Road sustainability management - ULisboa abstract... · the benefits of sustainability is...
Transcript of Road sustainability management - ULisboa abstract... · the benefits of sustainability is...
Road sustainability management
The case of the rehabilitation of Marginal Oeiras to Cascais
Bruno Filipe Castanheira Costa
Extended abstract of the dissertation submitted to obtain the
degree of Master in Environmental Engineering
Jury
President: Professor Doutor António Jorge Gonçalves de Sousa
Supervisor: Professor Doutor Manuel Guilherme Caras Altas Duarte Pinheiro
Member: Professor Doutor Filipe Manuel Mercier Vilaça e Moura
November, 2012
2
Road Sustainability Management
The case of the rehabilitation of Marginal Oeiras to Cascais
Bruno Filipe Castanheira Costa
Technical University of Lisbon (UTL) - IST - Lisbon, Portugal
Abstract
A methodology was developed to identify the demand level of sustainability in road
infrastructures. This methodology was applied to the rehabilitation and operation phases. The
results show that it is possible to apply Life Cycle Assessment with developing values in criteria,
such as Low energy consumption (C7) and Carbon Intensity (C9) in the rehabilitation phase of
LiderA system.
The application to the case study consisting of several types of road infrastructures allows us to
emphasize that this methodology is able to be adjusted and applied to any kind of typology.
Moreover, this paper contributes to the positioning of the rehabilitation works in environmental
performance and to emphasize the good practices.
Keywords: Sustainability, Environmental performance, Sustainable road, Road infrastructure,
LiderA system, Life Cycle Assessment
1. Introduction
The road infrastructures have significant
impacts throughout their lifecycle (Pinheiro,
2006).
The environmental impacts produced by a road
infrastructure affect the landscape, micro-
climate, geology and hydrogeology, land use,
water resources, air quality, noise, flora and
fauna, cultural heritage, waste production and
social component (Pinheiro, 2011a).
Thus, it is important to achieve sustainability,
by generalizing methods and techniques which
will contribute to a higher environmental and
socio-economical performance in the
rehabilitation and the construction of such
infrastructures (EURF, 2009).
The purpose of this paper is to develop the
threshold of LiderA system (a Portuguese
sustainable assessment) by searching for good
environmental practices which may be applied
to the road infrastructure, that reflect a high
level of environmental performance, from a
sustainability perspective.
The main methodological steps consisted in
identifying environmental best practices in road
infrastructures based on existing rating
systems.
Then, it was identified the levels of
performance, and transformed into thresholds
levels (classes), in order to construct a metric
towards sustainability.
This methodology was applied to a case study,
particularly, the rehabilitation of the Estrada
Nacional Nº6, which connects Oeiras to
Cascais (EN6) (Ramos, 2010).
The methodology was also applied to EN6 in
the operation phase.
The results of this paper allowed us to obtain
an assessment of the environmental
performance of the rehabilitation works on
infrastructures intervened, and also in the
operation phase of EN6.
2. Green and sustainable roads
Nowadays, the use of rating system to quantify
the benefits of sustainability is increasingly
growing in popularity, also due to the fact that
there is an increasing environmental
awareness (Muench and Soderlund, 2011).
Furthermore, urban sprawl requires road
builders to approach on sustainability, in order
to face a lot of issues involving sensitive areas,
such as, air, soil, water, building materials,
energy use, biodiversity and among others.
A rating system of environmental performance
enables an update of the current state of best
practices in road construction to include new
technologies and know-how in the mitigation of
environmental impacts (Greenroads, 2010).
This system can evaluate the several parts of
the construction of roads and thereafter
3
evaluate it based on its environmental
performance.
This approach would be beneficial for the
design and construction of road networks, as
well as the maintenance of the existing road
infrastructures (Greenroads, 2010).
There are several approaches to assess the
environmental performance, such as,
Greenroads, CEEQUAL and LiderA systems.
2.1 Greenroads system
The Greenroads system is a collection of
sustainability best practices that apply to
roadway design and construction.
It is a rating system by obtaining credits for
approval of sustainable practices that exceed
the common practices. This rating system may
be used to certify a project based on the total
points achieved (Muench and Soderlund,
2011).
It appeared through a research project to
assess the sustainability of road infrastructures
developed by the University of Washington and
CH2M HILL in 2007 (Greenroads, 2010).
The Green Roads rating system is divided into
two general types: Project Requirements and
Voluntary Credits.
At minimum, every Greenroads project must
complete 11 specific activities, in order to be
qualified for any award.
