Revised Pavement Design - Beawar Pali Section.pdf

download Revised Pavement Design - Beawar Pali Section.pdf

of 36

Transcript of Revised Pavement Design - Beawar Pali Section.pdf

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    1/119

    INDEPENDENT CONSULTANT :

    CONCESSIONAIRE : DESIGN CONSULTANT :

    L&T Construction

    DSGN 22.08.2012

    CHKD 22.08.2012

    APPD 22.08.2012

    DOC. No. O 11 2 3 8 - C - R P - R D - P D - 0 0 0 1

    RELEASED FOR   PRELIMINARY TENDER INFORMATION 

    APPROVAL CONSTRUCTION

     AAN

    INDIA

    MJT

    DESCRIPTION

     AAN

    VGS

    Approved

    Pavement Design Report (Beawr - Pali Section)

    Pavement Design Report (Beawr - Pali Section)

    CheckedDesigned

    RHN

    RHN MJT

    RHN

    SIGN

        T    h    i   s    d   o   c   u   m   e   n    t    i   s    t    h   e   p   r   o   p   e   r    t   y   o    f       L       &

           T       C     o     n     s       t     u     c       t       i     o     n  ,

           I     n       f     r     a     s       t     r     c     u       t     u     r     e  ,

           E       D       R       C       &       T

       m   u   s    t   n   o    t    b   e   p   a   s   s   e    d   o   n    t   o   a   n   y    t    h    i   r    d   p   e   r   s   o   n   o   r    f    i   r   m

       n   o    t   a   u    t    h   o   r    i   s   e    d    b   y   u   s ,

       n   o   r    b   e   c   o   p    i   e    d    /   m   a    d   e   u   s   e   o    f    i   n    f   u    l    l   o   r   p   a   r    t    b   y   s   u   c    h

       p   e   r   s   o   n   o   r    f    i   r   m    w

        i    t    h   o   u    t   o   u   r   p   r    i   o   r   p   e   r   m    i   s   s    i   o   n   w   r    i    t    i   n   g

    REVISIONS

    Pavement Design Report (Beawr - Pali Section)

    L&T Construc t ion 

      Infrastucture

    B AAN

    JOB No.

    L & T BPP TOLLWAY PRIVATE LIMITED

    CIRC

    PAVEMENT DESIGN REPORT

    (BEAWAR - PALI SECTION)

    TOTAL NO. OF PAGES

    O11238-C-RP

    CODE REV.

    VGS

    NAME

    RHN

     AAN

    NATIONAL HIGHWAYS AUTHORITY OF

    Infrastucture-EDRC&T

    TITLE :

    22.08.2012 C

    DATE

    DATE

    PROJECT :

    12.07.2101

    25.01.2012 A

    REV. NO.

    CLIENT :

    BEAWAR-PALI-PINDWARA ROAD PROJECT (BPPRP )

    EPC CONTRACTOR :

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    2/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 1 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    Table of Contents

    1.0  Introduction, Background and Description .......................................................................... 4 

    1.1  Introduction ...................................................................................................................... 4 

    1.2  Project Description and Scope ......................................................................................... 4 

    2.0  Field Investigations and Geotechnical Sampling ................................................................. 6 

    2.1  Pavement Condition Survey ............................................................................................. 6 

    2.2  Benkelman Beam Deflection Testing .............................................................................. 6 

    2.2.1  Leg Correction Factor ................................................................................................... 7 

    2.2.2  Correction for Temperature .......................................................................................... 7 

    2.2.3 

    Correction for Seasonal Variation ................................................................................ 8 

    2.2.4  Characteristic Deflection .............................................................................................. 8 

    2.3  Field Investigation and Sampling ..................................................................................... 8 

    2.4  Laboratory Testing ........................................................................................................... 9 

    3.0  Field Investigation Survey and Laboratory Test Results ................................................... 10 

    3.1  Pavement Condition Survey Results .............................................................................. 10 

    3.2  Benkelman Beam Deflection Testing Data and Results ................................................ 10 

    3.3  Field Investigation and Sampling Results ...................................................................... 13 

    3.3.1 

    Assessment of Existing Pavement Composition .................................................... 13 

    3.3.2  Assessment of In-situ Density of Subgrade ............................................................ 15 

    3.3.3  Assessment of Subgrade CBR Using Dynamic Cone Penetrometer ...................... 17 

    3.3.4  Laboratory Testing Results ..................................................................................... 19 

    4.0  Traffic Study & Analysis ................................................................................................... 21 

    5.0  Impact of Concession Agreement on Pavement Design .................................................... 23 

    6.0  Overlay Pavement Design (Flexible Pavement) ................................................................ 24 

    6.1 

    Calculation of Characteristic Deflection ........................................................................ 24 

    6.2  Pavement Overlay Thicknesses ...................................................................................... 24 

    7.0  Flexible Pavement Design for Main Carriageway Widening, Reconstruction Sections, and

    Approaches of Grade Separators .................................................................................................. 26 

    7.1  Discussion of Design CBR ............................................................................................. 26 

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    3/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 2 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    7.2  Pavement Layer Thickness Design ................................................................................ 27 

    7.2.1  Methodology for Pavement Sections with Design CBR 10% .................................... 27 

    7.2.2  Methodology for Pavement Sections with Design CBR 12% .................................... 27 

    7.2.2.1  Allowable Strains in the Pavement Structure ......................................................... 28 

    7.2.2.2  Actual Strains in the Pavement Structure ............................................................... 28 

    7.3  Validation of Analytical Approach of Pavement Design Using Standard IRC Sections 29 

    7.4  Pavement Layer Thicknesses Recommendation ............................................................ 29 

    8.0  Pavement Design (Flexible Pavement) for Service Road, and Slip Road of Flyover and

    Underpass ...................................................................................................................................... 31 

    9.0  Pavement Design (Rigid Pavement) for Toll Plaza ........................................................... 32 

    9.1  Methodology .................................................................................................................. 32 

    10.0  Conclusion ......................................................................................................................... 36 

    List of Figures

    Figure 1 Key Map ........................................................................................................................... 5 

    List of Tables

    Table 3.1 Summary of Pavement Condition Survey .................................................................... 10 

    Table 3.2 Pavement Distress Analysis .......................................................................................... 10 

    Table 3.3 Kilometer-wise Characteristic Deflections ................................................................... 11 

    Table 3.4 Existing Pavement Crust Composition ......................................................................... 13 

    Table 3.5 In-situ Density of Subgrade .......................................................................................... 16 

    Table 3.6 In-Situ DCP-CBR ......................................................................................................... 18 

    Table 4.1 Homogeneous Section-wise Cumulative Traffic .......................................................... 22 

    Table 6.1 Overlay Design ............................................................................................................. 25 

    Table 7.1 Design CBR Values for Pavement Design ................................................................... 26  

    Table 7.2 Recommendations for New Pavement Sections ........................................................... 30 

    Table 8.1 Pavement Crust for Service Road ................................................................................. 31 

    Table 9.1 Design Traffic ............................................................................................................... 33 

    Table 9.2 Design Calculations of Rigid Pavement ....................................................................... 33 

    Table 9.3 Rigid Pavement Design - Summary.............................................................................. 35 

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    4/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 3 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    List of Appendices

    Appendix 1 Pavement Condition Survey Data

    Appendix 2 Benkelman Beam Deflection Survey DataAppendix 3 Laboratory Testing Results

    Appendix 4 Overlay Design

    Appendix 5 Pavement Structural Sections Recommendations for New Pavement Design

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    5/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 4 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    1.0 Introduction, Background and Description

    1.1  Introduction

    This pavement design report is prepared in order to recommend suitable pavement structural

    sections for the overlay as well as the new pavement portions for four laning of the Beawar to

    Pali section of NH-14. Pavement design is the most important component of any highway

     project, since a pavement has to ultimately carry the entire traffic loads and protect the subgrade.

    The following pages contain a comprehensive report consisting of a review of the project site

     parameters; review and analysis of various field surveys and pavement materials; review of

    traffic components; analysis and design of the pavement overlay sections; and analysis and

    design of the new pavement structural sections.

    1.2 

    Project Description and Scope

    The aerial extent of the proposed project comprises of three districts: Ajmer, Pali, and Sirohi, all

    in the state of Rajasthan. The project road lies in the district of Ajmer, Rajasthan from Km 0.00

    to Km 6.900, in the district of Pali, Rajasthan from Km 6.900 to Km 185.00, and in the district of

    Sirohi, Rajasthan from Km 185.00 to Km 246.00.

    It is expected that about 4853028 persons (about 8.59% of total population of Rajasthan) are

    likely to be benefited. Among the three districts, Ajmer has the highest population density of

    about 257 persons/sq.km while Pali has the lowest population density of 147 persons/sq.km. The

    decadal population growth from 1991-2001 is maximum in Sirohi at 30.13 %, and the lowest inPali at 22.46%.

    The project alignment connects the western part of the state of Rajasthan to NH-8 in the north (to

    Jaipur) and to NH-76 in the south (to Udaipur and Abu Road). The project road from Beawar to

    Pali is a part of this National Highway (NH-14) in the state of Rajasthan. The limits of the

     project extend from the station at existing km 000+000 up to the station at km 115+400

    (proposed chainage of Km 113+000) just beyond the junction of NH-65 at Pali. The road is a

     part of a high density traffic corridor. Some of the major towns and villages through which the

    alignment of the road traverses through are: Sadatana, Lalpura, Sapalpura, Dhaba, Jhala ki

    Chowk, Barr, Raipur, Juta, Juta Mata Nagri, Pipalia Kalan, Sandiya, Dhaba, Sojat, Bhagavas,Ravia Bara, Jardan, Math, Pali Balaji Area, and the major town of Pali. A key map showing the

     project with the proposed bypasses is attached as Figure 1.

