TECHNICAL REPORT
Project: Overhauling And Calibration OfControl Valves
Engro Fertilizers Plant-II Shutdown, Dharki(April 27 – May 10, 2016)
Client:
Submitted to: Mr. Asad Naeem (Instrument Engineer)
Work Order Reference: 6636 Purchase Order Reference: 5000001993
Flowtronix Head Office: 101/s, Quaid-e-Azam Industrial Estate, Kot Lakhpat, Lahore 54760 – Pakistan. UAN: 111-355-355 (111-EKL-EKL) Tel: 92-42-35215611 Fax: +92-42-35151104
E-mail: [email protected]
Manpower DetailOrganogramTools & Equipment Used Page 3List of control valvesDaily Progress LogValve Record Sheets
6.1 11-XV-2011A6.2 11-FV-20486.3 11-HV-20116.4 11-XV-2011B6.5 11-FV-20306.6 11-FV-20116.7 11-FV-18016.8 11-FV-20336.9 11-PV-2046
Page 19Page 20Page 21
Overhauling and CalibrationsOf Control Valves
6
Table Of Contents12
Page 12
Page 1Page 2
Page 4Page 5
45
3
Page 12Page 13
Page 15Page 16
Page 18Page 17
Page 14
6.9 11-PV-20466.10 11-PV-20276.11 10-LV-10186.12 11-HV-30226.13 11-FV-20266.14 11-FV-20766.15 11-XV-20276.16 11-PV-74986.17 11-PV-2046B6.18 11-PV-71096.19 PIC-611V6.20 LIC-611A6.21 11-FV-70106.22 11-PV-3015B6.23 11-PV-20216.24 11-XV-2027A6.25 11-XV-2027C6.26 11-FV-3021B6.27 11-FV-3026D6.28 11-FV-30226.29 11-LV-5010A6.30 11-HV-10126.31 10-LV-10036.32 11-LV-5010B6.33 10-HV-10086.34 11-TV-3004
Page 20Page 21Page 22Page 23Page 24Page 25Page 26Page 27Page 28Page 29Page 30Page 31Page 32Page 33Page 34Page 35Page 36Page 37Page 38Page 39Page 40Page 41Page 42Page 43
Page 45Page 44
Page 46
Overhauling and CalibrationsOf Control Valves
Table Of Contents6.37 11-FV-20566.38 10-HV-10096.39 11-LV-3011B6.40 11-LV-3011A6.41 19-FV-9001A6.42 19-FV-90026.43 11-FV-20286.44 11-LV-20556.45 11-TV-54826.46 11-TV-54766.47 11-HV-1032B
Pictures (Work In Progress)
Page 53
7 Page 59
Page 48
Page 58
Page 54Page 55Page 56Page 57
Page 49Page 50Page 51Page 52
1. MANPOWER DETAIL:
Sr. No. Father's Name Trade Shift1 Amer Siddiq Project Incharge Day/Night
2 Mohammad Jamil Supevervisor Day
3 Haq Nawaz Supevervisor Night
4 Sher Muhammad Instr. Fitter Night
5 Abdul Rasheed Instr. Fitter Night
6 M Yameen Instr. Fitter Day
7 M Sadiq Instr. Fitter Day
8 M Ramzan Instr. Fitter Day
9 Basheer Ahmad Instr. Fitter Day
10 M Aslam Instr. Fitter Day
11 Abdul Hameed Instr. Fitter Night
Sagheer ahmad Sajid
M Ilyas
M Tariq
NameRamiz Siddiq
Sajid Tanveer
Sajjad ahmad
Overhauling and Calibrations OfControl Valves
Abdul Rehman
Saeed Ahmad
Jalal Uddin M Akbar
M Shafiq
Aamir Usman
M Khalid
11 Abdul Hameed Instr. Fitter Night
12 Ali Hassan Instr. Fitter Night
13 Riasat Ali Instr Tech Day
14 Maqbool Ahmad Instr Tech Day
15 Ghulam Akbar Instr Tech Day
16 Amman Ullah Instr Tech Day
17 Mohammad Bashir Instr Tech Night
18 Ghulam Hussain Instr Tech Night
19 Mushtaq Ahmad Instr Tech Night
20 Helper Night
21 Abdul Sattar Helper Day
22 Abdul Wahid Helper Day
23 Iftikhar Husain Helper Day
24 M Yousaf Helper Day
25 Mohammad Nazir Helper Night
26 M Alamgir Helper Day
27 Mushtaq Ahmad Helper Night
Mohammad Ali
M Umer
Mohammad Muddasar
Hafiz Adnan Hussain
Mohmmmad Mubasher
Amjad Mubeen
Anees Sattar
M Shoaib
M Zubair
M Adil
Mohammad Umair Riasat
Mohammad Abid Naeem
Abul Sattar
Irfan Ullah
Iftikhar Ahmad
M Shafiq
Aamir Usman
Page 1 of 59
2. ORGANOGRAM:
Day Shift Night Shift
Team 1 Team 2 Team 3
Ramiz Siddiq(Project Incharge)
Mohamad Tariq(Instr. Fitter)
Saeed Ahmad(Instr. Fitter)
Mohammad Ilyas(Instr. Fitter)
M Shoaib(Helper)
Umari Riasat(Instr. Technician)
M Adil(Helper)
Overhauling and Calibrations OfControl Valves
Sajid Tanveer(Instrument Supervisor)
Abdul Sattar(Instr. Technician)
Abid Naeem(Instr. Technician)
Irfan Ullah(Instr. Technician)
Abdul Rehman(Instr. Fitter)
Jallal Uddin(Instr. Fitter)
Anees Sattar(Helper)
Team 1 Team 2 Team 3
Mohammad Shafiq(Instr. Fitter)
M Shoaib(Helper)
M Adil(Helper)
Hafiz Adnan(Instr. Technician)
Sajjad Ahmad(Instrument Supervisor)
Amjad Mubeen(Helper)
Mohamamd Ali(Helper)
Sagheer Ahmad(Instr. Fitter)
M Umer(Helper)
Hafiz Iftikhar(Instr. Technician)
M. Muddassar(Helper)
Aamir Usman(Instr. Fitter)
Mohammad Khalid(Instr. Fitter)
Anees Sattar(Helper)
M. Mubasher(Instr. Technician)
Page 2 of 59
3. TOOLS USED:
Screw Drivers (Star Set)
Allen Key Set (Star, mm, inch)
Side Cutters
Monkey Pliers
Combination Pliers
Nose Pliers
Open End & Ring Spanner Sets
Needle File Set
Files (Round, Half Round and Flat)
Stacking Spanner Set (26-50mm)
Hammers (Rubber, Wooden, Brass & MS)
Overhauling and Calibrations OfControl Valves
Sr. No. Tools & Equipment
1
2
3
4
5
6
7
8
9
10
11
12
A. Used For Overhauling
Hammers (Rubber, Wooden, Brass & MS)
