RISK ASSESSMENT & DISASTER MANAGEMENT...

27
Project Name Environment Clearance for Group Housing Project EIA Project Proponent Sunrise Technobuild LLP Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra Marg Yojna, Rishikesh, Uttarakhand Environment Consultant Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-1 RISK ASSESSMENT & DISASTER MANAGEMENT PLAN 7.1 RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN Sunrise Technobuild LLP is developing a Group Housing Project at plot No. GH-1 in Awas Vikas Parishad Housing Colony, Veerbhadra Marg Yojna, Rishikesh. The project is spread over an area of approximately 3 acres. This is a residential project having three blocks A, B & C. Block A & C are residential Towers while block B is Villas. Maximum height of the buildings is approx. 29.5 metres. It also consists of a Commercial building and a Community Centre block. The salient features of the project include energy saving fixtures, sufficient aesthetic green cover and water conservation measures. The project involves a number of project specific activities on construction of high rise buildings such as installation of various types of structures and machineries. These activities include lifting and transportation of building materials at different levels, digging of pits, operation of concrete mixer, working near electrical circuit, which are required during construction of the project. Hence, such work puts workers at risk of burial, engulfment or falling from a height, risk of electrocution where the risk is particularly aggravated by the nature of the work or processes used or by the environment at the place of work or site. On completion of the project, the infrastructure created includes provision of lifts, DG set as power backup, laying of internal as well as external electrical cables, provision of pipeline for LPG uses (specially in kitchens), construction of internal roads etc, which pose risk of accident to the occupants . However, it is not always possible to totally eliminate such eventualities and random failures of equipment due to human errors or natural calamities like storms, cyclones, earthquake etc. It is thus necessary to carry out hazard identification and risk assessment for risk monitoring and to formulate its Control Measures like Risk response planning i.e. Disaster Management Plan / Onsite Emergency Plan for the project. An essential part of major hazard control is, therefore, to be concerned with mitigating the effects of such emergency situation and restoration of normalcy at the earliest by following Disaster Management Plan (DMP) for different type of Emergencies like Earthquake, LPG leakage, Fire in the building etc. The TOR for the project stipulates to submit details of a comprehensive Disaster Management Plan including emergency evacuation during natural and man-made disaster. In compliance of the above direction, a detailed Disaster Management Plan has been prepared for compliance by the project authorities.

Transcript of RISK ASSESSMENT & DISASTER MANAGEMENT...

Page 1: RISK ASSESSMENT & DISASTER MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/online/Risk... · 2018-08-01 · following Disaster Management Plan (DMP) for different type of

Project Name Environment Clearance for Group Housing Project

EIA Project Proponent Sunrise Technobuild LLP

Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra

Marg Yojna, Rishikesh, Uttarakhand

Environment Consultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-1

RISK ASSESSMENT & DISASTER MANAGEMENT PLAN

7.1 RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN

Sunrise Technobuild LLP is developing a Group Housing Project at plot No. GH-1 in Awas Vikas Parishad Housing Colony, Veerbhadra Marg Yojna, Rishikesh. The project is spread over an area of approximately 3 acres. This is a residential project having three blocks A, B & C. Block A & C are residential Towers while block B is Villas. Maximum height of the buildings is approx. 29.5 metres. It also consists of a Commercial building and a Community Centre block. The salient features of the project include energy saving fixtures, sufficient aesthetic green cover and water conservation measures. The project involves a number of project specific activities on construction of high rise buildings such as installation of various types of structures and machineries. These activities include lifting and transportation of building materials at different levels, digging of pits, operation of concrete mixer, working near electrical circuit, which are required during construction of the project. Hence, such work puts workers at risk of burial, engulfment or falling from a height, risk of electrocution where the risk is particularly aggravated by the nature of the work or processes used or by the environment at the place of work or site. On completion of the project, the infrastructure created includes provision of lifts, DG set as power backup, laying of internal as well as external electrical cables, provision of pipeline for LPG uses (specially in kitchens), construction of internal roads etc, which pose risk of accident to the occupants . However, it is not always possible to totally eliminate such eventualities and random failures of equipment due to human errors or natural calamities like storms, cyclones, earthquake etc. It is thus necessary to carry out hazard identification and risk assessment for risk monitoring and to formulate its Control Measures like Risk response planning i.e. Disaster Management Plan / Onsite Emergency Plan for the project. An essential part of major hazard control is, therefore, to be concerned with mitigating the effects of such emergency situation and restoration of normalcy at the earliest by following Disaster Management Plan (DMP) for different type of Emergencies like Earthquake, LPG leakage, Fire in the building etc. The TOR for the project stipulates to submit details of a comprehensive Disaster Management Plan including emergency evacuation during natural and man-made disaster. In compliance of the above direction, a detailed Disaster Management Plan has been prepared for compliance by the project authorities.

Page 2: RISK ASSESSMENT & DISASTER MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/online/Risk... · 2018-08-01 · following Disaster Management Plan (DMP) for different type of

Project Name Environment Clearance for Group Housing Project

EIA Project Proponent Sunrise Technobuild LLP

Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra

Marg Yojna, Rishikesh, Uttarakhand

Environment Consultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-2

7.1.0 RULES AND REGULATIONS ON SAFETY INVOLVING RISKS & HAZARDS

7.1.0.1 STATUTORY RULES AND REGULATIONS ON SAFETY, HEALTH AND

ENVIRONMENT

The responsibility of the management of any project is to comply with the provisions of various statutory rules and regulations on Safety, Health and Environment which are as follows: 1) Environment (Protection) Act, 1986 and Rules (as amended to date) made there

under including: (a) The Manufacture, Storage and Import of Hazardous Chemicals (MSIHC) Rules 1989

amended in 1994, 2000, 2008 and 2016; (b) Environment Impact Assessment Notification, 2006, as amended to date; (c) The Bio-Medical Waste (Management and Handling) Rules, 1998, as amended to date; (d) Hazardous and Other Wastes (Management & Trans-boundary Movement) Rules, 2016; (e) Solid Waste Management Rules, 2016; (f) Plastic Waste Management Rules, 2016; (g) Construction and Demolition Waste Management Rules, 2016; (h) E - Waste Management Rules, 2018; (i) The Public Liability Insurance (PLI) Act 1991, amended in 1992 and the Public

Liability Insurance Rules 1991, amended in 1993; (j) The Chemical Accidents (Emergency Planning, Preparedness & Response) rules, 1996; 2) Factory Act 1948 and the Factories (Amendment) Act 2014, as amended to date;

3) Petroleum Act 1934 and Petroleum Rules 1981 amended in 2002, as amended to date;

4) Gas Cylinder Rules 2004 and Static & Mobile Pressure Vessels (SPVM) (Unfired) Rules 1981 amended in 1993, as amended to date;

5) Explosives Act 1984 and Explosive Rules 1983, as amended to date; 6) The Electricity Act 2003 and Indian Electricity Rules 1956 as amended to date.

