Revista 2 Articulos de Diseño de Minas Sub Level Caving

download Revista 2 Articulos de Diseño de Minas Sub Level Caving

of 12

Transcript of Revista 2 Articulos de Diseño de Minas Sub Level Caving

  • 8/20/2019 Revista 2 Articulos de Diseño de Minas Sub Level Caving

    1/27

    The Captain's pit in Malmberget. Photo courtesy of LKAB

    A U S T R A L I A N C E N T R E F O R G E O M E C H A N I C S V o l u m e N o . 3 3 D e c e m b e r 2 0 0 9

    NEWSLETTER

    The views expressed in this newsletter are those ofthe authors and may not necessarily reflect thoseof the Australian Centre for Geomechanics.

    Continued page 2

    Sublevel caving — past and

    future

    N THIS EDITION• Sublevel caving – past and future, Page 1• In-pit risks, Page 7 • Mine closure planning, Page 11• Mining-induced seismicity, Page 15• Tailings disposal, Page 17 • Mine tailing solutions, Page 20• Increasing value of paste, Page 21• ACG event schedule, Page 24

    by William Hustrulid, University of Utah; and theColorado School of Mines, USA, and Rudolph Kvapil, USA

    www.minewaste2010.com

    29 September – 1 October 2010,

    Perth, Western Australia

    Abstracts due 1 March 2010

    IntroductionThe sublevel caving technique according to

    early mining books (Peele, 1918) evolved in

    the U.S. from top slicing. It was a logical next

    step in the mine geometry scale-up process.

    Block caving, in turn, was the logical scale-up

    from sublevel caving.

     Janelid (1972) indicates, “ In the rst

    application of sublevel caving, the ore was not

    drilled and blasted completely between twosublevels, but certain parts were broken by

    induced caving (hence the name sublevel caving).

     As the method is applied today, the whole

    quantity of ore between the different sublevels

    is broken (or at least should be) using controlled

    drilling and blasting. If this is done in a proper

    and rational way, there are good possibilities

    of developing a mining method which can be

    applied, technically as well as economically, on

    any orebody of suitable size, location and rock

    mechanical properties .” 

    In spite of some searching, the modern

    origins of today’s version could not be

    clearly identied. Possibly it was developed

    in the iron mines of Sweden. Janelid (1972)

    indicates, “For a long time, sublevel caving wasthe predominant mining method at Grängesberg.

    During the last ten years (since about 1960),

    however, block caving has given 70% of the

    production.” 

    In 1960, the sublevel caving technique

    was being used by 19 Swedish mines with a

    Mine Waste 2010 will tackle the full

    range of issues that constitute risks

    in the management of mining wastes,

    particularly tailings and waste risk.

    This forum will encourage debate

    amongst practitioners, researchers and

    regulators about the key shortcomings

    in industry’s current understanding

    of the performance of mining waste

    storage facilities and associated risks

    faced by owners and operators of these

    facilities.

    First International Seminar onthe Reduction of Risk in the

    Management of Tailingsand Mine Waste

  • 8/20/2019 Revista 2 Articulos de Diseño de Minas Sub Level Caving

    2/272 Australian Centre for Geomechanics • December 2009 Newsletter

    Continued from page 1

    © Copyright 2009. Australian Centre for Geomechanics (ACG), The University of Western Australia (UWA). All rights reserved. No part of this newsletter

    may be reproduced, stored or transmitted in any form without the prior written permission of the Australian Centre for Geomechanics, The University of

    Western Australia.

    The information contained in this newsletter is for general educational and informative purposes only. Except to the extent required by law, UWA and the

    ACG make no representations or warranties express or implied as to the accuracy, reliability or completeness of the information contained therein.

    To the extent permitted by law, UWA and the ACG exclude all liability for loss or damage of any kind at all (including indirect or consequential loss ordamage) arising from the information in this newsletter or use of such information. You acknowledge that the information provided in this newsletter is

    to assist you with undertaking your own enquiries and analyses and that you should seek independent professional advice before acting in reliance on the

    information contained therein.

    the economic benets which can be achieved

    through the development of the correct

    method are extraordinarily large.” 

    In Czechoslovakia in 1950, Rudolf

    Kvapil was given the task of determiningthe causes of problems in bins and silos

    and, based on this new understanding,

    to develop ways of improving their

    performance. It was evident to him that it

    would rst be necessary to determine the

    basic gravity ow principles for granular

    and coarse materials since they must

    be completely different from principles

    describing the ow of liquids which were

    then available for use. He decided that

    the only realistic way to proceed was

    to construct and test a large number of

    models and to make in situ observations.

    Many of these models and the knowledgegained are described in his recent book

    (Kvapil, 2004). In 1965, Kvapil joined Janelid

    at KTH and began applying the gravity ow

    principles gained in the study of bins and

    silos to sublevel caving.

    Figure 2 shows the application of this

    type of model to a sublevel cave design. In

    this particular case, the sublevel spacing is

    12.5 m, the drift dimension is 5 x 3.5 m,

    the sublevel drift spacing is 12 m and the

    burden is 2 m. These closely resemble the

    sublevel dimensions used by the Kiruna

    Mine in the early 1980s. It is interestingto note that the design is based on a

    drawbody width (WT) to drawpoint width

    (WD) ratio of 1.7.

    Figure 2 Application of gravity flow principles tosublevel caving design (Kvapil,1982, 1992)

    Over the past few years, the scale of

    sublevel caving has increased markedly with

    LKAB being a leader in this regard. Figure

    3 provides a comparison of the sublevel

    caving mining geometries appropriate

    for the years 1963, 1983 and 2003 at

    the Kiruna Mine. Some of the importantparameters are tabulated in Table 1.

    Figure 3 The sublevel caving geometry at the Kiruna Mine at three different points in time (Marklund andHustrulid, 1995)

    At the Kiruna Mine today the sublevelspacing is 28.5 m. In certain sectors of

    LKAB’s Malmberget Mine, the sublevel

    spacing is as high as 30 m.

    Table 1 Summary of some important

    design parameters (Marklund and

    Hustrulid, 1995)

    Today, with the continuing push to

    increase mining scale, a fundamental

    question is whether the gravity ow

    principles which served as the design

    basis for the small-scale sublevel caving

    mine designs of the past can be applied

    at much larger scales or whether some

    other approach is required. This article willprovide some thinking in that regard.

    total yearly production of about 9.5 Mton

    (Ohlsson, 1961). Figure 1 is a sketch of

    the method as practiced at LKAB’s Kiruna

    Mine at about that point in time.

    Figure 1 Composite section view of the sublevelcaving mine at Kiruna in 1957 

    The scale was small, certainly by today’s

    standards, with a sublevel spacing of 9 m, a

    drift size of 5 x 3.5 m, and a sublevel drift

    spacing of 10 m centre-to-centre.

    As Janelid (1961, 1972) pointed out,

    “Sublevel caving is in many respects simple. It

    can be used in orebodies with very different

    properties and it is easy to mechanize.

    However, from other points of view such as

    recovery, dilution and similar, the method is

    unfavorable. The designs which are used andthe measures which can be taken to eliminate

    the disadvantages are poorly understood. In

    the end of the 1950’s, model tests regarding

     gravity ow in material resembling broken

    rock were started at the Division of Mining,

    the Royal Institute of Technology (KTH) in

    Stockholm. The purpose was to study how the

     geometrical design of various parameters in

    sublevel caving are inuenced by the motion

    which is induced in the material when ore

    is loaded in a sublevel drift. Some of these

    model tests were performed as a part of

    senior theses and others by assistants and

    research engineers. Model tests and extensiveliterature studies on sublevel caving have

    also been carried out in Kiruna together with

    conducting practical tests underground. The

    results achieved have been so encouraging that

    continued research work is well justied since

    Year

    Parameter 1963 1983 2003

    Drift width (m) 5 5 7

    Drift height (m) 3.5 4 5

    Sublevel height (m) 9 12 27

    Sublevel drift spacing

    (m) 10 11 25

    Blasthole diameter(mm) 45 57-76 115

    Burden (m) 1.6 1.8 3

    Holes/ring 9 9 10

    Tons/ring (t) 660 1080 9300Tons/metre of drift

    (t/m) 400 600 3100

  • 8/20/2019 Revista 2 Articulos de Diseño de Minas Sub Level Caving

    3/273Australian Centre for Geomechanics • December 2009 Newsletter

    CavingMine marker studies

    It is one thing to study ow principles

    in a laboratory setting and quite another

    to show that they apply in the reality ofa mine setting. One way of doing this is

    through marker studies. Figure 4 shows

    some results from the rst marker studies

    conducted as part of the overall KTH

    sublevel caving research programme

    conducted at the Grängesberg iron mine in

    central Sweden in the early 1970s.

    Figure 4 Results of the Grängesberg marker tests(Janelid, 1972)

    Some of the relevant parameters are

    summarised in Table 2.