Lifting Belts & D-Shackles
Vernier Caliper
Digital Multimeter
HART Communicator
mAmp Source
DC Source
Pressure Guage
Air Regulator
5
6
1
2
3
4
B. Used For Calibration
11
12
13
Page 3 of 59
4. LIST OF CONTROL VALVES:Total Quantity : 47 Nos.
6
12-
208--
648
161612
Size (inch)8
12-
1248
11-FV-7010LIC-611APIC-611V
11-PV-2046B1819
11-LV-5010A11-FV-3022
11-LV-3026D11-FV-3021B11-XV-2027C11-XV-2027A
10-HV-1012
10-PV-1021A11-PV-3015B
6
345
789
1011
131415
12
1617
11-TV-300410-HV-100811-LV-5010B10-FV-1003
Overhauling and Calibrations OfControl Valves
Sr. No.12
Tag No.11-HV-2071A11-PV-7109
11-HV-1032B4647
-1
444-
11-TV-547645
19-PV-9001A11-FV-202811-LV-205511-TV-5482
42
4443
181888
1010
108-8
12
463
102412
612--88
-
10-HV-100911-FV-205611-PV-1048
11-FV-204811-XV-2011A11-LV-3011A11-LV-3011B19-FV-9002
11-FV-203310-FV-180111-FV-201111-FV-203011-HV-201111-XV-2011B
11-FV-207611-FV-202611-HV-302210-LV-101811-PV-2027
11-PV-2046A
PIC-611V11-PV-2046B
242526
2223
11-PV-749811-XV-2027
18192021
27
36373839
333435
4041
2829303132
Page 4 of 59
5. DAILY PROGRESS LOG:
Sr # Tag No. Activities Date Shift D/NCleaning, Oiling and PolishingFound resetting device faultyFound tyflon inside bodyPnumatic Relay CheckedCalibratedSent for Hydro testingCleaning, Oiling and PolishingFound Valve ball stuckCalibratedSent for Hydro testingCleaning, Oiling and PolishingAir leak test of actuator was found OKHand jack was made smooth by servicingCalibratedSent for HydrotestingCleaning, Oiling and PolishingOverhauling
3 11-HV-2011 27-4-16 Night
Day
4 27-4-16 Night
1 27-4-1611-XV-2011B
2 27-4-16 Day11-XV-2011A
11-FV-2048
Overhauling and CalibrationsOf Control Valves
OverhaulingCalibratedSent for Hydro testingCleaning, Oiling and PolishingOverhauling StartedCleaning, Oiling and PolishingRemoving & Cleaning PositionerRemoving & Cleaning Limit SwitchesOverhaulingFound leakage in CylinderCleaning, Oiling and PolishingOverhaulingCleaning, Oiling and PolishingOverhauling StartedCleaning, Oiling and PolishingOverhauling StartedCleaning, Oiling and PolishingOverhauling StartedValve body sent for machiningCleaning, Oiling and PolishingOverhaulingCalibratedSent for Hydro testingCleaning, Oiling and PolishingOverhaulingSent Actuator Stem for machiningCalibratedSent for Hydro testing
7 28-4-16 Day10-FV-1801
28-4-16
28-4-16
Day
Day
Night
4 27-4-16 Night
6 28-4-16 Day
5 27-4-16 Night
11-FV-2048
11-FV-2030
11-FV-2011
28-4-16
8
9
10
11-PV-2046B
11-FV-2033
10-LV-1018
Night
Night
11
12
28-4-16
28-4-16
11-PV-2027
11-FV-2030
Page 5 of 59
5. DAILY PROGRESS LOG:
Sr # Tag No. Activities Date Shift D/N
Day1 27-4-1611-XV-2011B
Overhauling and CalibrationsOf Control Valves
Cleaning, Oiling and PolishingRemoving & Cleaning of PositionerRemoving & Cleaning of Limit SwitchOverhaulingCalibrationSent for HydrotestingCleaning, Oiling and PolishingOverhaulingCalibrationSent for HydrotestingCleaning, Oiling and PolishingAir Leak test okCalibrationValve Body returned from MachiningCalibrationSent for HydrotestingCleaning, Oiling and Polishing
15 29-4-16 Day
14 29-4-16 Day
13 29-4-16 Day11-FV-2011
11-FV-2033
11-HV-3022
29-4-16 Night16
17
10-LV-1018
29-4-16 Night11-FV-2026
Cleaning, Oiling and PolishingOverhaulingCalibrationSent for HydrotestingCleaning, Oiling and PolishingOverhaulingCalibrationSent for HydrotestingCleaning, Oiling and PolishingAir Leak test okCleaning, Oiling and PolishingOverhauling StartedCleaning, Oiling and PolishingOverhaulingCalibrationSent for HydrotestingCleaning, Oiling and PolishingOverhaulingCalibrationSent for HydrotestingCleaning, Oiling and PolishingOverhaulingCalibrationSent for HydrotestingCleaning, Oiling and PolishingAir leak test okOverhauling Started
19
18
17
29-4-16 Night20
21 30-4-16 Day
Day30-4-1622
23
29-4-16 Night
29-4-16 Night
29-4-16 Night
