ROAD B5 BRIDGES INSPECTION DETAILED REPORT copy.docx

132
MTRD ICT MINISTRY OF TRANSPORT AND INFRASTRUCTURE STATE DEPARTMENT OF INFRASTRUCTURE MATERIALS TESTING AND RESEARCH DIVISION(MTRD) DETAILED INSPECTION OF BRIDGES ALONG NAKURU-NYAHURURU-NYERI – MARUA ROAD(B5) MTRD REPORT NO.1233 MAY,2015 CHIEF ENGINEER (MATERIALS ) P.O. BOX 11873-00400 NAIROBI INTERNATIONAL CONSULTANTS AND TECHNOCRATS(ICT) PVT LTD A-8, GREEN PARK NEW DELHI - 110016, INDIA DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Transcript of ROAD B5 BRIDGES INSPECTION DETAILED REPORT copy.docx

Page 1: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

MINISTRY OF TRANSPORT AND INFRASTRUCTURE

STATE DEPARTMENT OF INFRASTRUCTURE

MATERIALS TESTING AND RESEARCH DIVISION(MTRD)

DETAILED INSPECTION OF BRIDGES ALONG NAKURU-NYAHURURU-

NYERI –MARUA ROAD(B5)

MTRD REPORT NO.1233

MAY,2015

CHIEF ENGINEER (MATERIALS )P.O. BOX 11873-00400

NAIROBI

INTERNATIONAL CONSULTANTS AND TECHNOCRATS(ICT) PVT LTDA-8, GREEN PARK NEW DELHI -

110016, INDIA

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 2: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

1.0 INTRODUCTIONThis bridge inspection report is in response to a request made by M/S International Consultants and Technocrats (ICT) Pvt Ltd of A-8, Green Park New Delhi -110016, and India to undertake inspection of structures along road B5. This was done under the project: “Consultancy Services for a Feasibility Study, EIA, SIA and Detailed Designs Including Tender Documents for Rehabilitation of Nakuru-Nyahururu-Nyeri –Marua Road”.

A total of seven structures had been targeted for detailed inspection as listed below.

i. Bridge at Km 60+030ii. Bridge at Km 84+520iii. Bridge at Km 93+380iv. Bridge at Km 102+510v. Bridge at Km 125+670vi. Bridge at Km 142+450vii.Bridge at Km 173+120

This report contains a description of the structures, visual observations, description of testing methods, test results for various parameters based on different Non-Destructive Testing methods, conclusions and recommendations.

The report is factual and dwells mainly on the status of structural elements and their material components.

The primary results of these inspections are given and the critical problems have been highlighted.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 3: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

1.1 Scope of workThe scope of work as shown below involved testing of structural elements in both the superstructures and substructures for each of the seven bridges for several parameters using various Non-Destructive Testing methods.Table 1: Scope of work

Item no. Structural

elementParameters tested Inspection details/methods

1 Abutments

Appearance Carry out visual inspectionRe-bar details Carry out electromagnetic

testsInsitu Concrete strength Carry out Schmidt hammer

testsQuality, homogeneity and internal defects of concrete matrix

Carry out ultrasonic pulse velocity tests

Deterioration status of the concrete matrix

i. Corrosionii. Remaining effective

good covers

i. Carry out resistivity/half cell potential tests

ii. Carry out carbonation depth tests

Crack profilingi. Widthii. Depthiii. length

i. Use of crack width microscope to measure crack widths

ii. Carry out ultrasonic tests to measure crack depths

2Piers

i. Wall type ii. Column

typeDitto Ditto

3 Deck slab Ditto Ditto

4 Steel Girders

Laminations Carry out ultrasonic testsCorrosion Carry out visual inspection

and ultrasonic thickness testsPlate thicknesses Carry out ultrasonic tests

Continuity of critical welds if any

Carry out radiographic tests

5

Ancillary Fixturesi. bearingsii. expansion

gapsAppearance Carry out visual inspections

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 4: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

3.0 SUMMARY OF TEST RESULTSGenerally the findings from all the tests done indicate a lot of similarity for six structures in terms of re-bar distribution for various structural elements, cracking patterns, steel girder types ,numbers & sizes, type of ancillary fixtures and concrete deterioration status.

The findings for bridge at km173+120 (at Marua) were different from those of other structures.

Inspection results have been summarized for each structure and are presented below.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 5: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

3.1 BRIDGE AT KM 60+030…This is a single span structure comprising a composite deck with 5 no. steel beams, wall type RC abutments and wing walls.

Photo 1: A side view of bridge at km 60+030

3.1.1 ABUTMENTS3.1.1.1 Visual Inspection

Two vertical cracks running full height were found on the Nyeri side abutment. The cracks appear approximately midway between the beam supports at the abutment cap. The crack widths vary from 0.8-1.4mm

Fig. 1: showing crack profiles for Nyeri side abutment

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

23304050

Page 6: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 60+030

Photo 2: a vertical crack on an abutment wall

One vertical crack was found on the Nyahururu side abutment. The crack appearednear the inner RHS beam support at the abutment cap and propagated the full height of the abutment wall. The maximum crack width recorded was.1.0 mm

Fig. 1: showing crack profiles for Nyeri side abutment

3.1.1.2 Steel Reinforcement details for the Abutments

The reinforcement details as gathered through electromagnetic method revealed the spacing of the reinforcement bars in the abutment walls on

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

23304050

Page 7: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

either side of the bridge was not uniform in the vertical and horizontal directions, varying between 400mm- 450mm and 380-450mm respectively . The vertical re-bars were 25 mm diameter while the horizontal were 16 mm diameter.

BRIDGE AT KM 60+030Steel Reinforcement details for the Abutments

The average covers were varying at different points on either abutment with the lowest at 33 mm and the highest at 71 mm.

3.1.1.3 Concrete strength, quality and homogeneity for the Abutments

The concrete strength as measured through rebound (Schmidt) hammer method recorded strengths of between 44.0N/mm2 to 54.0N/mm2

The concrete matrix was generally homogeneous as revealed through ultrasonic method except at locations where cracks appeared.

3.1.1.4 Crack depths for the Abutments

The crack depths were ultrasonically determined and found to be106mm at the widest points.

3.1.1.5 Concrete Deterioration for the Abutments

Two methods were employed i.e. carbonation and resistivity potential to indicate the level of deterioration of concrete.

The highest carbonation depth recorded was 6mm indicating a remaining good cover of 27mm (least cover recorded was 33mm). This was an indication of low level deterioration.

Probability of corrosion activity was insignificant as indicated by a high resistivity potential of 111.4kΩcm.

3.1.2 DECK SLAB3.1.2.1 Visual inspection of the Deck Slab

Deck slab thickness was 200mm.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 8: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

There were several multi directional cracks appearing from the soffit of the deck. The cracks were distributed all over the deck soffit.

Maximum crack width was 1mm.

3.1.2.2 Steel Reinforcement details of the Deck Slab

The reinforcement details as gathered through electromagnetic method revealed that the distribution of the reinforcement bars in the deck slab was uniform both in both longitudinal and transverse directions. The longitudinal re-bars were 20 mm diameter at an average spacing of 400mm while the transverse were 16 mm diameter at an average spacing of 300 mm. The average covers were 50mm and 35mm for longitudinal re-bars and transverse re-bars respectively.

3.1.2.3 Concrete strength, quality and homogeneity

The concrete strength as measured through rebound (Schmidt) hammer method recorded an average strength of between 56N/mm2 62N/mm2

The concrete matrix was inhomogeneous as revealed through ultrasonic method. This could be due to cracking on the deck slab soffit.

3.1.2.4 Crack depths

The crack depths were ultrasonically determined and found to be “through cracks”

3.1.2.5 Concrete Deterioration of Deck Slab

Two methods were employed i.e. carbonation and resistivity potential to indicate the level of deterioration of concrete.

The highest carbonation depth recorded was 6mm indicating a remaining good cover of 29mm (least cover recorded was 35mm).This was an indication of low level deterioration.

Deterioration in this case refers to chemical effects and not physical.

Probability of corrosion activity was insignificant as indicated by high resistivity potential of 110.2DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 9: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 60+0303.1.4 WING WALLS3.1.4.1 Visual Inspection of the Wing Walls

There were no visual structural defects on the wing walls

3.1.4.2 Steel Reinforcement Details for the Wing Walls

The reinforcement details as gathered through electromagnetic method revealed the spacing of the reinforcement bars in the wing walls on either side of the bridge not to be uniform in the vertical and horizontal directions, varying between 380mm- 480mm and 390-470 mm respectively. The vertical re-bars were 20 mm diameter while the horizontal were 16 mm. The average covers were varying at different points on either side with the lowest at 26 mm and the highest at 71 mm.

3.1.4.3 Concrete strength, quality and homogeneity for the wing walls

The concrete strength as measured through rebound (Schmidt) hammer method recorded an average strength of 58.0N/mm2

The concrete matrix was generally homogeneous as revealed through ultrasonic method.

3.1.5 STEEL GIRDERS 3.1.5.1 Visual Inspection of Steel Girders

There were spots of paint peeling off from the bracings and beams.

The top flanges near the abutment supports had started to corrode as revealed by red/brown colouration stains at the slab soffit joint. However the corrosion was at an early stage without causing any significant reduction in thickness of the steel plate.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 10: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

There was accumulation of soil at the abutment caps which covered the bottom flanges of the steel girders causing the paint to peel off resulting in early stages of corrosion.

BRIDGE AT KM 60+030Visual Inspection of Steel Girders

The bolts and nuts for all the joints were in good condition.

There were no critical welded joints.

3.1.5.2 Ultrasonic Thickness Tests for Steel Girders

There was no delaminating of the plates as determined ultrasonically. The thicknesses for the flange and web plates were determined ultrasonically and found to be uniform.

3.1.6 BEARINGSThe bearing type was elastomeric of approximate size 400x280x 30 mm and was in good condition.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 11: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

3.2 BRIDGE AT KM 93+380This is a single span structure comprising a composite deck with 5 no. steel beams, wall type RC abutments and wing walls.

Photo 3: A side view of bridge at km 93+380

3.2.1 ABUTMENTS3.2.1.1 Visual Inspection Abutments

There were four regularly spaced vertical cracks running full height on the Nyeri side abutment. The cracks appeared approximately midway between the beam supports at the abutment cap.

Fig 3: sketch showing the crack profiles on the Nyeri side abutment wall

The crack widths varied from 0.6-1mm.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

2100 1900167018802600

Page 12: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

3.2 BRIDGE AT KM 93+380Three regularly spaced vertical cracks running full height were found on the Nyahururu side abutment. The cracks appeared approximately midway between the beam supports for the inner LHS& RHS beams and the centre beam.

Fig 4: showing crack profiles for Nyahururu side abutment-measurement in mm

Photo 4: Showing a vertical crack on an abutment

3.2.1.2 Steel Reinforcement details for the Abutments

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

2000m230026503140

Page 13: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

The reinforcement details as gathered through electromagnetic method revealed the distribution of the reinforcement bars in the abutment walls on either side of the bridge to be uniform in the vertical and horizontal directions.

BRIDGE AT KM 93+380Steel Reinforcement details for the AbutmentsThe vertical s re-bars were 25 mm diameter at an average spacing of 450mm while the horizontal were 16 mm diameter at an average spacing of 450 mm. The average covers were varying at different points on either abutment with the lowest at 28 mm and highest at 66 mm.

3.2.1.3 Concrete strength, quality and homogeneity for the Abutments

The concrete strength as measured through rebound (Schmidt) hammer method recorded strengths between 40.0 N/mm2 to 60N/mm2 for six test points.

The concrete matrix was generally homogeneous as revealed through ultrasonic method except at locations where cracks appeared.

3.2.1.3 Crack depths

The crack depths were ultrasonically determined and found to be 61mm at the widest points.

3.2.1.4 Concrete Deterioration for the Abutments

Two methods were employed i.e. carbonation and resistivity potential to indicate the level of deterioration of concrete.

The highest carbonation depth recorded was 5mm indicating a remaining good cover of 23mm (least cover recorded was 28mm).This was an indication of low level deterioration.

