Review A.6
Transcript of Review A.6
![Page 1: Review A.6](https://reader035.fdocuments.in/reader035/viewer/2022062504/586821881a28aba27d8b4848/html5/thumbnails/1.jpg)
A.6 Sensitivity Analysis Theory Review Questions
1
Lesson Topics
Sensitivity Analysis (or post-optimality analysis)
determines how an optimal solution is affected by changes in the objective function coefficients or in the right-hand side constants.
Sensitivity to Coefficients (1) measures how
changes in the objective function coefficients change optimal solutions. The range of optimality are those values keeping the current solution optimal.
Sensitivity to Constants (7) measures how
changes in the right-hand-side constants of constraints change optimal solutions. The dual price is the rate of improvement in the objective function. Computer Analysis computes the range of optimality of each decision variable, the dual price of each constraint, and range of feasibility for each dual price.
Resource Allocation Problems with Sensitivity
Analysis help production managers compute the value to them of buying additional resources to produce goods. That value guides mutually-beneficial trade.
![Page 2: Review A.6](https://reader035.fdocuments.in/reader035/viewer/2022062504/586821881a28aba27d8b4848/html5/thumbnails/2.jpg)
A.6 Sensitivity Analysis Theory Review Questions
2
Sensitivity to Coefficients
Question. The following problem that maximizes
profit from the production of two products has an
optimum where the first and third constraints are
binding.
Min x1 + 2x2
s.t. x1 + x2 30
2x1 + x2 40
2x1 + 5x2 > 75
x1 , x2 > 0
If the objective function becomes Min 2x1 + 2x2, what will be the optimal
values of x1, x2, and the objective function? Be sure to show your work and
your reasoning.
![Page 3: Review A.6](https://reader035.fdocuments.in/reader035/viewer/2022062504/586821881a28aba27d8b4848/html5/thumbnails/3.jpg)
A.6 Sensitivity Analysis Theory Review Questions
3
Answer to Question: For partial credit, find an optimal solution to the
new problem:
The solution to the original problem remains optimal if the slope of the
objective function remains between the slopes of the binding forms of the
first and third constraints.
Slope of the objective function c1x1 + c2x2 is -c1/c2.
Slope of the binding first constraint x1 + x2 = 30 is -1.
Slope of the binding third constraint 2x1 + 5x2 = 75 is -2/5.
Therefore, the solution to the original problem remains optimal if
-1 < -c1/c2 < -2/5, which means
1 > c1/c2 > 2/5, which is satisfied by the new objective function
Min 2x1 + 2x2.
Finally, find the solution to the original and the new problems by solving the
binding forms of the first the third constraints,
x1 + x2 = 30 and 2x1 + 5x2 = 75. And insert the solutions x1 = 25 and x2 =
5 into the objective function, Z = 2x1 + 2x2 = 50 + 10 = 60.
For full credit, find any alternative optimal solutions to the new
problem:
A constraint and iso-value-line graph reveals the iso-value-line passing
through the optimum (25,5) above lies along an edge of the feasible set. In
particular, (25,5) is not the only optimum. One other optimum is where the
first and second constraints bind, at (10,20). And there are an infinite
number of other optima. They are those points (x1 , x2) on the line segment
joining (25,5) to (10,20).
![Page 4: Review A.6](https://reader035.fdocuments.in/reader035/viewer/2022062504/586821881a28aba27d8b4848/html5/thumbnails/4.jpg)
A.6 Sensitivity Analysis Theory Review Questions
4
Sensitivity to Constants
Question. Blue Ridge Hot Tubs produces two types
of hot tubs: Aqua-Spas and Hydro-Luxes.
There are 5 pumps, 18 hours of labor, and 16 feet of
tubing available to make the tubs. Here are the input
requirements, and unit profits:
Aqua-Spa Hydro-Lux
Pumps 1 1
Labor 3 hours 6 hours
Tubing 6 feet 4 feet
Unit Profit $8 $20
Formulate Blue Ridge’s problem as a linear program.