11-FV-2026
11-FV-2076
11-XV-2027
10-LV-2018
11-PV-7498
11-FV-1801
30-4-16 Day
24 30-4-16 Day
11-PV-2046B
11-PV-7109
Page 6 of 59
5. DAILY PROGRESS LOG:
Sr # Tag No. Activities Date Shift D/N
Day1 27-4-1611-XV-2011B
Overhauling and CalibrationsOf Control Valves
Cleaning, Oiling and PolishingAir Leak test okOverhaulingValve Seat Missing, New installedNew Lock relay installedCalibrationSent for HydrotestingCleaning, Oiling and PolishingAir Leak test okOverhaulingCalibrationSent for HydrotestingCleaning, Oiling and PolishingOverhauling StartedCleaning, Oiling and PolishingAir Leak test okOverhauling
Night26 30-4-16
27 30-4-16 Night
25 30-4-16 NightPIC-611V
LIC-611A
11-FV-7010
28 01-5-16 Day11-PV-3015B OverhaulingServicing of hand wheelCalibrationSent for HydrotestingCleaning, Oiling and PolishingAir Leak test okRemoving & Cleaning of PositonerCleaning, Oiling and PolishingAir Leak test okCalibrationSent for HydrotestingCleaning, Oiling and PolishingAir Leak test okCalibrationSent for HydrotestingCleaning, Oiling and PolishingOverhauling StartedCleaning, Oiling and PolishingAir Leak test okOverhaulingFound Leakage in Pneumatic relayFixed Pneumatic realyCalibrationSent for HydrotestingCleaning, Oiling and PolishingAir Leak test okOverhauling Started
29 01-5-16 Day
30 01-5-16 Day
28 01-5-16 Day11-PV-3015B
11-PV-1021A
11-XV-2027A
32 01-5-16 Day
33 01-5-16 Night
31 01-5-16 Day11-XV-2027C
11-PV-7109
11-FV-7010
34 01-5-16 Night11-FV-3021B
Page 7 of 59
5. DAILY PROGRESS LOG:
Sr # Tag No. Activities Date Shift D/N
Day1 27-4-1611-XV-2011B
Overhauling and CalibrationsOf Control Valves
Cleaning, Oiling and PolishingAir Leak test okFound valve not 100% openingPositioner DismantledOverhaulingSent body for machiningHydrotest Failed @2400psiBench Set readjustedValve stem readjustedCalibratedSent For HydrotestingCleaning, Oiling and PolishingAir Leak test okCleaning, Oiling and PolishingAir Leak test okSent body for machiningHydrotest Failed
02-05-16 Day
38 02-05-16 Day
39 02-05-16 Night
35 02-05-16 Day
Day02-05-1636
37
11-LV-3026D
10-FV-1801
11-FV-3022
11-LV-5010A
11-FV-7010
Hydrotest FailedFound Valve Positioner faultyFound Pneumatic Relay faultyFixed pneumatic relay and reinstalledCalibratedSent For HydrotestingOverhaulingAir Leak test okSent seat, cage and stem for machiningCalibratedSent For HydrotestingCleaning, Oiling and PolishingAir Leak test okOverhaulingCalibration StartedCleaning, Oiling and PolishingAir Leak test okCalibratedSent For HydrotestingReceived Body from machiningOverhauling
44 10-FV-1003 Cleaning, Oiling and Polishing 03-05-16 DayCleaning, Oiling and PolishingAir Leak test okOverhaulingSent For HydrotestingCleaning, Oiling and PolishingAir Leak test ok
41 02-05-16 Night
39 02-05-16 Night
40 02-05-16 Night
42 03-05-16 Day
43 03-05-16 Day
45 03-05-16 Day
Day03-05-1646
11-LV-3026D
11-LV-5010A
11-LV-5010B
11-FV-7010
11-FV-3021B
11-FV-3022
10-HV-1012
Page 8 of 59
5. DAILY PROGRESS LOG:
Sr # Tag No. Activities Date Shift D/N
Day1 27-4-1611-XV-2011B
Overhauling and CalibrationsOf Control Valves
CalibrationSent For HydrotestingCleaning, Oiling and PolishingAir Leak test okSent seat, cage and stem for machining
49 10-HV-1008 Flange Opened 03-05-16 NightCleaning, Oiling and PolishingAir Leak test okSent seat, cage and stem for machiningOverhaulingSent For HydrotestingCleaning, Oiling and PolishingAir Leak test okOverhaulingCalibrationSent For HydrotestingCleaning, Oiling and Polishing
11-TV-300452 04-05-16 Day
48 03-05-16 Night
47 03-05-16 Night
50 04-05-16
04-05-16 Day
Day
51
11-FV-3022
11-PV-7109
11-LV-5010B
10-PV-1021A
