Restoration work for obstacle and upper core structure in …€¦ · · 2013-03-28scope Bent...
Transcript of Restoration work for obstacle and upper core structure in …€¦ · · 2013-03-28scope Bent...
Restoration work for obstacle and upper core structure
in reactor vessel of experimental fast reactor “Joyo” (2)
Misao TAKAMATSU, Takashi ASHIDA, Tetsuhiko KOBAYASHI,
Hirotaka KAWAHARA, Hideaki ITO, Akinori NAGAI
Japan Atomic Energy Agency (JAEA)
IAEA-CN-199/103
MK-III
J O Y O
Contents
• Background and restoration
work plan
• Design and development of
principal equipment
• Summary
1
Background
Hold
down
shaft
Lower part of UCS
Fiber
scope
Bent irradiation
test S/A
(MARICO-2)Top of S/As
MARICO-2 : Material
testing rig with
temperature control
IVS : In-vessel storage
rack
IVS
� The top of irradiation
test subassembly
(S/A) “MARICO-2” had
bent onto the IVS.
� “MARICO-2” had
damaged the upper
core structure (UCS).
3
This incident requires replacement of UCS and retrieval of
MARICO-2 S/A for Joyo re-start
Cask
(2) Retrieval of
ed-UCS
Door valve
(3) Retrieval of
MARICO-2 S/A
(4) Installation of
n-UCS
L-R/P
S-R/P Temporary pit cover
Screw jack-up equipment
Guide tube
(1) Jack-up of
ed-UCS
UCS
Cask
MARICO-2
S/A
MARICO-2 S/A retrieval equipment
Wire jack-up equipment
Ed-UCS is extracted through
small-diameter part.
UCS
Outline of restoration work plan
Plant condition :
- Fuel S/As are remained in reactor vessel.
>>> Sodium level is maintained at 50 mm below top of fuel S/A.
- Temperature of sodium is approximately 200deg-C, and temperature of
cover gas is approximately 140~160deg-C. 4
ed-UCS : existing damaged UCS
n-UCS : new UCS
Structure of UCS
UCS
(during construction))))
Inner diameter of
through-hole
UCS Weight : 16.5 ton
Operation time of Joyo (1977~~~~2007) ::::70,798 h 5
Driving
mechanism
Holding
mechanism
Guide tube
Latch
mechanism
S/A
Appro
x.
11m Core
IVS
Hold-down shaft
UCS
MARICO-2
R/P
Core address during
irradiation (3E3)
Location of
disconnection work
(IVS No.16 (R16))
Guide tube
Guide sleeve
Handling head
Cable etc.
Transfer pot
Ref. Normal state
IVS
R/V
S/A
Structure of MARICO-2
6
Major subjects and measures
in ed-UCS jack-up and retrieval
Bolts
UCSR/P
Guide
sleeve
Sodium bridgeUCS UCS
Deformation of GS
Guide sleeve
(thickness : 5mm)interference
Contact
Thermal
shielding
plate
: Bolt
(18××××3)
UCS UCS
Excessive
bending
strength
caused by
sodium bridge
Deformation of guide sleeve due to sodium bridge Deformation of ed-UCS due to interference and
contact between ed-UCS and guide sleeve
UCS
Excessive resistance Deformation of bolts
To prevent deformation of ed-UCS and guide sleeve
>>> Investigation of allowable load is required.
To prevent interference and contact between ed-UCS and guide sleeve
>>> Strict inclination control and visual monitoring are required.
8
Investigation of allowable load
Allowable load is investigated using finite element analysis code
“Abaqus” with 3-D modeling.
Pulling
height
(mm)
Allowable
load (t)Resistance notes
0 ~ 2 0.72 Sodium bridge shearing forceJack-up speed
: <2mm/h*1
2 ~ 484 0.72 Sodium bridge shearing force
484 ~ 862 1.09Resistance caused by interference
between ed-UCS and guide sleeve
862 ~ 1.73Resistance caused by contact
between ed-UCS and guide sleeve
*1: Deformation at the point of force application of wringing force*2 is unlikely owing to its
thick structure. However, in the case that sodium bridge shearing is incomplete, there
may be a risk of guide sleeve deformation due to rapid release of the wringing force.
jack-up speed is limited to below 2 mm/h to prevent permanently deforming guide sleeve.
