RISK ASSESSMENT & DISASTER MANAGEMENT...
Transcript of RISK ASSESSMENT & DISASTER MANAGEMENT...
Project Name Environment Clearance for Group Housing Project
EIA Project Proponent Sunrise Technobuild LLP
Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra
Marg Yojna, Rishikesh, Uttarakhand
Environment Consultant
Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-1
RISK ASSESSMENT & DISASTER MANAGEMENT PLAN
7.1 RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN
Sunrise Technobuild LLP is developing a Group Housing Project at plot No. GH-1 in Awas Vikas Parishad Housing Colony, Veerbhadra Marg Yojna, Rishikesh. The project is spread over an area of approximately 3 acres. This is a residential project having three blocks A, B & C. Block A & C are residential Towers while block B is Villas. Maximum height of the buildings is approx. 29.5 metres. It also consists of a Commercial building and a Community Centre block. The salient features of the project include energy saving fixtures, sufficient aesthetic green cover and water conservation measures. The project involves a number of project specific activities on construction of high rise buildings such as installation of various types of structures and machineries. These activities include lifting and transportation of building materials at different levels, digging of pits, operation of concrete mixer, working near electrical circuit, which are required during construction of the project. Hence, such work puts workers at risk of burial, engulfment or falling from a height, risk of electrocution where the risk is particularly aggravated by the nature of the work or processes used or by the environment at the place of work or site. On completion of the project, the infrastructure created includes provision of lifts, DG set as power backup, laying of internal as well as external electrical cables, provision of pipeline for LPG uses (specially in kitchens), construction of internal roads etc, which pose risk of accident to the occupants . However, it is not always possible to totally eliminate such eventualities and random failures of equipment due to human errors or natural calamities like storms, cyclones, earthquake etc. It is thus necessary to carry out hazard identification and risk assessment for risk monitoring and to formulate its Control Measures like Risk response planning i.e. Disaster Management Plan / Onsite Emergency Plan for the project. An essential part of major hazard control is, therefore, to be concerned with mitigating the effects of such emergency situation and restoration of normalcy at the earliest by following Disaster Management Plan (DMP) for different type of Emergencies like Earthquake, LPG leakage, Fire in the building etc. The TOR for the project stipulates to submit details of a comprehensive Disaster Management Plan including emergency evacuation during natural and man-made disaster. In compliance of the above direction, a detailed Disaster Management Plan has been prepared for compliance by the project authorities.
Project Name Environment Clearance for Group Housing Project
EIA Project Proponent Sunrise Technobuild LLP
Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra
Marg Yojna, Rishikesh, Uttarakhand
Environment Consultant
Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-2
7.1.0 RULES AND REGULATIONS ON SAFETY INVOLVING RISKS & HAZARDS
7.1.0.1 STATUTORY RULES AND REGULATIONS ON SAFETY, HEALTH AND
ENVIRONMENT
The responsibility of the management of any project is to comply with the provisions of various statutory rules and regulations on Safety, Health and Environment which are as follows: 1) Environment (Protection) Act, 1986 and Rules (as amended to date) made there
under including: (a) The Manufacture, Storage and Import of Hazardous Chemicals (MSIHC) Rules 1989
amended in 1994, 2000, 2008 and 2016; (b) Environment Impact Assessment Notification, 2006, as amended to date; (c) The Bio-Medical Waste (Management and Handling) Rules, 1998, as amended to date; (d) Hazardous and Other Wastes (Management & Trans-boundary Movement) Rules, 2016; (e) Solid Waste Management Rules, 2016; (f) Plastic Waste Management Rules, 2016; (g) Construction and Demolition Waste Management Rules, 2016; (h) E - Waste Management Rules, 2018; (i) The Public Liability Insurance (PLI) Act 1991, amended in 1992 and the Public
Liability Insurance Rules 1991, amended in 1993; (j) The Chemical Accidents (Emergency Planning, Preparedness & Response) rules, 1996; 2) Factory Act 1948 and the Factories (Amendment) Act 2014, as amended to date;
3) Petroleum Act 1934 and Petroleum Rules 1981 amended in 2002, as amended to date;
4) Gas Cylinder Rules 2004 and Static & Mobile Pressure Vessels (SPVM) (Unfired) Rules 1981 amended in 1993, as amended to date;
5) Explosives Act 1984 and Explosive Rules 1983, as amended to date; 6) The Electricity Act 2003 and Indian Electricity Rules 1956 as amended to date.
77..11..00..22 SSTTOORRAAGGEE && HHAANNDDLLIINNGG OOFF HHAAZZAARRDDOOUUSS MMAATTEERRIIAALLSS::
Both the hazardous & non hazardous materials generated within the industrial estates shall be temporarily accommodated in necessary units placed within the industrial estate in line with the safety, health and environmental standards. The size of these temporary units will depend on the quantity and the type of Hazardous
waste materials like asbestos, PCB, oils, fuels etc. Appropriate storage capacities are
proposed to be placed within the premises of the Group Housing Project as per the
Hazardous and Other Wastes (Management & Trans-boundary Movement) Rules 2016 (as
amended to date). Later, these materials will be disposed off at a centralized disposal
facility with utmost care following safety norms. For gas cylinders used / stored within
the premises of the GH Project, the Gas Cylinders Rules under the Explosives Act will be
Project Name Environment Clearance for Group Housing Project
EIA Project Proponent Sunrise Technobuild LLP
Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra
Marg Yojna, Rishikesh, Uttarakhand
Environment Consultant
Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-3
followed. Each unit in the GH Project is proposed to be facilitated with fire hydrant system
to handle fire hazards
7.1.0.3GUIDELINES FOR STORAGE OF PETROLEUM PRODUCTS
The Petroleum Rules 2002 dated 13th March 2002 stipulates the following criteria for storage and handling of Petroleum Products.
i) No license is required for storage, handling and transport of any such product (i.e. petroleum Class B ) if the total quantity in possession does not exceed 2500 litres in non-bulk (i.e. drums) or 1000 litres in a receptacle / tank (i.e. bulk).
ii) Application for renewal of petroleum license may be made to Chief Controller
of Explosive’s Office.
As this is a Group Housing Project, no bulk use / storage of petroleum products is envisaged in the project. Therefore, no petroleum license is required for this project.
7.1.0.4 OIL AND CHEMICAL PLANT LAYOUT AND SPACING – GAPS GUIDELINES
Global Asset Protection Services LLC (GAPS), USA and its affiliated organizations provide loss prevention surveys and other risk management, continuity and facility asset management services. Loss experience clearly shows that fires and explosions in congested areas of oil and chemical plants can result in excessive losses. Wherever explosion or fire hazards exist, proper plant layout and adequate spacing between hazards are essential to loss prevention and control. Layout relates to the relative position of equipment or units within a given site. Spacing pertains to minimum distance between units or equipments. Global Asset Protection Services (GAPS) layout and spacing recommendations are for the property loss prevention purposes only and are intended for existing and new oil and chemical facilities.