Probability of corrosion activity was insignificant as indicated by a high resistivity potential of 110.6kΩcm.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 14: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 93+3803.2.2 DECK SLAB3.2.2.1 Visual inspection Of the Deck Slab

Deck slab thickness was 200mm.There were several multi directional cracks appearing from the soffit of the deck. The cracks were distributed all over the deck soffit. There were two major cracks that ran full width on each half of the Nyeri side and Nyahururu side of the deck at approximatetly1500mm from the cross bracing. There were leakage stains along these cracks, an indication that the cracks were through hence the risk of exposure of re-bars to corrosion due to water ingress at the locations. (See photos below)

Photo 5: showing a transverse crack on the deck of bridge at km 93+380

Photo 6: a closer view of the crack in photo 5 above

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 15: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Maximum crack width was 1mm.

BRIDGE AT KM 93+3803.2.2.2 Steel Reinforcement details for the Deck Slab

The reinforcement details as gathered through electromagnetic method revealed that the distribution of the reinforcement bars in the deck slab was uniform both in both longitudinal and transverse directions. The longitudinal re-bars were 20 mm diameter at an average spacing of 400mm while the transverse were 16 mm diameter at an average spacing of 300 mm. The average covers were 50mm and 34mm for longitudinal re-bars and transverse re-bars respectively.

3.2.2.3 Concrete strength, quality and homogeneity for the Deck Slab

The concrete strength as measured through rebound (Schmidt) hammer method recorded an average strength of 55N/mm2 for three test locations.

The concrete matrix was inhomogeneous as revealed through ultrasonic method. This was especially due to numerous multi directional cracks on the deck slab soffit.

3.2.2.4 Crack depths

The crack depths for the major transverse cracks were ultrasonically determined and found to be through cracks at the widest points.

3.2.2.5 Concrete Deterioration

Two methods were employed i.e. carbonation and resistivity potential to indicate the level of deterioration of concrete.

The highest carbonation depth recorded was 5mm indicating a remaining good cover of 29mm (least cover recorded was 34mm).This was an indication of low level deterioration.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 16: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Deterioration in this case refers to chemical effects, not physical.

Probability of corrosion activity was insignificant as indicated by a high resistivity potential 108.6

BRIDGE AT KM 93+3803.2.3 WING WALLSVisual Inspection of the Wing Walls

There were no visible structural defects on the wing walls.

3.3.3.1 Steel Reinforcement Details

The reinforcement details as gathered through electromagnetic method revealed the distribution of the reinforcement bars in the wing walls on either side of the bridge to be uniform the vertical and horizontal directions. The vertical re-bars were 220 mm diameter at an average spacing of 450mm while the horizontal were 16 mm diameter at an average spacing of 350mm. The average covers were varying at different points on either side with the lowest at 37 mm and the highest at 68 mm.

3.2.3.2 Concrete strength, quality and homogeneity

The concrete strength as measured through rebound (Schmidt) hammer method recorded strengths of between 58.0N/mm2 to 65N/mm2.

The concrete matrix was generally homogeneous as revealed through ultrasonic method.

3.3.4 STEEL GIRDERS 3.2.4.1 Visual inspection of Steel Girders

There were spots of paint peeling off from the bracings and girders.

The top flanges near the abutments had started to corrode for approximately 700 mm length. However the corrosion was at an early stage without causing any significant reduction in thickness of the steel plates.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 17: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Photo 1: showing spots of paint peeling off a bracing on bridge at km 93+380

BRIDGE AT KM 93+380There was accumulation of soil at the abutment caps which covered the bottom flanges of the steel girders causing the paint to peel off resulting in early stages of corrosion.

The bolts and nuts for all the joints were in good condition.

There were no critical welded joints.

3.2.4.2 Thickness Tests for Girder Plates

There was no delaminating of the plates as determined ultrasonically. The thicknesses for the flange and web plates were determined ultrasonically and found to be uniform.

3.3.5 BEARINGSThe bearing type is elastomeric of approxsize400x280.30 while loaded and were in good condition.

photo 8:showing a bridge bearing for bridge at km 93+380

3.3.6 OTHER BRIDGE FITTINGSThe guard rails were in good condition.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 18: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

photo 2:showing guardrails for bridge at km 93+380

3.3 BRIDGE AT KM 84+520This is a three span structure comprising a composite deck with 5 no. steel girders for each span, wall type RC abutments, column type RC piers and wing walls.

Photo 9:Showing the Approach for bridge at km 84+520

Photo 10: showing the soffit of bridge at km 84+520

3.3.1 ABUTMENTS3.3.1.1 Visual Inspection of Abutments

Two vertical cracks running from mid way the height downwards were found on the Nyahururu side abutment. The crack widths ranged between 0.6-1.0mm.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 19: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Fig 5:showing crack profiles on the nyahururu side abutment

BRIDGE AT KM 84+520One vertical crack running from mid-way the height downwards was found on the Nyeri side abutment. The crack width was 0.8mm at the widest point.

3.3.1.2 Steel Reinforcement details for the Abutments

The reinforcement details as gathered through electromagnetic method revealed the spacing of the reinforcement bars in the abutment walls on either side of the bridge not to be uniform in the vertical and horizontal directions, varying between 480mm- 520mm and 360-440mm respectively. The vertical re-bars were 25 mm diameter while the horizontal were 16 mm diameter. The average covers were varying at different points on either abutment with the lowest at 36 mm and the highest at 66mm.

3.3.1.3 Concrete strength, quality and homogeneity for the Abutments

The concrete strength as measured through rebound (Schmidt) Hammer method recorded average strengths of 50.0N/mm2 and 54.0N/mm2 for the Nyeri and Nyahururu sides respectively.

The concrete matrix was generally homogeneous as revealed through ultrasonic method.

3.3.1.4 Crack depths for the abutment walls

The crack depths were ultrasonically determined and found to be 27 mm at the widest points.

3.3.1.5 Concrete Deterioration

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

3000mm 3000mm

Page 20: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

The highest carbonation depth recorded was 3 mm indicating a remaining good cover of 29mm (least cover recorded was 32mm.This was an indication of low level deterioration.

Probability of corrosion activity was insignificant as indicated by a high resistivity potential of 111.6 kΩcm

BRIDGE AT KM 84+520

3.3.2 DECK SLAB3.3.2.1 Visual Inspection of the Deck Slab

Deck slab thickness was 200mm.There were several multi directional cracks appearing from the soffit of the deck. The cracks were distributed all over the deck soffit. There were two major cracks that ran full width on each quarter of each span at approximately 1500mm from the transverse bracing. There were leakage stains along these cracks, an indication that the cracks were through hence the risk of exposure of re-bars to corrosion due to water ingress at the locations.Othermulti directional cracks are distributed over the entire deck slab soffit.

Photo 11: showing a transverse crack on the deck slab of bridge at km 84+520

Maximum crack width was 1mm.

3.3.2.2 Steel Reinforcement Details for the Deck Slab

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 21: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

The reinforcement details as gathered through electromagnetic method revealed the distribution of the reinforcement bars in the deck slab to be uniform in the longitudinal and transverse directions. The longitudinal re-bars were 20 mm diameter at an average spacing of 400mm while the transverse were 16 mm diameter at an average spacing of 300 mm. The average covers were 45mm and 27mm for longitudinal re-bars and transverse re-bars respectively.

BRIDGE AT KM 84+520

3.3.2.1 Concrete strength, quality and homogeneity for the Deck Slab

The concrete strength as measured through rebound (Schmidt) hammer method recorded an average strength of 46N/mm2

The concrete matrix was inhomogeneous as revealed through ultrasonic method. This could be attributed to numerous multi directional cracks on the deck slab soffit.

3.3.2.2 Crack depths for the Deck Slab

The crack depths were ultrasonically and visually determined and found to through at the widest points.

3.3.2.1 Concrete Deterioration for the Deck Slab

The highest carbonation depth recorded was 3mm indicating a remaining good cover of 24mm (least cover recorded was 27 mm).This was an indication of low level deterioration.

Deterioration in this case refers to chemical effects rather than physical.

Probability of corrosion activity was insignificant as indicated by a high resistivity potential of 111.6.

3.3.3 WING WALLS3.3.3.1 Visual Inspection of the Wing Walls

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 22: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

There were no visual structural defects on the wing walls.

3.3.3.2 Steel Reinforcement Details for the Wing Walls

The reinforcement details as gathered through electromagnetic method revealed the spacing of the reinforcement bars in the wing walls on either side of the bridge not to be uniform in the vertical and horizontal directions, varying between 350mm- 470mm and 260-370mm respectively. The vertical re-bars were 20 mm in diameter while the horizontal were 16 mm .The average covers were varying at different points on either side with the lowest at 36 mm and highest at 64 mm.

BRIDGE AT KM 84+5203.3.3.3 Concrete Strength, Quality and Homogeneity of the Wing Walls

The concrete strength as measured through rebound (Schmidt) hammer method recorded an average strength of 55.0N/mm2 and 54.0N/mm2 for Nyeri and Nyahururu side respectively.

The concrete matrix was generally homogeneous as revealed through ultrasonic method.

3.3.4STEEL GIRDERS 3.3.4.1 Visual Inspection of Steel Girders

The girders were generally in good condition.There were no critical welded joints along the entire length of the girders.

The bolts and nuts for all the joints were in good condition.

There were mud stains at the abutment support, causing early stages of corrosion to the LHS girder near the abutment support for a length of approximately 1m.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 23: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Photo 12:showing stains on a bottom flange of a steel girder for bridge at km 84+520

3.3.4.2 Ultrasonic Thickness Tests for Steel Girders

There was no delaminating of the plates as determined ultrasonically. The thicknesses for the flange and web plates were determined ultrasonically and found to be uniform.

BRIDGE AT KM 84+5203.3.5 PIER COLUMNS

3.3.5.1 Visual Inspection of Pier Columns

The pier columns were generally in good condition.

Photo 13: showing part of a pier column for bridge at km 84+520

3.3.5.2 Steel Reinforcement details

There were 2 No. pier columns on either side of the river channel where the central span is supported.The columns sizes were 750x600mm.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 24: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

The reinforcement details as gathered through electromagnetic method revealed 8 no.32mm diameter re-bars in each column. The average covers were varying at different points on the faces of each column with the lowest at 40 mm and highest at 70 mm.

3.3.5.3 Concrete strength, quality and homogeneity

The concrete strength as measured through rebound (Schmidt) hammer method recorded average strengths of 55 N/mm2 and 62 N/mm2 for Nyahururu side and 48N/mm2 and 54.0N/mm2 for Nyeri side.

The concrete matrix was generally homogeneous as revealed through ultrasonic method. The quality of concrete was also found to be good through direct transmission mode of ultrasonic pulses where an average velocity of 4.2 km/s was recorded.

BRIDGE AT KM 84+5203.3.5.4 Concrete matrix Deterioration for pier columns

The highest carbonation depth recorded was 3 mm indicating a remaining good cover of 37mm (least cover recorded was 40mm. This was an indication of low level deterioration.

Probability of corrosion activity was insignificant as indicated by a high resistivity potential of 111.6 kΩcm.

3.3.5.5 BEARINGSThe bearing type is elastomeric of approximate size400x280x30mm. They were in good condition.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 25: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Photo 14: Showing a bridge bearing for bridge at km 84+520

3.3.6 OTHER BRIDGE FITTINGSThe guard rails were in good condition.

photo 15:showing bridge fittings for bridge at km 84+52

3.4 BRIDGE AT KM 102+510The structure comprises a composite deck with 5 no. steel beams, wall type RC abutments and wing walls.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 26: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Photo 16: showing a side view of bridge at km 102+510

3.4.1 ABUTMENTS3.4.1.1 Visual inspection for the Abutments

Four vertical cracks running from approximately quarter the height of the abutment downwards were found on the Nyeri side abutment. The cracks appeared along a line approximately midway between the beam supports at the abutment cap. The crack widths varied from 0.4-1.2mm.