77..11..00..22 SSTTOORRAAGGEE && HHAANNDDLLIINNGG OOFF HHAAZZAARRDDOOUUSS MMAATTEERRIIAALLSS::

Both the hazardous & non hazardous materials generated within the industrial estates shall be temporarily accommodated in necessary units placed within the industrial estate in line with the safety, health and environmental standards. The size of these temporary units will depend on the quantity and the type of Hazardous

waste materials like asbestos, PCB, oils, fuels etc. Appropriate storage capacities are

proposed to be placed within the premises of the Group Housing Project as per the

Hazardous and Other Wastes (Management & Trans-boundary Movement) Rules 2016 (as

amended to date). Later, these materials will be disposed off at a centralized disposal

facility with utmost care following safety norms. For gas cylinders used / stored within

the premises of the GH Project, the Gas Cylinders Rules under the Explosives Act will be

Page 3: RISK ASSESSMENT & DISASTER MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/online/Risk... · 2018-08-01 · following Disaster Management Plan (DMP) for different type of

Project Name Environment Clearance for Group Housing Project

EIA Project Proponent Sunrise Technobuild LLP

Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra

Marg Yojna, Rishikesh, Uttarakhand

Environment Consultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-3

followed. Each unit in the GH Project is proposed to be facilitated with fire hydrant system

to handle fire hazards

7.1.0.3GUIDELINES FOR STORAGE OF PETROLEUM PRODUCTS

The Petroleum Rules 2002 dated 13th March 2002 stipulates the following criteria for storage and handling of Petroleum Products.

i) No license is required for storage, handling and transport of any such product (i.e. petroleum Class B ) if the total quantity in possession does not exceed 2500 litres in non-bulk (i.e. drums) or 1000 litres in a receptacle / tank (i.e. bulk).

ii) Application for renewal of petroleum license may be made to Chief Controller

of Explosive’s Office.

As this is a Group Housing Project, no bulk use / storage of petroleum products is envisaged in the project. Therefore, no petroleum license is required for this project.

7.1.0.4 OIL AND CHEMICAL PLANT LAYOUT AND SPACING – GAPS GUIDELINES

Global Asset Protection Services LLC (GAPS), USA and its affiliated organizations provide loss prevention surveys and other risk management, continuity and facility asset management services. Loss experience clearly shows that fires and explosions in congested areas of oil and chemical plants can result in excessive losses. Wherever explosion or fire hazards exist, proper plant layout and adequate spacing between hazards are essential to loss prevention and control. Layout relates to the relative position of equipment or units within a given site. Spacing pertains to minimum distance between units or equipments. Global Asset Protection Services (GAPS) layout and spacing recommendations are for the property loss prevention purposes only and are intended for existing and new oil and chemical facilities.

7.1.0. SAFETY CODES FOR BUILDING & FIRE FIGHTING SYSTEM

The Fire-fighting network followed by Emergency Response Mock Drills is essential part of

Risk Control Measures.

Construction of the group housing project has been done as per the provisions of National

Building Code 2016. The fire-fighting system has been designed considering the following

codes, manual and guidelines:

1) National Building Code of India (NBC) 2016;

2) Latest relevant NFPA codes, USA, in particular NFPA – 13, 14, 20 & 22;

3) IRI guidelines;

4) As per requirement of fire officer / local fire approving authorities; and

Page 4: RISK ASSESSMENT & DISASTER MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/online/Risk... · 2018-08-01 · following Disaster Management Plan (DMP) for different type of

Project Name Environment Clearance for Group Housing Project

EIA Project Proponent Sunrise Technobuild LLP

Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra

Marg Yojna, Rishikesh, Uttarakhand

Environment Consultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-4

5) As per Indian Standard Code for Fire Protection (IS Codes)

Following items are proposed for firefighting:

1) High Pressure Fire-Water Connections;

2) Firewater inlet and outlet connections have been provided to the water storage

tanks;

3) External main fire ring, having 150 mm diameter and hydrants @ 45 m3/s spacing

shall be provided. This external fire ring shall be separated from the Sprinkler Main

Systems;

4) All Flow Switches, Test Valves, Drain Pipes etc have been provided as per NFPA

guidelines on the sprinkler system;

5) All Pump installation and arrangements have been made in accordance with IRI

guidelines and NFPA-20;

6) All Pumps and accessories and electrical Controllers have been provided as per

UL/FM lists, tested, approved and certified;

7) By-pass arrangements have been provided (150 mm diameter nominal bore) with

NRV and Gate Valve and bulk Flow Meter on the discharge Header of each Pump to

check the duties of Pumps.

8) Storage Tanks have been provided in the basement for the supply of water for the

firefighting facility.

9) The Fire Extinguishers have been provided in conformance with Ozone Depleting

Substances (Regulation and Control) Rules 2000.

7.1.1RISK HAZARD AND ITS CONTROL MEASURES

On-Site and Off-Site emergency plans are in place to provide the necessary infrastructures

for control of risks and hazards so that the losses to personnel and property are minimum.

7.1.1.0 ON - SITE EMERGENCY PLAN

The on- site management plan will be circulated to all concerned member of emergency

team. It is essential that all concerned person are familiar with the overall on- site

emergency plan and their respective roles and responsibilities during emergency. They

should also participate regularly in the mock drills to keep in a state of perpetual

preparedness at all times to meet any emergency.

Page 5: RISK ASSESSMENT & DISASTER MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/online/Risk... · 2018-08-01 · following Disaster Management Plan (DMP) for different type of

Project Name Environment Clearance for Group Housing Project

EIA Project Proponent Sunrise Technobuild LLP

Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra

Marg Yojna, Rishikesh, Uttarakhand

Environment Consultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-5

77.1.1.0.1 ACTION PLAN OF ON-SITE EMERGENCY PLAN

The main objective of the plan is to take immediate actions to meet any emergency

situation for speedy and efficient rescue and relief operations. The main steps in an onsite

emergency plan are described below:

1) Cordon and isolate the affected area for smooth rescue operation.

2) Rescue and treat casualties and safeguards the rest.

3) Minimize damage to life, property and surroundings.

4) Contain and ultimately bring the situation under control.

5) Secure and safe rehabilitation of the affected area.

6) Identify any casualty and provide for the needs of the relatives.

7) Provide necessary information to statutory agencies.

8) Provide authoritative information to the news media.

9) Ward off unsocial elements and prying onlookers.

10) Counter rumor mongering and panic by relevant accurate information.

77..11..11..00..22 SSCCOOPPEE OOFF OONN--SSIITTEE EEMMEERRGGEENNCCYY PPLLAANN

The plan covers information regarding the properties of the group housing project, type of

disasters and disaster/accident prone zones. The important elements considered in this

plan are:

1) Statutory requirement

2) Emergency organization

3) Roles and responsibility

4) Communications during emergency

5) Emergency facilities

6) Important information

The primary purpose of the On- Site emergency plan is to control and contain the incident

and so to prevent it from spreading. To cover eventuality in the plan and the successful

handling of the emergency will depend on appropriate action and decision being taken on

the spot.

It is proposed to plan and construct the buildings following all safety norms. However, it is

not always possible to totally eliminate such eventualities and random failures of

equipment or human errors. An essential part of major hazard control has therefore, to be

concerned with mitigating the effects of such emergency and restoration of normalcy at the

earliest. A detailed table showing activities during construction and operation phase along

with mitigation measures are given in Table 1.1

Page 6: RISK ASSESSMENT & DISASTER MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/online/Risk... · 2018-08-01 · following Disaster Management Plan (DMP) for different type of

Project Name Environment Clearance for Group Housing Project

EIA Project Proponent Sunrise Technobuild LLP

Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra

Marg Yojna, Rishikesh, Uttarakhand

Environment Consultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-6

Table 1.1: Activities during construction and operation along with mitigation

measures

HAZARDS ASSOCIATED WITH ACTIVITIES

(During Construction & Operation)

CONTROL / MITIGATION MEASURES

Manual Handling:

- Strains and sprains incorrect lifting - too

heavy loads -twisting - bending - repetitive

movement - body vibration.