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    6/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 5 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    Figure 1 Key Map 

    The existing road consists of flexible type pavement, with two lanes. From a road inventory

    survey performed, it was observed that the most of the carriageway as about 7 m wide.

    The road has been identified by the National Highway Authority of India (NHAI) for

    strengthening of the existing carriageway and augmentation in its traffic carrying capacity.

    Keeping in view the importance of the project road for the socio economic development of the

    region and to meet the growing demands of traffic, it is proposed to: (i) strengthen the existing 2

    lane pavement, and (ii) augment its capacity by widening it to 4 lanes.

    Since the existing pavement is of flexible type, it is proposed to design flexible pavements for

    the additional two lane carriageway sections, and flexible overlays for strengthening the existing

     pavement.

    The scope of this work was to collect the data needed for the design of new pavements for the

    additional two lane carriageway portions, and to prepare pavement rehabilitation andstrengthening strategy. In order to perform the above broad scope of work, L&T also included in

    its scope field investigations field sampling, field testing, and laboratory testing. Some of these

    tasks were completed by L&T, while others were completed by outside agencies and reviewed

     by L&T.

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    7/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 6 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    2.0 Field Investigations and Geotechnical Sampling

    In order to perform the scope of work, the following investigations/surveys were conducted by

    L&T:

    1.  Pavement Condition Survey;

    2.  Benkelman Beam Deflection Testing;

    3.  Field Investigation and Sampling;

    4.  Laboratory Testing.

    Following is a brief description of the investigations and surveys that we conducted for the

     project.

    2.1 

    Pavement Condition Survey

    The visual condition survey was conducted in order to record the pavement condition for every

    100 m intervals. This included recording information on any deficiencies that were visible and

    also any improvements and treatments. The type of rehabilitation strategy to be adopted is

    contingent upon the existing pavement crust composition and the visual condition survey. The

    condition survey was conducted by considering the following details and their brief descriptions:

    1. Length : Minimum of 100 m section

    2. Surfacing Description : BT/CC/GR/ER

    3. Rut Depth : in mm4. Cracks : % of Area

    5. % Area Covered by : Potholes, Raveling, Patching

    6. Shoulder Condition : Good/Fair/Poor/Very Poor

    7. Remarks : If any

    The data and finding from this pavement condition survey are given in Appendix 1.

    2.2 Benkelman Beam Deflection Testing

    Benkelman Deflection Survey was carried out to assess the residual strength of the existingflexible pavement and thereby assess the requirement of structural overlay. The survey was

    conducted in accordance with IRC: 81-1997 provisions, and the Canadian Good Road

    Association (CGRA) method. Deflection readings were taken on previously identified stretches

    that were based on the pavement condition survey. The collected deflection data were analyzed

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    8/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 7 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    along with the corrections required in accordance with requirement of IRC: 81-1997. The

    corrections were calculated for:

      Leg correction.

      Pavement Temperature.

      Seasonal Correction.

      Subgrade moisture content.

      PI of Subgrade.

    The data and finding from Benkelman beam deflection survey are given in Appendix 2.

    2.2.1  Leg Correction Factor

    While measuring the deflection there is every chance of deflection bowl extending up tosupporting legs of the Benkelman beam. The deflection of legs is revealed by the difference in

    differential reading between initial, intermediate and final reading. If the differential reading

     between initial and final and intermediate and final differ by more than 0.025mm then leg

    correction needs to be applied. The true deflection is computed as:

    XT = XA + 2.91 Y

    Where,

    XT = True pavement deflection

    XA = Apparent pavement deflection i.e. 2X (Final  –  Initial reading)

    Y = Vertical movement of the front legs i.e., twice the difference between the final and intermediatereading.

    2.2.2  Correction for Temperature

    The stiffness of bituminous layers changes with temperature of the bonder and consequently the

    surface deflection of bituminous pavement will vary depending upon the temperature of the

    constituent bituminous layers. Therefore it is necessary that the measured deflection be corrected

    to a common standard temperature for tropical climate of India. The standard temperature is

    taken as 35°C. Correction for temperature variation on deflection for values other than those

    measured at 35°C shall be 0.01 mm for each degree of change from the standard temperature of

    35°C. The correction will be positive for pavement temperatures lower than 35°C and negative

    for pavement temperature higher than 35°C.

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    9/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 8 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    2.2.3  Correction for Seasonal Variation

    Since the pavement deflection is dependent upon change in climate/season of the year, it is

    always desirable to take deflection measurements during the season when the pavement in its

    weakest condition. This condition occurs immediately after the monsoons in India. When

    deflection measurements are taken during dry months, they require correction factor, which is

    defined as the ratio of maximum deflection immediately after the monsoon to that of deflection

    in the dry months.

    Correction for seasonal variation depends upon the type of the sub-grade soil, its field moisture

    content (at the time of deflection testing), and average rain fall in the area. For this purpose sub-

    grade soil has been divided into three broad categories namely sandy/gravely clayey with low

     plasticity (PI 15). Similarly rainfall has been divided

    into two categories namely annual low rainfall (< 1300mm) and annual high rainfall (>1300mm).

    2.2.4  Characteristic Deflection

    The statistical analysis involves calculation of mean deflection value, standard deviation and

    characteristic deflection. The design calculations are us under.

      

    ∑ ⃛

     

     

     

    Where,

    X = individual deflection, mm

    x = mean deflection, mm

    ƞ = number of deflection measurements

     

    2.3 Field Investigation and Sampling

    An extensive field investigation and sampling exercise was conducted. The following were the

    objectives of this exercise:

    1.  To assess the existing pavement composition;

    2.  To assess the in-situ density of the subgrade;

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    10/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 9 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    3.  To assess the subgrade California bearing ratio (CBR), using the dynamic cone

     penetrometer (DCP) test; and

    4.  To collect subgrade samples for performing laboratory tests.

    Assessment of the existing pavement composition was done by excavating test pits (size 1.0 m x

    1.0 m) at every 1 kilometer interval. These test pits were excavated on the shoulders, extending

    for about 10 cm into the outside lane of the project road. Test pit investigations were not

    conducted along those locations on the project road which formed a part of bypasses, re-

    alignments, and reconstruction sections. The number of test pits excavated along the project

    length was seventy one (71).

    Field density tests were conducted by Sand Replacement method for the test pits and also the

    natural moisture content were determined at each test pits. Dynamic Cone Penetration tests were

    conducted at pit locations to assess in-situ CBR at subgrade level. The equivalent CBR value was

    calculated based on different soil layers encountered. The slope change in the graph (Penetration

    Vs Number of Blows) indicates the interface of two layers of different penetration resistance.

    From the graph, thickness of layer and slope (penetration mm/blow) were calculated. The

    following TRRL equation has been used to calculate the layer DCPCBR value for each layer.

     

    2.4 Laboratory Testing

    The following laboratory tests were conducted for all the samples collected from the test pits.

      Grain Size Analysis (As per IS:2720-Part 4);

      Atterberg Limit test (As per IS:2720-Part 5);

      Standard Proctor tests (As per IS:2720-Part 8);

      4-day Soaked CBR at 3 energy levels (As per AASHTO method).

    Bulk sample of about 50 Kg was collected from all the test pits at sub grade level to analyze the

    characteristics of the existing subgrade material. The laboratory CBR tests were conducted on

    the test pit samples. Further three remoulded soil specimen were prepared from the samples

    collected from the test pits at an interval of 1 Km along the road and tested for CBR in

    accordance with AASHTO at three different energy levels by giving 10 blows, 30 blows and 65

     blows per layer in each CBR mould. These specimens were tested after soaking in water for four

    days. The CBR values were plotted in the Density Vs CBR graph and the CBR values

    corresponding to 97 % of MDD is interpolated.

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    11/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 10 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    3.0 Field Investigation Survey and Laboratory Test Results

    3.1 Pavement Condition Survey Results

    Table 3.1  below summarizes the overall pavement condition of the project road.

    Table 3.1 Summary of Pavement Condition Survey

    Pavement Condition Length (km)

    Good 33.300

    Fair 15.900

    Poor 20.400

    Table 3.2  below outlines the overall break-up and percentage distribution of the various

     pavement distresses such as cracking, potholes, raveling, and patching that were encountered

    along the length of the project.

    Table 3.2 Pavement Distress Analysis

    Sr.

    No

    Cracking

    (%)

    Length

    (km)

    Patching

    (%)

    Length

    (km)

    Pot holes

    (%)

    Length

    (km)

    Raveling

    (%)

    Length

    (km)

    1 1-5 2.4 1-5 6.6 1-5 1.4 1-5 1.3

    2 5-10 7.6 5-10 9.7 5-10 2.7 5-10 2.4

    3 10-20 12.7 10-20 10.9 10-20 2.3 10-20 6.1

    4 20-30 7.9 20-30 3.4 20-30 1.3 20-30 2.9

    5 30-40 5.7 30-40 2.5 30-40 0.5 30-40 2.0

    6 >40 6.7 >40 4.1 >40 - >40 1.5

    From the table above, it can be seen that the major distresses affecting the pavement were

    cracking, patching, pot holes and raveling. The portion of project length that was affected by

    more than 20% cracking was about 20 kilometers.

    3.2 

    Benkelman Beam Deflection Testing Data and Results

    The results of the Benkelman beam deflection testing are depicted in the following tables. Table

    3.3  below summarizes the kilometer-wise calculated characteristic deflections.

