RFP Design Architect Ver 1.4 rt Feb 27 15 - Squarespace · Indoor toddler play ... good condition...
Transcript of RFP Design Architect Ver 1.4 rt Feb 27 15 - Squarespace · Indoor toddler play ... good condition...
Prepared by and Property of Canadian Canoe Museum Page 2 of 25 Copyright retained by CCM. No reproduction or reuse in whole or in part without prior written consent of CCM
TABLE OF CONTENTS
1 EXECUTIVE SUMMARY .......................................................................................... 3
1.1 Facility ............................................................................................................................................... 3
1.2 Site .................................................................................................................................................... 5
2 BACKGROUND ....................................................................................................... 6
3 STRATEGIC PLAN .................................................................................................. 8
4 NEW MUSEUM FACILITY ..................................................................................... 10
5 DESCRIPTION OF SCOPE OF WORK FOR SUCCESSFUL ARCHITECT ......... 15
6 PROJECT REPORTING RELATIONSHIP ............................................................. 17
7 SCOPE OF SERVICE FOR SUCCESSFUL PROPONENT ................................... 18
7.1 General Requirements .................................................................................................................... 18
7.2 Scope of services ............................................................................................................................ 18
8 PROPOSED SCHEDULE ....................................................................................... 21
9 RFQ ........................................................................................................................ 22
9.1 Process ........................................................................................................................................... 22
9.2 Submittals ........................................................................................................................................ 23
9.3 Terms and Conditions of the RFQ .................................................................................................. 24
Prepared by and Property of Canadian Canoe Museum Page 3 of 25 Copyright retained by CCM. No reproduction or reuse in whole or in part without prior written consent of CCM
1 EXECUTIVE SUMMARY
1.1 FACILITY The facility is anticipated to be approximately 77,000 square feet of gross floor area located on
a single level with an anticipated hard cost of approximately $24 million dollars ($311.76 per sq
ft gross area) inclusive of a 10% contingency and exclusive of artifact display, FF&E, consultants,
soft costs and land. The facility is anticipated to include exterior ancillary features such as a
large east, north and south facing terrace, a porte‐cochere, canoe basin created by
modifications to the west canal wall and a seasonal boat storage house to support on water
programs (located a short walk north above the Lift Lock). The facility will be located on the
existing Lift Lock visitor centre and southwards to minimize disruption to the National Historic
site and will necessitate demolition of the existing structure.
The proposed space allocation is:
Canoe Exhibit – 15,000 Sq Ft
Canoe Exhibit Storage – 20,000 Sq Ft
Trent Severn Waterway Exhibit – 1,000 Sq Ft
Combined Administration, Gift Shop, Reception & Back of House –24,000 Sq Ft
The facility is intended to operate year round and is anticipated to attract approximately 60,000
visitors in its first year of operation
The ancillary facilities are designed to support both museum visitors and boaters extending the
museum and locking experience as well as bringing additional visitors to the facility. The
ancillary facilities will include:
Multifunction room and Pre‐function rooms seating 250 to 300 in banquet format
divisible into as many as three rooms of 150, 75 and 75. The facility is designed to
support weddings, corporate and charitable events and conferences. The room may
also serve for educational programs with First Nation Groups such as the Friendship
Center;
Full service restaurant (lunch/dinner) seating approximately 50 to 70;
Full service bar seating approximately 20 to 30 (lunch/dinner);
Café seating for 30 (all day);
Indoor toddler play area (parent supervised);
Prepared by and Property of Canadian Canoe Museum Page 4 of 25 Copyright retained by CCM. No reproduction or reuse in whole or in part without prior written consent of CCM
Terrace – Providing exterior seasonal seating expansion for café, bar, restaurant and
multifunction rooms
Exterior events area for interactive programs with First Nations groups and others
and a ceremonial tipi or longhouse
First Nation activities and events
Artisan activities, workshops and events
Canoe Basin created by reconfiguration of the west canal wall south of the historic
elements of the Lock 21 (Lift Lock)
Boat house for storage of canoes above Lock 21 for access to the upper canal
reaches
Mooring for at least five boats (visitor and overnight stay) out of the main channel
and with electrical hookup and access to potable water
In addition to broadening and supporting the museum experience, the ancillary facilities are
intended to create a financially sustainable facility that is less dependent on governmental
support and private donations for ongoing operations.
HRH Prince Andrew as Patron of the Museum and is involved in guiding and supporting the
strategic initiatives of the museum.