7.1.0. SAFETY CODES FOR BUILDING & FIRE FIGHTING SYSTEM
The Fire-fighting network followed by Emergency Response Mock Drills is essential part of
Risk Control Measures.
Construction of the group housing project has been done as per the provisions of National
Building Code 2016. The fire-fighting system has been designed considering the following
codes, manual and guidelines:
1) National Building Code of India (NBC) 2016;
2) Latest relevant NFPA codes, USA, in particular NFPA – 13, 14, 20 & 22;
3) IRI guidelines;
4) As per requirement of fire officer / local fire approving authorities; and
Project Name Environment Clearance for Group Housing Project
EIA Project Proponent Sunrise Technobuild LLP
Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra
Marg Yojna, Rishikesh, Uttarakhand
Environment Consultant
Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-4
5) As per Indian Standard Code for Fire Protection (IS Codes)
Following items are proposed for firefighting:
1) High Pressure Fire-Water Connections;
2) Firewater inlet and outlet connections have been provided to the water storage
tanks;
3) External main fire ring, having 150 mm diameter and hydrants @ 45 m3/s spacing
shall be provided. This external fire ring shall be separated from the Sprinkler Main
Systems;
4) All Flow Switches, Test Valves, Drain Pipes etc have been provided as per NFPA
guidelines on the sprinkler system;
5) All Pump installation and arrangements have been made in accordance with IRI
guidelines and NFPA-20;
6) All Pumps and accessories and electrical Controllers have been provided as per
UL/FM lists, tested, approved and certified;
7) By-pass arrangements have been provided (150 mm diameter nominal bore) with
NRV and Gate Valve and bulk Flow Meter on the discharge Header of each Pump to
check the duties of Pumps.
8) Storage Tanks have been provided in the basement for the supply of water for the
firefighting facility.
9) The Fire Extinguishers have been provided in conformance with Ozone Depleting
Substances (Regulation and Control) Rules 2000.
7.1.1RISK HAZARD AND ITS CONTROL MEASURES
On-Site and Off-Site emergency plans are in place to provide the necessary infrastructures
for control of risks and hazards so that the losses to personnel and property are minimum.
7.1.1.0 ON - SITE EMERGENCY PLAN
The on- site management plan will be circulated to all concerned member of emergency
team. It is essential that all concerned person are familiar with the overall on- site
emergency plan and their respective roles and responsibilities during emergency. They
should also participate regularly in the mock drills to keep in a state of perpetual
preparedness at all times to meet any emergency.
Project Name Environment Clearance for Group Housing Project
EIA Project Proponent Sunrise Technobuild LLP
Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra
Marg Yojna, Rishikesh, Uttarakhand
Environment Consultant
Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-5
77.1.1.0.1 ACTION PLAN OF ON-SITE EMERGENCY PLAN
The main objective of the plan is to take immediate actions to meet any emergency
situation for speedy and efficient rescue and relief operations. The main steps in an onsite
emergency plan are described below:
1) Cordon and isolate the affected area for smooth rescue operation.
2) Rescue and treat casualties and safeguards the rest.
3) Minimize damage to life, property and surroundings.
4) Contain and ultimately bring the situation under control.
5) Secure and safe rehabilitation of the affected area.
6) Identify any casualty and provide for the needs of the relatives.
7) Provide necessary information to statutory agencies.
8) Provide authoritative information to the news media.
9) Ward off unsocial elements and prying onlookers.
10) Counter rumor mongering and panic by relevant accurate information.
77..11..11..00..22 SSCCOOPPEE OOFF OONN--SSIITTEE EEMMEERRGGEENNCCYY PPLLAANN
The plan covers information regarding the properties of the group housing project, type of
disasters and disaster/accident prone zones. The important elements considered in this
plan are:
1) Statutory requirement
2) Emergency organization
3) Roles and responsibility
4) Communications during emergency
5) Emergency facilities
6) Important information
The primary purpose of the On- Site emergency plan is to control and contain the incident
and so to prevent it from spreading. To cover eventuality in the plan and the successful
handling of the emergency will depend on appropriate action and decision being taken on
the spot.
It is proposed to plan and construct the buildings following all safety norms. However, it is
not always possible to totally eliminate such eventualities and random failures of
equipment or human errors. An essential part of major hazard control has therefore, to be
concerned with mitigating the effects of such emergency and restoration of normalcy at the
earliest. A detailed table showing activities during construction and operation phase along
with mitigation measures are given in Table 1.1
Project Name Environment Clearance for Group Housing Project
EIA Project Proponent Sunrise Technobuild LLP
Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra
Marg Yojna, Rishikesh, Uttarakhand
Environment Consultant
Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-6
Table 1.1: Activities during construction and operation along with mitigation
measures
HAZARDS ASSOCIATED WITH ACTIVITIES
(During Construction & Operation)
CONTROL / MITIGATION MEASURES
Manual Handling:
- Strains and sprains incorrect lifting - too
heavy loads -twisting - bending - repetitive
movement - body vibration.
Exercise/warm up - get help when needed -
control loads - rest breaks/no exhaustion -
no rapid movement/twisting/
bending/repetitive movement - good
housekeeping.
Falls - Slips – Trips:
Falls on same level - falls to surfaces below -
poor housekeeping - slippery surfaces
Uneven surfaces -poor access to work areas
climbing on and off plant -unloading
materials into excavations wind - falling
objects.
Housekeeping - tidy workplace - guardrails,
handholds, harnesses, hole cover, hoarding,
no slippery floors/trip hazards - clear/ safe
access to work areas - ingress from work
areas - dust/water controlled - PPE.
Fire :
Flammable liquids/Gases like LPG, Diesel
Storage area and combustible building
materials - poor housekeeping - grinding
sparks - open flames, absence of Fire
hydrant net work.
Combustible/flammable materials properly
stored/used - good housekeeping - fire
extinguishers made available & Fire hydrant
Network with reserve Fire water (As per
NFPA Code) - Emergency Plan in case of
Fire or collapse of structure.
Absence of Personal Protective
Equipment (PPE):
Lack of adequate footwear - head protection
–hearing/eye protection - respiratory
protection - gloves -goggles.
Head/face - footwear – hearing/eye - skin –
respiratory protection provided - training -
maintenance.
Defective or wrong Hand Tools :
Wrong tool - defective tool - struck by flying
debris - caught in or on - missing guards -
carbon monoxide - strains and sprains -
dust.
Right tool for the job - used properly - good
condition/ maintenance guards - isolation –
eye/face protection - flying debris
controlled.