*2: Pushing force by atmospheric pressure with assuming that contacting surface of ed-
UCS has been vacuumed by tight contact (3.37t)
9
Measure for inclination control
(Ex. Jack-up equipment)
吊吊吊吊りりりり蓋蓋蓋蓋
Required Max. load : 400kN
( total load of three screw jack )
1100mm
Servomotor
Screw jackVertical
displacement
measuring
device
Base mechanism
of screw jack
Handle
Jack
holder base
Manual :
0.025mm/rotation
Auto :
0.017~~~~1mm/s
Level measuring
deviceHanging plate
Load
measuring
device
Three screw jacks are
located uniformly in a
concentric configuration.
Guide tube
Temporary
pit cover
Temporary boundary
R/P UCS
Jack-up
equipment
Screw jack
Assuming conservative 2.5 mm gap between ed-
UCS and GS (safety factor: 2), allowable inclination
is estimated as 0.6925 mm/m (0.039 deg).
Achieve strict control of inclination
>>> Applying three-point suspension
>>> Inclination monitoring with level- and load-
measuring devices
10
Ex-vessel function test of jack-up equipment
Dummy UCS
Dummy guide tube
Screw jack
Screw jack
Hanging plate
Guide pin
11
Dummy
guide sleeve
R/P
UCS fitting area
monitoring
equipment
UCSRef. Ex-vessel test
result using video-scope
Dummy UCS
((((O.D. : 1010mm)
Observation image
using video-scope
UCS fitting
area
UCS
Bottom of R/P
Video-scope
- Endurance of dose : 1000Gy
- Max. Temp. : 100 deg-C
- O.D. : 6mm
- View angle : 40 deg
- Lighting : LED
Improvement of
picture quality
UCS
Bottom of R/P
Dummy
guide sleeve
(I.D. : 1070mm)
Visual monitoring equipment for UCS replacement
Ex. UCS fitting area
monitoring equipment
12
Major subjects and measures
in MARICO-2 S/A retrieval
- it was confirmed that MARICO-2 S/A is stuck in transfer pot
owing to its deformation.
>>> Retrieval equipment for MARICO-2 S/A is designed to
retrieve MARICO-2 S/A together with transfer pot.
- To avoid contact, ed-UCS cannot be set just above MARICO-2
S/A.
* Retrieval is performed using hole through which ed-UCS is
extracted
>>> Offset arm to reach MARICO-2 S/A is designed as part of
MARICO-2 S/A retrieval equipment.
13
Large R/P
Small R/P
MARICO-2 S/A
UCS
Location of R/P
during restoration work
Retrieval
equipment
MARICO-2 S/A
Pantograph mechanism
Latch finger mechanism
Pantograph
Latch finger
Schematic diagram of
MARICO-2 S/A retrieval equipment
Pantograph and latch finger
mechanism are developed on
basis of remote control
techniques demonstrated in
fuel handling machine. 14
Dummy
S/A
Latch
fingerDummy
transfer pot
Transfer pot
70mm
MARICO-2
S/A
Insertion of latch finger
UCSHold-
down
shaft
Fiberscope
Latch
finger
Latch
fingerLatch
finger
MARICO-2
S/A
Pulling up MARICO-2 S/A
MARICO-2
S/A
Latch
finger
Preliminary in-vessel testPreliminary in-vessel test was conducted to demonstrate latch
finger performance.
15
- In this preparation work for restoration of Joyo, a series of
equipment has been successfully designed and developed.
[UCS replacement]
> Allowable loads are investigated.
> Measures to achieve strict inclination control are established.
[MARICO-2 S/A retrieval]
> Pantograph and latch finger mechanism are developed on basis of remote
control techniques demonstrated in fuel handling machine.
Summary
Current status and future plan
- n-UCS and all necessary equipment are currently being
manufactured.
- A full ex-vessel test is scheduled in 2013 to verify
performance of equipment and establish final work procedure
- Replacement of UCS and retrieval of MARICO-2 S/A will be
conducted in 2014.
Restoration work on Joyo will provide valuable experience and
insight into further improvements and verification of repair
techniques for sodium-cooled fast reactors.16