Rock Removal on the Middle Mississippi River

35
BUILDING STRONG ® Rock Removal on the Middle Mississippi River 1 RRAT 2014

description

Rock Removal on the Middle Mississippi River. RRAT 2014. Navigation Channel Design. Develop a Reliable, Safe, and Environmentally Sustainable Navigation Channel on the Middle Mississippi River. 1,500 feet long. 9 feet deep. - PowerPoint PPT Presentation

Transcript of Rock Removal on the Middle Mississippi River

Page 1: Rock Removal on the Middle Mississippi River

BUILDING STRONG®1

Rock Removal on the Middle Mississippi River

RRAT 2014

Page 2: Rock Removal on the Middle Mississippi River

BUILDING STRONG®2

9 feet deep

1,500 feet long

Navigation Channel Design

During low water periods required to maintain a 9 feet deep and a minimum of 300 feet wide navigation channel, with

additional width in bends

Develop a Reliable, Safe, and Environmentally Sustainable Navigation Channel on the Middle Mississippi River

Page 3: Rock Removal on the Middle Mississippi River

BUILDING STRONG®

Why is River Industry Important

3

Page 4: Rock Removal on the Middle Mississippi River

BUILDING STRONG®

Regulating Works Project Benefits vs. Costs

4

Page 5: Rock Removal on the Middle Mississippi River

BUILDING STRONG®5

Pools vs Open River

MVS

Pools 300-195

Open River 195-0

Page 6: Rock Removal on the Middle Mississippi River

BUILDING STRONG®6

Lock & Dam #24, Clarksville, MO

Pools: Impounded Mississippi RiverUpper River (RM 300-195)

Page 7: Rock Removal on the Middle Mississippi River

BUILDING STRONG®7

Tools To Maintain Navigation(Open River RM 195-0)

Dikes and other Rock Structures

Weirs

Revetments

Dredging

Rock Removal

Page 8: Rock Removal on the Middle Mississippi River

BUILDING STRONG®8

Rock RemovalWhat are we trying to remove?

MVS N

NThebesGrand Tower

Mississippi River

Page 9: Rock Removal on the Middle Mississippi River

BUILDING STRONG®9

Problem Statement

Low Mississippi River stages will impact the St. Louis Districts’ ability to maintain the navigation channel at authorized project dimensions, in the Thebes Reach (RM

46-38) and Grand Tower Reach (RM 80-79), in the mid-December 2012.

Pinnacle Rock

Thebes Reach

Page 10: Rock Removal on the Middle Mississippi River

BUILDING STRONG®10

Phase 1 Engineering AnalysisPinnacle Rock Impacts at Thebes Reach

St. Louis from -5.0 to -7.0A-Minimum

B-Unacceptable

GTA B C D E F G H

-3.0 - -4.0 300+ 300 300 300+ 300+ 300+ 300+ 300-4.0 - -5.0 300 300 300 300 300 300 300+ 300-5.0 - -6.0 300 300 300 190 300 300 NONE 150-6.0 - -7.0 300 150 300 170 300 300 NONE 150

A

M

U

Minimally Acceptable for a 20 (4x5) Barge Tow (300 ft maximum channel or

will have less than 9' depth)

ST. L

OU

IS

GAG

ETHEBES

Acceptable Channel Condition for a 20 (4x5) Barge Tow (300+ ft wide channel)

questionable channel width to flank through bend or for alignment purposes.

Unacceptable Channel Conditions for a 15 (3x5) Barge Tow (channel

C-Minimum

D-UnacceptableE-Minimum

F-Minimum

G-Unacceptable

Page 11: Rock Removal on the Middle Mississippi River

BUILDING STRONG®11

PHASE 1: • Accomplishes a 300 ft minimum channel in 4 locations that previously had insufficient width and depth.• The resultant channel can only support 15 barge tow. Larger tows must “double-trip” or break their tow apart and take

individual pieces separately through the reach.

PHASE 1 MILESTONES • 7 December 2012 – Decision made to go Urgent & Compelling

- Award 2 contracts based on sources sought query (Newt & Durocher)• 7 December 2012 – Received verbal approval on Justification & Approval• 7 December 2012 – Contract award. Letter contracts 50% ROM, Newt & Durocher • 11 January 2013 – Minimum channel requirements achieved through Thebes Gage 0’ (approx -7’ STL Gage)• 29 January 2013 – Contracts definitized to include modifications• 27 February 2013 – Phase 1 Completed• 1,000 cubic yards of material was removed at a cost of $8M

Rock Pinnacle Removal Phase 1

This what a 20 barge tow may look like trying to navigate through a 300 ft wide channel. Notice that there is no roomfor error considering the boxes along the channel border show additional phases of rock removal.

