Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety Personnel: Walt Sondheim:...

25
Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety •Personnel: • Walt Sondheim: Mechanical Project Engineer • Don Lynch: PHENIX Chief Engineer • Robert Pak: Integration Manager

Transcript of Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety Personnel: Walt Sondheim:...

Page 1: Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety Personnel: Walt Sondheim: Mechanical Project Engineer Don Lynch: PHENIX Chief.

Robert Pak 1DOE VTX Review

June 2, 2009

Mechanical Integration & Safety• Personnel:

• Walt Sondheim: Mechanical Project Engineer

• Don Lynch: PHENIX Chief Engineer

• Robert Pak: Integration Manager

Page 2: Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety Personnel: Walt Sondheim: Mechanical Project Engineer Don Lynch: PHENIX Chief.

Robert Pak 2DOE VTX Review

June 2, 2009

Outline

• Mechanical Integration:• Assembly plan (WBS 1.5.3) under development• Beam pipe (WBS 1.5.4.1.1) procurement in progress • Detector support (WBS 1.5.4.1.2) started in FY09• Power & water in IR (WBS 1.5.4.2.1) progress off project• External cooling system (WBS 1.5.4.2.3) start in FY10• Infrastructure for dry N2 system completed

• Safety:• 1st ESRC meeting for VTX/FVTX on June 11th

Page 3: Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety Personnel: Walt Sondheim: Mechanical Project Engineer Don Lynch: PHENIX Chief.

Robert Pak 3DOE VTX Review

June 2, 2009

Assembly procedure overview

3

Main assembly L3/L4 assembly L1/L2 assembly

Page 4: Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety Personnel: Walt Sondheim: Mechanical Project Engineer Don Lynch: PHENIX Chief.

Robert Pak 4DOE VTX Review

June 2, 2009

Stripixel ladder installation on layer #4

Page 5: Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety Personnel: Walt Sondheim: Mechanical Project Engineer Don Lynch: PHENIX Chief.

Robert Pak 5DOE VTX Review

June 2, 2009

Stripixel layer #4 on transport frame

Page 6: Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety Personnel: Walt Sondheim: Mechanical Project Engineer Don Lynch: PHENIX Chief.

Robert Pak 6DOE VTX Review

June 2, 2009

Gas enclosure placed in support truss

Details in HPS-111008-0016 on VTX TWiki

Page 7: Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety Personnel: Walt Sondheim: Mechanical Project Engineer Don Lynch: PHENIX Chief.

Robert Pak 7DOE VTX Review

June 2, 2009

Space frame installed into support truss

Page 8: Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety Personnel: Walt Sondheim: Mechanical Project Engineer Don Lynch: PHENIX Chief.

Robert Pak 8DOE VTX Review

June 2, 2009

Barrel layer #4 installed into space frame

Page 9: Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety Personnel: Walt Sondheim: Mechanical Project Engineer Don Lynch: PHENIX Chief.

Robert Pak 9DOE VTX Review

June 2, 2009

Barrel layers #1&2 installed into space frame

Details in HPS-111008-0015 on VTX TWiki

Page 10: Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety Personnel: Walt Sondheim: Mechanical Project Engineer Don Lynch: PHENIX Chief.

Robert Pak 10DOE VTX Review

June 2, 2009

Be beam pipe final CAP from Brush Wellman

Smaller dia Be section

Page 11: Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety Personnel: Walt Sondheim: Mechanical Project Engineer Don Lynch: PHENIX Chief.

Robert Pak 11DOE VTX Review

June 2, 2009

Off Project

Page 12: Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety Personnel: Walt Sondheim: Mechanical Project Engineer Don Lynch: PHENIX Chief.

Robert Pak 12DOE VTX Review

June 2, 2009

Additional stainless transitions and spools

Quotes in-hand based on final drawings

Page 13: Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety Personnel: Walt Sondheim: Mechanical Project Engineer Don Lynch: PHENIX Chief.

Robert Pak 13DOE VTX Review

June 2, 2009

NEG coating and bake-out of beam pipe

• $106k for entire 47 ft warm straight section in PHENIX• CAD has taken responsibility for SS sections

|------+-------------------------------------------+------------|| Item | Description | Price ||------+-------------------------------------------+------------|| 1 | 5 m long pipe CF125/CF75 (dwg 44035003-03)| $23,250.00 ||------+-------------------------------------------+------------|| 2 | 1.75 m conical pipe CF125/CF75 (dwg | $12,450.00 || | 44035003-04) | ||------+-------------------------------------------+------------|| 3 | 0.55 m pipe CF75/CF40 (dwg 105-0500-40 | $12,000.00 || | -part 01) | ||------+-------------------------------------------+------------|| 4 | 2.03 m pipe CF75/CF40 (dwg 105-0500-40- | $12,000.00 || | part 02) | ||------+-------------------------------------------+------------|| 5 | 1.8 m long pipe, CF 125 | $12,450.00 ||------+-------------------------------------------+------------|| 6 | 2.57 m long Be-section pipe, CF 35 ( dwg | $27,750.00 || | 002 0500-019) | ||------+-------------------------------------------+------------|

• Quote from SAES Getters SpA, Lainate, Italy :

Page 14: Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety Personnel: Walt Sondheim: Mechanical Project Engineer Don Lynch: PHENIX Chief.