The Project Requirements establish a
reference for any road project to achieve
certification and are intended for seeking
sustainable measures from design, planning,
construction, operation and maintenance
(Muench and Soderlund, 2011).
In addition to the Project Requirements, there
is a wide selection of Voluntary Credits that a
project can earn. (Muench and Soderlund
2011).
Each Voluntary Credits is associated with a
number of points (from 1 to 5) depending upon
the impact the credit has on sustainability.
Currently, there are 37 Voluntary Credits
totaling 108 points. The Greenroads system
also allows a project or organization to create
and use its own Voluntary Credits (called
“Custom Credits”), subject to approval of
Greenroads system, for a total of 10 more
points, which brings the total available points to
118.
The author (Glynn, 2009) said that by
encouraging sustainable transportation project
designs, we are taking significant steps to
conserve our natural resources, enhancing the
quality of our lives and reaffirming our
commitment to future generations.
2.2 CEEQUAL system
The CEEQUAL system was originally
developed by a team coordinated by the
Institution of Civil Engineers (ICE), with
financial support from Development Enabling
Fund (Pinheiro, 2006).
The application range is very wide, since it is
appropriate for any construction project
including roads, railways, airports, water
supply and treatment, power plants and trade.
The categories of evaluation of the system can
be assigned: Global Project (Designer or main
contractor); client and Designer; Project
(designer), Construction (main contractor) and
Design and Construction (for project teams,
does not include client) (Pinheiro, 2006).
The method consists of two steps, first is held
a self-assessment in which the client, the
designer and / or contractor presents a self-
assessment made by the assessor formed
CEEQUAL, gathering the documentation of
proof.
The second step consists in checking work of
the previous stage, by a verifier of CEEQUAL.
In order to follow a set guideline a manual was
created to define the criteria and 200 questions
that assessing several environmental aspects
(CEEQUAL, 2008).
The CEEQUAL system was based on
economic and financial models of its
customers based on the assessment of a wide
range of environmental and social issues,
including the effects on the community in
general.
The plan also includes indirect economic
issues through a set of questions that focus on
areas such as energy, materials and waste,
which can significantly influence the financial
result of a project (CEEQUAL, 2008).
2.3 Sustainable roads and good practices
In the last few years, the sector of road
infrastructures has been adopting a proactive
approach, taking into account environmental
and socio-economical parameters (Bryce,
2008).
4
The policy in the road sector is being targeted
based on economic interest and on the
adaptation of social concerns.
Ever more the principle that the infrastructure
is sustainable, is around the idea of being able
to face the changes that have an impact on the
own infrastructure, such as, durability and rate
traffic (Bryce, 2008).
Sustainable roads can be defined in many
ways, for example by (Bryce, 2008) that roads
must ensure performance in five major areas.
Figure 1- The five areas of sustainable roads (Bryce, 2008)
2.3.1 Watershed Driven Storm water
Management
The paving of roads based on the
incorporation of asphalt leads to soil sealing
causing serious problems in terms of water
lines (Bryce, 2008).
The consequences of reduced infiltration and
recharging aquifers correspond to increased
water stress and adverse impact on activities,
which are derived from use of these water
lines.
In addition to the problem of water stress, the
highways enhance the water pollution through
leachability of pollutants, such as,
hydrocarbons, heavy metals such as Arsenic,
Cadmium, Chromium, Copper, Nickel, Lead,
Zinc, among others, resulting from infiltration
through cracks or lateral areas not
waterproofed of the pavement (Bryce, 2008).
In modern times, the collected water is sent to
a drainage system and directed to the road
settling tanks, preventing direct discharge to
ground. Thus, it protects the water quality by
reducing the quantity of pollutants which are
dragged by leaching into water lines
surrounding (Grumbles, 2008).
There are several techniques to control
stormwater from the road, such as the case of
porous pavements, ditches bio-retention and
artificial wetlands and among others
(GreenHighways, 2011).
The construction and improvement of a road
should be an opportunity to modify and
redesign the management of water resources
in order to protect the reserves of groundwater,
rivers, wetlands and reduce flood risk (Bryce,
2008).
2.3.2 Life Cycle Energy and Emissions
Reduction
The construction of a road requires large
amounts of energy from the production of
materials (example: asphalt and cement) and
during operation.
The replacement of some materials can be a
solution for reducing energy consumption in
the construction of road infrastructures, such
as the replacement of cement by fly ash and
slag (USEPA, 2008).
Furthermore, the characteristics of the road
can help avoid traffic congestion, and
consequently the reduction of fuel consumption
and exhaust emissions (Bryce, 2008).