Fig 6: sketch showing crack profiles for Nyeri side abutment for bridge at km 102+510

Two vertical cracks from approximately mid height down wards were found on the Nyahururu side abutment. The cracks appeared along a line approximately midway between the two RHS beam supports and between the LHS and centre beam supports.DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

1400

10001890 1900 2800

Page 27: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Fig 6: sketch showing crack profiles for Nyahururu side abutment for bridge at km 102+510

Photo 17: showing a vertical crack on an abutment wall for bridge at km 102+510

There was scouring of the Nyeri side abutment bottom level up to 1400mm high reducing the re-bar covers along this line which is mostly submerged when water levels are high.

Photo 19: showing a scoured surface at the bottom of the abutment for bridge at km 102+510

BRIDGE AT KM 102+510

3.4.1.2 Steel Reinforcement details for the Abutments

The reinforcement details as gathered through electromagnetic method revealed the distribution of the reinforcement bars in the abutment walls on

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

4300mm 2600mm

2000mm

Page 28: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

either side of the bridge to be uniform in the vertical and horizontal directions. The vertical re-bars were 25 mm in diameter at an average spacing of 450mm while the horizontal were 16 mm diameter at an average spacing of 400mm. The average covers were varying at different points on either abutment with the lowest at 26 mm and highest at 60 mm.

3.4.1.3 Concrete strength, quality and homogeneity for the Abutments

The concrete strength as measured through rebound (Schmidt) hammer method recorded strengths of between 40.0 N/mm2 to 59.0N/mm2.

The concrete matrix was generally homogeneous as revealed through ultrasonic method except at locations where cracks appeared.

3.4.1.4 Crack depths

The crack depths were ultrasonically determined and found to be 42 mm at the widest points.

3.4.1.5 Concrete Deterioration for the abutments

The highest carbonation depth recorded was 4mm indicating a remaining good cover of 22mm (least cover recorded was 26mm), see table ... for calculation of balance of carbonation depth).This was an indication of low level deterioration.

Probability of corrosion activity was insignificant as indicated by a high resistivity potential of 110.8.

BRIDGE AT KM 102+510

3.4.2 DECK SLAB3.4.2.1 Visual inspection of the Deck

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 29: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Deck slab thickness was 200mm.There were several multi directional cracks appearing from the soffit of the deck. The cracks were distributed all over the deck soffit. There were two major cracks that ran full width on either half of the Nyeri side and Nyahururu side of the deck at approx1, 500 mm from the transverse bracing. There were leakage stains along these cracks, an indication that the cracks were through hence the risk of exposure of re-bars to corrosion due to water ingress at the locations. (See photos below).

Photo 20: showing cracks on the deck slab of bridge at km 102+510

Maximum crack width was 0.8 mm.

3.4.2.2 Steel Reinforcement details for the Deck Slab

The reinforcement details gathered through electromagnetic method revealed that the distribution of the reinforcement bars in the deck slab to be uniform in the longitudinal and transverse directions. The longitudinal re-bars were 20 mm in diameter at an average spacing of 400mm while the transverse were 16 mm diameter at an average spacing of 300 mm. The average covers were 45 mm and 60mm for longitudinal and transverse re-bars respectively. 3.4.2.3 Concrete strength, quality and homogeneity for the Deck Slab

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 30: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

The concrete strength measured through rebound (Schmidt) hammer method recorded an average strength of 55.5N/mm2.

The concrete matrix was inhomogeneous as revealed through ultrasonic method. This could be attributed to numerous multi directional cracks on the deck slab soffit.

3.4.2.4 Crack depths

The crack depths were ultrasonically determined and found to be 42mm at the widest points.

3.4.2.5 Concrete Deterioration

The highest carbonation depth recorded was 5mm indicating a remaining good cover of 40mm (least cover recorded was 45mm). This was an indication of no deterioration.

Probability of corrosion activity was insignificant as indicated by a high resistivity potential of 110.8 kΩcm.

3.4.3 WING WALLS3.4.3.1 Visual Inspection of Wing Walls

There were no visible structural defects on the wing walls

3.4.3.1 Steel Reinforcement Details for wing walls

The reinforcement details gathered through electromagnetic method revealed the distribution of the reinforcement bars in the wing walls on either side of the bridge to be uniform in the vertical and horizontal directions. The vertical re-bars were 20 mm diameter at an average spacing of 500mm while the horizontal were 16 mm diameter at an average spacing of 400mm. The average covers were varying at different points on either side with the lowest at 29 mm and highest at 55 mm.

BRIDGE AT KM 102+510

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 31: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

3.4.3.2 Concrete strength, quality and homogeneity for Wing Walls

The concrete strength as measured through rebound (Schmidt) hammer method recorded strengths between of 49.0N/mm2 to 60.0N/mm2.

The concrete matrix was generally homogeneous as revealed through ultrasonic method.

3.4.4 STEEL GIRDERS 3.4.4.1 Visual

There were spots of paint peeling off on the bracings and beams

Photo 21: showing a point where paint has peeled off a bottom flange plate of a girder for bridge at km 102+510

There was accumulation of soil at the abutment caps which covered the bottom flanges of the steel girders causing the paint to peel off resulting in early stages of corrosion.

The bolts and nuts for all the joints were in good condition.

There were no critical welded joints.

3.4.4.2 Ultrasonic Plate Thickness Tests for Steel Girders

There was no delaminating of the plates as determined ultrasonically. The thicknesses for the flange and web plates were determined ultrasonically and found to be uniform.

BRIDGE AT KM 102+510

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 32: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

3.4.4.3 BEARINGSThe bearing type was elastomeric of approximate size300x280.30 and were in good condition.

3.4.4.4 OTHER BRIDGE FITTINGSThe guard rails were intact and in good condition.

Photo 22: showing the guardrails for bridge at km 102+510

3.5 BRIDGE AT KM 125+670

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 33: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

This is a three span structure comprising a composite deck with 5 no. steel girders which are continuous through the three spans, wall type RC abutments, and wall type RC piers .There were no wing walls-gabion boxes had been used instead.

Photo 3: A side view of bridge at km 125+670

3.5.1 ABUTMENTS3.5.2 Visual Inspection of Abutments

The abutments could not be accessed due to protection works (stone pitching)

3.5.3 DECK SLAB3.5.3.1 Visual inspection of the Deck Slab

Deck slab thickness was 200mm.There were numerous (dense) multi directional cracks appearing from the soffit of the deck. The cracks were distributed all over the deck soffit. There were two major cracks that ran full width on each quarter of the span at the transverse bracings.

There were leakage stains along these cracks, an indication that the cracks were through hence the risk of exposure of re-bars to corrosion due to water ingress at the locations.(see photos below)

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 34: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Photo 23: showing cracks on the deck slab of bridge at km 125+670

Vibrations could be felt midspan upon movement of vehicles on the deck.

Maximum crack width was 1mm.

3.5.3.2 Steel Reinforcement details for the deck slab

The reinforcement details gathered through electromagnetic method revealed that the distribution of the reinforcement bars in the deck slab to be uniform in the longitudinal and transverse directions. The longitudinal re-bars were 20 mm in diameter at an average spacing of 400mm while the transverse were 12 mm diameter at an average spacing of 300 mm. The average covers were 25mm and 45 mm for longitudinal and transverse re-bars respectively.

3.5.3.3 Concrete strength, quality and homogeneity for the Deck Slab

The concrete strength measured through rebound (Schmidt) hammer method recorded a strength ranging between 40N/mm2 to 46.0N/mm2.

The concrete matrix was slightly inhomogeneous as revealed through ultrasonic method. This could be attributed to cracks on the deck slab soffit.

3.5.3.4 Crack depths for the Deck Slab

The crack depths were ultrasonically and visually determined and found to be through cracks at the widest points.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 35: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 125+670

3.5.3.5 Concrete Deterioration for the Deck Slab

The highest carbonation depth recorded was 4mm indicating a remaining good cover of 21mm (least cover recorded was 25 mm).This was an indication of low level deterioration.

Probability of corrosion activity was insignificant as indicated by a high resistivity potential of 112.3.

3.5.4 PIER WALLS3.5.4.1 Visual inspection of the Pier Walls

There were two vertical cracks on the Nyeri side pier wall.

The protection works near the bases of the pier walls and for the Nyeri side back fill were damaged.

The walls’ thicknesses were 600mm.

3.5.4.2 Steel Reinforcement Details for the Pier Walls

The reinforcement details gathered through electromagnetic method revealed the spacing of the reinforcement bars in the pier walls on either side of the bridge to be uniform the vertical and horizontal directions at 300 and 450 mm respectively. The vertical re-bars were 25 mm in diameter while the horizontal were 16 mm .The average covers were varying at different points on either side with the lowest at 40 mm and the highest at 67 mm.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 36: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 125+6703.5.4.3 Concrete Strength, Quality and Homogeneity of the pier walls

The concrete strength measured through rebound (Schmidt) hammer method recorded an average strength of 51.0N/mm2and 53.0 N/mm2 for Nyeri and Nyahururu side respectively.

The concrete matrix was generally homogeneous as revealed through ultrasonic method. Direct transmission of ultrasonic pulses gave an average ultrasonic velocity of 4.3 km/s, an indication of good quality concrete.

3.5.5 STEEL GIRDERS 3.5.5.1 Visual Inspection of Steel Girders

The paint had peeled off the bottom flanges of the steel girders near the abutment supports.

Photo 24: showing paint peeling off the bottom flange and web pates

Three bracings-two on Nyeri side and one on Nyahururu side-were missing, probably stolen. The beams were reachable near the abutments making it easy for vandals to remove bolts and steal the bracings.

Photo 25: Showing a missing bracing on bridge at km 125+670

There were no critical welded joints along the entire length of the girders.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 37: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

The bolts and nuts for all the joints were in good condition.

BRIDGE AT KM 125+670

3.5.6 BEARINGS

The bearings were elastomeric measuring 400x280x 30 mm and were in good condition.

Photo 26: Showing a bridge bearing for bridge at km 125+670

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 38: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

3.6 BRIDGE AT KM 142+450(NEAR MWEIGA TOWNSHIP)The structure comprises a composite deck with 5 no. steel beams, wall type RC abutments and wing walls.

Photo 27: showing a side view of bridge at km 142+450

3.6.1 ABUTMENTS3.6.1.1 Visual inspection of the Abutments

Three vertical cracks running mid-way the height from the abutment cap were found on the Nyahururu side abutment. One of the cracks appeared approximately midway between the two RHS beam supports while the other one propagated from the centre beam support at the abutment cap downwards.

Photo 28: Showing a vertical crack on the abutment wall for bridge at km 142+450

The maximum crack width was 1.1 mm

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 39: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 142+450(NEAR MWEIGA TOWNSHIP)3.6.1.2 Steel Reinforcement details for the Abutments

The reinforcement details gathered through electromagnetic method revealed the distribution of the reinforcement bars in the abutment walls on either side of the bridge to be uniform in the vertical and horizontal directions. The vertical re-bars were 25 mm in diameter at an average spacing of 450mm while the horizontal were 16 mm diameter at an average spacing of 400 mm. The average covers were varying at different points on either abutment wall with the lowest at 27 mm and highest at 67 mm.

3.6.1.3 Concrete strength, quality and homogeneity for The Abutments

The concrete strength measured through rebound (Schmidt) hammer method recorded strengths of between 54 N/mm2 to 64 N/mm2.

The concrete matrix was homogeneous except for LHS of Nyahururu side, though with no visible defects on the surface. This infers the likelihood of internal defects within the concrete matrix at the tested location.

3.6.1.4 Crack depths

The crack depths were ultrasonically determined and found to be 42mm at the widest points.

3.6.1.5 Concrete Deterioration

The highest carbonation depth recorded was 7mm indicating a remaining good cover of 20mm (least cover recorded was 27mm).This was an indication of low level deterioration.

Probability of corrosion activity was insignificant as indicated by high resistivity potential 111.5.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 40: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 142+450(NEAR MWEIGA TOWNSHIP)3.6.2 DECK SLAB3.6.2.1 Visual inspection of the deck slab

Deck slab thickness was 200mm.There were longitudinal cracks propagating from both Nyeri side and Nyahururu side towards the middle of the span.

Photo 29: showing longitudinal cracks on the deck of bridge at km 142+450

There were also other multi directional cracks distributed on the deck slab soffit.

Maximum crack width was 1.0mm.

There was lime like substance on the surface of the deck slab soffit which appeared prominently along the location of the re-bars forming a similar pattern to that of the re-bars layout.