    Table 2 Design parameters at Grängesberg

    From Figure 4, it appears that the ow

    width is of the order of 5 m. Since the

    drift width is 3.5 m, the ow width to

    drift width ratio is 1.43. Due to the roof

    curvature, the effective extraction width

    is somewhat less and the ratio would be

    corresponding slightly larger.

    It took quite a long time for the

    next group of mine marker tests to be

    performed. As noted by Quinteiro et al.

    (2001), “The sublevel caving layout used at

    Kiruna has reached dimensions that are far

    beyond those that formed the basis for thedevelopment of the early design guidelines.

    Thus, there was a need to verify the gravity

    ow pattern for this very large sublevel caving

    area. It was decided to install markers in the

    fans so one could estimate the ellipsoid of

    extraction.” 

    Figure 5 shows the fan geometry and

    Table 3 summarises some of the importantparameters.

    Figure 5 Fan geometry for the Kiruna sublevel cave

    Table 3 Summary of some important

    factors concerning the Kiruna marker tests

    Figure 6 shows the results of the

    recovered markers expressed as a

    percentage of the total number of markers

    installed at each particular location.

    Figure 6 Percentage of the recovered markers at a

    particular position

    It can be seen that only a very small

    number of markers were recovered from

    the sides of the fan indicating that the ore

    ow was small. On the other hand, a large

    number of markers were recovered from

    the central part of the fan indicating that

    the predominant ore ow pattern was inthe center. This type of ow behavior will

    result in early dilution. Figure 7 shows the

    results in Figure 6 in the form of a contour

    plot.

    Figure 7 Contour plots showing the percentrecoveries at the different marker positions

    Recently, comprehensive marker studies

    have been carried out at the Perseverance

    and Ridgeway sublevel caving mines inAustralia. At the Perseverance Mine, the

    overall ow pattern as demonstrated using

    the markers is shown in Figure 8. Some of

    the important parameters are presented in

    Table 4.

    Figure 8 Section showing the rings with the drawpattern superimposed. Perseverance Mine

    Parameter Value

    Sublevel drift spacing (m) 7

    Sublevel spacing (m) 13

    Hole diameter (mm) 41

    Burden (m) 1.5

    Sublevel drift width (m) 3.0 slashed to 3.5

    Sublevel drift height (m) 3

    Front inclination (degrees) 90

    Parameter Value

    Sublevel drift spacing (m) 25

    Sublevel spacing (m) 27

    Hole diameter (mm) 114

    Burden (m) 3

    Sublevel drift width (m) 7

    Sublevel drift height (m) 5

    Front inclination (degrees) 80

    “It is one thing to study ow

    principles in a laboratory

    setting and quite another toshow that they apply in the

    reality of a mine setting.”

  • 8/20/2019 Revista 2 Articulos de Diseño de Minas Sub Level Caving

    4/274 Australian Centre for Geomechanics • December 2009 Newsletter

    Table 4 Summary of some important

    factors concerning the Perseverance

    marker tests

    Table 5 summarises some of the

    important parameters concerning the

    Ridgeway marker tests.

    Table 5 Summary of design parametersfrom the Ridgeway Mine

    In reviewing the results of the marker

    tests from the Grängesberg, Kiruna,Perseverance and Ridgeway mines, it is

    interesting to note that they all basically

    reveal a type of “silo” ow such as shown

    in Figure 9 even if the drilling pattern

    extends far outside of the “silo.”

    Figure 9 “Silo” type of flow pattern. Kvapil (1955), Janelid and Kapil (1965)

    The “average” primary ow width/drift

    width ratios (Wf /Wd) for the four casesare summarised in Table 6.

    Table 6 A comparison of the marker ow

    The Wf /Wd ratio of 1.4 – 1.7 seems

    to apply for small scale sublevel caving

    geometries as well as very large scale.

    These results are in agreement with

    the early sublevel caving geometry

    recommended by Kvapil (see Figure 2)

    which used 1.7.In retrospect, there are three reasons

    why this is a very logical result:

    1. The middle holes of the ring are red

    rst and can make rst use of the

    swell volume offered by the underlying

    sublevel drift.

    2. The central holes are drilled subvertical,

    fairly parallel, and relatively close to one

    another. The result is a relatively high

    and uniform specic charge compared to

    the other holes in the round. Thus, one

    would expect the best, most uniform

    fragmentation.3. The ore material in the central part of

    the round can make the best use of the

    effect of gravity in directing it to the

    drawpoint.

    As indicated earlier, small-scale physical

    model test results have historically played

    a very important role in the dimensioning

    of sublevel caves. In the construction of

    these models, the sand or other material is

    simply poured into the forms. As such, the

    properties are uniform and the mobilities

    are the same independent of position

    within the model. In a sublevel cave, this is

    not the case. All of the material in the fanis drilled and blasted. Because of the fan

    geometry, the amount of explosive/unit

    volume and hence the fragmentation varies

    throughout the fan. The ore material in the

    centre part of the fan and the lower part

    of the fan has a much higher specic charge

    than that at the boundaries of the ring.

    Furthermore, the “cave” which lies in front

    of the blasted slice is an eclectic mixture of

    waste rock and ore remnants. Its mobility

    varies with location and with time (it

    changes with the extraction geometry).

    Finally, most rock materials upon beingblasted would like to bulk (swell) of the

    order of 50%. In sublevel caving, it is the

    sublevel drift located at the bottom end

    of the fan which is the primary provider

    of swell space for the ore in the ring. As

    shown in Table 7, the available free swell is

    highly mining scale dependent.

    Table 7 Available “free” swell for the

    different LKAB designs

    As the scale has increased over the

    years in the quest to reduce the specic

    development, the available free swell has

    correspondingly decreased. With the

    current LKAB design it is only about 5%.

    Since it is located at the bottom of thefan, the ore in the near vicinity of the drift

    has a much greater access to this volume

    and the chance to bulk. The ore at the

    extremities of the fan, on the other hand,

    has little chance to bulk and its mobility is

    very low. Based on material mobility alone,

    one would expect signicant differences

    in the mechanics of ow between the

    sand models and reality, particularly as

    the sublevel scale is increased. Hence,

    the marker test results have very high

    signicance.

    Sublevel cave layout rules basedupon marker test input

    Based upon the results of the four

    marker tests, it appears that the Wf can be

    expressed as a constant times the width of

    the Wd. As a rst approximation,

    Wf  = (1.4 – 1.7) Wd  (1)

    Some preliminary design rules for initial

    planning are summarised below:

    • Sublevel drift size (width (Wd) and

    height (Hd): determined based on

    equipment.• Sublevel interval (HS): the theoretical

    maximum value is based on the ability

    Parameter Value

    Sublevel drift spacing (m) 14.5

    Sublevel spacing (m) 25

    Hole diameter (mm) 102

    Burden (m) 3

    Sublevel drift width (m) 5.1

    Sublevel drift height (m) 4.8Front inclination

    (degrees) 75

    Parameter Value

    Sublevel drift spacing (m) 14

    Sublevel spacing (m) 30

    Hole diameter (mm) 102

    Burden (m) 2.6

    Sublevel drift width (m) 6

    Sublevel drift height (m) 4.7Front inclination

    (degrees) 80

    Mine

    Drift width

    (Wd)

    Level

    interval

    Flow width

    (Wf ) Wf /Wd 

    (m) (m) (m)Grängesberg 3.5 13 4.9 1.4

    Kiruna 7 27 10.3* 1.5

    Perseverance 5 25 7.1 1.4

    Ridgeway 5.9 25 - 30 10.0 1.7

    * Arbitrarily taken as the 30% contour

    Design "Free" Swell

    1963 24.0

    1983 17.9

    2003 5.5

    patterns

  • 8/20/2019 Revista 2 Articulos de Diseño de Minas Sub Level Caving

    5/275Australian Centre for Geomechanics • December 2009 Newsletter

    Cavingto drill long, straight holes. This, in turn,

    is based on the hole diameter (D). The

    actual limit is based on recovery and

    dilution considerations which are due to

    managing ore/waste pulsation.• Hole diameter (D): based on the

    available drilling equipment and the

    ability to charge long holes.

    • Spacing of the sublevel drifts (Sd):

    Sd = (2.4 – 2.7) Wd (2)

    • Ring spacing (burden (B)): based

    upon the damage radius (Rd) concept

    discussed by Hustrulid and Johnson

    (2008)

    B = 2 Rd (3)

    Where:

     

    (4)

    Rd = damage radius (m)

    rh = hole radius (m)

    P e Exp

     = explosion pressure for the

    explosive

    P e ANFO

     = explosion pressure for ANFO =

    1600 MPa

    ρrock = rock density (g/cm3

    )2.65 = density of typical rock (g/cm3)

    • Hole toe spacing (ST): based upon the

    burden

      ST = 1.3 B

    • Spacing for parallel holes (SP): based

    upon the burden

      SP = B (5)

    • Front inclination: 70–80 degrees

    (forward)

    If it is assumed that:

    D = 115 mm

    Drift dimensions: 7 m wide by 5 m highExplosive: emulsion (P

    e Exp = 3900 MPa)

    Rock density = 4.6 g/cm3

    Sublevel interval: 25 m based on drilling

    ability and control of pulsation

    One nds that the remaining dimensions

    are:

    Sublevel drift spacing: 17–19 m

    Burden: 2.7 m

    Toe spacing (fanned): 3.5 m

    Toe spacing (parallel): 3 m

    Front inclination: 80o selected

    It is noted that the new sublevel drift

    spacing rule has very limited basis and mustbe carefully complemented with further

    testing.