Exercise/warm up - get help when needed -

control loads - rest breaks/no exhaustion -

no rapid movement/twisting/

bending/repetitive movement - good

housekeeping.

Falls - Slips – Trips:

Falls on same level - falls to surfaces below -

poor housekeeping - slippery surfaces

Uneven surfaces -poor access to work areas

climbing on and off plant -unloading

materials into excavations wind - falling

objects.

Housekeeping - tidy workplace - guardrails,

handholds, harnesses, hole cover, hoarding,

no slippery floors/trip hazards - clear/ safe

access to work areas - ingress from work

areas - dust/water controlled - PPE.

Fire :

Flammable liquids/Gases like LPG, Diesel

Storage area and combustible building

materials - poor housekeeping - grinding

sparks - open flames, absence of Fire

hydrant net work.

Combustible/flammable materials properly

stored/used - good housekeeping - fire

extinguishers made available & Fire hydrant

Network with reserve Fire water (As per

NFPA Code) - Emergency Plan in case of

Fire or collapse of structure.

Absence of Personal Protective

Equipment (PPE):

Lack of adequate footwear - head protection

–hearing/eye protection - respiratory

protection - gloves -goggles.

Head/face - footwear – hearing/eye - skin –

respiratory protection provided - training -

maintenance.

Defective or wrong Hand Tools :

Wrong tool - defective tool - struck by flying

debris - caught in or on - missing guards -

carbon monoxide - strains and sprains -

dust.

Right tool for the job - used properly - good

condition/ maintenance guards - isolation –

eye/face protection - flying debris

controlled.

Electricity:

Electrocution - overhead/underground

services- any leads damaged or poorly

insulated - temporary repairs -no testing

and tagging - circuits overloaded – non-use

of protective devices.

Leads good condition and earthed - no

temporary repairs - no exposed wires -

good insulation - no overloading - use of

protective devices - testing and tagging -no

overhead/ underground services

Page 7: RISK ASSESSMENT & DISASTER MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/online/Risk... · 2018-08-01 · following Disaster Management Plan (DMP) for different type of

Project Name Environment Clearance for Group Housing Project

EIA Project Proponent Sunrise Technobuild LLP

Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra

Marg Yojna, Rishikesh, Uttarakhand

Environment Consultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-7

Scaffolding:

Poor foundation - lack of ladder access

insufficient planking - lack of guardrails and

toe boards - insufficient ties or other means

- all scaffolds incorrectly braced or

stabilized to prevent overturning.

All scaffolds correctly braced and stabilized

- 3:1 height to base ratio - firm foundation,

plumb and level - ladder access provided

and used - proper platform (3 planks/675

mm) - planks secured - guardrails and toe

boards – 900mm to 1100mm high, within

200mm of working face, mid-rail.

Ladders:

Carrying loads - not secured against

dislodgement - defective ladders - not

sufficient length - wrong positions -

incorrectly placed (angles, in access ways,

vehicle movements.

Secured against movement or footed -

ladders in good condition - regularly

inspected - extend 1m above platform - 4:1

angle - out of access ways, vehicle

movements - climbing - no carrying loads -

3 points of contact - no higher than 3rd step

down - use for access only, not working

platforms.

Excavations:

Trench collapse - material falling in

undetected underground services - falls -

hazardous atmosphere struck by traffic and

mobile plant.

Soil stability known - no water

accumulation - existing services known -

material 600mm from edge - clear of

suspended loads – hardhats/PPE - ladders -

public protection – atmospheric testing -

traffic controls - Emergency Plan.

Gas Cutting and Welding:

Fire - welding flash, burns, fumes,

electrocution in wet conditions - flashback

in oxygen set, leaking cylinders, acetylene

cylinders lying down - poorly maintained

leads.

Welding flash and burns controlled with

PPE and shields -fumes controlled with

ventilation and PPE

(in good condition and properly

positioned),Gas cylinders be kept upright &

secured position (properly tied) -

combustible materials to be kept at secured

place to avoid fire and Fire Extinguishers to

be kept in fire prone area with training to

people for its use.

Noise:

known noise levels over 85 decibels

Levels below 85 decibels - proper

protection.

Falling Materials:

Fall during carrying/Lifting materials-

dislodged tools and materials from

overhead work areas.

Materials to be secured – kept away from

edge - toe boards –Use of hard hats.

Cranes& Lifts:

Display of carrying capacity i.e. load (No. of

person), incorrectly slung, defective lifting

Periodic testing by competent authority -

correctly slung/secured loads, lifting

Page 8: RISK ASSESSMENT & DISASTER MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/online/Risk... · 2018-08-01 · following Disaster Management Plan (DMP) for different type of

Project Name Environment Clearance for Group Housing Project

EIA Project Proponent Sunrise Technobuild LLP

Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra

Marg Yojna, Rishikesh, Uttarakhand

Environment Consultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-8

equipment, unsecured loads, craning in

close proximity to building people and plant

- falls - falling materials.

equipment in good conditions - use of

proper hand signals - falls while unloading

controlled.

Visitors Presence at the Site:

Falls - struck by - dropped materials -

loading accidents -insufficient hoarding or

fencing - pedestrian access past site -

mechanical plant movement on and off site.

Sufficient hoarding - fencing and barricades

- safe pedestrian access past site traffic

management for loading and delivery -

construction separated from occupied areas

of projects.

77..11..11..00..33OOBBJJEECCTTIIVVEE OOFF OONN--SSIITTEE EEMMEERRGGEENNCCYY PPLLAANN

Risk analysis and risk assessment should provide details on risk posed to people who

work inside or live near hazardous facilities, and to aid in preparing effective emergency

response plans by delineating a disaster management plan (DMP) to handle on-site and

off-site emergencies. Hence, risk analysis and risk assessment is an invaluable method for

making informed risk-specific for any group housing project is complex and needs

extensive study that involves process understanding, hazard identification, consequences

probability data, vulnerability models / data, local weather and terrain conditions and

local population data. Risk analysis and risk assessment will be carried out to serve the

following objectives:

1) Identification of safety areas

2) Identification of hazard sources

3) Generation of accidental release scenarios for escape of hazardous materials from the

facility

4) Identification of vulnerable units with recourse to hazard indices

5) Assessment of risk on the basis of above evaluation against the risk acceptability

criteria relevant to the situation

6) Suggest risk mitigation measures based on engineering judgment, reliability and risk

analysis approaches

7) Delineation / up-gradation of DMP

8) Safety reports: with external safety report / occupational safety report

The risk assessment report may cover the following in terms of the extent of damage with

analysis and delineation of risk mitigations measures with an approach to DMP.

1) Hazard Identification- identification of hazardous activities, hazardous materials, past

accident records etc.

2) Hazard quantification- consequence analysis to assess the impacts

Page 9: RISK ASSESSMENT & DISASTER MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/online/Risk... · 2018-08-01 · following Disaster Management Plan (DMP) for different type of

Project Name Environment Clearance for Group Housing Project

EIA Project Proponent Sunrise Technobuild LLP

Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra

Marg Yojna, Rishikesh, Uttarakhand

Environment Consultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-9

3) Risk Presentation

4) Risk Mitigation Measures

5) Disaster Management Plans (DMP)

7.1.1.1OFF - SITE EMERGENCY PLAN

A major emergency in any situation is one, which has the potential to cause serious injury

or loss of life, which may cause extensive damage to the structure in vicinity and

environment and could result in serious disruption to normal operation both inside and

outside the industry premises. Depending on the magnitude the emergency, service of the

outside agencies may also be envisaged.