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    12/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 11 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    Table 3.3 Kilometer-wise Characteristic Deflections

    Chainage Characteristic

    Deflection (mm)From To

    9+600 10+550 0.430

    18+000 19+000 0.396

    19+000 20+000 0.545

    20+000 21+000 0.505

    21+000 22+000 0.719

    22+000 23+000 0.677

    26+100 27+000 0.516

    27+000 28+000 0.376

    28+000 29+000 0.397

    29+000 30+000 0.397

    30+000 31+000 0.422

    31+000 32+000 0.505

    32+000 33+000 0.780

    33+000 34+000 0.905

    36+000 37+000 1.160

    37+000 38+000 0.949

    38+000 39+000 0.836

    39+000 40+000 1.170

    40+000 41+250 1.323

    44+500 45+000 0.669

    45+000 46+000 0.773

    46+000 47+000 1.011

    47+000 48+000 1.017

    48+000 49+000 1.041

    49+000 50+000 1.171

    50+000 50+650 1.087

    53+000 54+000 0.746

    54+000 55+000 0.593

    55+000 56+000 0.751

    56+000 57+000 0.616

    57+000 58+000 0.782

    58+000 59+000 0.658

    59+000 60+000 0.786

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    13/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 12 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    Chainage Characteristic

    Deflection (mm)From To

    60+000 61+000 1.090

    61+000 62+000 0.720

    62+000 63+000 0.610

    63+000 64+000 0.566

    64+000 64+550 0.552

    65+150 66+000 0.665

    66+000 67+000 0.571

    67+000 67+850 0.682

    69+000 70+000 0.750

    70+000 71+000 0.795

    71+200 72+200 1.205

    73+000 74+000 1.650

    74+000 75+000 1.365

    75+000 76+000 0.957

    76+000 77+000 0.974

    77+000 78+000 0.889

    78+000 79+000 0.998

    78+600 79+600 1.073

    80+900 82+000 1.113

    82+000 83+000 0.861

    83+000 84+000 1.112

    84+000 85+000 1.252

    85+000 86+000 1.081

    86+000 87+000 1.166

    87+000 88+000 1.373

    88+000 89+000 1.083

    89+000 90+000 1.397

    90+000 91+000 1.033

    91+600 92+000 1.000

    92+000 93+000 1.273

    93+000 94+000 0.642

    94+000 95+000 1.181

    95+000 96+000 1.310

    96+000 97+000 1.695

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    14/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 13 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    Chainage Characteristic

    Deflection (mm)From To

    97+000 98+000 1.295

    103+000 104+000 0.866

    104+000 105+000 1.224

    106+600 107+000 1.618

    107+000 108+000 1.397

    108+000 109+000 1.264

    109+000 110+000 1.660

    110+000 111+000 1.942

    111+000 112+000 1.641

    Upon completion of the field survey, characteristic deflection was computed for each kilometer

    length of the project. These characteristic deflections formed the basis of delineations of the

     project length into various homogenous sections in terms of pavement distress.

    3.3 Field Investigation and Sampling Results

    The findings from the field investigations conducted are summarized in the following sections.

    3.3.1  Assessment of Existing Pavement Composition

    The profile of the excavated test pits was visually examined in order to record the existing

     pavement crust composition and identify the layer thicknesses. The outcome of this exercise is a

    table containing the break-up of the pavement crust, which is listed below in  Table 3.4. 

    Table 3.4 Existing Pavement Crust Composition

    Sr.

    No.Chainage

    (Km)Side

    Existing Crust Composition (mm)

    Bituminous WBM GSB Total

    1 19+000 LHS 110 180 290

    2 20+000 RHS 100 160 260

    3 21+000 LHS 110 200 310

    4 22+000 RHS 170 300 470

    5 27+000 RHS 200 140 340

    6 28+000 RHS 190 120 310

    7 29+000 RHS 200 130 330

    8 30+000 RHS 180 140 320

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    15/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 14 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    Sr.

    No.Chainage

    (Km)Side

    Existing Crust Composition (mm)

    Bituminous WBM GSB Total

    9 31+000 RHS 200 100 30010 32+000 RHS 200 230 430

    11 33+000 RHS 200 230 430

    12 34+000 LHS 110 200 310

    13 36+000 RHS 110 210 320

    14 37+000 RHS 160 210 370

    15 38+000 LHS 110 220 330

    16 39+000 RHS 170 220 390

    17 40+000 RHS 140 200 340

    18 41+000 RHS 170 180 350

    19 42+000 RHS 170 230 400

    20 45+000 RHS 170 250 420

    21 46+000 RHS 210 240 450

    22 47+000 RHS 180 220 400

    23 48+000 RHS 160 180 340

    24 49+000 RHS 180 240 420

    25 50+000 RHS 130 260 390

    26 54+000 RHS 270 160 430

    27 55+000 RHS 220 260 480

    28 56+000 RHS 110 150 260

    29 57+000 RHS 190 230 420

    30 58+000 RHS 250 210 460

    31 59+000 RHS 230 260 490

    32 60+000 RHS 200 320 520

    33 61+000 RHS 170 230 400

    34 63+000 RHS 170 190 360

    35 64+000 RHS 170 200 370

    36 66+000 RHS 200 160 360

    37 67+000 RHS 250 220 470

    38 69+000 RHS 120 240 360

    39 70+000 RHS 200 180 380

    40 71+000 LHS 120 300 420

    41 72+000 LHS 70 270 290 630

    42 73+000 RHS 70 260 270 600

    43 74+000 RHS 160 200 360

    44 75+000 RHS 150 270 420

    45 76+000 RHS 90 290 380

    46 77+000 RHS 130 270 400

    47 78+000 RHS 120 220 340

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    16/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 15 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    Sr.

    No.Chainage

    (Km)Side

    Existing Crust Composition (mm)

    Bituminous WBM GSB Total

    48 82+000 RHS 110 270 38049 83+000 RHS 150 220 370

    50 84+000 RHS 130 190 320

    51 85+000 RHS 100 200 300

    52 86+000 RHS 120 310 430

    53 87+000 RHS 180 180 360

    54 88+000 RHS 120 290 410

    55 89+000 RHS 90 320 410

    56 90+000 LHS 120 210 330

    57 92+000 LHS 160 250 410

    58 93+000 RHS 150 230 380

    59 94+000 RHS 270 180 450

    60 95+000 RHS 250 200 450

    61 96+000 LHS 320 290 610

    62 97+000 RHS 290 250 540

    63 98+000 RHS 260 190 450

    64 104+000 LHS 200 350 550

    65 107+000 RHS 130 310 140 580

    66 108+000 RHS 130 220 350

    67 109+000 RHS 150 220 370

    68 110+000 RHS 190 320 510

    69 115+050 LHS 290 220 510

    70 116+000 LHS 260 220 480

    71 117+000 LHS 190 220 410

    From the above table, it can be inferred that the combined thickness of the bituminous layers

    varies from 70 to 320 mm and that of WBM layer varies from 100 to 350 mm. The thickness of

    the GSB layer varies from 140 to 390 mm. The total pavement crust thickness over the subgrade

    varies from 260 to 630 mm.

    3.3.2  Assessment of In-situ Density of Subgrade

    The field density at the existing subgrade level was conducted in the test pits by means of SandReplacement method. Relative compaction ranged from 85.67 to 102.12 percent. The results of

    this testing are summarized in Table 3.5  below.

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    17/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 16 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    Table 3.5 In-situ Density of Subgrade

    Chainage  SideFMC

    (%)

    FDD

    (gm/cc)

    O M C

    (%)

    MDD

    (gm/cc)% Compaction

    19+000 LHS 7.86 1.987 9.80 2.084 95.3520+000 RHS 8.98 1.883 10.00 1.985 94.85

    21+000 LHS 7.40 1.860 9.90 2.107 88.25

    22+000 RHS 8.72 1.947 9.60 2.110 92.26

    27+000 RHS 7.80 1.831 8.25 2.060 88.90

    28+000 RHS 6.96 1.915 9.70 2.022 94.71

    29+000 RHS 8.15 1.875 7.90 2.036 92.09

    30+000 RHS 7.35 1.935 8.25 2.060 93.93

    31+000 RHS 7.93 1.858 8.20 2.105 88.26

    32+000 RHS 6.19 1.817 7.50 2.014 90.22

    33+000 RHS 4.47 1.690 9.20 1.889 89.45

    34+000 LHS 2.56 1.703 9.60 1.900 89.64

    36+000 RHS 1.22 1.862 8.50 1.952 95.39

    37+000 RHS 2.24 1.813 8.80 2.025 89.52

    38+000 LHS 1.35 1.854 8.00 2.100 88.28

    39+000 RHS 4.12 1.810 8.40 2.055 88.08

    40+000 RHS 4.15 1.635 9.50 1.909 85.67

    41+000 RHS 4.65 1.870 7.80 2.035 91.88

    42+000 RHS 4.12 1.634 11.30 1.870 87.37

    45+000 RHS 7.46 2.042 7.80 2.068 98.75

    46+000 RHS 4.19 1.831 8.20 2.074 88.27

    47+000 RHS 3.01 1.862 8.00 2.060 90.37

    48+000 RHS 2.66 1.905 9.60 2.050 92.92

    49+000 RHS 2.36 1.840 8.00 2.070 88.90

    50+000 RHS 2.52 1.768 8.90 1.956 90.40

    54+000 RHS 5.57 2.041 7.00 2.090 97.66

    55+000 RHS 6.10 1.920 8.10 2.062 93.12

    56+000 RHS 3.21 1.912 9.80 2.100 91.05

    57+000 RHS 8.32 2.013 7.50 2.104 95.66

    58+000 RHS 6.89 1.797 7.90 2.075 86.62

    59+000 RHS 11.68 1.953 7.70 2.112 92.46

    60+000 RHS 9.64 1.860 7.30 2.110 88.16

    61+000 RHS 7.77 1.758 9.60 2.035 86.37

    63+000 RHS 9.72 1.876 5.85 2.067 90.77

    64+000 RHS 2.59 1.767 7.40 1.985 89.0366+000 RHS 1.68 1.731 7.50 1.990 86.97

    67+000 RHS 2.33 1.930 7.20 2.066 93.43

    69+000 RHS 2.19 1.857 7.30 2.109 88.06

    70+000 RHS 4.17 1.866 7.10 2.118 88.12

    71+000 LHS 3.33 2.001 6.00 2.123 94.23

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    18/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 17 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    Chainage  SideFMC