Cleaning, Oiling and PolishingAir Leak test okBench Set was foundSent For HydrotestingCleaning, Oiling and PolishingAir Leak test okCalibrationSent For HydrotestingCleaning, Oiling and PolishingAir Leak test okCalibrationSent For HydrotestingCleaning, Oiling and PolishingAir Leak test okCalibrationSent For HydrotestingCleaning, Oiling and PolishingAir Leak test okSeat and plug were sent for machiningAll gaskets replacedDiapharm was found tornedDiapharm replacedCalibratedSent for Hydrotesting
56 05-05-16 Day
11-HV-2071A55 05-05-16 Day
11-TV-300452 04-05-16 Day
54 04-05-16 Night
Night04-05-1653 11-LV-3026D
11-HV-2011A
11-PV-1048
Page 9 of 59
5. DAILY PROGRESS LOG:
Sr # Tag No. Activities Date Shift D/N
Day1 27-4-1611-XV-2011B
Overhauling and CalibrationsOf Control Valves
Received seat, cage and stem from machiningSeat gasket replacedBody gaskets replacedAir leak test of actuator was found OKCalibratedSent for Hydro testingCleaning, Oiling and PolishingAir Leak test okPositioner DismantledCleaning, Oiling and PolishingAir Leak test okBench Set was foundCleaning, Oiling and PolishingAir Leak test okOverhauling of body and actuatorSeat and plug were sent for machiningCleaning, Oiling and Polishing
60 06-05-16 Day
06-05-1610-HV-100961 Day
11-PV-710957 05-05-16 Night
11-LV-3011A58 05-05-16 Night
05-05-16 Night11-LV-3011B59
19-FV-9002
Cleaning, Oiling and PolishingAir Leak test okOuter diapharm of actuator was disassembledBench Set was foundCleaning, Oiling and PolishingAir Leak test okPlug, seat and cage were sent for machiningCleaning, Oiling and PolishingAir Leak test okDiapharm was found OkOverhauling of body and actuatorO-rings replacedSeat, plug sent for machiningAll gaskets replacedCalibratedSent For HydrotestingBody gaskets replacedCalibratedSent for Hydro testingReceived Plug, seat and cage from machiningAll three gaskets of valve replacedGland packing was replacedCalibratedSent for Hydro testingReceived Plug, seat and cage from machiningGaskets were replacedGland packing was replaced
67 10-HV-1009 Plug and gland packing were removed 07-05-16 Day
11-LV-3011B65 06-05-16 Night
11-LV-3011A66 06-05-16 Night
19-FV-9001A63 6-5-16 Day
64 06-05-16 Night
06-05-1610-HV-100961 Day
62 06-05-16 Day
19-FV-9002
11-LV-3011B
Page 10 of 59
5. DAILY PROGRESS LOG:
Sr # Tag No. Activities Date Shift D/N
Day1 27-4-1611-XV-2011B
Overhauling and CalibrationsOf Control Valves
Received Plug, seat and cage from machiningBench Set readjustedCalibrationSent for Hydro testingCleaning, Oiling and PolishingPlug, seat and cage were sent for machiningTubing was readjustedCalibratedSent for Hydro testingCleaning, Oiling and PolishingAir Leak test okPositioner was removed for cleaningDiapharm was found okCalibratedSent For HydrotestingCleaning, Oiling and PolishingAir Leak test ok
68 11-LV-3011B 07-05-16 Day
10-LV-100772 08-05-16 Day
69 11-HV-1008 07-05-16 Day
11-LV-3011A70 07-05-16 Day
11-PV-749871 08-05-16 Day
Air Leak test okCalibration was tested and found okScratches were found on valve stemRemoved scratches by filing and embre paperAir Leak test okSent For HydrotestingActuator was reopenedOverhauling of body and actuatorCleaning, Oiling and PolishingAir Leak test okCalibrationCleaning, Oiling and PolishingAir Leak test okCalibrationCleaning, Oiling and PolishingAir Leak test okCalibrationCleaning, Oiling and PolishingAir Leak test okCalibrationCleaning, Oiling and PolishingAir Leak test okCalibration
10-LV-100772 08-05-16 Day
73 10-HV-1009 08-05-16 Day
11-TV-547677 10-05-16 Night
78 11-HV-1032B 10-05-16 Night
09-05-16 Day11-FV-202874
11-LV-205575 09-05-16 Night
11-TV-548276 10-05-16 Day
Page 11 of 59
CLIENT DATE: 27-04-2016
PROJECT DOC.NO. CV-E-001
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-XV-2011A SERVICE: Process Air SIZE: 12"
AREA: AMM-3 FLANGE TYPE: Flanged
PHYSICAL CHECKS:
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
27-04-2016
EXECUTED BY
Umair Riasat(Instrument Technician)
