RIIO-2 Business Plans Draft Guidance Document - ofgem.gov.uk · RIIO-2 Business Plans – Updated...
Transcript of RIIO-2 Business Plans Draft Guidance Document - ofgem.gov.uk · RIIO-2 Business Plans – Updated...
RIIO-2 Business Plans Draft
Guidance Document
Publication Date 21 December
2018
Contact: RIIO Team
Team: Network Price Controls
Tel: 020 7901 000
Email: [email protected]
This is an updated guidance document directed at gas and electricity network companies
and their stakeholders, which sets out the information we expect to see in companies’
business plans for RIIO-2.
This is a live document which we will update periodically, as and when appropriate.
RIIO-2 Business Plans – Updated Guidance
2
Contents
1. Introduction 4
Context 4
Purpose of this document 4
Cross-sector workshops 5
Electricty distribution 5
2. Proposed Content of Business Plans 6
Track-record 6
Business Plan commitment 6
A consistent view of the future 6
Outputs and incentives 7
Ensuring future resilience 8
Enabling whole system solutions 10
Innovation 11
Competition 11
Enhanced engagement 12
3. Costs and Finance information 13
Cost information 13
Cost drivers 13
Consideration of options 13
Cost justification 13
Business plan data templates 14
Cost benefit analysis (CBA) 15
Financial information 15
4. Managing Uncertainty 16
Uncertainty mechanisms 16
Proposed approach for new assets 17
Anticipatory investment 17
Real Price Effects (RPEs) 17
5. Business plan incentive 19
Proposed Minimum requirements 19
Proposed characteristics of a poor plan 19
Proposed characteristics of a good plan 20
RIIO-2 Business Plans – Updated Guidance
3
6. Next steps 21
Gas distribution, gas and electricity transmission networks 21
Electricity distribution 22
7. Appendix 1- Summary of proposed outputs in each sector 23
RIIO-2 Business Plans – Updated Guidance
4
1. Introduction
Context
1.1. In RIIO-2, we will set revenues for gas and electricity network companies. In
order to set these revenues, we need information from the companies on the
activities that they intend to undertake in RIIO-2 and their associated costs.
Companies will provide this information to us in the form of a Business Plan,
which we will then assess. The gas distribution, gas and electricity transmission
network companies will submit their final Business Plans to us in December 2019.
Their next price control will start in April 2021.1
1.2. In developing their plans, it is essential that companies carry out robust and high
quality engagement with their stakeholders2. Through the enhanced stakeholder
engagement framework,3 companies should also engage with the RIIO-2
Challenge Group and the User Group/Customer Engagement Group that each
company has established.
1.3. Companies should submit full drafts of their Business Plans to the RIIO-2
Challenge Group twice, before the plans are submitted to Ofgem in December
2019:
The companies are expected to submit a first draft of their full plans on 1
July 2019.
Following the first round of challenge, a second draft of their full plans is to
be submitted on 1 October 2019.
Purpose of this document
1.4. We are publishing this Draft Guidance Document to give network companies and
their stakeholders an indication of the kind of information that we are likely to
expect in their Business Plans.
1.5. This Guidance is based on our sector methodology proposals for RIIO-2, which we
are currently consulting on. This consultation closes on 14 March 2019, and we
expect to issue our decision in May 2019. Therefore, this Guidance – including the
type of information we may require and how we might assess it – may be
updated in light of this decision. We are aiming to update this Guidance prior to
the companies submitting the first draft Business Plans in July 2019.
1.6. There are a number of Sections in this Guidance:
Section 2 describes the content that we expect to receive in the Business Plans
and provides guidance on the issues we expect companies to have considered in
preparing their plans.
Section 3 describes the cost and financial information that we may require4.
Section 4 describes our proposed approach to managing uncertainty.
Section 5 describes our initial thinking on the characteristics of a Business Plan
that could determine whether it is of good, standard or poor quality. This would
1 The electricity system operator is also subject to a RIIO-2 price control, however this guidance does not apply to the ESO. 2 By stakeholders, we mean individuals, organisations or communities that are impacted by the activities of the network company. This includes existing and future consumers. 3 Please see Ofgem, RIIO-2 Framework Decision, July 2018. 4 Please see Ofgem, RIIO 2-RIIO-2 Sector Specific Methodology and RIIO-2 Framework Decision, July 2018.
RIIO-2 Business Plans – Updated Guidance
5
inform our assessment of the plan as part of the proposed business plan incentive
we have described in our December RIIO-2 Sector Specific Methodology
consultation, subject to responses to that consultation.5
Section 6 describes next steps.
1.7. We recognise that network companies require guidance in order to prepare their
Business Plan. We are interested in your views on this guidance document, in
particular on the following questions:
Q1. What further detail on the proposed content of the Business Plan do you
think network companies require?
Q2. Is there other information that we should be requesting in order to
assess a network company’s Business Plan?
Q3. What further information do network companies require on the
characteristics of a Business Plan that we need to consider in assessing its
quality?
Q4. Are there other characteristics that we should consider in assessing the
quality of a Business Plan?
