1
Chicksands. We built two three-storey accommodation blocks to house SNCOs. The buildings were each constructed from 42 modules, incorporating 36 en-suite bedrooms, four ancillary rooms and kitchen areas. Alexander Barracks. We delivered six projects, totalling 1628 beds at a value of £62million. RAF Brize Norton. We built a total of 16 blocks over five projects and temporary accommodation at a value of £77million. Catterick Garrison. We delivered 19 projects, including 48 accommodation blocks (4,495 beds) and six mess buildings. RM Poole. The first project we completed was at RM Poole in 2003. #DIOdelivers
Transcript of RM Poole. - GOV.UK · 2015. 12. 16. · RM Poole. The first project we completed was at RM Poole in...
-
Chicksands.We built two three-storey accommodation blocks to house SNCOs. The buildings were each constructed from 42 modules, incorporating 36 en-suite bedrooms, four ancillary rooms and kitchen areas.
Alexander Barracks.We delivered six projects, totalling1628 beds at a value of £62million.
RAF Brize Norton.We built a total of 16 blocks overfive projects and temporaryaccommodation at a value of£77million.
Catterick Garrison.We delivered 19 projects, including48 accommodation blocks(4,495 beds) and six mess buildings.
RM Poole.The first project we completed was at RM Poole in 2003.