1. Valve ball was stuck.2. Cleaning, oiling and polishing the vlave ball.
FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
87 psi
VALVE BENCH SET
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 12 of 59
CLIENT DATE: 27-04-2016
PROJECT DOC.NO. CV-E-002
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-FV-2048 SERVICE: Process Air SIZE: 8-/-4-/-8"
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
27-04-2016
EXECUTED BY
Umair Riasat(Instrument Technician)
1. Actuator O-rings were replaced.2. Pug and seat were sent for machining.3. All gaskits were replaced.4. Overhauling5. Calibrated6. Sent for Hydrotesting
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 13 of 59
CLIENT DATE: 27-04-2016
PROJECT DOC.NO. CV-E-003
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-HV-2011 SERVICE: Process Air SIZE: 8 "
AREA: AMM-3 FLANGE TYPE: RF 125 AARH
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Actuator was found stuck.2. Air leak test of actuator was found OK3. Hand jack was made smooth by servicing4. Calibrated5. Sent For Hydrotesting
DATE
27-04-2016
EXECUTED BY
Umair Riasat(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 14 of 59
CLIENT DATE: 27-04-2016
PROJECT DOC.NO. CV-E-004
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-XV-2011B SERVICE: Process Air SIZE:
AREA: AMM-3 FLANGE TYPE:
PHYSICAL CHECKS:
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
27-04-2016
EXECUTED BY
Umair Riasat(Instrument Technician)
1. Tyflon Seat seal was damaged.2. Found air leakage in resetting device.3. Tyflon seat seal replaced.4. Resetting device O-Rings were replaced5. Calibrated6. Sent for hydrotesting
VALVE BENCH SET FAIL SAFE ACTION
Open
SUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 15 of 59
CLIENT DATE: 27-04-2016
PROJECT DOC.NO. CV-E-005
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-FV-2030 SERVICE: Process Air SIZE: 10 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
27-04-2016
EXECUTED BY
Umair Riasat(Instrument Technician)
1. Overhauling of actuator and body.2. Actuator Stem was sent for machining.3. Actuator Gasket replaced4. Gland packing replaced.5. Calibration6. Sent for hydrotesting
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 16 of 59
CLIENT DATE: 28-04-2016
PROJECT DOC.NO. CV-E-006
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-FV-2011 SERVICE: Process Air SIZE: 12 "
AREA: AMM-3 FLANGE TYPE: RF-125 AARH
PHYSICAL CHECKS:
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
28-04-2016
EXECUTED BY
Umair Riasat(Instrument Technician)
1. Found air leakage in cylinder2. Overhauling of Actuator3. O-rings required relacements, tyflon was wound due to inavailablity.4. Found a embosed spot on piston5. Removing and cleaning of positioner6. Removing and cleaning of Actuator7. Feedback link plate gaskets replaced8. Calibration9. Sent for hydrotesting
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 17 of 59
CLIENT DATE: 28-04-2016
PROJECT DOC.NO. CV-E-007
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 10-FV-1801 SERVICE: Process Air SIZE: 24 "
AREA: AMM-3 FLANGE TYPE:
PHYSICAL CHECKS:
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
28-04-2016
EXECUTED BY
Umair Riasat(Instrument Technician)
1. Removing and Cleaning of Positioner2. Overhauling of Actuator3. Plug was sent for machining4. Gland packing replaced5. Seals replaced6. Found a embosed spot on piston.7. Calibrated8. Sent for hydrotesting
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 18 of 59
CLIENT DATE: 28-04-2016
PROJECT DOC.NO. CV-E-008
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-FV-2033 SERVICE: Process Air SIZE: 6 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
28-04-2016
EXECUTED BY
Umair Riasat(Instrument Technician)
1. Overhauling of Actuator2. Overhauling of Body3. Seat seals replaced4. Gland packing replaced5. Vapour Seals replaced6. Actuator O-rings replaced7. Inner and outer plug seals replaced8. Calibrated9. Sent for Hydrotesting
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
30
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 19 of 59
CLIENT DATE: 28-04-2016
PROJECT DOC.NO. CV-E-009
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-PV-2046A SERVICE: Process Air SIZE: 3 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
28-04-2016
EXECUTED BY
Umair Riasat(Instrument Technician)
1. Overhauling of actuator
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
40
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 20 of 59
CLIENT DATE: 28-04-2016
PROJECT DOC.NO. CV-E-010
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-PV-2027 SERVICE: Process Air SIZE:
AREA: AMM-3 FLANGE TYPE:
PHYSICAL CHECKS:
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
28-04-2016
EXECUTED BY
Umair Riasat(Instrument Technician)
1. Overhauling of Actuator2. Overhauling of Body3. Seat, Plug and cage were sent for machining4. Seat seals replaced5. Gland packing replaced6. Body and seat gasket replaced7. Actuator O-rings replaced
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 21 of 59
CLIENT DATE: 29-04-2016
PROJECT DOC.NO. CV-E-011
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 10-LV-1018 SERVICE: Process Air SIZE: 4 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
29-04-2016
EXECUTED BY
Umair Riasat(Instrument Technician)
1. Found Leak test of actuator OK2. Overhauling of Actuator3. Overhauling of Body4. Body was sent for machining5. Seat seals replaced6. Body gasket replaced7. Actuator O-rings replaced8. Gland packings replaced9. Calibrated
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 22 of 59
CLIENT DATE: 29-04-2016
PROJECT DOC.NO. CV-E-012
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-HV-3022 SERVICE: Process Air SIZE: 8 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
29-04-2016
EXECUTED BY
Umair Riasat(Instrument Technician)
1. Air Leak check of actuator was found OK2. Calibrated3. Sent for Hydrotesting
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
60
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 23 of 59
CLIENT DATE: 29-04-2016
PROJECT DOC.NO. CV-E-013
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-FV-2026 SERVICE: Process Air SIZE: 8 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
29-04-2016
EXECUTED BY
Umair Riasat(Instrument Technician)