1.8. We ask for responses by 15 February 2019, to allow us to update this Guidance
as necessary in sufficient time for network companies to be able to prepare their
plans in line within the RIIO-2 timetable.
Cross-sector workshops6
1.9. We recognise that network companies and stakeholders may require further
information in addition to that provided in this draft Guidance. We will be hosting
a series of cross-sector workshops between January and March 2019 to discuss
our thinking on the type of outputs companies could be expected to deliver, how
their plans may be assessed (including potential reward or penalty), and the
proposed specific format of financial and costs data submissions.
Electricty distribution
1.10. The next electricity distribution (RIIO-ED2) price control starts in April 2023.
1.11. We will consult separately on the sector methodology for electricity distribution
during 2020. This will include consideration of the applicability of the approach
taken for other sectors and the specific features of electricity distribution that
may warrant a different approach.
1.12. Subject to that process and full consideration of any further developments in the
interim period, the content of this draft guidance may, in principle, be broadly
applicable to the Distribution Network Operators (DNOs). An updated version of
this draft Guidance will be issued alongside the sector methodology consultation
for electricity distribution, taking into account any learning from the other sectors.
5 https://www.ofgem.gov.uk/publications-and-updates/riio-2-sector-specific-methodology-consultation 6 Further details on these cross-sector and sector-specific workshops, including arrangements for attendance,
will be published on our webpage in due course. https://www.ofgem.gov.uk/network-regulation-riio-
model/network-price-controls-2021-riio-2/riio-2-events-seminars-and-working-groups
RIIO-2 Business Plans – Updated Guidance
6
2. Proposed Content of Business Plans
Track-record
2.1. In assessing the credibility of the Business Plan being proposed, we propose to
consider how companies have performed and behaved in the RIIO-1 period.
Therefore, in their RIIO-2 Business Plan, we expect companies to explain:
their delivery against RIIO-1 output targets and their performance against
the incentive mechanisms available
what level of service has been provided to the average customer and to the
worst served customers in RIIO-1, and what steps they took within the
period to improve the service to the worst-served
how well different groups of customers have been served over the RIIO-1
period – e.g. customer in particual regions/circumstances
what additional value they have provided to consumers outside of the price
control/licence mechanisms (e.g. voluntary returns, voluntary additional
Guaranteed Standards of Performance payments, etc.)
how their expenditure has differed against allowances provided at the outset
of RIIO-1
what factors contributed to any differences between allowances, and how
these factors have been considered in the RIIO-2 Business Plans
the returns companies earned over the RIIO-1 period, and key drivers
behind this
the level of profit payment they distributed to investors over the RIIO-1
period.
Business Plan commitment
2.2. In assessing the credibility of the Business Plan being proposed, we propose to
take into account the level of commitment companies give to their RIIO-2
Business Plan. Therefore, in their RIIO-2 Business Plan, we would expect
companies to explain:
how they intend to align the structure of pay and reward within the
organisation to the delivery of commitments set out in their Business Plans,
including on accuracy of data provided
what level of assurance is provided by sufficiently independent directors that
the plan and associated costs have been tested for accuracy, ambition and
efficiency.
A consistent view of the future
2.3. In preparing their Business Plans, network companies should consider a range of
future outcomes and the different investments and activities they may need to
undertake. We want to ensure that the price control is sufficiently flexible to meet
changing circumstances. We have asked the networks to jointly develop a
‘consistent view of the future’ across all five regulated sectors (gas, electricity,
and the ESO).
RIIO-2 Business Plans – Updated Guidance
7
2.4. The consistent view of the future should also incorporate a view on the primary
drivers of investment, including relevant government policy,7 and a range of
plausible future scenarios associated with each.
2.5. Having a consistent view of the future will require some consideration of the
regional variations which will inevitably occur across the networks, and
differences in opinion on 'most likely' outcomes. Where networks believe their
plans will need to deviate from the common view, then they should provide
evidence for this and the most appropriate mechanism to allow expenditure
allowances to adjust.
2.6. We will work with network companies in early 2019 to ensure that a consistent
view of the future has been formed in the interests of consumers. While we
believe best practice dictates that networks should undertake this process, if
necessary, we will form our own view on some of the primary drivers of
expenditure and ask networks to implement these as a reference case.
Outputs and incentives
2.7. In the RIIO-2 December Sector Specific Methodology consultation, we set out our
proposal to specify outputs as a set of consumer-facing outcomes.
Figure 1: Output categories in RIIO-2
2.8. We also set out our proposed overarching framework for outputs and incentives
to deliver these outcomes.
We propose to set mimimum standards of performance which we will impose
through the introduction of Licence Obligations (LOs).
We propose to capture outputs directly associated with baseline funding
through Price Control Deliverables (PCDs). We will clarify consequences for
non-delivery or delivery to a lower than expected standard as appropriate,
including for example the use of uncertainty mechanisms.
We propose to apply Output Delivery Incentives (ODIs) where service quality
improvements beyond the minimum standard may be in the interests of
consumers and other network users.
7 For example we expect GDNs to set out in their Business Plan how they are preparing for Government decisions on the future of heat. This should include consideration of decarbonisation scenarios in which gas distribution plays a significant role, and scenarios in which their role is considerably diminished. Consideration of these scenarios should include a description of the potential impact of Government decisions during RIIO-GD2 on their investment plans, which we would consider when developing a heat policy reopener.
