Richard L. Smailes, Ph.D. Building Chan Chan; The Construction Managers Perspective University of...
-
Upload
jayden-pratt -
Category
Documents
-
view
217 -
download
1
Transcript of Richard L. Smailes, Ph.D. Building Chan Chan; The Construction Managers Perspective University of...
Richard L. Smailes, Richard L. Smailes, Ph.D.Ph.D.
Building Chan Chan; Building Chan Chan;
The Construction The Construction Managers’ PerspectiveManagers’ Perspective
University of Florida
Bachelor of Building Construction, UF Bachelor of Building Construction, UF 19761976
Master of Building Construction, UF 1977Master of Building Construction, UF 1977 25 years construction industry 25 years construction industry
experienceexperience Ph.D. Building Construction, UF 2000Ph.D. Building Construction, UF 2000
Mike Mosely co-chairMike Mosely co-chair
Practitioner turned academicPractitioner turned academic
Building Chan Chan; Building Chan Chan;
The Construction The Construction Managers’ Managers’ PerspectivePerspective
What is the labor What is the labor investment? investment?
How many people?How many people?
How long?How long?
Premis:Premis: The labor investment in ancient monumental architecture is an important factor in hypotheses concerning a society's size, organization, and complexity.
Premis:Premis: The labor investment in ancient monumental architecture is an important factor in hypotheses concerning a society's size, organization, and complexity.
Due to the lack of practical analytical methods, complex architecture is often described subjectively offering little quantitative value, resulting in inferences that could be misleading or wrong.
Massive amounts of labor, generations to build
Premis:Premis: The labor investment in ancient monumental architecture is an important factor in hypotheses concerning a society's size, organization, and complexity.
Due to the lack of practical analytical methods, complex architecture is often described subjectively offering little quantitative value, resulting in inferences that could be misleading or wrong.
The application of construction industry estimating and scheduling standards provides a consistent, accurate, and objective means to calculate the labor investment in complex structures.
Ciudadela Rivero
Ciudadela Rivero
1. Define the Scope of Work
2. Perform the Quantity Survey
3. Determine Productivity - Unit Rates
4. Calculate the Project Estimate
5. Develop a Work Plan - Schedule the Project
Construction Methodology
Scope of Work
Define exactly what is to be built
Usually provided by plans and specifications.
In the case of Chan Chan, the ruins are the “as-builts”.
Scope of Work - Work Breakdown Structure
Typical Storeroom Complex at Rivero
Storeroom Complex in Model
Individual Storeroom
Scope of Work – Work Breakdown Structure
Quantity Survey
Calculate the amount/quantity of each piece of work
Usually measured from the plans and specifications.
In the case of Chan Chan, perform field measurements.
Detailed Quantity Survey of a Storeroom
Quantity survey of a storeroom
Original ConfigurationMassive interior adobe walls 11,110 1,910,920 9,895North Sector walls & structures 13,346 2,295,512 25,877Central Sector walls & structures 9,686 1,665,992 22,194Conchone walls 230 39,560 456
Burial Mound 14,334 2,465,448 9,180 9,551
Tapia Walls 24,840 20,400
Totals for Original Configuration 48,706 CM 8,377,432 EA 34,020 CM 88,373 SM
Massive Adobe Wall Addition 17,680 CM 3,040,960 EA 21,370 SM
Volume of Adobes
Number of Adobes
Volume of Tapia
Area of Plaster
Quantity Survey
Productivity - Unit Rates
Calculate the rate of production for each type of work.
Determined by construction techniques
Usually considered proprietary information by construction companies.
Published rates, experiments.
Sources of Productivity - Unit Rates Hand excavation: Field experiment* & contemporary rates
Making adobes: Informants, contemporary rates
Transporting adobes: Field & UN experiments*
Erecting adobes: Practitioner, contemporary rates
Tapia walls: Contemporary rates*
Plastering: Contemporary rates
Harvesting cana: UN studies*
Fab & erect roof: Conceptual estimate
* Rates based on data from underdeveloped countries.
Informant making adobes in the Moche Valley
Construction Techniques
Large adobes
Small adobes
Intermediate adobes
Construction Techniques
Small adobes
Speed leads forvertical alignment
Cana poles for horizontal alignment
Using story poles for horizontal alignment and speed leads for vertical alignment.
Construction Techniques
Story pole
Tapia Blocks
Construction Techniques
Rammed earth construction
Construction Techniques
Direct molding construction
Construction Techniques
Source
Hours Worked
Total Hours
Raw DataWilson 3 8 24 4.59 m3 5.23 hrs/m3
Means 5 8 40 5.09 m3 7.85 hrs/m3
Adjusted Rates
Wilson 5 1 8 40 4.59 m3 8.72 hrs/m3
Means 7 1 8 56 5.09 m3 11.00 hrs/m3
1 Raw data based upon a wheelbarrow, hose, machine mixer for mortar
Add 2 extra persons for manual mortar mixing and transport of mud and water.