    Implications for future sublevelcaving designs

    The results of the marker studies would

    suggest that modications in some of thecurrent, very large scale sublevel caving

    designs should be considered. Assuming

    that the drift width is not changed, the

    results suggest that the sublevel drift

    spacing should be reduced. Presuming

    that there is no change in the sublevel

    height, this means that the overall mining

    scale would decrease and the specic

    development would increase. One way of

    maintaining the current scale is to increase

    the width of the sublevel drift. Figure 10

    shows one possibility.

    Figure 10 Silo design with super-scale extractiondrifts, patterned after Kvapil (1992)

    This has advantages with respect to the

    silo shape and the parallel hole drilling.

    However, one must be concerned with

    geomechanics issues (drift and brow

    stability). Furthermore, the draw must be

    well controlled over the entire face.

    If one wants to preserve the specic

    development ratios in place today, one

    would need to increase the sublevel

    height. However, this has problems with

    hole deviation, maintenance of long holes,

    charging of very long holes, and dealing

    with ore/waste pulsation over a much

    longer draw duration. This seems like avery difcult alternative to achieve on a

    day-to-day basis. On this basis, it would

    seem that in the future mining companies

    will be looking toward smaller scale designs

    than today and not larger. The current very

    large-scale designs may actually be too

    large-scale.

    Front caving implications

    This article has only dealt with standard

    sublevel caving. There are a number of

    variants, however. Front caving is a variety

    of the sublevel caving technique which isquite often used. It is, for example, a very

    interesting technique for the creation of

    the undercut required in block and panel

    caving. However, it is very important that

    the undercut be completely formed. The

    marker studies would indicate that the ow

    stream is much narrower than previously

    thought. If rock mass ow does not occurover the full drilled width, the remaining

    portions could form remnants and

    transmit loads to the production level with

    catastrophic consequences. This means that

    current undercut designs based upon front

    caving will have to be re-evaluated.

    Future possibilities to maintain/increase scale

    There are two possibilities, at least, to

    try and maintain or possibly even grow

    the scales used today. One possibility

    deals with using more of the sublevel drift

    for swell than just that taken by the orefalling down. This involves changing the

    blasting pattern and initiation sequence

    so that the ore at the lower part of the

    ring is propelled far out into the drift. A

    second possibility which also involves a

    change in the blasting is to use the available

    swell space more effectively. This means

    permitting the ore in the lower part of the

    ring to only swell 20%, rather than 50%.

    This would thereby increase by a factor of

    2.5 the amount of ore in the ring which has

    a chance to swell. Accomplishing both of

    these possibilities should be well within thecapabilities of electronic detonators with

    very precise timing.

    A problem with today’s typical ring

    drilling design is that the hole spacing

    changes from very small near the drift to

    large at the hole ends. The parallel hole

    design used in the silo design avoids this

    problem. Without a major change in drift

    width, one is conned to a rather narrow

    pattern. Figure 11 shows one possible

    futuristic design involving special drilling

    technology and the blasting innovations

    which better use the available “free” swell

    space.The design presents an opportunity

    to achieve improved fragmentation, an

    increase in ore mobility, and a more

    uniform distribution of ore mobility over a

    much wider front. An understanding of how

    the ore actually ows in sublevel caving will

    lead to better designs. The marker studies

    are an important step along that path.

    rock  ANFOe

     Expe

    hd  P 

     P r  R

     ρ 

    65.220/   =  

    “The results of the marker

    studies would suggest that

    modications in some of

    the current, very large scalesublevel caving designsshould be considered.”

  • 8/20/2019 Revista 2 Articulos de Diseño de Minas Sub Level Caving

    6/276 Australian Centre for Geomechanics • December 2009 Newsletter

    Second International

    Symposium on Block andSublevel Caving

    20–22 April 2010,

    Novotel Langley Hotel,

    Perth, Australia

    The growing popularity of cavingmethods around the world is largelydue to the very low production costand the intrinsic safety associatedwith this mining approach. Morethan 50 technical papers areexpected to be presented at this

    three day event.

    www.caving2010.com

    2010CAVING

    5thInternational Seminar onDeep and High Stress Mining

    2010

    6–8 October | Santiago - CHILE

    Ponticia Universidad Católica

    de Chile, in collaborationwith the Australian Centre forGeomechanics, the Universityof Toronto, and the University ofWitwatersrand, is organising anInternational Seminar on Deepand High Stress Mining.

    As the mining industryfaces new challenges toextract mineral resources atincreasing depths, the DeepMining International Seminarseries provides a forum for

    the industry, academicsand researchers to shareinformation, experience andideas on deep and high stressmining.

    For more details [email protected] or visit http://web.ing.puc.cl/~deepmining2010/

    Collaborating Organisations

    William HustrulidUniversity of Utah; andthe Colorado School of

     Mines, USA

    Future studiesIn closing, the authors believe that

    it is time to seriously revisit the

    recommendation made by Janelid (1961)

    nearly 50 years ago with regard to small-

    scale sublevel caving,“The results achieved

    have been so encouraging that continued

    research work is well justied since the

    economic benets which can be achieved

    through the development of the correct

    method are extraordinarily large.” 

    In spite of their obvious value, eld

    studies are few and far between in the

    mining business. In addition, if conducted,it is very difcult for others to access the

    results and perhaps gain and offer new

    insights. This must change if the mining

    business is to meet the technical, economic

    and safety challenges the future has to offer.

    There is a real danger that today’s

    sublevel caving designs are far from

    optimum due to a poor understanding

    of the fundamental processes involved.

    In the past, the application of sublevel

    caving has primarily been to iron ore,

    particularly magnetite, which because of its

    very forgiving magnetic property, permits

    easy and inexpensive separation from thewaste. The same is not true with other

    minerals, for example copper porphyry and

    gold ores. For these, it is very expensive

    to separate ore and waste. It would

    appear that prior to fully committing to

    any sublevel caving design, a pilot project

    should be run with a carefully planned and

    executed program of data collection. One

    very important piece of information to

    be extracted is the draw width. It is also

    very important to develop the required

    draw control techniques to be applied in

    the mine. Ore/waste pulsation, which isinherent in very high draw designs, makes

    practical draw control very difcult. Visual

    viewing of the cave front is not enough.

    AcknowledgementThis edited article is from the paper

    entitled, “Sublevel caving - past and

    present” featured in the proceedings of

    the 5th International Conference and

    Exhibition on Mass Mining, Lulea, Sweden,

    9–11 June 2008.

    Figure 11 New possibilities for large-scale sublevel caving 

  • 8/20/2019 Revista 2 Articulos de Diseño de Minas Sub Level Caving

    7/277Australian Centre for Geomechanics • December 2009 Newsletter

    Introduction

    Risk, risk assessment and risk analysis

    have a number of meanings across a range

    of disciplines. At the most fundamental,

    risk is simply a combination of uncertainty

    in an outcome and consequences for that

    outcome. Risk analysis or risk assessmentis the process of identifying, quantifying,

    and communicating those uncertainties

    and outcomes. In geological engineering,

    risk has traditionally been tied to the

    calculation of a factor of safety of a slope,

    or potential failure geometry, and has

    historically been a qualitative assessment

    of a calculated value. Advances in the

    computational power of stability analysis

    software programs have set the stage for

    more quantitative assessments. Depending

    on the scale of the slope under evaluation,

    and given the variation inherent in earthmaterials in general, almost every input

    can be considered to vary over a range of

    potential values.

    As such, risk assessment in geological

    engineering often considers both aleatory

    uncertainty - the variability inherent to

    natural materials, and epistemic uncertainty

    - the variability related to the ability to

    model a phenomenon. It is uncommon,

    however, that risk assessment considers a

    temporal element, i.e. how the inputs, and

    therefore the associated risk, change with

    time. To an extent this is to be expected

    as many inputs do not signicantly changeover the course of a project life. However,

    elements such as pore pressure, the surface

    topography of an excavation, the weight

    distribution on a potential failure plane,

    the probability of a seismic event and the

    properties of low strength materials can

    all change to a magnitude that materially

    affects the outcome of a risk analysis. No

    attempt has been made in this assessment

    to look at equipment or personnel

    temporal exposure.

    To evaluate the effect of the aleatory,

    epistemic and temporal variation, researchwas conducted at the Rio Tinto Minerals

     – Boron Operations open pit mine near

    Boron, California. The purpose of this

    The changing prole of risk associated

     with in-pit placement of waste

    orebody that was deposited as an evaporate

    by Raymond Yost, Rio Tinto Minerals – Boron Operations, USA

    article is to discuss the background to that

    work, the nature of the risk analysis and

    assessment, and to present preliminary

    results.