RIIO-2 Business Plans – Updated Guidance
8
2.9. As set out in the sector-specific methodology consultation, network operators will
have the opportunity to propose bespoke outputs in collaboration with their
stakeholders and Customer Challenge Group/User Groups. This could include
bespoke PCDs or ODIs.
2.10. Network company proposals should:
reflect the network services that existing and future consumers/network
users require/will require
be as complete as possible in capturing the activities of the network operator
focus on simpler output categories of value to consumers/network users
allow comparison of performance across companies where there is sufficient
commonality
capture the long-term nature of outputs.
2.11. In assessing proposals, we are likely to consider, amongst other things:
whether the output reflects a service that consumers expect to receive from
a network company that cannot be funded through the base revenues
provided in the price control settlement
whether the activity in question is best dealt with through the price control,
rather than through a government body responsible for the public interest in
that area (e.g. Highways Authorities for matters relating to the occupation of
the highway)
whether proposals are backed by robust evidence and justification (such as
cost-benefit analyses8) and demonstrate value for money for existing and
future consumers
the value that consumers will receive from a proposed new service level, and
by extension the potential associated reward and/ or penalty, and the extent
to which these are symmetrical, in terms of value and likelihood of outcome
the extent to which an independent measure of the existing level of service
that consumers receive is available, and the degree to which the target level
being proposed represents an improvement on this
the level of service provided by other companies/comparators (where
available)
the activities (and indicative cost) associated with achieving the targeted
level of service
proposals for licence conditions and/or penalties if performance falls below
existing service levels.
2.12. In the annexes that accompany the sector-specific methodology consultation, we
provide more information on the type of outputs that may be applicable in each
sector. If these are taken forward, then to support the design of these outputs,
we may require companies to submit output-specific information in their Business
Plans. Appendix 1 provides a summary of the proposed outputs in each sector.
The sector-specific methodology annexes should be referred to for more detail.
Ensuring future resilience
Asset resiliance
2.13. Network Asset Risk relates to the risk of asset failure and to the network
companies’ asset management activities that are aimed at maintaining this risk at
8 Please see our requirements for cost-benefit analysis in Section 2 of this guidance.
RIIO-2 Business Plans – Updated Guidance
9
levels which are acceptable to consumers. We expect companies to provide us
with the following information in their Business Plan submissions:
Monetised Risk objectives that are informed by stakeholder engagement,
including appropriate understanding of consumers’ willingness to pay
cost-benefit analysis (CBA), according to the guidelines specified in Section 3
of this document, to demonstrate that selected investment options efficiently
meet their stakeholder-driven objectives and deliver sufficient net benefit for
existing and future consumers.
Workforce resilience
2.14. We are currently consulting on whether network companies should be submitting
a sustainable workforce strategy as part of their RIIO-2 Business Plans. If this
proposal is taken forward then we would expect these plans to set out how
companies would ensure that their workforce better reflects the diversity of the
communities they serve. Specifically such plans should:
demonstrate where attracting and retaining skilled personnel is becoming
increasingly challenging, including areas of uncertainty outside the control of
the companies
demonstrate how existing approaches to recruitment and retention in these
areas need to be improved to address this challenge, including:
o where this involves changes to pay and benefits, this would need to be
justified against historical benchmarks supported by robust evidence of
market trends for these skills going forward
o where this involves recruiting increased numbers over and above those
required to operate efficiently in the shorter term (e.g. additional
apprenticeships / technical graduates), the longer-term benefits of such
recruitment should be clearly evidenced
not only cover the RIIO-2 period, but extend out at least another 10 years to
consider workforce resilience over the longer term.
Cyber resilience
2.15. As discussed in the RIIO-2 Sector Specific Methodology, under the Network and
Information Systems Regulations 2018 (“NIS Regulations”), network companies
must take appropriate and proportionate technical and organisational cyber
security measures to manage risks posed to the security of the network and
information systems on which their essential service depends, and to prevent and
minimise the impact of incidents on these essential services.
2.16. The National Cyber Security Centre (“NCSC”) has developed a sector-agnostic
Cyber Assessment Framework (“CAF”) to assist operators covered by the NIS
Regulations.
2.17. Each network company is expected to perform a self-assessment against the CAF
in the coming months and propose what short-to-medium term cyber-security
measures they consider proportionate and appropriate to manage risks identified.
These will form part of an improvement plan to be submitted to Ofgem for
approval in its role as the CA. We intend to establish a comprehensive audit and
inspection regime to monitor the delivery of these improvement plans.
RIIO-2 Business Plans – Updated Guidance
10
2.18. In addition, we require network companies in all sectors (including electricity
distribution) to develop and submit strategic investment plans for cyber
resilience. As the CA, we plan to publish guidance by June 2019 to inform the
development of these longer-term plans.These plans:
must consider the cost of additional security measures against the consumer
must consider the economic and societal impacts of a cyber-incident
provide all of the necessary information to allow us to take a view on the
proposed security measures, including the needs case, the range of options
considered and the efficient costs of delivery.