Solve graphically for the optimum.
How much should Blue Ridge be willing to pay for one more pump? for two
more pumps? for one more foot of tubing? for two more feet of tubing?
Tip: Your written answer should define the decision variables, formulate the
objective and constraints, and solve the problem.
![Page 5: Review A.6](https://reader035.fdocuments.in/reader035/viewer/2022062504/586821881a28aba27d8b4848/html5/thumbnails/5.jpg)
A.6 Sensitivity Analysis Theory Review Questions
5
Answer to Question:
Let A = number of Aqua-Spa’s and H = number of Hydro-Lux’s produced.
Max 8 A + 20 H
s.t.
A + H < 5 (pump constraint)
3A + 6H < 18 (labor constraint)
6A + 4H < 16 (tubing constraint)
Graphing the constraints and isovalue lines indicates the non-negativity of
A and the labor constraint are binding at the optimum (so A = 0 and 3A +
6H = 18), with the pump constraint and the tubing constraint both slack.
Therefore, the solution is to produce no Aqua-Spa’s and 3 Hydro-Lux’s.
Since both the pump and tubing constraints are slack at the optimum,
Blue Ridge should only be willing to pay whatever input prices are
embedded into the unit profits for one more pump, or for two more pumps,
or for one more foot of tubing, or for two more feet of tubing,
6
5
4
3
2
1
0
0 1 2 3 4 5 6 7
Aqua Spa’s on horizontal axis
Hydro-Lux’s on vertical axis
Pump-constraint intercepts A=5 and H=5
Labor-constraint intercepts A=6 and H=3
Tubing-constraint intercepts A=2.7 and H=4
Sample isovalue line (dashed)
![Page 6: Review A.6](https://reader035.fdocuments.in/reader035/viewer/2022062504/586821881a28aba27d8b4848/html5/thumbnails/6.jpg)
A.6 Sensitivity Analysis Theory Review Questions
6
Sensitivity to Constants
Question. Blue Ridge Hot Tubs produces two types
of hot tubs: Aqua-Spas and Hydro-Luxes.
To make the tubs, there are 5 pumps available at a
cost of $1 each, 16 hours of labor available at a cost
of $1 per hour, and 10 feet of tubing available at a cost of $1 per foot. Here
are the input requirements, sales prices, and unit profits:
Aqua-Spa Hydro-Lux
Pumps 1 1
Labor 3 hours 7 hours
Tubing 6 feet 4 feet
Sales Price $20 $32
Unit Profit $10 $20
Formulate Blue Ridge’s problem as a linear program.
Solve for the optimum.
How much should Blue Ridge be willing to pay for one more pump? for one
more hour of labor? for one more foot of tubing?
You may use computer software to compute your answers, but be sure to
define the computer input, write down the essential computer output, and
explain how the computer output solves the problem.
Tip: Your written answer should define the decision variables, formulate the
objective and constraints, and solve the problem.
![Page 7: Review A.6](https://reader035.fdocuments.in/reader035/viewer/2022062504/586821881a28aba27d8b4848/html5/thumbnails/7.jpg)
A.6 Sensitivity Analysis Theory Review Questions
7
Answer to Question:
Let A = number of Aqua-Spa’s and H = number of Hydro-Lux’s produced.
Max 10 A + 20 H
s.t.
A + H < 5 (pump constraint)
3A + 7H < 16 (labor constraint)
6A + 4H < 10 (tubing constraint)
Management Scientist output below reveals the optimum A = .2, H = 2.2,
with the pump constraint slack and the labor and tubing constraints binding,
with dual prices 2.667 and 0.333. Hence, Blue Ridge should be willing to
pay $1 for one more pump (the input price embedded into the unit profits),
$1 + 2.667 = $3.667 for one more hour of labor, and $1 + 0.333 = $1.333
for one more foot of tubing.
