RICH upgrade simulation: updates 11-2-2015 RICH upgrade-software meeting 1 S.Easo.
-
Upload
arabella-todd -
Category
Documents
-
view
218 -
download
2
Transcript of RICH upgrade simulation: updates 11-2-2015 RICH upgrade-software meeting 1 S.Easo.
1
RICH upgrade simulation: updates
11-2-2015
RICH upgrade-software meeting
S.Easo
2
Updates from LHCb tracking , PID algorithm
RICH 1 Optics : Fine tuning spherical mirror ROC
Plans : Evolutions of MAPMT array configurations
Outline
3
LHCb Tracking
• 2012-13 (TDR studies): No ‘upgrade tracking’ available for RICH studies Used current LHCb tracking geometry + different versions of RICH upgrade geometry Not a perfect , but a practical solution at the time.
2014 : ‘Upgrade tracking’ became available, so started using it for RICH. 2014 Feb : Upgrade/current tracking comparisons in terms of PID. Track quality parameters were not available. So assumed all long tracks are ‘good tracks’ as a first step.
2015 : Track ghost probability parameter available , Used this to filter the upgrade tracks used for RICH.
This talk: PID with some of the above tracking setups. They all use same PYTHIA (generator) and beam configurations . So expect only minor variations of PID performance among them.
• RICH performance depends on the tracks input to RICH.
4
Simulation Configuration
Gauss v47r0p1, Boole 29r3, Brunel v47r4
Tracking : Recent version as in Brunel v47r4 for upgrade/current LHCb
Luminosity : Lumi20 ( 2X 1034 cm2s-1 ) , no spillover
Bs ff events
RICH Optics:
• ROC 3800 mm, 3600 mm, 3650 mm• With/without photon plane shift of 100 mm.• Current standard setup in software: ROC 3800mm, no plane shift• RICH2 : large+ small pmts
PID Tuning: Current/Old tuning. Current tuning is default.
Several PID combinations: Different Tracking/PID Tuning/RICH Optics. Only a few combinations used in this presentation
5
Red: Upgrade LHCb Tracking + Tracks selected with ghost probability cut Blue: Upgrade LHCb Tracking + All tracks Black: Current LHCb Tracking + Tracks selected with ghost probability cut
PID from Upgrade LHCb trackingimproved compared to that fromCurrent LHCb tracking
RICH1: standard setup
6
RICH1 optics“out of focus”
Red: Upgrade LHCb Tracking + Tracks selected with ghost probability cut Cyan: Upgrade LHCb Tracking + All tracks Black: Current LHCb Tracking + Tracks selected with ghost probability cut
RICH1 optics:ROC= 3600 mm
PID from Upgrade LHCb tracking improved compared to that from Current LHCb tracking , for all optics
7
Upgrade tracking,ghost probability< 0.3
Red: RICH1 ROC 3800 mmBlack: RICH1 ROC 3800 mm, photon plane shift 100 mmBlue: RICH1 ROC 3600mm , photon plane shift 100 mmCyan : RICH1 ROC 3650 mm, photon plane shift 100 mm
Effect from photonplane shift recovered bychange in ROC
upgrade PID plots wth ‘recent best configuration’
8
Current LHCb tracking
Red: RICH1 ROC 3800 mmBlack: RICH1 ROC 3800 mm, photon plane shift 100 mmBlue: RICH1 ROC 3600mm , photon plane shift 100 mm
Upgrade tracking, : All tracks
• Effect from photon plane shift recovered by change in ROC• This conclusion on optics obtained , independent of the tracking used.
Effects from PID tuning
• Some tuning done in 2013• Now re-visiting with current versions• For illustration use tracks with 7.5 < P < 100 GeV/c on this page. (backup slide with full P range).
