RHM - ADAMS MISSION CHURCH BUILDING PROJECT
AFM Folweni Manase Branch
Phase I Erecting the steel structure with roof and isolated ceiling.
The vacant site in Manase (Adams Mission)
The Team from Gauteng arrivesThe off loading begins
Like puzzle pieces... The components of the structure is laid out
The first sections are made to stand
Making great progress. The roof about 80% completed!
Now for the last finishing touches
The view from inside
Phase II
Adding the side pannels (shade netting) During the next two weeks we will be preparing the
temporary side pannels made of sheet netting. These pannels will be added on all sides of the structure and will basically work like window blinds.
Phase III
Floor slab
The local church will start raising funds to pour the floor slab. In the meanwhile the ground will just be levelled completely and compacted. This will allow them to use the church even without the cement floor being in place.
Phase IVBuilding the permanent outer walls. The last phase will
be the building of permanent outer walls. Funds will be raised to buy building blocks for this purpose