Crew Size 4 to 6 Masons
Productivity Range % Optimistic 8.7 -12% Most Likely (Average) 9.9 0% Pessimistic 11.0 12%
(Wilson 2000: pers. comm.; RSMeans 1999: 134)
500
555
500
555
No. of Workers
No. of Adobes Installed
Volume of Adobes Installed
Unit Rate
Recap: Adobe Installation No. of average sized adobes installed per
hour
23hours per cubic meter per worker
2018
hours per cubic meter per worker
hours per cubic meter per worker
Productivity Rates
Recap of Productivity RatesCrew
Activity uom Optimistic Most Likely Pessimistic Size
Hand excavation CM 4.90 6.00 7.30 1Excavate walk-in wells CM 4.90 6.00 7.30 1Manufacture adobes CM 5.20 7.00 7.50 5Transport adobes CM 6.70 7.80 9.00 1Erect adobe structures CM 8.70 9.90 11.00 5Erect adobe walls 0-3m CM 8.70 9.90 11.00 5Erect adobe walls 3-6m CM 12.20 13.80 15.40 5Erect adobe walls 6-9m CM 15.70 17.70 19.80 5Erect tapia walls 0-3m CM 8.50 10.70 12.80 5Erect tapia walls 3-6m CM 11.90 14.90 17.90 5Erect tapia walls 6-9m CM 15.40 19.20 23.00 5Plaster walls 0-3m SM 0.57 0.83 0.98 2Plaster walls 3-6m SM 0.86 1.25 1.47 2Plaster walls 6-9m SM 1.15 1.66 1.96 2Harvest algorrobo LM 2.60 3.25 3.90 4Fabricate roof panels EA 23.90 29.80 36.50 2Erect roof panels EA 3.20 4.00 4.80 2
Labor hours per unit of measure
Project Estimate
Correlate quantities to productivity rates to calculate the estimated labor hours.
A x B = C
Adobe Shell
S-A-01 Manufacture Adobes 40.2 m3 7.0 hrs/m3 280 24%
S-A-02 Transport Adobes 40.2 m3 7.8 hrs/m3 315 27%
S-A-03 Erect adobe walls 40.2 m3 9.9 hrs/m3 396 33%
S-A-04 Plaster adobe walls 64.2 m2 0.83 hrs/m2 53 5%
S-A-05 Install clay floor 4.5 m2 0.95 hrs/m2 4 0.4%
Subtotal - Labor Estimate for Adobe Shell 1,049 89%
Roof
S-R-01Procure & Transport Cana Brava
1800 m 0.0262 hrs/m 47 4%
S-R-02Procure & Transport Cana de Guayaquil
60 m 0.1353 hrs/m 8 1%
S-R-03 Fabricate roof panels 4 ea. 16.0 hrs/ea. 64 5%
S-R-04 Erect roof panels 4 ea. 4.00 hrs/ea. 16 1%
Subtotal - Labor Estimate for Roof 135 11%
Total Labor Hours for Storeroom 1,184
TOTAL Labor Hours
Percent of Total
Project
Activity No.
Item DescriptionEstimated Quantity
Unit Rates
Project Estimate
Project Estimate
2.1 million labor hours
1. Establish Logical Sequences of Work
2. Determine Crew Sizes & Durations
3. Calculate Project Schedule
Work Plan - Scheduling
Factors Effecting Logical Sequences of Work
Laws of Nature
Constructability Issues / Curing Time
Logistics / Room to Work
Common Sense
Owner Requirements
Logical Sequencing of Work
Logical Sequencing of Work – Micro
ErectRoof
Panels
InstallClayFloor
ErectAdobeWalls
TransportAdobes
Manu-factureAdobes
FabricateRoof
Panels
StoreroomComplete
BeginStoreroom
Procurecanabrava
Procurecana
guayaquil
PlasterWalls
This wall came first
This wall abuts the first wall
Logical Sequencing of Work – Macro
Logical Sequencing of Work – Macro
Scheduling – Crew Sizes and Durations
Burial mound
South walls
Tapia walls &interior structure
Total number of workers
Sitework
250250
Results:
250 Workers
could have built it in
5 ½ Years
Calculate the Schedule - Macro
Effects on
Archaeological Theories
The compounds of Chan Chan were the palaces of the kings.
Each ruler built one such structure to house himself, be the seat of government, and serve as the center for the management of his wealth.
Split Inheritance aka 1 King 1 Compound
.. the palace passed to the king's corporation of secondary heirs after his death.
His principal heir became the next king of Chimor and built a new palace.
Split Inheritance aka 1 King 1 Compound
If true, the construction time must be rapid and well within the lifetime of the new king.
Split Inheritance aka 1 King 1 Compound
Based upon the data from Rivero, the construction effort and time was estimated for the remaining compounds.
The largest compound, Gran Chimu, is buildable in 9 years.
Split Inheritance aka 1 King 1 Compound
Rather than sequentially, the last four ciudadelas were built concurrently as pairs.
That, “rapid construction of the last four ciudadelas is compatible with the rise and formulation of quadripartition”
Dual Rule
Dual Rule
Velarde
Bandelier
8.3 years
Dual Rule
Tschudi
Rivero
8.5 years
Dual Rule
Tschudi
Rivero
Velarde
Bandelier
8.5 years
Dual RuleVelarde
Bandelier
16.8 years
Tschudi
Rivero
Could easily come from the local population of 30,000 without any major shifts in the local economy.
The decision to use imported workers from outlying areas would have been by choice not necessity. No need to feed or house workers from the provinces.
Production could be year ‘round.
The Workforce 250 - 1100
… theories regarding the Chimu concerning the control of mass labor and social complexity based solely on the construction of the monumental architecture of Chan Chan may need revisiting.
Ciudadela Rivero
Detailed analysis, renderings, and animations are available on my website.