Electricity:
Electrocution - overhead/underground
services- any leads damaged or poorly
insulated - temporary repairs -no testing
and tagging - circuits overloaded – non-use
of protective devices.
Leads good condition and earthed - no
temporary repairs - no exposed wires -
good insulation - no overloading - use of
protective devices - testing and tagging -no
overhead/ underground services
Project Name Environment Clearance for Group Housing Project
EIA Project Proponent Sunrise Technobuild LLP
Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra
Marg Yojna, Rishikesh, Uttarakhand
Environment Consultant
Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-7
Scaffolding:
Poor foundation - lack of ladder access
insufficient planking - lack of guardrails and
toe boards - insufficient ties or other means
- all scaffolds incorrectly braced or
stabilized to prevent overturning.
All scaffolds correctly braced and stabilized
- 3:1 height to base ratio - firm foundation,
plumb and level - ladder access provided
and used - proper platform (3 planks/675
mm) - planks secured - guardrails and toe
boards – 900mm to 1100mm high, within
200mm of working face, mid-rail.
Ladders:
Carrying loads - not secured against
dislodgement - defective ladders - not
sufficient length - wrong positions -
incorrectly placed (angles, in access ways,
vehicle movements.
Secured against movement or footed -
ladders in good condition - regularly
inspected - extend 1m above platform - 4:1
angle - out of access ways, vehicle
movements - climbing - no carrying loads -
3 points of contact - no higher than 3rd step
down - use for access only, not working
platforms.
Excavations:
Trench collapse - material falling in
undetected underground services - falls -
hazardous atmosphere struck by traffic and
mobile plant.
Soil stability known - no water
accumulation - existing services known -
material 600mm from edge - clear of
suspended loads – hardhats/PPE - ladders -
public protection – atmospheric testing -
traffic controls - Emergency Plan.
Gas Cutting and Welding:
Fire - welding flash, burns, fumes,
electrocution in wet conditions - flashback
in oxygen set, leaking cylinders, acetylene
cylinders lying down - poorly maintained
leads.
Welding flash and burns controlled with
PPE and shields -fumes controlled with
ventilation and PPE
(in good condition and properly
positioned),Gas cylinders be kept upright &
secured position (properly tied) -
combustible materials to be kept at secured
place to avoid fire and Fire Extinguishers to
be kept in fire prone area with training to
people for its use.
Noise:
known noise levels over 85 decibels
Levels below 85 decibels - proper
protection.
Falling Materials:
Fall during carrying/Lifting materials-
dislodged tools and materials from
overhead work areas.
Materials to be secured – kept away from
edge - toe boards –Use of hard hats.
Cranes& Lifts:
Display of carrying capacity i.e. load (No. of
person), incorrectly slung, defective lifting
Periodic testing by competent authority -
correctly slung/secured loads, lifting
Project Name Environment Clearance for Group Housing Project
EIA Project Proponent Sunrise Technobuild LLP
Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra
Marg Yojna, Rishikesh, Uttarakhand
Environment Consultant
Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-8
equipment, unsecured loads, craning in
close proximity to building people and plant
- falls - falling materials.
equipment in good conditions - use of
proper hand signals - falls while unloading
controlled.
Visitors Presence at the Site:
Falls - struck by - dropped materials -
loading accidents -insufficient hoarding or
fencing - pedestrian access past site -
mechanical plant movement on and off site.
Sufficient hoarding - fencing and barricades
- safe pedestrian access past site traffic
management for loading and delivery -
construction separated from occupied areas
of projects.
77..11..11..00..33OOBBJJEECCTTIIVVEE OOFF OONN--SSIITTEE EEMMEERRGGEENNCCYY PPLLAANN
Risk analysis and risk assessment should provide details on risk posed to people who
work inside or live near hazardous facilities, and to aid in preparing effective emergency
response plans by delineating a disaster management plan (DMP) to handle on-site and
off-site emergencies. Hence, risk analysis and risk assessment is an invaluable method for
making informed risk-specific for any group housing project is complex and needs
extensive study that involves process understanding, hazard identification, consequences
probability data, vulnerability models / data, local weather and terrain conditions and
local population data. Risk analysis and risk assessment will be carried out to serve the
following objectives:
1) Identification of safety areas
2) Identification of hazard sources
3) Generation of accidental release scenarios for escape of hazardous materials from the
facility
4) Identification of vulnerable units with recourse to hazard indices
5) Assessment of risk on the basis of above evaluation against the risk acceptability
criteria relevant to the situation
6) Suggest risk mitigation measures based on engineering judgment, reliability and risk
analysis approaches
7) Delineation / up-gradation of DMP
8) Safety reports: with external safety report / occupational safety report
The risk assessment report may cover the following in terms of the extent of damage with
analysis and delineation of risk mitigations measures with an approach to DMP.
1) Hazard Identification- identification of hazardous activities, hazardous materials, past
accident records etc.
2) Hazard quantification- consequence analysis to assess the impacts
Project Name Environment Clearance for Group Housing Project
EIA Project Proponent Sunrise Technobuild LLP
Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra
Marg Yojna, Rishikesh, Uttarakhand
Environment Consultant
Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-9
3) Risk Presentation
4) Risk Mitigation Measures
5) Disaster Management Plans (DMP)
7.1.1.1OFF - SITE EMERGENCY PLAN
A major emergency in any situation is one, which has the potential to cause serious injury
or loss of life, which may cause extensive damage to the structure in vicinity and
environment and could result in serious disruption to normal operation both inside and
outside the industry premises. Depending on the magnitude the emergency, service of the
outside agencies may also be envisaged.
The management has to take effective steps to assess, minimize and wherever feasible
eliminate the risk to large extent. Accident may still occur and it is necessary to be fully
prepared to tackle all such emergencies if and when they occur.
It is likely that the consequences of such emergencies will be confined to the units
concerned or may affect outside. If the consequences are confined within the plant
boundary, it will be controlled by Chief Emergency Controller. The most widely used
techniques in practice will be based on experience accumulated over many years and
safety audits.
77..11..11..22CCOOMMPPEENNSSAATTIIOONN TTOO TTHHEE VVIICCTTIIMMSS
The project authorities shall form an investigation team for an accident with the Safety
Officer and other members of the group housing project.
The Public Liability Insurance (PLI) Act, 1991, provides for the owner handling hazardous
substances to pay specified amount of the money to the victims as relief by taking
insurance policy for this purpose.
7.1.2MODELS FOR IMPACT PREDICTION & RISK ASSESSMENT
Hazards Identification, Hazards Evaluation and Hazards Quantification are done as per
the prediction of the Models used. These may be used for impact prediction and risk
assessment.