Where possible, we expect these strategic investment plans to form part of
the RIIO-2 Business Plan submissions. These plans must allow us to assess
and take a view on the how the proposed investments meet the
requirements set out in the detailed guidance.
2.19. We will assess these plans considering whether the measures proposed to meet
the security requirements of the Directive are appropriate, proportionate and
efficient. Any allowances provided under RIIO-2 will be based on this assessment.
For RIIO-2, we propose to consider cyber security resilience costs which are (1)
efficiently incurred as a direct result of the introduction of the NIS Regulations,
and (2) above ‘business-as-usual’ activities.
Physical security
2.20. As discussed in our RIIO-2 Sector Specific Methodology we expect network
companies to submit costs relating to Physical Security Upgrade Programme
(PSUP) as part of their business plans, as a (confidential) Price Control
Deliverable.
2.21. Changes in Government policy during the price control could result in changes to
the investment required for PSUP. Therefore, for RIIO-2, we are considering to
include a reopener to adjust allowed revenue (either upwards or downwards) if
Government mandates changes to the scope of the enhanced physical site
security work required during the period. These costs would be subject to the
normal cost assessment process (see Section 3). Companies would not need to
provide CBAs or assessment of needs case.
Enabling whole system solutions
2.22. Greater whole system thinking and coordination should increase the number of
options networks have at their disposal when seeking to provide services and help
ensure network companies’ actions are efficient overall. We expect companies to
provide information on their approach to enabling whole system solutions in their
Business Plan. We propose that this should include:
plans and processes for joint planning with other network companies / the
ESO
effective consideration of whole system solutions to network planning and
constraints in their cost benefit analyses, as well as reflecting how they have
taken account of the wider impacts and opportunities of their actions,
including identification of uncertainties and their mitigation
long term whole system thinking and value for money, including
identification of uncertainties and mitigation.
2.23. Any specific expenditure that network companies propose for enabling whole
system solutions should be clearly identified. We would expect to see supporting
information demonstrating:
RIIO-2 Business Plans – Updated Guidance
11
any costs that they anticipate incurring by implementing these projects or
activities
the benefits that they expect to flow as a result of the projects and what
may be the indicators of these
the level of coordination that has already been undertaken to support these
proposals
how uncertainty mechanisms, including reopeners, should be used or
triggered to support the project
what arrangements they will put in place to ensure these measures are
operating effectively, or can be revised accordingly
why this project or activity cannot already be undertaken through a totex
allowance, and why a market solution cannot be utilised to produce this
result, where applicable.
Innovation
2.24. Our expectation for RIIO-2 is that companies will undertake more innovation
through their business as usual (BAU) activities, especially lower-risk operational
and maintenance innovation projects. We also want greater third party
involvement in network innovation.
2.25. To support this, we would expect companies’ Business Plans to explain:
what steps companies are taking to ensure that previously proven innovation
is rolled out into BAU
what innovation activities companies are planning for RIIO-2 using their
totex allowance
how the benefits of previously proven and proposed innovation is reflected in
the company's proposed expenditure for RIIO-2
what arrangements companies will take to secure third party involvement
and colloborate with other network companies as part of their innovation
activities.
2.26. As the composition of the RIIO-2 innovation stimulus and level of funding
available is not yet confirmed, we only expect companies to include plans for
innovation projects funded via their totex allowance within their Business Plans.
Once details of the RIIO-2 innovation stimulus are confirmed, we may then ask
companies to set out more detailed plans regarding innovation projects funded
via the RIIO-2 innovation stimulus.
Competition
2.27. We are currently consulting on our plans for competition in RIIO-2, and further
information on our proposals is available in the RIIO-2 Sector Specific
Methodology consultation. Broadly, our consultation covers three areas: early
competition, late competition, and native competition.
2.28. We provide early sight of our thinking in relation to the information that
companies migh need to provide for late and native competition below. We do not
address early competition here. We may update this information after considering
stakeholder responses to the RIIO-2 Sector Specific Methodology consultation.
Late competition
2.29. Under our current proposals, in their Business Plan submissions, companies may
be expected to provide us with the best information available to allow us to
identify projects that may be eligible for late competition.
RIIO-2 Business Plans – Updated Guidance
12
2.30. We are currently consulting on the extension of our existing criteria for electricity
transmission (new, separable, high-value) to both gas sectors and electricity
distribution. We intend to update stakeholders on our view of the criteria for late
competition in each sector following the close of the RIIO2 sector methodology
consultation.
Native competition
2.31. Under our consultation proposals, in their Business Plan submissions, companies
may expect to provide us with information on how they intend to use competition
to drive efficiencies. Each company’s competition strategy would be expected to
be in line with the proposed principles outlined in our December RIIO-2 Sector
Specific Methodology consultation. The type of information we might expect to
receive could include:
clear governance processes for the competitions (such as annual public
reporting of their performance against their proposed procedures) the type of metrics and tangible audit methods by which Ofgem and
stakeholders can assess their performance throughout the price control.