    (%)

    FDD

    (gm/cc)

    O M C

    (%)

    MDD

    (gm/cc)% Compaction

    72+000 LHS 2.24 1.812 7.55 2.105 86.08

    73+000 RHS 5.56 1.834 7.70 2.015 91.03

    74+000 RHS 5.36 1.820 7.60 2.080 87.52

    75+000 RHS 3.84 1.903 7.95 2.082 91.42

    76+000 RHS 6.23 1.863 7.70 2.068 90.09

    77+000 RHS 7.35 1.915 7.60 2.047 93.55

    78+000 RHS 6.92 1.832 7.50 2.100 87.25

    82+000 RHS 5.07 1.816 7.50 2.056 88.35

    83+000 RHS 5.29 1.925 8.00 2.086 92.28

    84+000 RHS 6.09 1.798 8.00 2.066 87.03

    85+000 RHS 5.37 2.061 8.80 2.018 102.12

    86+000 RHS 4.70 1.859 7.20 2.040 91.11

    87+000 RHS 7.11 1.975 7.70 2.025 97.55

    88+000 RHS 5.77 1.966 7.60 2.032 96.7589+000 RHS 4.72 1.971 7.20 2.042 96.54

    90+000 LHS 5.83 1.778 9.80 1.963 90.58

    92+000 LHS 5.62 1.910 7.60 2.058 92.80

    93+000 RHS 3.81 1.884 8.20 2.032 92.73

    94+000 RHS 9.20 1.928 8.00 2.080 92.70

    95+000 RHS 4.36 1.852 8.20 1.990 93.06

    96+000 LHS 3.79 1.999 7.90 2.057 97.16

    97+000 RHS 4.35 1.899 7.60 2.070 91.74

    98+000 RHS 8.21 1.812 7.80 2.027 89.38

    104+000 LHS 7.93 1.918 7.60 2.092 91.69

    107+000 RHS 4.13 1.819 8.00 2.080 87.44

    108+000 RHS 3.46 1.838 7.80 2.105 87.29

    109+000 RHS 6.16 1.958 7.60 2.089 93.74

    110+000 RHS 3.49 1.862 7.30 2.043 91.16

    115+050 LHS 6.45 1.866 7.40 2.090 89.29

    116+000 LHS 6.26 1.923 7.50 2.102 91.47

    117+000 LHS 7.63 1.846 7.00 2.030 90.95

    3.3.3  Assessment of Subgrade CBR Using Dynamic Cone Penetrometer

    The maximum and minimum values of in-situ DCP-CBR for the existing subgrade were foundto be 33.04 and 3.33 percent respectively. The test results are summarized in Table 3.6  below.

    The CBR was found to be 10% or greater at sixty one out of a total seventy one locations.

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    19/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 18 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    Table 3.6 In-Situ DCP-CBR

    Chainage Side

    Field CBR (%)

    Layer-1 Layer-2 Layer-3 Layer-4 WeightedAverage

    19+000 LHS 11.87 13.82 17.25 13.84

    20+000 RHS 6.74 12.76 13.31 11.06

    21+000 LHS 13.57 16.54 17.25 15.36

    22+000 RHS 14.88 15.82 25.89 16.60

    27+000 RHS 17.47 16.18 23.38 17.82

    28+000 RHS 5.63 16.76 38.61 13.78

    29+000 RHS 13.25 18.09 15.41

    30+000 RHS 4.83 6.55 5.49

    31+000 RHS 17.25 6.79 5.10 7.58

    32+000 RHS 12.99 14.66 14.66 13.7933+000 RHS 10.92 11.94 11.94 11.62

    34+000 LHS 42.63 25.31 20.59 26.32

    36+000 RHS 40.93 25.67 8.81 21.50

    37+000 RHS 14.36 13.07 19.55 14.24

    38+000 LHS 18.74 21.19 18.54 19.45

    39+000 RHS 4.71 3.52 4.36

    40+000 RHS 4.83 5.15 5.05

    41+000 RHS 5.40 6.67 6.01

    42+000 RHS 20.92 18.74 16.88 18.25

    45+000 RHS 23.47 27.09 16.53 23.10

    46+000 RHS 9.23 28.07 22.58 18.3447+000 RHS 21.24 24.42 24.02 23.38

    48+000 RHS 38.47 22.46 19.64 23.62

    49+000 RHS 25.54 26.24 22.50 25.11

    50+000 RHS 38.61 23.74 15.85 23.58

    54+000 RHS 25.49 25.80 14.66 23.00

    55+000 RHS 18.39 18.21 18.77 18.55

    56+000 RHS 13.63 14.02 16.43 15.04

    57+000 RHS 17.77 16.12 19.26 17.36

    58+000 RHS 9.28 11.24 9.58

    59+000 RHS 14.13 26.49 15.19

    60+000 RHS 7.56 7.54 7.55

    61+000 RHS 4.37 7.32 5.90

    63+000 RHS 24.54 18.56 17.88 19.51

    64+000 RHS 10.62 21.10 26.75 17.89

    66+000 RHS 28.88 30.83 13.63 24.79

    67+000 RHS 8.29 27.61 22.91 17.80

    69+000 RHS 14.44 23.95 24.63 20.92

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    20/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 19 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    Chainage Side

    Field CBR (%)

    Layer-1 Layer-2 Layer-3 Layer-4Weighted

    Average

    70+000 RHS 15.94 16.41 17.25 16.45

    71+000 LHS 7.94 63.52 97.58 33.04

    72+000 LHS 19.56 29.71 32.25 27.28

    73+000 RHS 7.56 30.25 27.53 19.52

    74+000 RHS 12.90 24.63 37.07 21.84

    75+000 RHS 21.56 19.36 20.52 20.59

    76+000 RHS 28.88 27.44 16.59 24.72

    77+000 RHS 17.72 14.95 17.45 16.34

    78+000 RHS 12.09 25.36 25.15 19.37

    82+000 RHS 28.76 23.50 10.62 19.82

    83+000 RHS 17.25 21.61 20.39 20.02

    84+000 RHS 13.17 13.89 15.31 13.99

    85+000 RHS 29.61 17.06 6.01 14.63

    86+000 RHS 25.31 29.39 33.16 28.36

    87+000 RHS 14.66 26.26 24.63 21.75

    88+000 RHS 18.63 19.84 17.25 18.78

    89+000 RHS 35.90 12.62 9.77 12.80

    90+000 LHS 10.62 23.76 32.91 19.25

    92+000 LHS 17.25 10.50 8.29 10.95

    93+000 RHS 30.50 27.16 20.92 26.49 25.17

    94+000 RHS 30.50 16.44 14.61 18.18

    95+000 RHS 17.25 18.67 12.61 15.77

    96+000 LHS 12.73 17.25 19.19 16.9797+000 RHS 3.55 3.20 3.33

    98+000 RHS 9.37 13.44 9.88

    104+000 LHS 6.08 28.74 45.65 21.21

    107+000 RHS 35.28 22.10 24.13 27.96 24.73

    108+000 RHS 18.12 16.67 17.99 17.62

    109+000 RHS 11.24 14.13 23.79 14.30

    110+000 RHS 41.76 16.31 19.17

    115+050 LHS 26.49 8.75 9.94 10.63

    116+000 LHS 35.90 13.77 10.19 13.59

    117+000 LHS 14.02 30.81 40.13 23.68

    3.3.4  Laboratory Testing Results

    The laboratory testing results include CBR, sieve analysis, Atterberg’s limits, and moisture-

    density relationships for the existing subgrade. From the CBR testing program, it was seen that

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    21/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 20 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    the CBR values ranged from 6.5 to 27 percent. The CBR was 10% or greater at sixty one out of a

    total seventy one locations. Based on Atterberg’s limit test, it was seen that most of the soil

    samples were non-plastic (NP) soils. The plasticity index of the soil samples ranged from 7 to 22.

    The results are indicated in Appendix 3.

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    22/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 21 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    4.0 Traffic Study & Analysis

    The traffic study for this project is presented in the traffic report “Traffic Surveys & Analysis

    Report” dated 20-01-2012. The pavement design parameters such as growth rates, vehicle

    damage factor (VDF) values, and the annual average daily traffic (AADT) values are presented

    and analyzed in that report. The traffic volume calculations (MSA) which have been calculated

    in that report are highlighted hereunder.

    In accordance with IRC guidelines, the pavement of the main highway was designed for the

    cumulative number of standard axles of 8.16 tones over the design life. Base year traffic, axle

    load distribution, and vehicle damage factor for design shall be determined on the basis of survey

    and investigation to be carried out by the concessionaire.

    The design traffic is considered in terms of the cumulative number of standard axles (in the lane

    carrying maximum traffic) to be carried during the design life of the road. It is referred to as the

    "cumulative traffic" and measured in million standard axle, and was computed using the

    following equation:

    365 [(1 ) 1]nr  N A D F 

     

    Where,

     N = Cumulative number of standard axles to be catered for in the design in terms of Million Standard

    Axles (msa).A = Initial traffic in the year of completion of construction in terms of the number of Commercial

    vehicles per day (CVPD). It is computed by dividing the vehicle category-wise AADT by the

    directional distribution factor, which is equal to 0.5 for this project corridor.

    D = Lane distribution factor. According to IRC: 37- 2001 and its draft revision of 2011, the lane

    distribution factor for four-laning project is 0.75.

    F = Vehicle damage factor (VDF).

    n = Design life in years.

    r = Annual growth rate of commercial vehicles

    For the purpose of this Traffic study, the base year is 2011 and the concession period is twenty

    years excluding the construction period and it will end on 2033. Detailed computation is

     presented in the traffic report.