Acceptable Channel Condition for a 20 (4x5) Barge Tow (300+ ft wide channel)

Minimally Acceptable – at risk for a 20 (3x5) Barge Tow (300 ft maximum) channel or questionable channel width to flank through bend or foralignment purposes.

What Phase 1 Accomplished Thebes A B C D E F G H

3.9 - 3.0 300+ 300+ 300 300+ 300+ 300+ 300+ 300+

2.9 - 2.0 300+ 300+ 300 300+ 300 300 300+ 300+

1.9 - 1.0 300+ 300+ 300 300+ 300 300 300+ 300+

0.9 - 0.0 300+ 300+ 300 300+ 300 300 300+ 300+

A BC

D

G

E F

Page 12: Rock Removal on the Middle Mississippi River

BUILDING STRONG®12

Rock Pinnacle Removal

Typical view of rock formation impacting the navigation channel

Navigation Channel

DS View - Rock Pinnacles near River Mile 41, Thebes, IL

Page 13: Rock Removal on the Middle Mississippi River

BUILDING STRONG®13

Rock Pinnacles at River Mile 38.5Thebes Reach

Illinois Missouri

300 ft Minimum Channel

Phase 2 Rock Removal

Highest Pinnacle

Provided Cross Section

Page 14: Rock Removal on the Middle Mississippi River

BUILDING STRONG®14

Current Water Level

Removal Elevation

River Bed

Low Water Channel

Water Depth at 0 Thebes (9 ft Channel After Removal)0 Thebes (9 ft)

Water Depth at 1-29-13 0800 was 5.8 ft at Thebes

2 Thebes (11 ft)

4 Thebes (13 ft)

6 Thebes (15 ft)

1 Thebes (10 ft)

-1 Thebes (8 ft)

-2 Thebes (7 ft)

3 Thebes (12 ft)

5 Thebes (14 ft)

7 Thebes (16 ft)

8 Thebes (17 ft)

-4 Thebes (5 ft)

-3 Thebes (6 ft)

-5 Thebes (4 ft)

-6 Thebes (3 ft)

-7 Thebes (2 ft)

-8 Thebes (1 ft)

-9 Thebes (0 ft)

Gage Reading (Depth after

Removal)

Geometry of a cross section at RM 38.5 (Not to Scale)

Rock Pinnacles

Cross Section at River Mile 38.5

Page 15: Rock Removal on the Middle Mississippi River

BUILDING STRONG®

Rock Removal Surveys

15

Page 16: Rock Removal on the Middle Mississippi River

BUILDING STRONG®

Rock Removal Surveys

16

Page 17: Rock Removal on the Middle Mississippi River

BUILDING STRONG®17

Rock Removal Methodologies• Environmental Assessment required us to “minimize the impact of the

environment”

16,000 lb hydro-hammer

Page 18: Rock Removal on the Middle Mississippi River

BUILDING STRONG®18

Rock Removal Methodologies

4.5 ton Grapple Drill & Blast

Page 19: Rock Removal on the Middle Mississippi River

BUILDING STRONG®

Rock Removal - Drill and Blast Method

Courtesy of NWP19

Page 20: Rock Removal on the Middle Mississippi River

BUILDING STRONG®

Rock Removal - Drill and Blast Method

Courtesy of NWP20

Page 21: Rock Removal on the Middle Mississippi River

BUILDING STRONG®21

Rock Removal QA/QC

Page 22: Rock Removal on the Middle Mississippi River

BUILDING STRONG®

Rock Removal Phase 2 Base FY14

22

• 2 July – Awarded Rock Removal Phase 2 to Massman Construction for contract minimum of $1M

• Includes a base and 3 option years, total contract amount$19M to remove 6,300 cy• NTP given on 27 November.• Massman on site 7 December with removal beginning on 11 December.• Locations have been prioritized to minimize the impacts to navigation during the

months of December and January .• To date approximately 750 cy of material has been removed, 50% of the base

contract.

CB

D E

Page 23: Rock Removal on the Middle Mississippi River

BUILDING STRONG®

C

B

Rock Removal Phase 2 ThebesRiver Miles 46-43Massman Construction

AB

D

E

F

G

C

Removal CompleteUnder ConstructionNot Started

D

Minimum 300 feet Navigation Channel

PinnacleID

PinnacleLocation

PinnacleQuantity (cys) Date Started

%Complete

DateCompleted

RemovalMethod

C-100 B 312 3-Feb-2014 50% MechanicalC-101 B 16 3-Feb-2014 50% MechanicalC-102 C 116 0%C-103 C 117 0%C-104 C 312 0%C-105 D 1 14-Jan-2014 100% MechanicalC-106 D 174 11-Dec-2013 100% MechanicalC-107 D 114 12-Dec-2013 95% MechanicalC-108 D 333 14-Jan-2014 90% MechanicalC-109 D 11 14-Jan-2014 91% MechanicalC-110 D 18 0%C-111 E 3 0%