Enhanced engagement
2.32. The enhanced stakeholder engagement process for RIIO-2 has now been
established.9 We expect network companies to work with the Customer
Engagement Groups in Distribution, User Groups in Transmission, and the RIIO-2
Challenge Group to challenge and scrutinise their Business Plan proposals.
2.33. We would expect network companies to provide in their Business Plans:
evidence of appointment of company specific groups - timely appointment of
groups, governance arrangements at appointment and on an ongoing basis,
amongst other things as described in the enhanced engagement guidance
document issues in April 2018
evidence of effective engagement with User Groups , Customer Enagement
Groups and the RIIO-2 Challenge Group. We will also ask these groups to
provide us with evidence that the level of engagement was sufficient to help
them reach views on each part of the business plan.
Evidence of robust and high quality engagement with stakeholders by the
company in designing the plan.
Proposals in the plans on how companies will maintain a process of robust
and high quality engagement with stakeholders on an ongoing basis within
RIIO-2. This might include consideration of:
o how they will incorporate best practice from RIIO-1 into their activities.
o what commitments they will give to support engagement (including
what will be the consequences for non-delivery)
o whether KPIs and targets could be used to monitor within-period
performance10
o needs of existing and future customers and consumers.
9 Electricity distribution companies have started to set up their Consumer Engagement Groups. We welcome this with a view to the companies being prepared for the publication of our open letter for RIIO-ED2 in Q3 July 2019 10 As set out in the RIIO-2 sector methodology document we are currently consulting on whether to retain an ODI for stakeholder engagement for RIIO-2. Depending on the outcome of this consultation we might require additional information on KPIs and targets.
RIIO-2 Business Plans – Updated Guidance
13
3. Costs and Finance information
Cost information
3.1. In proposing costs for operating and developing their networks, we expect
companies to explain their costs/workload forecasts, particularly where these
diverge from historical trends. In particular we expect network companies to
provide information in their Business Plans on:
cost drivers
consideration of options
justification of costs.
Cost drivers
3.2. We expect companies to clearly set out:
the key drivers of expenditure for the RIIO-2 period - for example growth in
demand, conditions of assets/utilisation, legislative requirement, and any
other relevant drivers.
which categories of expenditure are uncertain and cannot be forecasted
using historical/independent benchmarks. Where this is the case we expect
companies to consider uncertainty mechanisms that mitigate risk associated
with uncertainty, and/or other evidence to justify their costs.
Consideration of options
3.3. We expect companies to clearly demonstrate the need for new investment
including:
The different options considered for meeting future network requirements,
including the cost of “doing nothing” and of “deferral” options and the
associated cost benefit analysis (CBA). Options discounted at this stage
should be accompanied by full reasoning, detailing key assumptions and
selection criteria given for exclusion. We expect CBAs to meet the criteria
described below.
The reasons for the timing of investment under the different options
considered, including expected outputs (eg the delivery of an increment in
boundary capacity transfer, the delivery of an electricity link, a gas pipeline)
related to the investment and year of delivery.
Cost justification
3.4. We expect companies to provide:
a justification of the efficiency of their costs, for example as compared to
historical benchmarks and/or benchmarking with national and international
comparators
details of assumptions and justification for projected changes in the efficient
levels of unit costs over time (i.e. ongoing efficiencies) caused by
improvements in project delivery, technological innovation, procurement
efficiencies
clear justification for any associated assumptions they consider we should
use when assessing costs. For example, robust and transparent justification
for the extent to which regional and company-specific factors determine
material (higher and lower) cost variations.
Details of the activities and indicative cost that are directly funded through
totex allowances and are associated with achieving service levels.
RIIO-2 Business Plans – Updated Guidance
14
For discrete projects, we expect companies to provide:
For high value, discrete projects, a detailed breakdown of costs that allows
individual cost elements to be benchmarked against relevant comparators.
A clear explanation of how they will account for the costs of projects that
straddle price control time periods.
A clear explanation of how they will deal with projects where the deliverable
changes, or the project itself is no longer needed (for example through the
use of PCDs).
Details of the activities and indicative costs associated with delivering PCDs
and ODIs.
3.5. We expect detailed information on costs and workloads during RIIO-2 to be
provided in the Business Plan data templates. We discuss these below.
Business plan data templates
3.6. Business plan data templates (BPDTs) enable the collection of business plan data
from all network companies on a consistent basis. We will work with the network
companies in each sector over the next few weeks to develop draft sector-specific
BPDTs and associated instructions. We expect to issue these draft BPDTs in March
2019. These draft BPDTs will identify the price terms (mindful of our proposed
move to away from RPI to CPIH) in which companies should present financial
information.
3.7. We expect network companies to use these draft BPDTs when submitting their
draft Business Plans to the RIIO-2 Challenge Group on 1 July 2019 and in October
2019.
3.8. We will use the draft Business Plan data, collected from the draft BPDTs, to test
whether we have all the information we require for our cost assessment and to
enable us to further develop our approach to assessing efficient costs.
3.9. Following the sector-specific methodology decision in May 2019 and our review of
draft Business Plan data, we will then develop the final RIIO-2 BPDTs. We intend
to issue final BPDTs in autumn 2019 for use in the December 2019 Business Plan
submission.