    A detailed analysis of the vehicular movement on the project road indicated that the traffic

     pattern was significantly different along the length of the project, and this resulted in designating

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    23/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 22 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    three (3) homogenous sections. The design chainage-wise limits of the homogenous sections are

    as follows:

    1.  Homogenous Section 1: 0+000 km to 21+300 km.

    2.  Homogenous Section 2: 21+300 km to 71+150 km.

    3.  Homogenous Section 3: 71+150 km to 113+143 km.

    It was also concluded that the traffic pattern in the Beawar to Pali direction (LHS carriageway) is

    significantly different from that in the Pali to Beawar direction (RHS carriageway). As result of

    this findings, the cumulative traffic on the LHS as well as RHS carriageway consisted of three

    different values.

    Summary of the results of cumulative traffic computations is presented in Table 4.1  below.

    Table 4.1 Homogeneous Section-wise Cumulative Traffic

    Homogeneous

    Section

    Existing

    Chainage, km

    Design

    Chainage,

    km

    10 Year MSA

    (2023)

    15 Year MSA

    (2028)

    20 Year MSA

    (2033)

    Pali to

    Beawar

    Beawar

    to Pali

    Pali to

    Beawar

    Beawar

    to Pali

    Pali to

    Beawar

    Beawar

    to Pali

    10+000 to

    22+700

    0+000 to

    21+30081 62 138 108 214 168

    222+700 to

    72+550

    21+300 to

    71+15067 49 113 86 174 133

    3

    72+550 to

    115+000

    71+150 to

    113+143 84 63 145 110 224 170

    Actual cumulative traffic values (in msa) have been rounded up or down, as applicable, to the nearest whole number. For example: A

    value of 61.90 msa has been rounded up to 62 msa, since 62 is the whole number that is nearest to 61.90. A value of 63.19 msa has been

    rounded down to 63 msa, since 63 is the whole number that is nearest to 63.19.

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    24/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 23 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    5.0 Impact of Concession Agreement on Pavement Design

    This project will be implemented as a DBFOT project to the Concessionaire for a concession

     period of 23 years. The operation period is 20 years. Hence, the service life of the project road is

    taken as twenty years after the project road is opened to traffic. The road is expected to be

    opened to traffic in 2014.

    In order to achieve economy in construction and to avail the benefits of any future technological

    and material improvements, it was decided to adopt the stage construction technique.

    Accordingly, the pavement designs in this report are completed assuming a design period of 10

    years for the bituminous layers and 20 years (operation period) for the granular layers. This

    complies with the provisions of IRC:SP:84 –  2009 (Schedule D).

    Flexible pavement has been proposed for the entire project road. The existing project road is of

    two lane configurations. The strengthening of the existing carriageway with flexible overlays

    will be in general accordance with IRC 81-1997, and the widening of the flexible pavement will

     be in general accordance with IRC 37-2001. The pavement designs were completed using the

    mechanistic method of pavement design.

    The crust thickness and composition of pavement under paved shoulder and the bus bays are

    kept identical to that of main carriageway.

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    25/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 24 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    6.0 Overlay Pavement Design (Flexible Pavement)

    The pavement designs for the overlay sections of this project have been conducted in general

    accordance with the IRC: 81-1997 “Guidelines for Strengthening of Flexible Road Pavements

    Using Benkelman Beam Deflection Technique”.

    The elastic deformation (deflection) of the pavement was measured at various locations along the

     project road. The sampling frequency was 50 m. The elastic deflection generated due to the

    application of load on the pavement is a function of various pavement crust and subgrade soil

    material properties. The elastic deflection was expressed in terms of “characteristic deflection”.

    From the characteristic deflection values so generated, the pavement was subdivided into various

    stretches of statistically similar characteristic deflections. These stretches were designated as the

     pavement homogenous sections. This analysis is outlined in the paragraphs below.

    6.1 

    Calculation of Characteristic Deflection

    The deflection data collected in the field survey was processed for calculating the characteristic

    deflections. This was the first stage of calculation of characteristic deflections. In this stage, the

     processed deflection values from the raw data for each kilometer length were averaged, and the

    standard deviation of the data set was calculated. Twice the value of the standard deviation was

    then added to the average in order to get the kilometer-wise characteristic deflection using the

    statistical approach as identified in IRC: 81, Section 6. The raw deflection values that were a part

    of approaches of VUP, PUP, flyovers, and reconstruction sections were not used in the

    calculation of overlay thickness.

    6.2 Pavement Overlay Thicknesses

    Based on the analysis, an overlay strategy that is outlined in Appendix 4 recommended. In

    general, for the wearing course, bituminous concrete (BC) overlay of 40 mm, composed of

     polymer modified binder (PMB) of VG30 grade is proposed throughout the length of the project.

    The binder course recommended for the overlay is dense bituminous macadam (DBM).

    A brief summary of overlay design is given in Table 6.1. 

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    26/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 25 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    Table 6.1 Overlay Design

    From to From to Ch. Def.Beawar -

    Pali

    Pali -

    BeawarBC

    DBM

    (Provided)BC

    DBM

    (Provided)

    0.000 7.790 0.000 6.110

    7.790 11.068 6.110 9.420

    11.068 16.454 9.420 15.200

    16.454 18.243 15.200 16.800

    18.243 18.780 16.800 17.370 570.000 0.394 62 81 50 --- -- ---

    18.780 19.600 17.370 18.170

    19.600 20.970 18.170 19.520 1350.000 0.516 62 81 -- --- 50 ---

    20.970 21.700 19.520 20.170

    21.700 22.749 20.170 21.300 1130.000 0.708 62 81 -- --- 50 ---

    22.749 26.182 21.300 24.750

    26.182 26.460 24.750 25.030 280.000 0.605 49 67 -- --- 50 ---

    26.460 27.210 25.030 25.780

    27.210 32.229 25.780 29.700 3920.000 0.475 49 67 -- --- 50 ---

    32.229 33.834 29.700 32.400

    33.834 34.034 32.400 32.600 200.000 0.914 49 67 40 50 -- ---

    34.034 35.979 32.600 34.400

    35.979   37.679   34.400 36.100 1700.000 1.237 49 67 -- --- 40 65

    37.679 38.620 36.100 37.000

    38.620 41.327 37.000 39.750 2750.000 1.494 49 67 -- --- 40 95

    41.327 44.302 39.750 42.900

    44.302 50.494 42.900 49.150 6250.000 1.103 49 67 -- --- 40 50

    50.494 53.145 49.150 51.700

    51.700 54.050 -- --- 50 ---

    54.050 54.950 50 --- -- ---

    54.950 58.200 -- --- 50 ---

    59.620 62.020 58.200 60.600

    62.020 62.709 60.600 61.300

    62.709 64.327 61.300 62.925 1625.000 0.580 49 67 -- --- 50 ---

    64.327 65.337 62.925 63.930

    65.337 67.791 63.930 66.440 2510.000 0.642 49 67 -- --- 50 ---

    67.791 68.616 66.440 67.140

    68.616 70.090 67.140 68.680 1540.000 0.900 49 67 -- --- 40 50

    70.090 71.000 68.680 69.590

    71.000 72.000 69.590 70.800 1210.000 1.191 49 67 40 50 -- ---

    72.000 72.980 70.800 71.580

    72.980 79.270 71.580 77.900 6320.000 1.368 63 84 -- --- 40 90

    79.270 80.510 77.900 79.150

    79.150 88.500 -- --- 40 70

    88.500 89.650 40 60 -- ---

    89.650 91.400 40 60 -- ---

    89.650 91.400 -- - 40 70

    92.680 94.590 91.400 93.330

    93.330 94.200 -- --- 40 100

    94.200 94.700 40 90 -- ---

    94.700 96.740 -- --- 40 100

    98.050 102.793 96.740 101.660

    102.793 104.800 101.660 103.540 1880.000 1.205 63 84 40 60 -- ---

    104.800 115.000 103.540 113.140

    Overlay Pavement Crust Thickness

    Existing Chainage,

    km

    Design Chainage,

    km

    Length ofOverlay (m)

    Characteristic

    Deflections in

    Pavement

    Traffic (MSA)

    Overlay Pavement Crust Thickness , mm

    RECONSTRUCTION

    Beawar - Pali Pali - Beawar

    BEAWAR BYPASS

    REALIGNMENT

    SENDRA BYPASS

    REALIGNMENT

    RECONSTRUCTION

    RECONSTRUCTION

    BARR BYPASS

    53.145 59.620 6500.000

    VUP

    RECONSTRUCTION

    REALIGNMENT

    RECONSTRUCTION

    PIPLIKALAN BYPASS

    CHANDAWAL BYPASS

    0.711 49 67

    RECONSTRUCTION

    PUP

    RECONSTRUCTION

    RECONSTRUCTION

    VUP

    RECONSTRUCTION

    80.510 92.680 12250.000 1.216 63 84

    RECONSTRUCTION

    94.590 98.050 3410.000 1.453 63 84

    RECONSTRUCTION

    RECONSTRUCTION

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    27/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 26 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    7.0 Flexible Pavement Design for Main Carriageway Widening, Reconstruction Sections,

    and Approaches of Grade Separators

    This section describes the philosophy and methods used to design the pavement crust for all

    those sections of the pavement that will carry full strength cumulative traffic through their design

    life. The sections that fall under this category are the widening portion of the main carriageway,

    full depth reconstruction portions, and approaches of all grade separators such as flyover, VUP,

    and PUP.

    7.1 Discussion of Design CBR

    The following discussion is based on a review of the CBR values of the subgrade as well as the

    results of the tests conducted on borrow area soils. The design CBR was chosen on the basis of a

    review of the test results and past experience on similar projects and conditions.

    From the laboratory CBR testing program and results, it was seen that the CBR values of the

    existing subgrade ranged from 6.5 to 27 percent. Atterberg’s limit test  results on soil samples

    indicated that most of the subgrade soils were non-plastic (NP). The plasticity index of the soil

    samples ranged from 7 to 22.