    Background and site characterisation

    The Boron open pit mine is located

    near the town of Boron, California in theMojave Desert Geologic Province. The

    mining operation extracts borates from

    a lenticular orebody that was deposited

    as an evaporite and is encased in layers

    of low permeability claystone. The clay

    and borate sequence is bounded on the

    bottom by a layer of basalt, which is in

    turn underlain by feldspar-rich sandstone

    (arkose) with interbeds of clayey sand (the

    Tropico Formation). Poorly to moderately

    consolidated and cemented arkose covers

    the borate and clay sequence. An intrusive

    body, composed primarily of quartzmonzonite, bounds the deposit to the

    south.

    The sequence of Tropico-basalt-

    evaporites-sediments has been tilted and

    dips moderately; 5 to 15° to the south.

    Faulting has offset the orebody into three

    primary components and a number of

    sub-blocks.

    The open pit operation was initiated in

    the late 1950s in the northwestern portion

    of the deposit where the borate layer was

    generally closest to the surface. Over the

    past 60 years, the pit has expanded to the

    south and east and has deepened as thehigher elevation ores have been mined out.

    Slope failures that have occurred during

    open pit mining operations typically form

    due to a combination of pore pressure,

    high-angle faults (which act as a back plane)

    and low-strength beds of clayey sand or

    claystone. All of the open pit slopes are

    designed in recognition of these variables.

    The design of the north wall, however,

    is also governed by the orientation of

    the orebody. As offset on most faults is

    relatively minimal, the overall slope of

    the wall generally follows the overallorientation of the orebody.

    The overall slope angle of the wall,

    in conjunction with the strength of the

    foundation material (basalt), generally

    results in factors of safety well in excess

    of industry required limits. Furthermore,

    the mineralised zone at the site is conned

    to a single geologic unit. Extraction of

    the borate layer represents complete

    extraction of the resource, so dumping

    over mined out areas does not presentany risk of covering potentially economic

    mineralised zones. The north slope of the

    pit was therefore an attractive option

    for overburden disposal given that it was

    stable, composed of a higher strength unit,

    and close to active mining operations. A

    risk assessment was conducted prior to

    the large-scale placement of overburden on

    the slope.

    Structure of the risk assessment and

    input variables

    Mining in the most general sense,balances two basic elements – benets

    realised against the potential for loss. In

    this case, they have been incorporated

    into the risk assessment. Benets are

    realised if the ground and overburden

    dump remain stable throughout the project

    life and costs are incurred if they do not.

    Evaluating risk in this case is therefore a

    matter of determining the potential for

    slope instability along with the values

    of the benets and costs. Stability is a

    function of the geology, the potential

    for a seismic event, the pore pressure,

    the size of the dumped volume and theslope conguration. While some of these

    variables remain constant over the project

    life, most of them change to a large enough

    degree that they affect the probability of a

    slope failure. A thorough risk assessment

    therefore requires an evaluation of

    conditions through the full time line of the

    project.

    The risk assessment was structured to

    evaluate the potential for slope failure.

    The risk through time was quantied via

    a series of steps to establish a probability

    of failure, determine the magnitude ofpotential negative outcomes and model the

    expected values. Specic tasks included:

    Open pit

  • 8/20/2019 Revista 2 Articulos de Diseño de Minas Sub Level Caving

    8/278 Australian Centre for Geomechanics • December 2009 Newsletter

    1) Estimating the probability of an outcome

    (a slope failure) through the use of

    limit equilibrium analysis and statistical

    sampling of analysis inputs.

    2) Estimating the likely extent of negativeresults (failure clean-up) through the

    use of numerical and empirical methods

    to develop a model of post-failure

    topography.

    3) Estimating the likely extent of positive

    results (savings associated with dumping

    near the area of extraction as opposed

    to ex-pit dumps) through an evaluation

    of equivalent tonne miles (ETM).

    4) Using the probability of an outcome

    and the estimated costs and benets to

    establish expected costs and benets

    with time.

    5) Adjusting the timing of benets and costs(benets are expected to be realised

    early while costs are expected to be

    realised later) with a discount rate.

    6) Estimating a net expected sum of

    benets at distinct points.

    Once these values were estimated,

    the risk was determined as the net sum

    of expected benets and costs. A value

    greater than zero implied that the outcome

    had a positive expected economic value,

    while a net sum of less than or equal

    to one implies that the outcome had anegative expected economic value and a

    negative risk. The evaluation was repeated

    at appropriate time increments for a range

    of in-pit dump volumes to determine if, and

    how much, waste could be economically

    placed in the pit.

    Results

    To illustrate the interplay of the

    various inputs to the risk assessment,

    the start and end points of one of the

    analyses are presented in Figure 1, from

    the limit equilibrium analysis through

    empirical modelling, to the nal economicassessment for a 30 million t in-pit waste

    dump.

    “Risk in the most general sense,balances two basic elements

     – benets realised against the

    potential for loss.”

    Figure 1 Pit topography at year 2010

    Probability of failure – 5.0% (with seismic load).•

    Probability of failure – 0.55% (without seismic load).•

    Failure volume (in section) 28,350 m• 3  (with seismic load).

    Failure volume (in section) 28,700 m• 3  (without seismic load).

    Probability of seismic event – 5.0%.•

    At this beginning stage, ore (blue and green units) is close to the toe of potential

    failure and subject to burial should failure occur. Failure volume is relatively high, but

    the probability of failure is relatively low. The probability of a seismic event occurring is

    relatively low.

    Figure 2 Pit topography for ultimate pit

    Probability of failure – 81.20% (with seismic load).•

    Probability of failure – 41.60% (without seismic load).•

    Failure volume (in section) 39,500 m• 3 (with seismic load).

    Failure volume (in section) 39,250 m•3

     (without seismic load).Probability of seismic event – 70.0%.•

    At this nal stage, failure volume increased by approximately 40%, but the probability of

    failure increased, on average, to approximately 60%. The potential for a seismic event has

    increased as well, but the ore zone is farther away from the toe of slope and is less likely to

    be covered by a slope failure.

     Modelling post-failure runout

    A combination of numerical modelling and empirical evaluation was used to develop

    potential post-failure topography. Post-failure proles were developed for all sections with a

    probability of failure greater than 0.01% regardless of the factor of safety. The conguration

    of the runout was based on an assessment of historical slope failures at the site. At Boron

    this was the angle of repose of the failed material relative to the dip angle of the underlying

    failure plane, and adjusted for the geometry of the runout area.

    Figure 3 Topography for failure at 2010 for 30 million tonne dump

    The ratio of the clean-up area to the post-failure area is 18.5%. The runout was contained

    to some extent by the concave geometry of runout area resulting in a low overall angle of

    repose.

  • 8/20/2019 Revista 2 Articulos de Diseño de Minas Sub Level Caving

    9/279Australian Centre for Geomechanics • December 2009 Newsletter

    Figure 4 Topography for failure at ultimate pit for 30 million tonne dump

    The ratio of the clean-up area to the post-failure area is 22.5%. The removal of material

    below the toe of failure has allowed considerable runout. The overall angle of repose has

    increased.

    Benets and costs

    Assessing benets and costs began with establishing values for dumping a unit of waste in

    the pit and for cleaning up a unit of failure debris from the pit. The value of dumping tonnes

    in the pit is a function of reducing both horizontal and vertical haul distances. Reducing

    the haul distance generally means that additional truck hours are available. These truck

    hours are either used to haul additional waste, or, if enough truck hours are offset by the

    short hauls, a truck(s) could be parked. The difference in either case is reected by overalllower haulage costs. The problem lies in translating these lower overall costs into what the

    specic unit cost difference is for dumping a portion of the waste in the pit versus hauling

    all waste outside of the pit.

    To accomplish this, it was necessary to evaluate haul costs with a unit that accounted

    for both the difference in horizontal and vertical travel distances associated with hauling

    to a site outside of the pit, versus hauling to a site inside the pit. The value used was the

    ETM, which assumes a difference in hauling effort for moving a unit of waste vertically

    versus horizontally. By determining the total ETMs necessary to move a quantity of waste

    to an ex-pit location versus an in-pit location, a difference in the hauling effort could be

    determined. That difference, along with a unit cost of an ETM, obtained by dividing the total

    haul costs for a unit time period by the total ETMs for that time period, could then be used

    to determine a total value. That total value divided by the quantity of waste (in tonnes) was

    used as the estimate for the unit ton value of in-pit dumping. The formula below illustratesthe concept for the difference between hauling 100 million t of waste to a northern dump

    versus an in-pit dump.

    [(ETMnorth – ETMin-pit) * $/ETM]/100 million t =

    average unit value realised by hauling to in-pit dump versus north dump

    To establish the cost of failure clean-up, records from the 1997-1998 slope failure were

    reviewed. Despite extensive documentation, there is still considerable variation in what

    constitutes ‘clean-up’ costs. On one end of the spectrum, the costs can be merely the labor

    and equipment charges associated with removing the portion of failure debris necessary to

    re-establish access into a mining area or to uncover buried ore reserves.