Project Name Environment Clearance for Group Housing Project
EIA Project Proponent Sunrise Technobuild LLP
Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra
Marg Yojna, Rishikesh, Uttarakhand
Environment Consultant
Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-10
FFIIGGUURREE 11..11:: RRIISSKK AASSSSEESSSSMMEENNTT--CCOONNCCEEPPTTUUAALL FFRRAAMMEEWWOORRKK
Table 1.2: Choice of Models for Impact Predictions: Risk Assessment
Name Application Remarks
EFFECT
WHAZAN
Consequence analysis for
Visualization of accidental
chemical release scenarios &
its consequence
Consequence of analysis for
visualization of accidental
chemical release scenarios &
its consequence
Heat load, press wave and
toxic release exposure
neutral gas dispersion
DEGADIS Consequence of analysis for
visualization of accidental
chemical release scenarios &
its consequence
Dense gas dispersion
HAZOP & fault
tree assessment
For estimating top event
probability
Failure frequency data is
required
Pathways
reliability and
protective
system hazard
analysis
For estimating reliability of
equipments and protective
systems
Markov Models
Hazard Evaluation
Hazard Quantification
Hazard Identification
Project Name Environment Clearance for Group Housing Project
EIA Project Proponent Sunrise Technobuild LLP
Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra
Marg Yojna, Rishikesh, Uttarakhand
Environment Consultant
Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-11
Vulnerability
Exposure
models
Estimation of population
exposure
Uses probity equation for
population exposure
F-X and F-N
curves
Individual/Societal risks Graphical Representation
7.1.3 HAZARD IDENTIFICATION
Hazard is the characteristic of any system or process which has the potential for accident.
Identification of hazards, in the presence of any hazardous waste generating activities
within the group housing project is of primary significance in the analysis, quantification
and cost effective control of accidents involving construction.
The typical methods for hazard identification employed are:
1) Identification of major hazardous units based on Manufacture, Storage and Import of
Hazardous Chemical Rules, 1989 of Government Of India (amended in 2000)
2) Identification of hazardous wastes based on Hazardous Waste (Management,
Handling and Trans-boundary Movement) Rules, 2008, and its amendments.
3) Hazardous substances may be classified into three main classes’ namely flammable
substances, unstable substances and toxic substances.
7.1.4 HAZARD ASSESSMENT & EVALUATION
A preliminary hazard analysis shall be carried out to identify the major hazards
associated with storages in the group housing project. This is followed by consequence
analysis to quantify these hazards. Following are the vulnerable zones of accident:
7.1.4.0 Frequent Causes of Accidents
1) Fire and explosion: explosives, flammable materials
2) Being struck by falling objects
3) Caught in or compressed
4) Snapping of cables, ropes, chains, slings
5) Handling heavy objects
6) Electricity
7) Poor illumination
8) Falls from height inside industrial units or on the ground
9) Struck by moving objects
10) Slipping on wet surfaces
11) Sharp objects
12) Oxygen deficiency in confined spaces
Project Name Environment Clearance for Group Housing Project
EIA Project Proponent Sunrise Technobuild LLP
Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra
Marg Yojna, Rishikesh, Uttarakhand
Environment Consultant
Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-12
7.1.4. Hazardous Substances and Wastes
1) Heavy and toxic metals (lead, mercury, cadmium, copper, zinc, etc.)
2) Organo metallic substances (tributyltin, etc.)
3) Lack of hazard communication (storage, labelling, material safety data sheets)
4) Batteries, fire-fighting liquids
5) Pcbs and PVC
6) Welding fumes
7) Volatile organic compounds (solvents)
8) Inhalation in confined and enclosed spaces
7.1.5 DISASTER MANAGEMENT PLAN
Disasters may be Manmade Disasters (such as Fires, Terrorism, and Stampede etc) or
Natural Disasters (such as earth quake, Tsunami, Flood & Cloud Burst etc). Various
criteria for the Natural Disasters and Manmade Disasters shall be considered.
For Manmade Disasters such as Fires, provisions of the National Building Code of India
(NBCI) have been considered and necessary provisions have been made.
For natural disaster management, there are the Natural Disaster Management Authority
(NDMA) at the Centre, Government of India and the State Disaster Management Authority
(SDMA) at the State level. For natural disasters, guidelines shall be followed as given in
the Vulnerability Atlas of India (Earth quake, windstorm, and flood hazard Maps and
Damage Risk Housing) prepared by the Building Materials and Technology Promotion
Council (BMTPC), Ministry of Housing & Urban Poverty Alleviation (MHUPA),
Government of India.
For Natural Disasters such as earth quakes, Earth Quake Zoning Maps have been
considered and earth quake resistant building structures and retrofitting of old buildings
and structures have been considered as applicable to the place where the project is
located. Flood & Cloud Burst data obtained from Indian Meteorological Department (IMD)
have been considered for structural design of the project.
Emergency planning is an integral part of the overall loss control program and is
essential for any well run organization. This is important for effective managem ent
of an accident /incident to minimize losses to people and property, both in and around
the facility. The format and contents of the Emergency Response Plan (ERP)/On-Site Disaster
Management Plan (DMP) has been developed taking into consideration the regulatory
guidelines, other applicable documents and accepted good construction practices
formulated as a result of lessons learned in actual emergencies requiring extensive
emergency response.
Project Name Environment Clearance for Group Housing Project
EIA Project Proponent Sunrise Technobuild LLP
Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra
Marg Yojna, Rishikesh, Uttarakhand
Environment Consultant
Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-13
Disaster can be defined as an “occurrence of undesired events of such magnitude so as
to create a situation in which normal pattern of life within the group housing project
is suddenly disrupted, adversely affecting not only the personnel and property within
the group housing project but also in its vicinity.”
As per the Manufacture, Storage and Import of Hazardous Chemical (Amendment)
Rules, 2000, “major accident” means–an incident involving loss of life inside or outside
the group housing project, or ten or more injuries inside and/or one or more injuries
outside or release of toxic chemicals or explosion or fire or spillage of hazardous
chemicals resulting in on-site or off-site emergencies or damage to equipment leading
to stoppage of construction or adverse affects to the environment;
A Disaster Management Plan (DMP) has been prepared considering the On-Site and Off-
Site disasters that can occur during construction and operational phases of the Project.
A disaster is a catastrophic situation in which suddenly, people are plunged into
helplessness and suffering and, as a result, need protection, clothing, shelter, medical and
social care and other necessities of life. The Disaster Management Plan is aimed to ensure
safety of life, protection of Environment, protection of installation, restoration of
production and salvage operations in this same order of priorities. For effective
implementation of the Disaster Management Plan, it shall be widely circulated and a
personnel training is to be provided through rehearsals/drills. To tackle the
consequences of a major emergency inside the project or immediate vicinity of the
project, a Disaster Management Plan (DMP) has been formulated and this planned
emergency document is called "Disaster Management Plan".