3.10. In large part, we expect the BPDTs for RIIO-2 to be very similar to the BPDTs
used in RIIO-1 and to RIIO-1 annual reporting templates. Some areas that we
currently think may change or develop from RIIO-1 are set out below:
• where we think the level of uncertainty has changed from RIIO-1 to RIIO-2
with consequences on what data we need in order to assess costs
• data that helps inform policy, for example to enable us to assess costs
associated with proposed PCDs, to determine output targets and to
implement indexation for Real Price Effects, if this is what we decide
• to adapt to Network Asset Risk Metric reporting requirements. This will be
driven by the development of our approach to assessing the NARM in
RIIO-2 at both cross-sector and sector-specific levels
• to inform how we develop our cost assessment approach, for example to
link outputs to costs and ensure transparency
• where we require a greater level of granularity, for example for specific
investment projects
• where useful, to reflect a multi-period approach to provide greater
transparency on investment cycles beyond RIIO-2 in recognition of the fact
that price controls are artificial boundaries.
RIIO-2 Business Plans – Updated Guidance
15
Cost benefit analysis (CBA)
3.11. CBA is an important decision support tool as part of the justification for
investment needs in RIIO-2. In demonstrating due diligence has been followed in
the appraisal of potential investment decisions by network companies, we
propose CBAs should:
be consistent with published guidance and recognised best practice, for
example the Green book and the Spackman discounting approach
demonstrate evidence of structured options development, including
consideration of whole system options and non-network options, where
applicable
demonstrate the value of projects across different scenarios, and include an
explicit consideration of (quasi) option values11 of deferring the investment
be clearly linked to the Business Plan, where applicable, with sensitivity to
changes in input parameters assessed, for example future energy scenarios
act as a robust decision support tool, open to scrutiny and challenge in
conjunction with other appropriate means of justification for investment
decisions
be transparent about which risks, costs and benefits have not been
considered and non-monetised as part of the analysis.
Be transparent about assumptions, inputs and rationale for decisions,
calculations and results.
3.12. We will work with the network companies on a sector-specific basis to agree the
scope for the application of CBA and develop detailed guidance and templates for
CBA submission. We expect to publish updated guidance and templates by March
2019.
Financial information
3.13. For business planning purposes, we will provide a business plan financial model
(BPFM) for network companies to complete, this will include additional financial
tables, for example for taxation, pensions and asset disposals. We intend to
provide more detailed guidance on the BPFM in early 2019.
3.14. The BPFM will be pre-populated with all the parameters set out in the finance
section of the December RIIO-2 sector-specific methodology and forecast closing
RIIO-1 price control financial model (PCFM) data, for example regulatory asset
value (RAV). It will allow network companies to populate with their plans to
calculate expected allowed revenues. It will also be used for assessing the
financeability of the plan and will include a suite of commonly used financial
metrics.
11 Guidance on this option value from Ofgem can be found in our Strengthening strategic and sustainability considerations in Ofgem decision making, and Real Options and Investment Decision Making papers and annexes.
RIIO-2 Business Plans – Updated Guidance
16
4. Managing Uncertainty
Uncertainty mechanisms
4.1. Forecasting costs for the duration of a price control is challenging. Uncertainty in
cost forecasts can arise for several reasons, including whether a network
company needs to conduct an activity or make an investment, the amount of an
activity they need to conduct, as well as the cost of the activity. Uncertainty
mechanisms allow changes to a network company's allowed revenues to be made
in light of what happens during the price control period.
4.2. In the December Sector Methodology consultation, we have set out our thinking
on some of the uncertainty mechanisms that we propose for RIIO-2.
4.3. As part of their Business Plans, network companies can propose, with suitable
justification, the inclusion of additional uncertainty mechanisms. The table below
gives an illustration of the type of material we may expect to see to support any
such company proposals.
Table 1: Information we may expect for additional uncertainty mechanisms
Issue Information
What is the issue/risk that the proposed mechanism addresses?
Set out the uncertainty identified and why an uncertainty mechanism might be appropriate.
Is the issue/risk regionally specific or industry wide?
Where does the ownership of risk lie in relation to the uncertainty?
Clearly set out where the risks lie with regard to customer/network company/both.
Materiality of issue Quantification of the materiality of the issue (ie what is the expenditure exposure of the issue) – we will not prescribe a specific methodology for the quantification of materiality.
Frequency and probability of issue over the price control period
What is the expected frequency and probability of the issue during the price control period?
What is the proposed mechanism?
A description of what the mechanism is and how it works. This needs to be detailed enough to allow for potential implementation. If there is a materiality threshold, this would need to be set out as a percentage of allowed revenue. If there is a specific trigger event this should be defined.
What are the justifications for the mechanism?
Set out the benefits of the mechanism.
What are the drawbacks from the proposed mechanism?
Set out the drawbacks of the mechanism. Again, where possible, the materiality of these drawbacks need to be set out (e.g. the impact on charging volatility).
Can the drawbacks be reduced? Explain why the drawbacks cannot be mitigated through alternative mechanism designs (eg by using a volume driver instead of logging-up or cost pass through).
Explanation of how on balance, the mechanism delivers value for money while protecting the ability to finance efficient delivery.
