RI Distributed Generation Seminar - National GridSeminar May 10, 2018 . 2 ... greater), hydro...
Transcript of RI Distributed Generation Seminar - National GridSeminar May 10, 2018 . 2 ... greater), hydro...
RI Distributed Generation
Seminar
May 10, 2018
2
9:00 a.m. Welcome Message, Introductions, Presentation Overview – John Kennedy
9:10 a.m. Interconnection Process – Pam Palumbo
9:45 a.m. DG Legislation Updates – John Kennedy
10:00 a.m. Portal Demo – Sean Diamond and Adam Markopoulos
10:45 a.m. Question and Answer Session
11:00 a.m. Conclude
Agenda
3
Outdoor digging projects?
Call 811 first.
Thinking about putting in a fence, a pool or planting shrubs or trees?
The first thing to do is call 811 before your dig – it’s a free service. And it’s the law!!!
When you call 811, they’ll mark existing water lines, electric lines cables and natural gas line running underground.
When you make the free call to 811 a few days before you dig, you’ll help prevent unintended consequences such as injury to you or your family, damage to your property, utility service outages to the entire neighborhood and potential fines and repair costs.
4
DG Activity Trends - NE
Received 3,413 interconnection applications representing about 868 MW
January 2018 – April 2018, compared to 2,976 applications / 346 MW in same
time period CY2017.
Small (<100kW) Interconnection application are triggering large studies because
of the aggregate generation on the circuit.
5
DG Activity Trends - RI
Received 659 applications representing 273 MW January 2018 – April 2018
Compared to 787 applications representing 158 MW same time period CY2017
and 771 apps representing 44 MW same time period CY2016
6
DG Activity Trends - RI
Interconnected 446 applications representing 8 MW January 2018 – April 2018
Compared to 494 applications representing 7 MW same time period in CY2017
and 304 applications representing 3 MW same time period CY2016
DG Activity Trends RI – Cancelled Applications
DG Interconnection Process
Pam Palumbo
Energy Integration Consultant
Customer Energy Integration
8
ERV Basics
Distributed Generation
and the Electric Grid
Two Types of grid-connected DG:
9
Behind Meter:
DG system partially or fully supplies an on-site load.
Unused electricity exported back to the distribution system
Direct Connect / Stand-alone:
DG system does not supply an on-site load
Is connected directly to the distribution system
RI PUC Interconnection
Tariffs
The most recent RI PUC Interconnection tariff is titled “RIPUC #2163, Standards for Connecting Distributed Generation”.
Includes interconnection standards and renewable energy interconnection process.
Current version of “Standards for Connecting Distributed Generation” can be found at:
http://www9.nationalgridus.com/non_html/RI_DG_Interconnection_Tariff.pdf
The RI PUC recently adopted a revised net metering tariff titled “RIPUC #2169, Net Metering Provision".
Includes Eligible Net Metering Rate Classes and Technologies
Current version of the “Net Metering Provision“ can be found at:
http://www9.nationalgridus.com/non_html/Net%20Metering%20Tarrif%202169.pdf
10
Importance of the
Interconnection Process
11
Safety of utility workers and general public
No adverse impact to power quality, in terms of:
Islanding
Transient Voltage Conditions
Noise and Harmonics
Frequency
Voltage Level
Machine Reactive Capability
Per tariff: customers cannot interconnect without an
interconnection agreement and approval. You proceed at your own
risk if you don’t have utility approval
Billing implications
Interconnection Process
Steps
Pre-Application
Simplified and Expedited Application
Standard Application
Impact Study and Detailed Study
Conditional Approval
Construction
Witness Test
Authorization to Interconnect
http://ngridustest/narragansett/home/energyeff/4_interconnection-process.asp
12
Pre-Application Report
13
Customer provides:
Contact and alternative contact Information
Facility Location (street address with cross
streets, including town, and a Google Map
still picture and GPS coordinates):
Generation type, size (AC kW), single or
three phase, service configuration:
Stand-alone (no on-site load, not including
parasitic load)?