7.1.5.0 OBJECTIVE OF THE DISASTER MANAGEMENT PLAN
The objective of the Disaster Management Plan is to make use of the combined resources
of the group housing project and the outside services to achieve the following:
Effect the rescue and medical treatment of casualties.
Safeguard other people;
Minimize damage to property and the environment;
Initially contain and ultimately bring the incident under control;
Identify any dead;
Provide for the needs of relatives;
Provide authoritative information to the news media;
Secure the safe rehabilitation of affected area;
Preserve relevant records and equipment for the subsequent inquiry into the
cause and circumstances of the Emergency.
Project Name Environment Clearance for Group Housing Project
EIA Project Proponent Sunrise Technobuild LLP
Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra
Marg Yojna, Rishikesh, Uttarakhand
Environment Consultant
Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-14
In effect, it is to optimize operational efficiency to rescue rehabilitation and render
medical help and to restore normalcy. Disaster Management Plan shall include Emergency
Preparedness Plan, Emergency Response Team, Emergency Communication, Emergency
Responsibilities, and Emergency Facilities and Emergency Actions.
7.1.5.1 PROVISION OF ESSENTIAL SERVICES
7.1.5.1.1 STORM WATER DRAINAGE
A detailed “Storm Water Management” has been developed. This will incorporate best management practices which will include following:
Regular inspection and cleaning of storm drains. Cover waste storage areas. Avoid application of pesticides and herbicides before wet season. Secondary containment and dykes in fuel/oil storage facilities Conducting routine inspections to ensure cleanliness Preparation of spill response plans, particularly for fuel and oil storage areas. Provision of slit traps in storm water drains Surface Water from parking area will be discharged to drain.
7.1.5.1.2 FIRE FIGHTING SYSTEM
A state of the art fire fighting system is proposed for the project to prevent and control
fire outbreaks. The fire fighting system will consist of portable Fire Extinguishers, Hose
Reel, Wet Riser, Yard Hydrant, automatic Sprinkler System, and manual Fire Alarm
System. The group housing project will also be provided with automatic Fire Detection
and Alarm System. The copy of Fire NOC is attached as Annexure VII.
1) Pumps shall be protected with Sprinkler as per NFPA 20 (refer to NFPA 13 for
design)
2) DG sets need to be protected with mist as per the applicable regulation (refer to
NFPA 750 for design).
The fire and safety considerations will be as per the applicable National Building Code
2016. Important components are mentioned below.
1) Provision of water Sprinklers
2) Provision of Hose Reels, external Hydrants and Wet Risers
3) Provision of fire fighting underground Water Storage Tank,
4) Provision of overhead Water Storage Tank on each buildings
5) There is a provision of Fire Fighting Pumps.
6) Adequate Fire Extinguishers shall be available for emergency situations
7) HT and LT Panels will be protected with manually operated CO2Protection System.
Project Name Environment Clearance for Group Housing Project
EIA Project Proponent Sunrise Technobuild LLP
Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra
Marg Yojna, Rishikesh, Uttarakhand
Environment Consultant
Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-15
8) Automatic Sprinklers will be installed in the entire building
9) Portable Fire Extinguishers shall be provided at strategic locations
10) Optical type smoke detectors shall be used in most areas
11) Automatic fire detection system i.e. Smoke/ Heat Detection System shall be
provided in the buildings at appropriate places. The system will be connected to
the Fire Alarm System
12) Rate of rise heat detectors shall be planned for all potentially smoky areas and in
the basement.
HSD and other petroleum products at site shall be stored at earmarked area having
impervious floor and adequate fire fighting arrangements. Hazardous wastes as waste oil
shall be collected and stored and periodically sold off to MoEF&CC/ SPCB authorized
Recyclers. Buy back arrangement shall be made with the authorized dealer of Lead Acid
Storage Batteries used in the DG Sets.
7.1.5.2 EMERGENCY RESPONSE PLAN
The overall objective of an Emergency Response Plan (ERP) is to make use of the
combined resources at the group housing project and outside services to achieve the
following:
1) To localize the emergency and if possible eliminate it;
2) To minimize the effects of the accident on people and property;
3) To Effect the rescue and medical treatment of casualties;
4) Safeguard other people;
5) Evacuate people to safe areas;
6) Informing and collaborating with statutory authorities;
7) Initially contain and ultimately bring the incident under control;
8) Preserve relevant records and equipment for the subsequent enquiry into the
cause and circumstances of the emergency;
9) Investigating and taking steps to prevent reoccurrence
The ERP is therefore related to identification of sources from which hazards can arise and
the maximum credible loss scenario that can take place in the concerned area. The plan
takes into account the maximum credible loss scenario - actions that can successfully
mitigate the effects of losses/ emergency need to be well planned so that they would
require less effort and resources to control and terminate emergencies.
Main hazards identified for the project include hazards pertaining to fires in buildings and
fire in diesel storage areas, earthquake and LPG leakage and an ERP pertaining to these is
described in the following section.
Project Name Environment Clearance for Group Housing Project
EIA Project Proponent Sunrise Technobuild LLP
Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra
Marg Yojna, Rishikesh, Uttarakhand
Environment Consultant
Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-16
77..11..55..33 OONN--SSIITTEE DDIISSAASSTTEERR MMAANNAAGGEEMMEENNTT PPLLAANN
The main objective of the plan is to take immediate actions to meet any emergency
situation for speedy and efficient rescue and relief operations. The main steps in an onsite
emergency plan are described below:
1) Cordon and isolate the affected area for smooth rescue operation.
2) Rescue and treat casualties and safeguards the rest.
3) Minimize damage to life, property and surroundings.
4) Contain and ultimately bring the situation under control.
5) Secure and safe rehabilitation of the affected area.
6) Identify any casualty and provide for the needs of the relatives.
7) Provide necessary information to statutory agencies.
8) Provide authoritative information to the news media.
9) Ward off unsocial elements and prying onlookers.
10) Counter rumor mongering and panic by relevant accurate information.
The parameters considered are given as follows:
1) To constitute Disaster Management Committee under a senior officer not below the
rank of General Manager.
2) To identify potential hazards areas in the layout map of group housing project
3) To use model to predict hazards impact in the surrounding areas in form of pool-fire
or gas leakage.
4) To predict degree of burns and distance of the risk zone by using model.
5) To evacuate the area within risk zone.
6) To localize the emergency and if possible eliminate it.
7) To minimize the effects of accidents on people and property.
8) To take remedial measures in the quickest possible time to contain the incident and
control it with minimum damage.
9) To mobilize the internal resource and utilize them in the most effective way.
10) To get help from the local community and government official to supplement internal
manpower and resources.
11) To minimize the damage in other sections.
12) To keep the required emergency equipment in stock at right places and ensure that
they are in working condition.
13) To keep the concerned personnel fully trained in the use of emergency equipment.