Since the extraction phase, with an impact on
natural regeneration of the raw material, to the
phases of production, transportation,
application and end-of-life there is a lot of air
emissions and hazardous waste generation,
among others.
Emissions related to industrial processes for
the production of materials may potentially be
reduced by using alternative materials (Bryce,
2008).
2.3.3 Recycle, Reuse and Renewable
The use of recycled materials in building a
road infrastructure can significantly reduce the
amount of material going to landfill and
reducing the amount of raw materials needed
(Bryce, 2008). Recycled materials derived from
industrial by-products allow to reduce
drastically the energy consumed in the
construction; reduce emissions of greenhouse
gases and reduce the overall cost of the
infrastructure.
Some examples of incorporation of recycled
materials are the reuse of layers of pavement
damaged, demolition waste, waste and by-
products of other industrial activities, such as
5
ash from combustion of coal, the use of used
tires, reducing to a minimum the consumption
of natural resources (Bryce, 2008).
According to the European Commission, about
3.5 million tons of scrap tires are added to
Europe stock of used tires every year. One
third of these tires were recycled in 2007,
mostly to make aggregate for use in road
construction, rehabilitation of quarries and
other projects (EURF, 2009).
2.3.4 Conservation and Ecosystem
Management
The conservation and management of
ecosystems have an important in minimizing
the impact of a road on local biodiversity.
In order to keep local biodiversity is important
to promote the preservation of habitats
(Pinheiro, 2011c).
The road infrastructures causing impacts on
natural ecosystems through habitat
fragmentation, changes in flows of water
resources, pressure on soil, among others.
The roads can promote the barrier effect due
to its development being more in length than in
width between ecosystems, resulting in a
threat to local biodiversity (Magina, 2008).
In the development of new road infrastructure,
it should find the most appropriate alignment in
the landscape to minimize the conflict between
the species and the road.
The management of the ecosystem
surrounding the road is to obtain solutions that
are compatible with the native biodiversity of
the region.
For example, in the surroundings of road
creates ecological corridors that connect
protected areas, enabling the continuity of the
species, and exchanges between individuals
Thus, promotes the evolution of ecosystems,
avoiding many situations trampling of animals
on roads (EURF, 2009).
2.3.5 Overall Societal Benefits
Over much time that sustainable construction
has been defined as a tool focused on the
natural environment and not based on the
effects of the environment on people.
The roads have an important impact on local
economies, the design of a road with a good
stretch can promote a business community
and a greater supply of local jobs (Bryce,
2008).
Furthermore, a poorly designed road can
directly or indirectly influence the business in
the region, forcing companies to seek new
locations for their facilities.
The roads are synonymous of flexibility in
terms of mobility. Currently, there are a set of
Intelligent Transport Systems which is an
extraordinary tool in the improvement of road
management to mobility, environment and
safety are enhanced (Molenaar, 2010).
3. LiderA System
System developed was the LiderA system for
road infrastructures (Pinheiro, 2011b).
The LiderA system is based on the concept of
reposition the building environment, from the
perspective of sustainability.
3.1 Methodology
The methodology is based on the use of an
environmental rating system for road
infrastructures, which aims to assess the
environmental performance of this type of
infrastructure.
The rating system used was the LiderA
system, whose own system was developed
and reformulated taking into account the
current state of the art.
Thus, a search was held on international rating
systems for road infrastructure, in particular,
the GreenRoads system of the United States
of America (USA) and the Civil Engineering
Environmental Quality and Assessment
Scheme system (CEEQUAL) from England.
The system consists of a set of areas that are
part a number of strands focused on this type
of infrastructure and a set of criteria that
specify the aspects to consider in each area.
Initially, all criteria previously defined were
analyzed in order to find a set of indicators that
would transform measurable criteria.
The indicators measured were subjected to
validation and refining processes through
meetings with the engineers responsible for
the rehabilitation works to be reliable
indicators.
Then, proceeded to the selection criteria that
are relevant both in the rehabilitation phase
and operation phase of the several
infrastructure intervened.
Thereafter, it developed the thresholds for
each criterion based on scientific research and
benchmarking. Depending on the type of
6
criteria thresholds can be quantitative or
prescriptive.
After the development of thresholds has
measured an average using the case study, in
order to frame these thresholds on scales
created by LiderA system.
Before the evaluation process was held for
each infrastructure a collection of data about
the location, characterization, and intervention
works.
In addition, during the course of rehabilitation
works there was a monitoring and verification
at the site of intervention works in order to
verify the existence of good practices.
Finally, based on the framework with threshold
levels (classes) proceeded to the assessment
of environmental performance in the
rehabilitation and operation phases, which the
class achieved can allow a certification.