Prepared by and Property of Canadian Canoe Museum Page 5 of 25 Copyright retained by CCM. No reproduction or reuse in whole or in part without prior written consent of CCM
1.2 SITE
Theoutlineboxinblueshowsapossiblediagrammaticlocationofthenewcombinedmuseum.
Prepared by and Property of Canadian Canoe Museum Page 6 of 25 Copyright retained by CCM. No reproduction or reuse in whole or in part without prior written consent of CCM
2 BACKGROUND The Canadian Canoe Museum (CCM) grew out of a collection of canoes held by Kirk Wipper, a
Professor of Physical and Health Education at the University of Toronto, and a recipient of the
Order of Canada. In 1957, Wipper established a museum of his canoes at Camp Kandalore, just
north of Minden, Ontario, which was originally known as the Kanawa International Collection of
Canoes, Kayaks and Rowing Craft.
By the early 80s it was apparent that the collection was outgrowing the capacity of the Camp to
accommodate it, and that a new home and professional organization structure would be
required. In 1994, Wipper transferred his ownership of the collection to the newly‐formed
Canadian Canoe Museum, which also began investigations into a new and more accessible
location than the Camp.
The former Outboard Marine Corporation factory in Peterborough was acquired with City
assistance in the 1990’s. Located at 910 Monaghan Avenue in Peterborough and consisting of a
main administration building in relatively good condition and a larger warehouse structure in a
lesser state of repair. The relocated museum began operations in 1996 with the official opening
on July 1, 1997.
Despite some setbacks the museum has continued to grow and develop despite its industrial
setting. The museum offers a surprising and inspiring experience to a new visitor. It is not the
dry object‐based displays that one might expect. Through the use of stories, panel boards and
a wide variety of experiences – artisan workshops, actor animations, restorations and on‐water
programming the museum brings the experiences and pioneering spirit of the designers,
builders and users of canoes out from the past and places them into the modern Canadian
context.
The museum interweaves past, present and future in a unique manner through the medium of
the canoe. It offers the opportunity to address and reconcile matters of National interest such
as the history and culture of Canada prior to railways, First Nations heritage, the reconciliation
of First Nations experiences with those of the Euro centric text books, how rivers and trading
routes defined the paths of development that still drive growth today and how we might be
able to address the divide between French and English based cultures.
In September of 2010, the current strategic plan was adopted. Diligent efforts by the Board,
staff volunteers, members, donors and friends (past and present) has continued and has
resulted in the current situation where in 2011, a motion was passed in the Senate recognizing
Prepared by and Property of Canadian Canoe Museum Page 7 of 25 Copyright retained by CCM. No reproduction or reuse in whole or in part without prior written consent of CCM
the CCM and its collection as a “cultural asset of outstanding national significance…” and the
museum is quietly recognized as the de facto National Canoe Museum.
In recent years there have been a number of accolades received by the CCM. In 2006, Prince
Andrew became the Royal Patron of the CCM, visiting the museum in May of that year and
gifting it with three canoes. Shelagh Rogers, of CBC fame was our first of the Ambassador at
Large. More recently Shelagh has been joined by fellow CCM Ambassador at Large inductees
author Joseph Boyden and Les Stroud (aka Survivourman).
To realize on its full potential and achieve a financial plan that is sustainable over the long term,
the museum must take the next step into a mission appropriate site that will bring to fruition
the full scope of the museum that the visitors, volunteers, staff and the board already
recognize.
The site at the Lift Lock in Peterborough will combine two great Canadian cultural assets in one
location, leveraging the potential of both to drive visitors and experiences and create a
sustainable institution of enduring significance for the early history and culture of Canada.
Further information is available at www.canoemusuem.ca
27/02/2015 4:39:00 PM
Prepared by and Property of Canadian Canoe Museum Page 8 of 25 Copyright retained by CCM. No reproduction or reuse in whole or in part without prior written consent of CCM
3 STRATEGIC PLAN
CCM is focusing on the strengths demonstrated at its current facility conveying early
Canadian history and culture through rich stories and interactive experiences. Despite
its stark industrial exterior, barren parking lot and complete lack of open water, CCM is
consistently the most popular tourist destination in Peterborough (Trip Advisor). Once
inside, visitors are surprised and delighted by the experience and environment they
encounter. Rather than a dry and dusty set of canoes lined up by year, CCM wraps each
canoe and related artifact with a rich tapestry of experience and inspiration that leaves
visitors looking for more. The following are just four of thousands of positive comments
from our visitor book:
“World class professional museum. On par with any museum in existence. Great
work. Keep it up.”
