommissioning phase.
7.195. There are 42 wind farm sites either under construction or at the planning stages within 35km of
Rooley Moor. Of these, 18 wind farms are located in surface water catchments which drain to the
same surface water receptors as Rooley Moor. These are shown in Table 7.14 below.
CPL PAGE 7-47
Rooley Moor Wind Farm Environmental Statement
Table 7.13 Wind Farms within same receiving surface water catchments
Wind Farm Name Status No. of Turbines Catchment
Reaps Moss Construction 3 River Irwell
Crook Hill Construction 12 River Spodden
Todmorden Moor Construction 5 River Irwell
Scout Moor Operational 26 Naden and Greenbooth
Reservoir, River Roch and
River Irwell
Scar End Farm Consented 4 River Irwell
Sillinghurst Farm Consented 1 River Irwell
Veterans Farm Consented 1 River Roch
Stand Lees Farm Consented 1 River Roch
Bottomly Bank Farm Consented 2 River Irwell
Height Side Farm Consented 1 River Irwell
Parrock Farm Consented 1 River Irwell
Crown Farm Consented 1 River Irwell
Gorpley Planning 4 River Irwell
Beet Farm Planning 1 River Roch
Under Brow Farm Planning 1 River Irwell
Wallsclough Planning 1 River Irwell
Scout Moor infill Scoping 6 Naden and Greenbooth
Reservoir, River Roch and
River Irwell
Scout Moor Northern
Extension
Scoping 16 Naden and Greenbooth
Reservoir, River Roch and
River Irwell
7.196. The magnitude of impact is likely to be highest in catchments where wind farms are in close
proximity. Scout Moor, Scout Moor infill and Scout Moor Northern wind farms are located within
5km of the Rooley Moor Wind Farm site, however, Scout Moor is operational and Scout Moor Infill
and Scout Moor Northern are only at scoping stages. It is highly likely construction will not have
started on these sites by the time the Rooley Moor construction phase ends, thus removing the risk
of significant cumulative impacts in the Naden and Greenbooth public water supply reservoirs,
Rivers Irwell and Roch.
7.197. The Todmorden, Reaps Moss and Crook Hill wind farms are all under construction. These wind
farms are located over 5km from the proposed Rooley Moor Wind Farm. As these wind farms are
under construction already, it is considered unlikely that there wold be any overlap in the
construction phase with Rooley Moot, resulting in no significant cumulative impacts.
7.198. The majority of the consented wind farms are single turbine developments on farms. Due to the
size of these developments and the relatively minor disruption they will cause, impacts to the water
and geological environments from these wind farms are likely to be negligible. Furthermore, the
CPL PAGE 7-48
Rooley Moor Wind Farm Environmental Statement
small scale of the developments means construction will likely be completed by the time Rooley
Moor construction phase commences.
7.199. Two slightly larger wind farms, Gorpley and Scar End Wind Farm are in planning or have been
consented. The Hydrology, Hydrogeology and Geology EIA chapter for Gorpley and Scar End
Farm Wind farm have been reviewed. In both cases, no significant residual impacts were expected
following the implementation of appropriate mitigation. Both wind farms are within the River Irwell
catchment, however they are in separate subcatchments to the Rooley Moor Wind Farm and
situated over 5km from the Development Area. Due to distance of these sites from the
Development Area, the cumulative effects and resultant significance of impact on the hydrological
environment is not anticipated to be significant.
7.15 Summary and Conclusions
7.200. Overall the residual effects of the Proposed Development on the hydrological, hydrogeological and
geological environments following the implementation of avoidance and mitigation measures are
considered to be minor or less than minor. Residual impacts are limited to:
A temporary decrease in surface water quality during construction and to a lesser extent, during
decommissioning from the generation of turbid runoff migrating to down gradient surface
watercourses;
A temporary decrease in surface water quality during construction in the event of a peat slide
causing peat to migrate to down gradient into surface watercourses;
Disturbance to stream banks causing changes in erosion rates and local morphology during the
construction and potential removal of watercourse crossings; and
Disturbance, degradation and draining of peat during construction.
7.201. With the adoption of a comprehensive CEMP, the incorporation of standard good practice
techniques and with the avoidance measures already taken into account in the design of the
Development, the potential changes to surface water, groundwater and geological environments
are not predicted to be significant.
7.202. There is potential for cumulative effects to down gradient surface watercourses during construction
if the construction periods of the Scout Moor Infill and Scout Moor North projects coincide. As these
EIAs have yet to be written an assessment of cumulative impacts is not yet possible, however, it is
likely these wind farms will need to adopt similarly stringent mitigation measures to ensure no
significant impacts occur, resulting in no significant cumulative impacts.
7.16 References
7-1 Institute of Environmental Management and Assessment (IEMA) guidance (2004)