Risk Management and Electricity Trade

41
- 1 - EE² 5. Vorlesung Energiewirtschaft II: Risk Management and Electricity Trade Georg Zachmann V 5.3

Transcript of Risk Management and Electricity Trade

Page 1: Risk Management and Electricity Trade

- 1 -EE²

5. Vorlesung Energiewirtschaft II:

Risk Management and Electricity Trade

Georg Zachmann

V 5.3

Page 2: Risk Management and Electricity Trade

- 2 -EE²

Agenda of Today's Lecture

1) Organizational Issues

2) Summary of Last Weeks Findings

3) Market Efficiency

1) Cross-Border Electricity Trade

2) Cross Commodity Arbitrage

3) Intertemporal Arbitrage

4) Solution of the Test Exam

5) Assignment 3

6) Exercise 5: Cross Border Efficiency

Page 3: Risk Management and Electricity Trade

- 3 -EE²

Organizational Issues

Klausur:

-Tachenrechner

-Normalverteilungstabelle

Page 4: Risk Management and Electricity Trade

- 4 -EE²

Summary of Last Weeks Findings

1) Organizational Issues

2) Summary of Last Weeks Findings

3) Market Efficiency

1) Cross-Border Electricity Trade

2) Cross Commodity Arbitrage

3) Intertemporal Arbitrage

4) Solution of the Test Exam

5) Assignment 3

6) Exercise 5: Cross Border Efficiency

Page 5: Risk Management and Electricity Trade

- 5 -EE²

Forecasting Electricity Prices

1) Model Selection

2) Data Reduction

3) Parameter estimation / Calibration for reduced da ta

4) Forecast reduced data

5) Re-extent data

+ 6) Option Pricing

Page 6: Risk Management and Electricity Trade

- 6 -EE²

Cross-Border Electricity Trade

1) Organizational Issues

2) Summary of Last Weeks Findings

3) Market Efficiency

1) Cross-Border Electricity Trade

2) Cross Commodity Arbitrage

3) Intertemporal Arbitrage

4) Solution of the Test Exam

5) Assignment 3

6) Exercise 5: Cross Border Efficiency

Page 7: Risk Management and Electricity Trade

- 7 -EE²

UCTE Map

Page 8: Risk Management and Electricity Trade

- 8 -EE²

Congestion Prevents Price Convergence

Page 9: Risk Management and Electricity Trade

- 9 -EE²

Congestion Management Systems

1) Nodal Pricing

2) Implicit Auctions (Zonal)

1) Market Coupling

2) Market Splitting

3) Explicit Auctions

Page 10: Risk Management and Electricity Trade

- 10 -EE²

Nodal Pricing 1

-Each injection and/or withdrawal point of a network is called a “node”

-The physical grid is owned by one or multiple compa nies

-The grid is managed by an independent system operat or

-At each node all interested parties might submit of fer and demand curves

-Then all bids and offers at each node are aggregate d

M D

G

10 MW100 MW

50 MW

Page 11: Risk Management and Electricity Trade

- 11 -EE²

Nodal Pricing 2

-An optimization software solves the system with res pect to various restrictions:

- Line capacity

- N-1 criterion

- Block bids

- …

-The result specifies:

- Production and consumption at each node

- Prices at each node

- Flows

-Investment incentives:

- Prices at the nodes might differ significantly, thus stipulating better generation and/or consumer allocation

- If flow = capacity (i.e. capacity is binding) the shadow price for the line utilization is paid to the line owner. This partly incentives line investments.

Page 12: Risk Management and Electricity Trade

- 12 -EE²

Implicit Auctioning I

-A group of nodes is assembled in zones.

-Each node of a zone has the same price.

-Again, demand and supply bids of each zone are coll ected by a zonal authority.

-Now a central dispatch center has two possibilities :

- Market coupling

- Market splitting

-Market coupling:

- The optimization program couples zones such that they have an equal price as long as this produces no congestion.

- There often is no single solution, e.g. because of - A “center zone” could be either coupled with the “north zone” or the “south zone” but not with both

- Block bids

- Inner zonal flows

-Market splitting

- The entire market is viewed as one zone with an single price.