The management has to take effective steps to assess, minimize and wherever feasible

eliminate the risk to large extent. Accident may still occur and it is necessary to be fully

prepared to tackle all such emergencies if and when they occur.

It is likely that the consequences of such emergencies will be confined to the units

concerned or may affect outside. If the consequences are confined within the plant

boundary, it will be controlled by Chief Emergency Controller. The most widely used

techniques in practice will be based on experience accumulated over many years and

safety audits.

77..11..11..22CCOOMMPPEENNSSAATTIIOONN TTOO TTHHEE VVIICCTTIIMMSS

The project authorities shall form an investigation team for an accident with the Safety

Officer and other members of the group housing project.

The Public Liability Insurance (PLI) Act, 1991, provides for the owner handling hazardous

substances to pay specified amount of the money to the victims as relief by taking

insurance policy for this purpose.

7.1.2MODELS FOR IMPACT PREDICTION & RISK ASSESSMENT

Hazards Identification, Hazards Evaluation and Hazards Quantification are done as per

the prediction of the Models used. These may be used for impact prediction and risk

assessment.

Page 10: RISK ASSESSMENT & DISASTER MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/online/Risk... · 2018-08-01 · following Disaster Management Plan (DMP) for different type of

Project Name Environment Clearance for Group Housing Project

EIA Project Proponent Sunrise Technobuild LLP

Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra

Marg Yojna, Rishikesh, Uttarakhand

Environment Consultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-10

FFIIGGUURREE 11..11:: RRIISSKK AASSSSEESSSSMMEENNTT--CCOONNCCEEPPTTUUAALL FFRRAAMMEEWWOORRKK

Table 1.2: Choice of Models for Impact Predictions: Risk Assessment

Name Application Remarks

EFFECT

WHAZAN

Consequence analysis for

Visualization of accidental

chemical release scenarios &

its consequence

Consequence of analysis for

visualization of accidental

chemical release scenarios &

its consequence

Heat load, press wave and

toxic release exposure

neutral gas dispersion

DEGADIS Consequence of analysis for

visualization of accidental

chemical release scenarios &

its consequence

Dense gas dispersion

HAZOP & fault

tree assessment

For estimating top event

probability

Failure frequency data is

required

Pathways

reliability and

protective

system hazard

analysis

For estimating reliability of

equipments and protective

systems

Markov Models

Hazard Evaluation

Hazard Quantification

Hazard Identification

Page 11: RISK ASSESSMENT & DISASTER MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/online/Risk... · 2018-08-01 · following Disaster Management Plan (DMP) for different type of

Project Name Environment Clearance for Group Housing Project

EIA Project Proponent Sunrise Technobuild LLP

Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra

Marg Yojna, Rishikesh, Uttarakhand

Environment Consultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-11

Vulnerability

Exposure

models

Estimation of population

exposure

Uses probity equation for

population exposure

F-X and F-N

curves

Individual/Societal risks Graphical Representation

7.1.3 HAZARD IDENTIFICATION

Hazard is the characteristic of any system or process which has the potential for accident.

Identification of hazards, in the presence of any hazardous waste generating activities

within the group housing project is of primary significance in the analysis, quantification

and cost effective control of accidents involving construction.

The typical methods for hazard identification employed are:

1) Identification of major hazardous units based on Manufacture, Storage and Import of

Hazardous Chemical Rules, 1989 of Government Of India (amended in 2000)

2) Identification of hazardous wastes based on Hazardous Waste (Management,

Handling and Trans-boundary Movement) Rules, 2008, and its amendments.

3) Hazardous substances may be classified into three main classes’ namely flammable

substances, unstable substances and toxic substances.

7.1.4 HAZARD ASSESSMENT & EVALUATION

A preliminary hazard analysis shall be carried out to identify the major hazards

associated with storages in the group housing project. This is followed by consequence

analysis to quantify these hazards. Following are the vulnerable zones of accident:

7.1.4.0 Frequent Causes of Accidents

1) Fire and explosion: explosives, flammable materials

2) Being struck by falling objects

3) Caught in or compressed

4) Snapping of cables, ropes, chains, slings

5) Handling heavy objects

6) Electricity

7) Poor illumination

8) Falls from height inside industrial units or on the ground

9) Struck by moving objects

10) Slipping on wet surfaces

11) Sharp objects

12) Oxygen deficiency in confined spaces

Page 12: RISK ASSESSMENT & DISASTER MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/online/Risk... · 2018-08-01 · following Disaster Management Plan (DMP) for different type of

Project Name Environment Clearance for Group Housing Project

EIA Project Proponent Sunrise Technobuild LLP

Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra

Marg Yojna, Rishikesh, Uttarakhand

Environment Consultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-12

7.1.4. Hazardous Substances and Wastes

1) Heavy and toxic metals (lead, mercury, cadmium, copper, zinc, etc.)

2) Organo metallic substances (tributyltin, etc.)

3) Lack of hazard communication (storage, labelling, material safety data sheets)

4) Batteries, fire-fighting liquids

5) Pcbs and PVC

6) Welding fumes

7) Volatile organic compounds (solvents)

8) Inhalation in confined and enclosed spaces

7.1.5 DISASTER MANAGEMENT PLAN

Disasters may be Manmade Disasters (such as Fires, Terrorism, and Stampede etc) or

Natural Disasters (such as earth quake, Tsunami, Flood & Cloud Burst etc). Various

criteria for the Natural Disasters and Manmade Disasters shall be considered.

For Manmade Disasters such as Fires, provisions of the National Building Code of India

(NBCI) have been considered and necessary provisions have been made.

For natural disaster management, there are the Natural Disaster Management Authority

(NDMA) at the Centre, Government of India and the State Disaster Management Authority

(SDMA) at the State level. For natural disasters, guidelines shall be followed as given in

the Vulnerability Atlas of India (Earth quake, windstorm, and flood hazard Maps and

Damage Risk Housing) prepared by the Building Materials and Technology Promotion

Council (BMTPC), Ministry of Housing & Urban Poverty Alleviation (MHUPA),

Government of India.

For Natural Disasters such as earth quakes, Earth Quake Zoning Maps have been

considered and earth quake resistant building structures and retrofitting of old buildings

and structures have been considered as applicable to the place where the project is

located. Flood & Cloud Burst data obtained from Indian Meteorological Department (IMD)

have been considered for structural design of the project.

Emergency planning is an integral part of the overall loss control program and is

essential for any well run organization. This is important for effective managem ent

of an accident /incident to minimize losses to people and property, both in and around

the facility. The format and contents of the Emergency Response Plan (ERP)/On-Site Disaster

Management Plan (DMP) has been developed taking into consideration the regulatory

guidelines, other applicable documents and accepted good construction practices

formulated as a result of lessons learned in actual emergencies requiring extensive

emergency response.

Page 13: RISK ASSESSMENT & DISASTER MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/online/Risk... · 2018-08-01 · following Disaster Management Plan (DMP) for different type of

Project Name Environment Clearance for Group Housing Project

EIA Project Proponent Sunrise Technobuild LLP

Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra

Marg Yojna, Rishikesh, Uttarakhand

Environment Consultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-13

Disaster can be defined as an “occurrence of undesired events of such magnitude so as

to create a situation in which normal pattern of life within the group housing project

is suddenly disrupted, adversely affecting not only the personnel and property within

the group housing project but also in its vicinity.”