“Avec le museé des civilizations et le muse du canot de Peterborough, j’ai
commence a comprendre le Canada. C’est passionnant”
“More than a Canadian Treasure – this is a world treasure” ; and
“A National treasure which should be recognized federally”
Through the medium of the canoe, these stories and tableaux’s bring to life past
cultures in a way that relates to the present. The principles of these stories are able to
address concerns and issues that embroil Canadian society today and provide guidance
to possible future resolutions. They provide relevant and compelling stories of physical
achievement and emotional fulfillment that can provide inspiration for the couch bound
youth of today. This relevance to today and the future is key to the sustainability of this
museum. Our experiential programs; artisanal crafts, canoe and paddle carving, on‐
water programming and educational animations bring to life these stories in a tangible
and enduring manner.
These are strategic advantages which are unique and not easily replicated. The CCM
canoe collection is exclusive and the supporting structure on which our stories and
experiences are built.
CCM is working on ways to bring these delights to the virtual world and has many novel
and innovative projects in progress that address how museums need to reinvent
themselves for the internet age. Passive displays, whether in situ or on line, are
harbingers of the rapidly receding past. The virtual museum will need to engage in a
27/02/2015 4:39:00 PM
Prepared by and Property of Canadian Canoe Museum Page 9 of 25 Copyright retained by CCM. No reproduction or reuse in whole or in part without prior written consent of CCM
constant multi‐dimensional dialogue with all its stakeholders and make its offering
relevant to the issues of the 21st century. We will pursue these opportunities regardless
of physical location.
On the ground in Peterborough, CCM is seeking a facility that will allow us to realize the
full strength of the above strategic plan and realize on the challenge of providing a fully
interactive and engaging experience that is aligned with the on line world yet offers
additional experiences to make a site visit worthwhile and compelling.
The Lift Lock, a National Historic Site, has the attributes that will allow us to meet and
exceed these expectations and provides:
A historical, water based setting that supports and reinforces CCM’s strategy of
stories and experiential learning with on water experiences;
Alignment with the national government on a national site;
The opportunity to leverage historical attendance at CCM and Lift Lock expanding
the audience and experience for both groups; and
A unique setting that provides sustainable and compelling advantages for the
ancillary facilities that will provide a dependable revenue stream to support both
museum operations in sustainable manner.
27/02/2015 4:39:00 PM
Prepared by and Property of Canadian Canoe Museum Page 10 of 25 Copyright retained by CCM. No reproduction or reuse in whole or in part without prior written consent of CCM
4 NEW MUSEUM FACILITY
CCM has considered and consulted on the following aspects of the site including:
The strategic plan of the museum
Fund raising opportunities
The history of the site
The context of the site within the Little Lake Master Plan and the Central Area
Master Plan from the City of Peterborough
The current Zoning and Official Plan designations
Stakeholders such as Parks Canada, the Downtown Business Improvement
Association, the Friendship Centre, the City of Peterborough, County of
Peterborough, Chamber of Commerce and Kawartha Tourism Board
National Monument Listings (Lift Lock and Canal)
Ownership boundary
Topography
Ingress and egress to the site
Parking
Bus and truck loading and unloading
Microclimate
Solar Exposure
Views and view corridors
Walking trail to Little Lake
Safely implementing seasonal on water programming at the lock basin by
reconfiguring the western canal wall south of the historic elements to provide a
canoe basin to the west of the main channel away from active channel vessel traffic
Canal based winter recreational activities
Potential environmental issues including water quality, federal and provincial environmental standards and approvals
Tourism data and drivers in the Peterborough area
Market conditions for the proposed ancillary facilities ‐ multiuse conference banquet
space, restaurant, bar, café and terrace
The proposed space summarised below is approximately 40% smaller than the total
space occupied today. Most of the efficiency gains are realized in the long term storage
of the collection which is reduced from an inefficiently utilized 60,000 feet down to
20,000 feet. This is realized in part by higher density storage and in part by de‐
27/02/2015 4:39:00 PM
Prepared by and Property of Canadian Canoe Museum Page 11 of 25 Copyright retained by CCM. No reproduction or reuse in whole or in part without prior written consent of CCM
accession of some redundant artifacts. The exhibition space and administration areas
are similar in size and the gift shop is 50% larger. The multi‐function room is over
double the size.
We have also included a thousand square feet of updated programming to replace the
Lift Lock visitor center currently on site that will now operate year round rather than
seasonally. The programming is proposed to be extended to cover both the Lift Lock
and Trent Severn waterway. The enlarged Gift Shop will operate year round and is
proposed to carry Parks Canada, Trent Severn and Lift Lock themed merchandise in
addition to the offerings from the Canoe Museum.