![Page 8: Review A.6](https://reader035.fdocuments.in/reader035/viewer/2022062504/586821881a28aba27d8b4848/html5/thumbnails/8.jpg)
A.6 Sensitivity Analysis Theory Review Questions
8
![Page 9: Review A.6](https://reader035.fdocuments.in/reader035/viewer/2022062504/586821881a28aba27d8b4848/html5/thumbnails/9.jpg)
A.6 Sensitivity Analysis Theory Review Questions
9
Sensitivity to Constants
Question. Blue Ridge Hot Tubs produces two types
of hot tubs: Aqua-Spas and Hydro-Luxes.
To make the tubs, there are 4 pumps available at the
cost of $4 each, 18 hours of labor available at a cost
of $1 per hour, and 16 feet of tubing available at a cost of $0.50 per foot.
Here are the input requirements, sales prices, and unit profits:
Aqua-Spa Hydro-Lux
Pumps 1 1
Labor 3 hours 6 hours
Tubing 6 feet 4 feet
Sales Price $13 $19
Unit Profit $3 $7
Formulate Blue Ridge’s problem as a linear program.
Solve graphically for the optimum.
How much should Blue Ridge be willing to pay for one more pump? for
one more hour of labor? for one more foot of tubing?
Tip: Your written answer should define the decision variables, formulate the
objective and constraints, and solve the problem.
![Page 10: Review A.6](https://reader035.fdocuments.in/reader035/viewer/2022062504/586821881a28aba27d8b4848/html5/thumbnails/10.jpg)
A.6 Sensitivity Analysis Theory Review Questions
10
Answer to Question:
Let A = number of Aqua-Spa’s and H = number of Hydro-Lux’s produced.
Max 3 A + 7 H
s.t.
A + H < 4 (pump constraint)
3A + 6H < 18 (labor constraint)
6A + 4H < 16 (tubing constraint)
Graphing the constraints and isovalue lines indicates the non-negativity of
A and the labor constraint are binding at the optimum (so A = 0 and 3A +
6H = 18), with the pump constraint and the tubing constraint both slack.
Therefore, the solution is to produce 0 Aqua-Spa’s and 3 Hydro-Lux’s.
Blue Ridge should be willing to pay just the embedded input prices of $4 for
one more pump, $0.50 for one more foot of tubing?
To find the dual price of labor, recompute the optimum for 19 hours
available: A = 0 and 3A + 6H = 19. So, 0 Aqua-Spa’s and 3 1/6 Hydro-
Lux’s. That increases profit $7x(1/6) = $1.17. Hence, Blue Ridge should
be willing to pay $1 + 1.17 = $2.17 for one more hour of labor.
6
5
4
3
2
1
0
0 1 2 3 4 5 6 7
Aqua Spa’s on horizontal axis
Hydro-Lux’s on vertical axis
Pump-constraint intercepts A=5 and H=5
Labor-constraint intercepts A=6 and H=3
Tubing-constraint intercepts A=2.7 and H=4
Sample isovalue line (dashed)
![Page 11: Review A.6](https://reader035.fdocuments.in/reader035/viewer/2022062504/586821881a28aba27d8b4848/html5/thumbnails/11.jpg)
A.6 Sensitivity Analysis Theory Review Questions
11
Sensitivity to Constants
Question. The Boeing Company seeks to maximize
profit by making Model 747 (4-engine widebody) and
Model 787 (2-engine widebody) commercial aircraft
from aluminum, titanium and labor.
It just received this month's allocation of 18 tons of aluminum and 5 tons of
titanium, and there is 16 thousand hours of labor available.
It takes 3 tons of aluminum to make each Model 747 aircraft, and 2 tons of
aluminum to make each Model 787 aircraft.
And it takes 1 ton of titanium to make each Model 747 aircraft .
And it takes 2 thousand hours of labor to make each Model 747 aircraft,
and 2 thousand hours of labor to make each Model 787 aircraft.
Model 747 aircraft have unit profit of 2 million dollars, and Model 787
aircraft have unit profit of 1 million dollars.