- If this simple solution is infeasible i.e. it would produce congestion, the market is split in sub-zones until a solution is reached

Page 13: Risk Management and Electricity Trade

- 13 -EE²

Implicit Auctioning II

-To optimize the system, virtual lines between the z ones (with estimated capacity constraints: the so called NTC) have to be calculat ed and taken into account

-Result in both cases- Multiple nodes are grouped in zones with equal prices- More liquid markets than in nodal pricing- In “perfect markets”: Less optimal dispatch than nodal pricing

-Market participants trade Contracts for Difference (CdF)

Zone 1

Zone 210 MW100 MW

50 MW

90 MW

Page 14: Risk Management and Electricity Trade

- 14 -EE²

Explicit Auctioning I

-The market for electricity and the market for transmission are separated.

-First, the market participants bid for transmission capacities in an auction.

-Second, the market participants can buy and sell electricity in the respective markets, subject to their national production and consumption as well as their capacity holdings.

-Simple example:

- Trader A buys the right to transport 500 MWh for the 13th hour of the 29 June 2006 from Germany to the Netherlands (9.00 28Jun)

- He now sells 500 MWh at the APX (10.00 28Jun)

- He then buys 500 MWh for the 13th at the EEX (12.00 28Jun)

-The main challenge for the grid operators is to offer the correct amount of capacity rights for auctioning

- Too much rights => lines are congested and the syst em operator is responsible for potentially expensive rescheduling

- Too few rights => the potentially valuable rights r emain unused.

- Doubtful: which incentive has an integrated company too offer as much capacity as possible?

Page 15: Risk Management and Electricity Trade

- 15 -EE²

Explicit Auctioning II

-Better then othertypical transitional arrangement for rationing congested lines:

- First come first serve

- Pro rata

-Illiquid markets

-Capacities remain unused or are even misused

-Prices are no reliable signal

-The current system has no sustainable investment incentives

- Example: 2005 the annual and monthly Polish-German auction attained ~68 Mio. €. Building a 100km 380 kV line that would be able to reduce this bottleneck would cost around 90 Mio. €. But nobody has an inte rest to do so.

Page 16: Risk Management and Electricity Trade

- 16 -EE²

System Comparison

-

+

++

LocationSignals forGeneration & Consumption

-

+

++

EconomicPricing

---ExplicitAuction

+++ImplicitAuction

-+++NodalPricing

Market Power Concerns

Transmission Investment Incentives

AllocationEfficency

(flows)

Page 17: Risk Management and Electricity Trade

- 17 -EE²

The European Reality 2004

Page 18: Risk Management and Electricity Trade

- 18 -EE²

Why we do not have nodal pricing?

-Deep system changes needed:

- Separation of grid ownership and system management (TSO vs. ISO)- A new European System Operator (ESO) has to be founded.

- The ESO has to seize the right to dispatch the system from the former TSOs.

- Combination of system operation and electricity exchange- The existing electricity exchanges (spot) have to merge or to disappear

- The new European power exchange has to go together with the ESO

-Many property rights affected

-Many national political decisions to coordinate

-Much political opposition from the potential losers :

- Existing TSOs

- Existing Electricity Exchanges

- Generators with market power

- Consumer in low price countries

Page 19: Risk Management and Electricity Trade

- 19 -EE²

What is a Dutch-German Arbitrageur doing?(Explicit Auction)

1) He bids for transmission rights in the potentiall y profitable direction. His bid price should be E(p APX-pEEX)-ε.

Sealed bid uniform price auction500 MW à 10 €/MWh

2) He is informed, that he obtained the desired capa city.

3) He sells electricity at the Amsterdam power excha nge. His sell price should be E(pEEX)+ε.

Sealed bid uniform price auction500 MW à 80 €/MWh

4) He is informed that he obtained the desired capac ity.

5) He buys electricity at the EEX. His bid price sho uld be p balancing - ε.*Sealed bid uniform price auction500 MW à 60 €/MWh

The profit of the trader is thus 500 x (80 – (60+10) ) = 5000 €.

The maximum loss is V x (p capacity + (pbalancing – pAPX)).

