MIPSYCON 2016
Luke Karels and Duane PhillipsStanley Consultants, Inc.
River Bank Foundation Design
![Page 2: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/2.jpg)
Objective and Basis
• Presentation of design and construction considerations for river bank and river crossing foundations on transmission line projects.
• Topics Covered• Loading• Structure Types• Design Process and Alternatives• Constructability and Construction Methodology
• Project Examples: • 2,700‐foot crossing of Missouri River• Multiple crossings of Minnesota River
![Page 3: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/3.jpg)
Examples ‐ Foundations
![Page 4: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/4.jpg)
Basic Foundation Design
![Page 5: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/5.jpg)
Loading Factors
Significantly higher load due to wire
selection (strength) and tension.
Resulting ground line moments significantly
higher.
Total loading may result in alternative
designs.
![Page 6: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/6.jpg)
Loading Considerations
• Guyed vs. self‐supporting• Deadend vs. tangent• Required additions• Markings, lighting, maintenance, underbuild
• Geotechnical (soils/rock)• Environmental concerns• Water flow, flooding, debris, wildlife
![Page 7: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/7.jpg)
• Conductor point loads
• Pole self‐weight
• Wind loads• Wind on pole
• Wind on wire
• Ice loads
• Hardware
• Maintenance/construction loads• Stringing loads
Pole Loads ‐General
![Page 8: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/8.jpg)
Conductor Resultant Load
• Conductor weight, ice, and wind combined
Ice
WindWind H Load
Ice V Load
Conductor V Load
NESC with “K” Overload Factor
Resultant Actual Load
![Page 9: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/9.jpg)
Structure Types
Monopoles
![Page 10: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/10.jpg)
Structure Types
Multi‐Pole Structures
![Page 11: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/11.jpg)
Structure Types
Lattice Structures
![Page 12: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/12.jpg)
Structure Loads
Transverse and longitudinal load due to conductor tension
• Changes in line direction• Span length variation• Unbalanced ice• Broken wires• Dynamic loads
![Page 13: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/13.jpg)
• Single Pole w/o Guys (self‐supporting)• Large overturning
moment (M)
• Relatively small horizontal load (H)
• Vertical load (V) driven by structure/foundation weight and wire
• Typically use drilled piers, driven steel caissons
Foundation Design Process
![Page 14: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/14.jpg)
Foundation Design Process
Lattice tower w/o guys
• Small base moment• Relatively small shear load• Large vertical load, downward or upward• Typically use caissons, spread footings, or driven piles
![Page 15: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/15.jpg)
• Borings taken at each pole location:• Identify cobbles, boulders or
other obstructions
• Drivability a concern
• Soil profile:• Low blow counts
• Soft organic swamp deposits (organic clay, organic silt, peat)
• Loose alluvial deposits (loose silty sand, silt)
• Glacial till (stiff sandy lean clay, stiff clayey sand)
Subsurface Conditions
![Page 16: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/16.jpg)
River Crossing Challenges
• Potential challenges include:• Dynamic terrain changes• Unique structure loading• Poor soil conditions• Unfavorable construction
access• Environmental restrictions
• Must use communication and collaboration to overcome challenges• Engineers, owners, and
contractors must work together
![Page 17: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/17.jpg)
Design Alternatives
![Page 18: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/18.jpg)
Alternatives
Considerations:
• Cost• Material availability• Procurement schedule• Hauling requirements• Required construction equipment• Access requirements• Maintenance requirements
Traditional Drilled Piers
• Deep, permanent casing, spoils, many concrete trucks (access)
Vibratory Caissons
• Eliminate need for large amounts of concrete
• Minimal equipment needed
• Requires soils conducive to vibratory installation
• Concrete, pad excavation with high water table
Driven Piles with Pile Cap
![Page 19: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/19.jpg)
Drilled Pier with Casing
![Page 20: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/20.jpg)
Drilled Pier with Casing
![Page 21: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/21.jpg)
Driven Pile with Pile Cap
![Page 22: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/22.jpg)
Micropiles
![Page 23: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/23.jpg)
Vibratory Caisson “Socket” Connection
![Page 24: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/24.jpg)
Vibratory Caisson
![Page 25: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/25.jpg)
Design Considerations
![Page 26: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/26.jpg)
Typical Long Span Concepts
• Tension vs. Height• ↑Tension →↑ Load and ↑Galloping• ↓Tension →↑ Sag →↑Height
• Tangent vs. Deadend• Typically trade height for load and type
![Page 27: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/27.jpg)
Operational Considerations
Terrain → access for construction and maintenance
Additional Support → lighting, supplemental power
Ground → geotech, grounding, ground water, flood plains
Flowing Water → flood plains, debris damage, erosion
![Page 28: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/28.jpg)
Flood Plain Factors
Height of foundation vs. flood plain levels
Loading from flowing water and ice
Loading from floating debris
Soil erosion from water flow
Soil bearing and skin friction assumptions
![Page 29: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/29.jpg)
100‐Year Flood Levels
![Page 30: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/30.jpg)
Riverbank Erosion Example
![Page 31: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/31.jpg)
Riverbank Erosion Example
![Page 32: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/32.jpg)
Riverbank Erosion Example
![Page 33: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/33.jpg)
Constructability
![Page 34: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/34.jpg)
Site Conditions
Space Availability →Can we build there?
Site Access →Can we get there?
Weather→When can we gain access and for how long?Environmental →Are there any environmental limitations to accessibility?Maintenance→When do we need to get there in the future? How will we get there (once contractor is long gone)?
![Page 35: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/35.jpg)
Installation Factors
Site access for materials and equipment
Limitations to construction sequence for installation
Locations to set‐up construction equipment
Environmental factors that would limit construction
Scheduling and coordination concerns
![Page 36: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/36.jpg)
Construction Methods
Experience and expertise of contractors
Detailed review of methods (and alternatives) and expectations
Site access requirement reviews
Review of equipment to be used during installation
Observation with design support during installation
![Page 37: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/37.jpg)
Collaborate with all partiesThoughtful planning Dynamic communication Efficient execution
Conduct thorough data collectionKnow what you are dealing with Study various alternatives Identify all possible obstacles
Define project constraintsScope/budget/schedule
Create sub‐project to enhance focus
Keys to Success
![Page 38: River Bank Foundation - UMN CCAPS · 2016-11-09 · Objective and Basis • Presentation of design and construction considerations for river bank and river crossing foundations on](https://reader033.fdocuments.in/reader033/viewer/2022050407/5f84778b89eda52f4a1f2abe/html5/thumbnails/38.jpg)
Luke Karels and Duane PhillipsStanley Consultants, Inc.
River Bank Foundation Design
QUESTIONS?