In order to develop the methodology and select
a case study, which allow their application has
been agreed by Estradas de Portugal (EP) and
contractor HCI / HTecnic the rehabilitation
works of EN6. The work interventions were
held simultaneously with the development of
the dissertation period, allowing a monitoring
and checking. Moreover, the contractor and
client had interest in the work interventions
obtain a good environmental performance.
As expected results is the analysis of the case
study phase of service to the community in
environmental management and rehabilitation
of road infrastructure to improve its
performance towards sustainability.
This assessment provides an overview of the
impacts either in the environmental, social and
economic activities that arise from the
rehabilitation works.
The evaluation process occurred throughout
the course of several interventions in road
infrastructure.
In assessments of the rehabilitation works of
the six infrastructure intervened was performed
for each infrastructure a report explaining in
detail the assessment.
4. Case study
The case study consists of the rehabilitation
works of 6 different places on Estrada Nacional
Nº6 from Lisbon to Cascais, in particular, the
Bridge over the Jamor river, the Retaining
Walls in the zone of Gibalta,the Railway
Overpass, two Underpass and the Crosswalk
(Ramos, 2010).
Figure 2- Bridge over the Jamor river
Figure 3- Retaining Walls in the zone of Gibalta
After defining strategic guidelines for each
criterion system, the research focuses on the
development of thresholds in the rehabilitation
phase. This paper will discuss the criteria that
were evaluated Life Cycle Assessment (LCA).
4.1 Developments of the thresholds
The criteria that were subject to a Life Cycle
Assessment are, notably, Low energy
consumption (C7) and Carbon Intensity (C9).
These criteria were measured based
consultation of Environmental Product
Declarations and scientific studies on the
several construction materials.
This paper used sixteen materials, such as
cement, steel, high density polyethylene pipe
(HDPE), epoxy resin, acrylic paint, wood, metal
plates of steel, wire mesh, structural bearings,
concrete, metal guard rails, sand, glassfibre
net , mortar, bitumen emulsion and asphalt.
The values founded in the Environmental
Product Declarations relating to construction
materials correspond to phases Cradle-to-
Gate.
In the emissions of carbon dioxide equivalent
refer to two types of cement because the
percentage of clinker is different on both.
The percentage of clinker in the cement type I
is between 95 and 100% of the cement type II
is between 80 and 94%.
7
The author (Henriques, 2011), said that clinker
production is a significant source of carbon
dioxide emissions equivalent to the
atmosphere in the manufacture of cement.
Thus, the cement type I have a greater
negative impact on emissions of carbon
dioxide equivalent in the environment of than
cement type II.
In an approach of Life Cycle Assessment, the
criteria Low energy consumption (C7) and
Carbon Intensity (C9) were studied through
five phases of the life cycle.
These five phases consisted in the production
phase, in the phase of transportation of the
materials, in the phase of transport of the
workers, in the construction phase, and in the
end-of-life phase.
In the production phase, we considered all
processes from extraction of raw materials to
obtain the final product.
The materials were transported by two types of
trucks: semi-trailer truck with carrying capacity
of 25 tons and another crane-truck with
carrying capacity of 12 tons.
It was assumed two assumptions, the first
assumption is that the variation of fuel
consumption and emissions between two
trucks to be about 30%.
The second assumption is that the variation of
fuel consumption and emissions from the same
type of truck load and no load is approximately
20%.
Table 1- Fuel consumption and CO2 emissions from trucks (IPCC, 1997)
Type of
truck
Fuel consumption with loaded
truck [l/100Km]
Fuel consumption
with unloaded
truck [l/100Km]
Emissions of CO2
with loaded truck
[gCO2/km]
Emissions of CO2
with unloaded
truck [gCO2/km
]
Semi-trailer truck
40 32 770 616
Crane-truck
28 22 539 431
In phase of transport of workers, it was made a
reference scenario in order to estimate the
energy consumption and emissions of carbon
dioxide equivalent relating to the displacement
of workers of their houses to work.
This scenario consisted of 4 types of transport,
particularly by car, bus, motorcycle and train.
In the construction phase, it was considered
fuel consumption and emissions of carbon
dioxide produced by equipment used for
intervention works.
The emissions of carbon dioxide in 2010 were
226.7 g CO2/kWh (EDP, 2010).
Finally, the end-of-life that corresponds to the
transportation of the waste to the landfill were
calculated the fuel consumption and the
emissions of carbon dioxide equivalent.