This could be significantly reduced by holding a po rtfolio of financial and physical rights in both countries which could be timely adju sted.

*pbalancin is the price for having to buy electricity in the D utch balancing market.

Page 20: Risk Management and Electricity Trade

- 20 -EE²

Timing of auctions

Cross Border Auctions

Power Exchanges

EON-TenneT(EEX-APX)

EON-ELTRA(EEX-DKW)

APX Elspot

(NordPool)

EEX

Available capacity known to market participants

8:30 9:00

End of bidding 9:00 9:30 10:30 12:00 12:00

Publication of Results 9:30 10:00 11:00 12:00 12:15

Page 21: Risk Management and Electricity Trade

- 21 -EE²

What should be the market outcome?

In the case of perfect full information markets there are t wo cases:

-No congestion: p capacity = pAPX – pEEX = 0

-Congestion: p capacity = pAPX – pEEX > 0

-Otherwise a fully informed trader could do risk fre e arbitrage.

Page 22: Risk Management and Electricity Trade

- 22 -EE²

What happens in imperfect markets?

Market power: the ability of a company to profitabl y move prices away from the competitive level.

A is a generation monopolist in the North with low cost and high prices.

B is a competitive generator in the South with high cost and marginal cost prices.

cA

cB

Trader

Competitive Price

Monopolist Price North

Monopolist Price South

Monopolist

Things get more complicated if we allow for simulta neous trade in both directions. If there is market power in one country, the owner of market power might for example be interested in withholding cross-border capacities.

Page 23: Risk Management and Electricity Trade

- 23 -EE²

What does reality teaches us?

Electricity often flows from high to low price

5 10 15 20-10

0

10

20

30

40

50EON =>TenneT

5 10 15 20-10

0

10

20

30

40

50RWE =>TenneT

200220032004

E.on and RWE auctionhave fairly similarprices

Page 24: Risk Management and Electricity Trade

- 24 -EE²

white noise process

with

and

Law of One Price

Time variant coefficient framework

Page 25: Risk Management and Electricity Trade

- 25 -EE²

EEX-APX 13h:Outlier dominatethe picture

EEX-APX 3h:Smoothconvergence

Time variant coefficient ( ααααt )

Page 26: Risk Management and Electricity Trade

- 26 -EE²

Proximity indices ( γγγγt) and convergence indicator ( θθθθ)

-Convergence towards arbitrage-freeness in off-peak.-No significant convergence in peak due to outliers

Page 27: Risk Management and Electricity Trade

- 27 -EE²

Cross Commodity Arbitrage

1) Organizational Issues

2) Summary of Last Weeks Findings

3) Market Efficiency

1) Cross-Border Electricity Trade

2) Cross Commodity Arbitrage

3) Intertemporal Arbitrage

4) Solution of the Test Exam

5) Assignment 3

6) Exercise 5: Cross Border Efficiency

Page 28: Risk Management and Electricity Trade

- 28 -EE²

Cross-Commodity Arbitrage

-Hedging fuel price risks for generators

- Spread (units: €/MWhel - €/MWhth / MWhel/MWhth = €/MWhel)

- Spark Spread (Pel - pGas / efficencyGas)

- Dark Spread (Pel - pCoal / efficencyCoal)

-Use correlations to hedge financial portfolios

- Sometimes there are no derivates on our underlying available that feature the desired properties. Historical data allow to find other commodities that are strongly correlated (positive or negative) with our underlying.

- Now one can go long or short in those commodities (or related derivatives) to hedge the portfolio.

-Make arbitrage gains

- In imperfect markets it might be possible to buy and/or sell derivates on different commodities such that the portfolio remains mainly hedged but arbitrage gains are attained.

Page 29: Risk Management and Electricity Trade

- 29 -EE²

Hedging fuel price risks for generators

There are many forms of contracts that help generat ors to reduce price risks:

-Contract for difference (CfD) is an assurance against interregional price differentials

-Dirty (Spark or Dark) Spread is the fuel cost - electricity price difference

-Clean (Spark or Dark) Spread is the fuel and emission cost – electricity price difference

-Spreads exist as weakly standardized contracts or as individual contracts (of e.g. big traders and small generators)

-Spread contracts allow generators to stabilize their cash flow. This is important to assure banks of the profitability of new investment projects.

