Module 9
Module 9 Robust 8D
1
Robust 8D
The Purpose of this module is to clearly define
Ford Customer Service Division (FCSD)
expectations as it relates to completion of 8Ds in
response to service quality rejects
2
Module 9 Robust 8D
Understand the components of an 8D and FCSD’s
expectations in terms of 8D content Examples provided
Know the importance of containment at each link
in the supply chain
3
Module 9 Robust 8D
8D is:
A Problem-solving methodology for product
and process correction and improvement
Simple and effective problem solving technique
Structured into eight disciplines(D1-D8)
Emphasizes team synergy
4
Module 9 Robust 8D
5
Module 9 Robust 8D
The focus of D1 is to establish the team necessary to solve
the problem and implement corrective actions and to begin
the team building process
When determining team membership:
Limit membership to between four and 10 members
Choose members with the right skills, knowledge, resources, authority, etc., to solve the problem at hand
Choose the right mix of qualifications
Change team membership as needed
6
Module 9 Robust 8D
A description of the problem provided by Ford. This field can’t be modified. The description will provide the following:
Statement of the problem found
Information for the packaging label
Picture of the nonconforming part and if available the correct part
If applicable packager information
7
Module 9 Robust 8D
When you develop an ICA, you:
Protect the customer from the effects of the problem
Contain the problem from a cost, quality and timing
perspective
8
Module 9 Robust 8D
Containment process consists of D1-D3◦ Enter into QIM within 2 business days of receiving a
quality reject
9
Module 9 Robust 8D
D1 Establish the Team
• Name, Title, Email and Phone Number, for each team
member
D2 Problem Description
• Description created by FCSD and is view only for a Supplier
D3 Interim Containment
• Define, Stock in Facility, Stock In Transit, Stock at Packager,
Similar Parts and Other
10
Module 9 Robust 8D
Facility Packager
• Are parts at a
Packager?• If so, are we
certain that they meet spec.?
• If uncertain, advise disposition
of parts at packager
• Are parts in transit
to a Ford facility?
• Are parts in transit to a Packager
facility?
• Are Like parts affected?
In Transit Similar Parts
• What is the fallout
rate of parts inside the manufacturing
plant?• What is being done
immediately to ensure no defective
parts leave the plant?
• Have RH or LH
parts been identified with the
defect?• Are parts of a
different color affected?
• Are parts a level up or down
affected?
◦ “Contained 375 door trim panels in house, no problems
found”.
◦ “Found and fixed 30 pieces of RH rocker arms identified as
LH in warehouse”.
◦ “No headliners to contain, all pats made to order”.
◦ “500 wheel covers contained, no gloss problems found”.
◦ “100 crankshafts in finished goods, 50 have corrosion and
50 are rust free”.
11
Module 9 Robust 8D
Report if any of the rejected part or any “like parts are in your facility.
◦ “20 pieces XL3Z-1130-AA, 12 pieces XL#Z-1131-AA, ‘X’
pieces of similar parts ‘Y’ & ‘Z’ are in transit. Conveyance #
: LMNOP”
◦ “Contacted packager, all like product in transit contained.”
◦ “No Product in transit.”
◦ “Shipped 1000 pieces of the rejected part on (3/1/15.)”
12
Module 9 Robust 8D
Report if any of the rejected part or any “like parts are on their way toward FCSD depots or Packagers in a truck.
◦ “Informed Packager the parts they have in house are nonconforming. Worked with the Packager to exchange
parts for parts to specification”
◦ “This part nor similar parts currently at the Packager.”
13
Module 9 Robust 8D
Report if any of the rejected part or any “like parts are at a packager or at FCSD.
o Ask yourself and report:
• “What ‘like’ parts did we ship with the ‘rejected’ parts”?
o Parts across different car lines
• Escape, Focus, Mustang, etc.
o Various colors shipped
o Model years shipped
o RH vs. LH parts
o Different engineering levels
14
Module 9 Robust 8D
Report if Similar Parts are involved with this concern.
Focus on the process, not the people
What has changed?
Multiple Root CausesMost likely causes
Weight multiple root causes (i.e. 80% or 20% at fault)
Utilize Quality Tools5 Whys
Review Process Flow Diagram for Escape Points
Is / Is Not
Fishbone Diagram
15
Module 9 Robust 8D
Used to identify the fault. Cross functional team asks “Why” 5
times in effort to determine root cause. Built into the QIM
system.
