Risk on complex_projects_project_auditors
description
Transcript of Risk on complex_projects_project_auditors
Risk on Complex Projects: A case study
PRJ05
Joy Gumz, CPA, CISA, PMP Project Auditors, LLC
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC All rights reserved
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
AGENDA
• Format of this session: case study
• Case study details
• Audience decision questions & discussion
• Q&A / wrap-up
2
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
Objectives
• Better identify risks, both positive and negative, in the procurement phase
• Define contractual clauses that may reduce complex project risk
• Understand importance of risk management during initiation and planning of the procurement phase
3
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
About Project Auditors LLC
• Professional consulting, training and auditing firm – Professionals certified in accounting, audit & PM
• Experts in project controls: preventative & detective
• Providing assessments, audits and reviews – Construction & Engineering Projects – Oil & Gas Projects – ICT (Information Communications Technology)
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
A few clients
See more at our website: http://www.projectauditors.com
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
Format of this session: Case Study • NASA Methodology
• Published by Chief Knowledge Officer
• Decision-oriented case study • You will be a main character
who will eventually make decisions • You’ll be provided with
data that was available at time of the event
6
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
An effective case study
Source: NASA Case Study Methodology
7
• Does NOT have just one answer
• Fosters decision making
• Generates questions
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
Audience participation - A few questions
8
1 Does anyone work in the oil & gas industry?
2 Is anyone a
risk manager?
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
Causes for underperformance
9
*Poor plan/bidding/estimating
*Bid/Tender evaluation
Owner intervention
Design changes
Poor PM / governance
Poor team performance
* Subcontractor performance
Labor / commodity escalation
* Inappropriate contract vehicle
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
Oil Refinery Program Background
Con
text
Com
mun
icat
ions
Rel
atio
nshi
ps
Trus
t
Und
erst
andi
ng
Influence
10
• Industrial process plant – Every refinery is unique – Expensive to build and operate – Tolerances fine to produce high quality products
• Take advantage of – Arabian crude capacity – Infrastructure in Jubail industrial city 2 complex – Proximity to potential petrochemical customers
and port facilities
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
Project Objectives
Con
text
Com
mun
icat
ions
Rel
atio
nshi
ps
Trus
t
Und
erst
andi
ng
Influence
11
• Full conversion refinery – Ultra low sulphur gasoline and diesel fuel products – Process Arabian heavy crude feedstock
• Within budget
• Provide petrochemicals for Jubail complex – Paraxylene, benzene, polymer grade propylene
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
Joint Venture Partners
Com
mun
icat
ions
Rel
atio
nshi
ps
Trus
t
Und
erst
andi
ng
Influence
12
62.5%
37.5%
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
Key Stakeholders
Con
text
Com
mun
icat
ions
Rel
atio
nshi
ps
Trus
t
Und
erst
andi
ng
Influence
13
• Saudi Aramco and Total executives, SATORP employees and contractors
• Saud Royal Family
• Royal Commission
• Tenants in the Jubail 2 industrial complex
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
Cost and Financing
Con
text
Com
mun
icat
ions
Rel
atio
nshi
ps
Trus
t
Und
erst
andi
ng
Influence
14
A 400,000 bpd (barrels per day) refinery costs around 30 billion yuan ($4.4 billion) in China, but would require 50 billion yuan investment ($7.3 billion) in Saudi Arabia.”
Sinopec Corp Chairman Su Shulin. (May 18 2010)
Expected financing from:
* Import-export banks
* Saudi Public Investment Fund
* Commercial banks
* Saudi Aramco
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
Projects Delivered over Original bid: Contractor’s view
15
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
Market and economic conditions
Con
text
Com
mun
icat
ions
Rel
atio
nshi
ps
Trus
t
Und
erst
andi
ng
Influence
16
The increasing size and complexity of projects has led to a growing reliance on contractors’ capabilities and project management skills. Infrastructure Today and E&Y Report, 2011
A soft EPC market will deliver
“comfortable” prices.
EPCs will concentrate on their core competencies, prudently select projects and focus on growth of profitability rather than order book.