Graphically determine how much The Boeing Company should produce of
each aircraft.
How much should The Boeing Company be willing to pay to expand its
labor force from 16 thousand hours to 17 thousand hours? That is, how
much more profit can be made if The Boeing Company can use 17
thousand hours of labor?
![Page 12: Review A.6](https://reader035.fdocuments.in/reader035/viewer/2022062504/586821881a28aba27d8b4848/html5/thumbnails/12.jpg)
A.6 Sensitivity Analysis Theory Review Questions
12
Answer to Question:
Let X = units of Model 747 produced.
Let Y = units of Model 787 produced.
Max 2X + Y
s.t. 3X + 2Y < 18 (tons of aluminum)
X < 5 (tons of titanium)
2X + 2Y < 16 (thousand hours of labor)
X, Y 0
Graphing the constraints and isovalue lines indicates the third constraint
(labor) is slack when the amount of labor is either 16 thousand hours or 17
thousand hours. Solving the binding form of the first two constraints yields
the optimal solution: X = 5, Y = 1.5.
How much should The Boeing Company produce of each aircraft? 5 units
of Model 747 and 1.5 units of Model 787.
How much should The Boeing Company be willing to pay to expand its
labor force from 16 thousand hours to 17 thousand hours? Since the labor
constraint is slack, they should not pay anything to expand that constraint.
6
5
4
3
2
1
0
0 1 2 3 4 5 6 7
Model 747 on horizontal axis
Model 787 on vertical axis
Aluminum-constraint intercepts X=6 and Y=9
Titanium-constraint intercept X=5
Labor-constraint intercepts X=8 and Y=8 (when
there are 16 units of labor)
Sample isovalue line (dashed)
![Page 13: Review A.6](https://reader035.fdocuments.in/reader035/viewer/2022062504/586821881a28aba27d8b4848/html5/thumbnails/13.jpg)
A.6 Sensitivity Analysis Theory Review Questions
13
Sensitivity to Constants
Question. Davison Electronics manufactures two
LCD television monitors, identified as model A and
model B. Each model has its lowest possible
production cost when produced on Davison’s new
production line. However, the new production line does not have the
capacity to handle the total production of both models. As a result, as least
some of the production must be routed to a higher-cost, old production line.
The following table shows the minimum production requirements for next
month, the production line table shows the minimum production
requirements for next month, the production line capacities in units per
month, and the production cost per unit for each production line:
Let: AN= Units of model A produced on the new production line AO= Units of model A produced on the old production line BN = Units of model B produced on the new production line BO= Units of model B produced on the old production line
Production Cost per
Unit on
Production Cost per
Unit on
Model New Line Old Line Minimum Production
Requirements
A $30 $50 50,000
B $25 $40 70,000
Production Line
Capacity
80,000 60,000
![Page 14: Review A.6](https://reader035.fdocuments.in/reader035/viewer/2022062504/586821881a28aba27d8b4848/html5/thumbnails/14.jpg)
A.6 Sensitivity Analysis Theory Review Questions
14
Davison’s objective is to determine the minimum cost production plan. The
computer solution is shown below.
a. Formulate the linear programming model for this problem using the
following four constraints: Constraint 1: Minimum production for model A Constraint 2: Minimum production for model B Constraint 3: Capacity of the new production line Constraint 4: Capacity of the old production line
b. Using computer solution below, what is the optimal solution, and what is
the total production cost associated with this solution?
c. Which constraints are binding? Explain.
d. The production manager noted that the only constraint with a positive dual price is the constraint on the capacity of the new production line. The manager’s interpretation of the dual value was that a one-unit increase in the right-hand side of this constraint would actually increase the total production cost by $15 per unit. Do you agree with this interpretation? Would an increase in capacity for the new production line be desirable? Explain.
e. Would you recommend increasing the capacity of the old production line? Explain.
f. Suppose that the minimum production requirement for model B is reduced from 70,000 units to 60,000 units. What effect would this change have on the total production cost? Explain.