If there is existing service at the Proposed
Facility site, provide: Interconnecting
Customer Account Number
Site minimum and maximum (if available)
current or proposed electric loads:
Is new service or service upgrade needed?
Utility provides:
Circuit voltage, circuit number
Whether single or three phase is
available near site; If single phase –
distance from three phase service;
Aggregate of connected Facilities (kW)
on circuit;
Aggregate of not yet connected (kW)
on circuit
Whether the Interconnecting Customer
is served by an area network, a spot
network, or radial system;
Identification of feeders within ¼ mile
Other potential system constraints or
critical items
14
Everything starts with
the Application
A complete complex application package includes:
Complete application, signed and dated, with generator info
Pre-application (optional; required for projects over 500kW)
Application Fee ($3 / kW – $300 minimum, $2,500 maximum)
Standard Renewable DG: Feasibility fee in lieu of application fee
PE-Stamped 1-line diagram preferably showing relay controls
Site Diagram showing electric service location, generator location, AC Utility Disconnect, metering,
access to metering and disconnect, assessor’s plat map, survey plan. Google Earth shots are not
acceptable.
Supplemental Information including tech sheets, inverter islanding info, etc.
Schedule B if planning to Net Meter.
Site Control – proof of site control is required where applicable.
Documentation problems “stop the clock” (Reference ESB756 as a guide to avoid customer/contractor
holds in the process).
15
Everything starts with
the Application: Site Plan A complete complex application package includes:
ESB 756D Section 5.1.1.3 Site Plan
A site plan shall be submitted showing the location of major customer equipment, the Company equipment to be
installed on site, and site details that will be helpful to define accessibility of the site. The site plan shall show the
following equipment at minimum:
1. Interfacing transformer
2. Interrupting devices
3. Isolation device(s) (e.g. Generator Disconnect)
4. Point of Common Coupling (PCC)
5. Company pole number nearest the proposed PCC
6. Company line extension to site and from nearest Point of Interconnection
7. Restricted accesses, fences, gates and access controls
8. Existing and proposed Access road(s) including, at a minimum, road material, surface loading criteria, and
dimensions to confirm Company personnel and equipment access requirements are met.
9. Generator location
10. Existing service(s) Site plans shall be to scale with approximate distances indicated. In addition to site plan, the
Company may request an assessor map to determine property lines, wetlands and easements.
Interconnection Review
Paths
16
There are three different interconnection review paths a project can
follow based on generation type, size, customer load and the
characteristics of the grid where the system is to be located.
Simplified Review Path
Expedited Review Path
Standard Review Path
Non-Renewable DG
Renewable DG
17
Simplified Review Path
Less than 15 kW single phase, or less than 25 kW three phase
Review Process Simplified Process
Acknowledge Receipt of
Application (3 days)
Review Application for
Completeness 10 days
Complete Review of All
Screens 10 days
Send Executable
Agreement (Note 4) Done
Total Maximum Days 20 days
Notice/ Witness Test < 1 day with 10 day notice
or by mutual agreement
Simplified Process
Application Fee (covers
screens) 0 (Note 1)
Supplemental Review or
Additional Review (if
applicable)
N/A
Standard Interconnection
Initial Review N/A
Feasibility Study N/A
Impact Study or ISRDG N/A
Detailed Study (if required) N/A
Facility Upgrades N/A (Note 5)
Witness Test 0
18
Expedited Review Path Greater than 15 kW single phase, or greater than 25 kW three phase
Maximum size based on review of screens
Does not apply to non-listed inverters or other generators