Photo 30: showing lime stains on the deck soffit

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 41: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 142+450(NEAR MWEIGA TOWNSHIP)3.6.2.3 Steel Reinforcement details for the Deck Slab

The reinforcement details gathered through electromagnetic method revealed the distribution of the reinforcement bars in the deck slab to be uniform in the longitudinal and transverse directions. The longitudinal re-bars were 20 mm diameter at an average spacing of 400mm while the transverse were 12 mm diameter at an average spacing of 300 mm. The average covers were 45mm and 33 mm for longitudinal and transverse re-bars respectively.

3.6.2.4 Concrete strength, quality and homogeneity for the Deck Slab

The concrete strength as measured through rebound (Schmidt) hammer method recorded an average strength of 53.3N/mm2 (see details at various point in table no....)

3.6.2.5 Crack depths

The crack depths were ultrasonically determined and found to be 65 mm at the widest points.

3.6.2.6 Concrete Deterioration

Two methods were employed i.e. carbonation and resistivity potential to indicate the level of deterioration of concrete.

The highest carbonation depth recorded was 6mm indicating a remaining good cover of 27mm .This was an indication of low level deterioration.

Probability of corrosion activity was insignificant as indicated by high resistivity potential of 111.3.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 42: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 142+450(NEAR MWEIGA TOWNSHIP)3.6.3 WING WALLS3.6.3.1 Visual inspection of the Wing Walls

There were no visual structural defects on the wing walls

3.6.3.2 Steel Reinforcement Details for the Wing Walls

The reinforcement details gathered through electromagnetic method revealed the spacing of the reinforcement bars in the abutment walls on either side of the bridge not to be uniform in both vertical and horizontal directions varying between 300mm- 450mm and 400-450mm respectively. The vertical re-bars were 20 mm diameter while the horizontal were 16 mm diameter the average covers were varying at different points on either abutment with the lowest at 40 mm and the highest at 68 mm.

3.6.3.3 Concrete strength, quality and homogeneity for the wing walls

The concrete strength measured through rebound (Schmidt) hammer method recorded strengths between 55.0N/mm2 to 62.0 N/mm2.

The concrete matrix was slightly inhomogeneous as revealed through ultrasonic method.

3.6.4 STEEL GIRDERS 3.6.4.1 Visual inspection of Steel Girders

There were spots of paint peeling off on the beams signalling early stages of corrosion. The LHS girder had a large spot where paint had peeled off on the bottom flange.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 43: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Photo 31: showing spots of paint peeling off from the steel girders

BRIDGE AT KM 142+450(NEAR MWEIGA TOWNSHIP)

There was accumulation of soil at the abutment caps covering the bottom flanges of the steel girders causing the paint to peel off resulting in early stages of corrosion.

The bolts and nuts for the joints were in good condition.

There were no critical welded joints.

3.6.4.2 Thickness tests

There was no delaminating of the plates as determined ultrasonically. The thicknesses for the flange and web plates were determined ultrasonically and found to be uniform.

3.6.5 BEARINGSThe bearing type was elastomeric of size 400x280x 30 mm and was in good condition.

Photo 32:showing a bridge bearing for bridge at km 142+450

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 44: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

3.7 BRIDGE AT KM 173+120(MARUA)This is a three span structure comprising a composite deck with 4 no. steel girders for each span, column type RC abutments and column type RC piers

Photo 33: a side view of bridge at km 173+120

3.7.1 ABUTMENTS3.7.2 Visual Inspection of the abutments

The abutments could not be accessed due to gabion box protection works

Photo34: showing gabion boxes which prevented access to the abutment columns

3.7.3 DECK SLAB

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 45: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

3.7.2.1 Visual Inspection of the Deck Slab

The deck slab is in good condition. No structural defects were visible

BRIDGE AT KM 173+120(MARUA)3.7.2.2 Steel Reinforcement details for the Deck Slab

The reinforcement details gathered through electromagnetic method revealed that the distribution of the reinforcement bars in the deck slab to be uniform in the longitudinal and transverse directions. The longitudinal re-bars were 16 mm diameter at an average spacing of 150mm while the transverse were 12 mm diameter at an average spacing of 130 mm. The average covers were 20 mm and 10mm for longitudinal re-bars and transverse re-bars respectively.

3.7.2.3 Concrete strength, quality and homogeneity for the Deck Slab

The concrete strength measured through rebound (Schmidt) hammer method recorded an average strength of between 30.0 N/mm2 and 55.0 N/mm2.

The concrete matrix was slightly inhomogeneous as revealed through ultrasonic method.

3.7.2.4 Concrete Deterioration of the Deck Slab

The highest carbonation depth recorded was 3mm indicating a remaining good cover of 4mm (least cover recorded was 6 mm).This was an indication of high level deterioration. It should be noted that the little balance of effective good cover is contributed to by small initial covers and not due to deep carbonation.

Probability of corrosion activity was insignificant as indicated by a high resistivity potential of 111.4kΩcm.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 46: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

3.7.3 STEEL GIRDERS 3.7.3.1 Visual inspection of steel girders

The girders were generally in good condition along the spans. There was accumulation of soil through the expansion joint at the abutment caps which upon removal revealed a serious corrosion attack for the bottom flanges, mounting bolts, anchor plates and stiffening plates at the abutment caps supports.

BRIDGE AT KM 173+120(MARUA)The Nyeri side girders’ mounting bolts, stiffener plates and the anchor plates were severely corroded and had started to peel off. See photos below.

Photo 35: showing corrode mounting bolt and bottom flange plate

Photo 36: showing a corroded mounting bolts and a stiffening plate.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 47: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Photo 37: showing corroded mounting bolt ,nut ,bottom flange plate and stiffener plate. Notice the peel off

BRIDGE AT KM 173+120(MARUA)Corrosion at early stages was also observed at the mid span joints.

See photo below

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 48: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Photo 38: showing corrosion at early stages at the midspan joint

3.7.4 PIER COLUMNS

3.7.4.1 Visual inspection of pier columns

The pier columns are generally in good condition.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 49: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Photo 39: showing a column pier for bridge at km 173+120

BRIDGE AT KM 173+120(MARUA)3.7.4.2 Steel Reinforcement details for Pier Columns

There were 4 No. pier columns on either side of the river channel where the central span is suspended.The columns sizes were 450x600mm.The reinforcement details as gathered through electromagnetic method revealed 8 No.32mm diameter re-bars in each column. The average covers were varying at different points on the faces of the columns with the lowest at 18mm and highest at 36 mm.The links were spaced at 250mm.

3.7.4.3 Concrete strength, quality and homogeneity for Pier Columns

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 50: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

The concrete strength measured through rebound (Schmidt) hammer method recorded average strengths of 32 N/mm2 and 45 N/mm2 for Nyeri side and 43.0N/mm2 and 55.0N/mm2 for Karatina side. The concrete matrix was generally homogeneous as revealed through ultrasonic method. The quality of concrete was also found to be good through direct transmission of mode of ultrasonic method where an average ultrasonic pulse velocity of 4.4 km/s was recorded.

3.7.4.4 Concrete Deterioration for Pier Columns

The highest carbonation depth recorded was 6 mm indicating a remaining good cover of 12mm (least cover recorded was 18mm).This was an indication of medium level deterioration.

Probability of corrosion activity was insignificant as indicated by a high resistivity potential of 111.4 kΩcm.

3.7.4.5 BEARINGS

The bearing type was found to be steel plate laminations which had started to corrode.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 51: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

photo 40& 41:showing laminated metallic bearing on the Nyeri side abutment cap support

4.0 CONCLUSIONSFrom the results obtained, the following conclusions can be made:

i. There is severe cracking of the deck slabs

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 52: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

ii. The steel girders for the structures except bridge at km 173+120 are in good condition but may need repainting.

iii. The concrete strengths recorded for the structural elements are structurally okay.

iv. The concrete covers for the abutments and wing walls vary considerably at different points on these structural elements.

v. The danger of re-bar corrosion is minimal except at locations where the crack depths are greater than the concrete covers where water can get to the re-bars.

vi. There is adequate effective good cover for steel reinforcement bars-carbonation effect is minimal except forbridge at km 173+120 deck slab.

vii.The bearings for the structures are in good condition-except for bridge at km 173+120

viii. The deck slab forbridge at km 173+120 is in good conditionix. The steel girders for bridge at km 173+120(Marua Bridge) are

damaged by corrosion at the abutment capsupport. This is the same case with the mounting bolts and anchor plates-immediate attention is needed.

5.0 RECOMMENDATIONS1) An action plan is needed to address the following

i. Cracking on the deck slabs and abutmentsii. Damaged protection works for bridge at km125+670iii. Vandalism and theft of bracings for bridge at km 125+670iv. Lime accumulation for bridge at km 142+450.v. Severe corrosion of anchor plates, mounting bolts and bottom

flange edges at the abutment caps for bridge at km 173+120vi. Damage or lack of bearings for bridge at km 173+120

2) Development of a periodic inspection plan to monitor any further deterioration or performance of any rehabilitation worksthat may be implemented in response to no.1 above.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 53: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

3) The custodians of the structuresshould maintain proper records for the structures in future to enable comparison of status during inspection and original design requirements.

6.0 TESTS DONE

Seven tests were done namely:

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 54: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

i) Visual Inspection to ascertain the extent of wear and tear of the structure.

ii) Ultrasonic Test to determine the homogeneity, quality, and internal defects in the concrete matrix.

iii) Ultrasonic test to determine steel plate thicknesses and test for delamination.

iv) Electromagnetic Test to establish the steel reinforcement details for reinforced concrete.

v) Schmidt Hammer Test to determine the concrete strength insitu.

vi) Carbonation test to determine the effective good cover to the reinforcement.

vii) Resistivity potential to determine the probability of corrosion of the re-bars.

4.1 Test Method Principles4.1.1 Visual InspectionVisual Inspection is used in maintenance of facilities, inspection of equipment and structures using either or all of human senses such as vision, hearing, touch and smell. Visual Inspection typically means inspection using human senses and/or any non-specialized inspection equipment.

4.1.2 Schmidt Hammer TestThis method is based on the principle that the rebound of an elastic mass depends on the hardness of the surface that it strikes. The rebound number obtained from the Schmidt Hammer is correlated with

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 55: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

concrete cube crushing strength, whose calibration curves for 7 days and 28 days curing periods are contained in the digital instrument

4.1.3 Electromagnetic TestThis method is employed for locating steel in concrete using an Electromagnetic Covermeter. The principle method of test is by electromagnetic induction. When a probe carrying an alternating field is brought close to steel, eddy magnetic fields are generated by the steel, which reduces the primary field of the probe. At maximum induction level depicted by audio signals and reduction in minimum cover measurement, the location and orientation of a reinforcement bar can be established. After appropriate calibration, the technique is used to determine concrete cover, location and diameter of reinforcement bars (when reinforcement bars are parallel to the surface of the probe).Normally, closely packed reinforcement bars influence the accuracy of this method while determining the bar size. The accuracy of the method employed for bar size determination is ±2mm. 4.1.4 Ultrasonic Pulse velocity Test

The velocity of ultrasonic pulses traveling through a solid material depends on the density and the elastic properties of that material. Ultrasonic pulse velocity testing using low frequency pulses of 54 kHz is employed as a Non Destructive testing technique to determine the quality and homogeneity of concrete. This is given by the velocity at which the pulses will travel through the concrete. Regions of cracks or damaged material will have a corresponding reduction in the pulse velocity due to their high acoustic impedance.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 56: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

In this case two modes of transmission were employed namely:

a) Direct transmission to determine the pulse velocity in km/s hence the quality of concrete.

b) Indirect transmission method was employed to determine the homogeneity of concrete. A straight line graph of transit time against distance indicates a homogeneous concrete matrix. Deviations from the straight line are indications of inhomogeneity.

4.1.5 Carbonation Test.

The drilling method is used to determine the depth of carbonation. The drilled out material at prescribed depth is then analyzed for carbonation using phenolphthalein reagent. Presence of carbonation is depicted by no color change while the color changes to pink in the absence of carbonation.

A deterioration degree is judged based on the balance of carbonation depth as shown in the table below.

