Robert Pak 1DOE VTX Review
June 2, 2009
Mechanical Integration & Safety• Personnel:
• Walt Sondheim: Mechanical Project Engineer
• Don Lynch: PHENIX Chief Engineer
• Robert Pak: Integration Manager
Robert Pak 2DOE VTX Review
June 2, 2009
Outline
• Mechanical Integration:• Assembly plan (WBS 1.5.3) under development• Beam pipe (WBS 1.5.4.1.1) procurement in progress • Detector support (WBS 1.5.4.1.2) started in FY09• Power & water in IR (WBS 1.5.4.2.1) progress off project• External cooling system (WBS 1.5.4.2.3) start in FY10• Infrastructure for dry N2 system completed
• Safety:• 1st ESRC meeting for VTX/FVTX on June 11th
Robert Pak 3DOE VTX Review
June 2, 2009
Assembly procedure overview
3
Main assembly L3/L4 assembly L1/L2 assembly
Robert Pak 4DOE VTX Review
June 2, 2009
Stripixel ladder installation on layer #4
Robert Pak 5DOE VTX Review
June 2, 2009
Stripixel layer #4 on transport frame
Robert Pak 6DOE VTX Review
June 2, 2009
Gas enclosure placed in support truss
Details in HPS-111008-0016 on VTX TWiki
Robert Pak 7DOE VTX Review
June 2, 2009
Space frame installed into support truss
Robert Pak 8DOE VTX Review
June 2, 2009
Barrel layer #4 installed into space frame
Robert Pak 9DOE VTX Review
June 2, 2009
Barrel layers #1&2 installed into space frame
Details in HPS-111008-0015 on VTX TWiki
Robert Pak 10DOE VTX Review
June 2, 2009
Be beam pipe final CAP from Brush Wellman
Smaller dia Be section
Robert Pak 11DOE VTX Review
June 2, 2009
Off Project
Robert Pak 12DOE VTX Review
June 2, 2009
Additional stainless transitions and spools
Quotes in-hand based on final drawings
Robert Pak 13DOE VTX Review
June 2, 2009
NEG coating and bake-out of beam pipe
• $106k for entire 47 ft warm straight section in PHENIX• CAD has taken responsibility for SS sections
|------+-------------------------------------------+------------|| Item | Description | Price ||------+-------------------------------------------+------------|| 1 | 5 m long pipe CF125/CF75 (dwg 44035003-03)| $23,250.00 ||------+-------------------------------------------+------------|| 2 | 1.75 m conical pipe CF125/CF75 (dwg | $12,450.00 || | 44035003-04) | ||------+-------------------------------------------+------------|| 3 | 0.55 m pipe CF75/CF40 (dwg 105-0500-40 | $12,000.00 || | -part 01) | ||------+-------------------------------------------+------------|| 4 | 2.03 m pipe CF75/CF40 (dwg 105-0500-40- | $12,000.00 || | part 02) | ||------+-------------------------------------------+------------|| 5 | 1.8 m long pipe, CF 125 | $12,450.00 ||------+-------------------------------------------+------------|| 6 | 2.57 m long Be-section pipe, CF 35 ( dwg | $27,750.00 || | 002 0500-019) | ||------+-------------------------------------------+------------|
• Quote from SAES Getters SpA, Lainate, Italy :
Robert Pak 14DOE VTX Review
June 2, 2009
Be beam pipe Schedule
• VTX, FVTX, PHENIX Management & CAD signed-off• Current ETA from Brush Wellman:
• 6 mos. to gun-drill Be tube (by mid-Oct. 2009)• Final assembly and QA (by mid-Nov. 2009)
• Deliver to BNL and reship to Europe for NEG coating• CERN to handle Be section (SAES refuses)• SAES Getters does all the rest
• Install prior to RHIC Run-11 (summer 2010)
Robert Pak 15DOE VTX Review
June 2, 2009
External support installed
Electrically isolated from central magnet pole tipsMeasurement of magnet vibrations proved negligible
Robert Pak 16DOE VTX Review
June 2, 2009
• Single support structure attached at 3 points to west detector sled
• 6 degrees of adjustment• East mirror images west
BNL concept for support truss
Robert Pak 17DOE VTX Review
June 2, 2009
2 DOF (Y & Z)
1 DOF (Z)
0 DOF
Kinematic mounts for mating east and west detector halves
6 interface points w/ HYTEC
Robert Pak 18DOE VTX Review
June 2, 2009
Mounts for theodolites to be installed
Provide stable location above beamline to shoot targets for CAD survey
Robert Pak 19DOE VTX Review
June 2, 2009
Platform for Electronics Racks
Off project
Shared infrastructure for VTX/FVTX/RPC electronics
Robert Pak 20DOE VTX Review
June 2, 2009
Platform water manifolds and cable trays
Platform Utilities
Platform water supply &
return flexible connections
Photos from D. Lynch, PHENIX Chief Engineer
Platform electrical
distribution and
disconnect
Off project
Robert Pak 21DOE VTX Review
June 2, 2009
Electronics rack lay-out
New Platform
HBD/RXNP(not shown)
MuTrgrFEE N
MuTrgrFEE S
VTX Power
FVTX
RPCS1
RPCN1
New Platform
RPCNS
VTX FEM
CAD courtesy of D. Lynch
Cooling system location under
discussion
Robert Pak 22DOE VTX Review
June 2, 2009
Cooling
F- Ion Extraction Test Report 10/21/2008Dele Fayemi3M Electronics Markets Materials DivisionTel: (651) 737-8115Email: [email protected] of 3M Novec 7000 and 7200 subjected to neutron irradiation received from Los Alamos National Laboratory were tested to determine if degradation had occurred. Decomposition was quantified through fluoride ion measurements as described in the 3M test method: “Fluoride ion extraction – indication of thermal decomposition”. The irradiated fluid samples showed slightly elevated, but insignificant fluoride ion levels when compared to control samples.Test ResultsThe results of the test are given in table 1. Table 1
InterpretationThe in-beam samples recorded average free fluoride ion concentration of ~0.03 ppm. Though these are elevated fluoride ion levels compared to the virgin samples, these concentrations are much less than 1 ppm and indicate insignificant degradation
beam
6.7x1011 Neq/cm2 integrated dose from LANSCE
Cooling Fluid has no problem from irradiation
Robert Pak 23DOE VTX Review
June 2, 2009
Bleed the boil-off5200 gal. capacity
LN2 Storage Dewar for Dry Nitrogren System shared by BBC/VTX/FVTX
Dry N2 System
Off project
Robert Pak 24DOE VTX Review
June 2, 2009
Safety
• 1st Experimental Safety Review Committee meeting for VTX/FVTX on June 11th
• Includes mechanical and electrical aspects• Participation from PHENIX and CAD safety experts
• In preparation, separate paperwork completed for VTX & FVTX• Design Review Questionnaire (14 page document)• CAD Hazard Identification Tool on the internet
Robert Pak 25DOE VTX Review
June 2, 2009
Summary
• Mechanical Integration:• Assembly plan (WBS 1.5.3) under development• Beam pipe (WBS 1.5.4.1.1) installed summer 2010• Detector support (WBS 1.5.4.1.2) started in FY09• Power & water in IR (WBS 1.5.4.2.1) progress off project• External cooling system (WBS 1.5.4.2.3) start in FY10• Infrastructure for dry N2 system completed
• Safety:• 1st ESRC meeting for VTX/FVTX on June 11th