As per the Manufacture, Storage and Import of Hazardous Chemical (Amendment)

Rules, 2000, “major accident” means–an incident involving loss of life inside or outside

the group housing project, or ten or more injuries inside and/or one or more injuries

outside or release of toxic chemicals or explosion or fire or spillage of hazardous

chemicals resulting in on-site or off-site emergencies or damage to equipment leading

to stoppage of construction or adverse affects to the environment;

A Disaster Management Plan (DMP) has been prepared considering the On-Site and Off-

Site disasters that can occur during construction and operational phases of the Project.

A disaster is a catastrophic situation in which suddenly, people are plunged into

helplessness and suffering and, as a result, need protection, clothing, shelter, medical and

social care and other necessities of life. The Disaster Management Plan is aimed to ensure

safety of life, protection of Environment, protection of installation, restoration of

production and salvage operations in this same order of priorities. For effective

implementation of the Disaster Management Plan, it shall be widely circulated and a

personnel training is to be provided through rehearsals/drills. To tackle the

consequences of a major emergency inside the project or immediate vicinity of the

project, a Disaster Management Plan (DMP) has been formulated and this planned

emergency document is called "Disaster Management Plan".

7.1.5.0 OBJECTIVE OF THE DISASTER MANAGEMENT PLAN

The objective of the Disaster Management Plan is to make use of the combined resources

of the group housing project and the outside services to achieve the following:

Effect the rescue and medical treatment of casualties.

Safeguard other people;

Minimize damage to property and the environment;

Initially contain and ultimately bring the incident under control;

Identify any dead;

Provide for the needs of relatives;

Provide authoritative information to the news media;

Secure the safe rehabilitation of affected area;

Preserve relevant records and equipment for the subsequent inquiry into the

cause and circumstances of the Emergency.

Page 14: RISK ASSESSMENT & DISASTER MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/online/Risk... · 2018-08-01 · following Disaster Management Plan (DMP) for different type of

Project Name Environment Clearance for Group Housing Project

EIA Project Proponent Sunrise Technobuild LLP

Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra

Marg Yojna, Rishikesh, Uttarakhand

Environment Consultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-14

In effect, it is to optimize operational efficiency to rescue rehabilitation and render

medical help and to restore normalcy. Disaster Management Plan shall include Emergency

Preparedness Plan, Emergency Response Team, Emergency Communication, Emergency

Responsibilities, and Emergency Facilities and Emergency Actions.

7.1.5.1 PROVISION OF ESSENTIAL SERVICES

7.1.5.1.1 STORM WATER DRAINAGE

A detailed “Storm Water Management” has been developed. This will incorporate best management practices which will include following:

Regular inspection and cleaning of storm drains. Cover waste storage areas. Avoid application of pesticides and herbicides before wet season. Secondary containment and dykes in fuel/oil storage facilities Conducting routine inspections to ensure cleanliness Preparation of spill response plans, particularly for fuel and oil storage areas. Provision of slit traps in storm water drains Surface Water from parking area will be discharged to drain.

7.1.5.1.2 FIRE FIGHTING SYSTEM

A state of the art fire fighting system is proposed for the project to prevent and control

fire outbreaks. The fire fighting system will consist of portable Fire Extinguishers, Hose

Reel, Wet Riser, Yard Hydrant, automatic Sprinkler System, and manual Fire Alarm

System. The group housing project will also be provided with automatic Fire Detection

and Alarm System. The copy of Fire NOC is attached as Annexure VII.

1) Pumps shall be protected with Sprinkler as per NFPA 20 (refer to NFPA 13 for

design)

2) DG sets need to be protected with mist as per the applicable regulation (refer to

NFPA 750 for design).

The fire and safety considerations will be as per the applicable National Building Code

2016. Important components are mentioned below.

1) Provision of water Sprinklers

2) Provision of Hose Reels, external Hydrants and Wet Risers

3) Provision of fire fighting underground Water Storage Tank,

4) Provision of overhead Water Storage Tank on each buildings

5) There is a provision of Fire Fighting Pumps.

6) Adequate Fire Extinguishers shall be available for emergency situations

7) HT and LT Panels will be protected with manually operated CO2Protection System.

Page 15: RISK ASSESSMENT & DISASTER MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/online/Risk... · 2018-08-01 · following Disaster Management Plan (DMP) for different type of

Project Name Environment Clearance for Group Housing Project

EIA Project Proponent Sunrise Technobuild LLP

Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra

Marg Yojna, Rishikesh, Uttarakhand

Environment Consultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-15

8) Automatic Sprinklers will be installed in the entire building

9) Portable Fire Extinguishers shall be provided at strategic locations

10) Optical type smoke detectors shall be used in most areas

11) Automatic fire detection system i.e. Smoke/ Heat Detection System shall be

provided in the buildings at appropriate places. The system will be connected to

the Fire Alarm System

12) Rate of rise heat detectors shall be planned for all potentially smoky areas and in

the basement.

HSD and other petroleum products at site shall be stored at earmarked area having

impervious floor and adequate fire fighting arrangements. Hazardous wastes as waste oil

shall be collected and stored and periodically sold off to MoEF&CC/ SPCB authorized

Recyclers. Buy back arrangement shall be made with the authorized dealer of Lead Acid

Storage Batteries used in the DG Sets.

7.1.5.2 EMERGENCY RESPONSE PLAN

The overall objective of an Emergency Response Plan (ERP) is to make use of the

combined resources at the group housing project and outside services to achieve the

following:

1) To localize the emergency and if possible eliminate it;

2) To minimize the effects of the accident on people and property;

3) To Effect the rescue and medical treatment of casualties;

4) Safeguard other people;

5) Evacuate people to safe areas;

6) Informing and collaborating with statutory authorities;

7) Initially contain and ultimately bring the incident under control;

8) Preserve relevant records and equipment for the subsequent enquiry into the

cause and circumstances of the emergency;

9) Investigating and taking steps to prevent reoccurrence

The ERP is therefore related to identification of sources from which hazards can arise and

the maximum credible loss scenario that can take place in the concerned area. The plan

takes into account the maximum credible loss scenario - actions that can successfully

mitigate the effects of losses/ emergency need to be well planned so that they would

require less effort and resources to control and terminate emergencies.

Main hazards identified for the project include hazards pertaining to fires in buildings and

fire in diesel storage areas, earthquake and LPG leakage and an ERP pertaining to these is

described in the following section.

Page 16: RISK ASSESSMENT & DISASTER MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/online/Risk... · 2018-08-01 · following Disaster Management Plan (DMP) for different type of

Project Name Environment Clearance for Group Housing Project

EIA Project Proponent Sunrise Technobuild LLP

Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra

Marg Yojna, Rishikesh, Uttarakhand

Environment Consultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-16

77..11..55..33 OONN--SSIITTEE DDIISSAASSTTEERR MMAANNAAGGEEMMEENNTT PPLLAANN

The main objective of the plan is to take immediate actions to meet any emergency

situation for speedy and efficient rescue and relief operations. The main steps in an onsite

emergency plan are described below:

1) Cordon and isolate the affected area for smooth rescue operation.

2) Rescue and treat casualties and safeguards the rest.

3) Minimize damage to life, property and surroundings.

4) Contain and ultimately bring the situation under control.

5) Secure and safe rehabilitation of the affected area.

6) Identify any casualty and provide for the needs of the relatives.

7) Provide necessary information to statutory agencies.

8) Provide authoritative information to the news media.

9) Ward off unsocial elements and prying onlookers.

10) Counter rumor mongering and panic by relevant accurate information.

The parameters considered are given as follows:

1) To constitute Disaster Management Committee under a senior officer not below the

rank of General Manager.

2) To identify potential hazards areas in the layout map of group housing project

3) To use model to predict hazards impact in the surrounding areas in form of pool-fire

or gas leakage.