    From the results of the CBR testing program conducted for borrow areas, it was seen that from

    the start of the project (existing chainage: 0+000 km) up to chainage 40+000 km, the CBR values

    ranged from 10 to 21 percent. Based on this evaluation, a design CBR value of 10 percent was

    adopted for this section of the project.

    Testing in borrow areas from existing chainage 40+000 km up to the end of the project (existing

    chainage: 115+000 km) indicated that the CBR values ranged from 14 to 36 percent. Based on

    this evaluation, a design CBR value of 12 percent was adopted for this section of the project.

    The design CBR values chosen for various sections of the road for this Project are tabulated

     below in Table 7.1. 

    Table 7.1 Design CBR Values for Pavement Design

    Homogeneous

    SectionExisting Chainage, km Design Chainage, km Design CBR, %

    1 0+000 to 40+000 0+000 to 38+420 10

    2 40+000 to 115+000 38+420 to 113+143 12

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    28/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 27 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    7.2 Pavement Layer Thickness Design

    The pavement was designed based on traffic parameters as outlined in Section 1.4.7.1. Pavement

    sections recommended were based on a design period of 10 years for the bituminous layers.

    However, in accordance with IRC: SP-84, “Manual of Specifications and Standards for Four

    Laning of Highways through Public Private Partnership”, and the Concession Agreement, the

    granular layers (base and subbase) were analyzed based on design life corresponding to the full

    concession period (20 years)

    The flexible pavement design was conducted in accordance with the guidelines stipulated in the

    IRC: 37-2001. In general, the traffic loading in terms of million standard axles (MSA) was

    determined using the data collected from the traffic surveys. The soil CBR was determined using

    the data collected from soil investigations. Based on the CBR value, typical values for moduli of

    various pavement layers were determined.

    7.2.1  Methodology for Pavement Sections with Design CBR 10%

    For the section of the project from design chainage 0+000 km to 38+420 km (existing chainage

    0+000 to 40+000), the design CBR value adopted was 10 percent. Pavement design for this

    section was accomplished using the recommended values for various pavement layers in IRC:

    37-2001, Plate 2.

    7.2.2  Methodology for Pavement Sections with Design CBR 12%

    For the section of the project from design chainage 38+420 km to 113+143 km (existing

    chainage 40+000 to 115+000), the design CBR value adopted was 12 percent. Pavement design

     procedures for this section were accomplished using the analytical approach of flexible pavement

    design, as outlined in IRC: 37-2001. Guidance for implementing the analytical approach is given

    in Section 4.3 "Pavement Design Catalogue", Page 42, sub-section 4.3.2, and the required

     parameters and equations are given in pages from 51 through 56 in the same IRC: 37-2001.

    FPAVE software was used for this evaluation.

    The allowable strains in pavement layers were calculated in terms of two primary pavement

    distress criteria: fatigue cracking and rutting. The actual strains arising in the pavement layers

    due to traffic loading were then calculated, assuming suitable thickness values for different

     pavement layers. The assumed pavement crust was deemed to be safe for the design loads if the

    actual strains were less that the allowable strains.

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    29/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 28 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    7.2.2.1 Allowable Strains in the Pavement Structure

    The allowable strains in the pavement layers were calculated primarily based on two pavement

    distress criteria: fatigue cracking and rutting.

    The distress of fatigue cracking is more critical in the bituminous layer in the pavement crust.

    This type of cracking is usually initiated at the bottom of the bituminous layer after repeated

    application of the axle loads. This initiation means that the actual horizontal tensile strain at the

     bottom of the bituminous layer has exceeded a certain limit, which is the allowable strain. The

    allowable tensile strains were calculated using the fatigue criteria equation as outlined in the

    Appendix I of IRC: 37-2001. The equation is as follows.

     

    Where;

     

     

     

    The distress of rutting is more critical in the subgrade under the pavement crust. This type of

    cracking is usually initiated at the top of the subgrade layer after repeated application of the axle

    loads. This initiation means that the actual vertical compressive strain at the top of the subgrade

    layer has exceeded a certain limit, which is the allowable strain. The allowable compressive

    strains were calculated using the rutting criteria equation as outlined in the Appendix I of IRC:

    37-2001. The equation is as follows.

     

    Where;

     

     

    7.2.2.2 Actual Strains in the Pavement Structure

    The actual tensile strains were calculated using the various pavement design parameters as inputs

    in the FPAVE program. The actual strains are computed using various trial pavement structural

    layer combinations.

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    30/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 29 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    The design and material parameters used for this project were in general accordance with the

     postulates of the IRC: 37-2001, "Guidelines for the Design of Flexible Pavements", (Second

    Revision).

    The type of binder (bitumen) used was polymer modified binder (PMB), and the base binder is

    of VG 30 grade. PMB is proven to enhance the performance of the pavement in terms of its load

    carrying capacity under heavy traffic loads. The pavement temperature was taken as 35°C. In

    accordance with IRC: 37-2001, the resilient modulus of the BC and DBM layer was chosen as

    1700 MPa, which corresponds to 60/70 grade bitumen. The statistical level of reliability used in

    the pavement design was 80 percent.

    The various layer moduli and Poisson's ratios were calculated in accordance with the guidance

    and equations given in IRC: 37-2001.

    The tyre pressure used in the analysis was 0.56 MPa. Standard axle used was dual type, having a

    mass of 8160 kg. This resulted in a single tyre load of 20,500 N.

    7.3 Validation of Analytical Approach of Pavement Design Using Standard IRC Sections

    Before generating pavement sections for 12% CBR using the FPAVE software, an exercise was

    conducted in order to validate the usage of FPAVE with respect to the standard pavement design

    sections given in IRC: 37-2001. In this exercise, three pavement sections given in the code for

    CBR 10% and cumulative traffic of 50, 100, and 150 msa were chosen. FPAVE software was

    run in order to calculate the actual tensile strains at the bottom of bituminous layer and actual

    compressive strains at the top of the subgrade layer. It was found that the actual strains were well

    within the allowable limits. It was also found that the pavement section thicknesses given in the

    IRC in each case satisfied the requirement of optimum pavement crust.

    7.4 Pavement Layer Thicknesses Recommendation

    Table 7.2  below indicates the pavement thickness strategy for new pavement and reconstruction

    sections of the project. The pavement design analysis parameters are indicated in Appendix 5.

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    31/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 30 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    Table 7.2 Recommendations for New Pavement Sections

    Description

    of Pavement

    Section

    Direction

    Existing

    Chainage

    Limits,km

    Design

    Chainage

    Limits,km

    CBR,

    %

    Cumulative

    Traffic, msa

    Layer Thickness, mm

    BC DBM WMM GSB

    Homogenous

    Section 1

    Beawar to

    Pali0+000 to

    22+700

    0+000 to

    21+30010 62 40 120 250 200

    Homogenous

    Section 1

    Pali to

    Beawar0+000 to

    22+700

    0+000 to

    21+30010 81 40 130 250 200

    Homogenous

    Section 2

    Beawar to

    Pali22+700 to

    40+000

    21+300 to

    38+42010 49 40 110 250 200

    Homogenous

    Section 2

    Pali to

    Beawar22+700 to

    40+000

    21+300 to

    38+42010 67 40 125 250 200

    Homogenous

    Section 2

    Beawar to

    Pali40+000 to

    72+550

    38+420 to

    71+150 12 49 40 95 250 200

    Homogenous

    Section 2

    Pali to

    Beawar40+000 to

    72+550

    38+420 to

    71+15012 67 40 110 250 200

    Homogeneous

    Section 3

    Beawar to

    Pali72+550 to

    115+000

    71+150 to

    113+14312 63 40 110 250 200

    Homogeneous

    Section 3

    Pali to

    Beawar72+550 to

    115+000

    71+150 to

    113+14312 84 40 120 250 200

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    32/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 31 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    8.0 Pavement Design (Flexible Pavement) for Service Road, and Slip Road of Flyover and

    Underpass

    This section describes the philosophy and methods used to design the pavement crust for all

    those sections of the pavement that will carry nominal traffic through their design life. The

    sections that fall under this category are the service roads, and slip roads of flyovers and

    underpasses.

    In accordance with the IRC: SP 84-2009, the roads that fall under this category were designed

    for a cumulative traffic of 5 msa.

    For the section of the project from design chainage 0+000 km to 38+420 km (existing chainage

    0+000 to 40+000), the intended field CBR value is 10 percent. Pavement design for this section

    was accomplished using the recommended values for various pavement layers in IRC: 37-2001,

    Plate 1.

    For the section of the project from design chainage 38+420 km to 113+143 km (existing

    chainage 40+000 to 115+000), the intended CBR value is 12 percent. The design Plates in IRC:

    37-2001 do not contain recommendations for CBR 12 percent. Since the layer thicknesses of

    SDBC, DBM, WMM and GSB that are recommended for the combination of cumulative traffic

    of 5 msa and CBR 10 percent are minimum that can be constructed practically, the same

     pavement design was adopted for the section with CBR 12 percent.

    Table 8.1  below summarizes the pavement design for service roads.

    Table 8.1 Pavement Crust for Service Road

    Description

    of Pavement

    Section

    Direction

    Existing

    Chainage

    Limits,

    km

    Design

    Chainage

    Limits,

    km

    CBR,

    %

    Cumulative

    Traffic, msa

    Layer Thickness, mm

    SDBC DBM WMM GSB

    Sections with

    CBR 10%

    Both

    directions0+000 to

    40+000

    0+000 to

    38+42010 5 25 50 250 150

    Sections with

    CBR 12%

    Both

    directions40+000 to

    115+000

    38+520 to

    113+14312 5 25 50 250 150

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    33/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 32 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    9.0 Pavement Design (Rigid Pavement) for Toll Plaza

    This section describes the philosophy and methods used to design the pavement crust for all

    those sections of the pavement that will form a part of the toll plaza.