This Life Cycle Assessment was not
considered the operation phase, since they are
rehabilitation works of road infrastructure is
assumed that the operation phase remains
unchanged. Thus, Average Daily Traffic is
nearly constant during and after the conclusion
of the rehabilitation works.
4.2 Functional unit
The functional unit considered to relativize the
performance was linear meter of the
infrastructure intervened for the useful life of
twenty-five years.
4.3 The Bridge over the Jamor river
Based on consultation of Environmental
Product Declarations and scientific studies on
the several materials used in the rehabilitation
works we obtained values for the Low energy
consumption (C7) and carbon intensity (C9),
774 MJ ano-1
m-1
and 34 kg CO2 eq ano-1
m-1
,
respectively.
The final results of primary energy on the
various materials used taking into account the
quantities used in the rehabilitation works are
shown in Table 2.
Table 2 – Primary energy of various materials relating to the Jamor Bridge
Material Unit Quantities
used
Primary energy
[MJ]
Primary energy
[MJ ano-
1m
-1]
Portland cement (Tipo II)
kg 4.620 22.167 13
Epoxy resin
kg 580 42.920 26
Acrylic paint
m2 2.900 104.284 63
Metal plates of steel
kg 51.325 857.127 519
Structural bearings
kg 1.280 23.040 14
Sand kg 7.500 208.275 126
Mortar kg 7.662 19.615 12
Total 1.277.428 774
8
In the figure 4 that concerns the contribution of
the different materials taking into account the
quantities used in rehabilitation works on
primary energy consumption reveals that the
largest percentage corresponds to steel plates,
followed by sand.
In this rehabilitation of the bridge over the
Jamor river were reincorporated all waste, so
the end-of-life was suppressed.
The following table presents the final results of
the various phases of the Life Cycle
Assessment, which the production phase as it
contributes to higher total primary energy.
Table 3- Phases of LCA in total primary energy relating to the Jamor Bridge
Primary
energy [MJ] Primary energy [MJ ano
-1m
-1]
Production phase
1.277.428 774
Phase of
transportation of
the materials
69.232 42
Phase of transport of the
workers 6.669 4
Construction phase
51.293 31
Total 1.404.622 851
Figure 4- Total primary energy (percentage) divided by several materials relating to the Jamor Bridge
Figure 5- Phases of LCA in total primary energy (percentage) relating to the Jamor Bridge
By relativizing the results achieved in primary
energy, we can verify that the total
consumption of primary energy in the
rehabilitation of the bridge over the Jamor river
is equivalent to fuel consumption of 33 cars per
year.
Table 4 Primary energy relating to the Jamor Bridge
Total primary energy [MJ] 1.404.622
Fuel consumption of the vehicle [L/100km] 6
Average distance traveled by vehicle per year [km ano
-1]
20.000
Number of vehicles 33
Portland cement (Tipo II) 1,74%
Epoxy resin 3,36%
Acrylic paint 8,16%
Metal plates of steel 67,10%
Structural bearings 1,80%
Sand 16,30%
Mortar 1,54%
Production phase 91%
Phase of transportation of the
materials 4,9%
Phase of transport of the workers
0,5%
Construction phase 4%
9
In the criteria of carbon intensity (C9), the final results of emissions of carbon dioxide equivalent of the several materials used taking into account the quantities used in the rehabilitation works are in Table 5.
Table 5- Emissions of carbon dioxide equivalent of several
materials relating to the Jamor Bridge
Material Unit Quantities
used
Emissions of CO2 eq
[kg CO2 eq]
Emissions of CO2 eq [kg CO2 eq ano
-1m
-1]
Portland cement (Tipo II)
kg 4.620 2.934 2
Epoxy resin
kg 580 870 1
Acrylic
paint
m2 2.900 1,807 1
Metal plates of
steel kg 51.325 47.378 29
Structural bearings
kg 1.280 1.391 1
Sand kg 7.500 395 0,2
Mortar kg 7.662 2.145 1
Total 56.920 34
In the figure 6 as regards the contribution of
the different materials taking into account the
quantities used in the rehabilitation works on
emissions of carbon dioxide equivalent, it
shows that the largest percentage corresponds
to steel plates, then the cement.
Figure 6- Emissions of carbon dioxide equivalent amount (percentage) divided by several materials relating to the Jamor Bridge
In Table 6 presents the final results of the
various phases of the Life Cycle Assessment,
which it is also the production phase as it
contributes more to the total emissions of
carbon dioxide equivalent.