Page 30: Risk Management and Electricity Trade

- 30 -EE²

Use correlations to hedge financial portfolios

What assets are correlated with German electricity prices?

-Stocks of electricity generators (e.g. RWE AG)

-Stocks of electricity consumer (e.g. Thyssen Krupp)

-Stocks of substitute provider (e.g. Gazprom)

-Stocks of fuel provider (e.g. RAG)

-Electricity intense commodities (e.g. aluminum)

-Fuels (e.g. gas / coal / uranium / EUAs)

-foreign electricity prices (e.g. PNX or APX)

-cross border capacity (e.g. Annual Dutch-German auc tion)

-…

Page 31: Risk Management and Electricity Trade

- 31 -EE²

Make arbitrage gains

Use the aforementioned cross-correlations of assets to construct a portfolio that lies above the return-risk line of capital mar ket products.

This is only possible in imperfect/immature markets .

Page 32: Risk Management and Electricity Trade

- 32 -EE²

Intertemporal Arbitrage

1) Organizational Issues

2) Summary of Last Weeks Findings

3) Market Efficiency

1) Cross-Border Electricity Trade

2) Cross Commodity Arbitrage

3) Intertemporal Arbitrage

4) Solution of the Test Exam

5) Assignment 3

6) Exercise 5: Cross Border Efficiency

Page 33: Risk Management and Electricity Trade

- 33 -EE²

Intertemporal Arbitrage

1) Buy or sell forward/future

2) Sell or buy spot

Again, in perfect markets, no arbitrage gains could be attained. The literature showed however, that electricity markets are still imperfect.

Page 34: Risk Management and Electricity Trade

- 34 -EE²

Solution of the Test Exam

1) Organizational Issues

2) Summary of Last Weeks Findings

3) Market Efficiency

1) Cross-Border Electricity Trade

2) Cross Commodity Arbitrage

3) Intertemporal Arbitrage

4) Solution of the Test Exam

5) Assignment 3

6) Exercise 5: Cross Border Efficiency

Page 35: Risk Management and Electricity Trade

- 35 -EE²

Assignment 3

1) Organizational Issues

2) Summary of Last Weeks Findings

3) Market Efficiency

1) Cross-Border Electricity Trade

2) Cross Commodity Arbitrage

3) Intertemporal Arbitrage

4) Solution of the Test Exam

5) Assignment 3

6) Exercise 5: Cross Border Efficiency

Page 36: Risk Management and Electricity Trade

- 36 -EE²

Normalized PC

Slide 27 in lecture 3: „Standardizing i.e. division by std would give all hours the same weight“

Two possibilities:

- Standardize the original data matrix (Data – Mean)/STD

- Decompose the correlation instead of the covariance matrix (corrcoef() instead of cov())

Result:

Page 37: Risk Management and Electricity Trade

- 37 -EE²

Spikes

Page 38: Risk Management and Electricity Trade

- 38 -EE²

Parameter uncertainty

Page 39: Risk Management and Electricity Trade

- 39 -EE²

Estimate the Option Value

With spikes

Page 40: Risk Management and Electricity Trade

- 40 -EE²

Exercise 5

1) Organizational Issues

2) Summary of Last Weeks Findings

3) Market Efficiency

1) Cross-Border Electricity Trade

2) Cross Commodity Arbitrage

3) Intertemporal Arbitrage

4) Solution of the Test Exam

5) Assignment 3

6) Exercise 5: Cross Border Efficiency

Page 41: Risk Management and Electricity Trade

- 41 -EE²

Exercise 5

1) Load prices for the German and Dutch electricity market and the daily RWE-TenneT auction results (international.mat)

2) Plot (x-axis: hours, y-axis €/MWh)

1) The average price differentials for all hours,

2) The average capacity prices for all hours

3) And the average remaining import and export arbitrage opportunities for all hours

3) Plot remaining arbitrage opportunities over time for the 3rd and 13th hour (x-axis time, y-axis €/MWh)

4) Calculate how often the Auction was overpaid and how often it was underpaid by more than 5% (10%).