1. Overhauling of Body2. Overhauling of Actuator3. Seat and plug were sent for machining4. Plug seal ring (carbon) was repalced.5. Inner and outer seals were replaced6. Gland packing replaced7. Calibrated
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 24 of 59
CLIENT DATE: 29-04-2016
PROJECT DOC.NO. CV-E-014
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-FV-2076 SERVICE: Process Air SIZE: 4 "
AREA: AMM-3 FLANGE TYPE: RTJ Flanges
PHYSICAL CHECKS:
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
29-04-2016
EXECUTED BY
Umair Riasat(Instrument Technician)
1. Overhauling of body2. Overhauling of actuator3. Inner and outer seals replaced4. Gland packing replaced5. O-rings replaced6. Calibrated
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 25 of 59
CLIENT DATE: 29-04-2016
PROJECT DOC.NO. CV-E-015
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-XV-2027 SERVICE: Process Air SIZE: 4 "
AREA: AMM-3 FLANGE TYPE: RTJ Flanges
PHYSICAL CHECKS:
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
29-04-2016
EXECUTED BY
Umair Riasat(Instrument Technician)
1. Air leak test of actuator was found OK2. Overhauling of actuator3. Overhauling of body4. Seat, Plug and Cage were machined5. Seat seals replaced4. Gland packing replaced5. Body and seat gaskets replaced6. Calibrated
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 26 of 59
CLIENT DATE: 30-04-2016
PROJECT DOC.NO. CV-E-016
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-PV-7498 SERVICE: Process Air SIZE: 12 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
30-04-2016
EXECUTED BY
Abid Naeem(Instrument Technician)
1. Diapharm was stretched and torn from nut & bolts holes at circumference.2. Overhauling of actuator3. Actuator seals replaced4. Diapharm replaced5. Calibrated
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
58
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 27 of 59
CLIENT DATE: 30-04-2016
PROJECT DOC.NO. CV-E-017
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-PV-2046B SERVICE: Process Air SIZE: 6-/-3-/-6
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
30-04-2016
EXECUTED BY
Abid Naeem(Instrument Technician)
1. Overhauling of actuator2. Plug and seat ring polished3. Seat gaskets changed4. Body gaskets replaced5. Gland packing replaced.6. O-rings of actuator replaced.7. Calibrated8. Sent for Hydrotesting
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 28 of 59
CLIENT DATE: 30-04-2016
PROJECT DOC.NO. CV-E-018
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-PV-7109 SERVICE: Process Air SIZE: 12 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
30-04-2016
EXECUTED BY
Abid Naeem(Instrument Technician)
1. Air leak test of actuator was found OK2. Valve bonut was stuck with actuator yoke, heated and hammered to get them separated.3. Overhauling of body4. Plug, Seat and Cage were sent for machining5. Inner and outer body gaskets were replaced6. Both rings of valve plug were replaced7. Calibrated8. Sent for Hydrotesting
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
60
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 29 of 59
CLIENT DATE: 30-04-2016
PROJECT DOC.NO. CV-E-019
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: PIC-611V SERVICE: Process Air SIZE:
AREA: AMM-3 FLANGE TYPE:
PHYSICAL CHECKS:
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
30-04-2016
EXECUTED BY
Abid Naeem(Instrument Technician)
1. Valve seat was not found during disassembly2. Lock relay was not working3. Seat and plug were sent for machining4. Air Leak test of Actuator was found OK5. Overhauling of Valve body6. Seals replaced7. Lock relay replaced8. Calibrated9. Sent for Hydrotesting
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 30 of 59
CLIENT DATE: 30-04-2016
PROJECT DOC.NO. CV-E-020
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: LIC-611A SERVICE: Process Air SIZE:
AREA: AMM-3 FLANGE TYPE:
PHYSICAL CHECKS:
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
DATE
30-04-2016
EXECUTED BY
Abid Naeem(Instrument Technician)
1. Air leak test of actuator was found OK2. Overhauling of Body3. Seals replaced4. Gland packing replaced5. Calibrated6. Sent for Hydrotesting
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 31 of 59
CLIENT DATE: 30-04-2016
PROJECT DOC.NO. CV-E-021
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-FV-7010 SERVICE: Process Air SIZE: 8 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
Flowtronix (Pvt) Ltd.
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Air leakage found in Pneumatic relay of positioner2. Overhauling of Body3. Overhauling of Actuator4. Actuator O-rings replaced5. Body gaskets replaced6. O-rings of pneumatic relay replaced7. Calibrated8. Sent for Hydrotesting
DATE
30-04-2016
EXECUTED BY
Abid Naeem(Instrument Technician)
FAIL SAFE ACTIONSUPPLIED PRESSUREVALVE BENCH SET
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 32 of 59
CLIENT DATE: 01-05-2016
PROJECT DOC.NO. CV-E-022
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-PV-3015B SERVICE: Process Air SIZE: 20 "
AREA: AMM-3 FLANGE TYPE: RF-125 AARH
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Handwheel was found stucking while rotating either way.2. Overhauling of actuator3. Servicing, oiling and cleaning of handwheel4. Calibrated5. Sent for Hydrotesting
DATE
01-05-2016
EXECUTED BY
Abid Naeem(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 33 of 59
CLIENT DATE: 01-05-2016
PROJECT DOC.NO. CV-E-023
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-PV-2021A SERVICE: Process Air SIZE:
AREA: AMM-3 FLANGE TYPE:
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Actuator air leak test was found OK.2. Positioner dismantled and cleaned3. Calibrated4. Sent for Hydrotesting
DATE
01-05-2016
EXECUTED BY
Abid Naeem(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 34 of 59
CLIENT DATE: 01-05-2016
PROJECT DOC.NO. CV-E-024
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-XV-2027A SERVICE: Process Air SIZE: 12 "
AREA: AMM-3 FLANGE TYPE: Flanged
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Valve ball was not smoothly opening and closing.2. Air leak test of actuator was found OK3. Polishing, oiling and cleanig of valve ball was done untill required smoothness was aquired.4. Calibrated5. Sent for Hydrotesting