Parks Canada has proposed that the Lease line be limited to the footprint of the new
museum building(s) and attached exterior elements (e.g. terrace and porte cochere).
Exterior amenities such as the proposed canoe basin, mooring, use of exterior
greenspace and parking will be subject to a shared access agreement that will set out
the terms and conditions for use and control of these spaces and the obligations for
maintenance and repair.
The proposed program has several further amenities to extend and improve the visitor
experience to an attractive all season offering including:
Sit down restaurant serving lunch and dinner;
Small bar with bar service;
Café serving tea, coffee and snacks all day;
Exterior Terrace for weddings and al fresco dining;
Exterior events area for summer camps and other events;
Canoe basin for:
o Putting canoes and kayaks in and out of the canal;
o Allowing tourists to rent canoes for self‐paddle exploration of the canal;
o Providing, for a fee, guided canal tours in larger Voyageur style canoes
paddled by CCM staff on the Lift Lock, on the canal above the Lift Lock
and across Little Lake to downtown and Del Crary Park;
o Canoe workshops and summer camps
Slips for mooring of boats while visiting the Museum or staying overnight with
access to electrical connections and domestic fresh water and as a stop on canal
tours offered by other operators
Canoe boat house above the Lift Lock to support canoe workshops and camps
and self‐paddle;
Improvements to the walkway on the west side of the canal; and
27/02/2015 4:39:00 PM
Prepared by and Property of Canadian Canoe Museum Page 12 of 25 Copyright retained by CCM. No reproduction or reuse in whole or in part without prior written consent of CCM
Indoor Toddler and Exterior play areas.
These amenities are designed to attract and retain museum oriented visitors and other
visitors such as boaters, skaters and trail walkers and cyclists.
The new museum facility will also support strategic partnerships with groups that
enhance the museum’s mission and are likely to increase the profile and attendance of
the museum. We have entered into preliminary discussions with local First Nations
groups and artisanal society to understand how we may develop a program that is
financially sustainable and is supportive of all parties objectives for their organisations.
From these considerations, CCM is initially proposing a program as follows:
Area
Space Usable GUF Gross
Galleries Canoe Exhibits 15,000 incl 15,000
Parks Canada Exhibits 1,000 incl 1,000
Storage 20,000 incl 20,000
36,000 36,000
Retail Sales 1,250 incl 1,250
Retail Storage 100 incl 100
1,350 1,350
Administration
Office 1,875 30% 2,438
Board Room 800 30% 1,040
Small Meeting 400 30% 520
Servery 150 30% 195
Break room 300 30% 390
Washrooms 150 30% 195
Copy & Print 200 30% 260
Files & Storage 200 30% 260
4,075 5,298
Archives Storage 500 30% 650
Research Room 200 30% 260
Work Room 200 30% 260
900 1,170
27/02/2015 4:39:00 PM
Prepared by and Property of Canadian Canoe Museum Page 13 of 25 Copyright retained by CCM. No reproduction or reuse in whole or in part without prior written consent of CCM
Multi Purpose Multipurpose Room 3,900 incl 3,900
Pre‐Function 1,560 incl 1,560
Education Room 1,500 30% 1,950
Storage 400 incl 400
Service 800 incl 800
8,160 8,610
Work Shops Artesan 1,500 30% 1,950
Artesan Storage 100 30% 130
Curatorial 1,500 30% 1,950
Maintenance & Ops Engineering 1,000 30% 1,300
4,100 5,330
Food Services Café 750 30% 975
Restaurant 1,050 30% 1,365
Bar 625 30% 813
Kitchen 3,500 30% 4,550
Gard Mange 400 30% 520
Pastry & Chocolate 400 30% 520
6,725 8,743
Public Support Lobby 1,500 incl 1,500
Reception & Admission 200 incl 200
Play Area 500 incl 500
Washrooms ‐ Education 400 30% 520
Washrooms ‐ Lobby 300 30% 390
Washrooms ‐ Restaurant & Banquet 600 30% 780
Coat Room 200 30% 260
3,700 4,150
Back of House Shipping & Receiving 500 30% 650
Dry Waste & Recycling 200 30% 260
Wet Waste 100 30% 130
Mechnical Room(s) 3,000 30% 3,900
IT/AV Room 400 30% 520
Operations storage 400 30% 520
Exterior events storage 300 30% 390
4,900 6,370
69,910 77,020
Exterior Terrace 4,000 4,000
27/02/2015 4:39:00 PM
Prepared by and Property of Canadian Canoe Museum Page 14 of 25 Copyright retained by CCM. No reproduction or reuse in whole or in part without prior written consent of CCM
Porte Cochere & Entrance 1,500 1,500
Boat House North of Lock 21 900 900
The facility is intended to provide an engaging, extended and interactive experience that
offers multiple routes to be introduced to and access the stories, culture and history
that the Canoe Museum offers:
Visitors
Canoeists
Boaters
Diners
Parents with a toddlers and children
Attendees at a business conference or wedding
Members of the First Nations
Canal skaters
Artisans
The ancillary facilities will allow visitors to extend their visit, experience the canoe on
water as a learner, Voyageur, tripper or naturalist and relax while shopping, over coffee
or a meal or while waiting for other family members participating in a canoe trip or
skating on the canal.