Table 6- Phases of LCA in total emissions of carbon
dioxide equivalent relating to the Jamor Bridge
Emissions of CO2 eq [kg
CO2 eq]
Emissions of CO2 eq [kg CO2 eq ano
-1m
-1]
Production phase 56.920 34
Phase of
transportation of
the materials
3.702 2
Phase of transport of the workers
1.300 1
Construction phase
4.195 3
Total 66.116 40
Portland cement (Tipo II) 5,15%
Resina epoxy 1,53%
Tinta acrilica 3,18%
Metal plates of steel 83,24%
Structural bearings 2,44%
Sand 0,69%
Mortar 3,77%
10
Figure 7- Phases of LCA in the emissions of carbon dioxide equivalent (percentage) relating to the Jamor Bridge
By relativizing the results achieved in
emissions of carbon dioxide equivalent, we can
verify that emissions from the rehabilitation
works of the bridge over the Jamor river are
equivalent to the carbon dioxide emissions of
26 cars per year.
Table 7 - Emissions of carbon dioxide equivalent relating
to the Jamor Bridge
Emissions of CO2 eq [kg CO2 eq] 66.116
Average emissions of CO2 [kg CO2/km] 0,13
Average distance traveled by vehicle per year [km ano
-1]
20.000
Number of vehicles 26
4.4 The Retaining Walls in the zone of
Gibalta
On the Retaining Walls in the zone of Gibalta
the values of the criteria low energy
consumption (C7) and carbon intensity (C9)
were 738 MJ ano-1
m-1
and 7 kg CO2 eq ano-1
m-
1, respectively.
The final results of primary energy of the
several materials used taking into account the
quantities used in the rehabilitation works are
shown in Table 8.
Table 8- Primary energy of various materials relating to the Retaining Walls
Material Unit Quantities
used Primary
energy [MJ]
Primary energy
[MJ ano-
1m
-1]
Portland cement
kg 138.270 663.419 30
Steel kg 1.600 51.200 2
High density polyethylene pipe (HDPE)
m 1.050 11.693 1
Epoxy resin kg 70 5.180 0,2
Acrylic paint
m2 7.000 251.720 11
Wood m3 10 11.272 1
Metal guard rails
m 105 22.680 1
Sand kg 540.780 15.017.461 675
Glassfibre
net m2 7.000 84.594 4
Mortar kg 60.123 153.915 7
Total 16.442.205 731
On the contribution of the different materials
taking into account the quantities used in
rehabilitation works on primary energy
consumption it shows that the highest
percentage corresponds to the sand, followed
by Portland cement as is shown in figure 8.
Production phase 86,1%
Phase of transportation of the
materials 5,6%
Phase of transport of the workers
2,0%
Construction phase 6,3%
11
Figure 8- Total primary energy (percentage) divided by several materials relating to the Retaining Walls
In Table 9 shows the final results of the various
phases of the Life Cycle Assessment, it is
observed that the production phase as that
contributes most to the total primary energy,
then the construction phase.
Table 9- Phases of LCA in total primary energy relating to the Retaining Walls
Primary energy
[MJ] Primary energy [MJ ano
-1m
-1]
Production phase
16.273.133 731
Phase of
transportation
of the
materials
46.019 2
Phase of transport of the workers
54.171 2
Construction phase
155.300 7
End-of-life phase
2.592 0,1
Total 16.531.215 743
By relativizing results achieved in primary
energy, we can verify that the total
consumption of primary energy in the
rehabilitation works of the Retaining Walls in
the zone of Gibalta is equivalent to fuel
consumption of 383 cars per year.
Table 10- Primary energy relating to the Retaining Walls
Total primary energy [MJ] 16.531.215
Fuel consumption of the vehicle [L/100km]
6,00
Average distance traveled by vehicle per year [km ano
-1]
20.000
Number of vehicles 383
Figure 9- Phases of LCA in total primary energy (percentage) relating to the Retaining Walls
Portland cement 4,03%
Steel 0,31%
Pipes of HDPE 1,10%
Epoxy resin 0,03%
Acrylic paint 1,55%
Wood 0,07%
Metal guard rails 0,14%
Sand 92,28%
Glassfible net 0,52% Mortar
0,95%
Production phase 99%
Phase of transportation of the
materials 0,3%
Phase of transport of the workers
0,3%
Construction phase 1%
End-of-life phase 0,02%
12
In the criteria carbon intensity (C9), the final
results of emissions of carbon dioxide
equivalent of the several materials used taking
into account the quantities used in the
rehabilitation works are in the table below.