    At the other end, the clean-up costs

    can include those charges along with a

    range of fees associated with consulting,

    additional equipment, accelerating strippingto continue mining in other parts of the

    site, overtime costs, contracting and leased

    equipment. Based on the previous two

    assessments, a range of values was obtained

    for both the unit cost of cleaning up a

    tonne of failure debris and the unit value of

    dumping a tonne of overburden in the pit.

    Economics of in-pit dumping 

    The nal step was to use weighted (by

    the probability of a seismic event) average

    values for the expected volume of failure

    debris, the expected value of the volume

    of material that would have to be cleanedup, and the associated expected costs and

    benets with time. Values of benets and

    costs were shifted with time by using a

    discount/interest rate of 7%.

    Table 1 Summary of benets and costs

    shifted with time

    The negative values in the nal row

    indicate that for the difference between

    the high expected benets and low

    expected costs (H/L) (best case), and the

    low expected benets and high expected

    costs L/H (worst case), the dump size of 30

    million t is not a feasible design in this case.

    This method of risk assessment has

    helped Rio Tinto to understand the

    interplay of a number of variables that

    inuence the risk associated with placing

    overburden on the north slope of the openpit. While the 30 million t dump option

    proved to not be an economically feasible

    option, other volumes evaluated in the

    course of research do have positive values

    throughout the mine life. The methodology

    described here has allowed Rio Tinto

    Minerals to identify those cases and

    proactively manage risk in the present and

    throughout the life of the project.

    Ray Yost,

    Rio Tinto Minerals -Boron Operations,USA

       A  r  t   i  c   l  e  r  e   f  e  r  e  n  c  e  s  a  r  e  a  v  a   i   l  a   b   l  e   f  r  o  m   t

       h  e   A   C   G .

    Rio Tinto’s Boron open pit operation was initiated in the 1950s

    Open pit

     

    YEARDUMP SIZE(TONNES)

    DIFFERENCE

    H/L L/H

    2010 30,000,000 positive positive

    2015 30,000,000 positive positive

    2020 30,000,000 positive positive

    2032 30,000,000 positive positive

    2036 30,000,000 negative negative

  • 8/20/2019 Revista 2 Articulos de Diseño de Minas Sub Level Caving

    10/2710 Australian Centre for Geomechanics • December 2009 Newsletter

    Many of the uncertainties surrounding

    the development of a large open pit

    mine have now been overcome with the

    publication of the 496-page “Guidelines

    For Open Pit Slope Design”.

    The publication is the result of four

    years of effort and support from a group

    of 12 mining companies representing the

    majority of the world’s production ofdiamonds and base metals.

    Open pit mining is an efcient way

    to mine many deposits. But there are

    complications. Make the slope of the

    pit too shallow and you have to move

    millions of additional tonnes of valueless

    overburden. But if it’s too steep, you risk

    failure with subsequent risk to people and

    property.

    Up until now, the only handbook of

    this type available to open pit mine slope

    design practitioners, including engineering

    geologists, geotechnical engineers,mining engineers, civil engineers and

    mine managers has been the “CANMET

    manual” last published in 1977.

    The new Guidelines For Open Pit Slope

    Design was ofcially released at the Slope

    Stability conference in Santiago, Chile,

    9 November. It is a direct outcome of

    the “Large Open Pit” research project

    and comprises 14 chapters that follow

    the life of mine sequence from project

    development to closure.

    CSIRO Earth Science and ResourceEngineering’s Dr John Read is one of two

    editors and has also authored a number of

    chapters in the book.

    Dr Read has over 40 years experience

    as a practitioner and consultant in the

    mining industry, with special interests and

    expertise in rock slope stability and open

    pit mine design and investigation tasks in

    Australia, Fiji, Papua New Guinea, Brazil,

    Argentina, Chile, Canada, South Africa and

    Zambia.

    He says that each chapter is written

    by an industry practitioner with specicexperience in the topic being described.

    “The purpose of the book is to be

    a new generation guideline that links

    innovative mining geomechanics research

    with best practice” he said. “The book

    outlines for today’s practitioners what

    works best in different situations and

    why, what doesn’t work and why not, and

    what is the best approach to satisfy best

    practice in a range of situations.”

    Guidelines For Open Pit Slope Design 

    is available from CSIRO publishing forAU$195. www.publish.csiro.au/

    CSIRO helps redene largeopen pit design

    Seventh Large Open Pit

    Mining Conference 201027–28 July 2010, Perth, Western Australia

    High demand for commodities, record fuel prices and a scarcity of skilled personnel

    have been replaced and surpassed by the recent global nancial crisis as the primary

    issues facing the mining industry. As demand for commodities improves the incentive

    to continue to drive operational and safety improvements will become paramount.

    The Seventh Large Open Pit Mining Conference 2010 (LOP 2010) will provide the

    opportunity to chart that progress in large open pit mines around the world

    The conference will provide the forum for operations with major achievements, along

    with those operators implementing changes, the chance to outline their innovations

    and to share and explore experiences with others. Consistent with the aims of The

    AusIMM, the Conference will allow members and the industry to keep abreast oftechnical developments and provide a forum to share views and opinions within the

    large open pit sector.

    For more information, please contact:

    Katy Andrews, The AusIMM

    Phone: +61 3 9658 6125

    Fax: +61 3 9662 3662

    [email protected]

    PUBLISHING

     ACG Open Pit Rock Mass

    Modelling Seminar

    29–30 July 2010, BurswoodConvention Centre, Perth

    This seminar will maximise thedissemination of geotechnical rock massmodelling and synthetic rock modelling

    technologies to industry.

    The trend of open pit operations

    mining to steeper and deeper levels

    has seen an increase in the stress

    environment and greater uncertainty

    about the mechanical behaviour of

    slopes, elevating mine worker safety

    and productivity risks. To better

    identify, understand and manage thesepotential geotechnical risks (including

    seismic hazard) associated with slope

    stability failure, the ACG will host this

    two day seminar immediately following

    The AusIMM’s Seventh Large Open Pit

    Mining Conference 2010.

    Please visit, www.acg.uwa.edu.au/events_courses

  • 8/20/2019 Revista 2 Articulos de Diseño de Minas Sub Level Caving

    11/2711Australian Centre for Geomechanics • December 2009 Newsletter

    Introduction

    Mining is an important activity in

    the economy of many South Americancountries. It is predominantly a formal

    sector, regulated and facilitated by laws and

    regulations; it is also a leading contributor

    of export earnings that is integrated into

    the global economy. The contribution of

    the mining sector can represent up to

    10% of the gross domestic product and

    over 50% of the value of all exports of a

    country with a strong and predominant

    mining sector. Mining has a multiplier effect

    - generating synergies with other economic

    and social sectors in the community and

    region where it was developed.

    However, society does not always have agood perception of the mining industry. In

    part, this may be due to the environmental

    liabilities left behind by legacy mining

    sites that date back to times when there

    was neither awareness of the impact that

    mining can have, nor a “modern” legal

    and supervising framework. Until recently,

    regulations requiring companies to prepare

    abandonment and closure plans were

    largely absent.

    The world has changed and the

    requirements for mining projects are

    evolving. Compliance with internationalagreements, such as those of biological

    diversity, community engagement,

    climate change, and the struggle against

    desertication and new environmental

    standards have demanded a new way

    of mining. This includes social andenvironmental impact studies and closure

    plans that are developed from the time

    when a mining project commences.

    This article presents for comparison the

    most important elements of mine closure

    standards in Chile, Argentina and Peru.

    Mine closure legal framework 

    Chile

    On 7 February 2004, modications to

    mining safety regulations came into force

    in Chile, establishing an obligation for all

    mines to prepare closure plans within

    ve years. The objective is… “to prevent,minimize and/or control the risks and

    negative effects that might result from or

    continue to take place after the cessation

    of the operations of a mine site, in the

    life and integrity of the people working

    there, and of those who, under dened and

    specic circumstances, are related to the

    operation and are within the inuence of

    its facilities and infrastructure”.

    In 2009, draft law addresses the closure

    scope of mine facilities and sites of the

    extractive mining industry. This draft

    legislation differentiates between thoseprojects that have an environmental

    resolution and those that do not. The

    second group are those mines that

    Mine closure planning in South Americaby Hugo Rojas, Teck Resources, Chile; and Roger Higgins, Teck Resources, Canada

    started operations before the Base Law

    of the Environment Nr. 19300 (1997) and

    Regulations of the Environmental ImpactAssessment System were enacted.

    With respect to nancial guarantees,

    mining companies have to provide these

    in annual instalments, over a period of ve

    years, or during the period of remaining

    mine life (if this is shorter).

     Argentina

    The law on environmental protection

    for mining activity and its supplementary

    regulations does not contain specic

    regulations for mining companies to submit

    abandonment and closure plans for the

    approval of authorities. This matter is opento different interpretations.