Page 24: Rock Removal on the Middle Mississippi River

BUILDING STRONG®

Rock Removal Phase 2 ThebesRiver Miles 46-43

Massman Construction

AB

D

E

F

G

C

Removal CompleteUnder ConstructionNot Started

Minimum 300 feet Navigation Channel

E

PinnacleID

PinnacleLocation

PinnacleQuantity (cys) Date Started

%Complete

DateCompleted

RemovalMethod

C-100 B 312 3-Feb-2014 50% MechanicalC-101 B 16 3-Feb-2014 50% MechanicalC-102 C 116 0%C-103 C 117 0%C-104 C 312 0%C-105 D 1 14-Jan-2014 100% MechanicalC-106 D 174 11-Dec-2013 100% MechanicalC-107 D 114 12-Dec-2013 95% MechanicalC-108 D 333 14-Jan-2014 90% MechanicalC-109 D 11 14-Jan-2014 91% MechanicalC-110 D 18 0%C-111 E 3 0%

Page 25: Rock Removal on the Middle Mississippi River

BUILDING STRONG®

Sites B, C, D, E ThebesRiver Miles 46-43

Massman Construction Update (As of 2-27-2014)

Hydro Hammer at C-106

Excavation at C-106

Page 26: Rock Removal on the Middle Mississippi River

BUILDING STRONG®

Rock Removal Phase 2 Option 1 ThebesRiver Miles 44-42

Massman Construction

AB

D

E

F

G

C

Removal CompleteUnder ConstructionNot Started

Minimum 300 feet Navigation Channel

E

PinnacleID

PinnacleLocation

PinnacleQuantity (cys)

Date Started

%Complete

DateCompleted

RemovalMethod

C-100 E 337 0%C-101 E 3 0%C-102 E 21 0%C-103 E 10 0%C-104 E 11 0%C-105 E 1 0%C-106 E 1 0%C-107 E 179 0%C-108 E 38 0%C-109 E 145 0%C-110 E 16 0%C-111 E 7 0%C-112 E 3 0%C-113 E 7 0%C-114 E 3 0%

Page 27: Rock Removal on the Middle Mississippi River

BUILDING STRONG®

Rock Removal Phase 2 Option 1 ThebesRiver Miles 44-42

Massman Construction

AB

D

E

F

G

C

Removal CompleteUnder ConstructionNot Started

Minimum 300 feet Navigation Channel

F

PinnacleID

PinnacleLocation

PinnacleQuantity (cys)

Date Started

%Complete

DateCompleted

RemovalMethod

C-115 F 46 0%C-116 F 178 0%C-117 F 75 0%C-118 F 12 0%C-119 F 14 0%C-120 F 16 0%C-121 F 1 0%C-122 F 31 0%C-123 F 1 0%C-124 F 150 0%

Page 28: Rock Removal on the Middle Mississippi River

BUILDING STRONG®

Rock Removal Stage Requirement

28

Page 29: Rock Removal on the Middle Mississippi River

BUILDING STRONG®29

Rock Removal at RM 44.8

Page 30: Rock Removal on the Middle Mississippi River

BUILDING STRONG®30

Rock Removal at RM 44.8June 2006 Survey

Page 31: Rock Removal on the Middle Mississippi River

BUILDING STRONG®31

Rock Removal at RM 44.8October 2012 Survey

Page 32: Rock Removal on the Middle Mississippi River

BUILDING STRONG®32

Rock Removal at RM 44.8February 2013 Survey

Page 33: Rock Removal on the Middle Mississippi River

BUILDING STRONG®33

Reporting Incorrect Information

Page 34: Rock Removal on the Middle Mississippi River

BUILDING STRONG®34

Current Water Level

Removal Elevation

River Bed

Low Water Channel

Water Depth at 0 Thebes (9 ft Channel After Removal)0 Thebes (9 ft)

Water Depth at 1-29-13 0800 was 5.8 ft at Thebes

2 Thebes (11 ft)

4 Thebes (13 ft)

6 Thebes (15 ft)

1 Thebes (10 ft)

-1 Thebes (8 ft)

-2 Thebes (7 ft)

3 Thebes (12 ft)

5 Thebes (14 ft)

7 Thebes (16 ft)

8 Thebes (17 ft)

-4 Thebes (5 ft)

-3 Thebes (6 ft)

-5 Thebes (4 ft)

-6 Thebes (3 ft)

-7 Thebes (2 ft)

-8 Thebes (1 ft)

-9 Thebes (0 ft)

Gage Reading (Depth after

Removal)

Geometry of a cross section at RM 38.5 (Not to Scale)

Rock Pinnacles

Cross Section at River Mile 38.5

Page 35: Rock Removal on the Middle Mississippi River

BUILDING STRONG®35

Questions ?