Based on this table, the degree of reinforcement corrosion is “None” for the results of tests having more than 30 mm depth for the balance of carbonation depth.

Table 2: Evaluation of Carbonation Depth

Deterioration degree

Balance of Carbonation Depth

Degree of reinforcement

corrosionHigh T < 0 mm Large

Medium 0 mm ≤ T < 10 mm MediumLow 10 mm≤ T < 30 mm LowNone 30 mm≤ T None

Note: Balance of Carbonation Depth = Cover – Carbonation DepthDETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 57: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

4.1.6 Reinforcement Corrosion Investigation (Resistivity potential method)

The time at which corrosion of steel may commence and the rate at which it may proceed is dependent upon the properties of the cement paste and the permeability of the concrete. Since the electrical conductivity of concrete is an electrolysis process, which takes place by ionic movement in the aqueous pore solution of the cement matrix, it follows that a highly permeable concrete will have a high conductivity and low electrical resistance.

The knowledge of the electrical resistance of concrete can provide a measure of the possible corrosion of steel embedded in it as shown below

Table 3: Resistivity Level vs Possible Corrosion Rate

Resistivity Level(k ohm cm) Possible Corrosion Rate<5 Very high

5-10 high10-20 moderate to low>20 insignificant

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 58: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

DETAILED RESULTS DATA SHEETS

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 59: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 60+030ABUTMENTSElectromagnetic test results for the abutments

Test Element/Location Re-bar spacing(mm)

Average covers(mm)

Re-bar size(mm)

Abutment wall

Thickness(mm)

A1 –Nyeri Side

At abutment cap

LHS Vertical:350Horizontal:400

Vertical:45Horizontal:65

Vertical:25Horizontal:16

700

Centre Vertical:450Horizontal:400

Vertical:42Horizontal:63

Vertical:25Horizontal:16

RHS Horizontal:480Horizontal: 400

Vertical: 35Horizontal:60

Vertical: 25Horizontal:16

Along the middle line

LHS Vertical:350Horizontal:450

Vertical:45Horizontal:60

Vertical:25Horizontal:16

Centre Vertical:450Horizontal:400

Vertical:36Horizontal:60

Vertical:25Horizontal:16

RHS Horizontal:480Horizontal: 400

Vertical: 35Horizontal:60

Vertical: 25Horizontal:16

A2 –Nyahururu Side

At abutment cap

LHS Vertical:450Horizontal:500

Vertical:45Horizontal:75

Vertical:25Horizontal:16

Centre Vertical:400Horizontal:470

Vertical:35Horizontal:65

Vertical:25Horizontal:16

RHS Horizontal:380Horizontal:450

Vertical: 61Horizontal:33

Vertical:25Horizontal:16

Along the middle line

LHS Vertical:450Horizontal:420

Vertical: 52Horizontal:66

Vertical: 25Horizontal:16

Centre Vertical:400Horizontal:400

Vertical:38Horizontal:73

Vertical:25Horizontal:16

RHS Horizontal:400Horizontal:400

Vertical: 33Horizontal:71

Vertical:25Horizontal:16

Schmidt Hammer Test Results for the Abutments

Test Element/LocationAverage concrete

strength (N/mm2)

A1 –Nyeri SideAt abutment cap

LHS 49.5Centre 53.1

RHS 53.1

Along the middle line

LHS 41.3Centre 44.1

RHS 44.0

A2 –Nyahururu Side

At abutment capLHS 54.0

Centre 48.0RHS 44.0

Along the middle line

LHS 48.0Centre 43.0

RHS 45.0

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 60: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 60+030Ultrasonic Pulse Velocity Results for the Abutments

Test Element/Location Homogeneity of concrete matrix

A1 –Nyeri Side

LHS Homogeneous Centre Homogeneous

RHS HomogeneousLHS Homogeneous

Centre HomogeneousRHS Homogeneous

A2 –Nyahururu Side

LHS HomogeneousCentre Homogeneous

RHS HomogeneousLHS Homogeneous

Centre HomogeneousRHS Homogeneous

Carbonation Test Results for the AbutmentsTest

Element/LocationCarbonation

depth(mm)

Least cover recorded

(mm)

Balance of carbonation

depth(mm)

Remarks

A1-Nyeri side 6 35 29Low

deterioration degree

A2-Nyahururu side 6 33 27

Resistivity Test Results for the AbutmentsTest

Element/LocationResistivity

(kΩcm)Remarks

A1-Nyeri side 111.3 Probability of corrosion is insignificant

A2-Nyahururu side 111.5

Crack Profiles for the AbutmentsTest

Element/Location

Crack no.

Crack length(mm)

Crack width(mm)

Crack depth(mm)

A1-Nyeri sideCr.1 Full height of the

abutment wall1.4 160

Cr.2 Full height of the abutment wall

0.8 76

A2-Nyahururuside

Cr.1 Full height of the abutment wall 0.8 70

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 61: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 60+030DECK SLABElectromagnetic Test Results for the Deck Slab

Test Location Re-bar spacing(mm)

Average covers(mm)

Re-bar size(mm)

Deck slab Thickness

(mm)

DS1-Nyeri Side Longitudinal:400Transverse:300

Longitudinal:50Transverse:35

Longitudinal:20Transverse:16

250DS3-Nyahururu side

Longitudinal:400Transverse:300

Longitudinal:55Transverse:37

Longitudinal:20Transverse:16

Schmidt hammer Test Results for the Deck Slab

Test LocationAverage concrete strength

(N/mm2)

DS1-Nyeri Side 56.1

DS2 –Mid Span 59.6DS3-Nyahururu side

62.0

Ultrasonic Pulse Velocity Results for the Deck SlabTest Element/Location Homogeneity of concrete matrix

DS1-Nyeri SideNot homogenous-transmission of ultrasonic pulses not consistent

DS2-Nyahururu side Not homogenous-transmission of ultrasonic pulses not consistent

Carbonation Test Results for the Deck SlabTest

Element/Location

Carbonation depth(mm)

Least cover recorded

(mm)

Balance of carbonation

depth(mm)

Remarks

DS1-Nyeri Side 6 35 29Low deterioration degree

DS3-Nyahururu side 6 37 31

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 62: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 60+030DECK SLABResistivity Test Results for the Deck Slab

Test Element/Locatio

n

Resistivity (kΩcm)

Remarks

DS1-Nyeri Side111.2

Probability of corrosion is insignificantDS2-Nyahururu

side109.1

Crack profiles For the Deck SlabTest

Element/Location

Crack no.

Crack length(mm)

Crack width(mm)

Crack depth(mm)

DS1-Nyeri side Cr.1 9.9-Full width 1.0 Through crackDS3-Nyahururu side

Cr.1 9.9-Full width 1.0 Through crack

WING WALLSElectromagnetic Test Results for the Wing Walls

Test Element/Location

Re-bar spacing(mm)

Average covers(mm)

Re-bar size(mm)

Nyeri Side LHS Vertical:380Horizontal:460

Vertical:39Horizontal:53

Vertical:20Horizontal:16

Nyahururu Side LHS

Vertical:480Horizontal:470

Vertical:45Horizontal:60

Vertical:20Horizontal:16

Schmidt Hammer Test Results for the Wing Walls

Test Element/LocationAverage concrete strength

(N/mm2)Nyeri Side

LHS 56.0

Nyahururu Side LHS 60.0

Ultrasonic Pulse Velocity Results for the Wing WallsTest Element/Location Homogeneity of concrete

matrix

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 63: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Nyeri Side LHS Homogeneous

Nyahururu Side LHS

BRIDGE AT KM 60+030Carbonation Test Results for the Wing Walls

Test Element/Locatio

n

Carbonation depth(mm)

Least cover recorded

(mm)

Balance of carbonation

depth(mm)

Remarks

Nyeri side 6 26 20Low deterioration degreeNyahururu side

6 31 25

Resistivity test results for the Wing WallsTest

Element/Location

Resistivity (kΩcm)

Remarks

Nyeri side 110.2Probability of corrosion is insignificant

Nyahururu side108.2

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 64: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 60+030STEEL GIRDERSUltrasonic Tests for Plate Thickness & Lamination for steel girders

Steel Girder No.

Section Dimensions (mm)

Continuity Across Plate Thickness

SG1 LHSNo Delamination

SG2 LHSNo Delamination

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

22.7

13.7

600

Page 65: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 60+030STEEL GIRDERSUltrasonic Tests for Plate Thickness & Lamination for steel girders

Steel Girder No.

Section Dimensions (mm)

Continuity Across Plate Thickness

SG3 CentreNo Delamination

SG2 RHSNo Delamination

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

22.6

14.5

600

22.4

14.0

600

Page 66: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 60+030STEEL GIRDERSUltrasonic Tests for Plate Thickness & Lamination for steel girders

Steel Girder No.

Section Dimensions (mm)

Continuity Across Plate Thickness

SG1 RHSNo Delamination

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

22.5

14.0

600

Page 67: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 84+520-NDARAGWAABUTMENTSElectromagnetic test results for the abutments

Test Element/Location Re-bar spacing(mm)

Average covers(mm)

Re-bar size(mm)

Abutment wall

Thickness

(mm)

A1 –Nyeri Side

At abutment cap

LHS Vertical:500Horizontal:450

Vertical:45Horizontal:66

Vertical:25Horizontal:16

770Centre Vertical:470Horizontal:370

Vertical:40Horizontal:60

Vertical:25Horizontal:16

RHS Vertical:480Horizontal:360

Vertical:36Horizontal:54

Vertical:25Horizontal:16

Along the middle line

LHS Vertical:500Horizontal:400

Vertical:40Horizontal:60

Vertical:25Horizontal:16

Centre Vertical:520Horizontal:400

Vertical:40Horizontal:60

Vertical:25Horizontal:16

RHS Vertical:480Horizontal:400

Vertical:37Horizontal:60

Vertical:25Horizontal:16

A2 –Nyahururu Side

At abutment cap

LHS Vertical:450Horizontal:400

Vertical:45Horizontal:65

Vertical:25Horizontal:16

770

Centre Vertical:400Horizontal:440

Vertical:37Horizontal:60

Vertical:25Horizontal:16

RHS Vertical:500Horizontal:400

Vertical:35Horizontal:60

Vertical:25Horizontal:16

Along the middle line

LHS Vertical:450Horizontal:380

Vertical:40Horizontal:65

Vertical:25Horizontal:16

Centre Vertical:400Horizontal:450

Vertical:36Horizontal:60

Vertical:25Horizontal:16

RHS Vertical:500Horizontal:400

Vertical:36Horizontal:60

Vertical:25Horizontal:16

Schmidt Hammer Test Results for the Abutments

Test Element/LocationAverage concrete

strength (N/mm2)

A1 –Nyeri SideAt abutment cap

LHS 51.7Centre 41.1

RHS 54.9

Along the middle line

LHS 54.1Centre 48.8

RHS 53.8

A2 –Nyahururu Side

At abutment capLHS 48.1

Centre 55.7RHS 52.5

Along the middle line

LHS 57.6Centre 53.3

RHS 54.9

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 68: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 84+520Ultrasonic Pulse Velocity Results for the Abutments

Test Element/Location Homogeneity of concrete matrix

A1 –Nyeri Side

LHS HomogeneousCentre Homogeneous

RHS HomogeneousLHS Homogeneous

Centre HomogeneousRHS Homogeneous

A2 –Nyahururu Side

LHS HomogeneousCentre Homogeneous

RHS HomogeneousLHS Homogeneous

Centre HomogeneousRHS Homogeneous

Carbonation Test Results for the AbutmentsTest

Element/Location

Carbonation depth(mm)

Least cover

recorded

(mm)

Balance of carbonatio

n depth(mm)

Remarks/deterioration degree

A1-Nyeri side 3 32 29 Low A2-Nyahururu side 3 36 33 None

Resistivity Test Results for the AbutmentsTest

Element/LocationResistivity

(kΩcm)Remarks

A1-Nyeri side111.7

Probability of corrosion is insignificantA2-Nyahururu side 111.5

Crack Profiles for the AbutmentsTest

Element/Location

Crack no.