Blue: Current tuningMagenta: Old Tuning
All Plots:RICH1 ROC=3800 mm using upgrade tracking
Top Plot: Standard setup, no shift in photon plane
Bottom plot: Photon plane shift=100 mm
Tuning gave a small improvement inPID performance in both plots
10
Optics and PID tuning : Upgrade LHCb Tracking
Upgrade LHCb Tracking,Current PID Tuning
Upgrade LHCb TrackingOld PID Tuning
• Effect from photon plane shift recovered by change in ROC• This conclusion on optics obtained , is independent of the PID tuning used
with Upgrade LHCb tracking
Red: RICH1 ROC 3800 mmBlack: RICH1 ROC 3800 mm, photon plane shift 100 mmBlue: RICH1 ROC 3600mm , photon plane shift 100 mm
11
Optics and PID tuning : Current LHCb Tracking
Current LHCb Tracking,Current PID Tuning
Current LHCb TrackingOld PID Tuning
• Effect from photon plane shift recovered by change in ROC• This conclusion on optics obtained , is independent of the PID tuning used
with Current LHCb tracking
Red: RICH1 ROC 3800 mmBlack: RICH1 ROC 3800 mm, photon plane shift 100 mmBlue: RICH1 ROC 3600mm , photon plane shift 100 mm
12
Plans
• Once the exact ROC is decided, freeze the optics geometry for a while.
• Long term: Rebuild the PMT arrays in software, using the Elementary Cells.
• Further tuning of the PID algorithm
13
SUMMARY
PID performance verified with different tracking and PID tuning combinations.
The usage of ghost probability gives a minor improvement in PID performance
All the PID performances obtained are consistent with each other and are as expected.
14
BACKUP SLIDES
15
PID vs Momentum
Upgrade tracking, ghost probability <0.3RICH standard setup (ROC 3800 mm)
Current LHCb tracking, ghost probability <0.3RICH standard setup (ROC 3800 mm)
16
PID vs Momentum
Upgrade tracking, All tracksRICH standard setup (ROC 3800 mm)
Upgrade tracking, All tracksRICH standard setup (ROC 3800 mm)Old PID tuning
17
Red: Upgrade LHCb Tracking + Tracks selected with ghost probability cut Cyan: Upgrade LHCb Tracking + All tracks Black: Current LHCb Tracking + Tracks selected with ghost probability cut
RICH1 optics“out of focus”
PID from Upgrade LHCb trackingimproved over that fromCurrent LHCb tracking
18
Red: Upgrade LHCb Tracking + Tracks selected with ghost probability cut Cyan: Upgrade LHCb Tracking + All tracks Black: Current LHCb Tracking + Tracks selected with ghost probability cut
PID from Upgrade LHCb trackingimproved over that fromCurrent LHCb tracking
RICH1 optics:ROC= 3600 mm
19
Red: RICH1 ROC 3800 mmBlack: RICH1 ROC 3800 mm, photon plane shift 100 mmBlue: RICH1 ROC 3600mm , photon plane shift 100 mm
PID has sametrend as in upgrade tracking
Current LHCbtracking
20
Red: RICH1 ROC 3800 mmBlack: RICH1 ROC 3800 mm, photon plane shift 100 mmBlue: RICH1 ROC 3600mm , photon plane shift 100 mmCyan : RICH1 ROC 3650 mm, photon plane shift 100 mm
Upgrade tracking,All tracks
Effects from PID tuning
• Some tuning done in 2013• Now re-visiting with current versions• For illustration use tracks with 1.5 < P < 100 GeV/c on this page.
Blue: Current tuningMagenta: Old Tuning
All Plots:RICH1 ROC=3800 mmTop Plot: No shift in photon plane
Bottom plot: Photon plane shift=100 mm
Tuning improved the PID in general,apart from very low momentum tracksbelow 7.5 GeV/c. So a minor retuning forthis in the future.
Black: Current LHCb trackingGreen/Blue: Upgrade LHCb tracking
Blue: Upgrade tracking + RICH2 ‘all small’ PMTsRed: Upgrade tracking + RICH2 mixed PMTs
Red : used as ‘reference plot’ in Dec 2014.
Recapitulation