Project Name Environment Clearance for Group Housing Project
EIA Project Proponent Sunrise Technobuild LLP
Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra
Marg Yojna, Rishikesh, Uttarakhand
Environment Consultant
Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-17
14) To give immediate warning to the surrounding localities in case of emergency
situation arising.
15) To mobilize transport and medical treatment of the injured.
16) To educate the public in the surrounding villages regarding hazards.
17) To arrange treatment of causalities.
18) To safe guard the people.
19) To identify the causalities and communicate to persons known to them.
20) To render necessary help to the concerned.
21) To rehabilitate the area affected.
22) To provide information to media and government agencies.
77..11..55..44OONN -- SSIITTEE EEMMEERRGGEENNCCYY PPLLAANN
Identification of Responsibilities: The on-site disaster management plan shall identify
the Chief Incident Controller (CIC) who shall be the Chief of the Project (i.e. The Project In-
Charge) and the support team to Work Incident Controller (WIC) and Designated Key
Personnel of emergency control centre. The plan also specifies responsibilities of these
personnel in case of an emergency and draws an action plan to be followed. Chief Incident
Controller and Works Incident Controller (WIC) shall be assisted by two support teams as
follows.
Table 1.3: Details of Incident Controller
Support team to Chief Incident Controller
(CIC)
Consisting of Heads of Personnel, Materials and Finance Division:
To function in consultation with CIC for the following
Contacting statutory authorities.
Arranging for relievers and catering facilities
Giving information to media.
Contacting media centers and nursing homes
Providing all other support, as necessary.
Arranging for urgently required materials through
Cash purchase or whatever means.
Support team to Work Incident Controller (WIC)
Consisting of Senior Supervisor and Works Manager and any more persons depending upon the need to assist the WIC in manning communication and passing Instruction to the team. One steno secretary shall also be available with WIC for recording all information coming in and instruction going out.
Project Name Environment Clearance for Group Housing Project
EIA Project Proponent Sunrise Technobuild LLP
Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra
Marg Yojna, Rishikesh, Uttarakhand
Environment Consultant
Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-18
77..11..55..55OOFFFF -- SSIITTEE DDIISSAASSTTEERR MMAANNAAGGEEMMEENNTT PPLLAANN
Incidents having off-site implications can be:
1) Natural calamities like earthquake, cyclone, landslide etc.;
2) Chlorine and other Toxic Gas Leaks;
3) Major Fire involving combustible materials like oil and Gas spreading from other
nearby facilities or installations.
4) Air raids / Crashing of aircraft or flying objects. Incidents, which could also lead
to a disaster;
5) Agitation / forced entry by external group of people;
6) Sabotage.
In an extremely rare event of massive disaster which will have potential to affect areas outside the group housing project premises, needs to be informed to the District Authorities responsible for the preparation and implementation of Offsite Disaster Management Plan. The measures will include - Allocation of duties among the Project Fire Brigade, Police and Auxiliary Force.
An important aspect of the disaster is its unforeseen nature. Thus by definition, a disaster is impossible to control completely. However, occurrence of events which lead to a disaster may be minimized through proper technology, engineering practices and adaptation of available Disaster Management Practices.
Under the Environmental (Protection) Act, 1986, the responsibility of preparation of Off-Site Emergency Plan lies with the State Government. The Collector, Deputy Collector by virtue of their occupation is normally nominated by the concerned State government to plan Off-Site Emergency Plan.
The District Collector or his nominated representative would be the Team Leader of the planning team, who shall conduct the planning task in a systematic manner. The members of the Planning Team for Off-Site Emergencies are Collector, Deputy Collector, District Authorities In-Charge of Fire Services and Police, members drawn from Medical Services, Factory Inspectorate, Pollution Control Board and Industries & Transport Departments. In addition to these members, there are Co-opted Members also from the district authorities concerned, Civil Defense, Publicity Department, Municipal Corporation, and non-officials such as representatives (MPs, MLAs, Voluntary Organizations, NGOs etc).
7.1.5.6ONSITE AND OFFSITE EMERGENCY RESPONSE PLAN
To take control of any mishaps, Disaster Management Plan (DMP) has been formulated for
various areas. All the above mentioned instructions can lead to less risk but can't
eradicate the possibility of occurrence of any mishap. Onsite and Offsite Emergency
Response Plans have been formulated and key points of the same are as follows:
1) First Aid at site, Safety Officer and a Doctor must be available to give First Aid at the
site and proper record for the same must be maintained at the site.
Project Name Environment Clearance for Group Housing Project
EIA Project Proponent Sunrise Technobuild LLP
Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra
Marg Yojna, Rishikesh, Uttarakhand
Environment Consultant
Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-19
2) Availability of Ambulance at the site for emergency moving of the patients from site to
the hospital.
3) Emergency numbers of nearest Hospital, Fire Brigade Office and Police Station must be
placed at the site.
4) Alarm must be blown in case of any hazard.
5) All the workers must be aware of the Assembly Point and must reach there in case of
any evacuation to be made from the site.
6) The Site Office shall serve as Emergency Control Room (Centre) in case of emergency.
7.1.5.7EMERGENCY STRUCTURE AND RESPONSIBILITY
The emergency preparedness organizational structure should consist of the following
persons:
1) Site Main Controller --The Project Manager shall be named as the site main
controller
2) Incident Controller – The Site Supervisor shall act as incident controller in case of
emergency.
3) Manager Safety or Fire & Safety shall be the Coordinator.
4) Security in Charge shall be in the Coordination Team.
5) Rescue Team consisting of Operators and Site Employees specially trained in safety
and/or first aid shall be formed.
7.1.5.7.0 ROLE OF SITE MAIN CONTROLLER
1) Site Main Controller shall relieve the Incident Controller of the responsibilities of
overall emergency control as soon as he arrives at the site and takes stock of the
situation. He will position himself in the Emergency Control Centre and shall
thereafter give directions to the emergency Team from here.
2) Ensures that the medical aid is promptly provided to the causalities and that their
relatives are informed.
3) Organizes evacuation and transportation of personnel from the Assembly Points to
a safe location outside.
4) If external help is needed, shall coordinate with outside emergency services like
Fire Brigade of the nearest town, Ambulance Centre etc.
5) Ensures that affected personnel are transported to external medical centers to
keep constant liaison with these medical centers through the Medical Officer
during the course of the emergency.
6) Keeps concerned Government Agencies informed of the emergency and if
necessary arranges information to the outside residents through police.
7) Decides to call off the emergency when everything is OK.
Project Name Environment Clearance for Group Housing Project
EIA Project Proponent Sunrise Technobuild LLP
Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra
Marg Yojna, Rishikesh, Uttarakhand
Environment Consultant
Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-20
7.1.5.7.1 ROLE OF INCIDENT CONTROLLER
1) Incident Controller on reaching the site of the incident relieves the In-Charge of the
responsibilities of directing the Emergency Operations and assumes total control of
emergency operations in the affected area.