Explanation of why the benefits of the mechanism outweigh
the drawbacks.
We also expect the quantification of how the proposed mechanism delivers value for money whilst ensuring efficient delivery.
RIIO-2 Business Plans – Updated Guidance
17
Proposed approach for new assets
4.4. To address the risk of stranding/under utilisation, we will be setting higher
evidentiary hurdles before approving new investment. We expect to see network
companies provide this evidence in their Business Plans.
4.5. We expect companies to provide probabilistic CBAs that explicitly consider
different scenarios, meet the requirements set out in cost benefit analysis set out
above, but also describe a number of elements, including:
with respect to the core scenarios and sensitivities mentioned in section 2,
the level of risk that new investments/existing assets could pose a stranding
risk in the future
the mitigation they will put in place to reduce the risk of stranding
what monitoring they will undertake to ensure a continuous assessment of
risk levels
availability of potential market solutions, and whether any ‘whole system’
solutions are available
a “least worst regrets” assessement.
Anticipatory investment
4.6. Where potential investments by gas and electricity networks are justified on the
basis of being in the interests of energy consumers, it may be consistent with our
principal objective and other statutory duties to support the delivery of these.
However, there may be circumstances where expenditure is justified on the basis
of policy objectives beyond our remit or whole economy implications.
4.7. In their Business Plan, we propose that companies describe these types of
investment in a separate section from their ‘core’ Business Plan proposals.
4.8. To support these proposals for anticipatory investment, we ask companies to
demonstrate:
the benefits to network consumers that may flow from earlier investment
the consequences of not making anticipatory investment
the other options they have considered to address the relevant need
the level of risk surrounding their assumptions on future demand, including
clarity on government policy
the justification for why network consumers should fund this work, including
an examination of which other parties (including local authorities, national
governments, and third parties) could fund the investment
the balance of risk that is to be shared between consumers, the network
company and any third party.
Real Price Effects (RPEs)
4.9. In RIIO-1, we provided companies with fixed, ex ante allowances for real price
effects (RPEs). These RPE allowances were for the forecast increase of certain
input prices (such as labour and materials) over and above the forecast increase
in the Retail Price Index (RPI). So far during RIIO-1, input price inflation has been
lower than forecast and this has had a material impact on companies’ costs and
returns.
4.10. To enable us to implement RPEs appropriately, we expect network companies to
provide us with the following information in their Business Plans:
proposed input prices indices
RIIO-2 Business Plans – Updated Guidance
18
justification for their choice (e.g. why an RPE is needed for a particular cost
and why the proposed index/indices are appropriate)
the costs to which they might apply
ongoing efficiency assumptions.
RIIO-2 Business Plans – Updated Guidance
19
5. Business plan incentive
5.1. In Chapter 9 of the December RIIO-2 Sector Specific Methodology, we describe
our proposal for a new business plan incentive for the gas distribution, gas and
electricity transmission sector.
5.2. The Business Plan incentive is intended to encourage companies to provide us
with information that enables us to set a better price control. This information
may come in many forms but could include more stretching cost or outputs than
we may otherwise set.
5.3. Our proposal for a Business Plan incentive includes the following elements.
A four stage assessment process of Business Plans. We propose that this
process would consider the level of ambition that is reflected in cost
forecasts and on qualitative elements. These qualitative elements may
include elements such as output delivery commitments, quality of
stakeholder engagement, effective proposals on dealing with uncertainty,
approach to enabling whole system solutions, competition and innovation.
We are proposing to assign a score based on our assessment of their costs
and a score based on the qualitative elements of their Business Plans.
We are proposing an upfront penalty regime for companies that submit
Business Plans that do not meet our minimum requirements or are of poor
quality. We describe the proposed minimum requirements below.
We are also proposing to allow network companies that submit a Business
Plan that offers additional value to consumers to earn an upfront reward.
5.4. Our assessment of the quality of the plan, if this proposal is taken forward, would
take into account the reports we receive from the various engagement groups, as
discussed above.
Proposed Minimum requirements
5.5. As part of the assessment of whether the Business Plan has met our minimum
requirements, we may consider, for example, whether:
the company submitted all the information detailed in this guidance in a clear
and understandable manner
the plan has been subject to a robust and auditable quality assurance process
to prevent inaccuracies and mistakes
the plan meets our formatting requirements, such as obligatory cross-
referencing
the plan is no longer than 200 pages excluding BPDTs and CBAs and business
plan financial model
the plan ensures the company can comply with relevant legislation, such as
for safety
the company used the enhanced engagement process to test and challenge
the plan, in line with our guidelines
the company provided the necessary information in line with our Business Plan
guidance and timetable for submission.
Proposed characteristics of a poor plan
5.6. A network company may submit a Business Plan that meets minimum
requirements but may still be of poor quality. This may be because, for example:
RIIO-2 Business Plans – Updated Guidance
20
limited commitments are offered to assure the credibility of the Business
Plan
proposed uncertainty mechanisms are overly biased on risks to companies
Little/no consideration has been given to non-network solutions and/or
whole system solutions, the whole system impacts of their actions or
benefits they could offer
PCDs and/or ODIs are proposed without credible justification, targets are at
too low a level, incentives are requested where baseline funding is already
provided.
potential projects/system needs that could be potentially competed are not
clearly presented
insufficient engagement in developing the plan and going forward – limited
stakeholder access to information, resource, personnel, time to properly
input to and challenge the plan
Proposed characteristics of a good plan
5.7. A network company may submit a Business Plan that provides more information
than the minimum required and in doing so, offers additional value to consumers.