4) To predict degree of burns and distance of the risk zone by using model.

5) To evacuate the area within risk zone.

6) To localize the emergency and if possible eliminate it.

7) To minimize the effects of accidents on people and property.

8) To take remedial measures in the quickest possible time to contain the incident and

control it with minimum damage.

9) To mobilize the internal resource and utilize them in the most effective way.

10) To get help from the local community and government official to supplement internal

manpower and resources.

11) To minimize the damage in other sections.

12) To keep the required emergency equipment in stock at right places and ensure that

they are in working condition.

13) To keep the concerned personnel fully trained in the use of emergency equipment.

Page 17: RISK ASSESSMENT & DISASTER MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/online/Risk... · 2018-08-01 · following Disaster Management Plan (DMP) for different type of

Project Name Environment Clearance for Group Housing Project

EIA Project Proponent Sunrise Technobuild LLP

Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra

Marg Yojna, Rishikesh, Uttarakhand

Environment Consultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-17

14) To give immediate warning to the surrounding localities in case of emergency

situation arising.

15) To mobilize transport and medical treatment of the injured.

16) To educate the public in the surrounding villages regarding hazards.

17) To arrange treatment of causalities.

18) To safe guard the people.

19) To identify the causalities and communicate to persons known to them.

20) To render necessary help to the concerned.

21) To rehabilitate the area affected.

22) To provide information to media and government agencies.

77..11..55..44OONN -- SSIITTEE EEMMEERRGGEENNCCYY PPLLAANN

Identification of Responsibilities: The on-site disaster management plan shall identify

the Chief Incident Controller (CIC) who shall be the Chief of the Project (i.e. The Project In-

Charge) and the support team to Work Incident Controller (WIC) and Designated Key

Personnel of emergency control centre. The plan also specifies responsibilities of these

personnel in case of an emergency and draws an action plan to be followed. Chief Incident

Controller and Works Incident Controller (WIC) shall be assisted by two support teams as

follows.

Table 1.3: Details of Incident Controller

Support team to Chief Incident Controller

(CIC)

Consisting of Heads of Personnel, Materials and Finance Division:

To function in consultation with CIC for the following

Contacting statutory authorities.

Arranging for relievers and catering facilities

Giving information to media.

Contacting media centers and nursing homes

Providing all other support, as necessary.

Arranging for urgently required materials through

Cash purchase or whatever means.

Support team to Work Incident Controller (WIC)

Consisting of Senior Supervisor and Works Manager and any more persons depending upon the need to assist the WIC in manning communication and passing Instruction to the team. One steno secretary shall also be available with WIC for recording all information coming in and instruction going out.

Page 18: RISK ASSESSMENT & DISASTER MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/online/Risk... · 2018-08-01 · following Disaster Management Plan (DMP) for different type of

Project Name Environment Clearance for Group Housing Project

EIA Project Proponent Sunrise Technobuild LLP

Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra

Marg Yojna, Rishikesh, Uttarakhand

Environment Consultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-18

77..11..55..55OOFFFF -- SSIITTEE DDIISSAASSTTEERR MMAANNAAGGEEMMEENNTT PPLLAANN

Incidents having off-site implications can be:

1) Natural calamities like earthquake, cyclone, landslide etc.;

2) Chlorine and other Toxic Gas Leaks;

3) Major Fire involving combustible materials like oil and Gas spreading from other

nearby facilities or installations.

4) Air raids / Crashing of aircraft or flying objects. Incidents, which could also lead

to a disaster;

5) Agitation / forced entry by external group of people;

6) Sabotage.

In an extremely rare event of massive disaster which will have potential to affect areas outside the group housing project premises, needs to be informed to the District Authorities responsible for the preparation and implementation of Offsite Disaster Management Plan. The measures will include - Allocation of duties among the Project Fire Brigade, Police and Auxiliary Force.

An important aspect of the disaster is its unforeseen nature. Thus by definition, a disaster is impossible to control completely. However, occurrence of events which lead to a disaster may be minimized through proper technology, engineering practices and adaptation of available Disaster Management Practices.

Under the Environmental (Protection) Act, 1986, the responsibility of preparation of Off-Site Emergency Plan lies with the State Government. The Collector, Deputy Collector by virtue of their occupation is normally nominated by the concerned State government to plan Off-Site Emergency Plan.

The District Collector or his nominated representative would be the Team Leader of the planning team, who shall conduct the planning task in a systematic manner. The members of the Planning Team for Off-Site Emergencies are Collector, Deputy Collector, District Authorities In-Charge of Fire Services and Police, members drawn from Medical Services, Factory Inspectorate, Pollution Control Board and Industries & Transport Departments. In addition to these members, there are Co-opted Members also from the district authorities concerned, Civil Defense, Publicity Department, Municipal Corporation, and non-officials such as representatives (MPs, MLAs, Voluntary Organizations, NGOs etc).

7.1.5.6ONSITE AND OFFSITE EMERGENCY RESPONSE PLAN

To take control of any mishaps, Disaster Management Plan (DMP) has been formulated for

various areas. All the above mentioned instructions can lead to less risk but can't

eradicate the possibility of occurrence of any mishap. Onsite and Offsite Emergency

Response Plans have been formulated and key points of the same are as follows:

1) First Aid at site, Safety Officer and a Doctor must be available to give First Aid at the

site and proper record for the same must be maintained at the site.

Page 19: RISK ASSESSMENT & DISASTER MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/online/Risk... · 2018-08-01 · following Disaster Management Plan (DMP) for different type of

Project Name Environment Clearance for Group Housing Project

EIA Project Proponent Sunrise Technobuild LLP

Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra

Marg Yojna, Rishikesh, Uttarakhand

Environment Consultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-19

2) Availability of Ambulance at the site for emergency moving of the patients from site to

the hospital.

3) Emergency numbers of nearest Hospital, Fire Brigade Office and Police Station must be

placed at the site.

4) Alarm must be blown in case of any hazard.

5) All the workers must be aware of the Assembly Point and must reach there in case of

any evacuation to be made from the site.

6) The Site Office shall serve as Emergency Control Room (Centre) in case of emergency.

7.1.5.7EMERGENCY STRUCTURE AND RESPONSIBILITY

The emergency preparedness organizational structure should consist of the following

persons:

1) Site Main Controller --The Project Manager shall be named as the site main

controller

2) Incident Controller – The Site Supervisor shall act as incident controller in case of

emergency.

3) Manager Safety or Fire & Safety shall be the Coordinator.

4) Security in Charge shall be in the Coordination Team.

5) Rescue Team consisting of Operators and Site Employees specially trained in safety

and/or first aid shall be formed.

7.1.5.7.0 ROLE OF SITE MAIN CONTROLLER

1) Site Main Controller shall relieve the Incident Controller of the responsibilities of

overall emergency control as soon as he arrives at the site and takes stock of the

situation. He will position himself in the Emergency Control Centre and shall

thereafter give directions to the emergency Team from here.

2) Ensures that the medical aid is promptly provided to the causalities and that their

relatives are informed.

3) Organizes evacuation and transportation of personnel from the Assembly Points to

a safe location outside.

4) If external help is needed, shall coordinate with outside emergency services like

Fire Brigade of the nearest town, Ambulance Centre etc.

5) Ensures that affected personnel are transported to external medical centers to

keep constant liaison with these medical centers through the Medical Officer

during the course of the emergency.

6) Keeps concerned Government Agencies informed of the emergency and if

necessary arranges information to the outside residents through police.

7) Decides to call off the emergency when everything is OK.