2) Determines the adequacy of the emergency services.
3) Directs the Emergency Operation from the incident site to localize emergency,
keeping in mind the priorities for safety of personnel, least damage to the property
and environment thereby minimize loss of materials.
4) Provides the necessary information and advises the Fire and Security Personnel
and Local Fire Services as and when they are called.
5) Continuously reviews the situation with the site Main Controller.
7.1.5.7.2ROLE OF MANAGER (SAFETY)/EXECUTIVE (FIRE AND SAFETY)
1) Proceeds to the Emergency Control Centre, establishes contact with Firefighting
men and Incident Controller and supplements efforts made in the fire fighting in
case of fire and other such emergencies involving people.
2) Assist nurse in providing First Aid to those who are injured.
3) Mobilizes Personal Protective Equipment (PPE) and safety appliances and assists
in using them to the personnel handling the emergency.
4) Collects and preserves evidences to facilitate future inquiry.
7.1.5.7.3 ROLE OF SECURITY IN-CHARGE
1) Assumes charge of all external communications in consultation with the Site Main
Controller.
2) Takes charge of the EPABX (Electronic Private Automatic Branch Exchange Board /
Box), if available and deputes a trained person (e.g. Security Guard) to man the
Board when regular Telephone Operator is off duty and thereby restrict the
unnecessary calls.
3) Assumes total control of the storage facility under the direction of the Site Main
Controller.
4) Controls traffic movement, removes Truck and Tanker Drivers, if any, gathered at
the Site Gate and prevents entry of all non-essential personnel.
5) Cordons off the Incident Site and keeps the site cleared off the observers gathered
at the place of the incident.
7.1.5.7.4 TRAINED FIRST AIDER
1) First Aider or the Team shall rush to Emergency Control Point and gets the
feedback from the Site Controller about the emergency.
Project Name Environment Clearance for Group Housing Project
EIA Project Proponent Sunrise Technobuild LLP
Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra
Marg Yojna, Rishikesh, Uttarakhand
Environment Consultant
Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-21
2) As per the instruction, they must rush to the area of emergency and assess the
situation.
3) Approach emergency site quickly with the First Aid Box Kit and other essentials.
4) Diagnoses the situation and decides whether the affected persons shall be moved
to the safe area.
5) Moves the injured personnel to the safe place and assists in offering the First Aid as
required by the situation.
6) Follows instructions from the Incident Controller.
7) Moves / Transports the causalities to the Ambulance / near to the Medical Centre
for necessary medical assistance.
7.1.5.8.0 RESPONSE IN CASE OF DISASTERS
The response procedure for earthquake, LPG leakage, outbreak of fire etc has been
discussed in detail as given below.
7.1.5.8.1RESPONSE IN CASE OF EARTHQUAKE
7.1.5.8.1.1 RESPONSE PROCEDURES FOR OCCUPANTS
7.1.5.8.1.1.1 IF INDOORS
Take cover under a piece of heavy furniture or against an inside wall and hold on.
Stay inside: The most dangerous thing to do during the shaking of an earthquake
is to try to leave the building in an effort to avoid the falling of probable object.
77.1.5.8.1.1.2 OUTDOORS
Move into the open, away from buildings, streetlights, and utility wires. Once in the open,
stay there until the shaking stops.
77.1.5.8.1.1.3 IF IN A MOVING VEHICLE
Stop quickly and stay in the vehicle. Move to a clear area away from buildings, trees,
overpasses, or utility wires. Once the shaking stopped, proceed with caution. Avoid
bridges or ramps that might have been damaged by the quake.
7.1.5.8.1.2 AFTER-SHOCKS
After the quake, be prepared for aftershocks
Although smaller than the main shock, aftershocks cause additional damage and
may bring weakened structures down. Aftershocks can occur in the first hours,
days, weeks, or even months after the quake.
Project Name Environment Clearance for Group Housing Project
EIA Project Proponent Sunrise Technobuild LLP
Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra
Marg Yojna, Rishikesh, Uttarakhand
Environment Consultant
Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-22
7.1.5.8.1.3 HELP INJURED OR TRAPPED PERSONS
Give first aid where appropriate. Do not move seriously injured persons unless
they are in immediate danger of further injury. Call for help.
Remember to help those who may require special assistance--infants, the elderly,
and people with disabilities.
Stay out of damaged buildings.
Use the telephone only for emergency calls.
7.1.5.8.1.4 RESPONSE PROCEDURE FOR EMERGENCY TEAM
Formulate an Emergency Response Team for earthquake response
Using the public address system, inform occupants of response procedures
discussed above.
Inform the necessary authorities for aid.
Ensure that no person is stuck beneath any debris, in case of a structural failure.
Ensure that all occupants standing outside near the buildings are taken to open
areas.
Ensure that the first aid ambulance and fire tender vehicles are summoned if
necessary.
Inform the nearby hospitals if there are any injuries.
Check the utilities and storage tanks for any damage.
7.1.5.8.2 RESPONSE FOR LPG LEAKAGE
1) The affected area should be evacuated and cordoned off immediately
2) Initiate an Emergency Response Team for LPG leakage
3) Shut down the main valves in the gas cylinder
4) Ensure that only concerned personnel are present in the affected area and all
other personnel and visitors are moved to the nearest assembly points
5) Rescue trapped personnel, also check if any personnel are unconscious in the area
and immediately move them outside and provide first aid.
6) Ambulance should be summoned to take injured personnel to the nearest hospital.
7) Personnel in the nearby buildings to close all doors and windows to prevent entry
of the leaked gas
8) Source of leakage to be traced and isolated from all the other areas. If required,
use pedestal fans to bring down the gas concentration
7.1.5.8.3 RESPONSE IN CASE OF FIRE
1) Required response in the event of a fire shall be described in signs located in the
lobby.
Project Name Environment Clearance for Group Housing Project
EIA Project Proponent Sunrise Technobuild LLP
Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra
Marg Yojna, Rishikesh, Uttarakhand
Environment Consultant
Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-23
2) On sighting a fire, it shall be immediately informed to the Environment Manager
giving the exact location and type of fire in detail.
3) Initiate the Emergency Response Team for fires
4) If the fire is small, engage in extinguishing the fire using the nearest fire
extinguisher.
5) Guide the Emergency Response Team staff to the emergency assembly point.
6) The Emergency Response Team shall immediately inform the nearest dispensary
and security force. If required, a fire tender shall be summoned.
7) The response team shall immediately move to the point of fire and take all
necessary steps to stop the fire. If the fire is not controllable and spreads, then
the Manager in charge shall inform the district authorities and call for external
help.