    Rigid pavement design is worked out as per the method outlined in IRC 58-2002 for toll plaza

    location. The design of rigid pavement is worked out for 30 years of design period.

    The parameters used for the design of rigid pavement method are as follows:

    9.1 Methodology

    Rigid Pavement Design is worked out as per recommended in IRC 58-2002, the parameters used

    for the design of rigid pavement method are as follows:

    Concrete

    Compressive Strength, f ck = 450 kg/cm2 

    Flexural modulus, f cr = 46.96 kg/cm2 

    Elastic modulus, Ec  = 3 x 105kg/cm

    Coefficient of thermal expansion, α  =10 x 10-6

     per0C

    Poisson’s ratio, µ = 0.15

    Other

    Modulus of subgrade Reaction = 5.500 kg/cm2/cm

    (Corresponding to Sub-grade CBR of 10% )

    Load safety factor = 1.2

    Tyre pressure = 8 kg/cm2

    Since the soaked CBR value of the sub-grade borrow material is taken as 10%, it has a

    ‘ksg’ value of 5.500 kg/cm2/cm which is less than the suggested minimum, of 6.0 kg/cm

    3,

    required for placing the slab directly over sub-grade. As per the Table-4 of IRC 58-2002

    the modified k-value of DLC sub- bases ‘ksb’ corresponding to 150 mm thickness is

    41.700 kg/cm3.

    The IRC Guidelines suggest 25% of traffic in one direction as sufficient for design

    against fatigue failure.

    Design Traffic

    The Design traffic for 30 years is worked out  based on the Continuous vehicle count

    survey data and Axle Load Survey data as illustrated in the 

    Table 9.1  below

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    34/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 33 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    Table 9.1 Design Traffic

    At Ch. 34+000 At Ch. 93+000

    Design life 30 years 30 years

    Cumulative repetition in 30 years 125670523 155954465

    Design Traffic (25% of total repetitions of

    commercial vehicle)31417631 38988616

    Average Number of Axles per Vehicle 2.05 2.25

     No. of Axles for Design Traffic 64406144 87724386

    The rigid pavement design is illustrated in Table 9.2 along with their joints detail.

    Rigid Pavement comprising of 290 mm PQC as per IRC 58-2002, resting over 150mm DLC

    over 150mm thick granular sub base. The design is found to be safe in fatigue stress, temperature

    stress and corner stress.

    Summary of Rigid pavement design is illustrated in Table 9.3. 

    Table 9.2 Design Calculations of Rigid Pavement

    Location of Toll Plaza At Ch. 34+000 At Ch. 93+000

    28 days Compressive Strength of Concrete fck 450 kg/cm2 450 kg/cm2

    Flexural Strength of Concrete Fcr 46.96 kg/cm2 46.96 kg/cm2

    Modulus of Elasticity of Concrete E 300000 kg/cm2 300000 kg/cm2

    Poisson’s Ratio of Concrete  µ 0.15 0.15

    Coefficient of Thermal Expansion of

    Concrete

    a 10.0E-6 / oC 10.0E-6 / oC

    Sub-grade CBR (%) 10.000 12.000

    K Value of Sub grade Ksg 5.500 Kg/cm3 5.780 Kg/cm3

    Dry lean concrete as Sub-base Type

    Thickness of Dry Lean Concrete >= 10

    cm

    15 cm 15 cm

    K Value of Sub-base Ksb 41.700 Kg/cm3 41.700 Kg/cm3

    Assume Trail Slab Thickness h 29 cm 29 cm

    Spacing of Contraction Joints L 4.5 m 4.5 m

    Length of Slab (Lane Width) W 3.5 m 3.5 m

    Radius of Relative Stiffness l 62.19 cm 62.19 cm

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    35/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 34 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    Design of Dowel Bars 

    Percentage of load transfer 40 % 40 %

    Joint width 2 cm 2 cm

    Diameter of Dowel bar d 3.2 cm 3.2 cm

    Design Wheel Load P 8000 kg 8000 kg

    Assumed spacing between the dowel bars 22 cm 22 cm

    Assumed length of dowel bars 50 cm 50 cm

    Modulus of elasticity of Steel 2000000 Kg/cm2  2000000 Kg/cm2 

    Modulus of concrete / dowel interaction K 41500.000 kg /cm3  41500.000 kg /cm3 

    Permissible bearing stress in concrete Fb 328.82 Kg/cm2  328.82 Kg/cm2 

     No. of dowel bars required for load

    transfer

    4  No.s 4  No.s

    Load transferred by dowel system Pt * 1.877 1.877

    Load carried by outer dowel bar Pt 1704.42 kg 1704.42 kg

    Moment of Inertia of Dowel bar MI 5.147 cm4 5.147 cm4

    Relative stiffness of Dowel bar β  0.238 0.238

    Bearing stress in dowel bar 314.35 Kg/cm2  314.35 Kg/cm2 

    SAFE SAFE

    Design of Tie Bars (With Plain Bars)

    Coefficient of friction f 1.5 1.5

    Diameter of Tie bar (Range : 12 to 16 mm) 12 mm 12 mm

    Density of Concrete 2400 kg/cm3  2400 kg/cm3 

    Select type of tie bar Plain Plain

    Allowable tensile stress in tie bars 1250 Kg/cm2  1250 Kg/cm2 

    Allowable bond stress for tie bars 17.5 Kg/cm2  17.5 Kg/cm2 

    Area of steel bar per unit length 2.923 cm2 2.923 cm2

    Cross sectional area of Tie bar 1.131 cm2 1.131 cm2

    Perimeter of Tie bar 3.770 cm 3.770 cm

    Spacing of Tie bars 38.69 cm 38.69 cm

    Take Spacing of Tie bars 38 cm 38 cm

    Length of Tie bar 42.857 cm 42.857 cm

    Adopt Length of Tie bar (increase 10 cm

    for loss of bond due to bending + 5 cm for

    improper placement)

    58 cm 58 cm

    Design of Tie Bars (With Deformed Bars) 

    Coefficient of friction f 1.5 1.5

    Diameter of Tie bar (Range : 12 to 16 mm) 12 mm 12 mm

    Density of Concrete 2400 kg/cm 2400 kg/cm

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    36/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 35 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    Select type of tie bar Deformed Deformed

    Allowable tensile stress in tie bars 2000 Kg/cm 2000 Kg/cm

    Allowable bond stress for tie bars 24.6 Kg/cm2  24.6 Kg/cm2 

    Area of steel bar per unit length 1.827 cm2  1.827 cm2 

    Cross sectional area of Tie bar 1.131 cm 1.131 cm

    Perimeter of Tie bar 3.770 cm 3.770 cm

    Spacing of Tie bars 61.9 cm 61.9 cm

    Take Spacing of Tie bars 61 cm 61 cm

    Length of Tie bar 48.78 cm 48.78 cm

    Adopt Length of Tie bar (increase 10 cm

    for loss of bond due to bending + 5 cm for

    improper placement)

    64 cm 64 cm

    Table 9.3 Rigid Pavement Design - Summary

    S.No Design ParametersAt Ch.

    34+000

    At Ch.

    93+000

    1 Pavement Quality Concrete (PQC) (mm) 290 290

    2 Dry Lean Concrete (DLC) (mm) 150 150

    3 Granular Sub-base (GSB) (mm) 150 150

    4 Subgrade (mm) 500 500

    5 Characteristic Strength of Concrete (kg/cm2) 450 450

    6 Slab length (m) 4.5 4.5

    7 Slab width (m) 3.5 3.5

    8 Joint width (mm) 20 20

    9 Dowel bar diameter (mm) 32 32

    10 Spacing of Dowel bar (mm) 22 22

    11 Length of Dowel bar(mm) 500 500

    12 Tie bar Diameter (mm) 12 12

    13 Spacing of Tie bar (mm) (Plain/Deformed) 380/610 380/610

    14 Length of Tie bar (mm) (Plain/Deformed) 580/640 580/640

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    37/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T SHEET 36 of 36

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    10.0  Conclusion

    The findings and recommendations of this pavement design report are summarized as follows:

    1.  Four-laning of Beawar to Pali section of NH-14 in the State of Rajasthan starts from

    design chainage 0+000 km in Beawar town up to chainage 113+143 km in Pali town.

    2.  Project corridor is divided into the following three (3) homogeneous sections, the limits

    of which are expressed hereunder in terms of design chainages:

    a.  Homogeneous Section 1: km 0+000 to km 21+300

     b.  Homogeneous Section 2: km 21+300 to km 71+150

    c.  Homogeneous Section 3: km 71+150 to km 113+143

    3.  Overlay Design: The recommended overlay design is given in Table 6.1 Appendix 4.

    4.   New Pavement Design:

    a.  A CBR values of 10 percent is used from design chainage 0+000 km up to

    38+420 km. From chainage 38+420 km up to chainage 113+143 km, a design

    CBR value of 12 percent is used.

     b.  The recommended pavement design is indicated in Error! Reference source not

    found., and Appendix 5.

    5.  Service Road Design: The recommended service road design is given in Table 8.1. 

    6.  Rigid Pavement Design: The recommended rigid pavement design is given in Table 9.3. 

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    38/119

      L&T Construction Document No.