DATE
01-05-2016
EXECUTED BY
Abid Naeem(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 35 of 59
CLIENT DATE: 01-05-2016
PROJECT DOC.NO. CV-E-025
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-XV-2027C SERVICE: Process Air SIZE: 12 "
AREA: AMM-3 FLANGE TYPE: Flanged
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Valve ball was not smoothly opening and closing.2. Air leak test of actuator was found OK3. Polishing, oiling and cleanig of valve ball was done untill required smoothness was aquired.4. Calibrated5. Sent for Hydrotesting
DATE
01-05-2016
EXECUTED BY
Abid Naeem(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 36 of 59
CLIENT DATE: 02-05-2016
PROJECT DOC.NO. CV-E-026
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-FV-3021B SERVICE: Process Air SIZE: 16 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Air leak test of Actuator was found OK2. Overhauling of actuator3. Overhauling of body4. Body seals replaced5. O-rings of actuator Replaced6. Inner and outer body seals were replaced7. Cage seals were replaced8. Gland packing replaced9. Calibration10. Sent for Hydrotesting
DATE
02-05-2016
EXECUTED BY
Abid Naeem(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
55
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 37 of 59
CLIENT DATE: 03-05-2016
PROJECT DOC.NO. CV-E-027
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-LV-3026D SERVICE: Process Air SIZE: 16-/-12-/-16"
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Valve was found not opennig 100%2. Overhauling of body3. Positioner was readjsuted4. Body was sent for machining5. Calibration6. Sent for Hydrotesting
DATE
03-05-2016
EXECUTED BY
Abid Naeem(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 38 of 59
CLIENT DATE: 03-05-2016
PROJECT DOC.NO. CV-E-028
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-FV-3022 SERVICE: Process Air SIZE: 8 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Air Leak test of actuator was found OK2. Overhauling of Actuator3. Overhauling of Body3. Actuator O-rings replaced4. Body gaskets replaced5. Gland packing replaced6. Calibration.7. Sent for Hydrotesting
DATE
03-05-2016
EXECUTED BY
Adnan Hussain(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 39 of 59
CLIENT DATE: 03-05-2016
PROJECT DOC.NO. CV-E-029
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-LV-5010A SERVICE: Process Air SIZE: 4 "
AREA: AMM-3 FLANGE TYPE: RTJ Flanges
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Air leak test of actuator was found OK2. Overhauling of body3. Inner and outer body seals replaced.4. Body gaskets replaced5. Plug seals replaced6. Calibrated7. Sent for Hydrotesting
DATE
03-05-2016
EXECUTED BY
Adnan Hussain(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
50
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 40 of 59
CLIENT DATE: 03-05-2016
PROJECT DOC.NO. CV-E-030
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 10-HV-1012 SERVICE: Process Air SIZE: 6 "
AREA: AMM-3 FLANGE TYPE: RF 125 AARH
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Air leak test of actuator was found OK2. Calibration3. Sent for Hydrotesting
DATE
03-05-2016
EXECUTED BY
Adnan Hussain(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 41 of 59
CLIENT DATE: 03-05-2016
PROJECT DOC.NO. CV-E-031
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 10-FV-1003 SERVICE: Process Air SIZE: 8 "
AREA: AMM-3 FLANGE TYPE: RTJ Flanges
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Air leak test of actuator was found OK2. Calibration3. Sent for Hydrotesting
DATE
03-05-2016
EXECUTED BY
Adnan Hussain(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Open
SUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 42 of 59
CLIENT DATE: 04-05-2016
PROJECT DOC.NO. CV-E-032
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-LV-5010B SERVICE: Process Air SIZE: 4 "
AREA: AMM-3 FLANGE TYPE: RTJ Flanges
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Air leak test of actuator was found OK2. Overhauling of body3. Inner and outer body seals were replaced.4. Body gaskets replaced5. Plug seal replaced6. Calibration7. Sent for Hydrotesting
DATE
04-05-2016
EXECUTED BY
Adnan Hussain(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
50
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 43 of 59
CLIENT DATE: 04-05-2016
PROJECT DOC.NO. CV-E-033
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 10-HV-1008 SERVICE: Process Air SIZE: 12 "
AREA: AMM-3 FLANGE TYPE: Lenticular
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Air leak test of actuator was found OK2. Vlave body stud bolts were jammed with solidified urea3. Seat, plug and cage were sent for machining.4. Calibration5. Sent for Hydrotesting
DATE
04-05-2016
EXECUTED BY
Adnan Hussain(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 44 of 59
CLIENT DATE: 04-05-2016
PROJECT DOC.NO. CV-E-034
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-TV-3004 SERVICE: Process Air SIZE:
AREA: AMM-3 FLANGE TYPE:
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Air leak test of actuator was found OK2. Overhauling3. Valve bench set was found4. Calibration5. Sent for Hydrotesting
DATE
04-05-2016
EXECUTED BY
Adnan Hussain(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
55
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 45 of 59
CLIENT DATE: 05-05-2016
PROJECT DOC.NO. CV-E-035
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-HV-2071A SERVICE: Process Air SIZE: 8 "
AREA: AMM-3 FLANGE TYPE: FLG.RF(F)
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Air leak test of actuator was found OK2. Overhauling3. Valve bench set was found4. Calibration5. Sent for Hydrotesting
DATE
05-05-2016
EXECUTED BY
Adnan Hussain(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 46 of 59
CLIENT DATE: 05-05-2016
PROJECT DOC.NO. CV-E-036
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 10-PV-1048 SERVICE: Process Air SIZE: 10 "
AREA: AMM-3 FLANGE TYPE:
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Cleaning, Oiling and Polishing2. Air Leak test of actuator was found OK3. Seat and plug were sent for machining4. All gaskets replaced5. Diapharm was found torned6. Diapharm replaced7. Calibrated8. Sent for Hydrotesting
DATE
05-05-2016
EXECUTED BY
Adnan Hussain(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 47 of 59