Table 11- Emissions of carbon dioxide equivalent of several materials relating to the Retaining Walls
Material Unit Quantities
used
Emissions of CO2 eq [kg CO2
eq]
Emissions of CO2 eq [kg
CO2 eq ano-
1m
-1]
Portland cement (Tipo I)
kg 11.550 10.383 0,47
Portland cement (Tipo II)
kg 126.720 80.467 3,62
Steel kg 1.600 2.688 0,12
High density polyethylene pipe (HDPE)
m 1.050 298 0,01
Epoxy resin kg 70 105 0,005
Acrylic paint m2 7.000 5.962 0,27
Wood m3 10 259 0,01
Metal guard rails
m 105 1.369 0,06
Sand kg 540.780 28.450 1,28
Glassfibre
net m2 7.000 3.786 0,17
Mortar kg 60.123 16.834 0,76
Total 150.603 7
In Figure 10 shows the contribution of the
different materials taking into account the
quantities used in the rehabilitation works
emissions of carbon dioxide equivalent
observes that the largest percentage
corresponds to Portland Cement (Type II),
followed by sand.
The following table presents the final results of
the various phases of the Life Cycle
Assessment, which the production phase as it
contributes more to the total emissions of
carbon dioxide equivalent, followed by the
construction phase.
Table 12- Phases of LCA in total emissions of carbon
dioxide equivalent relating to the Retaining Walls
Emissions of CO2 eq [kg CO2
eq]
Emissions of CO2 eq [kg CO2 eq ano
-1m
-1]
Production phase
150.603 7
Phase of
transportation
of the materials
2.461 0,1
Phase of transport of the
workers
11.296
0,5
Construction phase
13.360 0,6
End-of-life phase
139 0,01
Total 177.858 8
Figure 10- Emissions of carbon dioxide equivalent amount (percentage) divided by several materials relating to the Retaining
Walls
Portland cement (Tipo I)
7%
Portland cement (Tipo II)
53%
Steel 2%
Pipes of HDPE 3%
Epoxy resin 0,07%
Acrylic paint 4%
Wood 0,2%
Metal guard rails 1%
Sand 19%
Glassfibre net 3%
Mortar 11%
13
Figure 11- Phases of LCA in the emissions of carbon dioxide equivalent (percentage) relating to the Retaining Walls
By relativizing the results obtained in the
emissions of carbon dioxide equivalent, we can
verify those emissions of rehabilitation works of
the Retaining Walls in the zone of Gibalta are
equivalent to the carbon dioxide emissions of
69 cars per years.
Table 13- Emissions of carbon dioxide equivalent relating to the Retaining Walls
Emissions of CO2 eq [kg CO2 eq] 177.858
Average emissions of CO2 [kg CO2/km] 0,13
Average distance traveled by vehicle per year [km ano
-1]
20.000
Number of vehicles 69
5. Discussion
The results show that it was possible to identify
performance levels and best practices, thereby
served as a basis to create the LiderA
performance scale for this type of road
infrastructures.
The existing data about the characteristics of
materials and the performance of the works is
reduced, at least with regard to reliable
publications, so this is an important limitation,
which led to a search of additional life cycle.
However this approach has an important future
progress in their development.
The methodology allows find thresholds
nevertheless the limitation data, and led to the
application of methods of quantification (LCA)
that may have some uncertainty which is
reflected in accuracy.
An important aspect is the relationship
between performance classes and solutions
(prescriptive measures) that sometimes is
carried by reflection measurement being
desirable to search for quantification.
There is a wide variability in the type of road
infrastructure, so it was important to choose a
work with different infrastructures, particularly a
Bridge, Pavements, Retaining Walls,
Overpass, Underpasses and Crosswalk.
Thus, an important limitation is the
extrapolation of these data to other types of
infrastructure that must be analyzed carefully.
The application was made in construction
phase, although there is evidence of
recommendations to be developed and
integrated into the project (example: inclusion
construction and demolition waste in retaining
walls and a bridge) which shows the potential
of the project implementation. In addition, it
could also have a higher contribution if such
should occur in the project.
6. Conclusions
The application to the case study consisting of
several types of road infrastructures allows us
to emphasize that this methodology is able to
be adjusted and applied to any kind of
typology.
Moreover, the methodology allows evaluating
the rehabilitation works showing the good
practices.
In this study it was possible to apply Life Cycle
Assessment with developing values in criteria,
such as, Low energy consumption (C7) and
Carbon Intensity (C9) in the rehabilitation
phase of LiderA system.
Production phase 84,68%
Phase of transportation of the materials
1,38%
Phase of transport of the workers
6,35%
Construction phase 7,51%
End-of-life phase 0,08%
14
Based on LCA performed in the six
infrastructure intervened and not considering
the operation phase, it is concluded that the
phase which contributes most to energy
consumption and emission of carbon dioxide
equivalent is the production phase of the
materials.