![Page 15: Review A.6](https://reader035.fdocuments.in/reader035/viewer/2022062504/586821881a28aba27d8b4848/html5/thumbnails/15.jpg)
A.6 Sensitivity Analysis Theory Review Questions
15
Optimal Objective Value = 3850000.00000
Variable Value Reduced Cost
AN 50000.00000 0.00000
AO 0.0000 5.00000
BN 30000.00000 0.00000
BO 40000.00000 0.00000
Constraint Slack/Surplus Dual Price
1 0.00000 -45.00000
2 0.00000 -40.00000
3 0.00000 15.00000
4 20000.00000 0.00000
OBJECTIVE COEFFICIENT RANGES
Variable Objective Coefficient Allowable Increase Allowable Decrease
AN 30.00000 5.00000 Infinite
AO 50.00000 Infinite 5.00000
BN 25.00000 15.00000 5.00000
BO 40.00000 5.00000 15.00000
RIGHT HAND SIDE RANGES
Constraint RHS Value Allowable Increase Allowable Decrease
1 50000.00000 20000.00000 40000.00000
2 70000.00000 20000.00000 40000.00000
3 80000.00000 40000.00000 20000.00000
4 60000.00000 Infinite 20000.00000
![Page 16: Review A.6](https://reader035.fdocuments.in/reader035/viewer/2022062504/586821881a28aba27d8b4848/html5/thumbnails/16.jpg)
A.6 Sensitivity Analysis Theory Review Questions
16
Answer to Question:
a. The linear programming model is as follows:
Min 30AN + 50AO + 25BN + 40BO
s.t.
AN + AO 50,000
BN + BO 70,000
AN + BN 80,000
AO + BO 60,000
b. Optimal solution:
New Line Old Line
Model A 50,000 0
Model B 30,000 40,000
Total Cost $3,850,000
c. The first three constraints are binding because the values in the
Slack/Surplus column for these constraints are zero. The fourth
constraint, with a slack of 0 is nonbinding.
d. The dual price for the new production line capacity constraint is 15.
Because the dual price is positive, increasing the right-hand side of
constraint 3 will cause the objective function value to decrease
(improve). Thus, every one unit increase in the right hand side of this
constraint will reduce the total production cost by $15. In other words,
an increase in capacity for the new production line is desirable.
![Page 17: Review A.6](https://reader035.fdocuments.in/reader035/viewer/2022062504/586821881a28aba27d8b4848/html5/thumbnails/17.jpg)
A.6 Sensitivity Analysis Theory Review Questions
17
e. Because constraint 4 is not a binding constraint, any increase in the
production line capacity of the old production line will have no effect on
the optimal solution. Thus, there is no benefit in increasing the capacity
of the old production line.
f. The right hand side range for constraint 2 shows an allowable
decrease of 20,000. Thus, if the minimum production requirement is
reduced 10,000 units to 60,000, the dual value of 40 is applicable.
Thus, total cost would decrease by 10,000(40) = $400,000.
![Page 18: Review A.6](https://reader035.fdocuments.in/reader035/viewer/2022062504/586821881a28aba27d8b4848/html5/thumbnails/18.jpg)
A.6 Sensitivity Analysis Theory Review Questions
18
Sensitivity to Constants
Question: Vollmer Manufacturing makes three
components for sale to refrigeration companies.
The components are processed on two machines: a
sharper and a grinder. The times (in minutes)
required on each machine are as follows:
The sharper is available for 120 hours, and the grinder is available for 110
hours. No more than 200 units of component 3 can be sold, but up to 1000
units of each of the other components can be sold. In fact, the company
already has orders for 600 units of component 1 that must be satisfied. The
profit contributions for components 1,2, and 3 are $8, $6, and $9,
respectively.
a. Formulate and use the Management Scientist to solve for the
recommended production quantities.
b. What are the objective coefficient ranges for the three components?
