Reviewing the Indirect Support Cost Rate for WFP · Reviewing the Indirect Support Cost Rate for...

21
Reviewing the Indirect Support Cost Rate for WFP RM Seminar Rome, 29 January 2014

Transcript of Reviewing the Indirect Support Cost Rate for WFP · Reviewing the Indirect Support Cost Rate for...

Page 1: Reviewing the Indirect Support Cost Rate for WFP · Reviewing the Indirect Support Cost Rate for WFP RM Seminar Rome, 29 January 2014 . 2 2Resource Management and Accountability Department

Reviewing the Indirect Support

Cost Rate for WFP

RM Seminar

Rome, 29 January 2014

Page 2: Reviewing the Indirect Support Cost Rate for WFP · Reviewing the Indirect Support Cost Rate for WFP RM Seminar Rome, 29 January 2014 . 2 2Resource Management and Accountability Department

2 2 Resource Management and Accountability Department

ISC Rate Review Highlights

1. Objectives of the Review

2. Background

3. Drivers for the 2014 ISC Review

4. Issues for EB Guidance

5. Next Steps

Page 3: Reviewing the Indirect Support Cost Rate for WFP · Reviewing the Indirect Support Cost Rate for WFP RM Seminar Rome, 29 January 2014 . 2 2Resource Management and Accountability Department

3 3 Resource Management and Accountability Department

Objectives for the Review

Page 4: Reviewing the Indirect Support Cost Rate for WFP · Reviewing the Indirect Support Cost Rate for WFP RM Seminar Rome, 29 January 2014 . 2 2Resource Management and Accountability Department

4 4 Resource Management and Accountability Department

Objectives of the ISC Review

• Frame WFP’s ISC policies to support the Strategic Plan and the

Management Results Framework

• Ensure the ISC rate is sufficient to cover Programme Support and

Administrative (PSA) needs at different funding levels

• Agree a simple and transparent method for calculating and

applying ISC

• A two-phase approach is proposed:

• First phase - outline the current thinking and the questions that will

shape the discussion

• Second phase - draw conclusions and make recommendations

Page 5: Reviewing the Indirect Support Cost Rate for WFP · Reviewing the Indirect Support Cost Rate for WFP RM Seminar Rome, 29 January 2014 . 2 2Resource Management and Accountability Department

5 5 Resource Management and Accountability Department

Background

Page 6: Reviewing the Indirect Support Cost Rate for WFP · Reviewing the Indirect Support Cost Rate for WFP RM Seminar Rome, 29 January 2014 . 2 2Resource Management and Accountability Department

6 6 Resource Management and Accountability Department

Evolution of Indirect Support Cost policies in WFP

1995 CFA recommended the adoption of the full cost recovery

principle

1998 EB recommended a single ISC rate of 7.8 per cent as part of

the review of Resources and Long Term Financing Policy

2002 ISC review established the PSA Equalization account and set

the ISC rate at 7.0 percent

2006 ISC review recommended that the ISC rate be based on actual

audited results

7% ISC rate has been retained since 2003

Page 7: Reviewing the Indirect Support Cost Rate for WFP · Reviewing the Indirect Support Cost Rate for WFP RM Seminar Rome, 29 January 2014 . 2 2Resource Management and Accountability Department

7 7 Resource Management and Accountability Department

Drivers for the 2014 Indirect Support Cost Review

Page 8: Reviewing the Indirect Support Cost Rate for WFP · Reviewing the Indirect Support Cost Rate for WFP RM Seminar Rome, 29 January 2014 . 2 2Resource Management and Accountability Department

8 8 Resource Management and Accountability Department

Drivers for the 2014 Indirect Support Cost Review

Quadrennial Comprehensive Policy Review (QCPR) and

harmonization

Resource mobilization

Maximizing value for money

Adapting to WFP’s changing financial framework

Page 9: Reviewing the Indirect Support Cost Rate for WFP · Reviewing the Indirect Support Cost Rate for WFP RM Seminar Rome, 29 January 2014 . 2 2Resource Management and Accountability Department

9 9 Resource Management and Accountability Department

Quadrennial Comprehensive Policy Review (QCPR) and

UN harmonization

2012 -2016 QCPR seeks:

Transparent, harmonized, cost recovery framework based on full

cost recovery from core and non-core resources

A common definition of operating costs and a standard system of

cost control

Agreement on defining a critical mass for core resources

Harmonization among other agencies

UNDP, UNICEF, UNFPA, UN Women have a common cost recovery framework

and rate starting in 2014

FAO & WHO are reviewing their cost recovery methods (e.g. differentiated rates for

emergencies and development; “cost recovery uplift” as part of staff costs)

Page 10: Reviewing the Indirect Support Cost Rate for WFP · Reviewing the Indirect Support Cost Rate for WFP RM Seminar Rome, 29 January 2014 . 2 2Resource Management and Accountability Department

10 10 Resource Management and Accountability Department

Resource Mobilization

Desire for more flexible and multi year contributions

Changing environment from traditional donors to non-traditional

donors along with differing criteria and needs:

Host governments

South-south cooperation

Private Sector

Multi Partner Trust Funds

Page 11: Reviewing the Indirect Support Cost Rate for WFP · Reviewing the Indirect Support Cost Rate for WFP RM Seminar Rome, 29 January 2014 . 2 2Resource Management and Accountability Department

11 11 Resource Management and Accountability Department

Maximizing Value for Money

PSA levels and the ISC rate are regarded as a proxy for efficiency

But benefits of PSA expenditures are often reflected in more cost

effective project operations

For example: Supply chain initiatives funded through PSA can improve

delivery times and reduce project costs.