16
Module 9 Robust 8D
Example
• Fault: Wrong part was shipped
1. Why? Parts were labeled incorrectly
2. Why? New service part number launched at supplier
3. Why? Engineering part number changed and it was
assumed the Service part number should change
4. Why? Failure to properly manage the change
5. Why? Lack of understanding of Ford Service parts and
failed to ship according to their release
17
Module 9 Robust 8D
Used to understand how the problem escaped to the
customer and identify the escape point:
Review the process flow focusing on the location in the process
where the root cause occurred.
Determine if a control system exists to detect the problem.
Are service unique requirements included?
Is / Is Not – Used to develop the correct Problem Statement…Ask: What’s wrong with what?
Ask Next: Do we know why this is happening?
18
Module 9 Robust 8D
19
Module 9 Robust 8D
• A graphical representation used to organize and display the interrelationships of
various possible root causes of a problem.
• Possible causes of a potential defect or failure are organized in categories and
subcategories in a horizontal tree-structure, with the failure as the root node.
Current change over process (or lack of change over
process) allows mixed product to be shipped to customers
Once the part became “service only” production was
moved to a line with no poke-yoke
Change implemented internally, but Ford was not notified via proper channels (SREA, WERS Alert)
Change was approved via SREA by Ford, but no new
notice was issued and no new print was approved
20
Module 9 Robust 8D
D5 focuses on decision making and verification.
By focusing on these two steps, you can: Make the best decisions based on benefits and risks
Verify that the chosen solution will work
Any PCA you choose should: Fix the problem at the root cause level
Generate no additional problems
Be verified to work
21
Module 9 Robust 8D
◦ Revised current change over process to include first piece
and last piece inspection at each change over
◦ Developed a process to ensure that the control plan and
PFMEA are followed when an OE part becomes “service
only” to ensure appropriate error proofing is in place
◦ Revised “Manage the Change” process to include validation
of revised Ford Notice and print, as well as PPAP approval
at level 3 to ensure customer approval pf the change
22
Module 9 Robust 8D
D6 is when you implement the PCA to eliminate the root cause
of the problem. Validation makes sure the PCA works as
intended after implementation.
Develop an implementation plan for the PCA
Once PCA has been validated to work, remove the Interim
Containment Action (ICA)
Monitor long-term results
23
Module 9 Robust 8D
◦ Since first and Last piece inspection implemented for all changeovers, 2 months ago, no discrepancies have been found
◦ Reviewed 3 specific part numbers that moved from OE to service only line. All 3 parts have documented “Manage the Change” review and original error proofing is still in place Include inspection date(s), part number(s), quantity
inspected, and inspection results
◦ Verified that new notice number, print, and Ford-approved PSW have been received for the last 3 design changes
24
Module 9 Robust 8D
Behind every problem that creates the need to do a G8D, there is at least one system, practice, procedure, or policy that allowed the problem to occur and escape.
Document changes to Procedures
Policies
Work instructions
PFMEA, Process Flow Diagram
Control Plan
Ensure that service specific processes are added to these documents
Train employees in the new procedures, etc.
Determine whether this PCA should be applied systemically Other manufacturing lines
Other Manufacturing plants
Document technical lessons learned
25
Module 9 Robust 8D
Sincerely recognize both team and individual
contributions
CelebrateTeam Commitment
Problem resolution
Process improvement
Be Creative
Be Timely
26
Module 9 Robust 8D
27
Module 9 Robust 8D
D1-Establish Team
Reference Desk Procedures
• QIM-DP-11-Input Supplier 3D Comments
• QIM-DP-13-Input Supplier 8D Comments
*Training Material for QIM can be found on the FCSD Supplier Quality Portal
28
Module 9 Robust 8D
D2-Problem Description (Automatically populated)
Attachments tab-◦ All supporting Documents including the picture of the nonconforming part and if available the
correct part
29
Module 9 Robust 8D
D3 - Supplier Containment
Note: For K type rejects written by a Packager use the “Stock at Packager” field below for the 3D Containment and Disposition responses.
30
Module 9 Robust 8D
31
Module 9 Robust 8D
D4-Root Cause
32
Module 9 Robust 8D
D5-Choose & Verify Perm. Corrective Actions
33
Module 9 Robust 8D
D6-Implement & Validate Perm. Corrective Actions
34
Module 9 Robust 8D
D7-Action(s) to Prevent Reoccurrence
35
Module 9 Robust 8D
D8-Congratulate Your Team