Crack length(mm)

Crack width(mm)

Crack depth(mm)

A1-Nyeri side Cr.1 2000 0.8 25A2-Nyahururuside

Cr.1 1500 1.0 27Cr.2 1500 0.6 22

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 69: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 84+520DECK SLABElectromagnetic Test Results for the Deck Slab

Test Location Re-bar spacing(mm)

Average covers(mm)

Re-bar size(mm)

Deck slab Thickness

(mm)

DS1-Nyeri Side Longitudinal:400Transverse:300

Longitudinal:45Transverse:27

Longitudinal:20Transverse:16

220DS3-Nyahururu side

Longitudinal:400Transverse:300

Longitudinal:45Transverse:34

Longitudinal:20Transverse:16

Schmidt hammer Test Results for the Deck Slab

Test LocationAverage concrete strength

(N/mm2)

DS1-Nyeri Side 46.0

DS2-Nyahururu side 47.9

Ultrasonic Pulse Velocity Results for the Deck SlabTest Element/Location Homogeneity of concrete matrix

DS1-Nyeri SideSlightly inhomogeneous

DS2-Nyahururu side Slightly inhomogeneous

Carbonation Test Results for the Deck SlabTest

Element/Location

Carbonation depth(mm)

Least cover recorded

(mm)

Balance of carbonation

depth(mm)

Remarks/degree of

deterioration

DS1-Nyeri Side 3 24 21 lowDS2-Nyahururu

side 3 33 30 low

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 70: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 84+520DECK SLABResistivity Test Results for the Deck Slab

Test Element/Locatio

n

Resistivity (kΩcm)

Remarks

DS1-Nyeri Side 110.7 Probability of corrosion is insignificantDS3-Nyahururu

side 110.9

Crack Profiles for the Deck SlabTest

Element/Location

Crack no.

Crack length(mm)

Crack width(mm)

Crack depth(mm)

DS1-Nyeri side Cr.1 Full width 1.2Through cracksCr.2 Full width 1.0

DS2-Nyahururu side

Cr.1 Full width 1.2Cr.2 Full width 1.2

WING WALLSElectromagnetic Test Results for the Wing Walls

Test Element/LocationRe-bar spacing

(mm)Average covers(mm)

Re-bar size(mm)

Nyeri Side RHSVertical:470

Horizontal:450Vertical:40

Horizontal:61Vertical:20

Horizontal:16

Nyahururu Side LHSVertical:350

Horizontal:260,370Vertical:60

Horizontal:75Vertical:20

Horizontal:16

Schmidt Hammer Test Results for the Wing Walls

Test Element/LocationAverage concrete strength

(N/mm2)

Nyeri SideRHS 56.4

LHS 54.0

Nyahururu Side

LHS 53.9

RHS 55.0

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 71: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 84+520Ultrasonic Pulse Velocity Results for the Wing Walls

Test Element/Location Homogeneity of concrete matrix

Nyeri SideLHS Homogeneous

RHS Homogeneous

Nyahururu Side LHS Homogeneous

RHS Homogeneous

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 72: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 84+520STEEL GIRDERSUltrasonic Tests for Plate Thickness & Lamination

Steel Girder No.

Section Dimensions (mm)

Continuity Across Plate Thickness

SG1 LHSNo Delamination

SG2 LHSNo Delamination

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

23.5

14.2600

23.7

14.2

600

Page 73: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 84+520STEEL GIRDERSUltrasonic Tests for Plate Thickness & Lamination

Steel Girder No.

Section Dimensions (mm)

Continuity Across Plate Thickness

SG3 CentreNo Delamination

SG2 RHSNo Delamination

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

22.6

14.3600

22.3

14.1

600

Page 74: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 84+520STEEL GIRDERSUltrasonic Tests for Plate Thickness & Lamination

Steel Girder No.

Section Dimensions (mm)

Continuity Across Plate Thickness

SG1 RHSNo Delamination

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

22.4

13.9600

Page 75: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 84+520PIER COLUMNSElectromagnetic Test Results for the Pier Columns

Test element /location

Column Size(mm), No. & Arrangement of re-bars

Re-bar size

(mm)

Average covers(mm)

Link Details(mm)

PC 1-Nyeri sideLHS 32

Side A:50Side B:63Side C:70Side D:55

size:10Spacing:300

PC 2-Nyeri sideRHS 32

Side A:53Side B:56Side C:56Side D:50

size:10Spacing:300

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

D

200 200

250250

600

750

A

B

C

D

D

200 200

250250

600

750

A

B

C

D

Page 76: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 84+520Test

element /location

Column Size(mm), No. & Arrangement of re-bars

Re-bar size

(mm)

Average covers(mm)

Link Details(mm)

PC 1-Nyahururu

sideLHS

32Side A:58Side B:56Side C:51Side D:60

size:10Spacing:300

PC 1-Nyahururu

sideLHS

32Side A:55Side B:56Side C:50Side D:50

size:10Spacing:300

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

B

D

200 200

250250

600

750

A

B

C

D

Page 77: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 84+520Schmidt Hammer Test Results for the Pier Columns

Test Element/LocationAverage concrete strength

(N/mm2)

Nyeri SideRHS 55.0

LHS 61.6

Nyahururu Side

LHS 48.0

RHS 54.0

Ultrasonic Pulse Velocity Results for the Pier Columns for homogeneityTest Element/Location Homogeneity of concrete matrix

Nyeri Side

LHS Homogeneous

RHS Homogeneous

Nyahururu Side LHSHomogeneous

RHSHomogeneous

Ultrasonic Pulse Velocity Results for the Pier Columns for quality of concrete

Test Element/LocationTransit

time(µs)

Distance (mm)

Pulse velocity(km/s)

remarks

Nyeri SideLHS 144 600 4.16 Good quality

concreteRHS 148 600 4.05

Nyahururu Side LHS 137 600 4.40

RHS 142 600 4.22

Carbonation Test Results for the Pier ColumnsTest

Element/Location

Carbonation depth(mm)

Least cover

recorded

(mm)

Balance of carbonatio

n depth(mm)

Remarks/deterioration degree

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 78: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Nyeri side 3 49 46 None Nyahururu side

3 40 37

BRIDGE AT KM 84+520Resistivity Test Results for the Pier Columns

Test Element/Locatio

n

Resistivity (kΩcm)

Remarks

Nyeri side111.6

Probability of corrosion is insignificantNyahururu side

111.6

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 79: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 93+380ABUTMENTSElectromagnetic Test Results for the Abutments

Test Element/Location Re-bar spacing(mm)

Average covers(mm)

Re-bar size(mm)

Abutment wall

Thickness(mm)

A1 –Nyeri Side

At abutment cap

LHS Vertical:450Horizontal:400

Vertical:30Horizontal:55

Vertical:25Horizontal:16

700

Centre Vertical:450Horizontal:500

Vertical:32Horizontal:55

Vertical:25Horizontal:16

RHS vertical:450Horizontal:440

Vertical:40Horizontal:65

Vertical:25Horizontal:16

Along the middle line

LHS Vertical:450Horizontal:400

Vertical:40Horizontal:70

Vertical:25Horizontal:16

Centre Vertical:450Horizontal:400

Vertical:36Horizontal:50

Vertical:25Horizontal:16

RHS Vertical :450Horizontal:420

Vertical:40Horizontal:65

Vertical:25Horizontal:16

A2 –Nyahururu Side

At abutment cap

LHS Vertical:430Horizontal:400

Vertical:28Horizontal:55

Vertical:25Horizontal:16

700

Centre Vertical:440Horizontal:400

Vertical:35Horizontal:60

Vertical:25Horizontal:16

RHS Vertical :450Horizontal:400

Vertical:54Horizontal:72

Vertical:25Horizontal:16

Along the middle line

LHS Vertical:450Horizontal:400

Vertical:30Horizontal:55

Vertical:25Horizontal:16

Centre Vertical:440Horizontal:400

Vertical:30Horizontal:55

Vertical:25Horizontal:16

RHS Vertical :450Horizontal:400

Vertical:40Horizontal:66

Vertical:25Horizontal:16

Schmidt Hammer Test Results for the Abutments

Test Element/LocationAverage concrete

strength (N/mm2)

A1 –Nyeri SideAt abutment cap

LHS 45.5Centre 60.3

RHS 43.2

Along the middle line

LHS 57.6Centre 43.8

RHS 44.2

A2 –Nyahururu At abutment cap

LHS 40.1Centre 58.7

RHS 48.2

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 80: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Side Along the middle line

LHS 51.1Centre 56.2

RHS 45.8

BRIDGE AT KM 93+380ABUTMENTSUltrasonic Pulse Velocity Results for the Abutments

Test Element/Location Homogeneity of concrete matrix

A1 –Nyeri Side

LHS Homogeneous Centre Homogeneous

RHS HomogeneousRHS Homogeneous

A2 –Nyahururu Side

LHS HomogeneousCentre Homogeneous

RHS HomogeneousCentre Homogeneous

RHS Homogeneous

Carbonation Test Results for the AbutmentsTest

Element/Location

Carbonation depth(mm)

Least cover

recorded

(mm)

Balance of carbonatio

n depth(mm)

Remarks/deterioration degree

A1-Nyeri side 5 30 25 Low A2-Nyahururu side 5 28 23 Low

Resistivity Test Results for the AbutmentsTest

Element/LocationResistivity

(kΩcm)Remarks

A1-Nyeri side110.8

Probability of corrosion is insignificantA2-Nyahururu side 110.4

Crack Profiles for the AbutmentsTest

Element/Location

Crack no.

Crack length(mm)

Crack width(mm)

Crack depth(mm)

A1-Nyeri sideCr.1 Full height of

abutment wall 1.0 61

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 81: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Cr.2 Full height of abutment wall 1.0 60

Cr.3 Full height of abutment wall 0.8 48

Cr.4 Full height of abutment wall 0.6 40

BRIDGE AT KM 93+380Crack Profiles for the Abutments

Test Element/Locatio

n

Crack no.

Crack length(mm)

Crack width(mm)

Crack depth(mm)

A2-Nyahururuside

Cr.1 Full height of abutment wall

1.055

Cr.2 Full height of abutment wall 1.0 41

Cr,3 Full height of abutment wall 0.6 33

DECK SLABElectromagnetic Test Results for the Deck Slab

Test Location Re-bar spacing(mm)

Average covers(mm)

Re-bar size(mm)

Deck slab Thickness

(mm)

DS1-Nyeri Side Longitudinal:400Transverse:300

Longitudinal:54Transverse:34

Longitudinal:20Transverse:16

200DS2 –Mid Span

Longitudinal:400Transverse:300

Longitudinal:35Transverse:50

Longitudinal:20Transverse:16

DS3-Nyahururu side

Longitudinal:400Transverse:300

Longitudinal:34Transverse:48

Longitudinal:20Transverse:16

Schmidt Hammer Test Results for the Deck Slab

Test LocationAverage concrete strength

(N/mm2)

DS1-Nyeri Side 54.5

DS2 –Mid Span 56.6

DS3-Nyahururu side 56.1

Ultrasonic Pulse Velocity Results for the Deck SlabTest Element/Location Homogeneity of concrete matrix

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 82: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

DS1-Nyeri SideHomogeneous

DS2 –Mid SpanHomogeneous

DS3-Nyahururu side Homogeneous

BRIDGE AT KM 93+380Carbonation Test Results for the Deck Slab

Test Element/Locatio

n

Carbonation depth(mm)

Least cover

recorded(mm)

Balance of carbonation

depth(mm)

Remarks/degree of

deterioration

DS1-Nyeri Side 5 34 29 Low

DS2 –Mid Span 5 35 30DS3-Nyahururu

side 5 34 29

DECK SLABResistivity Test Results for the Deck Slab

Test Element/Locatio

n

Resistivity (kΩcm)

Remarks

DS1-Nyeri Side 106.8 Probability of corrosion is insignificant

DS2 –Mid Span 108.8DS3-Nyahururu

side 110.2

Crack profiles For the Deck SlabTest

Element/Location

Crack no.