Robert Pak 14DOE VTX Review

June 2, 2009

Be beam pipe Schedule

• VTX, FVTX, PHENIX Management & CAD signed-off• Current ETA from Brush Wellman:

• 6 mos. to gun-drill Be tube (by mid-Oct. 2009)• Final assembly and QA (by mid-Nov. 2009)

• Deliver to BNL and reship to Europe for NEG coating• CERN to handle Be section (SAES refuses)• SAES Getters does all the rest

• Install prior to RHIC Run-11 (summer 2010)

Page 15: Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety Personnel: Walt Sondheim: Mechanical Project Engineer Don Lynch: PHENIX Chief.

Robert Pak 15DOE VTX Review

June 2, 2009

External support installed

Electrically isolated from central magnet pole tipsMeasurement of magnet vibrations proved negligible

Page 16: Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety Personnel: Walt Sondheim: Mechanical Project Engineer Don Lynch: PHENIX Chief.

Robert Pak 16DOE VTX Review

June 2, 2009

• Single support structure attached at 3 points to west detector sled

• 6 degrees of adjustment• East mirror images west

BNL concept for support truss

Page 17: Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety Personnel: Walt Sondheim: Mechanical Project Engineer Don Lynch: PHENIX Chief.

Robert Pak 17DOE VTX Review

June 2, 2009

2 DOF (Y & Z)

1 DOF (Z)

0 DOF

Kinematic mounts for mating east and west detector halves

6 interface points w/ HYTEC

Page 18: Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety Personnel: Walt Sondheim: Mechanical Project Engineer Don Lynch: PHENIX Chief.

Robert Pak 18DOE VTX Review

June 2, 2009

Mounts for theodolites to be installed

Provide stable location above beamline to shoot targets for CAD survey

Page 19: Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety Personnel: Walt Sondheim: Mechanical Project Engineer Don Lynch: PHENIX Chief.

Robert Pak 19DOE VTX Review

June 2, 2009

Platform for Electronics Racks

Off project

Shared infrastructure for VTX/FVTX/RPC electronics

Page 20: Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety Personnel: Walt Sondheim: Mechanical Project Engineer Don Lynch: PHENIX Chief.

Robert Pak 20DOE VTX Review

June 2, 2009

Platform water manifolds and cable trays

Platform Utilities

Platform water supply &

return flexible connections

Photos from D. Lynch, PHENIX Chief Engineer

Platform electrical

distribution and

disconnect

Off project

Page 21: Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety Personnel: Walt Sondheim: Mechanical Project Engineer Don Lynch: PHENIX Chief.

Robert Pak 21DOE VTX Review

June 2, 2009

Electronics rack lay-out

New Platform

HBD/RXNP(not shown)

MuTrgrFEE N

MuTrgrFEE S

VTX Power

FVTX

RPCS1

RPCN1

New Platform

RPCNS

VTX FEM

CAD courtesy of D. Lynch

Cooling system location under

discussion

Page 22: Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety Personnel: Walt Sondheim: Mechanical Project Engineer Don Lynch: PHENIX Chief.

Robert Pak 22DOE VTX Review

June 2, 2009

Cooling

F- Ion Extraction Test Report 10/21/2008Dele Fayemi3M Electronics Markets Materials DivisionTel: (651) 737-8115Email: [email protected] of 3M Novec 7000 and 7200 subjected to neutron irradiation received from Los Alamos National Laboratory were tested to determine if degradation had occurred. Decomposition was quantified through fluoride ion measurements as described in the 3M test method: “Fluoride ion extraction – indication of thermal decomposition”. The irradiated fluid samples showed slightly elevated, but insignificant fluoride ion levels when compared to control samples.Test ResultsThe results of the test are given in table 1. Table 1

InterpretationThe in-beam samples recorded average free fluoride ion concentration of ~0.03 ppm. Though these are elevated fluoride ion levels compared to the virgin samples, these concentrations are much less than 1 ppm and indicate insignificant degradation

beam

6.7x1011 Neq/cm2 integrated dose from LANSCE

Cooling Fluid has no problem from irradiation

Page 23: Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety Personnel: Walt Sondheim: Mechanical Project Engineer Don Lynch: PHENIX Chief.

Robert Pak 23DOE VTX Review

June 2, 2009

Bleed the boil-off5200 gal. capacity

LN2 Storage Dewar for Dry Nitrogren System shared by BBC/VTX/FVTX

Dry N2 System

Off project

Page 24: Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety Personnel: Walt Sondheim: Mechanical Project Engineer Don Lynch: PHENIX Chief.

Robert Pak 24DOE VTX Review

June 2, 2009

Safety

• 1st Experimental Safety Review Committee meeting for VTX/FVTX on June 11th

• Includes mechanical and electrical aspects• Participation from PHENIX and CAD safety experts

• In preparation, separate paperwork completed for VTX & FVTX• Design Review Questionnaire (14 page document)• CAD Hazard Identification Tool on the internet

Page 25: Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety Personnel: Walt Sondheim: Mechanical Project Engineer Don Lynch: PHENIX Chief.

Robert Pak 25DOE VTX Review

June 2, 2009

Summary

• Mechanical Integration:• Assembly plan (WBS 1.5.3) under development• Beam pipe (WBS 1.5.4.1.1) installed summer 2010• Detector support (WBS 1.5.4.1.2) started in FY09• Power & water in IR (WBS 1.5.4.2.1) progress off project• External cooling system (WBS 1.5.4.2.3) start in FY10• Infrastructure for dry N2 system completed

• Safety:• 1st ESRC meeting for VTX/FVTX on June 11th