Review Process Expedited Process
Acknowledge Receipt of
Application (3 days)
Review Application for
Completeness 10 days
Complete Review of All
Screens 25 days
Complete Supplemental
Review (if needed) 20 days
Send Executable
Agreement (Note 3) 10 days
Total Maximum Days 45/65 days (Note 4)
Notice/ Witness Test 1-2 days with 10 day notice
or by mutual agreement
Expedited Process
Application Fee (covers
screens)
$3/kW, minimum $300,
maximum $2500
Supplemental Review or
Additional Review (if
applicable)
Up to 10 engineering hours
at $125/hr ($1,250
maximum) (Note 2)
Standard Interconnection
Initial Review N/A
Feasibility Study N/A
Impact Study or ISRDG N/A
Detailed Study (if required) N/A
Facility Upgrades Actual Cost
O&M (Note 6) TBD
Witness Test Actual cost, up to $300
+ travel time (Note 7)
19
Standard Review Path
Non-Renewable DG Non-listed inverters or other generators (induction, synchronous, asynchronous)
Most Combined Heat and Power (CHP) systems
Review Process Standard Process
Acknowledge Receipt of Application (3 days)
Review Application for Completeness 10 days
Complete Standard Process Initial
Review 20 days
Send Follow-on Studies
Cost/Agreement 5 days
Complete Impact Study or ISRDG (if
requested) 55 days
Complete Detailed Study (if requested) 30 days
Send Executable Agreement (Note 3) 15 days
Total Maximum Days 135/155 days
(Note 5)
Notice/ Witness Test By mutual
agreement
Standard Process
Application Fee (covers
screens)
$3/kW, minimum $300,
maximum $2500
Supplemental Review or
Additional Review (if
applicable)
N/A
Standard Interconnection
Initial Review
Included in application fee
(if applicable)
Feasibility Study N/A
Impact Study or ISRDG Actual Cost (Note 3)
Detailed Study (if required) Actual Cost (Note 3)
Facility Upgrades Actual Cost
O&M (Note 6) TBD
Witness Test Actual Cost
20 20
Standard Review Path
Renewable DG Large-scale PV (500 kW or greater), large-scale wind turbines (500 kW or
greater), hydro facilities, anaerobic digestion, etc.
Review Process Standard Process
Acknowledge Receipt of Application (3 days)
Review Application for Completeness 10 days
Complete Standard Process Initial
Review
20 days if
feasibility study
not requested
Send Follow-on Studies
Cost/Agreements 5 days
Feasibility Study (if requested) 30 calendar days
Complete Impact Study or ISRDG (if
requested)
The shorter of 55
days or 90
calendar days
Complete Detailed Study (if requested) 30 days
Send Executable Agreement (Note 3) 15 days
Total Maximum Days Varies depending
on studies done
Notice/ Witness Test By mutual
agreement
Standard Process
Application Fee (covers
screens)
Feasibility Study Fee in lieu of
Application Fee
Feasibility Study Residential:
≤ 25 kW: $0, > 25 kW: $50
Non-residential:
≤100 kW: $100, ≤250 kW:
$300, 250 kW-1MW: $1,000,
> 1MW: $2,500
Impact Study or ISRDG Residential:
≤ 25 kW: $0, > 25 kW: $100
Non-residential:
≤100 kW: $500, ≤250 kW:
$1,000, 250 kW-1MW:
$5,000, > 1MW: $10,000
Detailed Study (if
required) Actual Cost (Note 3)
Facility Upgrades Actual Cost
O&M (Note 6) TBD
Witness Test Actual Cost
21
Interconnection Process:
Summary and Recommendations
Submit your interconnection application with National Grid early, during
conception phase before committing to buy no matter how simple or small
the DG might be.
You can always request general utility information about a specific location
from your utility by requesting a Pre-application Report
Large interconnection applications take longer to study
The Interconnection Tariff is a wealth of information
Interconnection timeframes do not apply to Electric Power System
construction if required.
Time frames are standard working days and do not include delays due to
missing information or force majeure events
ISO-NE notification not included in time frame.
Interconnection applications have increased significantly in the past few
years – APPLY EARLY!