After the production phase, the construction
phase and phase transport materials are those
that have more expression in fuel consumption
and emissions.
It is important that new technologies allow the
optimization process to reduce the
environmental impact of the materials
generated in the production.
Moreover, in the construction phase the
selection of more efficient equipment can
reduction in the fuel consumption.
On the transport phase material should make
an effort to give priority and the choice of
materials local or national to shorten distances,
and minimize a significantly the impacts.
Currently, the absence of a solid base of
Environmental Product Declarations targeted
for construction materials of the road
infrastructure, making it difficult to obtain more
accurate data.
Besides, there is little systematization of values
and averages in studies on energy
consumption in construction / rehabilitation of
the road infrastructures.
Finally, this paper serves as a basis for the
development of future works by improving the
assessment method taking into account future
technologies.
Besides, it can also serve as a basis for other
studies, because the quantitative data provide
the opportunity to estimate the environmental
impacts in the rehabilitation and construction of
other road infrastructures.
Acknowledgement
The results present in this paper are a
summary of the dissertation developed in the
area of road infrastructures in relation to its
environmental performance.
References
Bryce, James M. Developing Sustainable
Transportation Infrastructure. University of
Missouri, 2008.
CEEQUAL. Scheme Description and
Assessment Process Handbook - Version
4, 2008 , pp 15.
EDP - Energia de Portugal. Obtained in
October 2011.
http://www.edpsu.pt/pt/origemdaenergia/P
ages/OrigensdaEnergia.aspx
EURF- European Union Road Federation.
Sustainable roads and optimal mobility.
Bruxelas, 2009.
Fernandes, Francisco, e De Sousa, João
Figueira. Os Efeitos das Infra-estruturas
Rodoviárias no Ordenamento e
Desenvolvimento do Território: o caso da
Ilha de Santiago, Cabo Verde. Cabo
Verde, 2007, pp 6-8.
Glynn, Astrid. The Importance of Green Roads.
2009.
GreenHighways. Obtained in October 2011
http://www.greenhighwayspartnership.org
Greenroads, rates sustainable road projects.
Obtained in October 2011
http://www.sciencedaily.com/releases/201
0/01/100113091646.htm
Grumbles, Benjamin. Green Transportation
Infrastructure: Challenges to Access and
Implementation . Washington Government
Priting Office, 2008.
Henriques, Valter. Impacte Ambiental de
estruturas de edificios- produção de CO2.
Lisboa: IST, 2011.
IPCC. Guidelines for National Greenhouse
Gas Inventories.. Reference Manual
(Volume 3) - Energy, 1997.
Magina, Ana. Avaliação da sustentabilidade de
infra-estruturas rodoviárias pelos Sistema
LiderA. IST, 2008.
Molenaar, André. Design and Construction of
Sustainable Roads. Delft University of
Techonology, 2010.
Muench, S, e Anderson, Jeralee. Greenroads:
A sustainability performance metric for
roadway design and construction. 2009.
Pereira, Paulo, e Pais, Jorge. A reabilitação da
rede rodoviária no século XXI. Portugal,
2007.
Pinheiro, M. D. Guia Técnico para a
elaboração de Estudos no âmbito da
Avaliação de Impacte Ambiental de Infra-
estruturas Rodoviárias. Portugal, 2011a.
Pinheiro, M. LiderA- Sistema voluntário para a
sustentabilidade dos ambientes
15
construídos. Lisboa: Instituto Superior
Técnico, 2011b.
Pinheiro, M. Ambiente e Construção
Sustentável. Amadora: Instituto do
Ambiente, 2006.
Pinheiro, Manuel. Dossier do Curso: LiderA -
Curso Certificação Ambiental da
Construção Sustentável - Sistema LiderA.
Lisboa: FUNDEC, IST, 2011c.
Ramos, Carlos. Empreitada da EN6- obras de
reabilitação e reforço. Lisboa, 2010.
Ribeiro, Anabela, e Pais Antunes, António.
Road accessibility and cohesion in
lagging regions: Empirical evidence from
Portugal based on spatial econometric
models. Journal of Transport Geography,
2010, pp 1-2.
USEPA - United States Environmental
Protection Agency . Waste and Materials -
Flow Benchmark Sector Report:
Beneficial Use of Secondary Materials -
Coal Combustion Products. Washington
DC, 2008.
Vita, Laura. Road Infrastructure- the backbone
of transport system. Milão: Bocconi
University, 2008.