27/02/2015 4:39:00 PM
Prepared by and Property of Canadian Canoe Museum Page 15 of 25 Copyright retained by CCM. No reproduction or reuse in whole or in part without prior written consent of CCM
5 DESCRIPTION OF SCOPE OF WORK FOR SUCCESSFUL ARCHITECT The Building refers to that portion of the project to be built in accordance with the Building Plans and Specifications. The Architect will be responsible for the architectural design and construction documents for the Building and the oversight, direction and coordination with all other consultants including but not limited to Interiors, Engineering, Testing, Quality Control and Exhibit Design. The architect will be designated as the Consultant under the Construction Contract and will be responsible for Construction Oversight including approving Project Progress Draws, Change Orders, Change Directives and such other duties as required by standard CCDC forms. The Architect will not be responsible for Project Management or Quantity Surveying. The following list outlines the scope of the Building construction to be addressed by the Architect’s Scope of Work. The Building scope of work includes but is not limited to:
Building structure
Foundations and retaining walls
Waterproofing and Damp proofing including any traffic membranes and toppings
Roof membrane and flashing
Exterior walls and weather enclosure including windows, curtain and/or window wall
Interior Finishes
Doors and Hardware
Insulation and air vapor barrier to all external surfaces
Decorative paving at ground level
Main entrances and lobby
All secondary entrances and egress
Elevators including elevator interiors
Elevator machine rooms
Egress stairwells
Male and Female toilets
Mechanical, electrical and telecommunications spaces
Interior finishes for all service spaces, toilets and egress routes
Fire pumps, standpipes and smoke control
Sprinklers (RCP)
Main Fire Alarm Annunciator Panel
Fire detectors and pull stations
Suspended ceiling systems
All exterior lighting including building and Lift Lock feature lighting
27/02/2015 4:39:00 PM
Prepared by and Property of Canadian Canoe Museum Page 16 of 25 Copyright retained by CCM. No reproduction or reuse in whole or in part without prior written consent of CCM
Main HVAC systems including risers, cooling towers, fans etc. and local distribution.
Vertical and Horizontal Distribution of the electrical and plumbing throughout the Building
Main lighting control and energy monitoring system
Complete communications raceway system, terminating in the main communication room in the basement
Fiber optic and copper based telecommunication carrier services to the building main telecommunications/telephone room
backbone cabling requirements, connected to the main telecommunications room
Lightning protection system
Loading dock and related equipment (i.e. levelers, pads, etc.)
Soft and hard landscaping
Relocation of the west canal wall to provide a canoe basin and boat mooring
Exterior irrigation system
Access and Egress to the site
Utility connections
Standby Power for life safety systems with the potential to support other building systems and supply excess power to the grid
Storm water management in accordance with governmental regulations including on site storage as required to meet code
Obtaining permits and governmental approvals
Compliance with OBC and all other governing codes and regulations
Compliance with Parks Canada requirements
Compliance with Heritage requirements under the National monument listings
Oversight of Environmental approvals at federal and provincial level to relocate canal walls
Coordination, direction and oversight of all consultants
Coordination and oversight of general and trade contractors and suppliers
Coordination with Project Manager and Quantity Surveyor Context of the site within the City of Peterborough’s Little Lake Master Plan and the Central Area Master Plan
Minimum 30 meter operational setback from the canal walls
Canal‐based winter recreational activities
27/02/2015 4:39:00 PM
Prepared by and Property of Canadian Canoe Museum Page 17 of 25 Copyright retained by CCM. No reproduction or reuse in whole or in part without prior written consent of CCM
6 PROJECT REPORTING RELATIONSHIP
CCM
ARCHITECT
Parks Canada
Project Manager
Structural
Building Services
Exhibit Design
Specialist Consultants
27/02/2015 4:39:00 PM
Prepared by and Property of Canadian Canoe Museum Page 18 of 25 Copyright retained by CCM. No reproduction or reuse in whole or in part without prior written consent of CCM
7 SCOPE OF SERVICE FOR SUCCESSFUL PROPONENT
7.1 GENERAL REQUIREMENTS The following expectations are only with respect to the successful Proponent CCM expects the Architect to provide Concept, Schematic and Design Development and Construction Document services for the Building and the direction, oversight and coordination with all other engineers and consultants retained to provide Designs, Specialist Recommendations and Reports and Construction Documents for the Building The Project Architect will be responsible for providing the knowledge, experience and detailed design expertise to implement the Building. The Architect will also be responsible for the overall coordination and management of the design of the project including the preparation of agenda and minutes for all project meetings, coordination of plans and specifications with engineers and specialty consultants.