Crack length(mm)

Crack width(mm)

Crack depth(mm)

DS1-Nyeri side Cr.1 11600-full width 1.0 Through crackDS3-Nyahururu side

Cr.1 11600-full width 1.0 Through crack

WING WALLSElectromagnetic Test Results for the Wing WallsDETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 83: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Test Element/LocationRe-bar spacing(mm)

Average covers(mm)

Re-bar size(mm)

Nyeri Side LHSVertical:450Horizontal:350

Vertical:37Horizontal:60

Vertical:20Horizontal:16

Nyahururu Side RHSVertical:450Horizontal:350

Vertical:45Horizontal:68

Vertical:20Horizontal:16

BRIDGE AT KM 93+380Schmidt Hammer Test Results for the Wing Walls

Test Element/LocationAverage concrete strength

(N/mm2)

Nyeri Side LHS 57.9

RHS 57.7

Nyahururu Side RHS 65.0

LHS 60.2

Ultrasonic Pulse Velocity Results for the Wing WallsTest Element/Location Homogeneity of concrete matrix

Nyeri SideLHS

Homogeneous

RHSHomogeneous

Nyahururu Side LHSHomogeneous

RHSHomogeneous

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 84: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 93+380STEEL GIRDERSUltrasonic Tests for Plate Thickness & Lamination

Steel Girder No.

Section Dimensions (mm)

Continuity Across Plate Thickness

SG1 LHSNo Delamination

SG2 LHSNo Delamination

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

22.1

14.2

600

22.0

14.2

600

Page 85: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 93+380Steel Girder

No.Section Dimensions

(mm)Continuity Across

Plate Thickness

SG3 CentreNo Delamination

SG2 RHSNo Delamination

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

22.5

14.0

600

22.4

14.2

600

Page 86: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 93+380Steel Girder

No.Section Dimensions

(mm)Continuity Across

Plate Thickness

SG1 RHSNo Delamination

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

22.1

14.0

600

Page 87: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 102+510ABUTMENTSElectromagnetic Test Results for the Abutments

Test Element/LocationRe-bar spacing(mm)

Average covers(mm)

Re-bar size(mm)

Abutment wall

Thickness(mm)

A1 –Nyeri Side

LHS Vertical:450Horizontal:400

Vertical:45Horizontal:60

Vertical:25Horizontal:16

Centre Vertical:450Horizontal:400

Vertical:40Horizontal:50

Vertical:25Horizontal:16

RHS vertical:450Horizontal:400

Vertical:26Horizontal:57

Vertical:25Horizontal:16

A2 –Nyahururu Side

LHS Vertical:450Horizontal:400

Vertical:40Horizontal:55

Vertical:25Horizontal:16

Centre Vertical:450Horizontal:400

Vertical:37Horizontal:51

Vertical:25Horizontal:16

RHS vertical:450Horizontal:400

Vertical:30Horizontal:55

Vertical:25Horizontal:16

Schmidt Hammer Test Results for the Abutments

Test Element/LocationAverage concrete strength

(N/mm2)

A1 –Nyeri Side

LHS 59.1Centre 57.7

RHS 51.0Side A2 –Nyahururu

LHS 40.8Centre 52.4

RHS 55.8

ABUTMENTSUltrasonic Pulse Velocity Results for the Abutments

Test Element/Location Homogeneity of concrete matrix

A1 –Nyeri Side

LHS Homogeneous Centre Homogeneous

RHS Homogeneous

A2 –Nyahururu Side

LHS HomogeneousCentre Homogeneous

RHS Homogeneous

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 88: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 102+510Carbonation Test Results for the Abutments

Test Element/Location

Carbonation depth(mm)

Least cover

recorded(mm)

Balance of carbonation

depth(mm)

Remarks/deterioration degree

A1-Nyeri side 4 26 22Low

A2-Nyahururu side 4 30 26 Low

Resistivity Test Results for the AbutmentsTest

Element/LocationResistivity

(kΩcm)Remarks

A1-Nyeri side110.8

Probability of corrosion is insignificant

A2-Nyahururu side 110.8

Crack Profiles for the AbutmentsTest

Element/Location

Crack no.

Crack length(mm)

Crack width(mm)

Crack depth(mm)

A1-Nyeri side Cr.1 1400 0.4 20Cr.2 1400 0.7 33Cr.3 1400 1.2 42Cr.4 1400 1.2 40

A2-Nyahururuside

Cr.1 2000 0.8 35Cr.2 2000 1.0 38

DECK SLABElectromagnetic Test Results for the Deck Slab

Test Location Re-bar spacing(mm)

Average covers(mm)

Re-bar size(mm)

Deck slab Thickness

(mm)

DS1-Nyeri Side Longitudinal:400Transverse:300

Longitudinal:45Transverse:30

Longitudinal:20Transverse:16 200

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 89: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

DS2 –Mid SpanLongitudinal:400Transverse:300

Longitudinal:45Transverse:60

Longitudinal:20Transverse:16

DS3-Nyahururu side

Longitudinal:400Transverse:300

Longitudinal:33Transverse:45

Longitudinal:20Transverse:16

BRIDGE AT KM 102+510Schmidt hammer Test Results for the Deck Slab

Test LocationAverage concrete strength

(N/mm2)

DS1-Nyeri Side 55.4

DS2 –Mid Span 57.7DS3-Nyahururu side

54.6

Ultrasonic Pulse Velocity Results for the Deck SlabTest Element/Location Homogeneity of concrete matrix

DS1-Nyeri SideInhomogeneous

DS2 –Mid SpanInhomogeneous

DS3-Nyahururu side Inhomogeneous

Carbonation Test Results for the Deck SlabTest

Element/Location

Carbonation depth(mm)

Least cover

recorded(mm)

Balance of carbonation

depth(mm)

Remarks/deterioration degree

DS1-Nyeri Side 5 30 25 Low

DS2 –Mid Span 5 45 40None

DS3-Nyahururu side 5 33 28

None

DECK SLABResistivity Test Results for the Deck Slab

Test Element/Locatio

n

Resistivity (kΩcm)

Remarks

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 90: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

DS1-Nyeri Side110.8

Probability of corrosion is insignificant

DS2 –Mid Span110.8

DS3-Nyahururu side

110.8

BRIDGE AT KM 102+510Crack profiles For the Deck Slab

Test Element/Locatio

n

Crack no.

Crack length(mm)

Crack width(mm)

Crack depth(mm)

DS1-Nyeri side Cr.1 Full width of the deck

0.8 Through

DS3-Nyahururu side

Cr.1 Full width of the deck

0.8 Through

WING WALLSElectromagnetic Test Results for the Wing Walls

Test Element/LocationRe-bar spacing(mm)

Average covers(mm)

Re-bar size(mm)

Nyeri Side RHSVertical:500Horizontal:400

Vertical: 29Horizontal:50

Vertical: 20Horizontal:16

Nyahururu Side LHSVertical:500Horizontal:450

Vertical: 35Horizontal:55

Vertical: 20Horizontal:16

Schmidt Hammer Test Results for the Wing Walls

Test Element/LocationAverage concrete strength

(N/mm2)

Nyeri SideRHS

59.1

LHS60.1

Nyahururu Side

LHS48.8

RHS55.8

Ultrasonic Pulse Velocity Results for the Wing WallsTest Element/Location Homogeneity of concrete matrix

Nyeri Side

LHS Homogeneous

RHS HomogeneousHomogeneous

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 91: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Nyahururu Side LHS

RHSHomogeneous

BRIDGE AT KM 102+510STEEL GIRDERSUltrasonic Tests for Plate Thickness & Lamination

Steel Girder No.

Section Dimensions (mm)

Continuity Across Plate Thickness

SG1 LHSNo Delamination

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 92: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

SG2 LHSNo Delamination

BRIDGE AT KM 102+510Steel Girder

No.Section Dimensions

(mm)Continuity Across

Plate Thickness

SG3 CentreNo Delamination

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

22.7

14.1

600

21.9

14.3

600

Page 93: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

SG2 RHSNo Delamination

BRIDGE AT KM 102+510Steel Girder

No.Section Dimensions

(mm)Continuity Across

Plate Thickness

SG1 RHSNo Delamination

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

22.4

14.0

600

Page 94: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 125+670DECK SLABElectromagnetic Test Results for the Deck Slab

Test Location Re-bar spacing(mm)

Average covers(mm)

Re-bar size(mm)

Deck slab Thickness

(mm)

DS1-Nyeri Side Longitudinal:400Transverse:300

Longitudinal:45Transverse:32

Longitudinal:20Transverse:12

200DS2 –Mid Span

Longitudinal:400Transverse:300

Longitudinal:45Transverse:25

Longitudinal:20Transverse:12

DS3-Nyahururu side

Longitudinal:400Transverse:300

Longitudinal:51Transverse:38

Longitudinal:20Transverse:12

Schmidt Hammer Test Results for the Deck Slab

Test LocationAverage concrete strength

(N/mm2)

DS1-Nyeri Side 40.2

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 95: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

DS2 –Mid Span 43.4DS3-Nyahururu side

46.5

Ultrasonic Pulse Velocity Results for the Deck SlabTest Element/Location Homogeneity of concrete matrix

DS1-Nyeri SideInhomogeneous

DS2 –Mid SpanInhomogeneous

DS3-Nyahururu side Inhomogeneous

Carbonation Test Results for the Deck SlabTest

Element/Location

Carbonation depth(mm)

Least cover

recorded

(mm)

Balance of carbonatio

n depth(mm)

Remarks/deterioration degree

DS1-Nyeri Side 4 25 21Low

DS2-Nyahururu side 4 38 34

None

BRIDGE AT KM 102+510DECK SLABResistivity Test Results for the Deck Slab

Test Element/Locatio

n

Resistivity (kΩcm)

Remarks

DS1-Nyeri Side112.3

Probability of corrosion is insignificant

DS2 –Mid Span 118.8DS2-Nyahururu

side 110.8

Crack Profiles for the Deck SlabTest

Element/Location

Crack no.

Crack length(mm)

Crack width(mm)

Crack depth(mm)

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 96: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

DS1-Nyeri side Cr.1 Full width of the deck

1.0

Through cracks

Cr.2 Full width of deck

1.0

DS2-Mid span Cr.1 Full width of deck

0.8

Cr.2 Full width of deck

1.0

DS3-Nyahururu side

Cr.1 Full width of deck

1.0

Cr.2 Full width of deck

1.0

BRIDGE AT KM 102+510STEEL GIRDERSUltrasonic Tests for Plate Thickness & Lamination

Steel Girder No.

Section Dimensions (mm)

Continuity Across Plate Thickness

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 97: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

SG1 LHSNo Delamination

SG2 LHSNo Delamination

BRIDGE AT KM 102+510Ultrasonic Tests for Plate Thickness & Lamination

Steel Girder No.

Section Dimensions (mm)

Continuity Across Plate Thickness

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

22.5

13.5

600

Page 98: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

SG3 CentreNo Delamination

SG2 RHSNo Delamination

BRIDGE AT KM 102+510Ultrasonic Tests for Plate Thickness & Lamination

Steel Girder No.