Page 20: RISK ASSESSMENT & DISASTER MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/online/Risk... · 2018-08-01 · following Disaster Management Plan (DMP) for different type of

Project Name Environment Clearance for Group Housing Project

EIA Project Proponent Sunrise Technobuild LLP

Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra

Marg Yojna, Rishikesh, Uttarakhand

Environment Consultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-20

7.1.5.7.1 ROLE OF INCIDENT CONTROLLER

1) Incident Controller on reaching the site of the incident relieves the In-Charge of the

responsibilities of directing the Emergency Operations and assumes total control of

emergency operations in the affected area.

2) Determines the adequacy of the emergency services.

3) Directs the Emergency Operation from the incident site to localize emergency,

keeping in mind the priorities for safety of personnel, least damage to the property

and environment thereby minimize loss of materials.

4) Provides the necessary information and advises the Fire and Security Personnel

and Local Fire Services as and when they are called.

5) Continuously reviews the situation with the site Main Controller.

7.1.5.7.2ROLE OF MANAGER (SAFETY)/EXECUTIVE (FIRE AND SAFETY)

1) Proceeds to the Emergency Control Centre, establishes contact with Firefighting

men and Incident Controller and supplements efforts made in the fire fighting in

case of fire and other such emergencies involving people.

2) Assist nurse in providing First Aid to those who are injured.

3) Mobilizes Personal Protective Equipment (PPE) and safety appliances and assists

in using them to the personnel handling the emergency.

4) Collects and preserves evidences to facilitate future inquiry.

7.1.5.7.3 ROLE OF SECURITY IN-CHARGE

1) Assumes charge of all external communications in consultation with the Site Main

Controller.

2) Takes charge of the EPABX (Electronic Private Automatic Branch Exchange Board /

Box), if available and deputes a trained person (e.g. Security Guard) to man the

Board when regular Telephone Operator is off duty and thereby restrict the

unnecessary calls.

3) Assumes total control of the storage facility under the direction of the Site Main

Controller.

4) Controls traffic movement, removes Truck and Tanker Drivers, if any, gathered at

the Site Gate and prevents entry of all non-essential personnel.

5) Cordons off the Incident Site and keeps the site cleared off the observers gathered

at the place of the incident.

7.1.5.7.4 TRAINED FIRST AIDER

1) First Aider or the Team shall rush to Emergency Control Point and gets the

feedback from the Site Controller about the emergency.

Page 21: RISK ASSESSMENT & DISASTER MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/online/Risk... · 2018-08-01 · following Disaster Management Plan (DMP) for different type of

Project Name Environment Clearance for Group Housing Project

EIA Project Proponent Sunrise Technobuild LLP

Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra

Marg Yojna, Rishikesh, Uttarakhand

Environment Consultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-21

2) As per the instruction, they must rush to the area of emergency and assess the

situation.

3) Approach emergency site quickly with the First Aid Box Kit and other essentials.

4) Diagnoses the situation and decides whether the affected persons shall be moved

to the safe area.

5) Moves the injured personnel to the safe place and assists in offering the First Aid as

required by the situation.

6) Follows instructions from the Incident Controller.

7) Moves / Transports the causalities to the Ambulance / near to the Medical Centre

for necessary medical assistance.

7.1.5.8.0 RESPONSE IN CASE OF DISASTERS

The response procedure for earthquake, LPG leakage, outbreak of fire etc has been

discussed in detail as given below.

7.1.5.8.1RESPONSE IN CASE OF EARTHQUAKE

7.1.5.8.1.1 RESPONSE PROCEDURES FOR OCCUPANTS

7.1.5.8.1.1.1 IF INDOORS

Take cover under a piece of heavy furniture or against an inside wall and hold on.

Stay inside: The most dangerous thing to do during the shaking of an earthquake

is to try to leave the building in an effort to avoid the falling of probable object.

77.1.5.8.1.1.2 OUTDOORS

Move into the open, away from buildings, streetlights, and utility wires. Once in the open,

stay there until the shaking stops.

77.1.5.8.1.1.3 IF IN A MOVING VEHICLE

Stop quickly and stay in the vehicle. Move to a clear area away from buildings, trees,

overpasses, or utility wires. Once the shaking stopped, proceed with caution. Avoid

bridges or ramps that might have been damaged by the quake.

7.1.5.8.1.2 AFTER-SHOCKS

After the quake, be prepared for aftershocks

Although smaller than the main shock, aftershocks cause additional damage and

may bring weakened structures down. Aftershocks can occur in the first hours,

days, weeks, or even months after the quake.

Page 22: RISK ASSESSMENT & DISASTER MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/online/Risk... · 2018-08-01 · following Disaster Management Plan (DMP) for different type of

Project Name Environment Clearance for Group Housing Project

EIA Project Proponent Sunrise Technobuild LLP

Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra

Marg Yojna, Rishikesh, Uttarakhand

Environment Consultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-22

7.1.5.8.1.3 HELP INJURED OR TRAPPED PERSONS

Give first aid where appropriate. Do not move seriously injured persons unless

they are in immediate danger of further injury. Call for help.

Remember to help those who may require special assistance--infants, the elderly,

and people with disabilities.

Stay out of damaged buildings.

Use the telephone only for emergency calls.

7.1.5.8.1.4 RESPONSE PROCEDURE FOR EMERGENCY TEAM

Formulate an Emergency Response Team for earthquake response

Using the public address system, inform occupants of response procedures

discussed above.

Inform the necessary authorities for aid.

Ensure that no person is stuck beneath any debris, in case of a structural failure.

Ensure that all occupants standing outside near the buildings are taken to open

areas.

Ensure that the first aid ambulance and fire tender vehicles are summoned if

necessary.

Inform the nearby hospitals if there are any injuries.

Check the utilities and storage tanks for any damage.

7.1.5.8.2 RESPONSE FOR LPG LEAKAGE

1) The affected area should be evacuated and cordoned off immediately

2) Initiate an Emergency Response Team for LPG leakage

3) Shut down the main valves in the gas cylinder

4) Ensure that only concerned personnel are present in the affected area and all

other personnel and visitors are moved to the nearest assembly points

5) Rescue trapped personnel, also check if any personnel are unconscious in the area

and immediately move them outside and provide first aid.

6) Ambulance should be summoned to take injured personnel to the nearest hospital.

7) Personnel in the nearby buildings to close all doors and windows to prevent entry

of the leaked gas

8) Source of leakage to be traced and isolated from all the other areas. If required,

use pedestal fans to bring down the gas concentration

7.1.5.8.3 RESPONSE IN CASE OF FIRE

1) Required response in the event of a fire shall be described in signs located in the

lobby.

Page 23: RISK ASSESSMENT & DISASTER MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/online/Risk... · 2018-08-01 · following Disaster Management Plan (DMP) for different type of

Project Name Environment Clearance for Group Housing Project

EIA Project Proponent Sunrise Technobuild LLP

Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra

Marg Yojna, Rishikesh, Uttarakhand

Environment Consultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-23

2) On sighting a fire, it shall be immediately informed to the Environment Manager

giving the exact location and type of fire in detail.

3) Initiate the Emergency Response Team for fires

4) If the fire is small, engage in extinguishing the fire using the nearest fire

extinguisher.

5) Guide the Emergency Response Team staff to the emergency assembly point.

6) The Emergency Response Team shall immediately inform the nearest dispensary

and security force. If required, a fire tender shall be summoned.

7) The response team shall immediately move to the point of fire and take all

necessary steps to stop the fire. If the fire is not controllable and spreads, then

the Manager in charge shall inform the district authorities and call for external

help.