7.2 SCOPE OF SERVICES Provide architectural design services to the Canadian Canoe Museum (“CCM or Client”) pursuant to the supervision of Richard Tucker (“Project Manager”) and to the approval of the regulatory authorities including but not limited to the following matters:
Review of existing surveys and studies
Review of the building budget. The consultant is required to develop a design within the proposed budget.
Provide suggestions on potential improvements to the design and existing information base for review and possible action by CCM
Research comparable projects for use as benchmarks for the proposed design. Provide a complete presentation to CCM of the research including the recommendations for benchmark projects. Consultant is to arrange for and coordinate visits to benchmark facilities if appropriate. The cost of such visit or visits is to be extra to the Contract.
Analyze CCM requirements and standards. Identify potential conflicts between the design and the standards and provide recommendations on potential solutions
Prepare presentation materials and present the project to CCM, City and County of Peterborough, Parks Canada, Federal and Provincial governments, the public, museum membership, staff and directors and major and founding donors
Assist in the preparation of specialty presentation materials such as scale models (do not include for the cost of scale models)
Develop several concept designs for the building based on the approved program
27/02/2015 4:39:00 PM
Prepared by and Property of Canadian Canoe Museum Page 19 of 25 Copyright retained by CCM. No reproduction or reuse in whole or in part without prior written consent of CCM
Obtain approval of the Concept Design from CCM, Parks Canada and the City of Peterborough
Develop several schematic designs which illustrate the implementation of the approved Concept Design. Provide working models and renderings as appropriate to fully illustrate the proposed design(s). Obtain approval from CCM and Parks Canada
Develop a detailed design from the approved schematic plan(s) which illustrates the implementation of the approved plans on all floors. Include several alternative material sample boards to fully illustrate the proposed design. Obtain approval from CCM and Parks Canada.
Oversee the production of construction documents to ensure compliance with the design documents
Conduct regular on site progress inspections (minimum monthly) to ensure compliance with the design documents
Respond to RFI’s and SI’s within two business days
Direct and coordinate schematic and design development documents with all consultants including but not limited to:
Interior Designer Structural Mechanical Elevators Electrical Life Safety Security Communications IT Acoustic Amenities Graphic Design Landscape Project Manager Building Manager Exhibits Food Services Environmental Historical Archeological
All design documents are to be fully coordinated. It is the Architects responsibility to ensure that all documents are fully coordinated prior to being issued for tender.
Provide for ongoing coordination with trades, supplier and contractors
Attendance at regular project meetings as well as other coordination meetings
Provide monthly progress reports to CCM during the design process
27/02/2015 4:39:00 PM
Prepared by and Property of Canadian Canoe Museum Page 20 of 25 Copyright retained by CCM. No reproduction or reuse in whole or in part without prior written consent of CCM
Obtain planning approvals required by governmental regulation as a pre‐condition to the issuance of a building permit (do not include the cost of said permits)
Obtain with specialized consultants all required approvals from CCM, Parks Canada, Environment Canada, Ministry of Natural Resources and the City of Peterborough
Include for all redesign as required to obtain governmental approvals, approvals by CCM and Parks Canada and in the event the design exceeds the agreed budget. Re‐design caused by a change initiated by CCM or Parks Canada after approval of a design stage is excluded from this provision.
Provide a deficiency list on substantial completion. Regularly update the deficiency list and provide follow up until the deficiency list is complete in all respects. Consultant is to provide final certificates of completion and compliance to CCM, Parks Canada and all sources of finance and the regulatory authorities
Provide for review of the works in one year and provide another deficiency list for warranty defects.