This may be because, for example:
companies propose uncertainty mechanisms that highlight risks to consumers
we are not aware of
companies make well-evidenced proposals of more stretching targets for PCDs
and/or ODIs
companies have demonstrated consideration of non-network solutions and
whole system approaches that are likely to deliver demonstrable benefits to
consumers.
5.8. In addition to the above, information to support the design of sector-specific
outputs (as set out in appendix 1) may contribute to the categorisation of a plan
as being of either good or poor quality.
RIIO-2 Business Plans – Updated Guidance
21
6. Next steps
Gas distribution, gas and electricity transmission networks
6.1. The gas distribution companies, gas and electricity transmission network
companies will make the formal submission of their Business Plans to us in
December 2019.
6.2. Prior to this, the companies should submit a complete draft of their plans,
including submission of BPDTs, to the RIIO-2 Challenge Group on 1st July 2019
and then a second draft on 1st October 2019. This is to ensure there are at least
two rounds of challenge before the final Business Plan is submitted to us in
December 2019.
6.3. We will hold open hearings prior to our initial determination, to focus on areas of
disagreement or contention raised by the various groups and to invite any other
evidence in support of, or against, company Business Plans.
6.4. The full timescales for Business Plan submission is detailed in Figure 2 below. As
discussed in section 3, we expect to issue draft RIIO-2 BPDTs at a sectoral level
in March 2019. We expect network companies to use these draft BPDTs when
submitting draft Business Plans on 1 July 2019.
6.5. We will develop the RIIO-BPDTs following the sector-specific methodology
decision in May 2019 and our review of draft business plan data. We intend to
issue the final BPDTs in autumn 2019.
Figure 2: High-level milestones for developing price controls for electricity
transmission, gas transmission, gas distribution and electricity system operator
RIIO-2 Business Plans – Updated Guidance
22
Electricity distribution
6.6. The next electricity distribution (RIIO-ED2) price control starts in April 2023 - two
years after the other sectors. As part of the RIIO-ED2 process for electricity
distribution, network companies will also be expected to submit both draft and
final Business Plans to the Challenge Group. Our suggested forward workplan for
RIIO-ED2 is below in Table 2. The final timescales will depend on whether we
retain fast-tracking for electricity distribution companes. We intend to start the
consultation process on this as part of our open letter for RIIO-ED2, due to be
issued in 2019.
Table 2: Indicative high-level milestones for electricity distribution price
control
RIIO-2 Business Plans – Updated Guidance
23
7. Appendix 1- Summary of proposed outputs in each
sector
Gas distribution Reference in RIIO-2 Sector Specific Methodology - Gas Distribution Annex (paragraph)
Consumer vulnerability and carbon monoxide safety awareness use-it-or-lose-it allowance
3.24, 3.31, 3.42
Fuel Poor Network Extension Scheme 3.47
Average restoration time incentive for total unplanned interruptions 3.170
Shrinkage 4.11
Decarbonisation of heat - Low and no regrets heat decarbonisation projects
4.30
Decarbonisation of heat - heat policy re-opener 4.41
Repex 5.35
GDN record keeping 5.64
Gas holder demolitions 5.70
Smart Meters rollout costs 7.8
Xoserve costs 7.41
Gas Transmission Reference in RIIO-2 Sector
Specific Methodology - Gas
Transmission Annex
(paragraph)
Stakeholder engagement incentive and customer satisfaction 3.9 & 3.21
Quality of demand forecast 3.33
Maintenance 3.42
Capacity constraint management 3.62
Residual balancing 3.73
Compressor emissions 4.6
RIIO-2 Business Plans – Updated Guidance
24
NTS shrinkage 4.46
BCF reporting 4.53
Low carbon energy systems and decarbonisation of heat 4.63
Network capability assessment and target 5.10
Xoserve costs 7.47
Electricity Transmission Reference in RIIO-2 Sector
Specific Methodology -
Electricity Transmission
Annex (paragraph)
Stakeholder engagement 3.7, 3.15, 3.25, 3.32
Stakeholder satisfaction survey 3.37
Timely connections output 3.57
Energy Not Supplied 3.132
Environmental considerations embedded in Business Plans 4.4, 4.7, 4.9, 4.16, 4.19, 4.27
Annual environmental performance reporting (incl. BCF and losses) 4.22, 4.83
Sulphur hexafluoride (SF6) and other IIG leakage 4.65
Additional contribution to low carbon transition 4.34, 4.43
Mitigating visual amenity impacts in designated areas 4.113
Network Access Policy 5.28
Successful delivery of large capital investment projects 5.33
Cost Assessment 6.11, 6.19, 6.23, 6.33, 6.39
Uncertainty Mechanisms 7.8, 7.11