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
Future Competitive Position
17
Source: Wood MacKenzie
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
Some procurement risks (owner)
• Project delivery method may not be optimum
• Contract prices may be over planned budget
• Contract clauses missing or will not drive desired behaviour – Conflict among contractors rather than teamwork
and coordination
18
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
Your role: Program risk engineer
Con
text
Com
mun
icat
ions
Rel
atio
nshi
ps
Trus
t
Und
erst
andi
ng
Influence
19
• Key Responsibilities – Provide assurance that high level risks and
opportunities are recognized, effectively assessed and managed
– Ensure mitigations are developed, tracked and implemented to reduce risk to acceptable levels
– Engage functional groups in cross discipline discussion on key risk areas and provide support
– Provide overall policy advice on risk management
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
Procurement (you are in this phase)
20
• Contracting strategy – Overall project delivery structure
• Use of a prime contractor • Number of packages • Lump sum
• Drafting of contracts
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
PMT: the project management team will control, manage and co-ordinate the project from conception to completion
Project management team - owner
Package 1 Package 2 Package 3 Package 4 etc
PMT – Owner staff
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
Disadvantages
• No single point of accountability
• Potential for increase in costs if lump sum contracts are not used or change are not controlled
• Owner assumes overall cost risk
• Considerable reliance on the project manager and PMT staff
Advantages
• Allow for fast tracking • Flexibility • Owner retains control • Project Manager provides overall
budget & control
PMT (internal) – owner’s perspective
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
Disadvantages Cost • Difficulty of comparing tender prices
of different designs
Design Process • Design approval process has to be
carefully managed • Owner’s requirements: often
performance based, less prescriptive
Quality • Less prescriptive specifications plus
lump sum pricing may drive ‘lowest permitted quality’ attitude
Advantages Risk • Single point of responsibility for the
EPC scope of work – fitness for purpose and defect warranties
Quality • IF one EPC, design likely to take full
account of buildability issues
Cost • Price control - usually lump sum
Time • Accelerate start of construction by
overlapping the design and construction process
EPC – owner’s perspective
EPC = Engineer, Procure and Construct
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
Disadvantages
• No single point of accountability
• Limited warranties from EPCM contractor
• Does not provide cost or time certainty
• Requires substantial management effort by the EPCM contractor and significant overview responsibility by the Owner
Advantages
• Enables design streams to be worked up concurrently
• Enables packaging of contracts by trade, skills or other capabilities where a single contractor entity does not have the capability to deliver the entire project
• Less “risk contingency” than EPC
EPCM – owner’s perspective
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
List of Packages
25
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
Project Status and Timeline
26
June, Year 1 Award of contracts Jan Year 2, Start Construction March 1, Year 3 15% Equipment on site July, Year 3 60% equipment and 30% piping | Spools Oct 1, Year 3 1st commissioning Dec Year 3 90% equipment 50% piping Spools May 31, Year 4 Final Commissioning Oct 31, Year 4, Final Startup
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
Simple Risk Matrix – 5 x 5
27
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
Questions and Discussion
28
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
Your next steps
• What advice would you provide?
29
What should we do now?
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
Audience questions
1 Project Delivery: Owner PMT with multiple EPCs
2 Re-tender – or not?
3 Number of packages – any suggestions?
4 Contractual clauses – any suggestions?
5 Other suggestions to reduce risk at this time?
30
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
Possible contractual clauses
• Contractor risk management
• Right to audit
• Schedule and WBS – Interim and full project – Levels and due dates
31
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
Wrap-up: An effective case study
32
• Generates more questions than answers • Leaves important issues unresolved • Allows for multiple levels of analysis • Captures a tension between courses of action • Fosters decision-making thinking
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
Risk Quantification Matrix
33
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
Contact Information
• Name: Joy Gumz, CPA, CISA, PMP
• Email: [email protected]
• Phone: +1.949.452.0578
• http://www.projectauditors.com
34
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2012 Project Auditors LLC
Your wrap-up
35