    According to the Second Section of the

    Complementary Title, the following must

    be considered:

    a) Environmental impact: modication of

    the environment, whether benecial or

    detrimental, direct or indirect, temporary

    or permanent, reversible or irreversible,

    may be potentially caused by mining

    activity.

    b) Environmental impact report: a

    document that describes a mining

    project, the environment where it isdeveloped, the environmental impact

    it will cause and the environmental

    protection measures proposed for

    The Chilean town of Andacollo and Teck's Carmen de Andacollo mine are close neighbours. This leads to a very close relationship between the community, for bothoperations and closure planning 

    Mine closure

  • 8/20/2019 Revista 2 Articulos de Diseño de Minas Sub Level Caving

    12/2712 Australian Centre for Geomechanics • December 2009 Newsletter

    These proceedings are a hard-bound, blackand white publication featuring 53 papers,

    comprising 622 pages.

     www.acg.uwa.edu.au/shop

    adoption. The EIR must address

    “measures and actions for prevention

    and mitigation of environmental

    impact, and rehabilitation, restoration

    or recomposition of the alteredenvironment”.

    c) Environmental impact declaration:

    an administrative act based on the

    mining environmental standards in

    force, approving an EIR, passed by the

    application authority, and in which are

    set the specic conditions that the

    holder company must comply with

    during all stages of the mining project.

      An aspect that is not regulated in

    Argentina is community involvement in

    the approval process of an EIR.

    Peru

    Peru applies regulations for mine closure

    to every mining activity, with the purpose

    of preventing, minimising and controlling its

    potential risks and effects to human health,

    safety, the environment, the surrounding

    ecosystem and property. The regulations

    were passed in 2005, and the articles

    clearly specify when and what details must

    be presented to the Director General

    of Mining Environmental Affairs of the

    Ministry of Energy and Mines.

    The mine closure plan complements the

    study of environmental impact and theprogramme of environmental management

    corresponding to a site’s operations.

    The ling of the mine closure plan is an

    obligation for every owner of mining

    activity that is in operation, beginning

    mining operations or resuming mining

    operations — after having been suspended

    or stopped by the validity of the law,

    or where there is no an approved mine

    closure plan.

    The approval of a mine closure plan leads

    to the constitution of guarantees through

    which assurance is given that the owner

    of a mining activity can comply with theobligations stated in the mine closure plan.

    In the event of a breach, the Ministry of

    Energy and Mines can execute the closure

    tasks.

    An important aspect of the regulations

    is the provision that allows citizen

    involvement. Every stakeholder can present

    their observations and make contributions.

    Once the closure plan is approved, it is

    to be executed in a progressive manner

    during the life of the mining operation. At

    operation end, the remainder of the areas,

    works and facilities that, due to operationalreasons had not been closed during the

    production stage must be closed. The

    regulations also establish mechanisms

    and periods for review, updating and

    accountability.

    Observations

    • The legal norms of closure plans inSouth America differ in their scope,

    depth and citizen involvement. This leads

    to different requirements for mining

    operations of similar characteristics.

    • The review and update of closure plans

    is a matter of interest for governments,

    as well as for organised communities and

    mining companies.

    • Even where there is a deciency in the

    law regarding mine site closure, there are

    companies that progressively design and

    apply high quality closure plans.

    • The design of closure plans in

    engineering stages prior to theconstruction of projects and their

    application from the beginning of the

    operations, represent an advantage

    for companies and should be seen as

    an opportunity to prevent, minimise

    and control risks and negative effects

    that might occur after the end of the

    operations.

    • The globalisation of markets,

    the requirement to comply with

    international norms and standards,

    the exchange and development of

    technical knowledge, together with opencommunication channels worldwide,

    will result in the further evolution of

    mine closure regulations, both legal and

    self-imposed. This will improve mining

    processes and practices, environmental

    stewardship and the efcient use of

    resources.

    • The voices and actions of communities

    that feel affected by mining will continue

    to grow, and constructive relationships

    with communities will be vital.

    • A good closure plan will contribute to

    obtaining and maintaining the social

    licence to operate.

    Hugo Rojas ,Teck Resources, Chile

    Roger Higgins, Teck Resources, Canada

    23-26 November 2010 Casa Piedra Events Centre

    Santiago, Chile 

    RESPONSIBLE CLOSURE: LIVINGUP TO COMMUNITIES’ AND

    STAKEHOLDERS’ EXPECTATIONS

    CONFERENCE THEMES

    • Designing and planning for closure

    • Progressive closure planning

    • Closure costs and nancing

    • Proactive stakeholder engagement

    • Long term water management• Mine site reclamation and rehabilitation

    • Control and monitoring

    • Soil ecology

    • Mine cluster, redeployment,

    redevelopment and decommissioning

    • Mine legacies and relinquishment

    • Legal and regulatory issues

    • Mining heritage and tourism

    • Recent closure case studies

    Send your abstracts by 25 January 2010 to:

    [email protected]

    For further information, please visit:

     www.mineclosure2010.com

    5th International Conference onMine Closure

  • 8/20/2019 Revista 2 Articulos de Diseño de Minas Sub Level Caving

    13/2713Australian Centre for Geomechanics • December 2009 Newsletter

    Summer vacation students in winter by Peter Hills, Tasmania Mine Joint Venture, BCD Resources (Operations) NL

    A phone call from Professor Marty

    Hudyma in February 2009 was my

    introduction to the idea of offering

    summer vacation experience to students

    during the winter. The concept had real

    merit. We had engaged summer students

    at Beaconseld before with somewhat

    mixed results. This is not usually a measure

    of the desire of the student to “have a

    go”, but rather it is the coincidence of

    the engagement with permanent staff

    wanting to take annual leave. Inevitably,

    the students are slotted in to ll the rolesof absent staff, while receiving insufcient

    guidance and mentoring from remaining

    staff who are left to carry the burden.

    Furthermore, summer vacation students

    often simply want a job to earn some

    money and gain some experience. Marty,

    however, was keen to see a student

    undertake a project and complete real

    work. The project was to be titled

    Retrospective Analysis of Mining Induced

    Seismicity at Beaconseld Gold Mine. It

    seemed ideal. A summer vacation student

    with a dened project, arriving in thewinter when minimal leave was planned

    by site personnel would avoid all the usual

    pitfalls of a summer placement, and so

    it was agreed that a placement could be

    made.

    The Beaconseld Gold Mine has

    experienced seismicity since 2003.

    Increasing incidents of seismic events saw

    the installation of a temporary seismic

    array logging six uniaxial channels in

    early 2004, and this was replaced by a

    permanent array logging 12 channels (nine

    uniaxial and one triaxial) in mid 2005. The

    system was upgraded in 2007 and again in2009, and currently logs 24 channels (12

    uniaxial and four triaxial).

    In late 2005, the Beaconseld Gold Mine

    signed on to be a minor sponsor of the

    ACG’s Mine Seismicity and Rockburst

    Risk Management project. Sponsorship

    commenced from January 2006 and has

    continued since then. At the time of the

    original sponsorship, the Beaconseld Gold

    Mine had been experiencing signicant

    mining-induced seismicity for a period

    of two years. Much effort had been

    expended on developing an understandingof the seismicity and procedures to deal

    with it were being implemented through

    the development of a Ground Control

    Management Plan. The ACG software MS-RAP offered the opportunity to enhance the

    management of seismicity in the day-to-day operation of the mine.

    Following an accident at the mine in early 2006, all aspects of the mining operation were

    redesigned under the umbrella of a Case to Manage Underground Safety (or Case for

    Safety). The Case for Safety was developed in four tranches by Coffey Mining, and covered

    mining of capital and operating access development (Ptzner, 2006), sill driving (Sidea, Scott

    and Reeves, 2007), stoping in the generally aseismic east zone of the mine (King, Thomas

    and Scott, 2007), and stoping in the seismically active west zone where the most signicant

    changes were required (Scott and Reeves, 2007). A key requirement of the Case for Safety

    was the establishment of protocols to manage seismicity, and MS-RAP was a key tool in that

    endeavour.

    Hills and Penney (2008) describe the management of seismicity at the Beaconseld

    Gold Mine in some detail. Of particular utility within MS-RAP is the ability to implementOmori Analysis (Figure 1) to monitor and manage re-entry times into areas excluded after

    stope blasts. Seismic analysis is coupled with intensive monitoring (Figure 2) (Penny, Hills

    and Walton, 2008), including stress change using H1 cells, and the impact of that change

    on the rock mass and the installed support using SMART instruments. Stope blasting is a

    key trigger for stress change (Figure 3), and as a consequence it is the primary trigger for

    seismic activity.