Interpret these ranges for company management.
c. What are the right-hand-side ranges? Interpret these ranges for
company management.
d. If more time could be made available on the grinder, how much would
it be worth?
e. If more units of component 3 can be sold by reducing the sales price
by $4, should the company reduce the price?
Machine
Component Sharper Grinder
1 6 4
2 4 5
3 4 2
![Page 19: Review A.6](https://reader035.fdocuments.in/reader035/viewer/2022062504/586821881a28aba27d8b4848/html5/thumbnails/19.jpg)
A.6 Sensitivity Analysis Theory Review Questions
19
Answer to Question:
a. LetC1 = units of component 1 manufactured C2 = units of component 2 manufactured
C3 = units of component 3 manufactured
Max 8C1 + 6C2 + 9C3
s.t. 6C1 + 4C2 + 4C3 < 7200
4C1 + 5C2 + 2C3 < 6600
C3 < 200
C1 < 1000
C2 < 1000
C1 > 600
C1, C2, C3 > 0
The optimal solution is
C1 = 600
C2 = 700
C3 = 200
b.
Variable Objective Coefficient Range
C1 No Lower Limit to 9.0
C2 5.33 to 9.0
C3 6.00 to No Lower Limit
Individual changes in the profit coefficients within these ranges will not cause a change in the optimal number of components to produce.
c. Constraint Right-Hand-Side Range
1 4400 to 7440 2 6300 to No Upper Limit
3 100 to 900 4 600 to No Upper Limit
5 700 to No Upper Limit 6 514.29 to 1000
![Page 20: Review A.6](https://reader035.fdocuments.in/reader035/viewer/2022062504/586821881a28aba27d8b4848/html5/thumbnails/20.jpg)
A.6 Sensitivity Analysis Theory Review Questions
20
These are the ranges over which the dual values for the associated
constraints are applicable.
d. Nothing, since there are 300 minutes of slack time on the grinder at
the optimal solution.
e. No, since at that price it would not be profitable to produce any of
component 3. To see that, the proposed reduction of $4 in the sales
price means a $4 reduction in the unit profit, from $9 to $5. That is
outside the range of optimality, so you need to re-compute an answer.
That answer is that the output of component 3 falls to 0. So, it is not
worth lowering the price by $4 to sell more.
![Page 21: Review A.6](https://reader035.fdocuments.in/reader035/viewer/2022062504/586821881a28aba27d8b4848/html5/thumbnails/21.jpg)
A.6 Sensitivity Analysis Theory Review Questions
21
Sensitivity to Constants
Question: The Ford Motor Company makes cars
and trucks on an assembly line. Each car and truck
requires labor and needs to visit three stations:
engine installation, hood installation, and wheel
installation. The hours of labor and hours required at each station are as
follows:
There are available 12 hours of labor, 48 hours of engine installation, 20
hours of hood installation, and 6 hours of wheel installation. Labor costs
$20 per hour, and each station costs $10 per hour to operate. Cars sell for
$700 each, and trucks sell for $540 each.
a. Formulate and graphically solve for the recommended production
quantities. Do not require production units to be integers.
b. How much should Ford be willing to pay to another potential worker
(Joe) to supply one more unit of labor. (Joe is not part of the 12
hours of labor mentioned above.)
Engine Hood Wheel
Vehicle Labor Installation Installation Installation
Car 4 6 4 3
Truck 3 8 5 4
![Page 22: Review A.6](https://reader035.fdocuments.in/reader035/viewer/2022062504/586821881a28aba27d8b4848/html5/thumbnails/22.jpg)
A.6 Sensitivity Analysis Theory Review Questions
22
Answer to Question:
a. The profit contributions are $500 for each car, and $300 for each truck.
Let C = cars produced.
Let T = trucks produced.
Max 500C + 300T
s.t. 4C + 3T < 12 (labor)
6C + 8T < 48 (engine)
4C + 5T < 20 (hood)
3C + 4T < 12 (wheel)
C, T 0
A graph of the feasible set shows the engine and hood constraints are
redundant, and the iso-value lines show the optimal solution occurs where
the labor constraint and the non-negativity of T bind (C = 3 and T = 0).
