RFP# 99FY12
Ashlawn ES/Williamsburg
ESJune 8, 2012
Need for More Capacity• Driven by increases in enrollment
system-wide – 18% increase in enrollment in 5
years
– 83 relocatable classrooms in place today
– Additional relocatables this summer
• Continued growth in number of births and County population and changing housing market suggest increases will continue for the foreseeable future 2
Cohort Analysis
3
Projected Capacity NeedK-12 Enrollment Projections 2012-2021
17000
19000
21000
23000
25000
27000
29000
31000
33000
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
Year
Stu
de
nts
5 Year Linear Regression5 Year Average Rate of Change3 Year Average Rate of ChangeIncrease of 2% Per YearIncrease of 3% Per Year
4
Projected Capacity Deficit
+ Capacity numbers do not include relocatable capacity.*Enrollment numbers do not include some alternative education programs. 5
Capacity Planning Process Goals
1. Respond to increasing enrollment by
adding permanent building
capacity to APS as part of the
Capital Improvement Plan
2. Achieve the plan for additional seats
through a transparent, structured,
and inclusive process
6
School Board Evaluation Criteria
Optimize Impact on Capacity
• Flexibility of the solution• Larger impact of the solution• Increase number of seats at
schools with specific admission policies
• Number of seats generated• Relieving crowding in schools
of critical capacity need
Minimize Variation from Preferred School Size
• Maintain preferred seat range
Neighborhood Resources
• Impact on playgrounds• Impact on playfields• Impact on parking• Impact on green space• Neighborhood impact
Optimize Operational Effectiveness
• Minimize administrative impact
• Equity of space utilization• Impact on transportation
structure
7
Criteria Weights as Established by School Board
8
Community Outreach – To Date
• 8 Civic Associations
• 8 PTA Meetings
• 5 School Board Work Sessions
• 5 Community Updates
• Various Staff, County, & Citizen Meetings– Evaluation Committee
– Facilities Advisory Council & PCS
– Public Facilities Review Committee
9
Community Outreach – Future
• BLPC APS Building Level Planning Committee
• PFRC Arlington County Public Facilities Review Committee
10
All APS/ Select County Sites
CAPITAL IMPROVEMENT PLAN 11
Option Set E: 2 New Schools & Additions
ID Project Quad ScoreProject Cost
(2011 $)
Addl Elem Cap
Current Cap
Final Cap
05 ATS 12-Room Addition NW 0.4294 13,900,000 225 465 690
08Ashlawn 12-Room Addition
NW 0.5821 13,900,000 225 459 684
15 Carlin Springs/Kenmore New Choice ES
SW 0.5856 40,145,000 600 0 600
41 McKinley 12-Room Addition NW 0.4833 13,900,000 225 443 668
59 Williamsburg - New Neighborhood ES
NE/NW 0.5616 40,145,000 600 0 600
Total (5 projects) 121,990,000 1875
12
Ten-Year CIP
• Ten-year CIP totals $538 million
• Adds approximately 4,800 new seats (2/3 of projected capacity deficit)
• Major Construction – Capital Reserve– Bonds
• Minor Construction/Major Maintenance (MC/MM)– Current Revenues
13
CIP Years 1-5Opening of New Elementary
Seats • School Opening Year (Fall)
– 2014: 225 seats at Ashlawn
– 2015: 600 seats at new neighborhood
school (WMS campus)
– 2016: 450 additional seats at McKinley &
ATS
– 2017: 600 seats at new choice school
(CS/Kenmore campus) 14
CIP Years 6-10Additional Elementary
Capacity• First projects achieve good balance of enrollment to capacity
• Need to re-examine model criteria and re-score options based on new boundaries and utilization rates
• Add’l 1,200 seats needed in years 6-10
• Funding needed to create 600 seats (locations TBD)
15
CIP Years 6-10Secondary Options
1. Develop robust list of secondary options (construction and non-building)
2. Re-examine criteria and rating scales for secondary capacity options
3. Continue to monitor growth and identify site options
4. Focus on secondary school building options in 2014 CIP/capacity planning process
5. Funding needed to create 2,300 seats (locations TBD) 16
Proposed Capacity Funding
• 2012: $46.8M (1 addition; 1 new school)
• 2014: $70.9M (2 additions; 1 new school)
• 2016:
• 2018:
• 2020:
$51 MElementar
y600 seats
$51 MElementar
y600 seats
$127 M
Middle1,500 seats
$127 M
Middle1,500 seats
$63 MHigh
800 seats
$63 MHigh
800 seats
17
Ten-Year CIP Funding
• Major Construction
– Capital Reserve funded• Ashlawn 12-Room Addition $14.9M• Williamsburg - new ES – design $
4.0M
18
Ten-Year CIP Funding• Major Construction
– Bond funded• Wakefield HS (2010 bond) $ 29.1M• Fiber Project/C-net (2010 bond) $ 0.3M• ATS 12-Room Addition $ 16.1M• McKinley 12-Room Addition $ 16.1M• Carlin Springs/Kenmore new ES $ 46.4M• Williamsburg - new ES – construction $ 39.1M• HVAC & Roofing (20-yr useful life) $ 34.6M• Infrastructure Projects (20-yr useful life) $ 21.0M• Capacity Projects – Years 6-10 $253.0M
19
Ashlawn Schedule
20
Williamsburg Schedule
21