     

    Figure 1 Omori analysis following a stope blast

    Underground

    Figure 2 Intensive monitoring at Beaconsfield showing the SMART cables (grey) and stress monitoring(HI cells) (yellow)

  • 8/20/2019 Revista 2 Articulos de Diseño de Minas Sub Level Caving

    14/2714 Australian Centre for Geomechanics • December 2009 Newsletter

    This is especially in the west zone of

    the mine where mining is conducted

    remotely (Hills, Mills, Penney and Arthur,

    2008), and exclusion zones of at least 50m are enforced. Other features within

    the MS-RAP package are also regularly

    interrogated to assist in the management

    of seismicity, including the various graphical

    analyses such as energy index/cumulative

    apparent volume (Figure 3) and apparent

    stress history, and mapping features such as

    excavation vulnerability potential.

    Real management decisions were being

    made and inuenced by the use of MS-RAP,

    but the potential of the package was not

    fully realised because a signicant database

    of seismic data had not been collectivelyreanalysed recently. A project was ready

    made, provided somebody could be

    dedicated to the task for a period of a few

    months.

    The student chosen to undertake

    the project was Natalie Kari, a 3rd year

    mining engineering student at LaurentianUniversity. While Marty provided

    supervising guidance from afar, a site

    based introduction to the use of MS-RAP

    was provided by Johan Wesseloo, ACG.

    Natalie was technically an employee of

    Allstate Explorations NL during her time

    at Beaconseld, and as such she technically

    reported to myself.

    Natalie provided the Beaconseld Gold

    Mine with a substantial analysis of its

    seismic data, particularly that collected

    over the 18 month period to June 2009

    when stoping had recommenced in earnestfollowing the 2006 accident. The database

    remained live for much of her stay, allowing

    Natalie to observe and understand all

    Figure 4 A plot of energy index/cumulative apparent volume

    the aspects of data capture through the

    ISSI system, its transfer to MS-RAP, and

    its analysis as an immediate tool through

    Omori Analysis after stope blasts, and as a

    longer term management tool in updatingEVP maps. She expended a signicant

    effort in analysing data to assist in the

    renement of re-entry protocols, and the

    latter formed the basis of her nal report.

    A synopsis of that report follows this

    article. The key to understanding the basis

    of a detailed data analysis such as Natalie

    performed can only be gained by observing

    the environment from which the data is

    obtained. Consequently, Natalie went

    underground to inspect the geotechnical

    environment regularly, and every effort was

    made to introduce her to as many facets

    of mining geomechanics at Beaconseldas possible. As a result, the report she

    ultimately produced has real practical

    application in the ongoing management of

    seismicity at the mine.

    The experience of hosting a project

    focused summer vacation student was a

    positive one for the Beaconseld Gold

    Mine. Our continued use of MS-RAP as

    a tool in the management of seismicity

    has been enhanced as a result. The fact

    that the summer vacation student came

    in the winter when vacation was not the

    focus of mine staff was a signicant factorin ensuring that maximum benet could

    be obtained by all parties concerned. In

    particular, the benet to the students

    of early career international experience

    cannot be over-emphasised.

     Article references are available on request.

    Figure 3 A plot of raw micro-strain change data illustrating the impact of stope blasting (and nonblast-related seismicity) on the local stress field 

     

    Peter Hills ,Tasmania Mine Joint Venture,

    BCD Resources (Operations)NL

  • 8/20/2019 Revista 2 Articulos de Diseño de Minas Sub Level Caving

    15/2715Australian Centre for Geomechanics • December 2009 Newsletter

    Understanding mining-induced seismicityat Beaconseld Gold Mineby Natalie Kari, Laurentian University, Canada

     

    Figure 1 Distribution of re-entry times for 73 production blasts at Beasonsfield Gold Mine in 2008 and 2009

    A project was undertaken at the

    Beaconseld Gold Mine to investigate the

    current mining-induced seismicity at the

    operation. The objectives of the project

    were to identify all of the main seismic

    sources currently active in the mine and to

    rate the seismic sources with regards to:

    • Seismic source mechanism (the rock

    mass failure mode causing the seismicevents).

    • Seismic hazard (the largest expected

    seismic event that would be expected).

    • How mining activities (particularly stope

    blasting) affects the rate of seismicity

    from each of the seismic sources.

    • The ability for seismic monitoring to be

    used as a re-entry tool for each of the

    seismic sources.

    The seismic analyses in this project were

    all conducted using the ACG’s MS-RAP

    program (Mine Seismicity Risk Analysis

    Program).The complex geology and geological

    structures of the Beaconseld Gold Mine,

    including faults, contact zones, shears,

    bedding and splays, contribute to the

    challenges of mining within the Tasmanian

    reef. More than 8500 seismic events

    were recorded at the Beaconseld Gold

    Mine between March 2008 and February

    2009, including nine events larger than

    local magnitude +1.0. A cluster analysis

    identied 56 groups of seismic events

    during this period, of which 23 were

    particularly active and investigated in detail.

    Each group was analysed to determine theseismic source mechanism, seismic hazard

    and the rock mass response to production

    blasting in the mine. This analysis helped

    to describe the character of each seismic

    source and highlight the seismic sources

    most likely to cause operational issues at

    the mine. When higher hazard seismic

    sources can be identied, a range of

    seismic risk mitigation techniques can

    be used to manage the hazard. Ten of

    the seismic sources were found to have

    a qualitative seismic hazard rating of

    moderate-high to high. The seismic hazardrating is a good indicator of the likelihood

    of larger magnitude events.

    The seismic source mechanism at each

    seismic source, for the one year time

    period March 2008 – February 2009,

    was compared to the seismic source

    mechanism over the last four years (June

    2005 – June 2009). In almost all cases, the

    analysis showed that the seismic source

    mechanism remained constant over time.

    This is an important conclusion, as itmeans that it is the local rock mass failure

    mechanism that is controlling the nature

    of the seismicity, irrespective of the nearby

    mining inuences. When the current

    seismic response to mining is similar to the

    past seismic response to mining, it gives

    greater condence in using the current

    seismicity to understand future seismicity.

    Overall, the majority of seismic source

    mechanisms at the Beaconseld Gold Mine

    are related to the volumetric fracturing

    associated with mining-induced stresses as

    a direct response to mine blasting.An investigation of how mining activities,

    particularly stope blasting, affects the rate

    of seismicity from each of the main seismic

    sources was conducted. The proximity

    of each of the seismic sources to the

    stope blasts was considered. As expected,

    seismic sources in close proximity to

    mine blasts have a higher rate of induced

    seismicity than stopes located at further

    distances. However, two particular seismic

    sources did not follow this trend; often

    having a disproportionately intense seismic

    response to distant mine blasts. Identifying

    seismic sources that do not follow

    expected trends is often an indicator of

    locations which have a strong geological

    control. These locations require particular

    vigilance with respect to monitoring and

    underground inspections.

    Post blast re-entry times were estimatedfor 73 production blasts, using 90% of the

    total seismic energy as a re-entry criterion.

    The overall distribution of re-entry times is

    shown in Figure 1. Using this 90% of total

    seismic energy re-entry criterion, 59 of the

    production blasts had a possible re-entry

    time of less than 12 hours, with 14 blasts

    requiring a re-entry time of more than 12

    hours. Figure 2 shows that re-entry times

    are somewhat controlled by local seismic

    sources and vary spatially in the mine. It

    was concluded that for the Beaconseld

    Gold Mine, a 24 hour re-entry period isusually conservative, although at times it

    may be required. It is suggested that other

    tools, such as the seismic hazard mapping

    tool in MS-RAP, be used in conjunction

    with the re-entry analysis when making a

    nal decision on re-entry following each

    blast. In addition, it is important that

    this analysis procedure be continued to

    monitor future changes in seismological

    patterns and their potential effect on re-

    entry times.

    Underground

  • 8/20/2019 Revista 2 Articulos de Diseño de Minas Sub Level Caving

    16/2716 Australian Centre for Geomechanics • December 2009 Newsletter

    An excavation vulnerability potential

    (EVP) map was built for the Beaconseld

    Gold Mine. The EVP map identies regions

    of the mine that need particular attention

    with regard to seismic risk management

    procedures such as re-entry times,

    enhanced ground support, etc. Other key

    points have also come to light during the

    course of this project:1. The Beaconseld Gold Mine data is

    well behaved. It provides good source

    parameters and locations and follows

    standards and expected trends in seismic

    data.

    2. The seismic data gives a clear indication

    of where the seismic problems are

    located within the mine and where

    there are no seismic problems. This is

    important for future planning, and shows

    that seismic monitoring is a key tool for

    forecasting future problems.

    3. The back-analysis shows that seismic

    data identies the areas with higher

    seismic hazard, or which sources are

    more prone or likely to have large

    events. It is apparent that some

    seismic sources are more active than

    others; the seismic system shows this

    clearly. It is important to note that the

    most seismically active sources do not

    necessarily have the highest seismic

    hazard.4. Daily analysis and management of seismic

    data is fundamental to understanding

    seismic risk.

    5. At this time, the analysis did not show

    any acceleration of event rate or

    increased seismic hazard with depth

    indicating that there are no obvious

    problems with incrementally deepening

    the mine.

    6. It is recommended that one person at

    the mine be dedicated to analysing the

    seismic data and familiar with MS-RAP,

    using it to its maximum potential.

