Retention in Construction

download Retention in Construction

of 2

Transcript of Retention in Construction

  • 8/9/2019 Retention in Construction

    1/2

    Retention

    Normally, in most construction contracts, portion of the payments due to the contractor from

    each interim bill is deducted and withheld. This amount is called retention. In ICTAD / SBD /

    01 Clause 48.1, it is stated.

    The Retention can be defined as;

    "an amount of money withheld from interim payments, as specified in the bidding

    document of works contracts which exist between employer and contractor.

    Purpose;

    To ensure repair of defects in the construction works within the defect liability period.

    (In the event of default by the Contractor, this retention money can be used to pay for

    remedies).

    To provide incentive for the Contractor to complete the construction in order to get

    the retention at the end of the contract.

    To ensure that the construction work is performed correctly.

    (Defects are;

    "situations and instances where the works quality deviates from or fails to comply with standards,

    design documents or the provisions in the construction contract."

    The Defects Liability Period;

    is defined as 6 months, 12 months, or 24 months, or as specified in the bidding document. The defects

    liability period will commence from the date of Practical Completion of the project by the contractor

    for acceptance by the owner. Where delay is caused by the contractor, the defects liability period will

    commence from the actual date of the completion acceptance.During the defects liability period, the

    contractor will be responsible for, and bear the cost of, repairing defects caused by the contractor.

    Where the contractor fails to make the repairs or pay the costs of such repairs, the employer may

    deduct the cost of the repairs from the retention money. Such repairs or payment will not release the

    contractor from its general indemnification obligations.

    For defects caused by others, the employer is required to arrange for the repair of such defects at no

    cost to the contractor, and the employer is not permitted to deduct such repair costs from theretention money).

    The employer shall specify in the bidding document all the details relating to the withholding

    of retention money.

    Specifically, the Employer must include contract provisions dealing with:

    The method for withholding and the return of retention money;

  • 8/9/2019 Retention in Construction

    2/2

    The percentage amount of retention money and the duration;

    Duration of the defects liability period;

    Normally, 10% of the interim bill will be withheld as retention. This is subjected to a

    maximum amount, normally 5% of the original contract value. On practical completion of

    work, 50 % of the money retained will be released to the contractor. That means only 2.5% of

    the original contract sum will be retained during the defects liability period. After the defects

    liability period has passed and the Engineer has certified that the Contractor has rectified all

    defects notified by the Engineer, the balance retention money also released. (ICTAD / SBD /

    01 Clause 48.2).

    (As an alternative to the 2.5% retention at the practical completion stage, the Contractor can submit

    an unconditional, on demand guarantee, acceptable to the Employer, to the value of the retention and

    up to 28 days beyond the end of Defects liability period) ICTAD / SBD / 01 Clause 48.3).

    Example:Contract Value = Rs: 1,000,000.00

    Contract Period = 10 months + 3 months defects liability

    Interim Bill Interim Bill Value Retention Remarks

    1st Rs: 100,000.00 Rs: 10,000.00 10 % of the bill value

    2nd

    Rs: 250,000.00 Rs: 25,000.00 10 % of the bill value

    3rd

    Rs: 325,000.00 Rs: 32,500.00 10 % of the bill value

    4th Rs: 410,000.00 Rs: 41,000.00 10 % of the bill value

    5th

    Rs: 490,000.00 Rs: 49,000.00 10 % of the bill value

    6th Rs: 590,000.00 Rs: 50,000.00 Max limit 5% of cont

    value

    7

    t

    Rs: 700,000.00 Rs: 50,000.00 Do8

    th Rs: 825,000.00 Rs: 50,000.00 Do

    9th

    Rs: 910,000.00 Rs: 50,000.00 Do

    10thP.C. bill Rs: 999,000.00 Rs: 25,000.00 50% released