0
1
2
3
4
5
6
7
8
9
10
0 1 2 3 4 5 6 7 8 9 10
![Page 23: Review A.6](https://reader035.fdocuments.in/reader035/viewer/2022062504/586821881a28aba27d8b4848/html5/thumbnails/23.jpg)
A.6 Sensitivity Analysis Theory Review Questions
23
b. How much should Ford be willing to pay to change the problem by
having Joe supply one more unit of labor.
Repeat analysis after changing the right hand side of the first constraint
from 12 to 13:
Max 500C + 300T
s.t. 4C + 3T < 13 (labor)
6C + 8T < 48 (engine)
4C + 5T < 20 (hood)
3C + 4T < 12 (wheel)
C, T 0
The new graph of the feasible set shows the engine and hood constraints
are redundant, and the iso-value lines show the optimal solution occurs
where the labor constraint and the non-negativity of T bind (C = 13/4 = 3.25
and T = 0). That new solution yields profit 500C + 300T = 1625, which is
125 higher than the previous profit of 1500. So, Ford should be willing to
pay up to 145 = 20+125 dollars to Joe.
0
1
2
3
4
5
6
7
8
9
10
0 1 2 3 4 5 6 7 8 9 10
![Page 24: Review A.6](https://reader035.fdocuments.in/reader035/viewer/2022062504/586821881a28aba27d8b4848/html5/thumbnails/24.jpg)
A.6 Sensitivity Analysis Theory Review Questions
24
Sensitivity to Constants
Question. The Iron Works, Inc. seeks to maximize
profit by making two products from steel and labor.
It just received this month's allocation of 18 pounds of
steel, and there is 160 hours of labor available.
It takes 3 pounds of steel to make a unit of Product 1, and 2 pounds of
steel to make a unit of Product 2. It also takes 40 hours of labor to make a
unit of Product 1, and 20 hours of labor to make a unit of Product 2.
The physical plant has the capacity to make up to 6 units of total product
(Product 1 plus Product 2).
Product 1 has unit profit 6 dollars, and Product 2 has 5 dollars.
Graphically determine how much Iron Works should produce of each
product.
How much should Iron Works be willing to pay to expand its plant capacity
from 6 to 7? That is, how much more profit can be made if Iron Works can
make up to 7 units of total product?
![Page 25: Review A.6](https://reader035.fdocuments.in/reader035/viewer/2022062504/586821881a28aba27d8b4848/html5/thumbnails/25.jpg)
A.6 Sensitivity Analysis Theory Review Questions
25
Answer to Question:
Let X = units of Product 1 produced.
Let Y = units of Product 1 produced.
Max 6X + 5Y
s.t. 3X + 2Y < 18 (steel)
40X + 20Y < 160 (labor)
X + Y < 6 (capacity)
X, Y 0
A graph of the feasible set reveals that the first costraint is redundant --- it
does not affect the feasible set. Adding a graph of isovalue lines reveals
the optimum occurs where the second and third constraints bind. Solving
the binding form of those two constraints yields the optimal solution: X = 2,
Y = 4.
How much should Iron Works produce of each product? 2 units of Product
1, and 4 units of Product 2.
How much should Iron Works be willing to pay to expand its plant capacity
from 6 to 7? That is, how much more profit can be made if Iron Works can
make up to 7 units of total product? After changing the third constraint from
X+Y < 6 to X+Y < 7, a graph of the feasible set and isovalue lines reveals
the first constraint is still redundant, and the optimum still occurs where the
second and third constraints bind. Solving the binding form of those two
constraints yields the new optimal solution: X = 1, Y = 6. That new
solution yields profit 6X + 5Y = 36, which is higher than the profit 6X + 5Y
= 32. Precisely, 4 dollars more profit can be made if Iron Works can make
up to 7 units of total product, so Iron Works should be willing to pay up to 4
dollars to expand its plant capacity from 6 to 7