8) The Emergency Response Team will provide immediate relief to the injured

Occupants at the scene of incident. Any injured persons shall be evacuated on

priority to the dispensary or one of the nearest hospitals based on their

condition.

7.1.5.8.3.0 INSTRUCTIONS FOR OCCUPANTS

1) Get out of buildings as quickly and as safely as possible.

2) Use the stairs to escape. When evacuating, stay low to the ground.

3) If possible, cover mouth with a cloth to avoid inhaling smoke and gases.

4) Close doors in each room after escaping to delay the spread of the fire.

5) If smoke is pouring in around the bottom of the door or if it feels hot, keep the

door closed.

6) Open a window to escape or for fresh air while awaiting rescue.

7) If there is no smoke at the bottom or top and the door is not hot, then open the

door slowly.

8) If there is too much smoke or fire in the hall, slam the door shut.

9) Stay out of damaged buildings.

10) Check that all wiring and utilities are safe.

A brief of Hazard-specific structural and non-structural measures for disasters caused by flood, earthquake, drought, fire and chemical & industrial accidents are outlined in the Table 1.4.

Page 24: RISK ASSESSMENT & DISASTER MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/online/Risk... · 2018-08-01 · following Disaster Management Plan (DMP) for different type of

Project Name Environment Clearance for Group Housing Project

EIA Project Proponent Sunrise Technobuild LLP

Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra

Marg Yojna, Rishikesh, Uttarakhand

Environment Consultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-24

Table --11..44:: BBRRIIEEFF of Hazard-Specific Structural & Non-Structural Measures

Hazard Structural Measures Non-Structural Measures Flood

Strengthening / construction of embankments, flood walls

Proper regulation of water storage reservoirs

Drainage improvement in Order to avoid congestion

Inspection, rehabilitation and maintenance programme to ensure that the design capabilities are maintained.

Flood plain zoning to regulate land use in the flood plains. Integrated Water Resource Management

such as water resources assessment, socio-economic assessment, water resources planning, implementation of action Plans, day-today water resources management (adjustments of the plans) and water resources protection and conservation.

Medical preparedness in terms of after-effects of floods requiring medical attention.

Earthquake Seismic strengthening of existing structures.

Structural safety audit of critical lifeline structure.

Earthquake-resistant construction

Development of Rapid Visual Screening procedures and Detailed Vulnerability Assessment.

Regular conduction of Fire Safety Audits and Electrical Safety Audits.

Public Awareness campaigns. Techno-legal regime for ensuring compliance

of earthquake-resistant design and construction practices in all new constructions.

Drought Water management including water harvesting and conservation.

Micro-irrigation including drip and sprinkler irrigation.

Study groundwater availability in area.

Page 25: RISK ASSESSMENT & DISASTER MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/online/Risk... · 2018-08-01 · following Disaster Management Plan (DMP) for different type of

Project Name Environment Clearance for Group Housing Project

EIA Project Proponent Sunrise Technobuild LLP

Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra

Marg Yojna, Rishikesh, Uttarakhand

Environment Consultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-25

Fire Implementation of all

applicable fire safety norms.

Training of community members in fire-fighting techniques. Putting in place audit system Compulsory

fire hazard evaluation of all types of buildings old and new

Planning and calendar of evacuation drills/ mock drills in vital installations/ industrial plants/ government buildings / schools and critical infrastructure like hospitals, etc.

Enforcement of fire approvals as per the provisions contained in National Building Code (NBC) 2005 for new constructions.

Chemical & Industrial Accidents

Creation of appropriate infrastructure as mentioned in Off-site and On-site plans including Public Address system.

Enforcement of code of practices, procedures and standards. Audits of on-site & off-site Emergency plans at regular intervals Statutory inspection, safety audit and

testing of emergency plans Safety auditing Hotline telephone connection with nearby

emergency services. Awareness generation among community regarding hazmat Training of specialized medical first aid responders

Biological Disasters

Enforcement of bio-safety measures in labs

Regular survey and proper maintenance of water supply and sewage pipeline.

Creation of awareness about personal hygiene. Vector control programs.

7.8 CORPORATE SOCIAL RESPONSIBILITY (CSR)

In the visit made to the site, it was found that around the proposed site area is developing

fast. Lack of jobs; lack of infrastructural facilities; high rate of school dropouts along with

the drug addiction were some the problems that were highlighted by the villagers. The

proponent M/S. Sunrise Technobuild LLP proposes to support the development activities,

to a budget of about Rs 1.4 /- Crore (2 % of the Total Project Cost i.e. 70 Crores) under its

corporate social responsibility. .

Steps for CSR Implementation:

The CSR programme will be implemented in the following steps

Floating of RFP/tender for CSR implementation

Finalization of CSR implementation organisation

Memorandum of Understanding and award of CSR Project

Page 26: RISK ASSESSMENT & DISASTER MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/online/Risk... · 2018-08-01 · following Disaster Management Plan (DMP) for different type of

Project Name Environment Clearance for Group Housing Project

EIA Project Proponent Sunrise Technobuild LLP

Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra

Marg Yojna, Rishikesh, Uttarakhand

Environment Consultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-26

Monitoring & Evaluation

Reporting

CSR Implementation Area: The CSR Programme will be implemented in the following

villages of Greater Noida

1 Veerbhadra

2 Rishikesh Nagar Nigam

3 Gumani Wala

CSR Programme: The following Corporate social responsibility programme will be

implemented in a phased manner.

1. Girl Child Education: The educated girls are the need of the society. According to

an estimate about 98 % students are dropping out of schools and the girl children

are the most affected. Keeping in view of the fact, the proponent proposes girl

child education programme in which the girls from weak financial background

will get financial help through the school in the project villages.

2. Distribution of Blankets & Clothes to homeless & poor people: The area

experiences harsh weather conditions and poor land less people are worst

affected by the adverse weather. The proponent Proposes to distribute the

blankets and clothes among the landless and poor people.

3. Night Shelters for homeless people: The proponent proposes to help the existing night shelters for homeless people and help to create the new one, to

accommodate the ever increasing population of the city.

Project Implementation Schedule:

4. Project Implementation Plan for 1st year to 7th year

Sr. No.

Activities Year 1

Year 2

Year 3

Year 4

Year 5

Year 6

Year 7

1 Girl Child Education (160 school girls)

a Floating the RFP, and selection of best implementation organization

b Selection & MoU with schools c Getting the list of girls

belonging financially weak household.

d Disbursement of Girl child scholarship @ Rs 5,000/- per year

e Monitoring and reporting 2 Night Shelters

a Floating the RFP, and selection of best implementation

Page 27: RISK ASSESSMENT & DISASTER MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/online/Risk... · 2018-08-01 · following Disaster Management Plan (DMP) for different type of

Project Name Environment Clearance for Group Housing Project

EIA Project Proponent Sunrise Technobuild LLP

Project Address Plot No. GH-1 in Avas Vikas Parishad Housing Colony, Veerbhadra

Marg Yojna, Rishikesh, Uttarakhand

Environment Consultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 7-27

Sr. No.

Activities Year 1

Year 2

Year 3

Year 4

Year 5

Year 6

Year 7

organization

b MOU with existing and new service providers

c Release of CSR grant for night shelters

d Monitoring and reporting 3 Blankets & Clothes Distribution (1600 poor people)

a Floating the RFP, and selection of best implementation organization

b MOU with distribution partners c Distribution of clothes and

blankets to rural people @ Rs 500/-

d Monitoring and reporting ***********