Section Dimensions (mm)

Continuity Across Plate Thickness

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

21.5

13.4

600

Page 99: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

SG1 RHSNo Delamination

BRIDGE AT KM 102+510PIER WALLSElectromagnetic Test Results for the Pier Walls

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 100: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Test Element/LocationRe-bar spacing(mm)

Average covers(mm)

Re-bar size(mm)

Pier wall Thickness

(mm)

Nyeri SideRHS

Vertical:300Horizontal:450

Vertical: 53Horizontal:67

Vertical:25 Horizontal:16

600

Centre Vertical:300Horizontal:450

Vertical: 48Horizontal:69

Vertical: 25Horizontal:16

LHS Vertical:300Horizontal:450

Vertical:55Horizontal:67

Vertical:25Horizontal:16

Nyahururu Side

LHSVertical:300Horizontal:450

Vertical: 42Horizontal:57

Vertical: 25Horizontal:16

Centre Vertical:300Horizontal:450

Vertical: 52Horizontal:66

Vertical: 25Horizontal:16

RHS Vertical:300Horizontal:450

Vertical:50Horizontal:64

Vertical:25Horizontal:16

Schmidt Hammer Test Results for the Pier Walls

Test Element/LocationAverage concrete strength

(N/mm2)

Nyeri Side

RHS 50.0

Centre 52.4

LHS 51.0

Nyahururu Side

LHS 53.8

Centre 56.4

RHS48.1

Ultrasonic Pulse Velocity Results for the Pier WallsTest Element/Location Homogeneity of concrete matrix

Nyeri Side

LHS Homogeneous

Centre Homogeneous

RHS Homogeneous

Nyahururu SideLHS

Homogeneous

Centre Homogeneous

RHSHomogeneous

BRIDGE AT KM 102+510Ultrasonic Pulse Velocity Results for the Pier walls for quality of concrete

Test Element/Location Transit time

Distance (mm)

Pulse velocity(km/s)

Remarks

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 101: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

(µs)

Nyeri Side LHS 133 600 4.5 Good quality concrete

Nyahururu Side LHS 139 6004.3

Carbonation Test Results for the Pier WallsTest

Element/Location

Carbonation depth(mm)

Least cover

recorded(mm)

Balance of carbonation

depth(mm)

Remarks/deterioration degree

Nyeri side 8 48 40None

Nyahururu side 4 42 38None

Resistivity Test Results for the Pier WallsTest

Element/Location

Resistivity(kΩcm)

Remarks

Nyeri side 111.3 Probability of corrosion is insignificant

Nyahururu side 112.3

BRIDGE AT KM 142+450ABUTMENTS

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 102: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Electromagnetic Test Results for the Abutments

Test Element/LocationRe-bar spacing(mm)

Average covers(mm)

Re-bar size(mm)

Abutment wall

Thickness(mm)

A1 –Nyeri Side

LHS Vertical:450Horizontal:400

Vertical:27Horizontal:50

Vertical:25Horizontal:16

900Centre Vertical:450Horizontal:400

Vertical:27Horizontal:50

Vertical:25Horizontal:16

RHS vertical:450Horizontal:400

Vertical:26Horizontal:57

Vertical:25Horizontal:16

A2 –Nyahururu Side

LHS Vertical:450Horizontal:400

Vertical:42Horizontal:60

Vertical:25Horizontal:16

900Centre Vertical:430Horizontal:420

Vertical:36Horizontal:55

Vertical:25Horizontal:16

RHS vertical:450Horizontal:400

Vertical:41Horizontal:67

Vertical:25Horizontal:16

Schmidt Hammer Test Results for the Abutments

Test Element/LocationAverage concrete strength

(N/mm2)

A1 –Nyeri Side

LHS 60.8Centre 64.8

RHS 63.9Side A2 –Nyahururu

LHS 60.7Centre 60.9

RHS 54.6

ABUTMENTSUltrasonic Pulse Velocity Results for the Abutments

Test Element/Location Homogeneity of concrete matrix

A1 –Nyeri Side

LHS Homogeneous Centre Homogeneous

RHS Homogeneous

A2 –Nyahururu Side

LHS HomogeneousCentre Homogeneous

RHS Homogeneous

BRIDGE AT KM 142+450Carbonation Test Results for the Abutments

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 103: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Test Element/Location

Carbonation depth(mm)

Least cover

recorded(mm)

Balance of carbonation

depth(mm)

Remarks/deterioration degree

A1-Nyeri side 7 26 19Low

A2-Nyahururu side 7 30 23 Low

Resistivity Test Results for the AbutmentsTest

Element/LocationResistivity

(kΩcm)Remarks

A1-Nyeri side111.8

Probability of corrosion is insignificant

A2-Nyahururu side 111.3

Crack Profiles for the AbutmentsTest

Element/Location

Crack no.

Crack length(mm)

Crack width(mm)

Crack depth(mm)

A1-Nyeri side Cr.1 3500 1.2 41Cr.2 3500 1.2 42Cr.3 2000 1.0 30

DECK SLABElectromagnetic Test Results for the Deck Slab

Test LocationRe-bar spacing

(mm)Average covers(mm)

Re-bar size(mm)

Deck slab Thickness

(mm)DS1-Nyeri Side Longitudinal:400

Transverse:300Longitudinal:41Transverse:29

Longitudinal:20Transverse:12

200DS2 –Mid Span

Longitudinal:400Transverse:300

Longitudinal:47Transverse:33

Longitudinal:20Transverse:12

DS3-Nyahururu side

Longitudinal:400Transverse:300

Longitudinal:45Transverse:30

Longitudinal:20Transverse:12

BRIDGE AT KM 142+450Schmidt hammer Test Results for the Deck SlabDETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 104: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Test LocationAverage concrete strength

(N/mm2)

DS1-Nyeri Side 53.3

DS2 –Mid Span52.1

DS3-Nyahururu side 48.8

Ultrasonic Pulse Velocity Results for the Deck SlabTest Element/Location Homogeneity of concrete matrix

DS1-Nyeri SideInhomogeneous

DS2 –Mid SpanInhomogeneous

DS3-Nyahururu side Inhomogeneous

Carbonation Test Results for the Deck SlabTest

Element/Location

Carbonation depth(mm)

Least cover

recorded

(mm)

Balance of carbonatio

n depth(mm)

Remarks/deterioration degree

DS1-Nyeri Side 6.0 29 23 Low DS3-Nyahururu

side 6.0 30 24 Low

DECK SLABResistivity Test Results for the Deck Slab

Test Element/Locatio

n

Resistivity (kΩcm)

Remarks

DS1-Nyeri Side110.0

Probability of corrosion is insignificant

DS2 –Mid Span 111.3DS3-Nyahururu

side 111.1

BRIDGE AT KM 142+450

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 105: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

WING WALLSElectromagnetic Test Results for the Wing Walls

Test Element/LocationRe-bar spacing(mm)

Average covers(mm)

Re-bar size(mm)

Nyeri Side LHS Vertical:300Horizontal:300

Vertical:68Horizontal:45

Vertical:20Horizontal:6

Nyahururu Side LHSVertical:450

Horizontal:450Vertical:33

Horizontal:45Vertical:20

Horizontal:16

Schmidt Hammer Test Results for the Wing Walls

Test Element/LocationAverage concrete strength

(N/mm2)

Nyeri SideRHS 59.4

LHS 62.0

Nyahururu Side

LHS 53.2

RHS 55.0

Ultrasonic Pulse Velocity Results for the Wing WallsTest Element/Location Homogeneity of concrete matrix

Nyeri Side

LHS Homogeneous

RHS Homogeneous

Nyahururu Side LHS Homogeneous

RHS Homogeneous

Carbonation Test Results for the Wing WallsTest

Element/Location

Carbonation depth(mm)

Least cover

recorded

(mm)

Balance of carbonatio

n depth(mm)

Remarks/deterioration degree

Nyeri side 7 33 28 LowNyahururu side

7 45 38 None

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 106: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 142+450Resistivity test results for the Wing Walls

Test Element/Locatio

n

Resistivity (kΩcm)

Remarks

Nyeri side110.0

Probability of corrosion is insignificantNyahururu side 111.5

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 107: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 142+450STEEL GIRDERSUltrasonic Tests for Plate Thickness & Lamination

Steel Girder No.

Section Dimensions (mm)

Continuity Across Plate Thickness

SG1 LHSNo Delamination

SG2 LHSNo Delamination

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

14.5

25

600

Page 108: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 142+450Ultrasonic Tests for Plate Thickness & Lamination

Steel Girder No.

Section Dimensions (mm)

Continuity Across Plate Thickness

SG3 CentreNo Delamination

SG2 RHSNo Delamination

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

14.3

23.2

14.5

23.5

600600

Page 109: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

BRIDGE AT KM 142+450Ultrasonic Tests for Plate Thickness & Lamination

Steel Girder No.

Section Dimensions (mm)

Continuity Across Plate Thickness

SG1 RHSNo Delamination

BRIDGE AT KM 173+120DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

14.0

22.4

600

Page 110: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

DECK SLABElectromagnetic Test Results for the Deck Slab

Test Location Re-bar spacing(mm)

Average covers(mm)

Re-bar size(mm)

Deck slab Thickness

(mm)

DS1-Nyeri SideRHS

Longitudinal:150Transverse:130

Longitudinal:20Transverse:10

Longitudinal:16Transverse:12

DS2 –Nyeri Side Centre

Longitudinal:150Transverse:120

Longitudinal:20Transverse:12

Longitudinal:16Transverse:12

DS3-Nyeri Side LHS

Longitudinal:150Transverse:130

Longitudinal:20Transverse:10

Longitudinal:16Transverse:12

Schmidt hammer Test Results for the Deck Slab

Test LocationAverage concrete strength

(N/mm2)

DS1-Nyeri Side LHS 30.7

DS1-Nyeri Side Centre 40.4

DS1-Nyeri Side RHS 55.2

DS2-Karatina side LHS 52.1

DS2-Karatina side Centre 51.3

DS2-Karatina side RHS 40.6

Ultrasonic Pulse Velocity Results for the Deck SlabTest Element/Location Homogeneity of concrete matrix

DS1-Nyeri SideRHS Slightly Inhomogeneous

DS2 –Nyeri Side Centre Slightly Inhomogeneous

DS3-Nyeri Side LHSSlightly Inhomogeneous

Carbonation Test Results for the Deck SlabTest

Element/Location

Carbonation depth(mm)

Least cover

recorded(mm)

Balance of carbonation

depth(mm)

Remarks/Deterioration degree

DS1-Nyeri Side 6 10 4 High BRIDGE AT KM 173+120

DECK SLABDETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 111: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Resistivity Test Results for the Deck SlabTest

Element/Location

Resistivity (kΩcm)

Remarks

DS1-Nyeri Side 111.4Probability of corrosion is insignificant

PIER COLUMNSTest

element /location

Column Size(mm), No.& Arrangement of re-bars

Re-bar size

(mm)

Average

covers(mm)

Link Details(mm)

PC 1-Nyeri sideLHS 32

Side A:53Side B:23Side C:26Side D:36

size:10Spacing:250

PC 2-Nyeri sideLHS 32

Side A:20Side B:18Side C:25Side D:22

size:10Spacing:250

BRIDGE AT KM 173+120PIER COLUMNSDETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

A

600

350

500

450

A

B

C

D

Page 112: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Test element /location

Column Size(mm), No.& Arrangement of re-bars

Re-bar size

(mm)

Average

covers(mm)

Link Details(mm)

PC 1-Nyeri sideRHS 32

Side A:31Side B:32Side C:24Side D:30

size:10Spacing:250

PC 2-Nyeri sideRHS 32

Side A:35Side B:30Side C:36Side D:25

size:10Spacing:250

BRIDGE AT KM 173+120Schmidt Hammer Test Results for the Pier Columns

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

A

600

350

500

450

A

B

C

D

A

600

350

500

450

A

B

C

D

Page 113: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Test Element/LocationAverage concrete strength

(N/mm2)

Nyeri SidePC1LHS 45.0

PC2LHS 32.0

PC1RHS 41.8

PC2RHS 45.0

Karatina Side

PC1LHS 43.0

PC2LHS 50.0

PC1RHS 52.1

PC2RHS 55.0

Carbonation Test Results for the Pier ColumnsTest

Element/LocationCarbonation

depth(mm)

Least cover

recorded(mm)

Balance of carbonatio

n depth(mm)

Remarks/deterioration

degree

Nyeri sidePC1LHS 6 23 17 Low

PC2LHS 6 18 12 Low

PC1RHS 6 24 18 Low

PC2RHS 6 25 19 Low

Resistivity test results for the Pier ColumnsTest

Element/LocationResistivity

(kΩcm)Remarks

Nyeri sidePC2 RHS 111.4

Probability of corrosion is insignificant

BRIDGE AT KM 173+120STEEL GIRDERSDETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Page 114: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Ultrasonic Tests for Plate Thickness & Lamination

Steel Girder No.

Section Dimensions (mm)

Continuity Across Plate Thickness

SG1 LHSNo Delamination

SG2 LHSNo Delamination

BRIDGE AT KM 173+120Ultrasonic Tests for Plate Thickness & Lamination

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

16.5

23

870

Page 115: ROAD B5 BRIDGES INSPECTION  DETAILED REPORT copy.docx

MTRD ICT

Steel Girder No.

Section Dimensions (mm)

Continuity Across Plate Thickness

SG3 CentreNo Delamination

SG2 RHSNo Delamination

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

16.5

23.5

16.0

22.5

870600