Consultant is to quote as an Identified Price (one that may be deleted from the proposal) for errors & omissions and liability coverage with a minimum available amount of $5,000,000 over and above all legal costs and waiver of subrogation. Provide a certificate from the insurance company to CCM, Parks Canada and the sources of finance. Consultant to maintain E&O insurance in effect for a minimum period of six years following substantial completion of the work on claims made basis.
Architect to provide all services ancillary to the above scope of work to provide a first rate, high quality design service that is complete in all respects to a project of this scope and quality.
27/02/2015 4:39:00 PM
Prepared by and Property of Canadian Canoe Museum Page 21 of 25 Copyright retained by CCM. No reproduction or reuse in whole or in part without prior written consent of CCM
8 PROPOSED SCHEDULE The Proposed Schedule of the Project is shown below. The schedule is likely to be effected by matters beyond the control of CCM and is subject to change at any time without prior notice.
March 5, 2015 Request for Qualification (“RFQ”) Available
March 30, 2015 RFQ Submission due to CCM
March 31 – April 29, 2015
Review of RFQ Submissions
April 30, 2015 CCM selects short list for Design Competition (3 to 5 proponents)
May 1, 2014 to June 29, 2015
Design Competition
June 30, 2015 to September 15, 2015
Selection Process and Presentations
September, 2015 Select Preferred Design
October, 2015 onwards Secure Capital Investment & Donor Presentations
2017 Target Groundbreaking
27/02/2015 4:39:00 PM
Prepared by and Property of Canadian Canoe Museum Page 22 of 25 Copyright retained by CCM. No reproduction or reuse in whole or in part without prior written consent of CCM
9 RFQ
9.1 PROCESS CCM is intending to implement a two stage process to select an Architect for the new Canadian Canoe Museum Project. This RFQ is Stage One and will result in the selection of a short list of Architects to continue further with the process and provide a concept design.
Stage One – RFQ: Select a short list of Architects (between 3 and 5) from received submissions who will be asked to compete in a design competition. Stage One duration is anticipated to take approximately two months from initial announcement through selection of a short list.
Stage Two – Design Competition with Service Fee CCM will request that the short listed Architects develop a Concept Design that will include floor plans, colored site plan and colored rendering(s). The architects will also be requested to make several presentations to at least CCM, Parks Canada, City of Peterborough and a public open house. CCM will select a winning design, if any, from the submissions. A fixed service fee will be paid to each of the short listed Architects who are not selected by CCM. Stage Two duration is anticipated to take approximately four and a half months from initiation through selection with approximately 6 weeks for the design period. The winning Architect, if any, will be awarded the contract for the design of the museum.
The selected concept design will be used for the purposes of seeking capital investment in the project from all levels of government as well as private and corporate donors. Given the nature and focus of the museum, CCM is targeting the Canadian sesquicentennial in 2017 to provide focus and drive to the investment efforts. If successful, CCM plans to raise investment through 2015 and 2016 with groundbreaking in 2017. CCM owns its current site free and clear of debt which is conservatively valued at in excess of $5 million. The site will be sold “as‐is” to provide funding for the new museum.
27/02/2015 4:39:00 PM
Prepared by and Property of Canadian Canoe Museum Page 23 of 25 Copyright retained by CCM. No reproduction or reuse in whole or in part without prior written consent of CCM
9.2 SUBMITTALS In evaluating the RFQ submissions, CCM is particularly interested in the experience of the firm and the staff the Architect is proposing. We are interested in the project experience and resource depth of the firm and the identity and name of the proposed Designer and Project Architect, their recent experience in the project type and who have good references from completed relevant projects. Please submit the following information in hard copy (5 copies) at the address below or in Adobe pdf soft copy (version 9 or higher) via USB drive or CCM drop box at http://www.canoemuseum.ca/upload on or before 5 pm EST on the RFQ Due Date (see section 8):
Background information on the proponent including: o Firm name o Contact name, address, phone number and e‐mail o Structure of the proponent (e.g. individual, corporation, partnership); o Number of years in business o Approximate average annual project volume (CDN dollars hard cost) for
each of the past three years o Aggregate number of claims made by clients against the architects PI
insurance in the last three years and the approximate aggregate face value of the claims (CDN Dollars)
o Organizational chart of the proponent showing main executive and management positons and names
o Prior experience with: Similar projects; Other Not for Profits; and Museums
Describe unique skills, resources and abilities that make the proponent particularly well suited to the proposed project;
Resume(s) for the individual(s) who will be leading the project for the proponent;
Three current or past clients who CCM may contact for references;
Confirmation that the Architect is willing to execute a non‐disclosure agreement with CCM to protect CCM information if they are short listed for Stage 2