    It is important to note that there are

    Figure 2 Location of the blasts for which the re-entry analysis was conducted 

    limitations to all of the analyses undertaken

    in this study. Sound judgment should be

    undertaken when utilising the information

    provided. Focus should be placed on

    minimising personnel exposure to areas ofthe mine where seismic hazard is greatest.

    It is important that all available data and

    tools continue to be utilised in order to

    minimise the seismic risk.

    Acknowledgments

    This project would not have been

    possible without the support, insights

    and direction of several people. I would

    like to express my gratitude to Marty

    Hudyma, Laurentian University, and

    Peter Hills, Beaconseld Gold Mine for

    providing me with this opportunity and

    whose supervision and direction played aninvaluable role in this project. I would like

    to thank Johan Wesseloo for conducting

    a site visit and help in using MAP3D. I am

    also grateful to Tim Parkin, Toby Collins and

     Jerome Paterson, Beaconseld Gold Mine

    for providing me with guidance during the

    course of my project. Notable thanks to

    Roger Hill for helping me understand the

    geology of the mine.

    Natalie’s project, undertaken between

    May and August 2009, was a joint effort

    between Beaconseld Gold NL, Laurentian

    University and the ACG. Similar student

    summer undergraduate projects have been

    organised each year, for the last ten years,

    for sponsors in the ACG’s “Mine Seismicity

    and Rockburst Risk Management” project.

     Mine Seismicity and Rockburst Risk Management Project

    Natalie Kari,

    Laurentian University,Canada

    Since its commencement in 1999, the goal

    of the ACG’s MSRRM research project has

    been to advance the application of seismic

    monitoring in the mining industry to quantify

    and mitigate the risk of mine seismicity and

    rockbursting. This has seen close involvement

    at research sponsor sites by undertaking

    detailed site seismic analysis, testing or

    experimental work and providing seismicsystem technical support and advice as

    required.

    Phase IV of this research project, entitled

    “Advancing the Strategic Use of Seismic Data

    in Mines”, is currently underway and aims to

    develop the strategic use of seismic data and

    promote an increased understanding of the

    rock mass seismic response to mining. The

    ACG acknowledges the generous support

    and encouragement of its Phase IV research

    project sponsors. Additional project sponsors

    are sought.For further information please contact

    project leader, Johan Wesseloo, ACG via

    [email protected]

  • 8/20/2019 Revista 2 Articulos de Diseño de Minas Sub Level Caving

    17/2717Australian Centre for Geomechanics • December 2009 Newsletter

    The risk oftailings disposal

    by Keith Seddon, ATC Williams

    Introduction

    In September 2010, the ACG will host

    the First International Seminar on the

    Reduction of Risk in the Management

    of Tailings and Mine Waste in Perth. The

    purpose of this article is to reect on

    some of the issues that contribute to that

    risk. It is written from the perspective of a

    consultant.

    A well known website (www.wise-

    uranium.org/mdas.html) catalogues tailingsdam failures. In the (nearly) 30 years since

    1980, it lists 52 incidents, spread across 20

    different countries, and all continents. An

    “incident” is broadly dened and includes

    everything from contaminated seepage into

    groundwater, and (relatively minor) spills

    from broken pipes, all the way through

    to overtopping during storm events,

    catastrophic failure and collapse. The list

    is by no means complete. Additionally,

    inspection of the list shows an over-

    representation of events from North

    America, mostly related to small leaks and

    spills. Are the North Americans worse atmanaging their operations than the rest of

    the world? Or, is it more likely that they

    are simply subject to greater scrutiny and

    higher standards? These questions aside,

    what can we learn from this list about the

    risks of tailing storages?

    • Incidents occur across all mineral types.

    • Incidents occur across the full range of

    company size and status.

    • Incidents occur in both developed and

    under-developed countries.

    • The frequency of incidents does not

    appear to be decreasing.

    If you have a tailings dam on your site, it

    is a risk.

    Management of risk 

    Tailings storage and disposal does not

    rank high on the scale of overall mine

    production costs. But it does weigh

    heavily in terms of the overall risk to

    an operation, both initially with permits

    and approvals, and in relation to ongoing

    operations. There is nothing like a well

    publicised tailings dam incident to damage

    a company’s “license to operate”. So,

    increasingly we see that managementof mine tailings is about understanding

    and management of risk. The risk based

    approach is not unique to tailings storages.

    It is also widely used for management of

    water dams and other activities.

    Two examples demonstrate the trend

    with respect to dam safety. The NSW

    Dams Safety Committee is currently in

    the process of a comprehensive re-casting

    of its requirements in order to integrate

    a risk based approach. And, the ANCOLD

    tailings dam guidelines (originally issued in

    1999) are being updated with increased

    emphasis on risk. For this approach tobe effective, a core requirement for

    management is to be fully committed to

    the process, through adequate support and

    resources.

    Fundamental hazards

    There are at least four fundamental

    hazards that need to be considered for all

    tailings storages.

    Potential energy [“Gravity is a bitch”]

    All above ground storages place tailings

    in an elevated location relative to someposition around the storage. In the event

    of a breach, this potential energy may

    convert to kinetic energy. This means that

    the runout distances and consequences of

    failure need careful consideration. These

    considerations also apply to in-pit storages.

    if there are underground workings belowthem.

    Low strength

    Strength inuences runout distances

    and the assessed consequences of failure.

    In addition, it also relates directly to

    bearing capacity and the safe access over

    the tailings for activities including raising

    and capping. The strength of geotechnical

    materials is tricky to dene. It varies

    with time and is dependent on the rate

    of loading. Almost all tailings start out as

    slurries, i.e. liquid. After deposition, some

    tailings progress towards the solid statefaster than others. But this does not mean

    that any tailings dam can be treated like a

    waste dump.

    Geochemistry/acid potential 

    Many types of tailings contain a

    proportion of sulphur, which may oxidise

    to form sulphuric acid. This in turn has the

    potential to mobilise trace heavy metals,

    and make even small amounts of seepage

    a very undesirable consequence. Little can

    be done to eliminate this basic hazard; the

    geochemistry of the orebody is not opento negotiation. However, in the future

    possibly more attention will be given to

    attempts to remove sulphides as part

    of the process, and reduce the residual

    hazard in the tailings. The potential for acid

    production impacts both on operations

    and on closure requirements for a storage.

    It needs to be evaluated during the design

    of all tailings dams, and may need to be

    monitored routinely over the mine life.

    Process chemistry 

    The tailings solids may prove to be

    relatively benign, but it is necessaryto consider the process and how this

    inuences the chemistry of the decant

    water. This includes processes that use

    cyanide (gold tailings), high pH (bauxite

    red-mud), and low pH (laterite nickel), and

    elevated levels of salinity should also be

    included.

    Many of the decisions relating to

    process chemistry are fundamental to the

    feasibility and design of the whole mine

    and concentration / beneciation process,

    and may be considered as “constraints” to

    the tailings dam designer. However, whenthese conditions occur, they are likely to be

    powerful drivers of the subsequent design.

    The author is looking forward to the day

    Tailings

  • 8/20/2019 Revista 2 Articulos de Diseño de Minas Sub Level Caving

    18/2718 Australian Centre for Geomechanics • December 2009 Newsletter

    that a laterite nickel process co-locates

    with a bauxite renery, and the two waste

    streams are combined to neutralise each

    other.

    Factors contributing to risk 

    In risk management terminology, it is

    usual to dene risk as consequence x

    probability of failure. Consequence relates

    to hazard, and is typically measured in

    terms of loss of life, or cost of remediation.

    Management of risk can address both

    of these components. For instance, the

    consequence of a failure will be dependent

    on the location and size of a dam, and

    factors such as the strength of the

    contained tailings. Most of these types of

    issues need to be addressed during site

    selection and design. It is too late to doanything about location after a dam is built.

    On the other hand, there are many issues

    related to the operation and management

    of a tailings dam that impact directly on

    the probability of failure, whether this

    is explicitly recognised during design or

    not. The following discussion covers both

    operation and management components,

    but is slightly biased towards operational

    issues.

    Poor communication

    Many problems stem from poorcommunication, i.e. between the designer

    and site management, or management

    and operators. The designer (often

    a consultant) may make particular

    assumptions regarding the way the dam

    will be operated and raised. Typically, these

    matters will be covered in a design report.

    But the implementation of these lies

    with the mine, and personnel rarely have

    time to read design reports. A common

    solution is to have an “operations and

    maintenance manual” (OM) to cover

    these aspects. A good OM manual needs

    to be comprehensive, structured, wellwritten, and be easily understood by all

    users. Usually the details require input

    from both the designer and the mine, and

    a co-operative approach to preparation is

    required.

    Tailings dams are not static structures,

    they are continually being raised or

    modied in some way, and all OMs need

    to be regularly checked and upgraded to

    mirror these changes.

    Bad decisions [“It seemed like a good idea atthe time”]

    There comes a time in the life of some

    storages when a decision is made that

    fundamentally effects safety performance,

    and what can be done with the storage

    in the future. This is typically somethi