Page 12: Reviewing the Indirect Support Cost Rate for WFP · Reviewing the Indirect Support Cost Rate for WFP RM Seminar Rome, 29 January 2014 . 2 2Resource Management and Accountability Department

12 12 Resource Management and Accountability Department

Adapting to WFP’s Changing Business Environment

Continual shift from food aid to food assistance

For example:

Less procurement and transportation of food

Increase in non-food activities such as cash and vouchers and

capacity augmentation

Page 13: Reviewing the Indirect Support Cost Rate for WFP · Reviewing the Indirect Support Cost Rate for WFP RM Seminar Rome, 29 January 2014 . 2 2Resource Management and Accountability Department

13 13 Resource Management and Accountability Department

Issues for Guidance

Page 14: Reviewing the Indirect Support Cost Rate for WFP · Reviewing the Indirect Support Cost Rate for WFP RM Seminar Rome, 29 January 2014 . 2 2Resource Management and Accountability Department

14 14 Resource Management and Accountability Department

Issues for Guidance

Funding Model for PSA costs

ISC versus other funding sources

Implications for ISC for the shift to food assistance

Resource Mobilization considerations

Page 15: Reviewing the Indirect Support Cost Rate for WFP · Reviewing the Indirect Support Cost Rate for WFP RM Seminar Rome, 29 January 2014 . 2 2Resource Management and Accountability Department

15 15 Resource Management and Accountability Department

Funding Model for PSA Costs

Key Questions:

Is there interest in supporting a move towards core budget for WFP?

In the absence of support for core funding is there value in

considering different approaches for fixed and variable indirect costs?

Additional material provided for information at this informal seminar

Phase 2 Analysis:

Heavily dependent upon feedback from the Executive Board in

February

Page 16: Reviewing the Indirect Support Cost Rate for WFP · Reviewing the Indirect Support Cost Rate for WFP RM Seminar Rome, 29 January 2014 . 2 2Resource Management and Accountability Department

16 16 Resource Management and Accountability Department

ISC versus other funding sources - Questions

Key Questions:

How should ISC be interpreted and what should be the scope of

PSA funding?

Should WFP continue to consider multiple funding sources for:

security, capital costs, or innovations?

Page 17: Reviewing the Indirect Support Cost Rate for WFP · Reviewing the Indirect Support Cost Rate for WFP RM Seminar Rome, 29 January 2014 . 2 2Resource Management and Accountability Department

17 17 Resource Management and Accountability Department

ISC versus other funding sources – Phase II

Phase 2 Analysis, subject to feedback from the February EB:

Revisit how ISC and DSC are interpreted and charged

Review recovery mechanisms and how to reduce the dependency

on unpredictable funding sources

Confirm an appropriate PSA Equalization Account target level

Propose guidelines for the use of the unearmarked portion of the

General Fund and PSA Equalization Account surpluses

Page 18: Reviewing the Indirect Support Cost Rate for WFP · Reviewing the Indirect Support Cost Rate for WFP RM Seminar Rome, 29 January 2014 . 2 2Resource Management and Accountability Department

18 18 Resource Management and Accountability Department

Implications of ISC for the transition to Food Assistance

Key Questions:

What are the implications for WFP’s transition to food assistance

on programme support and administration expenditures?

Should WFP continue with a single ISC recovery rate for all

programmes and activities?

Phase 2 Analysis, subject to feedback from the February EB:

Details of how the concept is applied in other agencies

More details on how the single rate was adopted in WFP

Page 19: Reviewing the Indirect Support Cost Rate for WFP · Reviewing the Indirect Support Cost Rate for WFP RM Seminar Rome, 29 January 2014 . 2 2Resource Management and Accountability Department

19 19 Resource Management and Accountability Department

Resource Mobilization Considerations

Key Questions:

Could variable ISC rates incentivize South–South cooperation,

host government contributions, unearmarked contributions,

multi-year contributions and private-sector contributions?

Phase 2 analysis, subject to feedback from the February EB:

Assess the effect of the ISC rate on attracting donors

Determine whether flexible ISC rates encourage contributions

from non-traditional donors

Make recommendations, recognizing the principle of simplicity,

and avoiding significant ISC rate subsidy

Page 20: Reviewing the Indirect Support Cost Rate for WFP · Reviewing the Indirect Support Cost Rate for WFP RM Seminar Rome, 29 January 2014 . 2 2Resource Management and Accountability Department

20 20 Resource Management and Accountability Department

Next Steps

Reactions to the 4 key questions, modified to reflect the view of

FAO Finance Committee, to be sought through the ACABQ, and

the February Board

Informal Consultations to be held in March, April, and May to

share outcomes and to seek additional inputs

Annual Session ISC Review to be submitted for Approval

November Board Session: 2015 ISC rate set through the approval

of the 2015-2017 Management Plan

Page 21: Reviewing the Indirect Support Cost Rate for WFP · Reviewing the Indirect Support Cost Rate for WFP RM Seminar Rome, 29 January 2014 . 2 2Resource Management and Accountability Department

21 21 Resource Management and Accountability Department

Thank you