8) The Emergency Response Team will provide immediate relief to the injured
Occupants at the scene of incident. Any injured persons shall be evacuated on
priority to the dispensary or one of the nearest hospitals based on their
condition.
7.1.5.8.3.0 INSTRUCTIONS FOR OCCUPANTS
1) Get out of buildings as quickly and as safely as possible.
2) Use the stairs to escape. When evacuating, stay low to the ground.
3) If possible, cover mouth with a cloth to avoid inhaling smoke and gases.
4) Close doors in each room after escaping to delay the spread of the fire.
5) If smoke is pouring in around the bottom of the door or if it feels hot, keep the
door closed.
6) Open a window to escape or for fresh air while awaiting rescue.
7) If there is no smoke at the bottom or top and the door is not hot, then open the
door slowly.
8) If there is too much smoke or fire in the hall, slam the door shut.
9) Stay out of damaged buildings.
10) Check that all wiring and utilities are safe.
A brief of Hazard-specific structural and non-structural measures for disasters caused by flood, earthquake, drought, fire and chemical & industrial accidents are outlined in the Table 1.4.
Project Name Environment Clearance for Group Housing Project
EIA Project Proponent Sunrise Technobuild LLP
Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra
Marg Yojna, Rishikesh, Uttarakhand
Environment Consultant
Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-24
Table --11..44:: BBRRIIEEFF of Hazard-Specific Structural & Non-Structural Measures
Hazard Structural Measures Non-Structural Measures Flood
Strengthening / construction of embankments, flood walls
Proper regulation of water storage reservoirs
Drainage improvement in Order to avoid congestion
Inspection, rehabilitation and maintenance programme to ensure that the design capabilities are maintained.
Flood plain zoning to regulate land use in the flood plains. Integrated Water Resource Management
such as water resources assessment, socio-economic assessment, water resources planning, implementation of action Plans, day-today water resources management (adjustments of the plans) and water resources protection and conservation.
Medical preparedness in terms of after-effects of floods requiring medical attention.
Earthquake Seismic strengthening of existing structures.
Structural safety audit of critical lifeline structure.
Earthquake-resistant construction
Development of Rapid Visual Screening procedures and Detailed Vulnerability Assessment.
Regular conduction of Fire Safety Audits and Electrical Safety Audits.
Public Awareness campaigns. Techno-legal regime for ensuring compliance
of earthquake-resistant design and construction practices in all new constructions.
Drought Water management including water harvesting and conservation.
Micro-irrigation including drip and sprinkler irrigation.
Study groundwater availability in area.
Project Name Environment Clearance for Group Housing Project
EIA Project Proponent Sunrise Technobuild LLP
Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra
Marg Yojna, Rishikesh, Uttarakhand
Environment Consultant
Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-25
Fire Implementation of all
applicable fire safety norms.
Training of community members in fire-fighting techniques. Putting in place audit system Compulsory
fire hazard evaluation of all types of buildings old and new
Planning and calendar of evacuation drills/ mock drills in vital installations/ industrial plants/ government buildings / schools and critical infrastructure like hospitals, etc.
Enforcement of fire approvals as per the provisions contained in National Building Code (NBC) 2005 for new constructions.
Chemical & Industrial Accidents
Creation of appropriate infrastructure as mentioned in Off-site and On-site plans including Public Address system.
Enforcement of code of practices, procedures and standards. Audits of on-site & off-site Emergency plans at regular intervals Statutory inspection, safety audit and
testing of emergency plans Safety auditing Hotline telephone connection with nearby
emergency services. Awareness generation among community regarding hazmat Training of specialized medical first aid responders
Biological Disasters
Enforcement of bio-safety measures in labs
Regular survey and proper maintenance of water supply and sewage pipeline.
Creation of awareness about personal hygiene. Vector control programs.
7.8 CORPORATE SOCIAL RESPONSIBILITY (CSR)
In the visit made to the site, it was found that around the proposed site area is developing
fast. Lack of jobs; lack of infrastructural facilities; high rate of school dropouts along with
the drug addiction were some the problems that were highlighted by the villagers. The
proponent M/S. Sunrise Technobuild LLP proposes to support the development activities,
to a budget of about Rs 1.4 /- Crore (2 % of the Total Project Cost i.e. 70 Crores) under its
corporate social responsibility. .
Steps for CSR Implementation:
The CSR programme will be implemented in the following steps
Floating of RFP/tender for CSR implementation
Finalization of CSR implementation organisation
Memorandum of Understanding and award of CSR Project
Project Name Environment Clearance for Group Housing Project
EIA Project Proponent Sunrise Technobuild LLP
Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra
Marg Yojna, Rishikesh, Uttarakhand
Environment Consultant
Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-26
Monitoring & Evaluation
Reporting
CSR Implementation Area: The CSR Programme will be implemented in the following
villages of Greater Noida
1 Veerbhadra
2 Rishikesh Nagar Nigam
3 Gumani Wala
CSR Programme: The following Corporate social responsibility programme will be
implemented in a phased manner.
1. Girl Child Education: The educated girls are the need of the society. According to
an estimate about 98 % students are dropping out of schools and the girl children
are the most affected. Keeping in view of the fact, the proponent proposes girl
child education programme in which the girls from weak financial background
will get financial help through the school in the project villages.
2. Distribution of Blankets & Clothes to homeless & poor people: The area
experiences harsh weather conditions and poor land less people are worst
affected by the adverse weather. The proponent Proposes to distribute the
blankets and clothes among the landless and poor people.
3. Night Shelters for homeless people: The proponent proposes to help the existing night shelters for homeless people and help to create the new one, to
accommodate the ever increasing population of the city.
Project Implementation Schedule:
4. Project Implementation Plan for 1st year to 7th year
Sr. No.
Activities Year 1
Year 2
Year 3
Year 4
Year 5
Year 6
Year 7
1 Girl Child Education (160 school girls)
a Floating the RFP, and selection of best implementation organization
b Selection & MoU with schools c Getting the list of girls
belonging financially weak household.
d Disbursement of Girl child scholarship @ Rs 5,000/- per year
e Monitoring and reporting 2 Night Shelters
a Floating the RFP, and selection of best implementation
Project Name Environment Clearance for Group Housing Project
EIA Project Proponent Sunrise Technobuild LLP
Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra
Marg Yojna, Rishikesh, Uttarakhand
Environment Consultant
Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-27
Sr. No.
Activities Year 1
Year 2
Year 3
Year 4
Year 5
Year 6
Year 7
organization
b MOU with existing and new service providers
c Release of CSR grant for night shelters
d Monitoring and reporting 3 Blankets & Clothes Distribution (1600 poor people)
a Floating the RFP, and selection of best implementation organization
b MOU with distribution partners c Distribution of clothes and
blankets to rural people @ Rs 500/-
d Monitoring and reporting ***********