National Grid Contacts &
Tariff Links
22
Director Kevin Kelly | (978) 725-1325
Managers - NE John Kennedy
(401) 784-7221
Will Kern
(781) 907-3023 Screening Team
Vishal Ahirrao
(781) 907-3002
MA Melissa Drury
508-897-5544
Andrea Agra
(781) 907-3040
Joshua Dibia
(516) 545-4778
Business Support Team
Jeffrey Crompton
(781) 907-1436
Jennifer Chalifoux
(978) 725-1029
Nicholae Gari
(781) 907-2018
Eric Munzert
(781) 907-3833
Ariella Cohen
(781) 907-1445
Andy Garsils
(516) 545-4682
Joseph Vuto
(781) 907-1435
John Gatti
(781) 907-3522
RI Patricia Matulaitis
(401) 267-6671
Bassey Iro
(781) 907-2522
Hannah Ferris
(401) 267-6619
Timothy Kounlavouth
(781) 907-3454
Brandon Lopes
(401) 267-6626
Sahir Shakir
(781) 907-3687
Evan Magno
tbd
Pamela Palumbo
(401) 267-6625
23
DG Legislation Update Discussion
John Kennedy
Manager
Customer Energy Integration
DG Legislation Update Discussion
Interconnection Applications received as of July 1, 2017 will be included in the new timelines resulting from DG Legislation passed last year.
The revised Standards for Interconnecting Distributed Generation tariff is pending RI PUC approval.
Highlights:
An executable interconnection service agreement must be delivered to the interconnecting renewable energy customer within 175
calendar days of a completed application, or 200 calendar days if a detailed study is required.
The electric distribution company must complete all system modifications by the later of the following dates: (i) 270 calendar days, or
360 calendar days if substation work is necessary, from the date of the electric distribution company's receipt of the executed
interconnection service agreement, or (ii) the interconnecting renewable energy customer's agreed upon extension of the time between
the execution of the interconnection services agreement and interconnection as set forth in writing.
System modification deadlines may not be extended due to customer delays in providing required information. The electric distribution
company must request and obtain all information prior to completion of the impact study.
Deadlines for completed system modifications will only be extended for events not within the control of the electric distribution company,
and include the following: (i) extended prohibitive weather, (ii) union work stoppage or force majeure, or (iii) third party delays, including,
without limitation, delays due to ISO-NE requirements. Such events must not be attributable to electric distribution company actions, and
cannot be resolved despite commercially reasonable efforts.
The electric distribution company must notify the interconnecting renewable energy customer in writing of the start of any claimed
deadline extension “as soon as practicable,” its cause, and when it concludes.
If a court of competent jurisdiction orders the electric distribution company to pay damages to the interconnecting renewable energy
customer, such damages are limited to actual damages arising directly from the electric distribution company’s failure to comply with the
requirements of this subsection. Such damages will be paid by the shareholders and are not recoverable from customers.
The electric distribution company is not liable for indirect, incidental, special, consequential, or punitive damages of any kind whatsoever
24
DG Legislation Update Discussion
Highlights continued:
Ways of Working Update
To serve the entire DG development community equitably, National Grid is required to efficiently facilitate the advancement of
interconnection applications through the interconnection process and adhere to the established timelines. This include s the cancellation
of applications that are not progressing in a timely manner.
DG Data Portal coming soon.
Customer Energy Integration “Job Owners” will now review applications for completeness as opposed to Screening Team members.
This allows them to be primary point of contact at the beginning of process and limit handoffs. Complete application packages are
required at time of application including proof of site control where applicable.
At time of application: complete application package is required – Google Earth shots are no longer accepted as site plan documents.
System Impact Study:
At day 50 of Impact Study a draft will be provided outlining any final customer requirements, e.g., one-line update, technical
information, site readiness information. These requirements must be completed prior to an Interconnection Service Agreement
being provided.
Once an Impact Study is delivered any changes to the Customer’s facility may result in a new interconnection application and
Impact Study being required along with associated fees.
Transmission Planning Studies
Transmission Planning Studies must be completed prior to Interconnection Service Agreements being provided. Agreements to
conduct the study will be provided once an Impact Study has reached the 20 business day mark.
25
Break
26
27
Rhode Island Application
Portal Demo
Sean Diamond - Process Excellence
and Adam Markopoulos - Customer Energy
Integration
Question and Answer
Contact for Follow-Up Questions:
Email: [email protected]
28
Thank you for Participating!
29
Other Information Resources
Commerce RI: http://www.commerceri.com
RI OER Website: http://www.energy.ri.gov/index.php
RI PUC Website: http://www.ripuc.org/utilityinfo/electric.html