CLIENT DATE: 05-05-2016
PROJECT DOC.NO. CV-E-037
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-FV-2056 SERVICE: Process Air SIZE: 10 "
AREA: AMM-3 FLANGE TYPE: RTJ Flanges
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Air leak of acutator was tested and found OK2. Calibration was tested and found OK3. Cleaning, oiling and polishing was done4. Sent for Hydrotesting
DATE
05-05-2016
EXECUTED BY
Adnan Hussain(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 48 of 59
CLIENT DATE: 05-05-2016
PROJECT DOC.NO. CV-E-038
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 10-HV-1009 SERVICE: Process Air SIZE: 8 "
AREA: AMM-3 FLANGE TYPE: Lenticular
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Actuator was found Leaked.2. Dismantled single diapharm of actuator (outter most)3. Body Overhauled4. Calibrated5. Sent for Hydrotesting
DATE
05-05-2016
EXECUTED BY
Adnan Hussain(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 49 of 59
CLIENT DATE: 05-05-2016
PROJECT DOC.NO. CV-E-039
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-LV-3011B SERVICE: Process Air SIZE: 18 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Air leak test of actuator was found OK2. Overhauling of body3. Plug, seat and cage were sent for machining4. All three gaskets replaced5. Calibrated6. Sent for Hydrotesting
DATE
05-05-2016
EXECUTED BY
Mohammad Mubasher(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Open
SUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 50 of 59
CLIENT DATE: 05-05-2016
PROJECT DOC.NO. CV-E-040
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-LV-3011A SERVICE: Process Air SIZE: 18 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Air leak test of actuator was found OK2. Overhauling of body3. Valve plug, cage and seat were sent for machining4. Cleaning, oiling and polishing were done to smoothen up the valve5. Calibrated6. Sent for Hydrotesting
DATE
05-05-2016
EXECUTED BY
Mohammad Mubasher(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Open
SUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 51 of 59
CLIENT DATE: 06-05-2016
PROJECT DOC.NO. CV-E-041
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 19-PV-9001A SERVICE: Process Air SIZE: 4 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Cleaning, Oiling and Polishing2. Air Leak test of Actuator was found OK3. Diapharm was found Ok4. Overhauling of body and actuator5. O-rings replaced6. Seat, plug sent for machining7. All gaskets replaced8. Calibrated9. Sent For Hydrotesting
DATE
06-05-2016
EXECUTED BY
Mohammad Mubasher(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 52 of 59
CLIENT DATE: 06-05-2016
PROJECT DOC.NO. CV-E-042
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 19-FV-9002 SERVICE: Process Air SIZE: 8 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Air leak test of actuator was found OK2. Overhauling of Body3. Overhauling of Actuator4. Seat and plug were sent for machining5. Body gaskets replaced6. Calibrated9. Sent For Hydrotesting
DATE
06-05-2016
EXECUTED BY
Mohammad Mubasher(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
40
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 53 of 59
CLIENT DATE: 08-05-2016
PROJECT DOC.NO. CV-E-043
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-FV-2028 SERVICE: Process Air SIZE: 4 "
AREA: AMM-3 FLANGE TYPE: RF Flanges
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Cleaning, Oiling and Polishing2. Air Leak test ok3. Overhauling of Body4. Overhauling of Actuator5. Diaphram was found OK6. O-Rings Replaced7. Plug and seat sent for machining8. Gland Packing Replaced9. Calibrated10. Sent For Hydrotesting
DATE
08-05-2016
EXECUTED BY
Mohammad Mubasher(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 54 of 59
CLIENT DATE: 08-05-2016
PROJECT DOC.NO. CV-E-044
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-LV-2055 SERVICE: Process Air SIZE: 4-/-3-/-4
AREA: AMM-3 FLANGE TYPE: RTJ Flanges
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Cleaning, Oiling and Polishing2. Air Leak test ok3. Overhauling of Body4. Overhauling of Actuator5. Seat Replaced6. Plug seal rings Replaced7. Plug and Stem sent for machining8. Gland Packing Replaced9. Calibrated10. Sent For Hydrotesting
DATE
08-05-2016
EXECUTED BY
Mohammad Mubasher(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 55 of 59
CLIENT DATE: 09-05-2016
PROJECT DOC.NO. CV-E-045
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-TV-5482 SERVICE: Process Air SIZE:
AREA: AMM-3 FLANGE TYPE:
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Cleaning, Oiling and Polishing2. Air Leak test ok3. Actuator Diapharm replaced4. Plug seal O-rings replaced9. Calibrated10. Sent For Hydrotesting
DATE
09-05-2016
EXECUTED BY
Mohammad Mubasher(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTION
Close
SUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 56 of 59
CLIENT DATE: 10-05-2016
PROJECT DOC.NO. CV-E-046
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-TV-5476 SERVICE: Process Air SIZE:
AREA: AMM-3 FLANGE TYPE:
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Cleaning, Oiling and Polishing2. Air Leak test ok3. Calibrated4. Sent For Hydrotesting
DATE
10-05-2016
EXECUTED BY
Mohammad Mubasher(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 57 of 59
CLIENT DATE: 10-05-2016
PROJECT DOC.NO. CV-E-047
CONTRACTOR JOB NO. F-689
VALVE INFORMATON:
TAG NO: 11-HV-1032B SERVICE: Process Air SIZE: 1 "
AREA: AMM-3 FLANGE TYPE: Flanged
PHYSICAL CHECKS:
Flowtronix (Pvt) Ltd.
Overhauling and Calibrations OfControl Valves
(Valve Record Sheet)
Engro Fertilizers Limited
Plant-II Shutdown 2016
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
TEST RESULTS:
CONDITIONS (As Found) & CORRECTIVE MAINTENANCE:
REMARKS:This valve has been overhauled, Calibrated and Cleared for area installation.
Witnessed by Engro Valve Supvervisor : Mr. Allah Baksh
1. Cleaning, Oiling and Polishing2. Air Leak test ok3. Calibrated4. Sent For Hydrotesting
DATE
10-05-2016
EXECUTED BY
Mohammad Mubasher(Instrument Technician)
VALVE BENCH SET FAIL SAFE ACTIONSUPPLIED PRESSURE
AIR FAILURE CORRECT
PNEU./ELECT.CONN.CORRECT
PLUG+SEAT MATERIAL CORRECT
PLUG+SEAT SIZE CORRECT
POSITIONER CORRECT
BODY ARROW IN DIRECTION OF FLOW
PROCESS CONN.CORRECT
Page 58 of 59