    Infrastructure O11238-C-RP-RD-PD-0001

    EDRC&T

    Beawar-Pali-Pindwara Road Project (BPPRP)

    (Beawar to Pali Section)

    APPENDIX 1

    Pavement Condition Survey Data

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    39/119

    Project: NH 14 (Beawar ‐ Pali) Chainage:

    Name of  Investigator: Anudeep, Ranjith Kumar & Satish Kumar Date:

    From To Cracks Pot holes Ravelling Bleeding Patching

    9+600 9+700 G F

    9+700 9+800 G F 6838 (SC)

    9+800 9+900 2 G F 6839

    9+900 10+000 G F 6840-41

    10+000 10+100 2 G F 6842

    10+100 10+200 G F 6843

    10+200 10+300 3 G F

    10+300 10+400 G F 6844 (SC)

    10+400 10+500 G F

    10+500 10+600 8 2 G F 6845-46 ,7295

    18+000 18+100 2 G F 730518+100 18+200 G F 7306

    18+200 18+300 G F 7307

    18+300 18+400 5 G F 6866

    18+400 18+500 G F 7308

    18+500 18+600 G F 6867

    Remarks ShoulderCondition

    Chainage Rutting(mm)

    Distressess in (%) PavementCondition

    PAVEMENT CONDITION SURVEY

    18+600 18+700 G F 6868-69

    18+700 18+800 G F 6870

    18+800 18+900 G F 6871

    18+900 19+000 G F 6872

    19+000 19+100 G F 6873-74

    19+100 19+200 15 F F 7309

    19+200 19+300 10 20 F F 6875 ,7310

    19+300 19+400 20 40 F F 6876 ,7311 , 731219+400 19+500 10 20 F F 6878 , 7313

    19+500 19+600 20 F F 6879 , 7314

    19+600 19+700 10 F F 6880 , 7315

    19+700 19+800 5 G F 6881

    19+800 19+900 5 25 F F 6882 ,7316-17

    19+900 20+000 G F 6883-84

    Page 1 of  20

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    40/119

    From To Cracks Pot holes Ravelling Bleeding PatchingRemarks

    Shoulder

    Condition

    Chainage Rutting

    (mm)

    Distressess in (%) Pavement

    Condition

    20+000 20+100 5 3 5 3 F F 690-691 , 7318

    20+100 20+200 3 15 F F 692-93 ,7319

    20+200 20+300 5 5 10 10 F F 694-95 , 7320-21

    20+300 20+400 15 5 F F 696 , 7322

    20+400 20+500 2 G F 697

    20+500 20+600 2 G F 698

    20+600 20+700 3 G F 699 , 7323

    20+700 20+800 G F 700

    20+800 20+900 G F 701

    20+900 21+000 10 F F 702-03 , 7324

    21+000 21+100 15 10 F F 704-05 ,7325

    21+100 21+200 15 10 3 F F 706

    21+200 21+300 5 5 F F 707

    21+300 21+400 10 3 3 F F 708-10

    21+400 21+500 G F 7326

    21+500 21+600 G F 711 , 7327

    21+600 21+700 50 10 5 20 VP F 712-13 , 7328-29

    21+700 21+800 2 G F 716 , 7330

    21+800 21+900 15 G F 717-18 , 7331

    21+900 22+000 2 10 G F 719

    22+000 22+100 15 3 G F 7332

    22+100 22+200 G F 6721

    22+300 22+400 2 G F 6723

    22+400 22+500 3 3 10 F F 6724

    22+500 22+600 5 10 10 F F 7333

    22+600 22+700 5 G F 6725

    22+700 22+800 G F 7334

    22+800 22+900 5 15 F F 6726 , 7335

    26+100 26+200 G F 7337

    26+200 26+300 2 G F 7338

    26+300 26+400 10 2 F F 7339-40

    26+400 26+500 10 3 F F 7341

    26+500 26+600 2 2 G F 7342

    26+600 26+700 3 G F

    Page 2 of  20

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    41/119

    From To Cracks Pot holes Ravelling Bleeding PatchingRemarks

    Shoulder

    Condition

    Chainage Rutting

    (mm)

    Distressess in (%) Pavement

    Condition

    26+700 26+800 5 2 G F 7343

    26+800 26+900 3 G F 7344

    26+900 27+000 G F

    27+000 27+100 G F 7345

    27+100 27+200 G F 6763

    27+200 27+300 15 G F 7346

    27+300 27+400 3 G F 7347

    27+400 27+500 5 3 G F 6764 ,7348

    27+500 27+600 G F 6765

    27+600 27+700 2 G F 7349

    27+700 27+800 2 G F 7350

    27+800 27+900 G F 7351

    27+900 28+000 G F 6767-766

    28+000 28+100 G F 7352

    28+100 28+200 G F 7353

    28+200 28+300 10 10 F F 7354-55

    28+300 28+400 12 G F 7356

    28+400 28+500 G F 7357

    28+500 28+600 25 5 F F 7358-59

    28+600 28+700 10 10 F F 7360-61

    28+700 28+800 G F 7362

    28+800 28+900 G F 7363

    - , -

    29+000 29+100 15 F F 7366

    29+100 29+200 5 G F 6771 , 7367

    29+200 29+300 G F 7368

    29+300 29+400 4 G F 7369

    29+400 29+500 G F 7370

    29+500 29+600 G F 6772

    29+600 29+700 G F 6773

    29+700 29+800 G F 7371

    29+800 29+900 G F 7372

    29+900 30+000 G F 6774-75

    30+000 30+100 G F 7373

    30+100 30+200 G F 7374

    30+200 30+300 G F 7375

    Page 3 of  20

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    42/119

    From To Cracks Pot holes Ravelling Bleeding PatchingRemarks

    Shoulder

    Condition

    Chainage Rutting

    (mm)

    Distressess in (%) Pavement

    Condition

    30+300 30+400 G F 7376

    30+400 30+500 G F 7377

    30+500 30+600 G F 7378

    30+600 30+700 G F 7379

    30+700 30+800 G F 7380

    30+800 30+900 G F 7381

    30+900 31+000 G F 6776-78

    31+000 31+100 5 G F 7382

    31+100 31+200 5 G F 6779 , 7383

    31+200 31+300 G F 6780 , 7384

    31+300 31+400 G F 6781 , 7385

    31+400 31+500 G F 7386

    31+500 31+600 G F 7387

    31+600 31+700 G F 7388

    31+700 31+800 5 5 G F 7389-90

    31+800 31+900 G F 7391

    31+900 32+000 G F 782-83 ,7392

    32+000 32+100 10 F F 7393

    32+100 32+200 5 3 G F 7394

    32+200 32+300 5 5 10 G F 7395-96

    32+300 32+400 10 10 G F 7397-98

    32+400 32+500 5 15 5 G F 7399

    32+600 32+700 5 10 5 G F 7401-02

    32+700 32+800 8 10 G F 7403-04

    32+800 32+900 25 P F 7405-06

    32+900 33+000 3 15 F F 7407-08

    33+000 33+100 15 3 F F 7409

    33+100 33+200 25 P F 7410

    33+200 33+300 20 P F 7411

    33+300 33+400 2 G F

    33+400 33+500 3 G F

    33+500 33+600 30 10 P F 7412

    33+600 33+700 25 5 P F 7413

    33+700 33+800 5 3 G F 7414

    33+800 33+900 G F

    Page 4 of  20

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    43/119

    From To Cracks Pot holes Ravelling Bleeding PatchingRemarks

    Shoulder

    Condition

    Chainage Rutting

    (mm)

    Distressess in (%) Pavement

    Condition

    33+900 34+000 10 G F

    36+000 36+100 10 30 5 5 P F

    36+100 36+200 40 5 VP F 7416-17

    36+200 36+300 20 P F 7418-19

    36+300 36+400 25 5 P F 7420

    36+400 36+500 30 10 P F 7421

    36+500 36+600 25 3 P F 7422

    36+600 36+700 25 P F 7423-24

    36+700 36+800 30 3 P F 7425

    36+800 36+900 5 3 G F 7426

    36+900 37+000 20 3 P F 6611-613

    37+000 37+100 25 P F 6615-616

    37+100 37+200 35 VP F 6617

    37+200 37+300 20 10 P F 6618-19 , 7427

    37+300 37+400 20 P F 6620

    37+400 37+500 10 F F 6621

    37+500 37+600 40 VP F 6622

    37+600 37+700 20 P F 6623

    37+700 37+800 20 P F 6624

    37+800 37+900 20 P F 6625

    37+900 38+000 30 P F 6626-27

    38+100 38+200 10 F F 7429

    38+200 38+300 5 G F 7430

    38+300 38+400 12 F F 7431

    38+400 38+500 5 3 G F 7432

    38+500 38+600 15 F F 7433

    38+600 38+700 10 F F 7434

    38+700 38+800 5 G F 7435

    38+800 38+900 10 F F 7436

    38+900 39+000 G F 6629-30

    39+000 39+100 5 3 G F 6631

    39+100 39+200 10 5 F F 7437

    39+200 39+300 25 10 P F 7438-39

    39+300 39+400 10 10 F F 7440

    Page 5 of  20

  • 8/21/2019 Revised Pavement Design - Beawar Pali Section.pdf

    44/119

    From To Cracks Pot holes Ravelling Bleeding PatchingRemarks

    Shoulder

    Condition

    Chainage Rutting

    (mm)

    Distressess in (%) Pavement

    Condition

    39+400 39+500 25 10 P F 7441-42

    39+500 39+600 10 3 F F 7443

    39+600 39+700 15 5 F F 7444

    39+700 39+800 30 3 10 P F 7445-46

    39+800 39+900 30 10 P F 7447-48

    39+900 40+000 35 10 VP 0 7449-50

    40+000 40+100 5 G F 7451

    40+100 40+200 3 G F 7452

    40+200 40+300 5 10 F F 7453

    40+300 40+400 10 10 P F 7454

    40+400 40+500 25 10 P F 7455-56

    40+500 40+600 15 2 F F 7457

    40+600 40+700 15 5 F F 7458

    40+700 40+800 15 5 F F 7459

    40+800 40+900 15 F F 7460

    40+900 41+000 5 3 G F 7461

    41+000 41+100 5 5 G F 7462-63

    41+100 41+200 10 F F 7464

    41+200 41+300 5 3 G F 7465

    44+700 44+