Blog 30 RISK ASSESSMENT FORM
ACTIVITY: Filming for Pastures New LOCATION: St John’s Evangelist Church & Park DATE: 10/01/2016
LEAD MEMBER: David Marriott
SIGNED: David Marriott DATE: 10/01/2016
List Hazards here: List groups of people who are especially at risk from the hazards you have identified
* How will you control this risk?
Post event review (for use if you have a concern or an incident occurred)
Members of the public may not wished to be filmed
General PublicSmall Children
Ensure there is appropriate signposting indicating that we are filmingFilm when volume of people is low
We placed up signs to indicate that we were filmingWe made sure people were always out of shot
People may find it offensive or disrespectful for us to film in a graveyard
Those who have recently lost loves ones
Ensuring we get the expressed permission of the Church Vicar and film as quickly as possible to free the area again
We made sure to minimise the time filming to only a few minutes
Traffic colliding with camera crew
ActorsCamera Crew
Have an extra person on standby looking around for oncoming traffic when filming
We did not film any scenes that required the crossing of a road in the end
Expensive equipment may be stolen
Camera crew Make all camera equipment is in the hands of one of the crew at all times
We adhered to this rule