Respondents may visit the museum at any time during regular museum hours (available on our web site). Please state “RFQ Proponent” to gain access to the museum without admission charge. Submit hard copy and USB drive responses to the RFQ in a sealed envelope to:
The Canadian Canoe Museum 910 Monaghan Road Peterborough, Ontario K9J 5K4
27/02/2015 4:39:00 PM
Prepared by and Property of Canadian Canoe Museum Page 24 of 25 Copyright retained by CCM. No reproduction or reuse in whole or in part without prior written consent of CCM
Attention: RFQ CCM is not planning an interview process for the RFQ at this time. However, for those submissions which may be short listed, CCM may decide to hold interviews at very short notice. The leader of the project team, the Lead Designer and Project Architect who will work on the project on a daily basis will be expected to attend such interview at a minimum. The interview will provide an opportunity for an exchange of questions and clarifications between CCM and the proponent’s project team. CCM is not interested in the full project team at this time. The purpose of the RFQ is to select a short list of architects for a concept design competition. CCM will not consider submissions or parts of submissions for other disciplines as part of the RFQ. The intent is that the Architect will identify and propose engineers and specialist consultants required for the Project as part of Stage 2 Design Competition. International architects will be requested in Stage 2 to partner with a well‐qualified Canadian based Architectural Firm for production of Construction Documents. International proponents are specifically directed to not pre‐arrange, commit to or enter into any partnerships or agreements with Canadian Firms for the RFQ (Stage One). For successful International proponents the selection of Canadian Partners will take place as part of Stage 2. Proposed partner firms will need to be approved by CCM in advance of entering into any agreement between the firms with respect to this project.
9.3 TERMS AND CONDITIONS OF THE RFQ By requesting and receiving this RFQ, the Proponent agrees that the contents of this RFQ are strictly confidential. The Proponent agrees and acknowledges that the release by the Proponent or its staff of any information pertaining to this RFQ agrees to indemnify CCM from direct and indirect damages and losses arising as a result of such release. This confidentiality provision will continue for two years after the date of receipt of the RFQ by the proponent regardless of whether or not:
1. The proponent is successful in providing design services to CCM; and 2. The project proceeds.
The proponent will not be held responsible for information concerning the Project that without the involvement of the Proponent or its staff is released to the public By providing a response to this RFQ, the proponents understand and agree that the review of the responses to the RFQ and the selection of a preferred proponent or proponents involves considering many diverse factors and qualitative matters for which CCM believes quantitative analysis is not appropriate including but not limited to relevancy of other work and responses from references.
27/02/2015 4:39:00 PM
Prepared by and Property of Canadian Canoe Museum Page 25 of 25 Copyright retained by CCM. No reproduction or reuse in whole or in part without prior written consent of CCM
The relative merit and value of such factors and the quality of the responses provided by the proponents are best judged by CCM in its sole discretion. As a result, CCM reserves the right in its sole discretion to:
1. Reject some, any and all proposals; 2. Review with any or all proponents on the contents and scope of
their responses 3. Deem proposals acceptable even if matters in the RFQ are not
completely or properly addressed 4. Reject bids that may comply with the RFQ in form 5. Accept or reject proposals that may or may not comply with the
RFQ 6. Request additional submissions or clarifications on none, some or
all proposals 7. Request interviews with none, some or all proponents 8. Short list some or all proposals for further consideration,
negotiations and/or interviews Proponent understands and agrees that CCM will not provide post‐selection debriefs, autopsy’s of unsuccessful submissions nor rational and explanations for the selection of the winning proposals or the selection process Proponents will not be compensated for any costs, fees, time or expenses incurred in the preparation or submission of a response to the RFQ regardless of the outcome. CCM is not requesting the submission of designs, proprietary trade concepts, confidential information or intellectual property from the proponents and strongly recommends against any such submission. Any such material received by CCM from a proponent will be deemed to be available in the public domain and as such proponents will not be compensated or reimbursed for any designs, proprietary trade concepts, confidential information or intellectual property submitted to CCM whether used by CCM or not. By submitting designs, proprietary trade concepts, confidential information or intellectual property, the proponent waives any and all claims for the use of such material by CCM in any manner and explicitly agrees to use by CCM without royalties, fees, charges, claims, limitations or costs of any kind. The RFQ Document and its contents remain the property of CCM and may not be reproduced in whole or in part or used in any other manner without the express written consent of CCM. Any questions regarding the RFQ may be emailed to Richard Tucker at [email protected]