Revised Timeline
description
Transcript of Revised Timeline
![Page 1: Revised Timeline](https://reader036.fdocuments.in/reader036/viewer/2022070422/568163e5550346895dd546bc/html5/thumbnails/1.jpg)
![Page 2: Revised Timeline](https://reader036.fdocuments.in/reader036/viewer/2022070422/568163e5550346895dd546bc/html5/thumbnails/2.jpg)
January – May 2013Existing Curriculum and Space Needs Summary• Facilities staff meets individually with all school principals, as well as Academics and Accountability (Curriculum and CTAE), Special Education, and Instructional Technology (Curriculum Support and Media Centers) staff:
• Verify curriculum programs/grade level meet the current and projected enrollment for each school.
• Match existing Instructional Units (IU) to meet the curriculum and grade level per published requirements
• Identify any deficiency with space assignment or quantity of IU’s to meet the future enrollment.
• Identify any additional IU’s or space modifications to address new curriculum programs.
Revised Timeline
![Page 3: Revised Timeline](https://reader036.fdocuments.in/reader036/viewer/2022070422/568163e5550346895dd546bc/html5/thumbnails/3.jpg)
Revised Timeline
January – May 2013 (cont.)Perform Physical Assessment of Facilities• Identify and assess Life Cycle items• Examples: plumbing, HVAC, carpentry and electrical
• Evaluate the building and site conditions for renovations
Receive Stakeholder Input on Facilities PlanLSC, online and Superintendent Advisory meetings
June – August 2013 Distribute Projected Enrollment and Review Capital Outlay Needs
• June 12: District Facilities Plan Committee meets to discuss and determine recommendations for BOE
• August 8: Present Committee notes to BOE, discussion
![Page 4: Revised Timeline](https://reader036.fdocuments.in/reader036/viewer/2022070422/568163e5550346895dd546bc/html5/thumbnails/4.jpg)
Revised Timeline
September – December 2013 • Sept. 12: BOE discusses June Committee notes• Oct. 7: District Committee meets to discuss and
determine final recommendations for BOE• Oct. 10: Present recommended Facilities Plan to BOE,
discussion• Nov. 14: BOE discusses recommended Facilities Plan• Nov. 21: BOE approves 2014-19 Facilities Plan• December: Outside Survey Team reviews Facilities
Plan/Deliver final plan to GA DOE
Spring 2014 2014-19 Facilities Plan Approved by GA DOE
July 1, 2014 2014-19 Facilities Plan Goes Into Effect
![Page 5: Revised Timeline](https://reader036.fdocuments.in/reader036/viewer/2022070422/568163e5550346895dd546bc/html5/thumbnails/5.jpg)
Committee Recommendations
www.forsyth.k12.ga.us/facilitiesplan
![Page 6: Revised Timeline](https://reader036.fdocuments.in/reader036/viewer/2022070422/568163e5550346895dd546bc/html5/thumbnails/6.jpg)
Previous Enrollment Trends
![Page 7: Revised Timeline](https://reader036.fdocuments.in/reader036/viewer/2022070422/568163e5550346895dd546bc/html5/thumbnails/7.jpg)
Enrollment Trends Update
![Page 8: Revised Timeline](https://reader036.fdocuments.in/reader036/viewer/2022070422/568163e5550346895dd546bc/html5/thumbnails/8.jpg)
Proposed Organization: Elementary Schools
![Page 9: Revised Timeline](https://reader036.fdocuments.in/reader036/viewer/2022070422/568163e5550346895dd546bc/html5/thumbnails/9.jpg)
Elementary #14: Project Summary
![Page 10: Revised Timeline](https://reader036.fdocuments.in/reader036/viewer/2022070422/568163e5550346895dd546bc/html5/thumbnails/10.jpg)
Proposed Organization: Middle Schools
![Page 11: Revised Timeline](https://reader036.fdocuments.in/reader036/viewer/2022070422/568163e5550346895dd546bc/html5/thumbnails/11.jpg)
Proposed Organization: High Schools
![Page 12: Revised Timeline](https://reader036.fdocuments.in/reader036/viewer/2022070422/568163e5550346895dd546bc/html5/thumbnails/12.jpg)
Explanation & Justificationfor Proposed Organization
![Page 13: Revised Timeline](https://reader036.fdocuments.in/reader036/viewer/2022070422/568163e5550346895dd546bc/html5/thumbnails/13.jpg)
Explanation & Justificationfor Proposed Organization
![Page 14: Revised Timeline](https://reader036.fdocuments.in/reader036/viewer/2022070422/568163e5550346895dd546bc/html5/thumbnails/14.jpg)
Tabulation of Priorities
![Page 15: Revised Timeline](https://reader036.fdocuments.in/reader036/viewer/2022070422/568163e5550346895dd546bc/html5/thumbnails/15.jpg)
Tabulation of Priorities
![Page 16: Revised Timeline](https://reader036.fdocuments.in/reader036/viewer/2022070422/568163e5550346895dd546bc/html5/thumbnails/16.jpg)
2014 Bond Referendum